LAPORAN KEMAJUAN PROJEK NO.22
‘JUN 2009’
PROJEK ADTEC TAIPING
KEMENTERIAN SUMBER MANUSIA
JABATAN KERJA RAYA MALAYSIA
KAMALBINA SDN. BHD
PEMILIK
PEGARAH PROJEK
KONTRAKTOR R&B
![Page 2: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/2.jpg)
ADTEC TAIPING
LOKASI PROJEK
![Page 3: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/3.jpg)
BANGUNAN PENTADBIRAN
BENGKEL TEK. MAKLUMAT& JAMIN KUALITI
DEWAN BESAR
PUSAT SUMBER
DEWAN KULIAH
LOBI UTAMA
KAFETERIA
MIKRO ELEKTRONIK
KOMPOSIT PLASTIK
M&E PLANT ROOM
1
TNB SUB
STATION
SERAMIK
M&E PLANT ROOM
2
GARAJ KENDERAAN
ASRAMA LELAKIASRAMA PEREMPUAN
DEWANMAKAN
SURAU
KELAS F
KELAS G
KUARTERSB, C, C&D
PELAN TAPAK ADTEC TAIPING
![Page 4: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/4.jpg)
KEMAJUAN KERJA FIZIKAL
JADUAL : 85.16 %SEBENAR : 87.59 %KESELURUHAN : 2.43 %
TARIKH LAPORAN : 12 JUN 2009
![Page 5: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/5.jpg)
KEMAJUAN KERJA KEWANGAN
JADUAL : 85.09 %SEBENAR : 86.12 %KESELURUHAN : 1.03 %
TARIKH LAPORAN : 12 JUN 2009
![Page 6: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/6.jpg)
![Page 7: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/7.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 88.35% 92.38% 4.03%
JUN 09’ 94.21% 96.74% 2.53%
MECHANICAL PLANNED
ACTUAL
AIR COND 94.85% 95.50%
FIRE FIGHTING 81.61% 95.74%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - DEWAN BESAR
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 90.00%
MAIN S/BOARD 100.00% 95.00%
LPS NA NA
PA 94.88% 67.17%
SMATV 83.38% 86.79%
CCTV NA NA
ICT 3.31% 74.25%
![Page 8: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/8.jpg)
DEWAN BESAR
![Page 9: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/9.jpg)
DEWAN BESAR
![Page 10: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/10.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 98.92% 94.90% -4.02%
JUN 09’ 99.68% 99.72% 0.04%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – LOBI
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 95.90% 100.00%
SUBMAIN CABLE 94.17% 100.00%
DB 75.00% 100.00%
LUMINAIRE 87.89% 100.00%
MAIN S/BOARD NA NA
LPS NA NA
PA NA NA
SMATV NA NA
CCTV 88.68% 92.58%
ICT NA NA
![Page 11: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/11.jpg)
LOBI UTAMA
![Page 12: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/12.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 92.24% 91.71% -0.52%
JUN 09’ 98.54% 98.19% -0.35%
MECHANICAL PLANNED
ACTUAL
AIR COND 96.19% 95.00%
FIRE FIGHTING 81.51% 86.04%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – DEWAN KULIAH UTAMABANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 75.00% 100.00%
LUMINAIRE 91.65% 95.00%
MAIN S/BOARD 75.00% 95.00%
LPS 90.51% 92.01%
PA 37.88% 65.71%
SMATV NA NA
CCTV NA NA
ICT 0.91% 74.48%
![Page 13: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/13.jpg)
DEWAN KULIAH UTAMA
![Page 14: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/14.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 95.30% 95.38% 0.09%
JUN 09’ 97.50% 98.54% 1.04%
MECHANICAL PLANNED
ACTUAL
AIR COND 93.54% 85.18%
FIRE FIGHTING 39.81% 81.59%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – PUSAT SUMBER/PERPUSTAKAAN
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 97.53% 97.00%
SUBMAIN CABLE 93.31% 98.00%
DB 85.00% 100.00%
LUMINAIRE 92.27% 98.00%
MAIN S/BOARD 85.00% 95.00%
LPS 91.25% 96.92%
PA 44.70% 69.69%
SMATV 94.54% 88.33%
CCTV NA NA
ICT 18.16% 23.36%
![Page 15: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/15.jpg)
PUSAT SUMBER / PERPUSTAKAAN
![Page 16: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/16.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 92.72% 92.73% 0.01%
JUN 09’ 96.42% 96.51% 0.09%
MECHANICAL PLANNED
ACTUAL
AIR COND 91.09% 94.96%
FIRE FIGHTING 47.94% 74.24%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – PENTADBIRAN & PENGURUSAN SUMBERBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 99.48% 97.00%
SUBMAIN CABLE 97.32% 98.00%
DB 85.00% 100.00%
LUMINAIRE 82.78% 95.00%
MAIN S/BOARD 75.00% 95.00%
LPS 87.80% 90.85%
PA 63.70% 58.92%
SMATV 95.99% 88.07%
CCTV 73.69% 70.43%
ICT 24.87% 51.37%
![Page 17: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/17.jpg)
BANGUNAN PENTADBIRAN & PENGURUSAN SUMBER
![Page 18: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/18.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 98.36% 98.71% 0.08%
