40. special meeting on pending protection … projects of ntpc, nlc, npcil, joint venture & umpp...
TRANSCRIPT
Minutes of the 30th SRPC Meeting held on 27th August 2016
CONTENTS 1. INTRODUCTION............................................................................................................................................... 4
2. CONFIRMATION OF THE MINUTES OF 29th MEETING OF SRPC ...................................................................... 6
3. MEMBERSHIP TO RPC ..................................................................................................................................... 6
4. FLEXIBILITY IN UTILIZATION OF DOMESTIC COAL FOR REDUCING COST OF POWER GENERATION .............. 8
5. TERMS OF REFERENCE FOR RENEWABLE INTEGRATION – TASK FORCE ...................................................... 10
6. DETERMINATION OF TRANFER PRICE OF LIGNITE IN RESPECT OF NLC MINES FOR THE PERIOD 2014-19 –
REQUEST FOR MODIFICATIONS IN THE NOTIFICATION OF MOC ................................................................. 11
7. PREPARATION FOR MEETING REVISED ENVIRONMENT NORMS AS PER ENVIRONMENT (PROTECTION)
AMEN DMENT RULES, 2015 .......................................................................................................................... 12
8. ROADMAP TO OPERATIONALISE RESERVES IN THE COUNTRY ..................................................................... 14
9. COMPLIANCE OF ORDER OF HON’BLE CERC IN PETITION NO. 420/MP/2014 – IN RESPECT OF LVRT AND
OTHER PROVISIONS OF CEA/CERC REGULATIONS ....................................................................................... 15
10. LOW VOLTAGES ............................................................................................................................................ 18
11. PATROLLING / MAINTENANCE OF CRITICAL LINES AND SUBSTATIONS ....................................................... 21
12. CONTINGENCY OF 400 kV NELLORE - NELLORE PS LINES ............................................................................. 22
13. STATUS OF GENERATION IN GENERATING STATIONS .................................................................................. 23
14. REVIEW OF ULDC / SCADA/COMMUNICATION ............................................................................................ 24
15. TTC/ATC ........................................................................................................................................................ 28
16. UPCOMING TRANSMISSION SYSTEM ........................................................................................................... 29
17. UPCOMING RENEWABLE PROJECTS AND THEIR INTEGRATION WITH TRANSMISSION NETWORK ............. 44
18. NEW PROJECTS OF NTPC, NLC, NPCIL, JOINT VENTURE & UMPP ................................................................ 46
19. NEW PROJECTS OF STATE SECTOR & IPP ...................................................................................................... 48
20. EMERGENCY RESTORATION SYSTEM (ERS) .................................................................................................. 49
21. PROGRESS OF BUS/LINE REACTORS TO BE COMMISSIONED IN SR .............................................................. 51
22. OUTSTANDING DUES BETWEEN SOUTHERN AND WESTERN REGIONS ....................................................... 56
23. NON-AVAILING OF OCC APPROVED SHUTDOWN ......................................................................................... 57
24. SPARE ICT AND REACTOR PLACEMENT AND USAGE PROCEDURE ............................................................... 58
25. IEGC RELATED ISSUES REQUIRING ATTENTION/ACTION .............................................................................. 59
26. AUGMENTATION OF TALCHER-II TRANSMISSION SYSTEM .......................................................................... 73
27. INCLUSION OF DRAWAL OF MAHE IN REA ................................................................................................... 73
28. SHARING OF TRANSMISSION CHARGES OF TRANSMISSION ASSETS OF NATIONAL IMPORTANCE ............. 74
29. APPROACH BEING TAKEN BY CTU FOR RESERVING THE TRANSMISSION CAPACITY FOR THE CUSTOMERS
WHO HAVE AVAILED LTA WITHOUT IDENTIFYING BENEFICIARIES .............................................................. 75
Minutes of the 30th SRPC Meeting held on 27th August 2016
30. STATUS OF PHASE I AND PHASE II OF PROTECTION AUDIT RECOMMENDATIONS ...................................... 75
31. GRID OPERATION .......................................................................................................................................... 79
32. THOROUGH REVIEW OF ALL THE DRAWAL POINTS OF STATES FOR DRAWAL COMPUTATIONS ................. 86
33. TPCIL REQUEST TO EXEMPT DEVIATION CHARGES ...................................................................................... 87
34. SCHEDULING OF NTPC RAMAGUNDAM SOLAR POWER PLANT (10 MW) .................................................... 87
35. GRID STUDY COMMITTEE (TASK- 2) AUDIT PROGRESS DETAILS .................................................................. 87
36. IMPLEMENTATION OF PROTECTION SUITE / PROTECTION MANAGEMENT SYSTEM (PMS) FOR SOUTHERN
REGION ......................................................................................................................................................... 89
37. OVER VOLTAGE RELAY (OVR) GRADINGS FOR 400 KV TRANSMISSION LINES OF THE SOUTHERN REGION 89
38. PROTECTION SYSTEM ANALYSIS GROUP (PSAG-15) MEETING HELD AT NTPL, TUTICORIN ......................... 89
39. SPECIAL MEETING ON ISSUES RELATING TO RECENT GRID DISTURBANCES IN GAJUWAKA – SIMHADRI -
KALPAKA CORRIDOR HELD ON 04TH MAY, 2016 AT SRPC, BENGALURU ....................................................... 91
40. SPECIAL MEETING ON PENDING PROTECTION ISSUES OF M/S KPCL HELD ON 03.06.2016 AT SRPC,
BENGALURU .................................................................................................................................................. 92
41. REVIEW OF ISLANDING SCHEMES OF SOUTHERN REGION .......................................................................... 92
42. PROTECTION SYSTEM ANALYSIS GROUP (PSAG-16) MEETING HELD AT AMBEWADI SS HELD ON
18.07.2016 .................................................................................................................................................... 94
43. PENDING IMPLEMENTATION OF RECOMMENDATIONS OF PROTECTION COORDINATION SUB-COMMITTEE
(PCSC) OF SRPC ............................................................................................................................................. 95
44. STUDY PROGRAMME ON THE INTEGRATION OF RENEWABLE ENERGY RESOURCES INTO THE GRID ......... 95
45. IEGC, FOURTH AMENDMENT REGULATIONS 2016- TECHNICAL MINIMUM OF GENERATORS /
COMPENSATION PROCEDURE FOR SHR & AEC ............................................................................................ 95
46. SCHEDULING/OPERATIONAL ISSUES IN RESPECT OF NP KUNTA UMSPPS – 1 ............................................. 95
47. COMMERCIAL COMMITTEE ISSUES .............................................................................................................. 95
48. REVIVAL OF UNITS AT SHARAVATHI GENERATING STATION ........................................................................ 97
49. REFERENCE FROM MNRE REGARDING COMPILATION OF DATA FOR MEETING RENEWABLE ENERGY
TARGETS OF 175 GW BY 2020 ...................................................................................................................... 98
50. PROVIDING INFORMATION REGARDING COMMISSIONING AND DECLARATION OF COD OF POWER
GENERATING UNITS ...................................................................................................................................... 98
51. FORECASTING, SCHEDULING AND DEVIATION SETTLEMENT OF WIND AND SOLAR GENERATING
STATIONS AT THE STATE LEVEL .................................................................................................................... 98
52. SKILL PLAN FOR POWER SECTOR BASED ON THE ASSESSED SKILL GAP IN THE SECTOR .............................. 99
53. ISSUES IN OPGW STRINGING UNDER FIBRE EXPANSION PROJECT OF SR (REFER ITEM 25.16) .................... 99
54. REPLACEMENT OF WRAP FIBRE CABLE WITH OPGW IN GOOTY-BANGALORE & UDUMALPET-TRICHUR
LINKS ........................................................................................................................................................... 100
55. SUBSTATION ICT- 3 BAY EXTENSION WORKS AT OUR 400 KV MADURAI AND TRICHY STATIONS ............. 101
Minutes of the 30th SRPC Meeting held on 27th August 2016
56. CALIBRATION TESTING OF SEMS IN SOUTHERN REGION CALIBRATION TESTING OF SEMS IN SOUTHERN
REGION ....................................................................................................................................................... 101
57. CONCURRENCE FOR EARLY COMMISSIONING OF 765KV WARDHA – NIZAMABAD D/C, 400KV
NIZAMABAD – DICHPALLI D/C (HTLS) AND 765/400KV NIZAMABAD GIS .................................................. 102
58. SRPC CERTIFICATION TO CLAIM ADDITIONAL ROE FOR LILO OF 400 KV KADAPA-KOLAR S/C LINE AT NP
KUNTA AND ESTABLISHMENT OF 400/220 KV SUB-STATION AT NP KUNTA ............................................. 102
59. NTPC KUDGI 400/220 KV LOSSES ............................................................................................................... 103
60. NTPC SIMHADRI-II SCHEDULING ISSUES ..................................................................................................... 103
61 20-YEAR (2016-36) PERSPECTIVE TRANSMISSION PLAN REPORT .............................................................. 106
62 REIMBURSEMENT OF SRPC EXPENDITURE ................................................................................................. 107
63 VOTE OF THANKS ........................................................................................................................................ 107
64 DATE & VENUE OF THE NEXT SRPC MEETING ............................................................................................ 107
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 4 of 107
SOUTHERN REGIONAL POWER COMMITTEE
BENGALURU
MINUTES OF THE 30th
MEETING OF SRPC HELD ON 27th
AUGUST 2016 AT CHENNAI
1. INTRODUCTION
1.1 The 30th
Meeting of Southern Regional Power Committee (SRPC) was held on 27th
August 2016 at Chennai. The list of the participants is given at Annexure-I.
1.2 On behalf of Chairman, NTECL as well as the NTECL team, NTECL extended a
hearty welcome to Chairperson , SRPC, Dr M Saikumar, CMD, TANGEDCO and all
other esteemed Members of SPRC to the proceedings. NTECL also cited the following
‘Coming together is the beginning. Keeping together is progress. Working together is
success..’ – Henry Ford.
1.3 Shri Thomas Joseph, CEO, NTECL welcomed Chairperson, SRPC and esteemed
Members of SRPC to the 30th
Meeting of SRPC. NTECL was honored to hold the 30th
SRPC meet in this beautiful heritage city of Mamallapuram. Team NTECL had been
meticulously planning the conduct of this Meeting. It was a matter of pride that
NTECL station was running to its full capacity after overcoming major technical and
logistic issues. Concern of the esteemed beneficiaries regarding delay in stabilization of
the station had been addressed and they were looking forward towards continued
support.
1.4 Shri K Biswal, Chairman, NTECL and Director (F), NTPC welcomed Chairperson, SRPC
& CMD, TANGEDCO, Principal Secretary (Energy), Govt. of Maharashtra, esteemed
members of SRPC and delegates to the meeting being held in the ancient port city of
Pallavas, Mamallapuram (heritage site declared by UNESCO). He thanked Chairperson,
SRPC for having given NTECL the opportunity to host this prestigious SRPC meeting.
SRPC plays a very pivotal role in facilitating stable and efficient grid operation. SRPC is
widely respected for its contribution in evolving a unified grid. Challenges in grid
operation had become increasingly complex on account of increased thrust on renewable.
SR grid had strong presence of wind energy and was going ahead with aggressive capacity
addition in solar power also. NTPC was going to add 2,000 MW of Solar – 1,000 MW on
its own and 1,000 MW under the National Solar Mission in various states like Andhra
Pradesh, Telangana and Karnataka in the near future. With strong presence of Wind and
Solar, Southern Region would be definitely be a trend setter in tackling issues linked to
assimilation of renewable into the grid. He requested the august gathering to fix norms
and establish a canon for balanced integration of renewable with conventional energy
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 5 of 107
resources. Generation level at NTECL had been an area of concern for beneficiaries in the
past 2-3 Meetings of SRPC. NTECL had faced certain stabilization/teething problems like
coal supply, logistics, turbo generator problem for 3rd
unit, desalination plant etc. With
continuous effort, all problems had been overcome and all the three units were running at
full capacity. Adequate coal stock for more than 15 days was available and they had also
started transporting coal from MCL through Dhamra port. NTECL was one of the
cheapest stations with variable cost of less than Rs.2/unit. He requested for continuous
support and patronage which would enable NTECL to support the beneficiaries. He
wished the Meeting best of deliberations.
1.5 Shri S R Bhat, Member Secretary, SRPC welcomed Dr M Saikumar, Chairperson, SRPC
& Chairman, TNEB and Members to the 30th
Meeting of SRPC. He on behalf of SRPC
placed on record, the leadership of Shri M Sivasankar, CMD, KSEBL outgoing
Chairperson during his tenure. He also welcomed Shri T K Barai, Member (GO&D,
Planning and Thermal), CEA to the Meeting.
SRPC welcomed the following Members:
Shri T K Barai, Member (GO &D), CEA Shri M M Nayak, CMD, APEPDCL Shri G Kumar Naik Managing Director, KPCL Shri Paul Antony, CMD, KSEB Ltd Shri N. Venugopal, Director (Distribution & Safety), KSEBL
Dr. S. Sundaravadivelu, Secretary (Power), Govt. of Puducherry Shri G Raghuma Reddy, CMD, TSSPDCL, Hyderabad
Shri A R Neelakanta Pillai CEO, NTPL Shri S M Zafrulla, MD, Coastal Energen Pvt
SRPC also placed on record, the excellent services rendered by following outgoing
Members:
Shri Major Singh, Member (GO &D), CEA Shri R Mutyala Raju CMD, APEPDCL
Shri M.Maheshwar Rao Managing Director, KPCL Ms B.Nina, Director (Distribution & Safety), KSEBL Shri G. Theva Neethi Dhas Secretary (Power), Govt. of Puducherry
Shri P.R.Raghuram, ED, SRLDC, POSOCO Shri S.Sathiyanarayanan, CEO, NTPL, Tuticorin Shri K.Venkatanarayana, CMD, TSNPDCL, Warangal
1.6 Dr M Saikumar, Chairperson, SRPC & Chairman, TNEB welcomed all Members to the
30th
Meeting of SRPC. He thanked the host, NTECL, who had taken meticulous care to
host the Meeting. Southern Region needs to concentrate on issues relating to renewable
and its integration. Tamil Nadu had around 9,000 MW of renewable sources. Andhra
Pradesh, Telangana and Karnataka were very bullish about Solar. Each of the state could
add about 2,000-3,000 MW of Solar power in next couple of years and it would be a real
challenge to integrate. Nuclear stations could not be backed down during any demand
crash. Managing renewable versus conventional energy and grid management was to be
deliberated and South had to show the way in this regard. Compared to North and East
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 6 of 107
Regions, South was better placed in sufficiency and integration of renewable, though
Western Region was quite advanced. In next couple of years about 20,000 to 25,000 MW
of renewable was to be integrated seamlessly. Contribution of Conventional energy was
also important and around 15,000 MW of conventional energy was in the pipeline in
Tamil Nadu in coming seven years. It was heartening to note that domestic coal usage
production had increased, though a few bottlenecks in transportation and railways still
persisted. While domestic coal was important, getting quality coal was also important.
Bottlenecks needed to be settled by Railways and Ports and till that time dependence on
imported coal might remain.
2. CONFIRMATION OF THE MINUTES OF 29th
MEETING OF SRPC
2.1 Minutes of the 29th
Meeting of SRPC held on 5th
March 2016 in Vishakhapatnam had
been circulated vide letter dated 19th
May 2016.
2.2 Minutes of the Meeting were confirmed.
3. MEMBERSHIP TO RPC
3.1 Special Invitee /Membership status to M/s.PTC in RPCs
3.1.1 In the 5th
NPC Meeting held on 08th
April 2016 (MoM at Annexure-II), the following had
been noted:
Grid Management Division, CEA had informed that M/s.PTC had requested for Special
Invitee / Membership status in all RPCs and had proposed deliberation on this issue in
the NPC meeting.
Chairperson, CEA had opined that it should be as per GoI resolution. For ERPC, due
to international transactions, special provision can be made but the approval of MoP
through CEA can be sought.
After detailed deliberations, it had been agreed that the issue of membership for Traders
would be deliberated in respective RPCs and outcome thereof would be communicated
to CEA for taking up the matter with MoP.
SRPC deliberations
3.1.2 MS, SRPC informed that MoP Resolution stipulated the composition of RPC. CEA had
recently nominated M/s Adani Enterprises Ltd., as Trader Member to SRPC. CEA was
working out Membership of traders to various RPCs on rotation basis.
3.1.3 SRPC concluded that the proposal to include M/s.PTC as SRPC Member could be
deferred. Presently, composition as stipulated in the MoP Resolution could be continued.
3.2 Membership of IPPs in RPCs
3.2.1 The number of IPPs having more than 1000 MW installed capacity was increasing. In the
5th
NPC Meeting held on 08th
April 2016 (refer Annexure-II), the following had been
noted:
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 7 of 107
WRPC had proposed to enhanced the limit of 1,000 MW to 2,000 MW for
membership of IPP in RPCs. NRPC had suggested that instead of allowing them
RPC membership the IPPs might be included in subcommittee like TCC/OCC.
NPC had suggested that the issue be deliberated first in respective RPCs and after
evolving a common view, the same would be referred to MoP for amendment in
Resolution.
SRPC deliberations
3.2.2 MS, SRPC stated that in case eligibility criteria was increased to 2,000 MW then none of
the present IPPs in the region would qualify to be Members of SRPC. There were a
number of issues like RGMO, PSS etc., where their contribution was essential.
3.2.3 MD, CEPL stated that it was very much necessary that IPPs more than 1,000 MW are
members to RPC. 1,000 MW capacity was a significant quantum and moreover
coordination with various power utilities was required. Hence, present provision of
1,000 MW could be continued.
3.2.4 Director & CEO (Trading), JSWEL said that they have been in Southern Region since
quite some time and serving power requirements of deficit states. They would like to
continue to be part of the esteemed SRPC forum and contribute their best to the sector.
SR was different from WR where many stations of more than 2,000 MW had come up.
Eligibility for membership may need to be different for different regions.
3.2.5 Director, CEA informed that the issue of membership of traders & IPPs to RPCs had
been discussed in the NPC. CEA had collected the inputs from RPCs and furnished their
recommendations to MoP. They had recommended that there would be one trader to
each RPC (being nominated by CEA in rotation) as per MoP Resolution. Any trader
engaged in foreign power trade and declared as Nodal Agency would be the member of
that particular RPC. Regarding IPPs, it was noted that most of the issues were technical
in nature like RGMO etc. Hence, IPPs could be invited to TCCs and various other sub
committees as per requirement. For RPC membership, 2,000 MW could be eligibility
criteria. Regarding Transmission Licensee, there were more than 16 licensees and it
may thus not be feasible to make them Members to RPCs. CEA representative
suggested that other Transmission Licensees could be invited to TCC and other
subcommittee meetings as per requirement.
3.2.6 SRPC concluded that the present eligibility of 1,000 MW as stipulated in the MoP
Resolution could be continued for Southern Region.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 8 of 107
3.3 Request of Adani Transmission Limited for inclusion as a Member in SRPC
3.3.1 Adani Transmission Limited vide their letter dated 05th
July 2016 (Annexure-III) had
informed that they are one of the largest transmission company operating in the private
sector in India and own, operate and maintain more than 5,000 ckms of Transmission lines
ranging from 400 kV to 765 kV. Additional projects of 2,000 ckms spanning across states
have been awarded to them through TBCB process. Highlighting the need of private
players in transmission planning /TBCB, ATL had requested to be a included as a Member
in SRPC.
SRPC deliberations
3.3.2 After deliberations, SRPC concluded that eligibility of Transmission License to be a
Member could be as per the prevalent MoP Resolution.
3.4 Membership of IL&FS, HNPCL and LKPPL to SRPC
3.4.1 IL&FS, HNPCL and LKPPL (letter dated 24.08.2016 Annexure-IV) are fulfilling the
eligibility for Membership to SRPC.
SRPC deliberations
3.4.2 SRPC agreed for membership of IL&FS, HNPCL and LKPPL to SRPC, in line with the
provisions of MoP Resolution.
4. FLEXIBILITY IN UTILIZATION OF DOMESTIC COAL FOR REDUCING COST
OF POWER GENERATION
4.1 MoP vide letter dated 10.06.2016 (Annexure-V) had informed that on 4th
May 2016
Cabinet had approved proposal of Ministry of Power for flexibility in utilization of domestic
coal for reducing cost of power generation. Presently, share of generation from coal based
power plants was about 78 % of the total generation in the country. These coal based power
plants are supplied coal against the plant specific Fuel Supply Agreement (FSA). There are
some power plants which generate cheaper power than others. There was scope for
utilization of coal in such power plants to achieve overall reduction in cost of generation.
4.2 In this regard, following mechanism for allowing flexibility in utilization of domestic coal
amongst power generating stations to reduce the cost of power generation had been
approved:
All long term coal linkages of individual Thermal Power stations of specific State (State
would include Union Territories) to be assigned to respective State or State notified
agency. Similarly, all long term coal linkages of individual General Generating Stations
shall be assigned to the company owning the Central Generating Stations (CGSs), instead
of individual Thermal Power stations to enable efficient coal utilization amongst end use
power generating stations.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 9 of 107
Annual Contracted Quantity (ACQ) of each individual coal linkages (as per respective
Fuel Supply Agreements) to be aggregated as consolidated ACQ for each State or the
company owning the Central generating stations, as the case may be. A supplementary
agreement shall be signed for each State /Company owning the CGS for such
consolidated ACQ and the terms and conditions of supplementary agreement shall be
applicable on the aggregated ACQ of State or Central generating stations.
There shall be flexibility in use of such coal amongst the generating stations of state
owned utilities, plans of other state power utilities, company owning the Central
Generating stations and IPPs, amongst each others as per methodology issued by CEA.
Mechanism shall initially be rolled out for Central Generating Companies and State
Power Utilities. Ministry of Power shall separately notify the methodology for use of
transferred coal in IPPs generating stations.
Methodology for flexibility in utilization of domestic coal for reducing the cost of power
generation prepared in consultation with all the Stakeholders had been issued by CEA
and also available on the CEA website.
TCC deliberations
TANGEDCO had stated as per computations, in Case-1 (use of coal aggregated with the
state in its own State GS), the cost is reducing. Ib valley coal (2,000 kM) linked to Mettur
could be utilized in North Chennai St-II. Presently computations for Case-2 (use of coal
aggregated with one state in GS to other state’s utilities) would be difficult to assess.
Case-3 (use of coal aggregated with state in CGS and vice versa) could also be utilized
by TANGEDCO as in some earlier cases NTECL & NTPL were requiring coal.
APGENCO has pointed out whether GCV, specific oil consumption, transit loss,
transportation cost, grade slippages, heat rate MoEF norms etc are to be factored in the
computations.
TSGENCO had stated that the main issues with coal were logistics. Transferring coal
from station to station within the state, state generators to other state generators/CGS etc
would further make the transportation matrix complex. During rainy season, difficulty of
transportation further aggravated.
CEA had informed that certain apprehensions were envisaged during the formulation of
this methodology. The methodology could be utilized only if there are some financial
benefits. Sample computations were carried out in consultation with NTPC; and the
estimated benefit for NTPC for one year was around Rs 760-900 Crores on internal
optimization only. Sample computations for Koradi (MAHAGENCO) had also shown
substantial saving. The three Ministries i.e Power, Coal and Railways had come together
for implementation of the scheme. Sample computations could be put in public domain
and financial/economic advantages of the methodology established to Authority or
Regulator, before implementation. Earlier objective was to ‘supply power’ which had
been modified to ‘supply cheap power’. Whatever help required from CEA, MoP and
other Ministries would be provided to the agencies willing to come forward. Regarding
third party sampling, it was informed that grade slippages would come down. There
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 10 of 107
would be no rebooking charges by the Railways during diversion of coal under this
scheme. Issues relating to coal quality could be taken up with Fuel Management Division
of CEA.
TCC had suggested that states/generators could approach CEA/CERC/SERC in line with
the methodology with sample computations to utilize the scheme for reducing cost of
power.
SRPC deliberations
4.3 Director, CEA stated that there had been some apprehensions while formulating the scheme
about its usefulness. However, sample calculation for coal transfer from Koradi
(MAHAGENCO) to NTPC station had shown significant savings of around 39 paise/unit in
variable cost. Ministry of Coal and Ministry of Railways had also extended support and
cooperation to the scheme to minimize the cost. In case coal optimization is carried out
within NTPC stations, there could be substantial savings as per computations. Case 2 & 3
could be utilized which would a learning experience and subsequently Case 4 could be
initiated in a transparent manner.
4.4 ED (C), NTPC clarified that the scheme had been implemented for intra-state GENCO
stations and between NTPC and GENCO stations also. After experience, MoP may open the
scheme for IPPs. The whole essence of the scheme was to minimize the cost of power.
Within NTPC, coal could be transferred within various stations, maximizing generation at
pit head stations while non pit head stations could possibly be run on partial loading, for
maintaining spinning reserve and taken for reserve shut down as per system requirement.
4.5 After deliberations, SRPC suggested that states/generators may approach
CEA/CERC/SERC in line with the methodology with sample computations to utilize the
scheme for reducing cost of power.
5. TERMS OF REFERENCE FOR RENEWABLE INTEGRATION – TASK FORCE
5.1 In the 29th
Meeting of SRPC, several issues had been highlighted in respect of renewable
integration since there was huge paradigm shift due to large volumes of renewable were
planned to be integrated into the grid. Impact of renewable integration on system operation,
balancing, infirm nature etc., was not fully known. Broader issues would be needed to be
studied in greater depth. In Europe, when renewable integration took place, they had tried to
use pan European grid like hydro reserves of Scandinavian countries to balance solar and
wind variability. So there would be a need to look into balancing power from hydro, gas
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 11 of 107
etc. with Southern Region perspective. Backing down of renewables could not be a good
option. Grid operational, commercial and strategic issues would be required to be
addressed. The manner in which renewables are getting integrated, all States could get
affected.
5.2 It had been agreed that a Task Force at TCC level could flag issues and come out with Term
of Reference and possibly get it examined through a Consultant.
5.3 This issue had been deliberated in the Special Meeting of TCC held on 2nd August 2016.
TCC deliberations
TCC recommended TOR for renewable integration as finalized in the Special TCC
meeting held on 02nd
August 2016 for approval of SRPC.
SRPC deliberations
5.4 Chairperson, SRPC stated that the issue of renewal integration was common to all and could
be taken forward. There needs to be some relaxation in respect of frequency and deviation
for renewable rich states. Even N-1 criteria needs to be relaxed for transfer of renewable
power. These are principles which need to be deliberated at the National level.
5.5 MD, KPTCL informed that they had tendered recently and were on the verge of entrusting
the task. None of the states in SR could be in surplus except Tamil Nadu (manage the load
by itself) in the near future. A study at regional / national level would be useful and KPTCL
would support any such initiative.
5.6 CMD, KSEBL said that they would support the study which could be taken up. Like in
Scandinavian countries, where hydro reserves were utilized for renewable integration, hydro
reserves in Kerala could be used for banking purposes etc.
5.7 Director (HR & GO), TSTRANSCO stated that they also support the proposal.
5.8 SRPC agreed to form a Working Group of Members from each of the states, SRLDC and
SRPC Secretariat to take forward the TOR by engaging a Consultant. Constituent states of
SRPC agreed to share the financial commitment equally. It was also agreed that approvals
etc in this regard would be sought from Chairperson, SRPC by MS, SRPC. Details would
be put up to SRPC in the next Meeting for kind information.
6. DETERMINATION OF TRANFER PRICE OF LIGNITE IN RESPECT OF NLC
MINES FOR THE PERIOD 2014-19 – REQUEST FOR MODIFICATIONS IN THE
NOTIFICATION OF MOC
6.1 CMD, TANGEDCO vide letter dated 16th
June 2016 (Annexure-VI) addressed to
Secretary, MoC had requested for modification of Notification on ‘Guidelines for fixation of
transfer price of lignite’ notified by MoC vide Order No. 228012/1/2014-CA-II dated
02.01.2015 keeping in view issues highlighted in the letter. Notification included three items
viz, 1. Removal of over burden charges, 2. Inclusion of 15 days lignite inventory under
working capital and 3. Shifting from Net Block to Gross block for the tariff period 2014-19.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 12 of 107
The issues in respect of these had been brought to attention. It had been requested to
consider the same as presently the cost of lignite is more than cost of coal (at mine head and
also at the powerhouse end) even though its calorific value is comparatively less than coal.
This increases the cost of energy from Neyveli stations. Cost thus arrived is prohibitive and
does not come under merit order dispatch.
TCC deliberations
MS, SRPC had stated that as can be kindly seen from TANGEDCO’s letter, the present
cost of lignite is more than cost of coal. With its calorific value being lesser, the merit
order for NLC lignite stations could go down further.
NLC had stated that this being a tariff related issue, needs to be resolved only at
Ministry of Coal. Guidelines for fixing lignite price were framed taking into
consideration, views of the beneficiaries and the concerns / justification of NLC. NLC
was studying the issues raised by TANGEDCO.
TANTRANSCO had expressed concern that they had worked out the rates which was
coming more than Rs.5/unit. The issue cannot be taken up with Hon’ble CERC also.
Under such circumstances, backing down may have to be resorted to.
SRPC deliberations
6.2 CMD, TANGEDCO informed that this issue had also been deliberated with Chairman,
NLC. With increased variable cost, the scheduled power of NLC may get reduced and it
was thus for NLC to take a call.
6.3 Director (P), NLC stated that they were also concerned with the increase in ECR. For
purpose of merit order dispatch, it was in the interest of NLC to cut down costs. NLC was
taking steps to cut down the cost and concern of TANGEDCO and beneficiaries would be
taken care. The letter of CMD, TANGEDCO was under review in MoC.
7. PREPARATION FOR MEETING REVISED ENVIRONMENT NORMS AS PER
ENVIRONMENT (PROTECTION) AMEN DMENT RULES, 2015
7.1 In the 29th
Meeting of SRPC, it had been noted that CEA had requested to furnish details of
preparedness and action plan in order to comply with revised water consumption and
emission norms by existing as well as new thermal units (to be installed from 01.01.2017
onwards) as per Environment (Protection) Amendment Rules, 2015 notified by Ministry of
Environment, Forest & Climate Change (MOEF & CC) (Gazette Notification dated
07.12.2015). SRPC vide letter dated 20.01.2016 had communicated the same to the
concerned utilities. MOEF guidelines had classified thermal generators into three categories
with different norms. The three classes were prior to 31st December 2003, 1
st Jan 2004 to
31st December 2016 and beyond 1
st January 2017. Existing as well as new plants were
required to meet the standards by the stipulated time lines. SLDCs had been requested to
kindly take up the matter with thermal power plants in their state. Information in this regard
was kindly to be arranged to be furnished to CEA with a copy to SRPC.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 13 of 107
7.2 In the Sub Committee Meetings, the following had been noted:
Neyveli TS I, TS II, CEPL, KSEBL, TPCIL and NCTPS St-II had submitted the
information.
APTRANSCO had informed that APGENCO had submitted the details to their
management and details would be furnished.
NTPC had informed that they had submitted the details to their Corporate and the same
would be furnished to CEA for all NTPC stations.
NTECL, Vallur had informed that draft had been submitted to Corporate and they would
furnish the information.
TSTRANSCO had informed that TSGENCO was studying the issue internally.
NLC TS I Exp & KPCL had informed that they would furnish the information.
TCC deliberations
NTPC had informed that the details for all NTPC stations had been submitted to CEA
and a follow up meeting had also taken place. There were some constraints like space
availability in old NTPC stations. There was no proven technology for NOX control
and such concerns had been taken up with CEA. The time period of two years to
comply with norms was also difficult so they had sought for extension of time.
