antamina’s mine to mill throughput - ceecthefuture.org · minera antamina and walter valery, alex...
TRANSCRIPT
Antamina’s Mine to Mill Throughput
Improvement
Ed Rybinski
November 2012
http://www.antamina.com
Based on Paper “Optimization and Continuous
Improvement of Antamina Comminution Circuit” presented
originally at SAG 2011 in Vancouver, Canada.
2
Agenda
1. Antamina Overview
2. Objective “Mine to Mill”
3. Why Mine to Mill
4. What was Done
5. Changes to the Process
6. Results
7. Other KPIs
8. Summary and Conclusion
9. Acknowledgements
1. Antamina Overview
1. BHP, Xstrata, Teck Resources and Mitsubishi
2. Mine: 270 km NE of Lima, Peru
3. Pipeline: 302 km
4. Port: 300 km NW of Lima
5. Resource (MII): 1.8Bt
6. Head Grade: 0.84%Cu, 0.53%Zn
7. Mine (630ktpd):
a. 4 Bucyrus, 2 P&H shovels
b. 77 CAT 793
c. 15 Komatsu 930E
8. Concentrator (130ktpd)
a. 2 SAG (38‘x19‘, 20MW)
b. 4 BM (24‘ x 35.5‘,11MW)
3
4
2. Objective of Mine to Mill Project
1. Increase the SAG Mill Throughput
2. Focus on “Harder” CuZn Ores
3. Budget Throughput 2007:
• CuMo ores: 4,120 tph
• CuZn ores: 2,705 tph
4. Energy Consumption
• CuMo ores: 2.8 kWh/t
• CuZn ores: 5.0 kWh/t
5. Review Operations from “Mine to Mill”
5
3. Why “Mine to Mill”
1. Mine Optimizes their Process
2. Concentrator Optimizes their Process
3. Need to Look at the Big Picture – Geology, Drill/Blast, Loading, Hauling, Crushing, Grinding
PROCESS EFFICEINCY AUTHOR
Blast 20% Brinkman(1987)
Grind 1%
Willis(1988)
Hukki(1975)
6
4. What was Done (with Metso)
1. Collect Data
– Geology, drilling, blasting, crushing and grinding
2. Audit of Current Practices
– Drilling, blasting, crushing and grinding
– Complete crusher and mill circuit surveys (January 2007 and
December 2008)
3. Modelling of Process
– Blasting, Crushing and Grinding
4. Recommendations/Implementation/Analysis
7
Audit Current Practice (Drill/Blast)
8
Review Fragmentation and Hardness
9
Mill Survey
10
Blast Tags
DETECTOR
DETECTOR
[ID,x,y,z]
[ID, time]
RECEPTOR
POST BLAST
POST CRUSHER
SAG1 MILL FEED
[ID, time)
11
Modeling Blasting, Crushing and Grinding
12
5. Changes to Process (Drill/Blast)
Blast Design Pre MtM(2006) Post MtM(2007) New Designs (2008)
Bench height m 15 15 15
Burden m 7 6 5.5
Spacing m 8 7.5 6.5
Hole diameter mm 311 311 311
Stemming length m 7 7 7
Subdrill m 2 2 2
Explosive Weight kg 988 988 988
Explosive Type HA64 HA64 HA64
Initiation Type Pyro-technic Pyro-technic Electronic
Powder Factor kg/t 0.35 0.43 0.54
13
Changes to Process (Concentrator)
1. Increased Pulp Lifter Capacity (1Q 2007)
– Focused on reducing slurry pooling in CuMo ores
– Pulp Lifters Depth Increase from 250 to 350 mm
– Other 38 ft SAGs operate with 375-600 mm pulp lifters
2. Install Pebble Crusher Plant (May 2008)
– Focus on Harder/Coarser CuZn ores
– 2 x 500kW crushers
3. Install SAG Bypass (1Q 2009)
– Designed to be used during replacement of SAG stator
– 1 x 600kW crusher
14
6. Results: Increase in Fines
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
0.01 0.1 1 10 100 1000
Cu
m %
Pas
s (µ
m)
Particle Size (mm)
SAG Feed Particle Size Analysis (Pre and Post Mine to Mill)
CuZn 15/01/07
CuZn 28/09/11
Increase in Fines
15
Results (Theoretical Improvement)
CuZn
15%11% 4%
16%16%
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
Base Case, PF=0.35kg/t,
Axb=84
Inc PF 1, PF=0.43kg/t
Pebble Crusher,
Pulp Lifters
Ball Charge Inc PF 2, PF=0.54kg/t
Ore Hardness, Axb=174
SAG
Th
rou
ghp
ut (T
PH
)
Modifications
SAG Mill Throughput Improvements
16
Results (Actual Improvement)
2000
2500
3000
3500
4000
4500
5000
2006 2007 2008 2009 2010 2011
SAG
TP
H
Year
SAG TPH Improvements
CuZn CuMo
17
7. Other Key Process Indicators (KPIs)
1. Dilution
2. Wall Damage and Spillage over Crest
3. Fly Rock
Reconciliation Mine vs Concentrator
0.60
0.65
0.70
0.75
0.80
0.85
0.90
0.95
1.00
1.05
1.10
2005 2006 2007 2008 2009 2010 2011
Year
Rati
o C
on
cen
tra
tor
vs M
ine
Cu Grade (%) Zn Grade (%)
18
8. Summary and Conclusion 1
1. Started Mine to Mill in 2007
• Modeled Entire Process, Focused on Drill/Blast
• Increased Powder Factor by 55%
• Controlled Secondary Metrics (dilution, wall damage, fly rock)
2. Antamina Implemented Pebble Crushing, Pulp Lifter
3. Mother Nature Made Rock Softer
19
Summary and Conclusion 2
SAG TPH
Ore Type 2005/2006 2011 % Increase
CuMo 4,078 4,769 17%
CuZn 2,788 4,373 57%
Difference 46% 9% -
SAG kWh/t
Ore Type 2005/2006 2010/2011 % Decrease
CuMo 2.9 2.6 11%
CuZn 5.0 3.0 40%
Difference 43% 15% -
20
1. To Compañía Minera Antamina for permission to present at
PROCEMIN 2012.
2. To Jorge Ghersi, Frank Davila and Javier Linares of Compañía
Minera Antamina and Walter Valery, Alex Jankovic, Roberto Valle
and Serkan Dikmen of Metso Process Technology and Innovation,
Co-authors of “Optimization and Continuous Improvement of
Antamina Comminution Circuit” presented originally at SAG 2011 in
Vancouver, Canada.
SOMOS ANTAMINA
¡NOSOTROS CUMPLIMOS!
Av. El Derby 055, Torre 1, Oficina 801. Santiago de Surco. Lima - Perú
Telf. (51-1) 217-3000 Fax (51-1) 217-3095
www.antamina.com
9. Acknowledgements: