adtec pre no.23 july 09

71
LAPORAN KEMAJUAN PROJEK NO.23 ‘JULAI 2009’ PROJEK ADTEC TAIPING KEMENTERIAN SUMBER MANUSIA JABATAN KERJA RAYA MALAYSIA KAMALBINA SDN. BHD PEMILIK PEGARAH PROJEK KONTRAKTOR R&B

Upload: muhammad-arkam

Post on 03-Nov-2014

21 views

Category:

Business


0 download

DESCRIPTION

 

TRANSCRIPT

Page 1: ADTEC Pre No.23 July 09

LAPORAN KEMAJUAN PROJEK NO.23

‘JULAI 2009’

PROJEK ADTEC TAIPING

KEMENTERIAN SUMBER MANUSIA

JABATAN KERJA RAYA MALAYSIA

KAMALBINA SDN. BHD

PEMILIK

PEGARAH PROJEK

KONTRAKTOR R&B

Page 2: ADTEC Pre No.23 July 09

ADTEC TAIPING

LOKASI PROJEK

Page 3: ADTEC Pre No.23 July 09

BANGUNAN PENTADBIRAN

BENGKEL TEK. MAKLUMAT& JAMIN KUALITI

DEWAN BESAR

PUSAT SUMBER

DEWAN KULIAH

LOBI UTAMA

KAFETERIA

MIKRO ELEKTRONIK

KOMPOSIT PLASTIK

M&E PLANT ROOM

1

TNB SUB

STATION

SERAMIK

M&E PLANT ROOM

2

GARAJ KENDERAAN

ASRAMA LELAKIASRAMA PEREMPUAN

DEWANMAKAN

SURAU

KELAS F

KELAS G

KUARTERSB, C, C&D

PELAN TAPAK ADTEC TAIPING

Page 4: ADTEC Pre No.23 July 09

KEMAJUAN KERJA FIZIKAL

JADUAL : 95.18 %SEBENAR : 95.42 %KESELURUHAN : 0.24 %

TARIKH LAPORAN : 10 JULAI 2009

Page 5: ADTEC Pre No.23 July 09

KEMAJUAN KERJA KEWANGAN

JADUAL : 94.99 %SEBENAR : 94.97 %KESELURUHAN : -0.02 %

TARIKH LAPORAN : 10 JULAI 2009

Page 6: ADTEC Pre No.23 July 09

Graf Kemajuan Kerja Fizikal Sehingga 10/7/2009 (EOT 1)

0.00

10.00

20.00

30.00

40.00

50.00

60.00

70.00

80.00

90.00

100.00

Bulan

Per

atu

s %

% Kem. Fizikal J adual Asal

% Kem. Fizikal Sebenar

% Kem. Fizikal J adual EOT NO.1

% Kem. Fizikal J adual Asal 0.00 0.48 1.04 2.56 4.19 6.12 7.70 9.98 13.53 18.44 20.82 23.34 26.09 29.06 30.76 33.81 36.84 41.32 43.00 47.08 60.55 70.88 84.22 99.14 100.00

% Kem. Fizikal Sebenar 0.00 2.59 5.28 7.56 9.30 11.64 13.12 15.62 18.74 22.53 26.73 29.56 32.40 35.71 37.09 41.47 45.77 46.74 50.89 55.19 58.46 67.03 68.03 73.45 80.28 87.59 95.42

% Kem. Fizikal J adual EOT NO.1 0.00 2.59 5.28 7.56 9.30 11.64 13.12 15.62 18.74 22.53 26.73 29.56 32.40 35.71 37.09 41.47 45.77 46.74 50.89 55.19 58.46 67.03 68.03 73.45 79.69 85.16 95.18 100.00