JUN 09’ 99.58% 99.23% -0.35%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 100.00%
FIRE FIGHTING 90.22% 74.56%
KITCHEN EQUIP. 65.55% 69.00%
LPG INSTALL. 40.84% 48.50%
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - KAFETARIA
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD NA NA
LPS 100.00% 88.81%
PA 94.53% 62.91%
SMATV 92.47% 87.44%
CCTV NA NA
ICT 0.00% 75.00%
![Page 19: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/19.jpg)
KAFETERIA
![Page 20: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/20.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 93.95% 95.49% 1.54%
JUN 09’ 98.05% 98.01% -0.05%
MECHANICAL PLANNED
ACTUAL
AIR COND 86.90% 91.36%
FIRE FIGHTING 31.85% 63.60%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – BENGKEL TEKNOLOGI MAKLUMATBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 99.23% 96.00%
SUBMAIN CABLE 98.21% 100.00%
DB 97.27% 100.00%
LUMINAIRE 92.51% 100.00%
MAIN S/BOARD 75.00% 95.00%
LPS 100.00% 96.80%
PA 100.00% 73.49%
SMATV 95.09% 89.00%
CCTV 79.13% 291.22%
ICT 8.53% 19.28%
![Page 21: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/21.jpg)
BENGKEL TEKNOLOGI MAKLUMAT
![Page 22: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/22.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 96.82% 95.67% -1.14%
JUN 09’ 98.42% 98.30% -0.12%
MECHANICAL PLANNED
ACTUAL
AIR COND 93.36% 93.41%
FIRE FIGHTING 45.37% 72.69%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 87.25% 85.00%
DUST CONTROL NA NA
PROCESS COOLING
41.53% 0.00%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 75.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 75.00% 95.00%
LPS 92.90% 96.80%
PA 62.47% 75.48%
SMATV 75.18% 74.39%
CCTV 83.97% 93.08%
ICT 26.23% 23.86%
![Page 23: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/23.jpg)
BENGKEL KEJ. BAHAN TERMAJU (PLASTIK)
![Page 24: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/24.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 97.05% 95.65% -1.40%
JUN 09’ 98.46% 98.41% -0.05%
MECHANICAL PLANNED
ACTUAL
AIR COND 80.73% 78.34%
FIRE FIGHTING 43.93% 69.10%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 87.25% 85.00%
DUST CONTROL 31.69% 77.29%
PROCESS COOLING
38.45% 0.00%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 95.00%
LPS 97.29% 93.25%
PA 92.78% 72.21%
SMATV 75.26% 75.20%
CCTV 86.10% 92.75%
ICT 21.23% 18.81%
![Page 25: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/25.jpg)
BENGKEL KEJ. BAHAN TERMAJU (KOMPOSIT)
![Page 26: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/26.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 95.12% 94.67% -0.46%
JUN 09’ 97.15% 97.14% -0.02%
MECHANICAL PLANNED
ACTUAL
AIR COND 91.33% 92.19%
FIRE FIGHTING 44.40% 69.54%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 87.25% 85.00%
DUST CONTROL 11.65% 72.95%
PROCESS COOLING
21.79% 0.00%
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 99.29% 100.00%
DB 78.00% 100.00%
LUMINAIRE 96.30% 100.00%
MAIN S/BOARD 85.00% 95.00%
LPS 90.20% 96.49%
PA 96.64% 72.96%
SMATV 73.29% 74.70%
CCTV 90.23% 93.97%
ICT 33.22% 27.44%
![Page 27: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/27.jpg)
BENGKEL KEJ. BAHAN TERMAJU (SERAMIK)
![Page 28: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/28.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 94.30% 95.17% -0.87%
JUN 09’ 96.50% 96.99% 0.48%
MECHANICAL PLANNED
ACTUAL
AIR COND 82.68% 59.54%
FIRE FIGHTING 26.16% 63.17%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 87.25% 85.00%
DUST CONTROL 38.25% 80.74%
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – BENGKEL KEJ. JAMINAN KUALITIBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 97.67% 96.00%
SUBMAIN CABLE 95.02% 97.00%
DB 95.02% 95.00%
LUMINAIRE 77.98% 90.00%
MAIN S/BOARD 57.17% 95.00%
LPS 86.74% 96.20%
PA 42.25% 68.68%
SMATV 87.59% 85.36%
CCTV 80.71% 90.90%
ICT 7.17% 18.61%
![Page 29: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/29.jpg)
BENGKEL KEJ. JAMINAN KUALITI
![Page 30: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/30.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 92.86% 94.80% 1.94%
JUN 09’ 95.58% 95.59% 0.01%
MECHANICAL PLANNED
ACTUAL
AIR COND 93.43% 91.50%
FIRE FIGHTING 22.33% 59.71%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR 87.25% 85.00%
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – BENGKEL MIKRO ELEKTRONIKBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 96.00%
SUBMAIN CABLE 96.67% 95.00%