NTECL had informed that they had submitted the details to Corporate (NTPC
Engineering).
TSGENCO had stated that as per new norms for environment, there may not be any
necessity to implement modifications for stations which are to be closed within next 3-
5 years. For stations recently commissioned and also stations which are under
construction, this is a major concern. As such, NOX control (less than 100 pp) would
be quite difficult. SPM could be controlled by adding more fields, if space is available
while SOX could be controlled through FGD (Flue Gas Desulphurization). They were
looking forward to NTPC for similar implementation in TSGENCO stations.
Commercial implications were also to be factored since there could be additional cost
of about Rs 1 Crore /MW which would ultimately (80 p/unit) be passed on to
consumers. The total cost implication for the country could be around Rs 1.5 lakh
crores in coming 2-3 years.
CEA had stated that technical difficulties could be highlighted to CEA. To seek any
relaxation etc, support and necessary technical justification from Generators was very
much required.
NLC had informed that they were taking action regarding water and were approaching
Consultant in respect of SOX and NOX.
After deliberations, it was noted that action plan and the constraints needs to be
communicated to CEA at the earliest.
SRPC deliberations
7.3 ED (C), NTPC stated that the major parameters to be controlled were SOX and NOX and
SPM. Estimated expense to meet the revised norms was around Rs 1 crore/MW which may
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 14 of 107
get translated to about Rs 47,000 crores and rise of per unit cost by 40 paise. Lot of
modifications would need to be carried out on existing units and could have subsequent
impact on operational issues. NTPC had raised these issues and concern with MoEF and
were in discussion to address the cost issues also.
7.4 APGENCO pointed out the space constraints for older units. Even M/s BHEL had been
citing these limitations to take up the works. For new plants, the space requirements were
being taken care appropriately.
7.5 Chairperson, SRPC & CMD, TANGEDCO observed that the investments would only get
passed through to the end consumers. Huge investment (Rs 17,000 crores for TANGEDCO)
would need to be made in the next 2-3 years which was a major challenge. However
considering the practicality involved, some concession could be sought on the time lines
for complying with the norms. He informed that they had already taken up this issue and
suggested other State Governments/GENCOs may also take up the concerns appropriately.
8. ROADMAP TO OPERATIONALISE RESERVES IN THE COUNTRY
8.1 In the 29th
Meeting of SRPC it was noted that Hon’ble CERC vide Order dated 13.10.2015
on Petition No. 11/SM/2015 in the matter of Roadmap to operationalize Reserves in the
country had directed as follows:
(b) The Commission reiterates the need for mandating Primary Reserves as well as
Automatic Generation Control (AGC) for enabling Secondary Reserves.
(i) All generating stations that are regional entities must plan to operationalise AGC along
with reliable telemetry and communication by 1st April, 2017. This would entail a one-
time expense for the generators to install requisite software and firmware, which could
be compensated for. Communication infrastructure must be planned by the CTU and
developed in parallel, in a cost-effective manner.
(ii) On the other hand, National/Regional/State Load Dispatch Centres
(NLDC/RLDCs/SLDCs) would need technical upgrades as well as operational
procedures to be able to send automated signals to these generators. NLDC /RLDCs
and SLDCs should plan to be ready with requisite software and procedures by the same
date.
(iii) The Central Commission advises the State Commissions to issue orders for intra-state
generators in line with this timeline as AGC is essential for reliable operation of India’s
large inter-connected grid.
(c) To start with, a regulated framework in line with the Ancillary Services Regulations
would need be evolved for identification and utilizing of spinning reserves and
implemented with effect from 1st April, 2016. This framework may continue till 31
st
March, 2017.
……………
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 15 of 107
(d) In the long term, however, a market based framework is required for efficient provision
of secondary reserves from all generators across the country. For this, NLDC/POSOCO
is directed to commission a detailed study through a consultant and suggest a proposal
to the Commission for implementation by 1st April, 2017, giving due consideration to
the experience gained in the implementation of Spinning Reserves w.e.f. 1st April, 2016.
8.2 In the earlier Meeting the following had been noted:
NLDC had informed that they had conducted regional level workshop to create
awareness on the implementing process. AGC issues were being looked into by the
Expert Committee of Members. Concept paper on operationalization of reserves has
been submitted to Hon’ble Commission. Issue regarding implementation of reserves
from 1st April 2016 was discussed and it was noted that each RLDC would compute the
ACE at the regional level which would be displayed on the website. Regional entity
generators would be required to take appropriate action. They had sought some more
time from Hon’ble CERC for operationalizing the reserves since many other issues such
as telemetry etc., were to be addressed. NTPC was responding positively and the
process of transmitting signals to the station as a pilot project was being contemplated in
each region. Changes in generators side controls were required and NTPC was taking a
lead in it.
SRPC had noted that sensitization and more interaction with SR utilities was required
and NLDC/SRLDC were requested for needful action in this regard.
TCC deliberations
MS, SRPC had stated that in the long term, a market based frame work was to be in place.
Ancillary Services had been implemented from 12.04.2016 with manual control. SRLDC
had addressed a letter dt.5.7.2016 informing that Secondary Control (AGC) through Pilot
Project has been planned which could be scaled to All India level. Also, Area Control
Error (ACE) was to be computed and displayed in RLDC’s website.
SRLDC had informed that a Pilot Project had been taken up through M/s Siemens and
NTPC. Action was being taken for the detailed report of NLDC through Consultant and
in a couple of months, the report would be submitted. Feedback on Ancillary services had
been given to Hon’ble CERC. ACE would soon be posted on website for the benefit of all
entities. POSOCO would also be conducting a workshop on AGC issues.
After deliberations, it was noted that NLDC/SRLDC would conduct workshops as part of
capacity building exercise and also display ACE on its website.
8.3 SRPC noted the above.
9. COMPLIANCE OF ORDER OF HON’BLE CERC IN PETITION NO. 420/MP/2014
– IN RESPECT OF LVRT AND OTHER PROVISIONS OF CEA/CERC
REGULATIONS
9.1 Three Meetings have been held so far for compliance of Hon’ble CERC’s Order in Petition
No.420/MP/2014 in respect of LVRT and other provisions of CEA/CERC Regulations. No
tangible progress is observed though Hon’ble Commission has specified time lines for a
number of actionable points for various entities.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 16 of 107
Following issues merit kind attention for ensuring action for compliance:
Submission of data as per Format A & B annexed with MoM of 1st Meeting (held on
05.02.2016).
Nomination of Nodal Officer from APSLDC was pending. Ensuring participation of
Nodal Officers in Special Meetings.
STU/SLDC (except TSSLDC) to call for a meeting with Wind Developers.
STU/SLDC to ensure strict compliance of CEA’s Connectivity Regulations for all WTGs
commissioned after 15.04.2014.
STU/SLDC to ensure strict compliance of LVRT feature for all Solar Generators
connected above 11 kV (whose NIT was not issued by 05.01.2016).
SLDCs to prepare quarterly reports and submit to SRPC with regard to monitoring of
installation and performance of LVRT installed on existing WTGs.
STUs to study line loading in their systems to ensure N-1 compliance and submit reports
in this regard to CEA by 10.3.2016.
STU/SLDCs would communicate to the Wind Developers for setting the characteristics
of LVRT feature (and other provisions of CEA Regulations) as envisaged in CEA
Connectivity Regulations within end of July 2016. Wind Developers needed to certify
the same by end of August 2016. Status on this need to be covered in the quarterly
reports.
PMU may be required at Wind pooling stations and Wind Developers/STU/DISCOMs
could take pro-active steps in this regard.
STU/SLDC to approach respective SERC’s for the following:
To make suitable provisions in their relevant regulations or through orders to provide
for mandatory installation of LVRT in WTGs which fall within their jurisdiction.
To make suitable provisions in their regulations and through orders to ensure that
solar/wind generators provide real time data to SLDCs as per the provisions of Grid
Code. SLDCs to ensure availability of data in respect of real time data from their Data
Acquisition Systems of solar/wind generators in SCADA systems to respective RLDCs
as per the provisions of the Grid Code.
To issue appropriate regulations/orders to align with the provisions of the Grid Code in
respect of forecasting and scheduling for intra-State solar/wind generators and demand
estimation by SLDCs.
CTU and STUs to make provisions in this regard in their Connection Agreements to
ensure that wind energy generators comply with the provisions of CEA Technical
Standards for Connectivity Regulations for grid connectivity before granting
connectivity to the grid.
9.2 SRLDC vide letter dated 15.07.2016 (Annexure-VII) had taken up with CEA in this
regard.
9.3 The issue had been deliberated in the Special TCC Meeting held on 02.08.2016.
9.4 The following was discussed and noted in the TCC:
All states had identified and communicated details of Nodal Officers.
APTRANSCO had informed that they had conducted a Meeting with Renewable
Developers and formats had been given to them to be filled up appropriately. Recently,
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 17 of 107
on 24.08.2016, requirement of data (as per format), LVRT, forecasting, scheduling etc
had been taken up. A Follow up Meeting was also planned on 07.09.2016.
KPTCL had informed that they had conducted a Meeting on 17.08.2016 and generators
had been advised to furnish details by month end. SRLDC pointed out that CEA
Connectivity Regulations were to be ensured from 15.04.2014 (KPTCL had informed
that they were ensuring the same from April 2015).
APTRANSCO, KPTCL & KSEBL had agreed to furnish data in the requisite format by
10th
September 2016.
Quarterly reports for two quarters (Jan-March 2016 & April-June 2016) would be
furnished by 15.09.2016.
TN would conduct the meeting with WTGs by next week.
KPTCL had expressed concern that for Solar, it has been observed that large amount of
MVAR (8 to 10%) is being drawn from the grid. It suggested that automatic reactive
compensation of around 10 % for solar generators should also be made part of
regulations.
SRLDC had stated that N-1 was very necessary for RE generators and STUs should
make RE generator’s system N-1 compliant. APTRANSCO stated that as per CEA’s
Transmission Planning Criteria, N-1 was not envisaged for complete Wind and Solar
evacuation. The interest of STU should not be compromised for RE developers. It was
clarified that in accordance with Transmission Planning Criteria, N-1 may not be applied
to immediate connectivity of wind/solar farms with ISTS/Intra-state grid i.e. the line
connecting the farm to the grid and step-up transformers at the grid station.
States were requested to study N-1 compliance in their system and submit details to CEA
within a period of 3 months.
Recommendations finalized in the Special Meeting on LVRT were noted for necessary
compliance of CERC Order. All turbines/units commissioned and being commissioned
after 15.04.2014 needed to comply with CEA Connectivity Regulations. All WTGs
equipped with LVRT should be directed to implement the settings in line with CEA
Connectivity Regulations.
SRLDC had informed that in recent interactions with Wind Developers, they were
voluntarily coming forward for MVAR injection also. Some of the WTGs were tripping
in Coimbatore area when the voltage was going below 89 kV (rated voltage of 110 kV) .
It was ambiguous whether the generation was backed down or the WTGs had withdrawn
and it was thus in the interest of the WTGs to go for LVRT.
KPTCL had raised certain issues on low voltage conditions with respect to WTGs and
the requirement for LVRT. It was clarified that LVRT was required during fault
conditions in nearby locations and not during steady state voltage conditions being
referred by KPTCL.
TANTRANSCO had informed that they had not faced WTGs withdrawal cases this year.
This may be due to VAR injection by new machines in Udumalpet and Coimbatore areas.
During one incident last week during bus fault at Tudaliyur (Udumalpet area), around
450 MW of Wind had withdrawn and had come back within five minutes. SRPC pointed
out that it appeared that LVRT was not set as per CEA characteristics and the WTGs had
withdrawn in this case.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 18 of 107
On a query from TSTRANSCO about accepting the Manufacturer’s Certificate for LVRT
(without field testing provision) compliance, it was clarified that TSTRANSCO/other
constituents could kindly refer the MoM of Special Meetings on LVRT available on
SRPC website for necessary compliance.
TSTRANSCO had informed that they had developed their own document with regard to
Wind and Solar Integration which includes substation automation, protection, LVRT,
CEA Regulations Provisions etc for smoother RE integration. TSTRANSCO requested
CEA to cover PMU installation at Pooling Stations, in the draft amendment.
CEA had informed that draft amendment to Connectivity Regulations would be made
available shortly on its website for comments. Most of the concern expressed by the
constituents had been covered in the draft amendment.
SRLDC had suggested that reference to voltage levels could be removed in the draft
amendment. Regulations could be framed for grid connected generators and for
standalone generator as it was leading to ambiguity in interpretation.
9.5 SRPC noted the above.
10. LOW VOLTAGES
10.1 A Special Meeting on low voltages was held on 18th
April 2016 at SRPC, Bengaluru
(minutes available at SRPC website). After deliberations, the following had been
recommended:
KSEBL/TANTRANSCO/KPTCL to implement UVR scheme and settings to be in
place as recommended by 2nd
May 2016 at the following locations/nodes and furnish
compliance report. In case not implemented by 2nd
May 2016, non-compliance
messages would be issued by SRLDC.
Kerala: Trichur, Palakkad & Kochi
Tamil Nadu: Udumalpet, Salem & Hosur
Karnataka: Nelamangala, Somanahalli, Hoody and Bidadi
UVRs should not be bypassed or kept out of service. IEGC clause 5.2 (t) was referred
‘All Users, CTU and STUs shall provide adequate voltage control measures through
voltage relay as finalized by RPC, to prevent voltage collapse and shall ensure its
effective application to prevent voltage collapse/ cascade tripping…’
Physical Regulatory Procedure as enumerated in the minutes was agreed for
implementation. Step 4 was a critical step and thus SLDCs needed to take action to
avoid any situation which would compel SRLDC to take such step.
In case Specific instructions for opening 220/230 kV and below lines were not adhered
by SLDCs it would be deemed as violation of provisions of IEGC/EA 2003.
SLDCs to take action proactively by observing falling trend/pattern of voltages even
before receipt of SRLDC messages. SLDCs to also furnish the physical regulatory
measures to be taken up at low voltage nodes in their system. It was felt that physical
regulatory measures at 220 kV and below would give optimum results than physical
regulatory measures by SRLDC.
SRLDC real time messages/instructions to be adhered within 15 minutes of issuance
and the action taken report should be furnished within 30 minutes.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 19 of 107
As a drive, faulty capacitor banks to be rectified immediately.
Chairperson, SRPC would be kindly requested to take up the issue with the concerned
since it was threat to system integrity.
Constituents were requested to revert back on utilization (operational/commercial
limitations & possibilities) of reactive support from wind/solar units even when they
are not generating.
States to furnish data of load management actions taken to overcome low voltage
conditions.
10.2 SRLDC had also presented the Study (SR snapshot of 0915 Hrs on 15th April, 2016) to
ascertain requirement of capacitive compensation in low voltage areas of SR. In the study,
the capacitors were lumped at 220/230kV Station on 110/66 kV side and Capacitor
requirement had been arrived as below:
Additional 15 % more capacitor compensation needs to be added to compensate for
outages/maintenance of capacitor banks and considering the future growth.
All states were requested to install the capacitors as suggested before December 2016 i.e.
before next high demand period for SR. Since time was limited, immediate action was
required to be taken.
10.3 Chairperson, SRPC vide letter dated 28.04.2016 (Annexure-VIII) had taken up the issue
with States for necessary action.
10.4 A Special Meeting was conducted on 17th
June 2016 (MOM available at SRPC website)
with respect to pending KPTCL issues. The following recommendations had been finalized
in that Meeting:
Retrofitting of Somanahalli and Hoody Capacitor Bank of 30 MVAR each to be
expedited. KPTCL to furnish the action plan within 2 weeks.
Faulty Capacitor Banks to be rectified in Bengaluru adjoining areas of KPTCL system.
KPTCL to furnish the details of faulty capacitor banks and action plan for rectification
within 2 weeks.
Sub-Station
Capacitor –
Requirement
in
MVAR
Constituent wise
requirement
Nelamangala 160 Karnataka-505 MVAR
Hoody 185
Somanahalli 160
Mywadi 275 Tamil Nadu – 1025
MVAR Arasur 330
Salem 210
Hosur 210
Palakkad 12 Kerala – 102 MVAR
Trichur 90
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 20 of 107
KPTCL / SLDC would call for a meeting with BESCOM with participation at
appropriate level within 2 weeks and following issues would be taken up:
Special drive on rectifying the faulty capacitors in BESCOM in a time bound manner
with the details of status of capacitor banks.
Tap optimization in the distribution transformers of BESCOM (to reduce drawal of
VAR)
Study of additional capacitor requirements. This needs to be taken up by BESCOM on
urgent basis.
Discom wise or location wise limitation on MW drawal due to low voltages and high
MVAR drawal.
Extending scope of maintaining power factor by other consumers (presently being
limited to HT Consumers).
BESCOM to identify feeders for Physical Regulatory Procedure based on MVAR
drawal by the respective feeders
Senior Managements of KPTCL and BESCOM to be appraised that MW drawal
capacity had reached saturation and could be curtailed unless voltage profile is
improved and also if sub--transmission system is not strengthened on war footing basis.
Future increase in loads and even share from Yeramarus, Bellary, LTA etc., would be
difficult to meet keeping in view the voltage profile.
SLDC could envisage taking up the issue with Hon’ble KERC to ensure that BESCOM
takes appropriate steps to improve voltage profile.
A Task Force could be set up on urgent basis to identifying the issues (Low voltages,
high MVAR drawal, strengthening of transmission & distribution system, drawal
capability of Bengaluru area , reactive requirement at DISCOMs etc) and to finalize the
action plan to resolve these issues in a time bound manner.
10.5 In the OCC/Special Meetings, the following had been noted:
UVR had been implemented at Udumalpet (TN), Palakkad, Trichur & Kochi (KER).
Udumalpet - Palakkad SPS had been implemented by KSEBL on 22.06.2016.
TCC deliberations
KSEBL had informed that two stages of UVR had been implemented at Trichur,
Palakkad and Kochi.
TANTRANSCO had informed that two stages had been implemented at Udumalpet. It
was also informed that voltage at Arasur had improved due to commissioning of
Karaimadai SS. New stations at Palvadi and Kanchipuram were expected to be
commissioned shortly and therefore the need for UVR at Hosur and Salem could be
reassessed. It was clarified that requirements for Karnataka, Kerala and Tamil Nadu had
been firmed up based on studies by SRLDC. Chairperson SRPC had also taken up this
issue with other Chairpersons/MDs. TANTRANSCO agreed to implement UVRs at
Salem and Hosur within 2 months.
SRLDC/SRPC had expressed concern that UVR in Karnataka system was not being
implemented despite repeated follow ups. KPTCL had informed that feeders list for UVR
had been furnished to BESCOM for approval. The scheme would be implemented at
Somanahally, Nelamangala, Hoody and Bidadi.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 21 of 107
TANTRANSCO had informed that in respect of 206 MVAR capacitors at 11kV level in
Coimbatore area, administrative approval had been received and tendering activities were
being undertaken. In respect of other areas, study with regard to SRLDC recommended
quantum of 1,025 MVAR would be completed in a months’ time.
MS, SRPC had stated that KPTCL and BESCOM management may be kindly apprised of
the saturation in drawal due to low voltage issues as discussed in the Special Meeting.
KPTCL informed that they had taken up issues regarding capacitor installation, tap
optimization, extra penalty on PF etc with BESCOM. A Meeting with BESCOM would
also be held shortly.
SRPC deliberations
10.6 SRPC noted the above and suggested for necessary action by the respective entities.
10.7 MD, KPTCL said that UVR scheme cannot be implemented by 09.09.2016 and around 3
months additional time would be required. He added that it would be ensured before
November 2016.
11. PATROLLING / MAINTENANCE OF CRITICAL LINES AND SUBSTATIONS
11.1 In recent times insulator tracking has been observed in Transmission lines and Substations
located in the coastal and polluted areas and SRPC vide letter dated 05th
May 2016
(Annexure-IX) had communicated to the concerned in this regard. Transmission Lines and
Substations in the most vulnerable terrain, coastal and polluted areas were to be categorized
for monitoring to ensure that Patrolling and Maintenance is being carried out as per
Patrolling guidelines. Format for furnishing details of schedule / Patrolling and Maintenance
carried out of the critical Transmission lines and Substations had been enclosed. MEPL,
SEPL, NTPC Simhadri, APTRANSCO & KSEBL had furnished the details.
TCC deliberations
MS, SRPC had pointed out that the issue was very critical and concerted action was
required.
APTRANSCO had stated that the guidelines were being followed. They had carried out
silicon coating at Kalpakka S/S. Silicon coating works at VSS and insulator replacement
works were also being undertaken.
TCC had noted that concerned entities need to kindly take necessary steps to ensure that
Patrolling and Maintenance is carried out regularly as per the Patrolling Guidelines.
SRPC deliberations
11.2 MS, SRPC highlighted the need for adhering to Patrolling Guidelines specifically for critical
elements/sub-stations whose details had already been communicated. This assumed
significance keeping in view Orders of Hon’ble CERC and also IEGC Provisions.
11.3 SRPC noted the TCC deliberations and suggested the concerned entities to initiate necessary
action.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 22 of 107
12. CONTINGENCY OF 400 kV NELLORE - NELLORE PS LINES
12.1 The contingency of 400 kV Nellore- Nellore PS is under deliberation in various forums.
12.2 The following had been noted in the 29th
Meeting of SRPC :
NLDC had stated that they were envisaging a separate bid area for NPS connected
Generators. They would inform Hon’ble CERC regarding formation of separate bid
area. Power Exchanges would also be apprised accordingly.
TPCIL had suggested that alternate means like re-conductoring (HTLS) for this short
line could be considered. Any other measure which could help enhance evacuation
from this complex also needed to be explored.
CTU had pointed out that NPS-Nellore line included PGCIL and MEPL/SEL sections
and there could be issues in changing the conductor to HTLS for the entire line. There
could be equipment rating issues in the bay also. Since in the long term, the
interconnector was planned to be kept open, changing to HTLS did not appear to be an
economically viable solution. With bid area there could possibly be higher
curtailment, hence till other identified system came up, SPS (generation backing
down) based higher evacuation could be considered as an option.
SRPC had noted that already more than 2,000 MW of generation was available at NPS
and the first unit of NCC was also expected by May 2016. Any tripping of these lines
with generation loss would have adverse impact on the already loaded critical
inter/intra regional sections. STOA applications thus need to be judiciously processed
keeping in view the line flows.
TCC noted that NCC Unit I was scheduled to be commissioned by May 2016 and thus
process of formation of separate bid area needs to be completed at the earliest.
CTU stated that they would also examine other options like shifting of one or two
lines etc. for enabling higher evacuation from the complex.
12.3 In the OCC Meetings, SRLDC had informed that NLDC had called a Meeting with the
Power Exchanges in this regard. SRLDC had stated that they would carry out mock
computations to identify the export limits from the complex.
12.4 Subsequently SGPL (formerly NCC) vide letter dated 23.06.2016 (Annexure-X)
addressed to CEA had taken up the issue regarding evacuation from Nellore complex.
12.5 The following was deliberated in the TCC Meeting:
MS, SRPC had informed that a Meeting on this issue had been conducted at CEA on
05.08.2016, and the minutes were awaited. Another meeting was also held at CEA on
02.08.2016 (CEA MoM dated 05.08.2016 at Annexure-XI) on temporary
reconfiguration at Bidadi which has been implemented.
CTU had informed that there were basically two issues - high loading of Nellore- NPS
and high voltage at Nellore. In the 34th
SCPSPSR it had been noted that the
interconnector was to be opened to control short circuit levels. With temporary
reconfiguration of Tumkur-Bidadi, around 550 MW of power was flowing on Gooty-
Tumkur lines. In case required, the interconnector could be closed during critical
conditions. The system would be N-1 compliant to evacuate power from the complex. If
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 23 of 107
the interconnector is opened, other lines get loaded and voltage profile at Nellore also
improves.
SRLDC had informed that the N-1 limit was around 1,700 MW (750 C conductor) for
Nellore- NPS lines. Complex generation would be around 4,140 MW and flow would be
more than 1,200 MW on each line which would violate N-1 criteria. CTU could therefore
consider (i) strengthening this short line or (ii) making the line through to Thiruvalam (by
bypassing the Nellore (PG) 400 KV) or (iii) connecting SEPL/MEPL to Nellore(PG)
through switching arrangement (by bypassing NPS 400 KV).
CTU had informed that were not envisaging any issues with regard to LTA/ MTOA in
the Complex. They would examine suggestions of SRLDC in this regard.
SRPC deliberations
12.6 ED, PGCIL stated that there was no N-1 violation envisaged. However, they would examine
proposal of SRLDC in this regard.
13. STATUS OF GENERATION IN GENERATING STATIONS
13.1 Issue regarding low generation in KKNPP, NLC TS-II Expansion, NTECL and NTPL had
been deliberated in the 29th
Meeting of SRPC. The following had been noted:
NPCIL had informed that full generation of 1,000 MW was expected by the end of
March 2016.
NTECL had informed that second grab unloader had been commissioned on
17.02.2016 and conveyer related issues have been resolved. CEA team had also visited
after the commissioning of second grab unloader and they were satisfied that there
were no unloading constraints. Against requirement of 4.5 rakes/day, they were
getting only 2.6 rakes per day till January 2016. From February, they were getting 3.5
rakes per day and with this the PLF had also increased. Coal was also planned to be
availed through the Dhamra port and the Railways has given approval for 25
rakes/month through Dhamra Port on 04th
March 2016.
NLC had informed that NLC TS II Expn units were first of its kind at this capacity.
Problems had been narrowed down but there were issues of falling of the refractory.
Experts had been called and specification of the refractory has been changed. Certain
modifications were being carried out and all the issues were expected to be resolved
within 3-4 months (by July 2016).
NTPL had informed that with assured domestic coal supply, blending issues would get
resolved. There were no coal issues and the PLF for the month of February was 81%
(Availability was around 86%). The generation would be increased to about 90 %.
They were getting 1 LT coal from MCL and balance was being imported.
TCC had observed that KKNPP and other units need to furnish realistic expected
generation level/revival dates enabling improved planning. KKNPP and NLC TS II
Expn were requested to improve their generation levels.
13.2 Level of generation of some ISG stations is given below:
Station Mar’ 16 Apr’16 May’16 June’16 July’ 16
KKNPP
U1, NPCIL
Generation
in MU
639.22 707.68 720.84 721.38 748.73
PLF 86% 98% 97% 100% 101%
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 24 of 107
13.3 The following was noted in the OCC Meetings:
NTECL had informed that pipe conveyor issue had been resolved during June 2016.
Supply of coal through Dhamra port had started. NTECL had requested SRPC to take
up the issue regarding coal supply. MS, SRPC vide letter dated 18.05.2016
(Annexure-XII) had taken up the issue with MCL.
Modification works on NLC TS II Expansion Unit I had been carried out.
TCC deliberations
It had been noted that the performance of NTECL units had improved.
NLC had informed that they had narrowed down the issues which were related to
refractory etc and had carried out necessary modifications. Unit-2 was generating
around 220-225 MW of power. Unit-1 would be lighted up in few days after
modification works. A PLF of about 80-85 % was anticipated.
SRPC deliberations
13.4 Director (P), NLC informed that they had achieved PLF of 49 % in TS II Expn during the
last month. All issues were getting resolved and PLF of around 75-80 % was anticipated
in the coming months.
14. REVIEW OF ULDC / SCADA/COMMUNICATION
14.1 In the earlier Meetings, the following had been noted:
Review of SCADA and Communication availability was being carried out in the
OCC/Special meetings.
Hon’ble Commission has issued Order dated 29th January 2016 in respect of Petition
No.7/SM/2014. The following direction merits attention please:
‘14. Under the Grid Code, it is the responsibility of all users, STUs and CTU to
provide systems to telemeter power system parameters in line with interface
requirements and other guideline made available by RLDC and associated
communication system to facilitate data flow up to appropriate data collection point
on CTUs system. Telemetry of on-line operational data is not only essential for
effective monitoring of grid but also forms key input for effective running of State
estimation and other EMS tools at RLDC and SLDCs, which are essential for reliable
and secure operation of the grid. In view of the critical importance of telemetry and
associated communication system for ensuring reliability in operation of the grid and
optimum utilization of the transmission system, there is an imperative need for all
users to establish the telemetry and associated communication system in time bound
NTECL,
Vallur
Generation
in MU
500.02 742.78 707.9 554.98 582.03
PLF 45% 69% 63% 51% 52%
NTPL,
Tuticorin
Generation
in MU
538.27 592.67 576.35 295.47 478.17
PLF 72% 82% 77% 41% 64%
NLC TS II
Exp
Generation
in MU
31.62 106.59 77.40 128.81 181.68
PLF 9% 30% 21% 36% 49%
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 25 of 107
manner so that the power system operation may be most reliable and optimum.
Moreover, in view of the requirement of communication system for a generating
station and sub-station, the planning should be done in advance by the generating
company and transmission licensee to ensure that necessary system are in place
before commissioning of generating station or sub-station to take care of the
communication requirements even at the time of injection of power infirm by a
generating station and sub-station during testing.
……………………………..
17. We further direct all the utilities/generating companies which have to still
establish telemeter power system parameters as per details given in para11 above to
provide data to RLDCs/SLDCs as per the provisions of the Grid Code and CEA Grid
Standards Regulations by 31.7.2016. If the utilities/generating companies do not
comply with our directions, it will be construed as non-compliance of the order of the
Commission and appropriate proceedings under Section 142 of the Electricity Act,
2003 shall be initiated against such utilities/generating companies. NLDC is directed
to submit user- wise latest status of telemetry, by 31.8.2016.
18. NLDC and respective RLDC are directed to up-date the status of telemetry every
month at their web-site and persistent non-availability of data from the generating
stations/sub-stations be taken up in RPC meetings for appropriate direction and
action.’
APTRANSCO had expressed concern over the differences between SCADA and SEM
values. There were huge operational and commercial implications and the issue had
been raised by AP continuously TSTRANSCO & TANGEDCO had also raised similar
apprehensions.
After deliberations, the following had been agreed in the earlier TCC:
Monthly meetings would be held to resolve the issues. Representatives from SLDC
and SCADA of each state would attend the Meeting along with participation from
PGCIL, SRPC Ssecretariat. SRLDC would coordinate the Meetings.
Other issues on SCADA/ULDC features would also be discussed during the
Meetings. The concerned OEMs may also be called as per requirements. States
were suggested to give their agenda points.
State-wise reconciliation would be continued.
AP report would also be reviewed keeping in view ISTS touch points and manual
entries
The following was noted in the earlier SRPC meeting:
CMD, APTRANSCO & Chairperson SRPC had expressed serious concern over the
long pending issue. It was noted that a crash action plan was highly essential.
SR-II, PGCIL had assured that communication issues would be sorted out.
Communication failure issues need to be communicated to PGCIL at the earliest in
real time.
It was agreed that PGCIL & SRLDC would nominate a Co-ordinating Officer at
senior level. Periodic monitoring/review would also be carried out during next 2-3
months. Mr. V.K. Khare, GM, SR-II and Mr. P. Ranga Rao, AGM, SR-I were
identified as Co-ordinating Officers from PGCIL to address the associated issues.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 26 of 107
14.2 SCADA/communication issues were deliberated in two Special Meetings held on
21.03.2016 & 17.05.2016 and also in OCC meetings. The following was noted in
OCC/Special meetings:
Steps needs to be taken on the taken on the actionable points finalized in the Special
/ OCC meetings.
SCADA/Communication issues addressing procedure was firmed up which needs to
be followed by all the entities. Details of Nodal officers for contacting in State /
PGCIL were also noted.