16-05-

07

25-06-

07

24-07-

07

20-08-

07

13-09-

07

18-10-

07

09-11-

07

05-12-

07

12-01-

08

21-02-

08

27-03-

08

15-04-

08

29-05-

08

08-07-

08

15-07-

08

22-08-

08

19-09-

08

28-10-

0814-11-08

04-12-

08

08-01-

09

12-02-

09

11-03-

09

15-04-

09

16-05-

09

12-06-

09

10-07-

09

13-08-

09

% Kem. Fiz ikal Jadual EO T 95.18%

% Kem. Fiz ikal Sebenar 95.42%

Page 7: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 94.21% 96.74% 2.53%

JULAI 09’ 98.28% 99.36% 1.08%

MECHANICAL PLANNED

ACTUAL

AIR COND 98.46% 100.00%

FIRE FIGHTING 92.70% 100.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - DEWAN BESAR

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 100.00%

LPS NA NA

PA 100.00% 93.51%

SMATV 100.00% 99.29%

CCTV NA NA

ICT 100.00% 99.25%

Page 8: ADTEC Pre No.23 July 09

DEWAN BESAR

Page 9: ADTEC Pre No.23 July 09

DEWAN BESAR

Page 10: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 99.68% 99.72% 0.04%

JULAI 09’ 99.95% 100.00% 0.05%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – LOBI

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 98.80% 100.00%

SUBMAIN CABLE 97.69% 100.00%

DB 75.00% 100.00%

LUMINAIRE 94.22% 100.00%

MAIN S/BOARD NA NA

LPS NA NA

PA NA NA

SMATV NA NA

CCTV 100.00% 98.70%

ICT NA NA

Page 11: ADTEC Pre No.23 July 09

LOBI UTAMA

Page 12: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 98.54% 98.19% -0.35%

JULAI 09’ 99.93% 99.94% 0.01%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 100.00%

FIRE FIGHTING 90.81% 100.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMABANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 75.00% 100.00%

LUMINAIRE 99.82% 100.00%

MAIN S/BOARD 75.00% 100.00%

LPS 98.84% 98.00%

PA 84.88% 93.10%

SMATV NA NA

CCTV NA NA

ICT 90.38% 99.00%

Page 13: ADTEC Pre No.23 July 09

DEWAN KULIAH UTAMA

Page 14: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 97.50% 98.54% 1.04%

JULAI 09’ 99.42% 99.83% 0.42%

MECHANICAL PLANNED

ACTUAL

AIR COND 98.33% 100.00%

FIRE FIGHTING 84.79% 100.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 98.77% 100.00%

SUBMAIN CABLE 96.40% 100.00%

DB 85.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 85.00% 100.00%

LPS 93.29% 98.29%

PA 91.27% 94.22%

SMATV 100.00% 99.63%

CCTV NA NA

ICT 28.81% 81.00%

Page 15: ADTEC Pre No.23 July 09

PUSAT SUMBER / PERPUSTAKAAN

Page 16: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 96.42% 96.51% 0.09%

JULAI 09’ 99.37% 99.66% 0.29%

MECHANICAL PLANNED

ACTUAL

AIR COND 95.34% 100.00%

FIRE FIGHTING 92.57% 87.38%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBERBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 99.00%

SUBMAIN CABLE 100.00% 100.00%

DB 85.00% 100.00%

LUMINAIRE 96.42% 98.00%

MAIN S/BOARD 75.00% 100.00%

LPS 87.80% 96.95%

PA 21.28% 91.07%

SMATV 100.00% 99.57%

CCTV 100.00% 99.90%

ICT 78.44% 92.00%

Page 17: ADTEC Pre No.23 July 09

BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER

Page 18: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 99.58% 99.23% -0.35%

JULAI 09’ 100.00% 99.85% -0.15%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 100.00%

FIRE FIGHTING 78.00% 100.00%

KITCHEN EQUIP. 83.70% 92.00%

LPG INSTALL. 82.56% 90.00%

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - KAFETARIA

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD NA NA

LPS 100.00% 93.78%

PA 100.00% 92.30%

SMATV 100.00% 99.43%

CCTV NA NA

ICT 0.00% 100.00%

Page 19: ADTEC Pre No.23 July 09

KAFETERIA

Page 20: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 98.05% 98.01% -0.05%