DB 72.68% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 95.00%
LPS 92.34% 96.70%
PA 52.92% 72.02%
SMATV 91.26% 86.86%
CCTV 84.11% 91.21%
ICT 6.84% 22.94%
![Page 31: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/31.jpg)
BENGKEL MIKRO ELEKTRONIK
![Page 32: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/32.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 100.00% 100.00% 0.00%
JUN 09’ 100.00% 100.00% 0.00%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 100.00%
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘B’
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 100.00%
LPS 100.00% 95.68%
PA NA NA
SMATV 84.58% 68.14%
CCTV 79.71% 93.15%
ICT 100.00% 90.00%
![Page 33: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/33.jpg)
KUARTERS KELAS ‘B’
![Page 34: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/34.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 100.00% 100.00% 0.00%
JUN 09’ 100.00% 100.00% 100.00%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 100.00%
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C’
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 90.00%
LPS 100.00% 95.78%
PA NA NA
SMATV 82.56% 46.09%
CCTV NA NA
ICT 100.00% 84.06%
![Page 35: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/35.jpg)
KUARTERS KELAS ‘C’
![Page 36: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/36.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 100.00% 100.00% 0.00%
JUN 09’ 100.00% 100.00% 0.00%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 100.00%
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS ‘C+D’BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 90.00%
LPS 100.00% 96.33%
PA NA NA
SMATV 84.58% 86.14%
CCTV NA NA
ICT 100.00% 90.00%
![Page 37: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/37.jpg)
KUARTERS KELAS ‘C’ + ‘D’
![Page 38: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/38.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 97.14% 98.49% 1.36%
JUN 09’ 98.63% 98.85% 0.12%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS F ( 1 BLOK 4 TINGKAT & I BLOK 5 TINGKAT)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 90.00%
LPS 93.30% 96.98%
PA NA NA
SMATV 95.77% 93.31%
CCTV NA NA
ICT 96.04% 92.34%
![Page 39: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/39.jpg)
KUARTERS KELAS ‘F’ ( 4 TINGKAT )
![Page 40: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/40.jpg)
KUARTERS KELAS ‘F’ ( 5 TINGKAT )
![Page 41: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/41.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 97.58% 98.48% 0.90%
JUN 09’ 99.57% 99.58% 0.01%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING NA NA
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – KUATERS KELAS G
(1 BLOK 4 TINGKAT & 1 BLOK 5 TINGKAT)BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 90.00%
LPS 100.00% 96.98%
PA NA NA
SMATV 95.77% 93.31%
CCTV NA NA
ICT 100.00% 98.37%
![Page 42: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/42.jpg)
KUARTERS KELAS ‘G’ ( 5 TINGKAT )
![Page 43: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/43.jpg)
KUARTERS KELAS ‘G’ ( 4 TINGKAT )
![Page 44: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/44.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 99.42% 99.60% 0.18%
JUN 09’ 99.83% 96.63% 0.01%
MECHANICAL PLANNED
ACTUAL
AIR COND 90.95% 100.00%
FIRE FIGHTING 57.40% 72.89%
KITCHEN EQUIP. 65.55% 69.00%
LPG INSTALL. 40.84% 48.50%
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – DEWAN MAKAN
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 98.00%
DB 100.00% 95.00%
LUMINAIRE 100.00% 80.00%
MAIN S/BOARD 100.00% 90.00%
LPS 100.00% 97.32%
PA 56.87% 73.23%
SMATV 92.47% 90.79%
CCTV NA NA
ICT 100.00% 75.35%
![Page 45: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/45.jpg)
DEWAN MAKAN
![Page 46: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/46.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 98.70% 99.43% 0.73%
JUN 09’ 99.39% 99.55% 0.16%
MECHANICAL PLANNED
ACTUAL
AIR COND 89.66% 100.00%
FIRE FIGHTING 39.31% 84.41%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – ASRAMA LELAKI A & BBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 99.33% 100.00%
SUBMAIN CABLE 94.80% 97.00%
DB 100.00% 90.00%
LUMINAIRE 100.00% 95.00%
MAIN S/BOARD 100.00% 90.00%
LPS 98.56% 97.48%
PA 64.19% 76.16%
SMATV 72.72% 89.94%
CCTV 79.47% 92.93%
ICT 97.72% 92.43%