Redundant channel availability from Bhadravathi, Talcher etc., was to be made
through by PGCIL. New RTU was to be made available at Talcher by NTPC.
PGCIL to ensure availability of communication link across back up (main) control
centers of SLDCs to back up control centers of SRLDC (at NRLDC, New Delhi).
Data validation with respect to TSTRANSCO was carried out on 17.03.2016.
In respect of AP the following had been noted:
Many of the interstate lines between AP and Telangana were having RTU only on
one side. Urgent action to be taken by AP and Telangana to provide RTUs on the
other side also which can act as standby.
Considerable time drift was observed in some of the SEMs. These SEMs (> 10 min
drift) are to be replaced immediately. It is understood that OEMs had consented to
replace/rectify these SEMs on immediate basis.
It was clarified that as per CEA Metering Regulations, respective transmission
licensees would provide/replace/rectify SEMs on respective ends.
14.3 A reconciliation Meeting was convened by SRLDC with APTRANSCO on 03.03.2016 and
19.7.2016. Data validation for Puducherry, Karnataka, Kerala and TN was carried out on
20.04.2016, 28.04.2016, 28.04.2016 and 07.06.2016 respectively.
TCC deliberations
MS, SRPC had informed that there had been some perceptible improvement and PGCIL
needs to be complimented for attending the pending issues. On 23rd
August 2016, a
Meeting was held to discuss URTDSM, SCADA and Communication issues (MoM
available at SRPC website). SCADA vs SEM validation for all the states has been
carried out. For AP, the validation was carried out three times and recently again at
Hyderabad on 19.8.2016 (MoM at Annexure-XIII). Few remedial actions like
rectification/procurement of transducers/RTUs at some locations had to be carried out.
In the recent validation, it had been noted that there was significant improvement and
issues contributing to difference like data hanging etc., were discernibly identified.
SRLDC had informed that issues were progressively being resolved and many of the
pending points were under convergence/completion. Status as on 31.08.2016 was to be
furnished to Hon’ble Commission. Entities to complete/rectify pending field inputs and
furnish status updates to SRLDC.
APTRANSCO had informed that SCADA vs SEM differences were still around 15-20%
at times. In certain cases, during tripping of 400 kV lines, the field input was not getting
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 27 of 107
reflected in SCADA. SRLDC had clarified that all over the regions, the difference was
equal to or less than about 5%. In last 15 days the difference was within 5% for 13 days
while on 2-3 days, it was going up to 10-15%. SRLDC in coordination with AP would
identify such nodes having more differences and the same would be rectified within a
month.
SRLDC had informed that they were working out SCADA computation points for drawl
of the constituents in line with the existing SEMs.
KSEBL had expressed concern that the VC facility was not getting stabilized (due to
SDH equipment issues) and also those personnel of M/s.Tejas were not available at
SLDC as per the contract clause. MS, SRPC had informed that this issue had been
deliberated in the Special meeting held on 23.08.2016 and the Vendor had assured of the
necessary corrective action. SRLDC had assured that the issue would be resolved by 30th
August 2016. SR-II had assured that appropriate person from M/s.Tejas would be
deputed to attend the problem.
KSEBL had informed that regarding AMC by M/s Alstom, a separate meeting with
participation from SRLDC, PGCIL and other states was required as some of the punch
points were to be clarified / cleared and M/s Alstom were claiming payments. AP &
Telangana also supported for a regional level meet to sort out the issues. SRLDC had
informed that they had called M/s Alstom for two days meeting to sort out Contract
related issues. AP, Telangana and Kerala would also be invited to address common
issues. SR-II had informed that a Meeting (on 9.6.2016) with KSEBL, M/s Alstom and
PGCIL was held on these issues. Some punch points were not possible to complete due
to design issues while others had been agreed to be completed. MoM of the meeting
could be referred and the pending punch points could be converted into payment and
recovered. TSTRANSCO had stated that issue regarding recovery and the necessity of
completing the pending punch points needed to be deliberated. SRLDC had assured that
all the issues of the states with M/s Alstom would get settled in the proposed meeting.
SRPC deliberations
14.4 MS, SRPC informed that there was significant improvement in SCADA performance.
SCADA Vs SEM reconciliation had also been taken up and the issues were getting settled
as part of an ongoing exercise.
14.5 Director (G & TM), APTRANSCO requested that the gap between SCADA and SEM be
narrowed down further.
14.6 GM, SRLDC said that nationally the difference between SCADA and SEM was of the
order of 5%. In recent exercise for 30 days, the difference had been less than 5% for 25-26
days, while for 4-5 days it had been10-20%.The gap would be further narrowed down in
coordination with APTRANSCO within a month.
14.7 CMD, KSEBL pointed out that there were certain deficiencies in the SCADA system
provided by M/s Alstom and the issues had been brought to the notice of PGCIL. The
price (total-LD) to be paid despite about 16 observed deficiencies needed scrutiny.
14.8 GM, SR II, PGCIL assured that all the identified issues would be addressed in a Meeting.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 28 of 107
14.9 ICCP link between RTAMC & SRLDC
14.9.1 In the SCADA Meetings, PGCIL had suggested ICCP link connectivity between RTAMC
and SRLDC. SRLDC had stated that present system of data through dual communication
channels from the RTU shall be ensured. The proposal of providing data from RTAMC to
SRLDC through ICCP link as a supplementary additional arrangement could be reviewed
at an appropriate level. PGCIL had pointed out that in some of the other regions, the link
was being established and thus the apprehensions of SRLDC were not understood. It had
been suggested that this issue be taken up in TCC/ SRPC forum.
TCC deliberations
ICCP link connectivity between RTAMC and SRLDC as third connectivity was agreed.
The data requirement in this regard would be mutually settled between RTAMC and
SRLDC.
14.9.2 SRPC noted the above.
15. TTC/ATC
15.1 In the 29th
Meeting of SRPC the following had been noted:
In the 4th
meeting of NPC held on 10th
December 2015 (MoM dated 1.1.2016), it had
been decided that to begin with, power system study for assessment of operational limits
/ power transfer capability for each state would be done by the concerned RLDC in
association with concerned SLDC. Monthly TTC/ATC would be uploaded by SLDCs in
their respective websites and also communicated to concerned RLDC & NLDC
subsequently.
Some of the states had cited man power crunch to carry out the ATC/TTC computations
presently. SRPC had pointed out that this was a regulatory requirement. Further as per
decision taken in the NPC Meeting, States needed to carry out ATC/TTC computations
of their area. Besides this helped state utilities in gaining insight to likely constraints and
in taking proactive corrective measures.
APTRANSCO had stated that they would nominate officials for this exercise.
After deliberation, the following was agreed /noted in the TCC:
As per 4th
NPC Meeting, all states were required to compute monthly ATC/TTC limits
for their control area.
SRLDC/NLDC had agreed to render necessary assistance/conduct workshops for the
purpose.
For the base cases, constituents were suggested to kindly coordinate with SRLDC.
SRLDC had assured of full assistance in this regard.
In the SRPC meeting, It was agreed that capacity building/workshop on ATC/TTC
computation would be held as part of the exercise.
15.2 In the OCC Meetings, the following was noted:
Manpower issues were once again raised by AP, TS and KAR SLDCs.
Nominations for dedicated study groups from AP and TS were still pending.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 29 of 107
ATC/TTC work shop for KPTCL, KSEBL & TANTRANSCO was held on 31st
March/1st
April 2016, 12th
/13th
May 2016 and 6th
/7th
June 2016.
Works shop for APTRANSCO and TSTRANSCO was scheduled for July/August 2016
Converged PSSE base cases to be furnished to SRLDC.
15.3 In the 5th
NPC Meeting held on 08th
April, 2016 (refer MoM at Annexure-II), RPCs had
been requested to have regular interaction with states for carrying out power system study
in their network.
15.4 In the TCC, the following was noted:
SRLDC had stated that intra-state TTC/ ATC computations could also help in transfer
of power among SR-Constituents and they would render full assistance in this regard.
For instance, TN power could be sold to Telangana during the months of June-
September.
CEA had stated that intra-state ATC/ TTC computations were very much essential to
implement GoI initiative of Discovery of Efficient Electricity Price (DEEP). In DEEP
platform, certain transactions were cleared but could not be materialized due to
TTC/ATC limitations. States need to furnish ATC/TTC computations, long term,
medium term and short power purchase agreement/plans and procurement through this
platform. This would help in reducing the cost of power purchase and uphold
transparency. ATC/TTC computations transparency has been achieved at CTU/RLDC
level and same has to be achieved at state level to ensure that all are on same platform.
TSTRANSCO had informed that they had recently imparted training to their personnel
at SRLDC. AP was also kindly requested for similar action.
SRPC deliberations
15.5 GM, SRLDC observed that there was good opportunity for exchange of power between
constituents of Southern Region. There were constraints in WR and ER towards NR but
there were no constraints in SR. He requested the constituents to nominate officials to
coordinate with SRLDC to identify these trading possibilities so that it would be
commercially beneficial to all. He added that all states need to host ATC/TTC
computations on their websites.
15.6 Director (G & TM), APTRANSCO assured that despite manpower shortage, they would
nominate some officials to get trained for ATC/TTC computations.
15.7 SRPC noted the above and suggested that concerned entities initiate appropriate action.
16. UPCOMING TRANSMISSION SYSTEM
16.1 MS, SRPC informed that a Committee for finalization of compensation in regard to Right of
Way (RoW) for transmission lines in urban areas has been constituted by MoP vide OM
dated 11.08.2016 (Annexure-XIV). Principal Secretaries of Karnataka and Kerala from
Southern Region were also Members of this Committee
SRPC noted the above.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 30 of 107
16.2 Pending transmission elements in WR and SR for proper utilization of 765 kV
Raichur- Sholapur line (Out of planned 18 elements)
16.2.1 Updated status of pending transmission elements in WR and SR for proper utilization of
765 kV Raichur - Sholapur lines (out of planned 18 elements) is furnished below please:
TCC deliberations
SR-II, PGCIL had informed that there was not much progress in three districts,
Bengaluru Urban, Bengaluru Rural and Tumkur. Only 5 km of stringing work was
pending in Tumkur-Yelahanka line.
KPTCL had informed that Additional Chief Secretary had also intervened in this matter.
Further status would be updated in the SRPC meeting. LILO of Madhugiri-Bidadi at
Bidadi could not be a permanent arrangement though it was helping in utilizing Gooty-
Madhugiri line and loading in other lines had come down. MS, SRPC had clarified that as
per the MoM, it was a temporary reconfiguration and normal configuration had to be
restored by November 2016.
PGCIL had informed that in recent orders, Hon’ble CERC had directed that transmission
charges are to be paid by state utilities, in case downstream network is not ready. In the
recent Grid Code Amendment, the Commission has stated that there has to be an
Implementation Agreement between the respective state and PGCIL. Firm dates for
downstream evacuation system at Madhugiri and Yelahanka needs to be confirmed by
KPTCL for proper coordination.
SRPC deliberations
16.2.2 MD, KPTCL informed that Govt of Karnataka was seized of the issue. Recently,
Hon’ble Chief Minister had reviewed the matter and directed the concerned to deploy
police force, wherever required. With directives from the top, he stated that he was
hopeful that issues would be resolved at an early date.
16.2.3 PGCIL assured that they would also follow up the issue.
16.2.4 The following had been noted in earlier Meetings:
Downstream system by KPTCL was needed to be expedited to reap the benefit. LILO of
Sl.
No
Name of
Transmission
Element
Exe.
Agency
Sch.
CoD
Expected
date
Remarks
1 400 kV Gooty-
Tumkur D/C line
PGCIL June
2014 Commissioned
on 01.12.2015
Power flow of around 550
MW observed with
temporary reconfiguration
at Bidadi SS.
2 400/220 kV , 2 x
500 MVA, 63
MVAR Reactor
Tumkur S/S
PGCIL June
2014 Commissioned
on 01.12.2015
Downstream network not
available
3 400 kV Tumkur-
Yelahanka D/C line
PGCIL June
2014
Severe RoW problem. 400
kV Yelahanka S/S is
ready.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 31 of 107
400 kV Nelamangala – Hoody along with 400 kV Tumkur – Yelahanka together could
help in further evacuation.
Constituents had expressed that LILO of 400 KV Nelamangala - Hoody at
Yelahanka and Tumkur - Yelahanka line (even without downstream at Yelahanka)
could help increase ATC and hence PGCIL may prioritize commissioning.
16.3 Upcoming inter-regional transmission schemes
16.3.1 The updated status is furnished below please:
S S.No. Transmission Element Remarks
a) 765 kV Wardha – Nizamabad-
Hyderabad D/C line
Original Schedule by May 2018.
PGCIL trying to complete the Wardha
- Nizamabad system by May 2017
29th
TCC update:
Wardha-Nizamabad section was being planned in Jan-Mar’2017. Nizamabad -
Hyderabad section was planned during Apr-Jun’ 2017. 1000 MW of LTA has been
granted to Telangana with the commissioning of this line. Within one and a half
years of investment approval the first system would be ready. Telangana has
confirmed that they would be bringing up the downstream system in the same
timeframe.
30th
SRPC update:
Director (O), PGCIL informed that they were making efforts to complete the entire
system of Wardha – Nizamabad-Hyderabad D/C line by June 2017. He stated
that they were anticipating around 2,800 MW through the 765 kV D/C with inter
connectivity of 400 kV lines.
Chairperson, SRPC observed that 2-3 SR states were tying DVC power through this
link.
Sl.
No
Name of
Transmission
Element
Exe.
Agency
Sch. CoD Expected
date
Remarks
Tumkur downstream
1 220 kV Tumkur –
Antharasana Halli
D/C
KPTCL Tenders for
the above
line had
been
placed on
18.03.15
and it
would take
18 months
for
completion
29th TCC
update :
November
2016
2 220 kV Tumkur
(400 kV) S/S – 220
kV Tumkur S/S
D/C
KPTCL 29th TCC
update :
November
2016
Yelahanka downstream
1 220 kV Yelahanka
(400/220 kV) S/S- 220
kV Yelahanka S/S D/C
Cable – 5 kM
KPTCL 6/7 months’
time (5 kM)
once the
award was
in place
Special cable (international
source) was required.
29th
TCC update: Tender
was likely to be finalized
shortly. It could take around
one year after PO.
2 400/220 kV Yelahanka
S/S – 220 kV BIAL S/S
D/C
KPTCL 29th
TCC update: KPTCL
informed would be dropped
keeping in view
Devanahalli SS
connectivity.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 32 of 107
b) WR-SR 6000 MW HVDC Bipole Link
[Raigarh (Chhatisgarh) - Pugalur-
Trichur (TN/KER)]
Nov’ 2019
Raigarh HVDC terminal Award
Placed in Jun’16.(Pkg under court
case)
Award under progress for other
packages under Scheme-I
29th
TCC update: PGCIL informed that final hearing for the Package (Terminal) was scheduled for
26.08.2016.
c) 765 kV Angul - Srikakulam PS D/C
line
By August 2016, other associated
elements by Jun’2017-Dec’ 2019
29th
TCC update:
Angul-Srikakulam and Srikakulam- Vemagiri (PG TBCB) lines were ready. However
due to delay in delivery of terminal equipments at Vemagiri/Srikakulam for the
TBCB line from China, they were planning to charge the Srikakulam- Vemagiri (PG
TBCB) line at 400 kV level by directly connecting Gajuwaka-Nunna LILO at
Vemagiri and the issue was being referred to CEA. By November/December 2016,
the line could be charged at 765 kV level.
30th
SRPC update:
Director (O), PGCIL informed that Angul-Srikakulam line was getting charged at 765
kV level. Srikakulam- Vemagiri could not be charged at 765 KV due to delay in
terminal equipment. He suggested a proposal for temporary reconfiguration till the
complete system comes up by November/December 2016. In the meantime, they
were also trying to get the studies done through CEA to utilize the system with
anchoring of reactors at Vemagiri. If the same is useful to SR to get some additional
power, the configuration could be contemplated. SRPC agreed to the proposal of
temporary configuration subject to due ratification through studies.
d) Additional inter-Regional AC link for
import to Southern Region, i.e.,
Warora - Warangal - Hyderabad-
Kurnool 765 kV link
TBCB, PFCCL- BPC–Some
scope of work/ reactive
compensation modified and RfQ
modified accordingly.
RfP opened. Schedule was 40
months from the transfer of SPV
(around mid-2019).
36th
Meeting of Empowered
Committee scheduled for 26.07.16
29th
TCC update:
M/s Essel Infra has been selected through TBCB. SPV was transferred on
06.07.2016 with a schedule of 40 months.
e) System strengthening within SR for
transmitting power beyond Vemagiri
TBCB- RECTPCL-BPC–Some
scope of work/ reactive
compensation modified.
The project has been awarded to
PGCIL under TBCB, and was
expected by April, 2019.
29th
TCC update:
PGCIL informed that works have been awarded for all the packages and
under progress.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 33 of 107
16.3.2 Updated status of upcoming inter regional scheme is furnished at Annexure-XV.
16.3.3 The following had been noted in earlier Meetings:
CMD, APTRANSCO & APGENCO had pointed out that considerable generation was
coming in Vemagiri area. With Angul-Srikakulam also injecting into Vemagiri,
system strengthening in SR beyond Vemagiri needs to be fast tracked.
16.3.4 As noted in 29th
SPRC Meeting a Joint Study Meeting was held at SRPC, Bengaluru
between 14th
-17th
March 2016 to study Short Term Planning & Long Term Planning Issues
(MoM copy at Annexure-XVI).
Short-term (temporary) connectivity between Vemagiri-II(PG) and KV Kota
(APTRANSCO) for increasing TTC of SR
The studies were carried out and it was found that after commissioning of the Wardha –
Hyderabad and Angul – Sirikakulam – Vemagiri 765 kV lines, the TTC for import of
power by Southern Region would increase from 6650 (at present) to 9600 MW.
However, this TTC reduces by 1700 MW upon commissioning of the scheme – “Removal
of constrains in 400 kV by extension at 400 kV Vemagiri substation”, which had been
planned for accommodating the KV Kota - Vemagiri at Vemagiri (AP). In these studies,
one unit (660 MW) of East Coast was also considered. To overcome the reduction in
TTC for import of power by Southern Region, system studies were carried out by
considering a short-term (temporary) connectivity between Vemagiri-II (PGCIL) and
KV Kota (APTRANSCO) as detailed above. It was observed that with this measure, the
TTC would increase to 11000 MW. Considering the benefit of this temporary
connectivity which would be needed till the commissioning of ISTS system beyond
Vemagiri, all the states requested APTRANSCO to consider this proposal positively.
APTRANSCO requested POWERGRID to send draft proposal for consideration and
approval of their boards. Draft proposal sent by POWERGRID is enclosed at Appendix-
5.0
Determination of TTC to import power into Southern Region
From the above study following is observed:
A. TTC is expected to increase to 7275 (6650 + 625 MW) with commissioning of 765
kV D/c Angul-Srikakulam-Vemagiri and LILO of Gajuwaka-Vijayawada at Vemagri-
II (PG). However, with commissioning of Kudgi generation, TTC is expected to
decrease which can be offset by increasing transfer limit on 765 kV D/C Raichur –
Solapur to 2750 MW.
B. After commissioning “Angul-Srikakulam-Vemagiri 765 kV D/c line along with
“Constraints in 400kV bay extensions at Vemagiri” the TTC value is getting reduced
to 5980 MW from present level of 6650 MW. However, after rearrangement as
proposed in 39th
Standing Committee meeting on Power System Planning in Southern
region held on 28th
& 29th
December, 2016, the TTC value is increased to about 7800
MW to 8100 MW depending on gas generation at Vemagiri(AP).
C. S1-S2 corridor capacity significantly improved with commissioning of 400kV Tumkur
(Vasanthanarasapura) – Dharmapuri D/C line
TCC deliberations
MS, SRPC had informed that to overcome the overloading of Vemagiri-I (AP)-
Vemagiri-II (PG), temporary rearrangement had been proposed .One circuit of
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 34 of 107
Vemagiri (PG)-Vemagiri (AP) was proposed to be connected with KV Kota while
other circuit connected to Vijayawada (PG). APTRANSCO’s acceptance had been
requested.
APTRANSCO had observed that with this temporary arrangement they were losing
part of their network and it may cause congestion at Vemagiri SS.
CTU had clarified that they were ensuring that TTC got increased and also AP’s
internal evacuation did not get affected.
It was agreed that a joint Meeting between AP and PGCIL would be held on 08th
September 2016 at Hyderabad to discuss this proposed rearrangement.
16.3.5 SRPC requested APTRANSCO to consider the proposal.
16.4 Status of various Associated Transmission Systems (ATS) of upcoming generators
16.4.1Common System Associated with NTPL / Costal Energen Private Ltd / Ind-Barath
Power Ltd
Updated status of associated links is furnished below:
Transmission Elements Line
Length
(ckm)
Impleme
nting
Agency
Sch
COD
Ant
COD/
Act
COD
Constraints/
Remarks
765 kV D/C Tuticorin
PS - Salem PS line
(Dharmapuri) (initially
charged at 400 kV)
735 PGCIL Dec'14 Oct’16
400 kV D/C Salem PS –
Salem line
120 PGCIL Sep’16 Line is ready
765 kV S/C Salem PS
(Dharmapuri) -
Madhugiri P S line
(initially charged at 400
kV)
244 PGCIL Dec'14 29th
TCC update:
Severe ROW
problems in
Karnataka. Critical.
Covered under
PRAGATI.
765/400 kV Salem PS
(initially charged at 400
kV)
PGCIL Dec’16 Supply civil works
and erection under
progress.
400 kV D/C Coastal
Energen – Tuticorin PS
54 Coastal
Energen
Sep’16 29th
TCC update:
CEA inspection
awaited and
charging of the line
expected within
two weeks.
TCC deliberations
PGCIL had requested for firm commitment from CEPL on completion of 400 kV D/C
Coastal Energen – Tuticorin PS. Hon’ble CERC in its Order dated 29.7.2016 on petition
No.127/TT/2014 had directed CEPL to pay the transmission charges for PGCIL assets till the
dedicated line is declared on CoD.
CEPL had requested for cooperation of PGCIL so that all other activities like SCADA
integration, inter-locking etc., are completed and the line is charged once CEA gives
clearance.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 35 of 107
SRPC deliberations
MD, CEPL informed that they had executed the line in record six months time and
were awaiting CEA inspection.
16.4.2 Transmission system associated with IPPs (IL&FS) of Nagapattinam/Cuddalore Area
Updated status of associated links is furnished below please:
(i) Transmission system associated with IPPs of Nagapattinam/Cuddalore Area–
Package A
Transmission
elements
Line
Length
(ckm)
Imp. Agency Sch
COD
Ant.
COD
Constraints/
Remarks
Nagapattinam PS-
Salem New 765
kV D/C line
406 Powergrid
Nagapattinam-
Madhugiri
Transmission
Company
Limited
(PNMTCL)
(A subsidiary
of PGCIL)
Mar’
15 Sep’16
Salem New –
Madhugiri 765 kV
S/c line.
219 - Severe RoW issues
being faced in
Karnataka.
SRPC deliberations
ED, PGCIL informed that Nagapattinam PS – Salem New line was expected to be
commissioned by October 2016. Salem New (Dharmapuri) was connected to
Salem existing. With this, the connectivity to SR grid would get established. As
per TSA, both Nagapattinam PS-Salem New D/C and Salem New – Madhugiri S/C
line were required to be commissioned for declaring under COD. Since line
between Nagapattinam PS-Salem New D/C could get utilized, he suggested that
COD of this line be agreed. Salem New – Madhugiri S/C line was held up on
account of ROW issues in Karnataka.
Chairperson, SRPC observed that this may not help for additional inward power
transfer from WR but may help in outward power transfer.
SR constituents agreed for the suggestion of PGCIL, subject to ratification through
studies.
(ii)Transmission System Associated with Contingency plan for Evacuation of Power
from IL&FS (2x600MW)
The following was noted in the 29th
Meeting of SRPC:
It was noted that some stringing/ upgradation was pending within NLC Complex.
These works had been envisaged as a contingency evacuation for IL&FS.
It was noted that strengthening of Neyveli TS-II-Neyveli TS-I with HTLS conductor
was part of contingency plan for evacuation of IL & FS power as per CERC Order.
The transmission capability remains unchanged in view of the replacement not carried
out in NLC complex. To allow higher power, balance works were also to be
completed to comply with the intent of CERC Order.
In the sub Committee Meetings, PGCIL had informed that BOQ had been put to
Management for approval.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 36 of 107
16.4.3 Evacuation of Power from HNPCL (1,040 MW) Power Plant
(i) Updated status of associated links under APTRANSCO’s scope is furnished below:
Transmission
Elements
Line
Length
(ckm)/M
VA cap.
Implementin
g Agency
Target
Date
Target
date
completi
on
Constraints/ Remarks
Startup Power Line
from M/s. HNPCL
TPP to 400/220 kV
Kalpakka SS
7 APTRANSCO Dec’16
400 kV TM D/C
Line from HNPCL -
Kamavarapukota S/S
(Lot-I, II & III)
200 APTRANSCO Jul ‘15 Dec’16 Purchase Order issued
on 03.11.2015. 24
Foundations completed
out of 256.
400 kV TM D/C Line
from Kamavarapukota
S/S - Vemagiri 400 kV
S/S
APTRANSCO Dec’16 All the foundations, tower
erections and stringing
works are completed.
400 kV TM D/C
Line from
Kamavarapukota S/S
- 400 kV Chinna
Korukondi S/S
212 APTRANSCO Sept. ‘15 Dec’16 Works under progress.
Kamavarapukota
Substation
2x315
APTRANSCO Mar ‘16 Dec’16 All works completed
for 1 No. of 400 KV
Bay on 07.02.2014
2 Nos. of 400 KV
Bay Extensions at
existing 400/220 KV
Kalpaka S/S of
HNPCL
APTRANSCO Dec’16
(ii) Updated status of associated links under TSTRANSCO’s scope is furnished below:
Transmission Elements Line
Length
(ckm)/M
VA cap.
Implement
ing
Agency
Target
Date
Target
date
completio
n
Constraints/
Remarks
400 kV TM D/C Line
from Chinna Korukondi -
400 kV Suryapet S/S
212 TSTRANS
CO
Works completed.
Suryapet S/S -
Nandiwanaparthi S/S 400
kV Quad D/C Line
240 TSTRANS
CO
Mar’15 By Sep 16 Works awarded in
Sep-13. Stringing
completed. OPGW
4.682 kM under
progress.
400 kV Quad D/C Line
from Nandiwanaparthi
S/S - Shankarapally S/S
222 TSTRANS
CO
Mar’15 By Dec 16 Tower erection: 300
out of 315 completed.
Stringing: 60.77 km
out of 111 km
completed/
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 37 of 107
Suryapet Substation
400/230/132 & 2 Nos. of
400 KV Bay Extensions
at 400 KV Shankarapalli
S/S
2x315
TSTRANS
CO
All works completed.
Suryapet SS charged
on 30.03.2016
through LILO of 400
kV VTS-Malkaram
Ckt 1
16.4.4 Transmission system of KPTCL for evacuation of power from Yermarus TPS (2x800
MW)
Updated status of associated links is furnished below:
Transmission elements Imp.
Agency
Line
Length
(ckm)/
MVA
cap.
Sch. COD Constraints/ Remarks
Bellary 400 kV PS near
‘BTPS’
JSWEL
(KPTCL)
Nov’16 (As
informed by
JSWEL)
Works under progress
Gulbarga 400/220 kV
substation
KPTCL 2x500 Land acquired. Geo tech
survey work will be
awarded within a week. Bill
of Materials prepared and
within 15 days estimate will
be prepared.
Yermarus TPS - Gulbarga
400 kV D/C line (QM)
KPTCL Detailed survey completed.
Estimate is being prepared.
400 kV SS at
Chikkanayakanahalli (C.N
Halli) near “Loop in Loop
Out” (LILO) point on the
Nelamangala – Talaguppa
400 kV lines to Hassan.
KPTCL 2x500
MVA
In 39th SCPSPSR
a step down SS
with 2 x 500
MVA, 400/220
kV ICTs was
agreed.
Land Acquisition is under
progress. The proposal is
submitted from AC Tiptur
to DC Tumkur on
28.03.2016
LILO of both the circuits of
Nelamangala – Talaguppa
400 kV lines to the proposed
pooling station near CN
Halli.
KPTCL Linked with CN Hally
station
Termination of 400 kV D/C
line feeding 400/220 KV
station at Hassan from
Nelamangala – Talaguppa
line at CN Halli 400 kV
pooling station.
KPTCL After CN Halli land
identification, survey would
be taken up.
Yermarus TPS - Bellary
Pooling Station 400 kV D/C
line with quad moose
conductor
KPTCL 300
(400 kV
MC Line
(5.138
Kms) and
400 kV
DC line
(137.355
Km)
totally
Expected by
Mar’17 29
th TCC update:
Total Locations : 399 Nos
Excavated : 245/399
Stubs concreted : 242/399
Towers erected: 109/399
Stringing : Nil
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 38 of 107
for a
route
length of
142.493
Kms)
Bellary Pooling Station -
C.N.Hally 400 kV D/C line
with quad moose conductor
KPTCL 360 Survey using
MST conducted
and reports
submitted to
zonal office vide
ltr no:1682-83
Dt:30.06.15 and
the same is
submitted for
approval to
CEE(P&C) vide
ltr.no.2504-06 dt
7.7.2015
29th
TCC update:
Part of the work from
Rampura-Jagalur 65 kM
had been awarded.
Bellary PS to Madhugiri line
(765/400kV V.N.pura
substation (PGCIL)
a) Madhugiri to Rampura
limits): 400kV DC line
with Quad Moose ACSR
(188.74 Kms)
b) Bellary pooling Stn 400
kV to Rampura limits
(KelaginaKanavi): (43.018
Kms)
KPTCL
Under
Executio
n by
KECIL
By
Kalpataru
PTL
380
22-Dec-16
29th TCC update:
Nov’16
24-Apr-17
29th TCC update:
Nov’16
29th
TCC update:
Out of 512 locations, 484
excavations over, 481 stubs
concreted, 469 towers
erected &159.2/188.74 km
stringing completed.
29th
TCC update:
Out of 125 locations, 119
excavations over, 119 stubs
concreted, 97 towers
erected & 3.2 km stringing
completed.
Bellary TPS – Bellary
Pooling Station 400 kV D/C
line with quad moose
conductor
KPTCL 10 In 39th SCPSPSR it was
agreed to drop the proposal.
Dropped
De-link 400 kV S/C line
running between RTPS-
BTPS-JSW-Guttur with
JSW Bus
KPTCL
Nov’16 Agreed in 39th SCPSPSR
400 kV M/C line from
JSW to BPS is under
progress, once this is
commissioned the link
between JSW & BPS will
be delinked.
JSW TPS – Bellary Pooling
Station 400 kV D/C line
with quad moose conductor
KPTCL Jul’16 (As
informed by
JSWEL)
Only after all other
Transmission Elements
under Stage I are
commissioned.
KPTCL/JSW to discuss to
take up this work as
dedicated transmission line
by the generator.
Works to be carried by
JSW.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 39 of 107
16.4.4.1 The following had been noted in earlier Meetings:
KPTCL had informed that 400 kV Tumkur-Bellary PS D/C line had been awarded
and was expected to come along with Bellary PS with schedule of one and half years
i.e March 2017. They were trying to compress construction to one year against
schedule of one and half year. Land identification was completed in C N Hally but
KPTCL was targeting this system in the second stage. CEA had been requested to
allow 500 MW of evacuation from Yermarus coupled with drawal at Tumkur. It
was assured that 500 MW of injection from Yermarus would not be at the cost of
regional ATC.