JULAI 09’ 99.85% 99.70% -0.15%

MECHANICAL PLANNED

ACTUAL

AIR COND 94.61% 100.00%

FIRE FIGHTING 83.25% 100.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMATBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00 % 100.00 %

SUBMAIN CABLE 100.00 % 100.00%

DB 100.00 % 100.00%

LUMINAIRE 100.00 % 100.00%

MAIN S/BOARD 75.00% 100.00%

LPS 100.00% 98.22%

PA 100.00% 95.30%

SMATV 100.00% 99.79%

CCTV 100.00% 99.30%

ICT 89.88% 82.28%

Page 21: ADTEC Pre No.23 July 09

BENGKEL TEKNOLOGI MAKLUMAT

Page 22: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 98.42% 98.30% -0.12%

JULAI 09’ 99.99% 99.61% -0.38%

MECHANICAL PLANNED

ACTUAL

AIR COND 98.20% 100.00%

FIRE FIGHTING 90.15% 100.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 93.26% 95.00%

DUST CONTROL NA NA

PROCESS COOLING

91.12% 39.45%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 75.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 75.00% 95.00%

LPS 100.00% 98.22%

PA 98.80% 95.87%

SMATV 76.76% 98.87%

CCTV 100.00% 99.32%

ICT 97.03% 81.86%

Page 23: ADTEC Pre No.23 July 09

BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)

Page 24: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 98.46% 98.41% -0.05%

JULAI 09’ 99.87% 99.64% -0.23%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 100.00%

FIRE FIGHTING 89.89% 100.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 93.26% 95.00%

DUST CONTROL 87.72% 96.58%

PROCESS COOLING

91.30% 22.05%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 100.00%

LPS 100.00% 96.25%

PA 100.00% 94.94%

SMATV 79.29% 98.24%

CCTV 100.00% 99.20%

ICT 97.00% 80.81%

Page 25: ADTEC Pre No.23 July 09

BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)

Page 26: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 97.15% 97.14% -0.02%

JULAI 09’ 99.20% 99.60% 0.40%

MECHANICAL PLANNED

ACTUAL

AIR COND 96.66% 100.00%

FIRE FIGHTING 86.34% 100.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 93.26% 95.00%

DUST CONTROL 92.74% 95.59%

PROCESS COOLING

47.25% 39.45%

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 99.29% 100.00%

DB 78.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 85.00% 100.00%

LPS 100.00% 98.05%

PA 100.00% 95.15%

SMATV 77.45% 97.54%

CCTV 100.00% 99.34%

ICT 100.00% 82.44%

Page 27: ADTEC Pre No.23 July 09

BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)

Page 28: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 96.50% 96.99% 0.48%

JULAI 09’ 98.70% 99.63% 0.94%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 100.00%

FIRE FIGHTING 81.58% 100.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 93.26% 95.00%

DUST CONTROL 58.90% 96.91%

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITIBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 98.98% 100.00%

SUBMAIN CABLE 97.49% 100.00%

DB 97.48% 100.00%

LUMINAIRE 89.27% 100.00%

MAIN S/BOARD 85.25% 100.00%

LPS 89.22% 97.89%

PA 88.09% 93.93%

SMATV 100.00% 98.97%

CCTV 100.00% 99.00%

ICT 15.65% 81.61%

Page 29: ADTEC Pre No.23 July 09

BENGKEL KEJ. JAMINAN KUALITI

Page 30: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 95.58% 95.59% 0.01%

JULAI 09’ 98.23% 98.62% 0.39%

MECHANICAL PLANNED

ACTUAL

AIR COND 97.16% 100.00%

FIRE FIGHTING 80.91% 100.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR 93.26% 95.00%

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIKBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 99.00%