![Page 47: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/47.jpg)
ASRAMA LELAKI A & B
![Page 48: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/48.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 98.95% 99.37% 0.52%
JUN 09’ 99.44% 99.50% 0.06%
MECHANICAL PLANNED
ACTUAL
AIR COND 76.12% 100.00%
FIRE FIGHTING 81.16% 85.89%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – ASRAMA PEREMPUAN C & DBANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 99.23`% 100.00%
SUBMAIN CABLE 98.85% 97.00%
DB 94.81% 90.00%
LUMINAIRE 92.21% 95.00%
MAIN S/BOARD 100.00% 90.00%
LPS 100.00% 97.64%
PA 60.31% 74.66%
SMATV 72.35% 89.94%
CCTV 84.84% 92.62%
ICT 99.49% 91.62%
![Page 49: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/49.jpg)
ASRAMA PEREMPUAN C & D
![Page 50: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/50.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 95.20% 92.10% 0.69%
JUN 09’ 96.94% 96.63% -0.31%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING 100.00% 75.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - SURAU
BANGUNAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 76.89% 100.00%
MAIN S/BOARD 85.00% 95.00%
LPS 91.35% 96.24%
PA 30.52% 64.71%
SMATV NA NA
CCTV NA NA
ICT NA NA
![Page 51: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/51.jpg)
SURAU
![Page 52: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/52.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
MEI 09’ 99.80% 99.83% 0.04%
JUN 09’ 99.99% 99.83% -0.16%
MECHANICAL PLANNED
ACTUAL
AIR COND NA NA
FIRE FIGHTING 100.00% 75.00%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL - ASTAKA
BANGUNAN SOKONGAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 100.00%
SUBMAIN CABLE 100.00% 100.00%
DB 100.00% 100.00%
LUMINAIRE 100.00% 100.00%
MAIN S/BOARD 100.00% 90.00%
LPS 97.85% 93.89%
PA 38.16% 67.38%
SMATV NA NA
CCTV NA NA
ICT NA NA
![Page 53: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/53.jpg)
BANGUNAN SOKONGAN
ASTAKA
![Page 54: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/54.jpg)
MONTH PLANNED ACTUAL AHEAD / DELAY
JUN 09’ 100.00% 100.00% 0.00%
MECHANICAL PLANNED
ACTUAL
AIR COND 100.00% 99.53%
FIRE FIGHTING 32.54% 90.34%
KITCHEN EQUIP. NA NA
LPG INSTALL. NA NA
COMPRES. AIR NA NA
DUST CONTROL NA NA
PROCESS COOLING
NA NA
KEMAJUAN KERJA FIZIKAL – M&E PLANT ROOM
BANGUNAN SOKONGAN
ELECTRICAL PLANNED ACTUAL
WIRING 100.00% 97.00%
SUBMAIN CABLE 100.00% 90.00%
DB 100.00% 0.00%
LUMINAIRE 92.72% 90.00%
MAIN S/BOARD 54.00% 100.00%
LPS NA NA
PA NA NA
SMATV NA NA
CCTV NA NA
ICT NA NA
![Page 55: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/55.jpg)
BANGUNAN SOKONGAN
M&E PLANT ROOM – PUSAT SUMBER
![Page 56: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/56.jpg)
BANGUNAN SOKONGAN
M&E PLANT ROOM - BENGKEL
![Page 57: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/57.jpg)
DECORATIVE FENCE
![Page 58: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/58.jpg)
BANGUNAN SOKONGAN
GARAJ KENDERAAN
![Page 59: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/59.jpg)
ELEVATED WATER TANK, PUMP HOUSE & SUCTION TANK
![Page 60: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/60.jpg)
RUMAH SAMPAH
![Page 61: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/61.jpg)
LALUAN BERBUMBUNG
![Page 62: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/62.jpg)
OPEN PLAZA
![Page 63: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/63.jpg)
KERJA INFRA – JALAN UTAMA
![Page 64: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/64.jpg)
GELANGGANG PERMAINAN
![Page 65: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/65.jpg)
GELANGGANG PERMAINAN
![Page 66: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/66.jpg)
GELANGGANG PERMAINAN
![Page 67: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/67.jpg)
BENGKEL MIKRO - CLEANROON
![Page 68: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/68.jpg)
M&E : FIRE FIGHTING
![Page 69: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/69.jpg)
STAGE : DEWAN KULIAH
![Page 70: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/70.jpg)
BENGKEL JAMINAN KULITI
![Page 71: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/71.jpg)
KITCHEN HOOD : CAFETERIA
![Page 72: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/72.jpg)
M&E
![Page 73: ADTEC JUN 09](https://reader033.vdocuments.mx/reader033/viewer/2022061112/54566b4aaf7959ac688b55cb/html5/thumbnails/73.jpg)
• SEKIAN TERIMA KASIH