SRLDC had pointed out that 400 KV Hiriyur - Nelamangala lines were getting
overloaded and ATS was not ready for Bellary Unit-III and Yermarus TPS.
Generation from the Complex maybe required to be regulated by Karnataka SLDC.
SRLDC had stated that only 2,090 MW of evacuation would be possible from
Raichur TPS, Yermarus TPS & Bellary TPS. KPTCL pointed out that with the
present network about 2,600 MW of power was already getting evacuated. SRLDC
confirmed that 400 kV N/W had only been considered in the studies.
16.4.4.2 In the Joint Study Meeting held at SRPC; Bengaluru between 14th
-17th March 2016 to study
Short Term Planning & Long Term Planning Issues (Refer Annexure-XVI) the following
had been concluded:
So, based on studies, it was decided that Karnataka may commission first unit of
Yeramarus TPS either by reducing about 700 MW at Raichur TPS or by drawing about
500 MW at Madhugiri. Considering that a March/early April is low wind season,
Karnataka should attempt to achieve COD within March/ early April. This discussion
is exclusively for the purpose of COD. Regarding scheduling of YTPS power,
KPTCL/Karnataka would coordinate with SRLDC. The LTA and MTOA in ISTS would
have priority and the margins if any after meeting these LTA/MTOA commitments may
be considered by SRLDC.
TCC deliberations
KPTCL had informed that line from Yeramarus to Bellary PS may not be immediately
required for evacuation of Yeramarus power. Around 1,100 MW of JSWEL power
which was getting evacuated through their lines would now be using the line through
Bellary PS to Madhugiri. It had been acknowledged by CEA/CTU that around 600
MW could be injected at Yeramarus in case KPTCL ensures 500 MW drawal at
Madhugiri. From November 2016, they would be able to pump Yeramarus power with
normal/temporary reconfiguration at Bidadi and downstream system at Madhugiri.
It was noted that injection at Yeramarus needed to be coordinated with SRLDC in line
with studies (CEA’s MoM dated 03.05.2016).
16.4.4.3 SRPC noted the above.
Additional JSW TPS –
Bellary Pooling Station 400
kV D/C line with quad
moose conductor
Agreed in 39th SCPSPSR
400 kV BTPS-Guttur D/C
line (QM)
Agreed in 39th SCPSPSR
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 40 of 107
16.4.5 Transmission System required for evacuation of power from Kudgi TPS (3x800 MW
in Phase-I) of NTPC Limited
The updated status is furnished below:
The following had been noted in earlier Meetings:
Three 220 kV D/C lines were planned evacuation lines at 220 kV level to Vajramatti,
Basavana Bagewadi and Bijapur. The Vajramatti line had just been awarded and could
take about 1 year. There were some RoW issues in that area. Construction from B
Bagewadi and Bijapur ends had already commenced and about 50 % of the lines are
completed
16.4.6 Transmission System for evacuation of power from Singareni Collieries
Generating Project (2 x 600 MW)
The following is the status update:
Transmission
Elements
Imp. Agency Scheduled
CoD
Revised
Target
Date
Constraints/ Remarks
400 kV Kudgi TPS –
Kudgi (PG) 2xD/C
Line
M/s Kudgi
Transmission
Limited (L&T
Infrastructure
Development
Projects Ltd.)
Feb-15 2015-16
One D/C line Kudgi TPS –Kudgi
(PG) declared on deemed CoD
from 04.08.15.
Kudgi (PG)-Tumkur
765 kV D/C Line
Dec - 15 Line is ready
Tumkur - Bidadi 400
kV D/C (quad) Line
Line is charged through temporary
reconfiguration
400/220 kV ICT 2 at
NTPC Kudgi
Switchyard
NTPC Aug’16
400 kV Bus Reactor -2 NTPC Aug’ 16 Under Progress
Transmission
elements
Length
(ckm/MVA
capacity)
Imp. Agency
Sched
uled
CoD
Target
date of
Completi
on
Constraints/
Remarks
1. 400 kV Singareni- Gajwel in two parts
a) 400 kV Jaipur
(Singareni) -
Rangampet D/C
(Quad)
149.636
TSTRANSCO
Comp
leted
Charged on
Nov 15
Reactor also
commissioned
b) 400 kV
Rangampet- Gajwel
D/C (Quad)
174.852
TSTRANSCO
Comp
leted
2. 400 kV Singareni-Nirmal in two parts
a) STPP, Jaipur -
Jagityal
142 TSTRANSCO Mar’ 17 Works Awarded on
Nov’15.
b) Jagityal - Nirmal 156 TSTRANSCO Feb
17
Dec’ 16 Works Awarded on
Oct’15.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 41 of 107
16.4.7 Transmission System for Rayalaseema TPS (600 MW)
The following is the status update:
16.5 Status of upcoming links having impact on S1-S2
Following is the updated status:
Sl.
No.
Transmission
Element Schedule
Expected
Commissioni
ng Date
Remarks
1 400 kV
Somanahalli-
Dharmapuri PS
Jun’15 Severe RoW problems being faced in
Karnataka. Critical issues related
compensation not yet resolved.
2
400 kV
Mangalore
(UPCL ) -
Kasargode-
Kozhikode
In the 39th
SCPSPSR, it was noted that
the process of implementation of 400
kV UPCL-Kasargode- Kozhikode line
in TBCB or regulated tariff in
compressed time schedule will be
initiated as applicable.
16.5.1 In earlier Meetings the following had been noted:
PGCIL had informed that regarding 400 kV Dharmapuri - Somanahalli line, DC (Urban)
had ordered compensation of 100 % of fair value for tower footing and 55 % for line
corridor. With this, cost of 30 kM line was working out to as high as Rs 90 crore. SR-II,
PGCIL had informed that ROW issues for 400 kV Somanahalli - Dharmapuri PS were yet
Transmission
elements
Length
(ckm/M
VA
capacity)
Imp. Agency
Scheduled
CoD
Target
date of
Complet
ion
Constraints/ Remarks
RTPP (Stage - IV) -
Chittoor TM D/C
Line
(a). RTPP - Pedda
Jamgam Palli
(P.J.Palli)
(b). P.J. Palli-
Chittoor
(c) 220 kV
Muddanur(RTPP)-
Chinakampally 3 &
4
432
120
APTRANSCO
Dec’ 16
Dec’ 16
Foundations: 291 out
of 321 completed.
Tower erection: 250
completed.
Stringing of 49.049 kM
completed.
Foundations: 309 out
of 321 completed.
Tower erection: 220
completed. Stringing of
38.868 kM completed.
Commissioned on
16.06.2016
400/220 kV,
Kalikiri S/S
2 x 315
MVA
APTRANSCO Feb’17 PO is placed in Nov-
15.
LILO of both
circuits of
Rayalseema IV-
Chittoor 400 kV
D/C line| at Kalikiri
APTRANSCO
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 42 of 107
to be resolved and it would take around two months to complete the work once the ROW
issues are resolved.
16.6 Critical Intra-regional transmission elements
The following is the status update:
Sl.
No. Transmission Element Expected CoD Remarks
1 765 kV Salem- Tumkur
By PGCIL
Through TBCB
-
-
Severe RoW being faced in
Karnataka. Critical.
29th
TCC update:
TBCB line is progressing as in
different corridor
2 400 kV Edamon-Kochi Jun’17 Govt. of Kerala issued revised
G.O in Jan’2015 with
enhanced compensation.
Being monitored under
PRAGATI
16.6.1 The following was noted in earlier Meetings:
SR-II, PGCIL had informed that regarding 400 kV Edamon - Kochi there was not
much progress. KSEBL had informed that the survey was being carried out from both
the ends and the ROW issues would be settled by Kerala Govt. The line was being
monitored under ‘PRAGATI’ (Pro Active Governance And Timely Implementation).
Regarding 765 kV Tumkur - Dharmapuri, PGCIL had informed that the line was
crossing four districts in Karnataka (Tumkur, Kolar, Chikkaballapur & Bengaluru
Rural) and RoW issues were being addressed in a stepwise manner.
TCC deliberations
PGCIL had informed that they had recommenced survey works but there was lot of
resistance and Govt. of Kerala support was required to move forward.
KSEBL had informed that once the ROW affected people are identified they would
pay the compensation.
SRPC deliberations
CMD, KSEBL informed that they were giving top priority for completion of this line.
They were hopeful of getting the entire ROW in possession by December 2016.
16.7 400 kV Trichur-Kozhikode line (Madakkathara-Areakode)
In the 39th
SCPSPSR it had been noted that Madakkathara - Areakode (Kozhikode) -
Kasaragode 400 kV D/C link may be taken up by KSEBL.
16.8 Requirement of additional ICT at 400 kV sub-station at Kozhikode
16.8.1 In the 39th
SCPSPSR, 1 x 500 MVA ICT at Areakode (Kozhikode) substation was
agreed.
16.8.2 KSEBL vide letter dated 20.02.2016 had stated that PGCIL may take necessary steps to
provide additional ICT at 400 kV substation at Kozhikode temporarily by using spare 315
MVA ICT till 500 MVA ICT is available. The following was deliberated in the SRPC /
TCC meetings:
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 43 of 107
TANTRANSCO had informed that they would return back the spare ICT of PGCIL
being utilized at Sriperumbudur as their ICT was ready for commissioning.
PGCIL had stated that they would consider shifting either of the two ICTs and most
likely the ICT from Tamil Nadu would be feasible. They would initiate the bay
works also.
TCC deliberations
KSEBL had informed that PGCIL had given an estimate of Rs.3 Crores for which
approval was required. The transformer was required by December 2016. They would
intimate their decision within two weeks.
SR-II, PGCIL had stated that consent needs to be communicated at the earliest since there
were time schedule indicated for shifting the ICT. Transformer from some other package
may have to be diverted.
SRPC deliberations
16.8.3 CMD, KSEBL said that they would convey their decision within a week’s time. PGCIL
was quite proactive. It was felt that in case they had taken up tendering activities,
wasteful expenses of temporary usage of 315 MVA ICT could have been avoided.
16.8.4 GM, SR-II, PGCIL informed that 500 MVA Transformer approved in the Standing
Committee was under NIT with a schedule of one year. Once the tender is awarded, the
commissioning could be expedited or even diversion from other package could be
contemplated. He clarified that as discussed in the TCC, the tariff component had not
been included in their proposal.
16.8.5 It was noted that PGCIL had taken up the work for the 3rd
ICT expeditiously, soon after
approval in the Sanding Committee on Power System Planning.
16.9 NLDC vide letter dated 21st July 2016 (available in NLDC website) had highlighted
following transmission constraints in their Operational Feedback for the quarter April-
June 2016 in respect of SR:
Transmission Line constraints:
400 kV Nellore Pooling Station -Nellore D/C line
400 kV Gooty-Nelamangala line & 400kV Gooty- Somanahalli line
400 kV Udumalpet- Palakkad D/C line
400 kV Hiriyur-Nelamangala D/C line
220 kV Bangalore Metro Network
Overloading of 220 kV Shoolagiri-Hosur(TN)-Yerrandahalli-Somanahalli S/C line
220 kV Sharavathy-Shimoga lines (4 nos) and 220 kV Sharavathy-Talaguppa D/C
Constraints in Coastal AP
Constraints for Rayalaseema TPS Generation Evacuation
Transformation Capacity at 400/220 kV Kozhikode SS
Constraints in Chennai 230 kV System
Overloaded 220 kV Lines in Tamil Nadu
Constraints in 230 kV Evacuation lines of MTPS and Kundah complex
Constraint in Evacuation of Coastal Energen
Constraints in wind Evacuation
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 44 of 107
ICT Constraints
400/220 kV 2 x 315 MVA ICTs at Gazuwaka
400/220 kV 2 x 315 MVA ICTs at Vemagiri
400/220 kV 2 x 500 MVA ICTs at Nelamangala
400/220 kV 2 x 500 MVA ICTs at Somanahalli
400/220 kV 2 x 500 MVA ICTs at Hoody
400/220 kV 2 x 315 MVA ICTs at Mysore
400/230 kV 2 x 315 MVA ICTs at Pugalur
400/230 kV 2 x 315 MVA ICTs at Trichy
SRPC noted the above and requested respective entities to kindly identify and implement
short term and long term measures to overcome these constraints.
17. UPCOMING RENEWABLE PROJECTS AND THEIR INTEGRATION WITH
TRANSMISSION NETWORK
17.1 Status update of the upcoming schemes in Southern Region for renewable as given below
is furnished at Annexure-XVII.
Uravakonda Wind – AP
Solar Power Park at Ghani/Panyam (1000 MW )Phase-I Works – AP
1000 MW Wind Power at Aspiri- AP
1500 MW NP Kunta Solar Project- AP
TN – 1000 MW Solar Park to be developed by M/S Adani at Kamuthi
Kamuthi Solar (Max 100 MW injection)- TN
Samugarengapuram Wind (1800 MW existing + 300 MW) - TN
Green Energy Corridors:- Inter State Transmission Scheme (ISTS) - Part - A
LTA to Wind Generators in Tirunelveli Area - Tamil Nadu
Connectivity to Wind Generators in Coimbatore Area -Tamil Nadu
Connectivity/LTA to Wind Generators -Tamil Nadu (600 MW progressively from
March 2017)
Connectivity to Wind Generators in Anantpur/Kurnool Area – AP
Renewables (KfW) Hindupur - AP
Renewables (KfW) Jammalamadugu - AP
Renewables (KfW) Uravakonda - AP
Renewables (KfW) 220 kV Interconnectivities - AP
Renewables (KfW) 132 kV Interconnectivities – AP
Renewables (KfW) Intra-state (modified scheme)- Karnataka
Renewables (KfW) Phase I – Tamil Nadu
Renewables (KfW) Phase II – Tamil Nadu
17.2 It was observed that timely progress on the above scheme needs to be communicated to
SRPC Secretariat since it was a critical issue being monitored by various bodies.
17.3 Transmission System associated for Tumkur Ultra Mega Solar Park (2000 MW)
Transmission
Elements
Line Length
(ckm)/ MVA
Capacity
Implem
enting
Agency
Sch
COD
Ant
COD/
Act COD
Constraints/
Remarks
Phase-I : Transmission system for Tumkur Ultra Mega Solar Park (1000 MW) April 2017
400/220 KV Tumkur
PS
Bus Reactor
3 x 500 MVA
1 x 125
MVAR
L & T Oct’18 Award placed in Apr’16.
Expediting to complete
along with Generation
Commissioning.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 45 of 107
LILO of 400kV Gooty
– Tumkur
(Vasantnarsapur) D/C
at Tumkur (Pavagada)
PS
3 PGCIL Oct-18 Award placed in
Jun’16. Expediting to
complete along with
Generation
Commissioning.
400 kV Tumkur P S -
Hiriyur D/C
218 PGCIL Dec’18 For 400kV Tumkur –
Mysore line section
routed via Hiryur S/s.
Award placed in
Jun’16. LILO of 400kV
Bellary Pool –
Tumkur
(Vasantnarsapur) D/C
(Quad)(both
circuits)[KPTCL line]
at Tumkur (Pavagada)
Pooling station*
107 PGCIL Dec’17 *KPTCL would
complete Bellary
pooling station –
Tumkur
(Vasantnarsapur) line
D/c (Quad) by
December- 2016.
Award placed in
Jun’16. 4 nos. sub pooling
stations (4x250 MW,
66/220kV), 4 no. of
interconnecting 220
kV D/C lines
KSPDC
L
Phase-II : Transmission system for Tumkur Ultra Mega Solar Park (1000 MW) Sep 2017
Augmentation of
400/220KV Tumkur
PS
2nd Bus Reactor
2 x 500 MVA
1 x 125
MVAR
Hiriyur–Mysore 400
kV D/C line
Switchable Line
Reactor at Mysore
190
1 x 80
MVAR
Tumkur PS – Mysore
– De LILOed at
Hiriyur
400 kV Tumkur PS-
Devanhally (KPTCL)
D/C (Quad)
125 KPTCL would
complete
establishment of
400/220 kV substation
at Devanahally
including inter-linking
400 kV and 220 kV
lines before Phase-II
at Ultra Mega Solar
Power Park. Third 400/220
kVMVA transformer
at Tumkur
(Vasantnarsapur)
1 x 500 MVA
4 nos. sub pooling
stations (4x250 MW,
66/220kV), 4 no. of
interconnecting 220
kV D/C lines
KSPDC
L
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 46 of 107
TCC deliberations
SR-II, PGCIL had informed that they were focusing on completing the Pavagada SS
and LILO of Gooty-Tumkur line at Pavagada SS. As per Investment Approval
scheduled date of LILO of Gooty-Tumkur at Pavagada and Pavagada SS was Oct
2018 but PGCIL was expediting to advance the commissioning.
It was noted that Tumkur Ultra Mega Solar Park Phase-I (1,000 MW) was expected
by April 2017.
SRPC noted the above.
18. NEW PROJECTS OF NTPC, NLC, NPCIL, JOINT VENTURE & UMPP
18.1 Krishnapatnam UMPP (6x660 MW)
18.1.1 The following had been noted in earlier Meetings of SRPC:
The matter is sub-judice in High Court of Delhi.
CMD, APTRANSCO & APGENCO had informed that APSPDCL was the lead
procurer. Over a period of time this project was non-starter and it was unlikely to start
in future also. Except land leveling no work had been undertaken. Last week, CAPL
made presentation to the procurers for exit from the project. Hon’ble High Court had
posted the case on 22nd
April 2016 and project was being constantly monitored. Even
in the last procurer’s meeting, CAPL was suggested to come out with a reasonable
proposal.
Progress of Krishnapatnam UMPP had been uploaded in MoP website with the
observation ‘The project was handed over to Reliance Power Ltd. on 29.01.2008. The
developer has stopped work at site, citing new regulation of old pricing in Indonesia.
Lead Procurer namely Andhra Pradesh South Power Distribution Company
(APSPDCL) has issued termination notice to Coastal Andhra Power Ltd (CAPL). The
case is subjudice in division bench, Delhi High Court.’
18.1.2 In the SRPC Meeting it was noted that there was no update on this issue.
18.2 Cheyyur UMPP (4,000MW)
18.2.1 In the 27th
TCC Meeting, CTU had informed that this project had been identified under
‘Plug and Play Mode’ and new bids would be invited during 2015-16.
18.2.2 The following was noted in earlier TCC meeting:
The progress of Cheyyur UMPP has been uploaded in MoP website with the observation
‘The site at Cheyyur in Kanchipuram District in Tamil Nadu has been identified along with
captive port at Panaiyur village. Request for Qualification (RfQ) and Request for Proposal
(RfP) issued in 2013 were withdrawn. Fresh RfQ and RfP are to be issued after the
finalization of Standard Bidding Documents.’
TCC deliberations
TANGEDCO had informed that land acquisition is over. In case the bidding process is
getting delayed they were willing to take the project by themselves.
18.2.3 SRPC noted the above.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 47 of 107
18.3 Schedule of synchronizing/commissioning of the new projects of NTPC, NLC, NPCIL,
BHAVINI & UMPP is furnished below:
Station Unit
InstalledC
apacity
MW
Scheduled date of
synchronizing /
commissioning
Remarks
NTPC
Kudgi TPS Stage-
I
I,I,
III
3 x 800=
2400 Unit-I Synchronization by
Oct’16. CoD by
Mar’17.
Unit-II
Synchronization by
Mar’17. CoD by
Sep’17
Unit–III Synchronization by
Jun’17.CoD by Dec’17
Telangana STPP
Phase I
2 x 800 U-I CoD May 2020
U-2 CoD Nov 2020
Pudimadaka AP 4 x 1000 52 Months from Zero
Date
85% share to AP.
Zero date yet to be finalized.
AP requested NTPC to firm up
the zero date at the earliest.
AP informed evacuation
system would be developed by
PGCIL
29th TCC: NTPC informed that the plant was envisaged with imported coal.
MoP has given directives for utilizing domestic coal. NTPC has taken up the
issue with GoAP. Principal Secretary, GoAP has written to MoC for allocation
of mines with higher grade domestic coal. Zero Date has not been firmed as
specifications are under deliberation between AP authorities.
NLC
New Thermal
Power Project
I 500 October 2017 NLC expressed concern that the
evacuation system needs to be in
place. CEA had given its
recommendation vide letter dated
10.02.2016.
CTU informed that the line to
Araliyur could only be taken up after
getting authorization from MoP.
Araliyur S/S was being developed by
TANTRASCO and was expected by
June 2018
II 500 April 2018
29th TCC: CTU informed that for evacuation LILO of Neyveli - Puducherry
and 400 kV D/C to Araliyur lines are planned. NLC had applied for LTA of
340 MW which could be managed with the LILO of Neyveli – Puducherry.
Balance 600 MW would be catered by 230 kV system of TANTRANSCO.
Sirkali TPP I, II,
III
3 x 660 From GoI approval
Unit I – 52 months
Unit II – 58 months
Unit-III – 64 months
PPA has been signed. Fuel
imported coal. Approval of
Feasibility Report was awaited
from NLC Board.
29th TCC: NLC informed that the capacity has been changed to 3 x 800 MW
and suggested that the project monitoring could be dropped from agenda and
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 48 of 107
could be taken up once the Project is firmed up. TCC agreed to drop the project
monitoring.
NPCIL
Kudankulam St-I II 1000 Unit-II:
Synchronization by
August/Sept. 2016
COD by Dec 2016
KKNPP informed that they
would approach Hon’ble CERC
for extension of availing start
up power. Extension available
upto 31.07.2016.
29th
TCC: NPCIL informed that all clearances from AERB had been received.
Unit was started and turbine was rolled and due to some minor problem in
turbine secondary system and the unit was under shutdown. Unit-II would be
synchronized in 3-4 days. COD was anticipated within 6 months.
SRPC deliberations
NPCIL informed that at 50% power level some physics experiments are to be
conducted. The results of the experiments are to be vetted by AERB. The same
experiments and the process has to be followed for 75% and 90%. This process
takes around 2-3 months, hopefully it would be expedited based on experience
of Unit-I. They were anticipating COD in early Dec 2016.
SRLDC pointed out that this power would be scheduled to Tamil Nadu and
extra backing down may be necessary. MS, SRPC clarified that the power
would be scheduled to all the beneficiaries.
Chairperson, SRPC stated that Unit-II commissioning by Dec 2016 would be
beneficial to all as the loads pickup in January.
Director (T), KPTCL pointed out that nuclear power needs to be supported and
absorbed unlike the deliberations in the TCC.
BHAVINI
Kalpakkam
(PFBR)
I 500 Synchronization by
March 2017
COD by Sep 2017
UMPP
Krishnapatnam 3960
(6 x 660)
APEPDCL and PCKL had
taken steps with their legal
counsel to expedite the hearing
before Honorable High Court
of Delhi
Cheyyur 4000 New bids would be called
19. NEW PROJECTS OF STATE SECTOR & IPP
19.1 Updated status of new projects of State sector is furnished below:
Sl
No
Name of project Located
in
Capacity in
MW
Commissioning Schedule
/Remarks
1 Rayalaseema TPS ST-IV AP 1 x 600 CoD by Dec’ 2016
2 Dr. NTTPS, Vijayawada AP 1 x 800
3 Polaki AP 4000
4 Bellary TPS U-3 KAR 1 x 700 Achieved full load on 01.03.2016.
COD by 2016-17
5 Yermarus TPS KAR 2 x 800 Unit-I: FL achieved on 29.03.2016.
Unit II: COD by 2016-17
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 49 of 107
6 Kakatiya TPP St.-II Telangana 1 x 600 COD from 24.03.2016.
Confirmation yet to be received
from Commercial Wing
7 Singareni Telangana 2 x 600 Unit I: CoD by 2016-17
Unit II: CoD by 2016-17
8 Manuguru PPP Telangana 4 x 270
9 Kothagudem TPS Phase
VII
Telangana 1 x 800
10 Damaracherla Telangana 2 x 600 +
4 x 800
19.2 Updated status of new projects of IPPs is furnished below:
Sl
No.
Name of project Located
in
Capacit
y in
MW
Commissioning Schedule /Remarks
1 Meenakshi PH-II AP 1 x 700 2017-18
Untied: 640 MW
2 East Coast Energy
Thermal
AP 2 x 660
2016-17
AP : 300 MW
3 Thermal Powertech
(TPCIL) Unit-III
AP 1 x 660
CoD : 2016-17
4 SGPL (NCC)
Krishnapatnam
AP 2 x 660
Unit I : CoD by 2016-17
Unit II: Syn. by September 2016
AP: 500 MW (firmed up PPA to be
signed).
5 Hinduja NPCL,Vizag AP 2 x 520 COD of Unit 1: 11.01.2016
COD of Unit 2: 03.07.2016
6 Coastal Energen Unit-II TN 1 x 600 COD on 15.1.2016
7 IL&FS
(ITPCL) Unit-II
TN 1 x 600 First synchronized to grid on
30.04.2016. COD from 30.04.2016
20. EMERGENCY RESTORATION SYSTEM (ERS)
20.1 Requirement of ERS had been outlined in MoP letter dated 05.12.2014. CEA vide letter
dt.18.04.2016 (Annexure-XVIII) had sought updated status on the ERS which was
communicated to the States. Status update is given below:
Transmission
Utility
Requirement
as per MoP
Existing Status/Remarks
APTRANSCO 3 Nos. ERS I – Placed at Nellore.
ERS II – received on 25.04.2016 and
would be kept at Vizag.
29th
TCC update :
APTRANSCO informed that they were
planning to drop ERS-III.
It was clarified that the requirement had
been given by MoP, and APTRANSCO
should go for the third ERS.
TSTRANSCO 1 No. 29th
TCC update : TSTRANSCO informed that tenders
had been called, and ERS would come
up in 5- 6 months time.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 50 of 107
KPTCL 2 No. 2 Nos.
KSEBL 1 No. 29th
TCC update : Tenders would be initiated in a
month’s time.
TANTRANSCO 2 Nos 29th
TCC update : Administrative approval had been
received and tenders would be floated.
PED Nil
PGCIL 4 Nos. ( 2
Nos.
additional)
2 Nos (SR
I & SR II
was having
1 No. each)
29th
TCC update : Order had been placed. Would be kept at
Vizag and Chennai. Expected by June
2017. One would be 765 kV ERS.
TCC deliberations
CEA had informed that it has been decided that all Transmission Licensees (irrespective
of ownership) would maintain ERS as mandated in CEA Regulations. All ERS locations
should be available at RLDC website to ensure availability of ERS at particular location in
a timely manner.
TANTRANSCO had enquired about status of ERS S/S which had been approved earlier
by SRPC. PGCIL had informed that that they had taken up tendering but there was no
response, ERS S/S has been dropped. ERS SS was available upto 220 kV, but 400 kV
ERS was too bulky and transportation was a problem.
TCC had noted that PGCIL should have furnished the updates in this regard since ERS
S/S was approved in SRPC after a lot of deliberations.
SRPC deliberations
20.2 Director (G & TM), APTRANSCO observed that PGCIL is having one set of ERS at
Vijayawada and Vizag. In addition APTRANSCO was having two ERS one at Nellore
and other at Vizag and hence third ERS may not be required.
20.3 Director (GM), CEA stated that a practical problem was faced in the capital city of Delhi,
when the Transmission Licensee not owning ERS was depending only on PGCIL. PGCIL
may not be able to come to the rescue every time. As per National Disaster Management
System, one should be able to deploy these ERS within two days. Even single line owners
(TBCB) had been directed to have ERS and there was an Order of CERC in this regard
also.
20.4 Chairperson, SRPC observed that Andhra Pradesh and Tamil Nadu need to have higher
number of ERS since their coastal belt was more prone to cyclones. He added that during
floods in Chennai, PGCIL ERS had come in very handy.
20.5 Director (G & TM), APTRANSCO said that they would discuss the matter with their
Management.
20.6 On a query about ERS SS, Director (O), PGCIL informed that the cost was exorbitantly
high (around Rs 400 crores). They were still trying for a smaller transformer of 100/160
MVA with minimum breakers instead of 315/500 MVA.
20.7 Chairperson, SRPC stated that as per Disaster Management plan, ERS SS may also be
required. This was basically required to run some essential services.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 51 of 107
20.8 Director (O), PGCIL said that smaller capacity transformers were still under
consideration.
20.9 Chairperson, SRPC suggested that PGCIL should go for smaller capacity transformers to
meet the objectives.
21. PROGRESS OF BUS/LINE REACTORS TO BE COMMISSIONED IN SR
21.1 Status of implementation of Bus / Line Reactors / Dynamic Compensation approved in the
Standing Committee / SRPC pending for commissioning by the SR constituents is
furnished below:
Entity Bus Name Status REMARKS
KPTCL
Hoody Received at site by August
2016
As identified in the 22nd
Standing
Committee Meeting on Power System
Planning of SR and as approved in the
4th SRPC Meeting held on 7
thJune
2007
Nelamangala By December 2016
Entity Bus Name Capacity in
MVAR
Approved
in Type Remarks
PGCIL
Vijayawada 2x125 20
th SRPC/
34th SC
Bus
Would be
Commissioned
progressively from
Sep 2016.
Vijaywada reactor
expected by July
2016.
Nagarjuna Sagar 125 21
st SRPC/
34th
SC Bus
Narendra 125 21
st SRPC/
34th SC
Bus
Hyderabad 125 21st SRPC
Gooty 125 22
nd SRPC /
36th SC
Bus
Hassan 125
36th SC
Bus
Khammam 125 Bus
Kudgi PG 125 Bus
Trivandrum 125 Bus
Nellore (Existing) 125 Bus
Yelahanka 2x63 Bus
Nellore PS on
NPS-Gooty Line
2 x 63 (37th
SC) Line
Kudgi PG–
Tumkur D/C at
each end
4 x 63 Line
Cuddapah 50 to 125 39th
SC
Thiruvalam 765
kV 2 x 240 39
th SC
APTRANSCO
Vemagiri 80 21
st SRPC/
34th
SC Bus
Commissioned in
May 2015
Vemagiri 125
Bus PO has been
placed in the Kurnool 125 Bus
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 52 of 107
21.2 Subsequently, Chairperson, SRPC vide letter dated 19.05.2016 (Annexure - XIX) had
taken up the issue regarding expediting installation of reactors.
TCC deliberations
SRLDC/SRPC Secretariat had requested all entities to expedite the reactor
commissioning since AP, Telangana and North Karnataka were facing sustained
high voltages. In the Special TCC Meeting held on 02.08.2016, it had been noted
that action on the reactors identified in 39th
SCPSPSR was yet to be taken.
APTRANSCO had suggested that Reactors could also be funded through PSDF.
TCC had stated that the proposals in this regard could be submitted to NLDC for
PSDF funding.
21.3 SRPC noted the above and requested the concerned entities to expedite the reactor
commissioning.
Kalpakka 125
36th
SC
Bus
month of June
2016 with a
delivery schedule
of 18 months.
Chittoor 125 39th
SC
Vijayawada 125 39th
SC
APTRANSCO/APGENCO
VTPS Stage IV 125 39th
SC
KPTCL Davangere 125 39
th SC
Talguppa 125 39th
SC
TANTRANSC
O
Almathy 125 39th
SC
Kaythar 125 39th
SC
TANTRANSC
O/ TANGEDCO Mettur 125 39
th SC
TSTRANSCO
Mamidipalli 125
36th
SC
Bus
LOI was ready and
awaiting PSDF
funding.