SUBMAIN CABLE 99.95% 100.00%

DB 96.10% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 100.00%

LPS 99.48% 98.16%

PA 97.01% 94.88%

SMATV 100.00% 99.30%

CCTV 100.00% 98.91%

ICT 98.34% 92.94%

Page 31: ADTEC Pre No.23 July 09

BENGKEL MIKRO ELEKTRONIK

Page 32: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 100.00% 100.00% 0.00%

JULAI 09’ 100.00% 100.00% 0.00%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 100.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 100.00%

LPS 100.00% 97.60%

PA NA NA

SMATV 100.00% 98.74%

CCTV 100.00% 99.82%

ICT 100.00% 100.00%

Page 33: ADTEC Pre No.23 July 09

KUARTERS KELAS ‘B’

Page 34: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 100.00% 100.00% 0.00%

JULAI 09’ 100.00% 100.00% 0.00%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 100.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 100.00%

LPS 100.00% 97.66%

PA NA NA

SMATV 100.00% 98.55%

CCTV NA NA

ICT 100.00% 99.06%

Page 35: ADTEC Pre No.23 July 09

KUARTERS KELAS ‘C’

Page 36: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 100.00% 100.00% 0.00%

JULAI 09’ 100.00% 100.00% 0.00%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 100.00%

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 90.00%

LPS 100.00% 97.96%

PA NA NA

SMATV 100.00% 98.74%

CCTV NA NA

ICT 100.00% 100.00%

Page 37: ADTEC Pre No.23 July 09

KUARTERS KELAS ‘C’ + ‘D’

Page 38: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 98.63% 98.85% 0.12%

JULAI 09’ 99.99% 100.00% 0.01%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 90.00%

LPS 99.02% 98.32%

PA NA NA

SMATV 100.00% 99.83%

CCTV NA NA

ICT 99.42% 99.34%

Page 39: ADTEC Pre No.23 July 09

KUARTERS KELAS ‘F’ ( 4 TINGKAT )

Page 40: ADTEC Pre No.23 July 09

KUARTERS KELAS ‘F’ ( 5 TINGKAT )

Page 41: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 99.57% 99.58% 0.01%

JULAI 09’ 100.00% 100.00% 0.00%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING NA NA

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G

(1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 100.00%

LPS 100.00% 98.32%

PA NA NA

SMATV 100.00% 99.83%

CCTV NA NA

ICT 100.00% 98.37%

Page 42: ADTEC Pre No.23 July 09

KUARTERS KELAS ‘G’ ( 5 TINGKAT )

Page 43: ADTEC Pre No.23 July 09

KUARTERS KELAS ‘G’ ( 4 TINGKAT )

Page 44: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 99.83% 96.63% 0.01%

JULAI 09’ 99.82% 100.00% 0.18%

MECHANICAL PLANNED

ACTUAL

AIR COND 98.79% 100.00%

FIRE FIGHTING 78.92% 100.00%

KITCHEN EQUIP. 83.70% 92.00%

LPG INSTALL. 82.56% 90.00%

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 100.00%

LPS 100.00% 98.51%

PA 96.95% 95.23%

SMATV 100.00% 99.43%

CCTV NA NA

ICT 100.00% 100.00%

Page 45: ADTEC Pre No.23 July 09

DEWAN MAKAN

Page 46: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 99.39% 99.55% 0.16%

JULAI 09’ 99.97% 100.00% 0.03%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 100.00%

FIRE FIGHTING 40.44% 100.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & BBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 100.00%

LPS 100.00% 98.60%

PA 93.00% 96.06%

SMATV 99.82% 99.31%

CCTV 100.00% 99.78%

ICT 100.00% 99.43%

Page 47: ADTEC Pre No.23 July 09

ASRAMA LELAKI A & B

Page 48: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 99.44% 99.50% 0.06%

JULAI 09’ 100.00% 100.00% 0.00%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 100.00%

FIRE FIGHTING 92.70% 100.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & DBANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 97.77% 100.00%

