city of newark, ohio high rate treatmentfacility started-up in march/april 2011. project background....

25
Imagine the result HIGH RATE TREATMENT AS PART OF THE SOLUTION FOR WET WEATHER FLOWS City of Newark, Ohio Wet Weather Control Building High Rate Treatment Tanks/UV Wet Weather Screen Building JC2/Wet Weather Pump Station Final Clarifiers Chemical Storage and Feed Room Wet Weather Grit Tanks Presented By: Joe Jacobs, P.E. JUNE 22, 2011

Upload: others

Post on 17-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

HIGH RATE TREATMENTAS PART OF THE SOLUTION FOR WET WEATHER FLOWS

City of Newark, Ohio

Wet Weather Control Building

High Rate Treatment Tanks/UV

Wet Weather Screen Building

JC2/Wet Weather Pump Station

Final Clarifiers

Chemical Storage and Feed Room

Wet Weather Grit Tanks

Presented By: Joe Jacobs, P.E.

JUNE 22, 2011

Page 2: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

Long Term Control (LTC) Plan Development 2000-2004o Recommended conveyance of wet weather flows to treatment

plant siteo Recommended construction of physical/chemical high rate

treatment facilities NPDES Permit Compliance Schedule:

o Submit permit-to-install application: August 2008o Complete construction: December 2010

Planning/Basis of Design Report in 2007 Detail Design/Bid in 2008 Construction began in March of 2009 Facility Started-up in March/April 2011

PROJECT BACKGROUND

Page 3: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

54” LICKING RIVER INTERCEPTOR

42” MAIN STEM INTERCEPTOR

JUNCTION CHAMBER 2

JUNCTION CHAMBER 1

CSO-1006 ELIMINATED AND NEW 48” INTERCEPTOR REPLACED EXISITNG 30-INCH SEWER

42” TO WWTP

CSO-1008

48” NORTH FORK INTERCEPTOR SEWER

WET WEATHER PUMP STATION

36” TO WET WEATHER SYSTEM

EXISTING RACOON CREEK INTERCEPTOR SEWER

CSO-1012

CSO-1013

SOUTH FORK LIFT STATION

CSO-1015

CSO-1014A

CSO-1014BRAC

CO

ON

CR

EEK N

NEW RACCOON CREEK INTERCEPTOR SEWER

COLLECTION SYSTEM

EXISTING SEPARATE SEWER

EXISTING COMBINED SEWER

NEW/PROPOSED SEPARATE SEWER

NEW COMBINED SEWER

Page 4: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

Limit 6 Upstream CSOs to 4 to 6 events per year No effluent permit limits in proposed draft permit. Permit

provides for effluent monitoring only. Basis of Design Assumed:

• Minimum of 80 Percent of TSS• No limit for CBOD• No limit for NH3-N• Disinfection required during summer months

o E. Coli: 284/100 ml on weekly basiso E. Coli: 126/100 ml on a monthly basis

• No limit for dissolved oxygen

HIGH RATE TREATMENT GOALS

Page 5: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

SWMM MODEL DEVELOPMENT

The SWMM model was developed as part of Long Term Control Plan

Model included all planned improvements to the collection systemo 54-inch Licking River Interceptor (Completed)o CSO-1007 Separation (Completed)o CSO-1006 Elimination (Recently completed)o CSO-1013 Underflow (Recently completed)o 48-inch Raccoon Creek Interceptor (Under Design)o CSO-1030 Separation (Under Design)

Model run with actual 2005 annual rainfall data

Page 6: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

INFLUENT HYDROGRAPH

EXTENDED STORM EVENT WITH MULTIPLE RAINFALL EVENTS RESULTS IN MULTIPLE PEAKS AT WWTP

SWMM Model Results

WWTP Secondary Treatment Capacity

Page 7: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

SWMM MODEL CONCLUSIONS

The existing 42-inch and 54-inch interceptors convey approximately 51-mgd before overflowing at CSO-1008

51 separate overflow events per year were identified where High Rate Treatment or Equalization would be required

6 events were identified where CSO-1008 would have activated with High Rate Treatment