Gajwel 125 Bus
Sankarapalli 125 Bus
Mehboob Nagar 125 Bus
Malkaram 125 Bus
TSTRANSCO/
TSGENCO Srisailam LB 125
39th
SC
NPCIL Kaiga 2 x 125
Bus
Tender document
for both the
reactors under
preparation.
UPCL Udupi 2 x 125 39
th SC
Awaiting CERC
clearance for
capitalization.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 53 of 107
21.4 Dynamic Compensation (Approved in 36th
SC)
Entity Bus Name
SC
MVA
GVA /
KA
Dynamic
Compensation
(STATCOM)
Mechanically
Switched
Compensation
(MVAR) Remarks
Reactor Capacitor
PGCIL
Hyderabad 18.4/
26.5
+ 200 MVAR 2x125 1x125
Under
Tendering
Udumalpet 19.4/
28.0
+ 200 MVAR 2x125 1x125
Trichy 12.5/
18.0
+ 200 MVAR 2x125 1x125
PSDF– Installation of STATCOM by Powergrid in Northern and Southern Region
21.4.1 MS, Appraisal Committee and ED, NLDC vide letter dated 23.06.2016 (Annexure -XX)
had referred to funding of the schemes of POWERGRID under PSDF for installation of
STATCOM in Northern and Southern Region submitted by POWERGRID at an
estimated cost of Rs 367.7 crore and Rs 472.55 crore respectively. The schemes were
deliberated by the Appraisal Committee headed by Chairperson, CEA in the Meeting
held on 31.05.2016. Committee was of the view that approval of the concerned RPC
may be taken for further evaluation.
21.4.2 The issue had been deliberated in the Special TCC Meeting held on 02.08.2016.
TCC deliberations
PGCIL had stated that the Tariff (O&M expenses and other expenses) as decided by
CERC would be required to be borne by beneficiaries. In case PSDF funding is not
approved, PGCIL was willing to take up the project on its own funding. On a query on
STATCOM at Jeypore, CTU informed that STATCOM was also covered in ER scheme
and has been submitted for PSDF funding.
KPTCL had suggested that one STATCOM could be shifted to any 400 kV SS of
Bengaluru. KPTCL was suggested to kindly take up the matter with the Standing
Committee on Power System Planning.
TCC had recommended the proposal for funding through PSDF. PGCIL could take up
the project by itself in case proposal was not approved through PSDF. However, all
efforts should be made by PGCIL for PSDF funding.
SRPC deliberations
21.4.3 Director (T), KPTCL requested SRPC for diversion of one STATCOM to Bengaluru
area.
21.4.4 Director (O), PGCIL said that STATCOMs were getting firmed up, based on the studies
carried out 2 years back and hence one should go ahead with the approved locations. The
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 54 of 107
scenario had changed significantly with huge integration of renewable; and a new study
could be carried out to identify additional requirement of STATCOMs.
21.4.5 Director (T), KPTCL opined that one STATCOM was required for Bengaluru area.
21.4.6 After deliberations, SRPC approved the TCC recommendations. SRPC suggested that a
new study on STATCOM requirement could be carried out and feedback provided to the
Standing Committee. KPTCL’s request could also be considered in the Standing
Committee.
21.5 Reactive Power Planning
21.5.1 In the 5th
NPC meeting held on 08.04.2016 (MoM dated 29.04.2016), the following had
been noted:
In 4th
meeting of NPC, it was agreed that states should adopt a proactive approach in
the matter of reactive power planning, and that the provisions regarding reactive
power planning similar to those mandated in the IEGC for the CTU should be
included in the respective State Grid codes.
After detailed deliberation, it was agreed that the proposal of capacitor installation
planning by stars/entities would be referred to RPCs by PSDF Sub-Committee or
routed through RPCs by States/entities and the proposal would be vetted by the
respective RPC.
21.5.2 The status of Capacitor installation in Transco/Discoms is given below:
Utility Reactive Power Planning Voltage
level Remarks
APTRANS
CO
32 x 7.2 MVAR
4 x 14.4 MVAR
On 33 kV
side
4 x 7.2 MVAR Capacitors installed
APEPDCL Srikakulam : 5 x 2 MVAR
Vizianagaram: 2 x 2 MVAR
Visakhapatnam:5x2 MVAR
Rajahmundry:10x 2 MVAR
Eluru : 4 x 2 MVAR
33/11 kV
Level
APSPDCL April 2015 : 11 x 2 MVAR
May 2015 : 16 x 2 MVAR
July 2015 : 1 x 2 MVAR
Aug 2015 : 2 x 2 MVAR
Sep 2015 : 2 x 2 MVAR
11 kV
level
TSNPDCL 123 x 2 MVAR
118 x 2 MVAR
54 x 2 MVAR and 36 x 1 MVAR
capacitors had been installed.
TSSPDCL 221 x 2 MVAR 11 kV
level
185 x 2 MVAR erected.
KPTCL Bengaluru Tr. Zone:708.8
MVAR
12.1 kV Retendered on 19.05.2016. PO likely in
July 2016. Commissioning by Aug 2017
Bagalkot Tr. Zone :258.1
MVAR
12.1 kV 39 Capacitor Bank supplied- to be
erected. 35 nos/ 15 nos inspection raised/
to be raised.11 KV switchgear placed on
M/s MEI – delivery from last week of
July 2016
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 55 of 107
Hassan Tr. Zone :136.3
MVAR
12.1 kV 13 Capacitor Bank supplied- to be
erected. 16 nos partially supplied.
Balance 11 Nos to be supplied. 7 nos
Capacitor cell installed. Foundation
completed 22 nos.
Mysore Tr. Zone :60.9
MVAR
12.1 kV All 21 nos (2.9 MVAR) Capacitor Bank
supplied.
11 KV switchgear placed on M/s MEI
on 28.01.2016
18 Nos Capacitor Banks & 18 Nos DP
Structure started
Gulbarga Tr. Zone :98.60
MVAR
12.1 kV 17 nos (2.9 MVAR) Capacitor Bank
supplied. 17 Nos to be supplied.
Tumkur Tr. Zone :281.3
MVAR
12.1 kV
KSEBL 15 MVAR 66 kV Dropped as N/w changed. To be revised
after study.
360 MVAR New proposal to be firmed up
TANGEDC
O
34 x 2.4 MVAR 11 kV Materials received. Drawing approvals
of 18 sides were pending
36 x 2.4 MVAR 11 kV Additional – Administrative approval
accorded for Coimbatore region
16 x 2.4 MVAR 22 kV 6 x 2.4 MVAR would be installed at
Salem/Coimbatore by July 2016
51 x 2.4 MVAR 22 kV Additional – Administrative approval
accorded for Coimbatore region
7 x 24 MAVR 110 kV Works yet to be taken up
780 MVAR of capacitors at
distribution level had been
commissioned out of 1,005
MVAR capacitors planned.
21.5.3 PSDF – Funding of the schemes of the state utilities for installation of
capacitors in the state network at transmission / distribution network
21.5.3.1 MS, Appraisal Committee & ED, NLDC vide letter dated 22.06.2016 (Annexure-
XXI) had referred to the schemes of state utilities for installation of capacitors in the
State Network at transmission/distribution network for funding from PSDF. The
matter was deliberated by the Appraisal Committee during the meeting held on
31.05.2016 wherein, it was decided that assessment of capacitor requirement may be
carried out at regional level by engaging expert agency like CPRI.
21.5.3.2 The issue had been deliberated in the Special TCC Meeting held on 02.08.2016.
TCC Deliberations
TCC had recommended that a regional proposal for capacitors installation would be put
up for PSDF funding. The Study would be conducted by CPRI.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 56 of 107
SRPC deliberations
SRPC approved the recommendations of TCC. It was also agreed that all necessary
approvals would be sought from Chairperson, SRPC. The progress would be appraised
in the next meeting of SRPC.
22. OUTSTANDING DUES BETWEEN SOUTHERN AND WESTERN REGIONS
22.1 In the 31st CCM meeting, the following had been noted:
Puducherry Electricity Department vide letter dated 01.04.2016 informed that they had
received Rs 27,39,427/- from Maharashtra State Electricity Board (MSEDCL) for WR-SR
bilateral energy transactions done during October 2001 to December 2002.
Pending payments between WR& SR Constituents as on 02.06.2016 are as follows:
State Receivable from Payable to
Entity Rs Entity Rs
Andhra Pradesh /
Telengana
MPPMCL 1,21,76,270 MPPMCL Nil
Karnataka MPPMCL 13,27,208 CSPDCL 73,72,176
GUVNL 9,40,320
Kerala MPPMCL 1,21,47,260
CSPDCL 7,05,279
GUVNL 4,98,019
Tamil Nadu MPPMCL 1,17,17,268 CSPDCL 92,77,878
Puducherry GUVNL 1,02, 721 GUVNL Nil
KSEBL and TANTRANSCO had informed that they had taken up pending payment
issue with WR constituents, with a copy to SRPC / WRPC Secretariat.
SRTS II, PGCIL had stated that Rs 39,09,165 paid by MPPMCL (MPSEB) towards
50% UI charges from PTC-WR for the energy drawls during September 2002 had
been disbursed to SR constituents.
22.2 Payable amount by PGCIL (WRTS / SRTS) to SR Constituents (as on 02.06.2016)
State/UT Amount
(Rs)
Received(Rs) Paid by SRTS II
on 01.04.2016
(Rs)
Balance to
receive (Rs)
Andhra Pradesh &
Telangana
47,05,447 3,69,848 10,16,847 33,18,752
Karnataka 49,79,733 3,91,407 10,76120 35,12,206
Kerala 27,58,402 2,16,811 5,96,091 19,45,500
Tamil Nadu 47,21,994 3,71.149 10,20,423 33,30,422
Puducherry 9,24,035 72,629 1,99,684 6,51,722
Total 1,80,89,611 14,21,844 39,09,165 1,27,58,602
SR constituents were requested to take up the pending payment issue with the
concerned WR utility directly, with a copy to SRPC / WRPC Secretariat.
TCC Deliberations
SR-II, PGCIL had informed that MP, Goa & DNH had made payments and the same
had been passed on to SR constituents. The same was under process with Chhattisgarh
& Maharashtra. Gujarat and Daman & Diu had stated that they were not able to trace
the documents when the credit was passed on.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 57 of 107
PGCIL was requested to expedite the payment issue with WR-Constituents.
TN & PCKL had agreed to settle payment on net-basis (without interest component) as
an initial measure.
PCKL had stated that all accounts with KSEBL had been settled except for Rs. 1.56
Crores towards Interest Component which has to be paid by KSEBL. KSEBL &
PCKL agreed to settle the payment on net-basis (without the Interest component).
SRPC deliberations
22.3 MD, PCKL informed that total payable from KPTCL (to Kerala) was Rs 21.38 crores, while
receivable from KSEBL was Rs 24 crores (including interest component also). KSEBL had
paid them Rs 2.93 crores disallowing KPTCL’s interest component while at the same time
considering its own interest component.
22.4 CMD, KSEBL assured that they would look into this issue and settlement would be without
interest on both the sides.
22.5 Director (F), KSEBL informed that KPTCL had claimed interest of around Rs 11.44 crores.
Statement of account has already been communicated to PCKL and they were willing to sit
together and settle the payments amicably.
23. NON-AVAILING OF OCC APPROVED SHUTDOWN
23.1 In the OCC Meetings, it had been noted with concern that entities were not availing the
OCC approved shut downs as per schedule. Details of availed outages against OCC
approved shut downs are given below:
23.2 Necessary steps were requested to be initiated to adhere to schedules since it affected
ATC/TTC computations, purchase planning by states etc. All constituents had been
suggested to furnish list of availed/non availed/emergency shutdowns in the previous
month against the OCC approved dates along with the reason for non-availing by 5th
of
Entity Mar-16 Apr-16 May-16 Jun-16 Jul-16
Availed % with respect to the OCC approved outages
AP TRANSCO 44 41 35 61 43
KPTCL 9
46 50 20
KER 67 40 83 100
TANTRANSCO 53 16 7 33 35
TSTRANSCO 50 90 64 83 100
PGCIL, SR1 32 21 25 39 55
PGCIL, SR2 50 33 34 54 31
NTPC 75 33 20
NLC 100 100 100 100
NTECL 100
NPCIL 50
KPCL 100 100
PNMTC 100 100 33
KTL 100
MEPL 100
TOTAL 44 35 35 48 41
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 58 of 107
every month. SRLDC was requested to keep the record of deferred or postponed outages
(which are OCC approved) due to system constraints.
23.3 SRLDC had developed a web based outage coordination system for requisitioning the OCC
approved outages on D-3/5 basis which is available at RLDC website (http://scheduling-
srldc.org:8080/OCS/Account/Login.aspx).
TCC Deliberations
SRLDC had stated that this monitoring may not be required.
SRPC and CEA had pointed out that seriousness in Outage Planning was necessitated
especially after the Grid Disturbance and as per directives of Hon’ble Commission.
Chairperson TCC had stated that all efforts should be to comply to OCC approved dates.
After deliberations, SRLDC had stated they would continue monitoring the outages.
SRPC deliberations
SRPC noted the above.
24. SPARE ICT AND REACTOR PLACEMENT AND USAGE PROCEDURE
24.1 In the 13th
Meeting, SRPC (14.05.2010), SRPC had approved one number of 400/220 kV,
315 MVA Transformer and one number of 80 MVAR Shunt Reactor as spare for the entire
Southern Region. In Standing Committee meetings also, some of the existing Reactors
(during enhancement with higher capacity) have been recommended to be maintained as
spares. These spares ICTs and Reactors are to be maintained and used during contingency
for short period of time.
24.2 PGCIL had been requested to kindly furnish the status of spare ICTs/Reactors available in
SR. Presently, there is no ICT is available as spare. The methodology of using the spare
could be discussed and firmed up.
TCC deliberations
PGCIL had informed that as agreed in 13th
& 22nd
SRPC the following was the status:
Region Equipment Location
SR ICT Madurai (would be
reaching in Sep 2016) &
Hyderabad (was being
used at Sriperumbudur)
Reactor Vizag & Gooty (being
used at Somanhalli)
PGCIL had informed that the tariff for utilization of the spare ICT/ Reactor would be billed
to the entity utilizing the spare. It would not be claimed from other beneficiaries.
SRPC noted the above.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 59 of 107
25. IEGC RELATED ISSUES REQUIRING ATTENTION/ACTION
25.1 Automatic Demand Management Schemes
25.1.1 In line with clause 5.4.2 (d) of IEGC, Automatic Demand Management Scheme was to
have been provided by all constituents by 1st
January 2011. SRLDC & SRPC Secretariat
had repeatedly pointed out that automated scheme was to be in place to meet Regulatory
requirements.
25.1.2 In earlier Meetings, the following had been noted:
AMDS logic was finalized as OD >250 MW or 20 % of Schedule, whichever lower, for
15 minutes when frequency < 49.8 Hz.
This setting (49.8 Hz) would be reviewed in 29th
TCC for subsequent enhancement to
49.9 Hz.
25.1.3 The number of incidents satisfying the existing logic and proposed logic is given in the
table. It was recommended to migrate to IEGC limits of 49.9 Hz:
Month
Present settings Proposed settings as per IEGC
Frequency < 49.8 Hz for 15
Min. and OD = Min DSM
limit
Frequency < 49.9 Hz for 15 Min. and
OD = Min DSM limit
No of
instances
meeting the
freq. limit
No of
instances
applicable to
states
No of
instances
meeting the
freq. limit
No of instances
applicable to states
AP KAR TN
March-16 0 Nil 23 7 0 0
April-16 0 Nil 77 12 4 4
May-16 1 Nil 33 14 5 5
June-16 0 Nil 44 8 8 8
July-16 0 Nil 19 1 1 4
TCC Deliberations
SRLDC and SRPC Secretariat had suggested changing the settings to 49.9 Hz in line
with IEGC. APTRANSCO had stated till the real time SCADA is stabilized the present
set points could be maintained. TSTRANSCO had opined that the revising the set point
to 49.9 Hz was not required.
It was agreed to retain the present set points of 49.8 Hz till next TCC/SRPC.
SRPC noted the above.
25.2 UFR and df/dt reliefs
25.2.1 All States had implemented AUFR and df/dt schemes fully. SRPC vide letter dated
29.01.2016 had submitted status report duly certified by SRLDC and SRPC wrt
implementation of SCADA mapping of all constituents to Hon’ble CERC in respect of
Order dated 27.11.2015 vide Petition No. 60/MP/2014. Details of recommended,
implemented, SCADA monitorable and actual relief being realized are shown in the
Table below:
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 60 of 107
State AP TS KAR KER TN PUD SR
Recommended MW A 2782 2965 3539 1173 4176 103 14738
Implemented MW B 2782 2978 3559 1207 4544 116 15186
% B/A 100 100 101 103 109 113 103
SCADA
monitorable
MW C 1169 1898 3557 1184 3849 116 11773
% C/B 42 64 100 98 85 100 78
Average Visible
Relief in May
2016
MW E 1218 837 2556 1142 1982 94 7829
Wrt monitorable % E/C 104 44 72 96 51 81 67
Average Visible
Relief in June
2016
MW F 1117 825 2077 991 1794 91 6896
Wrt monitorable % F/C 96 43 58 84 47 78 59
25.2.2 In earlier Meeting, the following had been noted:
TSTRANSCO had informed that they had achieved about 70 % mapping.
APTRANSCO had informed that they would ensure 74 % mapping by June 2016.
SRPC had informed that in the NPC meeting it has been noted that there could be no
uniform df/dt settings. Settings for SR would be deliberated in the
Protection/Operation sub-committee Meetings. All constituents had been requested to
take steps to achieve 100 % mapping to comply with Order of Hon’ble CERC.
25.2.3 In the 5th
NPC meeting held on 8.4.2016 (refer Annexure-II), the following had been
noted:
Ensuring proper functioning of Under Frequency Relay (UFRs) and df/dt relays:
“After deliberation it was agreed that each RPC would ensure proper functioning of
UFR and df/dt relays as per the agreed procedure of the region. Actual tripping of
feeder may not be required to test the healthiness of the UFRs. It was also agreed
that RPCs would sent their comments/suggestion on preparation of procedure for
certification of healthiness of UFR and df/dt relays”.
Observation on present UFR setting by Hon’ble CERC Order dt. 27.11.2015 in
Petition No.113/MP/2014 :
“After deliberation, NPC decided that there was no need to review the setting of UFR
and df/dt in present power scenario”.
25.2.4 In the TCC Meeting the following was noted :
APTRANSCO had informed that 25 RTUs would be commissioned by Dec’2016,
and the visibility would be increased to 70 %. APTRANSCO was requested to initiate
action to improve the visibility to 100 %.
TSTRANSCO had informed that administrative approval had been received for 24
RTUs. The visibility would then improve to 100%.
TANTRANSCO was also requested to improve the visibility to 100% which is
presently at 85%.
TSTRANSCO, KPTCL & TANTRANSCO were requested to improve the relief
realization and in case required, additional feeders needed to be identified.
SRPC noted the above.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 61 of 107
25.3 Restricted Governor Mode of Operation (RGMO)/FGMO of Generating Units
25.3.1 RGMO response is being analyzed in the meetings of OCC. SLDCs were to analyze
RGMO instances posted by SRLDC for the generators in their control area and initiate
suitable action as per orders in respect of 84/MP/2015. Inadequate Response was to be
taken up with SERC (Petition No.302/MP/2013).
25.3.2 Performance of RGMO is being analyzed in the OCC. Summary of instances is given in
the Table below:
State
Hydro Thermal TOTAL
Possible
(MW)
Actual
(MW) %
Possible
(MW)
Actual
(MW) %
Possible
(MW)
Actual
(MW) %
For the incident on 14th
March 2016 (at 01:36 Hrs Frequency change from 49.99 to 49.82 Hz)
AP 5.9 1.3 22.6 145.9 110.6 75.8 151.8 112.0 74
TG 6.2 0.0 0.0 82.8 36.2 43.8 89.0 36.2 41
KAR 2.7 6.2 232.3 152.4 0.0 0.0 155.1 6.2 4
KER 9.9 12.0 121.4 0.0 0.0 9.9 12.0 121
TN 6.7 0.0 0.0 148.2 25.5 17.2 154.9 25.5 16
CGS 0.0 0.0 452.4 119.9 26.5 452.4 119.9 27
SR 31.4 19.6 62.2 981.7 292.3 29.8 1013.1 311.9 31
For the incident on 17th
April 2016 (at 01:19 hrs. frequency change from 49.99 to 49.80 Hz)
AP 188 37 19.6 0 0 187.89 36.87 19.6
KAR 181 7 3.6 16.84 18.17 108 198.17 24.77 12.5
KER 0 0 16.06 35.27 220 16.06 35.27 219.6
TG 83 50 60.3 2.96 -0.66 -22 86.24 49.52 57.4
TN 175 5 3.1 20.02 0 0 194.87 5.46 2.8
ISGS 519 87 16.7 0 0 519.47 86.54 16.7
SR 1147 186 16.2 56 53 94.5 1203 238 19.8
For the incident on 18th
May 2016 (at 17:31 hrs. frequency change from 50.05 to 50.45 Hz).
AP -104 -59 57.3 0 0 -103.6 -59.4 57.3
KAR -166 -42 25.5 -0.8 -20.1 2513 -167.1 -62.5 37.4
KER 0 0 -2.4 -11.3 471 -2.4 -11.3 470.8
TG -87 -87 100.3 0 0 -86.7 -87 100.3
TN -133 -56 42.5 -0.8 -1.4 175 -133.55 -57.83 43.3
ISGS -457 -160 35.0 0 0 -457.23 -159.93 35.0
SR -947 -405 42.8 -4 -33 820.0 -951 -438 46.1
For the incident on 9th
June 2016 (at 14:27 hrs. frequency change from 49.89 to 50.37 Hz).
AP -161 -118 73.6 -2.7 -2.7 -163.2 -120.8 74.0
KAR -171 -10 6.0 -46.5 0 0 -217.9 -10.2 4.7
KER 0 0 -13.2 -12.7 96 -13.2 -12.7 96.2
TG -75 -64 85.6 0 0 -74.8 -64 85.6
TN -132 -47 35.9 -5.8 -0.8 14 -137.8 -48.2 35.0
ISGS -433 -172 39.8 0 0 -432.6 -172 39.8
SR -971 -412 42.4 -68 -16 23.8 -1040 -428 41.2
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 62 of 107
For the incident on 13th
July 2016 (at 02:37 Hrs, frequency change from 49.98 to 49.73 Hz)
AP 143 53 37.3 0 0 142.7 53.2 37.3
KAR 54 30 56.5 9.9 33.6 339 63.7 64.0 100.5
KER 0 0 11.5 0.5 4 11.5 0.5 4.3
TG 53 53 100.2 0 0 53.0 53.1 100.2
TN 112 25 22.7 0 0 111.9 25.4 22.7
ISGS 431 185 42.9 0 0 430.7 184.6 42.9
SR 792 347 43.8 21 34 159.3 813.5 380.8 46.8
25.3.3 SRLDC vide letter dated 14.07. 2016 (Annexure-XXII) had furnished a summary of
RGMO performance of generating stations of SR during quarter-1 (April-June 2016) to
Hon’ble CERC. SRLDC vide letter dated 06.07.2016 (Annexure-XXIII) had taken up
the issue of primary response referring to NLDC letter dated 27.6.2016.
25.3.4 Regarding extension of RGMO status point to SRLDC/SLDC, the following had been
noted in the Meetings of OCC:
APTRANSCO: Upper Sileru (Cable problems) & Machkund (RTU problem) stations
yet to be extended.
TSTRANSCO: Hydro units to be extended. RGMO was enabled for KTPP St 2 Unit
but status point to be updated.
TANTRANSCO: MTPS- I & II & Hydro stations status point to be extended. Status
point of Mettur Stage III is extended to SLDC.
KPCL: All the status point (except Raichur Unit IV) had been extended to SLDC. It
was informed that these points can be extended to SRLDC also. Status points of all
hydro units like Almathy, Kadra & Gerusoppa HEPs to SLDC had been made
available but yet to be configured to SLDC. RGMO was implemented in BTPS U-3
and has been enabled.
25.3.5 Hon’ble CERC had issued Order on 23.10.2015 in respect of Petition No.
302/MP/2013 and the following was agreed in the 28th
TCC meeting:
Certification regarding declaration (DC) being in conformance with 100 % MCR
(based on CERC order) and other provisions of the Order/Regulation would be
obtained from the generators.
SRLDC would schedule up to the DC of the generators.
In real time, RGMO performance would be monitored
25.3.6 In the OCC Meetings, SRLDC had informed that in the absence of declaration certificate
from all the generators they would be restricting the schedule to the minimum of
Normative DC taking care of the Units on bar and DC declared by the station.
25.3.7 The following was noted in the TCC Meeting:
SRLDC& SRPC Secretariat had expressed concern that some of the generators were
not performing as required. SRLDC presented a summary and informed that in Kerala
& TS performance was good (nearing 100%). In TN & Central Sector it was around
40 %, in Karnataka it was varying between 5-40% while in AP it was in the range of
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 63 of 107
20-65 % Performance of Talcher Stage-II, NLY TS-II, NLY TS-I Exp, NTPL, CEPL,
IL&FS & TPCIL needed to be improved.
NTPC had stated that there was no problem with RGMO at Talcher Stage II and they
would take up the issue and ensure necessary action. NLC assured that performance
would be improved.
SRLDC had agreed to post FRC computations on its website.
SLDCs were requested to analyze RGMO/ FGMO performance of the embedded
generators. SLDCs were to present analysis of embedded generators in the OCC to
bring out more seriousness on the issue. Senior Management was requested to
allocate staff for such activities in SLDC. TSTRANSCO informed that TSSLDC was
carrying out the analysis and the same was being furnished to SRLDC/SRPC
secretariat. Efforts of TSSLDC were placed on record.
TCC had suggested that all generators should make efforts to ensure RGMO response
and status availability to SLDC/SRLDC.
SRPC deliberations
SPRC noted the above and suggested that all generators should make efforts to ensure
RGMO response and status availability to SLDC/SRLDC.
GM, SRLDC informed that FRC computations had already been posted on SRLDC
website and would be carried out regularly for future events also.
25.4 Demand Estimation for Operational Purpose (Clause 5.3 of IEGC)
25.4.1 Each SLDC was to create a mechanism and facilities to facilitate on-line demand
estimation of demand for daily operational purpose for each 15 minutes block by
01.01.2011. In this regard, following may kindly be noted as contained in Order dated
19th
December 2013 of Hon’ble CERC in Petition No. 249/250/251/MP/2012:
“We direct all STUs/SLDCs of the Northern Region, Southern Region and Eastern
Region to forecast their demand and make adequate arrangements to avoid dependence
on Unscheduled Interchange for meeting their demand or for injecting short term
surplus power, irrespective of the frequency.”
Load Forecasting tool meeting the regulatory requirement was yet to be developed by all
utilities.
25.4.2 In the OCC Meetings, it had been noted that forecast was required for RRAS and
Renewable Framework.
25.4.3 The following was noted in the TCC Meeting:
MS, SRPC had stated that this exercise was essential especially with Renewable
Framework being implemented in most of the states. Difference between forecast and
actual was being discussed in OCC and needs to be minimized. SRLDC stated that it
was a mandated item as per IEGC and was also required for Ancillary Services.
Forecast of wind generation in TN was also to be significantly improved.
TANTRANSCO had informed that forecast of NIWE and Wind Developers was having
a difference of 600- 700 MW (equivalent to 3 thermal units). Demand estimation was
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 64 of 107
quite accurate and they were in the process of procuring the software and they would be
fully equipped before next summer.
CEA had informed a seminar on load forecasting had been carried out on 25.05.2016.
A model in one state may not work in other state. MoP was willing to give the task of
load forecasting to CEA. In this model, load forecasting data and weather inputs would
be communicated to CEA and CEA would furnish the forecast to the states. Prototype
for each state would be developed. Around Rs. 2.2 Crores was envisaged for the
project and if more states show interest, it could be taken ahead.
It was agreed that a small group would be formed at SRLDC, and demand forecast
exercise would be undertaken for individual states in coordination with SLDCs.
SRLDC was entering into MoU with IMD and weather data would be integrated.
Parallely, all state entities agreed that CEA could carry out state-specific forecasting.
SLDC would submit necessary data to CEA. This would not involve any financial
commitment for the states.
25.4.4 SRPC noted the above.
25.5 Sudden Change in Demand/Frequency Excursion
25.5.1 In the earlier Meetings, violation of Clause 5.2 (j) of the IEGC Regulations had been
highlighted. No user is to cause sudden variation in its load by more than 100 MW
without prior intimation to and consent of the RLDC. Similarly no user should reduce the
generating unit output by more than 100 MW without prior intimation to and consent of
the RLDC. Necessary action is sought in respect of demand and generation management
as well as power purchases, so that clause 5.2 (j) of IEGC Regulations is not violated.
25.5.2 Constituents noted the above for compliance.
25.6 Arranging of interruptible loads in four groups
25.6.1 As per IEGC, to maintain the frequency within stipulated band and also to ensure
network security, interruptible loads are to be arranged in four groups of loads. This was
for the purpose of scheduled power cuts/load shedding, loads for unscheduled load
shedding, loads to be shed through UF relays, df/dt relays and loads to be shed under any
SPS Scheme. These loads are to be grouped in such a manner that there was no
overlapping between different groups of loads.
25.6.2 Existing schemes are not meeting Regulatory requirement fully and further action was
required in this regard.
25.6.3 Constituents noted the above for compliance.
25.7 PSS Tuning
25.7.1 3rd
Meeting of PSS tuning was held on 28.06.2015 and MoM is available at SRPC
website. PSS Study group also analyzed the Step Response Test Reports for the
generators which had furnished the reports and the recommendations had been finalized.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 65 of 107
It is kindly requested that necessary action may kindly be taken as finalized in the 3rd
meeting of PSS.
25.7.2 Following units were yet to carryout Step Response Test (PSS Tuning) and the action
plan/schedule for SRT was finalized in the 3rd
Meeting of PSS:
Entity Stations/Units
APGENCO Vijayawada TPS U 5 & U6, Lower Sileru HEP U2 to U4, Upper
Sileru HEP U1 to U4, Srisailam RB HEP U1 to U7.
AP IPPs HNPCL U 1 & U2, All gas generating stations
TSGENCO Kakatiya TPP U 2, Kothagudem TPS U5 to U8, Nagarjunasagar HEP
U1, Srisailam LB HEP U1 to U6
KPCL Raichur TPS U1 to U8, BTPS U1 & U2, Yeramarus TPP , Almathy
HEP U2 to U6, Sharavati Tail Race U1 to U4, Varahi UGPH HEP U1
to U4, Nagjheri HEP U1 to U6, Sharavathy HEP U1 to U10
KAR IPPs JSWEL U1 to U4
KSEBL Idukki HEP U1 to U6, Lower Periyar HEP U1 to U3, Sabarigiri HEP
U1 to U6
TANGEDCO NCTPS St- I U1 to 3, NCTPS St-II U1 & U2, Tuticorin TPS U1 to
U5, Mettur St-I TPS U3, Mettur St-II TPS U1, Kundah III HEP U1
to U3, Aliyar HEP U1, Kodayar I U1, Kadamparai HEP U1 to U4,
Kovil Kalappal (Gas)
TN IPPs: STCMS, Private Gas Stations
CGS NTPC, Ramagundam STPS U1 to U7, NTPC Talcher STPS St-II U 4 to U5,
NTPC Kudgi, NTPC- RGCCP, Kayamkulam 2 GTs & 1 ST, NTECL-
Vallur TPS U1 – U3, Neyveli TPS I U7 to U9, Neyveli TPS I Exp U1 &
U2, Neyveli TPS II U1 to U7, Neyveli TPS II Exp U1 & U2, (NLC & TN
JV)NTPL U1 & U2, NPCIL- KGS U1 to U4, NPCIL- MAPS U1 & U2
ISTS connected
IPPs
Simhapuri Energy Ltd (SEL) U 1 to U4, MEPL U1 & U2, , Coastal Energen
U1 & U2, IL& FS U2, Lanco Stage II & III, SGPL, Nellore
TCC deliberations
MS, SRPC had requested all entities to kindly adhere to the action plan finalized in the 3rd
PSS meeting.
