USER STORY POINT ESTIMATION

South Wales Agile Group

Hello!I am Fred Heath

Developer, Problem solver, Ruby evangelist, Agile practitioner.

You can find me at:@FredAtBootstrapbootstrap.me.uk

SCRUM ESTIMATION

○ Planning Poker○ T-Shirt Size○ Fruit Eating○ ….and others

Story Points

“There is currently no standard unit

of measurement in software development

“Current estimation measures effort without accounting for factors that affect said effort

What’s this all about

○ Current estimation methods not fit for purpose

○ A new structured, empirical way introduced: USP estimation

USP = User Story Point

4 - easy

4 - easyNot to

me - 16

but, look here………………..easy, see?

I suppose you’re right,4 then!

What went wrong

Environmental factors ignored

Ben unfamiliar with project, programming language and application domain.

Technical factors ignored

Asynchronous processing is inherently complex, setup is not trivial.

Human interaction factors ignored

Jerry charismatic and influential leader. Peer pressure always wins.

Key problems with current estimation methods

○ Inconsistent

○ Subjective

○ Unreliable

Velocity Assumptions

○ Stable previous velocity○ Team doesn’t change○ Sprint duration doesn’t change○ Initial planning session is inerrant○ Technology / platform doesn’t change○ Individual productivity doesn’t change

USER STORY POINT ESTIMATION

A consistent, reliable, structured, empirical estimation method

Use Case Point Estimation

for Object-Oriented, Use-Case based development

Use Case Points

Environmental Factors (EF)

Project familiarity, application experience, motivation, language complexity, etc.

Technical Factors (TF)

Complex algorithms, concurrency, cross-platform support, etc.

Use Case complexity (UUCP)

Simple, average or complex

Use Case Points = UUCP * TCF * ECF

UCP References1. Karner, G, 1993, “Metrics for Objectory”. Diploma thesis, University

of Linköping, Sweden. No. LiTHIDA-Ex-9344:21. December 1993.2. Smith, John, 1999, “The Estimation of Effort Based on Use-Cases.

Rational Software.Cupertino, CA.TP-171. October 1999.3. Anda, Bente, D. Dreiem, Dag Sjøberg and Magne Jørgensen, 2001,

“Estimating Software Development Effort Based on Use-Cases - Experiences from Industry”, The Unified Modeling Language.Modeling Languages, Concepts, and Tools, 4th International Conference, Toronto, Canada, October 1-5, 2001, LNCS 2185

4. Roy Clem, Project Estimation with Use Case Points, http://www.codeproject.com/KB/architecture/usecasep.aspx

UCP

USP

Object-Orientated

UML

Waterfall

Multi-paradigm

Agile

Use Cases

User Stories

USP - STEP 1PRODUCTIVITY FACTORS

Productivity Factors

0.5

1.5

1

1

1

-1

-1

1.5

0 1 2-1-2

Total Impact

= F1 weight * F1 score+ F2 weight * F2 score + F3 weight * F3 score + F4 weight * F4 score + F5 weight * F5 score + F6 weight * F6 score + F7 weight * F7 score + F8 weight * F8 score

X

P FACTOR

PF = 1.4 + (-0.03*Total Impact)

USP - STEP 2USER STORY COMPLEXITY

COMPLEXITY FACTORS

Weight Name

2 Distributed or Parallel processing

2 Concurrency

2 High Performance

1 Reusability & Modularity

1 Complex internal Processing

COMPLEXITY FACTORS (cont’d)

Weight Name

0.5 Ease of Use

1.5 Cross-Platform Support

0.5 Complex Setup or installation

1 Extensibility & Compliance

1 Security

USER STORY COMPLEXITY

Complexity Score (USCS) = 5 + Σ{Weights}

USER STORY POINTS

USP = USCS * PF

Example: Shopping app

Estimate during planning meeting. Whole team participates.

PRODUCTIVITY FACTORS

Name Weight Score Impact

Project Familiarity 1.5 4 6

Application Experience 0.5 4 2

Proramming paradigm experience

1 2 2

Team Cohesion 1 4 4

PRODUCTIVITY FACTORS

Name Weight Score Impact

User Story Robustness 1.5 5 7.5

New / part-time team-members

-1 3 -3

Proramming language complexity

-1 3 -3

Motivation 1 5 5

TOTAL IMPACT = 20.5

P FACTOR

PF = 1.4 + (-0.03*20.5)= 0.785

User Story

Epic: “As a user, I want to backup my hard drive.”

Story: “As a power user, I can specify files or

folders to backup based on file size, date created and date modified.”

USCP = 7

USER STORY POINTS

USP = 7 * 0.785= 5.495=~ 5.5

USP ADVANTAGES

○ Objective

○ Repeatable

○ Quick to apply

○ Adaptable to change

“The greatest gift is the power to

estimate things at their true worth.

Francois de la Rochefoucauld

Discussion, suggestions, feedback

https://muut.com/usp-estimation

THANKS!Any questions?