Use of existing Equalization could reduce the number of times High Rate Treatment is used by half

Page 8: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

BASIS OF DESIGN

WWTP Influent Pumping & Grit Removal

WWTP Screening

Administration Building

Aeration

Equalization

Final

Clarifiers

PrimaryClarifiers

Wet Weather Control Building

Wet Weather Screen Building

JC2/Wet Weather Pump Station

High Rate Treatment Tanks

WWTP Flow Rates:• 8-mgd Average Dry Day• 20-mgd Peak Secondary

High Rate Treatment System:• 28-mgd sustained• 32-mgd intermittent peak

Total Wet Weather Capacity• 48-mgd sustained• 52-mgd intermittent peak

Construction Cost: $15.3 Million ARRA Funding: $5.0 Million

Page 9: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

PROCESS OVERVIEW

Junction Chamber No. 2 Wet Weather Pump Station Wet Weather Screening Wet Weather Grit Removal Equalization High Rate Treatment

o Microsand Recirculation Circuito Bulk Sand Feed Systemo Coagulant Feed Systemo Polymer Feed Systemo Defoamer Feed System

Wet Weather Disinfection

Page 10: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

JUNCTION CHAMBER 2

Purpose: Provides flow splitting between

Wastewater Treatment Plant and Wet Weather Treatment Facility

Provides preferential diversion of separate sanitary sewer flows to Wastewater Treatment Plant

Provides preferential diversion of combined sewer flows to Wet Weather Treatment System

Wet Weather Pumps

JC2 Control Gate

Wet Weather Pump Station

Junction Chamber 2

54” Licking River Interceptor (Combined)

42” Main Stem (Separate)

42” WWTP Influent

24” Secondary Effluent

N

36” HRT Force Main

Junction Chamber 2

Wet Weather Pump Station

Flow Meter Chamber

Page 11: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

WET WEATHER PUMPING

Purpose: Convey flow to wet weather process and control

hydraulic grade in upstream sewers

Basis of Design: Firm Pumping Capacity: 34 mgd Number of Pumps Five (4 duty, 1 standby) Type Submersible Centrifugal Pump Capacity 6,000 gpm @ 30 ft Drive Type: Variable Speed

Submersible Wet Weather Pumps

Wet Weather Pump Station and Junction Chamber 2 Section View

Page 12: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

WET WEATHER SCREENING

Purpose: Floatables control, mitigate plugging of downstream equipment (hydrocyclones)

Basis of Design: Number of Screens: Two Type: Automatic Self Cleaning Filter Element Size: 6 mm Compactor: Screw conveyor w/press

Conveyor Discharge Chute Continuous Conveyor Screen

Two Parkson Aqua Guard Type Screens

Page 13: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

WET WEATHER GRIT REMOVAL

Purpose: Remove 95 percent of grit 100 microns and larger, essential for Actiflo process No grit dewatering or classifying equipment provided to simplify operation; grit

returned to wastewater treatment plant influent

Basis of Design No. of grit tanks: Two Type: Vortex tray settler No. of trays per tank: Eight 12 ft diameter

Grit Underflow Valve

Screen Channel and Grit Tank Section View

Multiple Tray Vortex Settler

Page 14: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

EQUALIZATION

Purpose: Store volume from low intensity short

duration storm events

Basis of Design: Convert existing equalization to wet

weather operation Volume: 1,000,000 gallons

Existing Equalization Basins at Newark

New Equalization Junction Chamber

Page 15: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

HIGH RATE TREATMENT

Purpose: Treat and discharge wet

weather flows from highintensity long durationstorm events

Provide enhancedprimary treatment of wetweather flows

Basis of Design No. of Trains Two Type Ballasted flocculation process Manufacturer Actiflo process by Kruger Capacity 14 mgd per train sustained

16 mgd per train intermittent peak Overflow rate 60 gpm/sf sustained

66 gpm/sf intermittent peak

Page 16: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

MICROSAND

Purpose: Microsand serves as the seed for floc formation and ballast (weight) to

aid with settling

Basis of Design: Sand Concentration 3,000 to 6,000 mg/l

Initial Sand Feed 800 lbs/MGD Capacity

@ 14 MGD = 11,200 lbs per HRT tank

Sand Loss 2 to 3 mg/l per MG treated

16 to 25 lbs per MG treated

Page 17: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

MICROSAND CIRCUIT

Purpose: Separate settled solids from microsand and return

microsand to the injection tank. Settled solids are conveyed to the wastewater treatment plant

Basis of Design Microsand Pumps

o Purpose: Recirculation of microsand and settled solids

o No. of pumps: 3 per train (2 duty, 1 standby)o Capacity: 310 gpm each at 76 ft TDH

Hydrocycloneso Purpose: Separate microsand from settled solidso Hydrocyclones: 3 per train (2 duty, 1 standby)o Capacity: 310 gpm at 22 psig Underflow: 60 gpm to injection tank Overflow: 250 gm to WWTP @ 0.1 to 0.5 percent solids

Microsand Pumps

Train 1 Hydrocyclones and Sample Sink

Page 18: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

BULK SAND FEED SYSTEM

Major Components Bulk Bag Unloader Unloading Bin Volumetric Feeder: (2,000 lb/hr) Wetting Cone Eductor Nozzle Booster Pump

Booster Pump

Eductor Nozzle Wetting

Cone

1 Ton Mini Sack

Monorail & Hoist

Volumetric Feeder

Unloading Bin

Bulk Sand Feed System

Page 19: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

COAGULANT FEED SYSTEM

Purpose: Destabilize suspended solids and colloidal matter in raw water

Basis of Design: Coagulant: Aluminum Chlorohydrate (ACH) Feed Pumps: 4 each (2 duty, 2 standby) Type: Peristaltic (Hose) Pumps Dosage 10 to 50 mg/l (Based on ACH) Feed Range 2.4 to 130 gph

6,000 Gallon Coagulant Storage Tank

Coagulant Feed PumpsCoagulant Induction Units

Page 20: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

High Rate Treatment – Coagulant Process Flow Schematic

Page 21: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

POLYMER FEED SYSTEM

Purpose: Flocculent aid for coagulated water

Basis of Design Polymer Type: Anionic Emulsion Blending Units: 4 each (2 duty, 2 standby) Polymer Dosage: 1 to 3 mg/l Feed Range: 0.5 to 10 gph

Feed Points Between the coagulation tank and the injection

tank Between the injection tank and the maturation

tank Mid-point of the maturation tank

Polymer Blending Unit

Page 22: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

High Rate Treatment – Polymer Process Flow Schematic

Page 23: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

DEFOAMER FEED SYSTEM

Purpose: Mitigate foaming in HRT Effluent

Basis of Design: Defoamer Agent: TRAMFLOC Feed Pumps: 2 each (1 duty, 1 standby) Dosage: 1 to 5 mg/l Feed Range 1.2 to 6 gph

Feed Points HRT Effluent Channel Downstream of UV System

HRT Effluent Channel Foam at Start-up

Defoamer Feed System

Page 24: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

WET WEATHER DISINFECTION

Purpose: Provide disinfection of wet weather flows prior to discharge

Basis of Design: Type: Medium Pressure Manufacturer: Trojan Technologies Sustained Capacity: 28 mgd Intermittent Peak: 32 mgd Total No. of lamps: 128 each UV Transmittance: 50 percent

Influent and Effluent Automatic Samplers

Trojan UV4000 Plus UV Disinfection System

Page 25: City of Newark, Ohio HIGH RATE TREATMENTFacility Started-up in March/April 2011. PROJECT BACKGROUND. 54” LICKING RIVER INTERCEPTOR 42” MAIN STEM INTERCEPTOR JUNCTION CHAMBER 2

Imagine the result

QUESTIONS?

Joe Jacobs, P.E.Malcolm Pirnie, Inc.1900 Polaris Parkway, Suite 200Columbus, Ohio 43240

[email protected]

Wet Weather Treatment Facility West Elevation

Wet Weather Treatment Facility East Elevation