SRPC noted the same.
25.8 Scheduling of Simhadri STPS Stage-I by SRLDC
25.8.1 APTRANSCO had filed a Petition in CERC in this regard and the petition was admitted
on 7th
January 2016.
25.8.2 Commission had reserved Order in the matter in respect of Petition No.291/MP/2015.
25.9 SPS related Issues
25.9.1 Implementation of additional loads for KKNPP Unit-2 SPS
25.9.1.1Unit II of Kudankulam was expected by July 2016 and all constituents thus needed to
identify feeders for the quantum envisaged as given below:
Trip
Signal AP KAR KER TN TS PUDU SR
KKNPP 116 174 91 315 132 20 848
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 66 of 107
25.9.1.2 In the OCC Meeting, it had been noted that Karnataka and Puducherry were yet to
identify loads for KKNPP Unit-2 SPS. In 121st OCC meeting a mock test for the
identified loads was proposed to be carried out in July 2016.
TCC deliberations
MS, SRPC had informed that mock test for SPS had been scheduled but could not take
place since Somanahalli link was down. However, in a couple of days, the mock test
would be taken up.
25.9.2 SPS Maintenance Protocol
25.9.2.1 In the 28th
Meeting of SRPC, SPS Maintenance Protocol to be implemented by PGCIL
was agreed. In the OCC Meetings, PGCIL had informed that Management Approval
has been received and the order may be placed on M/s Alstom.
TCC deliberations
PGCIL informed that offer of M/s ALSTOM was very costly. PGCIL suggested that
they would maintain sufficient spares and carry out maintenance by themselves.
TCC agreed for the same.
25.9.2.2 SRPC noted the above
25.10 Instantaneous Scheme for Sudden Withdrawal of Wind
25.10.1 TANTRANSCO had implemented the SPS for sudden withdrawal of Wind generation
at Udumalpet and Kayathar area and the same was in operation with effect from
27.04.2016.
25.10.2 In the Special / OCC meeting, KPTCL had also been suggested to implement
instantaneous scheme for sudden withdrawal of wind in line with TANTRANSCO.
TCC deliberations
MS, SRPC had informed that instantaneous scheme for sudden withdrawal of wind in
respect of KPTCL has been dropped in the 122nd
OCC Meeting keeping in view the
dispersed wind injection . The scheme could be reconsidered, if need arose in future.
25.11 Energy Generation data Management from Renewable Energy Sources
Monthly generation data in respect of renewal energy sources is to be submitted to CEA
with a copy to SRPC.
25.12 Pending issues in respect of NPCIL / BHAVINI Units
25.12.1 A Special Meeting on pending issues in respect of NPCIL/BHAVINI was held on 19th
May 2016 in SRPC, Bengaluru (MoM available at SRPC website). The following had
been deliberated:
Deviations of planned outages of NPCIL units
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 67 of 107
Maintenance of Units should not be planned during the period January to May of
the year in view of high demand in Southern region.
NPCIL to adhere to maintenance schedule finalized in the annual outage plan/OCC
without deviations.
Status of 2 x 125 MVAR Reactors at Kaiga GS
In view of grid requirement and time involved in procurement/commissioning of
reactors, NPCIL was recommended to take up procurement of both 125 MVAR
reactors simultaneously.
KKNPP Stage-II (2 x 1000 MW) and reactors planned were 2 x 125 MVAR
NPCIL assured that they would take up the matter with CTU regarding finalization of
reactive requirements, keeping in view no absorption by the Stage II units. Limitation
of 100-150 MVAR absorption for limited period but not on a sustained basis would
also be communicated.
Enabling of Auto Reclose feature
Kaiga-Guttur Lines
Time differentiated A/R scheme of 400 kV Kaiga- Guttur lines would be implemented
by June 2016. A/R scheme may be reviewed subsequently, in case more trippings
occur.
KPTCL was also suggested to increase patrolling and maintain ROW of the line.
Clearing of ROW was required to be taken up once before the monsoon commences
and also immediately after monsoon. Specific instructions in this regard needs to be
communicated to field staff (copy of which would be furnished to SRPC/SRLDC).
400 kV KKNPP – Madurai line
Concern of KKNPP regarding shunt reactor /PIR would be taken up with PGCIL.
Subsequently, the A/R implementation would be reviewed.
Status update on KKNPP-Tuticorin PS D/C lines would be sought from PGCIL.
All 230 kV lines emanating from MAPS
MAPS agreed to implement the A/R scheme by June 2016
All 230 kV lines emanating from BHAVINI
BHAVINI was suggested to implement A/R scheme by June 2016.
MVAR interchange at Kaiga GS and KKNPP Tap changing at Kaiga GS and KKNPP
KKNPP and KGS confirmed that they would issue specific directives to control room
to control the VAR injections above 400 kV and 220 kV, as applicable. They would
also make the control room staff aware of grid requirements and about the action to be
taken by them.
In case further restrictions are coming up with regard to MVAR absorption at KGS, it
was very imperative that KGS goes for 2x125 MVAR reactors now itself.
Pending SCADA inputs from NPCIL/BHAVINI
MAPS, KGS, KKNPP and BHAVINI to take action as deliberated in the Meeting.
Difficulties in laying OFC cable in switchyard of Kaiga GS
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 68 of 107
It was noted that in the communication meeting held on 17.5.2016, PGCIL had
informed that the issues had been resolved and the works would be completed by the
end of June 2016.
Declared Capacity (DC) revision in case of generating Unit outages/revisions
KGS, MAPS and KKNPP also felt that DC should be close to actual. Necessary
mechanism would be put in place to avoid such discrepancy.
It was noted that redundant internet connectivity needs to be ensured by NPCIL units.
Planning of Black Start Mock drill of Nuclear Power Plants
It was agreed that Black Start Restoration Procedure Mock Exercise for Nuclear
Power Plants would be co-ordinated on days of Bus Shutdown / maintenance program.
The station would take care of necessary resources required for such Mock Exercise
and co-ordinate effectively. In this regard, it was agreed to have a plant level meeting
with SRLDC and develop an internal procedure for detailing sequence of operations
required at plant level in a similar manner as was earlier done for NTPC,
Ramagundam.
Status of recommendations finalized in PSAG-14 meeting held on 16.12.2015
MAPS to complete all actionable points.
TCC deliberations
NPCIL had informed that proposal for 2x125 MVAR reactors at Kaiga had been
agreed and tenders would be called for both the reactors. Engineering details had been
worked out and tender specifications were being taken up. KPTCL had expressed that
reactors needed to be expedited since insulators were failing due to sustained high
voltages.
A/R for Kaiga-Guttur and MAPS lines would be commissioned within two months.
Hardware issues at MAPS had been addressed. Study for Kaiga-Guttur delayed A/R
had been carried out at HQ and they had confirmed in affirmative. Even the line
healthiness had also improved.
PGCIL had stated that line reactor and PIR were generally required for line lengths for
more than 200 kms. PGCIL had suggested that A/R for Kudankulam – Madurai line be
dropped for the time being.
Details of A/R scheme had been intimated to BHAVINI by NPCIL.
SRLDC had informed that Kaiga Stage-II Units were not absorbing VARs as agreed in
the special meetings. NPCIL had informed that stator core failure was experienced in
unit 3, and preliminary indications were that the failure could be attributable to the
units continuously operating on leading side. SRLDC had pointed out that all thermal
generators are same and many of the units are running continuously on leading side
and apprehensions of NPCIL needed to be viewed in larger perspective. SRLDC had
requested NPCIL to furnish the necessary details to them.
SRPC deliberations
25.12.2 Director (T), KPTCL pointed out that KPTCL was making all efforts to keep the line
healthy and all restoration works were taken earnestly. Operating the line on sustained
over voltage could lead to disruptions and also affect the reliability of evacuation from
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 69 of 107
nuclear station. He requested NPCIL to commission the two reactors at Kaiga at the
earliest.
25.12.3 Director (O), NPCIL assured of necessary action on the above points. He informed that
two reactors at Kaiga are being taken up simultaneously.
25.12.4 SRPC noted the TCC deliberations.
25.13 Un-requisitioned Power
25.13.1 Hearing of CERC on Petition No. 16/SM/2015 (Difficulty encountered in
implementation of the Commission`s order dated 5.10.2015 in Petition No.
310/MP/2014 regarding scheduling of unscheduled surplus power from the inter-
State generating stations) was heard on 23.02.2016. CERC Order is awaited.
25.13.2 Issue of URS sale had also been discussed in the OCC Meetings. MoP vide letter
dated 09.05.2016 (Annexure-XXIV) had suggested for enabling of URS sale in
order to implement the provisions of Tariff Policy, and it was requested to kindly
take necessary action.
25.14 Treatment of Bilateral short term and collective transaction in case of grid
disturbances
In the 5th
Meeting of NPC held on 08.04.2016 (refer Annexure-II), after deliberations,
NPC decided that in view of the comments received on the proposed accounting
methodology, the Working Group would meet again to arrive at consensus on the
methodology. The finalized methodology would be put up to NPC in the next Meeting
for approval.
25.15 Power swing blocking (PSB) setting in Distance relays
In the 5th
Meeting of NPC held on 08.04.2016 (refer Annexure-II), NPC while
agreeing to NRPC's opinion to have a uniform PSB setting across all regions, decided
to maintain status quo in different regions and await the report of the Consultant
appointed for implementation of the recommendations of the 'Task Force for Power
System Analysis under contingencies' before further deliberations in the matter.
25.16 Other Issues requiring kind attention of TCC / SRPC
The following issues which are being followed up in the Meetings of Sub-Committees of
SRPC merit kind attention:
It was noted that some of the units / elements were being commissioned from
retrospective dates. Recently, Kakatiya TPS Stage-II (600 MW) unit was
commissioned by TSGENCO retrospectively from 24.03.2016 and the same was
informed to SRLDC on 20.05.2016. It was noted that proper procedure for testing,
declaration of COD etc. is to be followed diligently.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 70 of 107
Hon’ble CERC had brought out CERC (Deviation Settlement Mechanism and related
matters) {Third Amendment} Regulation 2016 which was implemented with effect
from 30.05.2016. Definition of renewable rich state and deviation limits for renewable
rich states etc. have been specified for computation of charges and additional charges
for deviation. In this regard SRPC vide letter dated 30.05.2016 (Annexure-XXV) had
requested all constituents to verify the wind and solar installed capacity values which is
tabulated and furnish certified installed capacity of wind and solar in state control area
(excluding the wind/solar being scheduled by SRLDC). It was also requested that
whenever the installed capacity increases to more than 1,000 MW and more than 3,000
MW, values need to be certified and communicated to SRPC. Whenever scheduling
responsibility changes from SLDC to SRLDC the revised figures are also needed to be
certified and communicated.
Ramagundam ICT 2 is under prolonged outage from 30th
June 2015. Replacement of
this faulty 200 MVA, 400/132kV ICT with 315 MVA, 400/220kV ICT by
TSTRANSCO was agreed in 39th
Standing Committee. SRLDC vide letter dated
01.06.2016 had requested TSTRANSCO that immediate action may kindly be taken for
commissioning of the new ICT as there is continuous violation of N-1 security
constraints during peak hours due to the non-availability of the ICT, which may lead to
cascade tripping and loss of load. TSTRANSCO informed that ICT had reached site
and commissioning/erection activities had started was expected to on bars by end of
July 2016.
In the OCCM, it was noted that Ramagundam ICT 2 was expected to be
commissioned by September 2016.
N’Sagar – Cuddapah FSC 1 at Cuddapah station is under prolonged outage from 12th
March 2016 due to capacitor failure. SR-I, PGCIL had informed that rectification works
were under progress and were expected to be completed by end of July 2016.
In the OCCM, it was noted that FSC-I was rectified on 27.07.2016.
Issue of frequent tripping of Vallur- NCTPS lines due to insulator tracking and causing
heavy dip in voltages was under discussion since May 2014. NTECL has been
continuously raising the issue of regular washing of the insulator/replacement with
polymer insulators. TANTRANSCO had been requested to go for complete
replacement of the insulators with polymer insulators. Gantry insulator replacement was
to be carried out either by NTECL / PGCIL for the other lines emanating from NTECL.
In OCCM, TANTRANSCO had informed that they were planning for replacement
of some insulators from Oct’2016 in coordination with PGCIL. TANTRANSCO
was suggested (again) to go for complete replacement.
Regarding NLC TS II – NLC TSI Expn reconducting works, it was noted that end span
works were yet to be reconductored. SR-II PGCIL had informed that BOQ had been
put up for management approval.
In OCCM, PGCIL had informed that they would carry out the reconductoring
works in Dec’ 2016
Regarding implementation of URTDSM (PMU) project in SR, PGCIL had informed that
in the first phase, installation of 62 PMUs were under progress. In the Special
SCADA/communication Meeting held on 17th
May 2016, constituents/generators
expressed the difficulties being faced w.r.t . PMU installation at sites under URTDSM.
Following had been finalized after deliberations:
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 71 of 107
PGCIL to furnish detailed procedure with respect to PMU installations under
URTDSM project viz, roles and responsibilities of users, responsibility upon receipt of
equipment at location, responsibilities during the installation, O&M after installation,
handing over, mandatory spares / O&M Spares responsibility etc.
Prior communication about material supply, commissioning, installation, testing etc
would be ensured to identify Nodal Officers.
PGCIL Official should be present during material receipt and during
installation/commissioning/testing.
Equipment handing over procedure should be clearly specified.
Regarding O&M, the concerned entity would inform PGCIL regarding any issue and
in-turn PGCIL would get the issue resolved.
URTDSM status was discussed in the Special meeting held on 23.08.2016 (MOM
available on SRPC website).
Status of Video Conferencing facility at SLDCs is given below:
State Status
KER SLDC &TS SLDC Implemented
AP SLDC Would be provided at Vijayawada
by Dec 2016
KAR SLDC All equipments installed final
connectivity to be made through.
TN SLDC PO placed- would be implemented
by Oct 2016.
PUD SLDC Budget for 2016-17 not yet
finalized.
SRLDC had taken up ICT Tap optimizations studies periodically and suggested tap
change action at 765/400 kV and 400/230-220 kV SS. However, this optimization is
effective only if it is carried out upto sub transmission level. To expand optimization
study to this level, SRLDC had requested 230/110 kV, 220/110 kV, 220/66 kV, 210/130
kV transformer technical data and voltage data from SCADA for peak and off peak
scenario. Constituents which have not furnished the data in the requisite formats are
requested to please furnish the same.
SRLDC had emphasized the need for alternate path between Somanahalli and SRLDC
and requested PGCIL to ensure the redundant alternate path considering the recent
SCADA blackout for long duration due to fiber cut between Somanahalli & SRLDC.
SRLDC requested SRPC to take up the requirement with Senior Management of PGCIL
and flag the issue to TCC / SRPC. SRLDC vide letter dated 16.06.2016 (Annexure-
XXVI) has taken up the issue with POWERGRID SR- II in this regard. SRPC vide letter
dated 13.06.2016 (Annexure-XXVII) had taken up the issue of OPGW stringing works
in Karnataka enclosing SR II, PGCIL letter dated 09.06.2016. In the 121st
OCC, SR-II
PGCIL had informed that Powertel OFC redundant connectivity was available to
SRLDC.
All tripping details need to be uploaded on SRLDC web portal. Para 29 of Hon’ble
CERC Order dated 20.02.2014 in respect of Petition No.146/MP/2013 is brought to kind
attention. Non furnishing of timely tripping details would be treated as non-compliance.
Tripping information details are to be uploaded within the stipulated time frames.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 72 of 107
Information regarding Cyber Security to be furnished to Chief Engineer, DPD, CEA,
New Delhi. Report on Physical Security, other Mock Drills for CMP, Mock Drill for
Black Start Restoration to be furnished to Chief Engineer, DMLF, CEA, New Delhi.
Copy of the report is to be sent to SRPC Secretariat by e-mail.
Procedure for restoration of remotely controlled sub stations of PGCIL along with the
contact no. of the person who would take care during emergency conditions needs to be
developed and furnished to SRLDC. SR-II PGCIL had furnished the partial details in this
regard. Comprehensive procedure was yet to be developed.
In the OCC meetings, PGCIL had informed that all the Substations were manned
and mock test could be carried out at any time under intimation to RTAMC.
Auto Reclose feature was to be enabled for 220 kV Ambewadi – Ponda and Nagjheri
connected lines. Regarding Ambewadi-Ponda, KPTCL had informed that the R&M
works were going on for this line and the A/R would be covered in R&M works.
Regarding Nagjheri connected lines, KPCL had informed that numerical relays had been
received and works would to be completed by August 2016.
In the OCC meetings, it was noted that A/R for Ambewadi-Ponda has been
implemented and for Ambewadi-Xeldam, it was to be implemented.
Operation of Nagarjuna Sagar in pump mode.
In OCCM, , it was informed that NSR Tail pond was ready for commissioning and
testing was yet to be carried out. Present reservoir level was around 504.7 m and
the level required for testing was 535 m.
SRLDC had expressed concern on high loadings and N-1 violation of ICTs in TN
(Arasur, Udumalpet, Pugalur, Trichy, Madurai,), AP (Vemagiri), KAR (Somanahalli,
Mysore, Hoodi & Nelamangala) and TS (Ramagundam). It was pointed out that there
was insufficient action in controlling the loading of ICTs leading to N-1 criteria violation
in compliance of Regulation 3.1f (8) of CEA (Grid Standards) Regulations 2010 and
Regulation 3.5 a(i) of CERC Indian Electricity Grid Code Regulations 2010.
SRLDC had expressed concern about the line loading on 400 kV Gooty-Nelamangala,
Gooty-Somanahalli and Hiriyur-Nelamangala lines which were violating N-1 criteria.
RRAS generators had expressed concern that Forms AS-4 & AS-5 were not being
received by them as stipulated in Procedure. This information was sought by the
Management and by the Accounts Section to settle the bills. SRLDC had clarified that
the nodal agency (NLDC) was issuing Up/Down regulation through SRLDC. RRAS as
reason was being showed in remarks of Form “D”. The exact details of block wise
schedule were being shown for every revision and implemented schedule was available
in SRLDC website. Accordingly necessary information is already available on the
SRLDC website. Regarding details of timing and reasons for kicking in, NLDC was
preparing a monthly report and the same was being submitted to CERC which would be
shared with the constituents. Quantum conveyed by NLDC (Nodal agency) may get
changed at RLDC while scheduling due to ramp up/ ramp down rates and other pending
requisition (of beneficiaries). Thus forwarding the message to generators in real time may
not be feasible. Implementation difficulties are being faced by Nodal agency and
accordingly the Procedure would be relooked after experiencing for 6 months and this
clause could be modified.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 73 of 107
26. AUGMENTATION OF TALCHER-II TRANSMISSION SYSTEM
26.1 KSEBL vide letter dated 25th
September 2015 had stated that since all Southern states
would get benefitted with the early commissioning of Talcher-II transmission system, all
SR Constituents may jointly implead as a party in the Civil Appeal filed by TNEB before
Hon’ble Supreme Court. In the 27th
TCC meeting it was suggested that SR constituents
may jointly implead as a party in the Civil Appeal filed by TNEB in Honorable Supreme
Court.
26.2 Hon’ble Commission in its Order dated 05.11.2015 in respect of Petition No. 14/SM/2015,
in the matter of ‘Notice under Section 19 of the Electricity Act, 2003 for revocation of the
inter-State transmission licence granted to Talcher II Transmission Company Ltd.’ had
passed the Order :
‘13. In exercise of our power conferred under Section 19 (3) of the Act and Regulation 20
of the Transmission Licence Regulations notice is given to the licensee to show cause
within three months from the date of this order as to why the transmission licence granted
for the transmission project should not be revoked in terms of the provisions of Section 19
of the Electricity Act and Transmission Service Regulation as quoted above. If no
response is received within three months from the date of issue of the order, the licence
shall be deemed to have been revoked.’
26.3 In the 29th
SRPC Meeting, TANTRANSCO had stated that as discussed in earlier SRPC
meeting, all constituents had been suggested to jointly implead but no action has been
taken. They were in the process of invoking the Bank Guarantee.
27. INCLUSION OF DRAWAL OF MAHE IN REA
27.1 PED vide letter dated 11.01.2016 had informed that including the drawl of Mahe region
into REA was approved in 21st SRPC Meeting. It had been requested to arrange for ABT
compliant SEMs at both the ends.
27.2 In the 29th
SRPC Meeting the following had been noted:
Puducherry ED had informed that the S/S is owned by PED but maintained by
KSEBL and thus applying for LTA with Kerala did not arise. The communication
and the metering requirements had been established and the procedure could be
agreed at the earliest.
KSEBL had stated that in view of the ownership of the S/S by PED they would look
into the matter. The drawal visibility needed to be ensured at Kerala SLDC.
Director, KSEBL had agreed to look into this matter favorably.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 74 of 107
27.3 SRPC vide letter dated 08.07.2016 had requested the following:
Total number of interconnections between Kerala and Mahe with complete details
The Status of RTU – communication facility to SRLDC from KSEB and Mahe ends
The SEM scheme installed
The status of petition to be filed in CERC for the approval of YTC of line (s) between
Kerala and Mahe
TCC deliberations
KSEBL & PED confirmed that all the issues had been resolved.
27.4 SRPC noted the above.
28. SHARING OF TRANSMISSION CHARGES OF TRANSMISSION ASSETS OF
NATIONAL IMPORTANCE
28.1 Hon’ble Commission in its Order in Petition No. 67/TT/2015 (Sharing of Transmission
charges) had stated the following in Para 30:
“Since, these assets are proposed to be considered as assets of national importance and
all the regions are proposed to bear the transmission charges, we consider it necessary
to hear the DICs of all the regions”.
28.2 The following had been deliberated in the 29th
Meeting of SRPC:
KSEBL/TANTRANSCO had stated that the planning of this system had not been
deliberated in the Standing Committee of SR and SRPC meetings. In the present
scenario the SR constituents were unlikely to reap any benefit from this HVDC links
between NER and NR.
PGCIL had stated that Kerala and Tamil Nadu were the main beneficiaries of Raigarh
– Pugalur – Madakathara HVDC link. Hence, all the constituents should show
positive approach towards sharing of the transmission charges for the assets of
National importance.
It was agreed that Chairperson, SRPC could take up the issue and concerns of SR
constituents with Chairperson, CERC.
28.3 Subsequently, Chairperson, SRPC vide letter dated 16.03.2016 (Annexure-XXVIII) had
taken up the issue with Chairperson, CERC.
In the ROP for date of order dt.03.03.2016, the following had been stated:
‘…Accordingly, we direct that the transmission charges allowed in para 6 of this order
shall be provisionally recovered from DICs of all regions in accordance with the
provisions of Central Electricity Regulatory Commission (Sharing of Inter-State
Transmission Charges and Losses) Regulations, 2010 as amended from time to time,
subject to the final decision of the Commission in the present petition. It is further
directed that any grant/assistance received from Government of India/PSDF Fund shall
be applied to reduce the cost of the assets and consequently, the Order in Petition
No.67/TT/2015 Page 13 of 13 transmission charges of these assets. We direct PGCIL to
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 75 of 107
pursue the matter in the right earnest for early release of grant/assistance.
The matter shall be listed on 14.4.2016 for further directions.’
In the ROP for date of hearing 19.04.2016, the following had been stated:
‘………..The Commission directed the respondents, who have not filed their reply, to file
reply as a last opportunity by 29.4.2016 and the petitioner to file rejoinder, if any, by
6.5.2016. The Commission directed the parties to comply with the directions within the
timeline specified.
4. The Commission directed to list the matter on 31.5.2016 for final arguments.’
SPRC deliberations
MS, SRPC informed about ROP of Hon’ble CERC for date of hearing
05.07.2016. It could be kindly noted that submissions had been made by various
entities like GRIDCO, KSEBL etc and final Order was awaited.
29. APPROACH BEING TAKEN BY CTU FOR RESERVING THE TRANSMISSION
CAPACITY FOR THE CUSTOMERS WHO HAVE AVAILED LTA WITHOUT
IDENTIFYING BENEFICIARIES
29.1 The following was noted in the earlier Meetings of SRPC:
KSEBL had pointed out that the generators had been granted LTA with target region
about 5-6 years ago. The prospect of entering PPAs by these generators was quite
remote. Most of the generators were selling power under STOA/MTOA. Many
generators were not paying transmission charges since LTA had not been
operationalized. Basic issue was the time limit for the LTA to get operationalized and
also applicability of the transmission charges. KSEB felt that this arrangement was
blocking eligibility of other states.
CTU had stated that most of the referred generators had been granted LTA in 2009-10.
Transmission corridors were planned for them which was getting commissioned in
phases. LTA would get operationalized once the identified system is commissioned and
they would be liable to pay transmission charges. System takes around 3 -4 years to
develop. It was also pointed out that the Regulation allowed application with only
target region.
29.2 KSEBL issue was further heard on 26.04.2016 by Hon’ble CERC on Petition No.
249/MP/2015. In the ROP ( date of hearing 19.05.2016) CTU had been directed to file
minutes of SPRC meeting held during 14.3.2016 to 17.3.2016. The petition was listed for
hearing on 30.6.2016.
SRPC deliberations
29.3 MS, SRPC informed that Petition had been disposed off as KSEBL was not further
pursuing the matter.
30. STATUS OF PHASE I AND PHASE II OF PROTECTION AUDIT
RECOMMENDATIONS
30.1 Timelines given by Hon’ble CERC to various SR-Constituents for the completion of their
respective Phase-I and Phase-II works of Protection Audit recommendations are given
below:
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 76 of 107
Constituent CERC Petition
No. /Date of
Order
Date for
completion of
Phase-I
activities
Date for
completion
Phase-II
activities
Remarks
APGENCO 146/MP/2013
Date of Order:
20.02.2014
Affidavits dt:06.09.2014 & 17.09.2014
were filed on behalf of APGENCO in
CERC duly stating that the
implementation of Phase-l & Phase-II
activities of Thermal & Hydel Stations
would be completed by 31-05-2015 &
31-12-2015 respectively, pursuant to
CERC order dated 20.02.2014 against
the Petition No.146/MP/ 2013.
APGENCO vide their letter
dated 16.05.2016 informed that
a further affidavit Dt. 10-05-
2016 had been filed before
CERC on behalf of APGENCO
duly stating the status of
implementation of Phase-I and
Phase-II activities of Thermal
and Hydel Stations would be
completed by 31-07-2016 and
31-12-2017 respectively.
APTRANSCO 95/MP/2015
Date of Order:
27.04.2015
IA No. 10/2016
in Petition
95/MP/2015
Date of Order : 15.06.2016
31.12.2015
31.08.2016
31.12.2015
31.08.2016
APTRANSCO had filed an
Interlocutory Application in
Petition No. 95/MP/2015 before
Hon’ble CERC on 09.03.2016
seeking extension of time up to
31.08.2016 for completion of
Phase-I & Phase-II of Protection
Audit Recommendations.
The Commission in their final
Order dated 15.06.2016 gave
time extension up to 31.08.2016
with the following remarks:
‘Taking note of difficulty
projected by the petitioner, we
allow time to the petitioner till
31.8.2016 as a last opportunity
for completion of Phase-I and
Phase-II of protection audit
remarks failing which the
petitioner shall be liable for
proceedings under Section 142
of the Electricity Act, 2003 and
other relevant provisions.’
TSGENCO 146/MP/2013
Date of Order :
20.02.2014
TSGENCO made Affidavit dt:
16.12.2014 on status of
implementation of Phase-I and Phase-
II activities pursuant to CERC order
dated 20.02.2014 (Petition No.
146/MP/2013) and informed to
complete the above subject
work on 31.08.2015.
TSGENCO has filed an
affidavit before Hon’ble CERC
seeking further time extension
up to 31.03.2017 for
implementation of balance
activities of Phase-I and Phase-
II recommendations against the
CERC Order dated 20.02.2014
in respect of petition no:
146/MP/2013 with IA. 36/2013.
TSTRANSCO 83/MP/2015
Date of Order:
14.5.2015
31.10.2015 31.08.2016 W.r.t. Phase-I works,
TSTRANSCO informed that
more than 90% of Phase-I
activities had already been
completed, and the balance
works would also be completed
in one month time.
W.r.t. Phase-II works,
TSTRANSCO informed that
they are in the process filing an
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 77 of 107
application before CERC
seeking further time extension
up to December, 2016.
KPCL 374/MP/2014
Date of Order:
18.8.2015
265/MP/2015
Date of Order:
03.05.2016
31.10.2015
31.12.2016
31.12.2015
31.12.2016
KPCL had filed a Petition (No.
265/MP/2015) dated 29.10.2015
before Hon’ble CERC praying
to grant an extension of time up
to 30.12.2016 for completing
the Phases I and II activities.
The Commission in their final
Order dated 03.05.2016 gave
time extension up to 31.12.2016
with the following remarks:
"Taking note of difficulty
projected by the petitioner, we
allow time to the petitioner till
31.12.2016 as a last
opportunity for completion of
Phase-I and Phase-II of
protection audit remarks. If the
petitioner fails to comply with
the order, it shall be liable for
action under Section 142 of the
Electricity Act, 2003 as already
observed in our order dated
20.2.2014 in Petition No.
146/MP/2013.”
KPTCL 374/MP/2014
Date of Order :
18.8.2015
15.1.2016 15.1.2016 KPTCL filed a separate
application before CERC on
07.01.2016 seeking time
extension up to 31.05.2017.
Based on the further
communication received from
CERC through the Advocate at
New Delhi a separate petition
was filed on 08.08.2016
before CERC seeking time
extension up to 31.05.2017.
The petition is yet to be listed
for hearing by CERC.
KPTCL also informed that
attending protection audit
observations at all 220 kV and
above voltage class sub stations
is included under R&U project.
The work is awarded to M/s
ALSTOM by issuing LOA on
26.12.2015. M/s Alstom has
completed site survey, finalizing
purchase of materials. Pre
dispatch inspection of materials
at ALSTOM factory premises is
under progress. Supply of
materials and execution of
works at each substation will
start from September 2016.
KSEBL 86/MP/2014
Date of Order :
31.12.2015
31.12.2015
(excepting for
R&M works at
KSEB filed an affidavit dated
20.05.2016 before Hon’ble
CERC seeking further time
extension up to 31.11.2016 for
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 78 of 107
18.8.2015 Idduki HEP for
which time
extension is up to
31.3.2016)
completion of balance Phase-I
activities, and up to 31.12.2017
for completion of balance
Phase-II activities (except for
Idukki HEP for which the time
extension has been sought up to
31.12.2020) against the CERC
Order dated 18.08.2015 in
respect of petition no:
86/MP/2014.
TANTRANSCO 374/MP/2014
Date of Order :
18.8.2015
30.6.2016 30.11.2016 W.r.t. Phase-I works,
TANTRANSCO informed that
they are in the process filing an
application before CERC
seeking further time extension
up to March, 2017.