MAIN S/BOARD 100.00% 100.00%

LPS 100.00% 98.69%

PA 94.38% 95.64%

SMATV 99.75% 99.31%

CCTV 100.00% 99.75%

ICT 100.00% 99.62%

Page 49: ADTEC Pre No.23 July 09

ASRAMA PEREMPUAN C & D

Page 50: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 96.94% 96.63% -0.31%

JULAI 09’ 98.50% 99.90% 1.40%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING 100.00% 80.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - SURAU

BANGUNAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 85.00% 100.00%

LPS 99.32% 97.61%

PA 86.67% 92.79%

SMATV NA NA

CCTV NA NA

ICT NA NA

Page 51: ADTEC Pre No.23 July 09

SURAU

Page 52: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JUN 09’ 99.99% 99.83% -0.16%

JULAI 09’ 100.00% 100.00% 0.00%

MECHANICAL PLANNED

ACTUAL

AIR COND NA NA

FIRE FIGHTING 100.00% 80.00%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL - ASTAKA

BANGUNAN SOKONGAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 100.00% 100.00%

MAIN S/BOARD 100.00% 100.00%

LPS 100.00% 96.60%

PA 98.28% 93.55%

SMATV NA NA

CCTV NA NA

ICT NA NA

Page 53: ADTEC Pre No.23 July 09

BANGUNAN SOKONGAN

ASTAKA

Page 54: ADTEC Pre No.23 July 09

MONTH PLANNED ACTUAL AHEAD / DELAY

JULAI 09’ 100.00% 100.00% 0.00%

MECHANICAL PLANNED

ACTUAL

AIR COND 100.00% 99.53%

FIRE FIGHTING 78.13% 99.22%

KITCHEN EQUIP. NA NA

LPG INSTALL. NA NA

COMPRES. AIR NA NA

DUST CONTROL NA NA

PROCESS COOLING

NA NA

KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM

BANGUNAN SOKONGAN

ELECTRICAL PLANNED ACTUAL

WIRING 100.00% 100.00%

SUBMAIN CABLE 100.00% 100.00%

DB 100.00% 100.00%

LUMINAIRE 96.52% 100.00%

MAIN S/BOARD 80.52% 100.00%

LPS NA NA

PA NA NA

SMATV NA NA

CCTV NA NA

ICT NA NA

Page 55: ADTEC Pre No.23 July 09

BANGUNAN SOKONGAN

M&E PLANT ROOM – PUSAT SUMBER

Page 56: ADTEC Pre No.23 July 09

BANGUNAN SOKONGAN

M&E PLANT ROOM - BENGKEL

Page 57: ADTEC Pre No.23 July 09

DECORATIVE FENCE

Page 58: ADTEC Pre No.23 July 09

BANGUNAN SOKONGAN

GARAJ KENDERAAN

Page 59: ADTEC Pre No.23 July 09

ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK

Page 60: ADTEC Pre No.23 July 09

RUMAH SAMPAH

Page 61: ADTEC Pre No.23 July 09

LALUAN BERBUMBUNG

Page 62: ADTEC Pre No.23 July 09

OPEN PLAZA

Page 63: ADTEC Pre No.23 July 09

KERJA INFRA – JALAN UTAMA

Page 64: ADTEC Pre No.23 July 09

GELANGGANG PERMAINAN

Page 65: ADTEC Pre No.23 July 09

GELANGGANG PERMAINAN

Page 66: ADTEC Pre No.23 July 09

PADANG PERMAINAN BOLA SEPAK

Page 67: ADTEC Pre No.23 July 09

BENGKEL MIKRO - CLEANROON

Page 68: ADTEC Pre No.23 July 09

M&E : AHU @ CLEAN ROOM

Page 69: ADTEC Pre No.23 July 09

BENGKEL KEJ. BAHAN TERMAJU (SERAMIK) - EPOXY

Page 70: ADTEC Pre No.23 July 09

PERABUT – PUSAT SUMBER

Page 71: ADTEC Pre No.23 July 09

• SEKIAN TERIMA KASIH