NPCIL (MAPS) 146/MP/2015
Date of Order :
20.02.2014
01.05.2014 01.09.2014 As per the status furnished to
SRPC, one no. of
recommendation pertaining to
providing Y-ph Line CVT’s on
the lines emanating from MAPS
at MAPS is yet to be
implemented.
30.2 From the above, it can be kindly seen that time extensions given to various Constituents
have been completed. As such, following SR-Constituents, viz., APGENCO,
APTRANSCO, TSGENCO, TSTRANSCO, KPCL, KPTCL, KSEB, NPCIL (MAPS),
Spectrum PGL, GMR Barge - Kakinada, Konaseema GPL, APGPCL Vijjeswaram Stage-I
& Stage-II), & LANCO-Kondapalli PL had been requested to kindly approach Hon’ble
CERC for obtaining further time extension for the completion of their respective pending
protection audit works.
30.3 In the TCC meeting the following was noted:
APTRANSCO had informed that maximum points were completed except Event
Loggers. REF at Bommur has been commissioned.
TSTRANSCO had informed that about 90 % of Phase-I has been completed and some
panels are under commissioning. Most of the works of Phase-II were over, some
procurement are awaited and expected to be completed by December 2016.
After hearing KSEBL’s Petition, Hon’ble CERC had sought comments of SRPC &
SRLDC which have been furnished.
TANTRANSCO had informed that they would be approaching Hon’ble CERC for time
extension up to 31.12.2016 & 31.03.2017 for Phase I & II respectively.
TCC had suggested that the entities whose time-lines had elapsed needed to approach
Hon’ble CERC for obtaining time-extension for their respective pending protection audit
works.
30.4 SRPC noted the above and requested entities to approach Hon’ble CERC for obtaining
time extension wherever required.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 79 of 107
31. GRID OPERATION
Salient Achievements
Reserve Regulatory Ancillary Services (RRAS) came in operation w.e.f. 12.04.2016.
Efforts put by KPCL to bring back three units and two lines at Sharavathy HEP
within a very short duration (almost 30 -35 days).
SRLDC had developed web based outage coordination system for requisitioning the
OCC approved outages.
KKNPP Unit-1 achieved 100 % PLF in the month of June 2016.
200 MW out of 250 MW Ananthapur Ultra Mega Power project in Andhra Pradesh
was declared on COD on 09.05.2016. NTPC was the developer of the project.
Gazuwaka HVDC Mock Exercise was successfully conducted on 23rd
July-2016.
TN had absorbed record 97.35 MU of Wind generation 16th
August 2016.
31.1 Grid events/highlights during March 2016
Andhra Pradesh met a maximum demand of 7,680 MW on 22.03.2016 which is the
maximum till date.
Kerala met a maximum demand of 3,860 MW on 28.03.2016 which is the maximum till
date.
Puducherry met a maximum demand of 352 MW on 29.03.2016 which is the maximum
till date.
Southern Region met a maximum demand of 40,899 MW on 21.03.2016 which is the
maximum till date.
Kerala met a per day maximum energy consumption of 76.43 MU on 31.03.2016 which
is the maximum till date.
Tamil Nadu met per day maximum energy consumption of 327.02 MU on 22.03.2016
which is the maximum till date.
Puducherry met a per day maximum energy consumption of 7.45 MU on 29.03.2016
which is the maximum till date.
CEA vide letter dated 04.04.2016 had informed that 2nd
Unit of Vizag TPP (2x520
MW) of M/s Hinduja Power Corporation Limited of Andhra Pradesh had achieved full
load on 31.03.2016 and declared commissioned.
Yeramarus Unit I of capacity 800 MW of KPCL achieved full load on 29.03.2016.
BTPS Unit III of Capacity 700 MW of KPCL achieved full load on 01.03.2016
Singareni - U1 of TSGENCO test synchronization was carried out on 12th
Mar 2016
achieved full load on 13.03.2016.
SR I, PGCIL vide letter dated 31.03.2016 had informed that consequent to successful
completion of Trial Operation, the following assets under “ Transmission System for
connectivity for NCC Projects, Ltd. (1320 MW) have been put under Commercial
Operation w.e.f 00:00 hrs of 22nd
March 2016 :
NCC Generation Switchyard - Nellore Pooling Station 400 kV (Quad) D/C line.
2 Nos 400 kV line bays at Nellore Pooling Station for termination of NCC
Generation Switchyard-Nellore Pooling Station 400 kV(Quad) D/C line.
Transmission charges for the above assets are payable with effect from 22nd
March 2016.
2nd
Unit stringing on existing 220 kV DC/SC line from 400/220 kV S/S
Mahadevamangalam to 220 kV S/S Palamaneru in Chittur District of ckm 57.11 was
carried out and charged on 01.03.2016 by APTRANSCO.
SR II, PGCIL vide letter dated 31.03.2016 notified that the OPGW communication
links along with associated Communication Equipment and EPABX systems (hot line
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 80 of 107
speech Communication Systems for Grid Operation) as per the list enclosed under the
project - “Fiber Optic communication System for Central Sector Sub-Stations &
Generating Stations in Southern Region” are successfully commissioned. The above
assets are put into service for commercial operation w.e.f. 31.03.2016.
400 kV Jammangudu-Kurnool D/C line was idle charged on 31st Mar 2016 by
APTRANSCO.
LILO of 400 kV Malkaram-VTPS at Suryapet was first synchronised to grid on 30th
Mar 2016 by TSTRANSCO.
220 kV D/C line from 220 KV Fabcity to 132 kV Mamidipalli SS Length of 19.972
ckm was commissioned on 31.03.2016 by TSTRANSCO.
400 kV LILO VTS-Malkaram (Ckt-I) to Suryapet SS (3.655kM) was commissioned
on 30.03.2016 by TSTRANSCO.
220/132 kV Parigi SS with 1 x 100 MVA Transformer in Rangareddy District was
commissioned on 04.03.2016 by TSTRANSCO.
220 kV SS Shapurnagar in R.R.Dis of 2 x 160 + 1 x 100 existing MVA was
augmented to a capacity of 3 x 160 MVA and was commissioned on 02.03.2016 by
TSTRANSCO.
220 kV SS Tandur in R.R.Dist 2 x 100 existing MVA was augmented to a capacity of
3 x160 MVA and commissioned on 03.03.2016 by TSTRANSCO.
220 kV SS Warangal in Warangal Dist of 1 x 130 + 2 x 100 existing MVA was
augmented to a capacity of 2 x 160 + 1 x 100 MVA and was commissioned on
06.03.2016 by TSTRANSCO.
220 kV SS Budidampadu in Khammam Dist of 2 x 100 existing MVA was
augmented capacity is 1 x 160 + 1 x 100 MVA commissioned on 10.03.2016 by
TSTRANSCO.
220 kV SS Shamshabad in R.R.Dist of 2 x 100 existing MVA was augmented to a
capacity of 3 x100 MVA and was commissioned on 12.03.2016 by TSTRANSCO.
220 kV SS Durshed in Karimnagar Dist of 2 x 160 + 1 x 100 existing MVA was
augmented to a capacity of and was 3 x 160 MVA and was commissioned on
14.03.2016 by TSTRANSCO.
220 kV SS Sadasivpet in Medak Dist of 2 x100 existing MVA was augmented to a
capacity of 1 x 160 + 1 x100 MVA and was commissioned on 18.03.2016 by
TSTRANSCO.
220 kV SS Nirmal in Adilabad dist of 2 x100 existing MVA was augmented to a
capacity of 3 x 100 MVA and was commissioned on 18.03.2016 by TSTRANSCO.
220 kV SS Jagitial in Karimnagar Dist of 2 x 100 existing MVA was augmented to a
capacity of 3 x 100 MVA and was commissioned on 19.03.2016 by TSTRANSCO.
220 kV SS Kalwakurthy in Mahaboobnagar dist of 1 x 160 + 2 x 100 existing MVA
was augmented to a capacity of 2 x 160 + 1 x 100 MVA and was commissioned on
21.03.2016 by TSTRANSCO.
220 kV SS Manuguru in Khammam dist of 1 x 160 + 2 x 100 existing MVA was
augmented to a capacity of 2 x 160 + 1 x 100 MVA and was commissioned on
31.03.2016 by TSTRANSCO.
31.2 Grid events/highlights during April 2016
Andhra Pradesh met a maximum demand of 7,740 MW on 28.04.2016 which is the
maximum till date.
Telangana met a maximum demand of 7,115 MW on 04.04.2016 which is the
maximum till date.
Karnataka met a maximum demand of 9,776 MW on 12.04.2016 which is the
maximum till date
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 81 of 107
Kerala met a maximum demand of 4,004 MW on 27.04.2016 which is the maximum
till date.
Tamil Nadu met a maximum demand of 15,240 MW on 29.04.2016 which is the
maximum till date.
Puducherry met a maximum demand of 370 MW on 23.04.2016 which is the
maximum till date.
Southern Region met a maximum demand of 41607 MW on 07.04.2016 which is the
maximum till date.
Andhra Pradesh met a per day maximum energy consumption of 169.15 MU on
28.04.2016 which is the maximum till date.
Telangana met a per day maximum energy consumption of 159.62 MU on 05.04.2016
which is the maximum till date.
Karnataka met a per day maximum energy consumption of 223.35 MU on 20.04.2016
which is the maximum till date.
Kerala met a per day maximum energy consumption of 80.44 MU on 29.04.2016
which is the maximum till date.
Tamil Nadu met per day maximum energy consumption of 345.62 MU on 29.04.2016
which is the maximum till date.
Puducherry met a per day maximum energy consumption of 7.83 MU on 22.04.2016
which is the maximum till date.
Southern Region met a per day maximum energy consumption of 962.01 MU. which
is the maximum till date
Hon’ble CERC had issued CERC (IEGC) Regulations (Fourth Amendment) 2016 on
06.04.2016.
Tamil Nadu had added 0.45 MW in windmill capacity (Private sector).
CEA vide letter dated 03.05.2016 had informed that 2nd
Unit of M/s IL & FS Tamil
Nadu Power Company Limited (ITPCL) (2 x 600 MW) in Tamil Nadu had achieved
full load on 18.04.2016 and declared commissioned.
2nd
Unit of M/s IL & FS Tamil Nadu Power Company Limited (ITPCL) (2x600 MW)
in Tamil Nadu had declared COD from 00:00 Hours of 30.04.2016.
SR I, Powergrid vide letter dated 30.04.2016 had informed that consequent to
successful completion of Trial Operation, the following assets under “Transmission
System for Ultra Mega Solar Park in Anantapur Dist, Andhra Pradesh – Part – A
(Phase –I)” have been put under Commercial Operation w.e.f 00:00 hrs of 28th
April
2016 :
1 No. 500 MVA, 400/220kV Transformer at NP Kunta Pooling Station along
with associated bays and equipment.
LILO of 400 kV Kadapa (Cuddapah) – Kolar S/C line at NP Kunta Pooling
Station.
2 Nos of 220 kV line bays at NP Kunta Pooling Station
Transmission charges for the above assets are payable with effect from 28th
April 2016.
220 kV D/C line from Jurala SS to Lower Jurala Hydro power of 22 ckm was
commissioned on 29.04.2016 by TSTRANSCO.
220 kV SS at Dichpally in Nizamabad Dist of 1 x 160 + 2 x 100 existing MVA
capacity was augmented to a capacity of 2 x 160 + 2 x 100 MVA and was
commissioned on 06.04.2016 by TSTRANSCO.
220 kV SS at Bongiri in Nalgonda Dist of 2 x 100 existing MVA capacity was
augmented to a capacity of 3 x 100 MVA and commissioned on 16.04.2016 by
TSTRANSCO.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 82 of 107
220 kV SS at Waddekothapally in Warangal Dist of 2 x 160 + 1 x 100 MVA existing
Capacity was augmented to a capacity of 3 x 160 MVA and was commissioned on
25.04.2016 by TSTRANSCO.
220 kV SS at Miryalguda in Nalgonda Dist of 2 x160 + 1 x 100 existing MVA was
augmented to a capacity is of 2 x 160 + 2 x 100 MVA and was commissioned on
26.04.2016 by TSTRANSCO.
220 kV SS at Renigunta in Chitoor Dist of 3 x 100 MVA was augmented to a capacity
of 2 x100 + 1 x 160 MVA and was commissioned on 01.04.2016 by APTRANSCO.
220 kV SS at Chinakampally in YSR Dist of 1 x 100 MVA was augmented to a
capacity of 1 x 100 + 1 x 160 MVA and was commissioned on 02.04.2016 by
APTRANSCO.
220 kV SS at Kondapally in Krishna Dist of 3 x100 MVA Capacity was augmented to
a capacity of 2 x 100 + 1 x 160 MVA and was commissioned on 25.04.2016 by
APTRANSCO.
31.3 Grid events/highlights during May 2016
Tamil Nadu had added 12 MW in windmill capacity (Private sector).
220 kV SS at Siddipet in Medak Dist of 2 x 100 existing MVA capacity was
augmented to a capacity of 1 x 160 + 2 x 100 MVA and was commissioned
on13.05.2016 by TSTRANSCO.
220 kV SS at Minpur in Medak Dist of 1 x 160 + 2 x100 existing MVA capacity was
augmented to a capacity of 2 x 160 + 1 x 100 MVA and commissioned on 14.05.2016
by TSTRANSCO.
220 kV SS at Narketpally in Nalgonda Dist of 1 x 160 + 2 x 100 MVA existing
Capacity was augmented to a capacity of 2 x 160 +1 x 100 MVA and was
commissioned on 20.05.2016 by TSTRANSCO.
220 kV SS at Warangal in Warangal Dist of 2 x 160 + 1 x 100 MVA was augmented
to a capacity is of 3 x 160 MVA and was commissioned on 26..04.2016 by
TSTRANSCO.
31.4 Grid events/highlights during June 2016
Tamil Nadu had added 6 MW in windmill capacity (Private sector) during June 2016.
SGPL vide letter dated 30.05.2016 informed that Unit I of Sembcorp Gayatri Power
Ltd (SGPL) 660 MW was synchronized with Grid at 19:26:52 Hrs on 26th
May 2016.
220 kV RTPP Chinnakampally 3rd
& 4th
circuit in YSR Dist of 121ckm was
commissioned on 16.06.2016 by APTRANSCO.
2nd
Circuit from 400 kV Gajwel to loc No 34 of 132 kV line from Gajwel to Thumki
Bolarum line of 10 ckm was commissioned on 08.06.2016 by TSTRANSCO.
220 kV SS at Budidampadu in Kammam Dist(9hrs Agricultural) of 1 x 100+1x160
existing MVA capacity was augmented to a capacity of 2 x160 MVA and
commissioned on 08.06.2016 by TSTRANSCO.
220 kV SS at Kondamallepally in Nalgonda Dist of 3 x 100 MVA existing Capacity
was augmented to a capacity of 4 x 100 MVA and was commissioned on 13.06.2016 by
TSTRANSCO.
220 kV SS at Jurala in Mehaboobnagar Dist (9 hrs Agricultural) of 2 x100 MVA
existing Capacity was augmented to a capacity is of 3 x 100 MVA and was
commissioned on 21.06.2016 by TSTRANSCO.
220 kV SS at Moulali in Ranga Reddy Dist of 2 x 80 + 1 x 50 MVA existing Capacity
was augmented to a capacity of 3 x 80 + 1 x 50 MVA and was commissioned on
22.06.2016 by TSTRANSCO.
125 MVAR Vijayawada Bus reactor – III was charged by PGCIL on 19.06.2016.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 83 of 107
NP Kunta ICT – II & III (400/220 kV, 500 MVA each) charged by PGCIL on
02.07.2016 & 11.07.2016.
Udumalpet – Pallakad SPS implemented by effect from 20.06.2016 by KSEBL.
Jammalamadugu – Kurnool commissioned on 29.06.2016 by APTRANSCO.
SR I, Power grid vide letter dated 11.07.2016 informed that consequent to successful
completion of Trial Operation, the following assets under “Transmission System for
Ultra Mega Solar Park in Anantapur Dist, Andhra Pradesh – Part – A (Phase –I)” have
been put under Commercial Operation w.e.f 00:00 hrs of 11th
July 2016 :
2 No. 500 MVA, 400/220kV Transformer at NP Kunta Pooling Station along
with associated bays and equipment.
1 no. 125 MVAR 420kV Bus Reactor along with associated bays and
equipment.
SR II, Power grid vide letter dated 22.06.2016 informed that consequent to successful
completion of Trial Operation, the following asset under transmission system
associated with “System strengthening – XX in Southern Regional Grid” have been put
under Commercial operation with effect from 00:00 hours of 22nd
June 2016:
1 X 500 MVA, 400/220/33kV ICT at Malekuttaiayur Substation along with
associated bays and equipments.
Transmission charges for the above assets are payable with effect from 22nd
June 2016.
31.5 Grid events/highlights during July 2016
220 kV DC line with Twin Moose from 400kV Urvakonda SS to 220kV Vajrakarur SS
in Ananthapur Dist of 32 ckm was commissioned on 14.07.2016 by APTRANSCO.
100 MVA capacity Transformer at 220 kV SS at Vajrakarur in Ananthapur Dist was
commissioned on 14.07.2016 by APTRANSCO.
220 kV SS at Nagjari in Chittoor Dist of 2 x 100 MVA existing Capacity was
augmented to a capacity of 3 x 100 MVA and was commissioned on 15.07.2016 by
APTRANSCO.
220 kV SS at Pedurthy in Visakapatnam Dist of 1 x 160 + 2 x 100 existing MVA was
augmented to a capacity is of 2 x 160 + 1 x 100 MVA and was commissioned on
31.07.2016 by APTRANSCO.
220 kV DC line from proposed 220kV Parigi to 220/132kV Kosigi in Mehaboobnagar
Dist of 80.092 ckm was commissioned on 4.07.2016 by TSTRANSCO.
220 kV features at 132/33kV Kosigi SS in Mehaboobnagar Dist of 1 x 100 kV ratio
capacity of 100 MVA and was commissioned on 04.07.2016 by TSTRANSCO.
SR II, PGCIL vide letter dated 01.08.2016 had informed that consequent to the
successful completion of Trial Operation, the following asset under “Common
Transmission Scheme associated with ISGS Projects in Nagapattinam / Cuddalore area
of Tamil Nadu – Part – A1 (a)” in Southern Region have been put under Commercial
Operation w.e.f 00:00 hrs of 01st August 2016 in terms of Clause 4 of CERC (Terms
and Conditions of Tariff Regulations 2014).
1x125 MVAR Bus Reactor at 400 kV Nagapattinam GIS
SR I, PGCIL vide letter dated 28.07.2016 had informed that OPGW Communication
links along with associated communication equipment under the project “Establishment
of Fiber Optic Communication System for Central Sector stations project of SR” are
successfully commissioned. These assets have been put under Commercial Operation in
terms of clause 4 of CERC(terms and Conditions of Tariff) Regulation 2014.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 84 of 107
31.6 Installation of Shunt Capacitors
Progress of installation of capacitors by the constituents during the year
2016-17 is furnished in the Table below:
(Figures in MVAR)
State Requirement
for 2016-17
Installed during the year 2016-
17
Andhra Pradesh 239.8 0
Telangana 115.20 0
Karnataka 56.31 0
Kerala 10.00 0
Tamil Nadu 51.00 0
Puducherry 16.80 0
31.7 Demand Variation (Peak Vs Off-peak)
Issue regarding large variation between minimum and maximum demands has been under
the consideration of TCC/SRPC. The issue is also being discussed in the monthly
Meetings of OCC. Following was observed with regard to the period from March 2016 to
July 2016:
Descripti
on
Minimum to Maximum Demand Variation %
Andhra
Pradesh Telangana Karnataka Kerala Tamil Nadu Puducherry
Southern
Region
March 2016
Highest 28.75 22.58 19.41 34.09 27.33 32.66 26.75
Date (Day) 29.03.2016
(Tuesday)
19.03.2016
(Saturday)
13.03.2016
(Sunday)
27.03.201
6 (Sunday)
14.03.2016(
Monday)
03.03.2016
(Thursday)
29.03.2016
(Tuesday)
Lowest 14.29 8.89 10.53 25.18 10.16 14.90 16.32
Date
(Day)
27.03.2016
(Sunday)
12.03.2016
(Saturday)
18.03.2016
(Friday)
11.03.201
6 (Friday)
27.03.2016
(Sunday)
13.03.2016
(Sunday)
03.03.2016
(Thursday)
Average 19.86 15.12 15.66 30.71 18.59 24.83 22.79
April 2016
Highest 31.81 24.23 22.73 32.87 23.37 35.43 14.14
Date
(Day)
08.04.2016
(Friday)
17.04.2016
(Sunday)
09.04.2016
(Saturday)
15.04.2016
(Friday)
11.04.2016(
Monday)
11.04.2016
(Monday)
11.04.2016
(Monday)
Lowest 9.86 11.44 12.89 24.90 9.16 13.63 5.58
Date
(Day)
06.04.2016
(Wednesday)
24.04.2016
(Sunday)
14.04.2016
(Thursday)
28.04.2016
(Thursday)
03.04.2016(
Sunday)
14.04.2016
(Thursday)
08.04.2016
(Friday)
Average 18.83 16.77 16.66 28.55 14.54 22.54 10.61
May 2016
Highest 31.67 67.12 42.34 42.80 37.65 49.70 28.43
Date
(Day)
12.05.2016
(Thursday)
06.05.2016
(Friday)
20.05.2016
(Friday)
20.05.2016
(Friday)
17.05.2016
(Tuesday)
16.05.2016
(Monday)
20.05.2016
(Friday))
Lowest 14.85 14.82 16.83 24.33 9.24 13.25 12.51
Date
(Day)
17.05.2016
(Tuesday)
07.05.2016
(Thursday)
17.05.2016
(Tuesday)
14.05.2016
(Saturday)
01.05.2016(
Sunday)
08.05.2016
(Sunday)
10.05.2016
(Tuesday)
Average 22.34 25.87 22.45 32.47 19.45 25.14 16.60
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 85 of 107
June 2016
Highest 29.96 34.90 36.82 47.26 30.31 34.63 34.78
Date
(Day)
02.06.2016
(Thursday)
07.06.2016
(Tuesday)
03.06.2016
(Friday)
30.06.2016
(Thursday)
24.06.2016
(Friday)
24.06.2016
(Friday)
30.06.2016
(Thursday)
Lowest 14.69 13.75 20.53 28.65 12.31 17.72 14.48
Date
(Day)
21.06.2016
(Tuesday)
12.06.2016
(Sunday)
05.06.2016
(Sunday)
10.06.2016
(Friday)
05.06.2016
(Sunday)
05.06.2016
(Sunday)
19.06.2016
(Sunday)
Average 19.76 22.72 27.48 37.11 20.97 26.76 21.18
July 2016
Highest 33.40 31.86 36.93 49.27 29.35 50.51 27.08
Date
(Day)
10.07.2016
(Sunday)
12.07.2016
(Tuesday)
29.07.2016
(Friday)
03.07.2016
(Sunday)
25.07.2016
(Monday)
21.07.2016
(Thursday)
01.07.2016
(Friday)
Lowest 14.92 15.95 23.08 34.29 11.56 16.24 12.15
Date
(Day)
22.07.2016
(Friday)
03.07.2016
(Sunday)
16.07.2016
(Saturday)
17.07.2016
(Sunday)
17.07.2016
(Sunday)
23.07.2016
(Saturday)
17.07.2016
(Sunday)
Average 21.60 25.14 28.71 39.21 21.38 26.90 19.81
Note: Highest &lowest figures for the month have been computed based on the daily values.
31.8 Frequency of Operation of Southern Grid
Frequency of operation of the Southern Grid for the period under review is furnished
below please:
Month
Percentage of time when frequency (Hz) was
Month
Avg.
freq.
Less
than
49.5
49.5
to
49.7
49.7
to
49.9
49.9
to
50.0
50.0
to
50.05
50.05
to
50.20
More
than
50.20
Within
IEGC
range
49.9 to
50.05
March 2016 0.00 0.00 10.79 42.66 26.84 19.56 0.15 69.50 49.99
April 2016 0.00 0.07 14.21 43.89 25.63 16.11 0.09 69.52 49.98
May 2016 0.00 0.03 7.51 39.28 30.67 22.20 0.31 69.95 50.00
June 2016 0.00 0.04 8.31 43.35 29.93 18.34 0.03 73.27 49.99
July 2016 0.00 0.00 4.58 38.70 33.52 23.11 0.08 72.22 50.01
During the period under review, caution / violation messages (Annexure- XXIX) were
issued to the constituents by SRLDC. Matter regarding overdrawal at low frequency by
some constituents is being regularly deliberated in the OCC forum. Utilities were
requested to kindly adhere to Regulations in this regard.
31.9 Reasons for demand -supply gap and its variation:
31.9.1 In 4th
Meeting of NPC held on 10.12.2015 (MoM dated 1.1.2016) the following had been
noted:
Reason for demand-supply gap needed to be clearly mentioned to reflect true picture
of power supply position in different states and also to invite attention of various
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 86 of 107
agencies including policy makers to the specific problem areas in the power sector
for suitable solution. It was requested to RPCs to advise the states in their respective
regions to intimate broad break-up of demand-supply gap due to various reasons, or
at least, the main reason(s) for demand-supply gap in each month. It was suggested
that this matter could be discussed in the OCC forum of RPCs on regular basis and
the reasons for demand-supply gap ascertained from the States therein and
communicated to CEA.
RPCs agreed to take action accordingly and furnish above information to CEA along
with the power supply position related data every month.
31.9.2 In the 29th
Meeting of SRPC, SRPC had informed that the reasons for demand-supply
gap had been sought to reflect true power supply position in the states. Only Kerala
was furnishing the information, other states/UT are kindly requested to furnish the
details along with PSP data.
TCC deliberations
MS, SRPC had stated that the information was being sought by MoP/CEA. Though
Surplus power was available, reasons for deficits such as transmission constraints,
distribution constraints, financial constraints etc needed to be elucidated.
CEA had stated that at times they are not able to furnish real reasons for shortages
whenever the same was sought by MoP. In Vidhyuth Pravah App it could be seen that
power is available and also at cheaper rate. The reasons for power not being supplied
were to be understood. States were to come forward with exact reason of demand not
met whether due to transmission or financial constraints or it being a one off incident.
Constituents were requested to kindly furnish details to SRPC Secretariat in the format
already circulated.
SRPC deliberations
31.9.3 Director (GM), CEA said that the data being furnished by SRPC for SR constituents was
very reliable. However during shortage conditions at times, MoP desired exact reason of
shortages like transmission constraint or some other financial reason etc. In certain states,
power was not being supplied due to financial limitations. Vidhyuth Pravaah App showed
power availability in different areas and consumers were raising several questions in
social media to MoP.
32. THOROUGH REVIEW OF ALL THE DRAWAL POINTS OF STATES FOR
DRAWAL COMPUTATIONS
32.1 SRPC vide letter dated 30.10.2015 had suggested a methodology for reviewing the Touch
Points for drawl computations. The issue was further discussed in the 31st CCM wherein the
following was noted:
SRPC and SRLDC would be reviewing node points for installation of SEMs as per CEA
Metering Regulations and would post the details of location ID and formulas on SRPC
website. The same was posted in the SRPC website.
The comments/feedback of the constituents was to be sent to SRPC Secretariat within
two/three weeks’ time to finalize the methodology.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 87 of 107
TCC deliberations
APTRANSCO had stated that they had furnished some comments which needed to be
considered. MS, SPRC had stated that touch points were being reviewed to have a
uniform methodology and that the comments of APTRANSCO would be taken into
consideration.
33. TPCIL REQUEST TO EXEMPT DEVIATION CHARGES
33.1 TPCIL vide letter dated 07.01.2016 had requested for to consider the event of 30.12.215
as “force majeure” during CTU system outage (ISTS) and revise the deviation account for
the week 28-Dec-15 to 03-Jan-16.
33.2 The issue was deliberated in the 31st CCM wherein it was noted a Working Group of NPC
was meeting shortly to recommend the methodology for ‘Treatment of Bilateral short term
and collective transaction in case of grid disturbances’.
33.3 In the 5th
Meeting of NPC held on 08.04.2016, it was noted that the working group would
meet again to arrive at consensus on the methodology. Finalized methodology would be
communicated put up to NPC in the next meeting for approval.
34. SCHEDULING OF NTPC RAMAGUNDAM SOLAR POWER PLANT (10 MW)
34.1 A Special Meeting was held on 17th
November 2015, to facilitate scheduling by SRLDC
and identifies certain prerequisite criteria to be ensured by NTPC. The issue is being
regularly followed up in the OCC Meetings. NTPC to kindly ensure technical/regulatory
requirement to enable scheduling by SRLDC.
TCC deliberations
NTPC had informed that they were envisaging generation from the project to Telangana
fully by swapping with some other project. Subsequently, they would approach MoP/
CEA for unallocated power.
SRPC deliberations
34.2 Regional ED, NTPC informed that any decision regarding scheduling domain would be as
per Regulations. For a small plant of 10 MW, it was not appearing feasible for two states
have a share in it. They were in discussion with Andhra Pradesh and Telangana in this
regard. Some power could be given to Andhra Pradesh from other NTPC Solar plant (NP
Kunta) while this plant could be dedicated solely to Telangana.
34.3 MS, SRPC stated that in that case, MoP may need to be approached for necessary
amendment with regard to unallocated power linked with this project.
34.4 SRPC noted the above.
35. GRID STUDY COMMITTEE (TASK- 2) AUDIT PROGRESS DETAILS
35.1 As per the MoP order dated 16.07.2014, M/s Tractebel Engineering (TE) has been
appointed as the Consultant to conduct the study/ analysis of National Grid. The terms of
reference of the Consultant are as follows:
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 88 of 107
a) To Review the status of implementation of the recommendations of the Enquiry
Committee (Task-1).
b) Carrying out actual protection audit check for 10% (76 nos.) of 762 substations across
the country to address the gaps, in consultation and collaboration with states and all
stakeholders as per present and future requirements (Task-2).
Task-1 for SR-Constituents was already completed by the first week of September, 2015.
The draft report on Task-1 prepared by the Consultant was discussed in the third Grid
Study Committee (GSC) meeting held on 18th
November, 2015. Subsequently, the
feedback of the SR-Constituents was furnished to the Consultant by the last week of
November, 2015. The final report on TASK-1 by the Consultant is expected soon.
Under Task-2, 15 Stations have been identified from SR for protection audit-check by the
Consultant. Various inputs (relating to relay settings, protection parameters, etc.) sought by
the Consultant in this regard have been collected from respective SR-Constituents, and
furnished to the Consultant. Based on the data furnished, Consultant is to provide a set of
recommended settings covering various relays for each of the 15 Stations, and to carry out
physical protection audit of the same. The audit activities proposed to be carried out by the
Consultant during audit-period would cover verification of the status of each CBs, VTs and
CTs and various interlocks in the substation, verification of the relay settings implemented,
checking the availability of Auxiliary supply, etc.
In this regard, the protection-audit of all 15 stations from SR had been completed as given
below:
Sl. No. Name of the Station Period of Audit
1 Hosur SS of PGCIL (SR-II) 9-11 December, 2015
2 Gazuwaka SS of PGCIL (SR-I) 28-30 December, 2015
3 Alamathy SS of TANTRANSCO 4-6 January, 2016
4 Tirunelveli SS pf PGCIL (SR-II) 8th,
,9th and 11
th January, 2016
5 Edamon SS of KSEB 18-20 January, 2016
6 NLC TPS-II Station 8–10 February, 2016
7 Nelamangala SS of KPTCL 8–10 February, 2016
8 Gooty SS of PGCIL (SR-I) 12th,13
th and 15
th February, 2016
9 Kurnool SS of APTRANSCO 16–18 February, 2016
10 Ramagundam STPS of NTPC 18-20 February, 2016
11 Kothagudem TPS of TSGENCO 14-16 March, 2016
12 Kaiga APS of NPCIL 4-6 April, 2016
13 Guttur SS of KPTCL 4-6 May, 2016
14 Raichur TPS of KPCL 8-10 June, 2016
15 Nagjheri HPS of KPCL 14-16 July, 2016
Draft report on Task-2 by the Consultant is awaited. Based on their audit, the Consultant
had given certain general observations w.r.t. each station, and the final set of
recommendations would be provided by M/s Tractebel Engineering in their final report on
Task-2, which is expected by September/ October, 2016.
35.2 SRPC noted the above
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 89 of 107
36. IMPLEMENTATION OF PROTECTION SUITE / PROTECTION MANAGEMENT
SYSTEM (PMS) FOR SOUTHERN REGION
36.1 In the 26th
SRPC meeting held on 20th
December, 2014 at Visakhapatnam, SRPC had
approved the proposal to procure Protection Suite (Protection Management System) that
comprises Web based management software and protection setting calculation tool through
PSDF funding. In this regard, steps have been initiated to procure Protection Suite through
PSDF funding. A total of 35 licenses would be procured for the Constituents of Southern
Region.
36.2 After obtaining approval for PSDF funding, tendering process for executing Protection Suite
would be initiated. For evaluating the technical and financial bids that would be received, a
Committee comprising members from SR- Constituents would later be constituted with
approval from Chairperson, SRPC.
TCC deliberations
TSTRANSCO had requested for inclusion of 132kV SS stating that until downstream
system is mapped it would not give complete picture. SRPC Secretariat had clarified
that system is capable of integration up to 11 kV also but manpower requirements had
been assessed up to 220 kV level and hence downstream may have to be developed by
respective entities. However, it was noted that possibility of including 132 kV SS would
be explored.
TCC had noted that presently, the proposal of PMS for PSDF funding is under
evaluation by the Appraisal Committee of PSDF.
SRPC noted the above.
37. OVER VOLTAGE RELAY (OVR) GRADINGS FOR 400 KV TRANSMISSION
LINES OF THE SOUTHERN REGION
37.1 In the past one year, a number of new 400 kV transmission lines have been added to SR
Grid in addition to reconfiguration (including LILO) works of the existing 400 kV
transmission lines. In this regard, a comprehensive exercise for OVR grading 400 kV
transmission lines of SR (existing as on March, 2016) has been carried out, and revised
OVR Gradings proposed to be adopted for these lines (along with study results) had been
circulated to all Constituents for any modifications/ omissions/ comments vide SRPC letter
dated 24.03.2016.
37.2 Final OVR gradings to be adopted for 400 kV lines after incorporating Constituents'
comments have been issued for implementation vide SRPC letter dated 18.04.2014. OVR
gradings have also been kept in SRPC website for easy reference.
37.3 In the TCC meeting, it was noted that all the Constituents had confirmed implementation of
OVR gradings as applicable to their respective systems in the 54th
meeting of PCSC held on
28th
April, 2016.
37.4 SRPC noted the above.
38. PROTECTION SYSTEM ANALYSIS GROUP (PSAG-15) MEETING HELD AT
NTPL, TUTICORIN
38.1 As decided in the 52nd
Meeting of the Protection Coordination Sub-Committee (PCSC-52)
held on 30.03.2016, a team of PSAG-15 comprising Officials from SRPC, SRLDC, PGCIL
(SRTS-II), KPTCL, and TANTRANSCO visited NTPL, Tuticorin on 12th
April, 2016 to
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 90 of 107
make an in-depth analysis of the circumstances that led to the GD’s on 14th
and 15th
March,
2016, and suggest suitable actionable measures to avoid recurrence of such incidents in
future.
38.2 The recommendations given by the Committee and their compliance by NTPL as intimated
vide their letter dated 17.05.2016 is given below:
Sl.
No.
Recommendation Action Taken by NTPL (intimated
vide their letter dated 17.05.2016)
1 a) To examine the feasibility of using
relays of different make for Main-I and
Main-II line protection on all the lines
emanating from NTPL, and implement
accordingly.
b) To examine the feasibility of providing
line differential protection on all 400 kV
lines emanating from NTPL after it is got
connected by the PGCIL’s fibre optic
back-bone.
Main I & II relays are of Siemens make
having different versions. However,
feasibility of providing different makes
for Main I & II relays with line
differential protection will be taken up
in future in consultation with PGCIL
for provision of overhead FO cable.
In this regard, PGCIL informed that as
part of the on-going project to connect
all its substations and ISGS stations
with fibre optic network, NTPL would
also be covered.
2 To consider mutual compensation factors
for distance protection at the earliest to
avoid mal-operations associated with
coupling phenomenon.
Will be carried out when lines
emanating from NTPL become
independent in July 2016, after the
CEPL – Tuticorin PS separate lines are
made ready.
3 To revise Pole Discrepancy Relay timing
from the present 2.5 sec to 1.5 sec.
Already carried out for NTPL- Coastal
line and NTPL-Pooling station feeders.
4 To perform CRM/ DCRM test on all
breakers, and take appropriate steps to
ensure their healthiness.
LC will be availed in second week of
June, 2016 for testing of breakers.
CRM and timing tests will be carried
out on breakers and results will be
compared with the commissioning
report.
5 Main-I relay in NTPL-Pooling station
feeder has mal- operated on 02 .05.2016
and the matter to be referred to OEM for
necessary action including replacement of
relays.
Main-I relay output contacts have been
changed as temporary measure in
NTPL - Tuticorin Pooling station
feeder. LC will be availed in the second
week of June, 2016 for complete testing
of Main-I Relay and the same will be
re-configured/replaced in consultation
with OEM.
6 The Distance Protection Zone-settings
adopted by NTPL at their end for NTPL-
LC will be availed in the second week
of June, 2016 for relay testing and
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 91 of 107
TTNPS and NTPL-CEPL lines have been
considered with a view to verify whether
they are in line with Ramakrishna
Committee guidelines. In this regard, the
existing Zone-settings, and new Zone-
settings calculated as per Ramakrishna
Committee general guidelines have been
made available to NTPL for adoption after
suitable examination.
implementation of resistive reaches in
Main I & II relays of both the feeders as
per recommendation.
7 To take concrete steps to commission the
second set of battery bank and battery
charger at the earliest for reliable PLCC
communication.
Procurement action is being initiated.
38.3 In the SRPC meeting, concerned entities were requested to comply with the
recommendations.
39. SPECIAL MEETING ON ISSUES RELATING TO RECENT GRID
DISTURBANCES IN GAJUWAKA – SIMHADRI - KALPAKA CORRIDOR HELD
ON 04TH
MAY, 2016 AT SRPC, BENGALURU
39.1 A Special Meeting was held on 4th
May, 2016 at SRPC Secretariat, Bengaluru to deliberate
on the issues/ factors that led to recent disturbances in Gajuwaka – Simhadri - Kalpaka
corridor which resulted in trippings of various 400 kV interconnected lines, and finally
culminated in Grid Disturbances at Gajuwaka SS (PGCIL-SRTS1), Vizag SS
(APTRANSCO), and Kalpaka SS (APTRANSCO) during 24-26 April, 2016.
The following actionable measures/steps had been finalised in the Meeting:
Line patrolling protocol & maintenance procedures to be adhered.
Insulator replacement to be carried out up to the firmed up distance.
Hot-line/ Cold-line washing of Insulators & attending to hot-spots.
Silicon Insulator Coatings.
Reducing emissions during commissioning tests of new generating units.
Ensuring supply reliability to Railway Traction network of North Coastal Andhra
Pradesh.
In addition, following protection-specific recommendations have also been given:
Provision of Line differential Protection on all 400 kV transmission lines
interconnecting Gajuwaka SS (PGCIL-STRS1), Simhadri STPP (NTPC), Kalpaka SS
(APTRANSCO), and Hinduja TPS (HNPCL).
Ensuring healthiness of PLCC & Carrier-aided communication.
Provision of GPS/ Time synchronization facility in all 220 kV & above substations/
generation switchyards in Gajuwaka – Simhadri – Kalpaka corridor.
Furnishing of tripping details in compliance of Regulation 5.2 (r) of IEGC.
39.2 In the Meeting, SRPC was appraised of the action taken by the Constituents [PGCIL (SR-I),
APTRANSCO, NTPC-Simhadri, HNPCL] (Details at Annexure-XXX). Concerned
constituents were requested to comply with the recommendations.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 92 of 107
40. SPECIAL MEETING ON PENDING PROTECTION ISSUES OF M/S KPCL HELD
ON 03.06.2016 AT SRPC, BENGALURU
40.1 A Special Meeting was held on 03rd
June 2016 in SRPC Secretariat, Bengaluru to deliberate on
pending protection issues of M/s KPCL. Certain issues were observed to be occurring
recurrently at their major generating stations such as 400/ 220 kV Raichur TPS and 220 kV
Nagjheri PH. As regards the recurring grid disturbances at Nagjheri PH, specific actionable
measures/ recommendations w.r.t. the following issues have been proposed:
Line maintenance issues
SPS Modification at Nagjheri PH
Revising GT back-up protection settings appropriately at Nagjheri PH
Putting 220 kV Nagjheri-Kodasalli lines into service
KPTCL was further recommended to actively undertake re-conductoring (with HTLS
type of conductors) of 220 kV Nagjheri – Ambewadi D/C line, 220 kV Ambewadi –
Narendra D/C line, 220 kV Nagjheri – Kodasally D/C line, 220 kV Kaiga-Kodasally
S/C line and furnish an action plan for implementing the same.
KPCL had also been recommended to undertake the following remedial measures to avoid
breaker flashovers:
Replacing all porcelain insulators with composite insulators
Carrying out hot-line water washing of all insulators on regular basis.
Applying Room Temperature Vulcanizing (RTV) Silicone high voltage insulator
coatings to all bus-connected ceramic insulators of equipment like CT, PT, CB, Isolators
etc.
To take steps to provide dedicated breaker flashover protection to all breakers at Raichur
TPS at the earliest.
Auto-Reclosure scheme implementation on all 220 kV lines emanating from Kali
Complex
Line differential protection for 400 kV Raichur-Raichur TPS line-1&2 and 400 kV
Raichur-YTPS and in future lines from Bellary pooling station to nearby generating TPS
as frequent over-reach is being observed with distance protection relays.
D.R and station event logger to be triggered with operation of Main and Back-up
protections of transmission line/ generator /bus-bar protection with proper time
synchronization for performing proper analysis.
Integrity test for Station earth mats in KPCL stations
40.2 In the meeting, SRPC was apprised of the action taken Action taken by the Constituents
(Details at Annexure-XXXI). Concerned constituents were requested to comply with the
recommendations.
41. REVIEW OF ISLANDING SCHEMES OF SOUTHERN REGION
41.1 There are four Islanding Schemes functional in the Southern Region. However, since their
implementation in 2014, number of network changes (additions/ deletions/ reconfigurations
of transmission elements & generators) have taken place in the grid.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 93 of 107
41.2 In this regard, a comprehensive exercise of reviewing existing Islanding Schemes
incorporating adverted changes has been carried out. Suitable inputs based on extensive
consultation with the concerned Constituents have been duly factored into in the process.
Document containing the reviewed Islanding Schemes along with the relevant schematics
and necessary system studies has been kept on SRPC website for easy reference.
41.3 Concerned Constituents as given below had been requested vide SRPC letter dated
18.07.2016 to kindly initiate steps to implement the reviewed Islanding Schemes by
appropriately configuring the frequency settings of the transmission lines/ ICT’s/ generators
as brought out in the document so that they get tripped at the Islanding frequency of 47.9
Hz.
Name of the
Islanding
Scheme (IS)
Constituents responsible for configuring frequency settings
Hyderabad IS
TSTRANSCO, PGCIL (SRTS-I), NTPC (Ramagundam)
Chennai IS
TANTRANSCO, TANGEDCO, PGCIL (SRTS-II) Neyveli IS
TANTRANSCO, TANGEDCO, NLC, PGCIL (SRTS-II), KSEB
Kudankulam IS
TANTRANSCO, TANGEDCO, PGCIL (SRTS-II), KSEB, CEPL,
STERLITE, IBPTL
(TANTRANSCO is requested to kindly intimate CEPL, STERLITE
and IBPTL in this regard)
TSTRANSCO, TANTRANSCO and KSEBL in their capacity as STU of their respective
states had also been requested to ensure that all island-participating generators are capable
of FGMO/ RGMO and House-load operation.
41.4 In the Meeting, SRPC was apprised of the following implementation status:
PGCIL (SR-I), PGCIL (SR-II), TANTRANSCO, TANGEDCO, and KSEB had
confirmed implementation of above islanding schemes by appropriately configuring
frequency settings of feeders/ ICT’s/ generators in their respective control areas.
NLC vide their mail dated 23.08.2016 had informed that they had implemented the
requisite frequency settings on the Pugalur feeder emanating from NLC TPS-II. The
same on Pugalur feeder emanating from NLC TPS-II Expn. would be done after
procuring a new UFR by 25.09.2016.
NTPC vide their mail dated 23.08.2016 had informed that frequency settings of the
island-forming feeders emanating from RSTPS had been carried out but with a time
delay of 100 msec (the minimum possible setting with the existing UFR’s), since
existing UFR’s did not have provision to provide for instantaneous tripping. It was also
informed that new UFR’s with provision for instantaneous tripping would be procured
and commissioned in two months time.
TSTRANSCO informed that frequency settings of the Island-forming feeders at 220 kV
& above and some at 132 kV level had been properly configured. However, on some of
the 132 kV feeders the same had been done with the minimum possible time setting
(100 msec) allowed by the UFR. It was also informed that new UFR’s with provision
for instantaneous tripping would be procured and commissioned soon on the relevant
132 kV feeders.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 94 of 107
42. PROTECTION SYSTEM ANALYSIS GROUP (PSAG-16) MEETING HELD AT
AMBEWADI SS HELD ON 18.07.2016
42.1 There was a grid disturbance at 220 kV Ambewadi SS of KPTCL on 24th
June, 2016, during
which the fault current had been observed to be fed for about 5 sec, and caused damage to
the distance relay Ponda-II line. It was also observed that the newly commissioned auto-
recloser had not operated as intended during the incident.
42.2 Accordingly, it a PSAG-16 meeting was held on 18th
July, 2016 at Ambewadi SS to
investigate the cause of delayed clearance of fault and verify the healthiness of other
protection systems in place at Ambewadi SS in the context of above grid disturbance.
42.3 The Committee after analysing the reasons for delayed fault clearance and reviewing the
status of R&U works of Ambewadi SS, finalised the following recommendations for
implementation:
Reasons for SOTF non-operation during the second fault to be investigated, and if
required, its settings shall be suitably revised for correct operation.
The settings of back-up protections (O/C & E/F relays) at Narendra and Nagjheri ends
on the Ambewadi – Narendra and Ambewadi – Nagjheri lines for a typical fault on 220
kV lines emanating from Ambewadi shall be suitably revised so that they operate with
minimum possible time allowed by their respective I-t (current-time) characteristics.
For this, the use of IDMT characteristics may be explored to be in the fitness of the
things.
To go for immediate replacement (for deteriorated conductors) / strengthening of the
existing earth-mat on war-footing basis to avoid further failure of the equipments &
interruptions of power supply to the consumers as brought out in the KPTCL report
dated 19.04.2014.
The R&U works covering LBB protection, Busbar protection, GPS provision, Main-II
protection to be completed without further delay in the time-lines stipulated by Hon’ble
CERC.
Both the buses (Bus I & Bus II) to be made operational with bus-coupler in service.
Auto-reclose feature to be provided for all 220 kV feeders emanating from Ambewadi
SS.
Line CVT’s to be provided in all three phases for all 220 kV lines
Two sets of battery-banks and chargers to be provided for both protection (220 V) and
communication (48 V) applications.
Redundancy in PLCC communication to be provided by providing two channels for
both protection and speech for each circuit.
All breakers and substation equipment to be properly maintained. CB replacement
works may be undertaken wherever required.
Care to be taken to maintain proper upkeep of substation by regularly undertaking
cutting of weeds, grass & unwanted vegetation growth, esp. in the switchyard area.
42.4 In the Meeting, SRPC was apprised of the action taken by the Constituents (Details at
Annexure-XXXII). Concerned constituents were requested to comply with the
recommendations.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 95 of 107
43. PENDING IMPLEMENTATION OF RECOMMENDATIONS OF PROTECTION
COORDINATION SUB-COMMITTEE (PCSC) OF SRPC
The recommendations given in various PCSC meetings to SR-Constituents have been
regularly sent to respective Constituents for implementation. Concerned constituents were
requested to kindly comply with the Recommendations.
In the SRPC meeting, concerned entities were requested to kindly initiate action.
44. STUDY PROGRAMME ON THE INTEGRATION OF RENEWABLE ENERGY
RESOURCES INTO THE GRID
The proposal had been discussed in the Techno-Economic sub group of PSDF on
27.05.2016. Modifications based on the observations had been communicated to the sub
group on 13.07.2016.
In the SRPC meeting, it was noted that the proposal would be placed before the Appraisal
Committee.
45. IEGC, FOURTH AMENDMENT REGULATIONS 2016- TECHNICAL MINIMUM
OF GENERATORS / COMPENSATION PROCEDURE FOR SHR & AEC
4th
Amendment to IEGC had been brought out by Hon’ble CERC in which Technical
Minimum of 55 % of MCR/IC and compensation for SHR / AEC for low unit loading had
been envisaged. Compensation Procedure (SRPC) and the Operating Procedure for RSD
(NLDC) had been deliberated in OCC/CC/Special meeting (30.05.2016) / VC (20.06.2016).
Compensation Procedure has been finalized by SRPC Secretariat and uploaded in the
website and the same would be fine tuned with feedback from other RPCs. NLDC is in the
process of finalizing the Operating Procedure for RSD.
SRPC noted the above.
46. SCHEDULING/OPERATIONAL ISSUES IN RESPECT OF NP KUNTA UMSPPS – 1
46.1 A Meeting on scheduling/operational issues in respect of NP Kunta Ultra Mega Solar
Power Project Stage – 1 (250 MW) at Ananthapur in Andhra Pradesh was held at SRPC,
Bengaluru on 02.05.2016. (MoM is available at SRPC web site).
46.2 APSLDC had given consent and is scheduling the NP Kunta UMSPPS-1 as the installed
capacity criteria of IEGC to be scheduled by SRLDC had not been met. Other actionable
points need to be ensured (as enumerated in the MoM) by the concerned entities to enable
smooth transfer of scheduling responsibility to SRLDC as and when it takes place.
46.3 SRPC noted the above.
47. COMMERCIAL COMMITTEE ISSUES
47.1 The following issues were discussed in the 31st CC meeting and brought to the attention of
SRPC/TCC.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 96 of 107
Assessment of Metering requirement
CTU, STUs and generators were to furnish assessment of SEM requirement for the next
one-year period regularly. The Assessment of Metering requirement was discussed in the
31st CCM wherein the following was noted:
CC forum had requested all Regional entities to furnish the SEM requirements to the
Committee. Sufficient spare SEMs, DCDs and accessories are also to be factored in the
projected requirement.
Issuing Reactive Energy Accounts –Erratic readings by SEM
SRLDC had informed that erratic readings in high voltage cumulative readings (used for
reactive account) were observed from December 2015 to May 2016. Abnormal readings
were detected in SEMs located at Kayathar, Thiruvalam, Karaikudi and Kochi.
CC forum had agreed to issue the reactive energy to issue the reactive energy accounts by
eliminating the erratic reading making H register value as Zero (0) for the week.
Calibration and testing of SEMs in the region
As per CEA metering regulations 2006, 18.1(a), interface meters are to be tested at least
once in 5 years. In this regard, the owners of SEMs are requested to initiate necessary
action. All the utilities were requested to furnish the database, regarding the previous
date of calibration and tests carried out, to SRLDC. PGCIL and other utilities were
requested to initiate the process of Calibration of Testing of Meters in a phased manner to
meet the regulatory requirement.
Non Availability of SEMs as per CEA metering regulations
A consolidated list of locations where SEMs were not available as per CEA Metering
Regulations is given below:
S.NO Element Non availability of
SEM
To be installed by
1 MAPS: GTs (HV side) Stand By CTU/MAPS
2 Vallur : 400kV NCTPS lines
1 & 2
Check NCTPS/CTU
3 400kV Mysore-Nelamangala
Lines 1&2
At Mysore CTU
4 400kV Hoody-Kolar Lines
1&2
Hoody KPTCL
5 400kV UPCL-Hassan line
1&2
UPCL CTU/KPTCL/UPCL
6 400kV Nelamangala-Hassan
line
Nelamangala CTU/KPTCL
7 400kV Talaguppa-Hassan
Line
Talaguppa KPTCL
8 400kV Guttur-Hiriyur lines
1&2
Both Guttur and
Hiriyur
CTU / KPTCL
9 Bonakaalu-Chillakallu lines
1&2
Bonakaalu end of 132
kV Line
TS
10 400kV Hiriyur-BTPS lines
1&2
Both Hiriyur and BTPS KPTCL
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 97 of 107
SRTS II, PGCIL had stated that irrespective of the ownership of the bay and line, the
owner of the sub-station shall install the SEM at their stations.
Forum requested that the concerned utilities (SRTS II / PGCIL, KPTCL, UPCL, TN) to
install the SEMs in the above locations immediately.
Approval of Metering Scheme for new Generation and Transmission scheme
In the 22nd and 28th CCM, it was decided that all the regional entities, new Generating
Stations and CTU have to submit the Metering Scheme for the new projects and
Substations to CCM forum for the approval at least one year in advance.
It was noted that metering scheme does not only imply installation of SEMs, but also
includes finalising the accounting philosophy. Also, since transmission projects come up
in a planned manner, SRLDC suggested that it should not be a problem for PGCIL to
estimate and submit the SEM assessment in advance.
All constituents were requested to submit the Metering scheme to SRLDC / SRPC with
the requisite documents to get it approved in the CCM of SRPC.
MEPL Metering Scheme Approval
The Commercial committee approved the metering scheme as proposed by MEPL.
Submission of C1-C4 formats for New Element Charging
As per the new NLDC procedure, complete C1-C4 format need to be submitted, soon
after successful trial operation, to declare COD.
Failure to intimate new Bay charging details to SRLDC
All the entities were requested to inform the SLDC/SRLDC and the other end utility (if
applicable) regarding the bay changing works etc., that affect commercial accounting
issues to have effective and correct accounting system.
Non-compliance/Pending Issues as per 2nd
Meeting of Nodal Officers for SEM Data
Coordination
It was noted that most of the SEM issues raised are yet to be resolved
47.2 SRPC noted the above and requested the concerned entities to comply with the actionable
points.
48. REVIVAL OF UNITS AT SHARAVATHI GENERATING STATION
It was noted that all the generating units were revived on the dates given in the table below:
Unit No. Revived Date
Unit-7 23.03.2016
Unit-6 29.03.2016
Unit-8 03.04.2016
Unit-9 28.06.2016
Unit-10 08.07.2016
Unit-3 18.07.2016
Unit-4 30-07-2016
Unit-5 26-07-2016
Unit-1 07-08-2016
Unit-2 14-08-2016
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 98 of 107
220 kV Lines status:
Lines Revived Date To be revived by
SGS-Shimoga Line-3 21.03.2016
SGS-Shimoga Line-4 26.03.2016
SGS- Talaguppa Line - 2 27.06.2016
SGS- Sirsi-1 01-08-2016
SGS- Sirsi -2 16-07-2016
SGS-Shimoga Line-1 August’2016
SGS- Talaguppa Line - 3 August’2016
SGS-Talaguppa Line - 1 August’2016
SGS- Balligave line August’2016
49. REFERENCE FROM MNRE REGARDING COMPILATION OF DATA FOR
MEETING RENEWABLE ENERGY TARGETS OF 175 GW BY 2020
MNRE/ MoP /CEA vide letters dated 02.03.2016, 22.03.2016 and 29.03.2016
respectively had communicated regarding compilation of data for meeting renewable
energy targets of 175 GW by 2020. Concerned State Utilities/Generating companies are
requested to furnish the data suggested by MNRE. SLDCs had also been requested to
coordinate and furnish the data for the generators in their control area.
Constituents noted the above.
50. PROVIDING INFORMATION REGARDING COMMISSIONING AND
DECLARATION OF COD OF POWER GENERATING UNITS
CEA letter dated 31.05.2016 (Annexure-XXXIII) had requested that all related information
for date of commissioning and commercial operating of units may kindly be informed to
OPM Division of CEA so as to update CEA reporting system / database. Information may
be arranged to be sent to the following e-mail ids.
[email protected], [email protected], [email protected] &
SRPC noted the above.
51. FORECASTING, SCHEDULING AND DEVIATION SETTLEMENT OF WIND
AND SOLAR GENERATING STATIONS AT THE STATE LEVEL
Hon’ble CERC in its Order dt.13.07.2016 in respect of Petition No. 91/MP/2014 & I.A.
No. 20/2014 had noted the following:
‘….38. The Forum of Regulators (FoR) has evolved a „Model Regulations on
Forecasting, Scheduling and Deviation Settlement of Wind and Solar Generating Stations
at the State level‟ (Model Regulations), which outlines a model for operational and
commercial management of variable RE sources. The objective of above Model
Regulations is to facilitate large-scale grid integration of solar and wind generating
stations while maintaining grid stability and security as envisaged under the Grid Code,
through forecasting, scheduling and commercial mechanism for deviation settlement of
these generators. The Model Regulations have been proposed to be applicable to all wind
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 99 of 107
and solar generators which are connected to the State grid, including those connected via
pooling stations, and selling power within or outside the State………..
……………………
40. We are of the view that the Model Regulations on Forecasting, Scheduling and
Deviation Settlement of Wind and Solar Generating Stations at the State level have been
evolved to address the issues of forecasting, scheduling and settlement of over/under
drawl of power arising out of over /under injection of power from renewable sources
which are connected to the State grid and selling power within or outside the State. The
State Electricity Regulatory Commissions are advised to implement these regulations in
letter and spirit to ensure grid integration of huge renewable resources as envisaged to be
connected to grid in next 5 to 7 years.’
SRPC noted the above.
52. SKILL PLAN FOR POWER SECTOR BASED ON THE ASSESSED SKILL GAP IN
THE SECTOR
52.1 CEA vide letter dated 04.07.2016 (Annexure-XXXIV) had informed that a Meeting on
Skill Plan for Power Sector was conducted in MoP on 01.07.2016. The main emphasis
was on the following:
The Report has to be submitted by PSSC by 10th
of July, 2016 clearly indicating the
needs of training and skill gaps in power sector.
All the data captured, analysis made and other facts in the draft skill plan have to be
validated by CEA before finalization of the Report.
52.2 Further to this, MoP vide their letter No. 7/5/2015-T&R dated 01-07-2016 had sought
information in the matter. Based on the letter of MoP a proforma has been prepared. It is
requested that the relevant information pertaining to the sector/sub-sector as per the
proforma may please be arranged to be sent to CEA at mail id [email protected].
52.3 SRPC noted the above and requested the concerned to furnish the required information
to CEA.
53. ISSUES IN OPGW STRINGING UNDER FIBRE EXPANSION PROJECT OF SR
(REFER ITEM 25.16)
53.1 PGCIL vide their letter dated 01st August 2016 (Annexure-XXXV) had stated that out of
total 5,600 km OPGW cable on POWERGRID/SEB lines in Southern Region envisaged
under Fibre Expansion Project, stringing has been completed for 5,556 km while only 44 km
is balance on KPTCL lines.
53.2 KPTCL had requested to include the following additional OPGW links during the progress
of stringing in SR on various lines :
a) Hoody-LILO of Nelamangala-Hoody to Yelahanka
b) Mysore-Hootagalli
c) Hassan-Shantigrama
d) Kolar-Hoody (POWERGRID line)
e) Hoody-HSR
f) Hoody-HAL
g) NRS-Peenya-Hebbal
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 100 of 107
53.3 KPTCL had accorded approval and communicated to the concerned TL In-Charges vide
their letter dated 20.04.2015. OPGW stringing has been completed on Kolar-Hoody,
Mysore-Hootagalli, partially completed in Hoody-LILO of Nelamangala-Hoody to
Yelahanka & Hoody-HSR lines and stringing is yet to start on the balance lines. When the
stringing on NRS- Peenya- Hebbal was taken up after due confirmation, KPTCL instructed
to suspend OPGW stringing on all the lines. POWERGRID was advised to wait for one
month by KPTCL. Since then, POWERGRID has been pursuing for resuming the stringing
to complete the project. In spite of continuous follow up at all levels POWERGRID has not
received any communication from KPTCL to commence stringing.
53.4 All the above OPGW links, being executed on KPTCL lines around Bangalore city, are
very important and have been included in Fibre Expansion project for establishing reliable
alternate communication paths not only to SRLDC, but also to facilitate communication
among the control centres of KPTCL spread across Karnataka.
53.5 SRPC took up the matter with KPTCL during the Special Meeting on 17th
June 16. During
the meeting KPTCL agreed to arrange the permission by 21.06.16 for starting the works,
but till date, there has been no permission granted by KPTCL.
53.6 Since all works are completed in the subject project except the OPGW stringing of 44 km
on KPTCL lines and the contract cannot be kept alive indefinitely, POWERGRID is
constrained to short close the contract in case KPTCL does not grant permission within one
month time and the balance works may have to be carried out by KPTCL on their own.
TCC deliberations
SR-II, PGCIL had confirmed that all the material had been returned. It was pointed out
that the contract needs to be closed.
KPTCL had agreed to grant permission once the verification of returned ground wire
was concluded.
SRPC deliberations
53.7 MS, SRPC informed that non-completion of balance of 44 kms of OPGW stringing in
KPTCL was affecting the reliable communication to SRLDC. There had been a recent
incident where both the communication links to SRLDC had failed and there was no data
availability at SRLDC. In the TCC Meeting, PGCIL had confirmed that entire removed
ground wire had been returned to KPTCL.
53.8 MD, KPTCL said that a Nodal Officer could be nominated from PGCIL side and it could
be ensured that stock of removed ground wire is taken. He assured that he would look into
this issue.
54. REPLACEMENT OF WRAP FIBRE CABLE WITH OPGW IN GOOTY-
BANGALORE & UDUMALPET-TRICHUR LINKS
54.1 PGCIL vide their letter dated 01st August 2016 (refer Annexure-XXXV) had informed
WRAP Fibre cable was installed on Gooty-Bangalore (313 km) & on Udumalpet-Trichur
(130 km) lines under SR-ULDC project in 2002 and are in operation till date. The WRAP
fibre cable is exposed to outside environment since its installation and hence developed
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 101 of 107
high signal losses. Half of the 24 fibres are available for usage and rest got damaged in
mid-span and hence not possible to rectify. Wherever it was possible, the WRAP cable has
been replaced with available OPGW. In the recent past Gooty-Bangalore link had failed
many times due to high losses/fibre breaks in mid-span. This is leading to more
maintenance problems and long downtime. The above two inter-state fibre links are very
vital and are part of back-bone fibre network for real time data communication and need to
be maintained with high availability. Since the fibre links are also completing 15 years life
by June’ 2017 and in order to ensure reliable communication, it is proposed to replace the
WRAP fibre cable of Gooty-Bangalore and Udumalpet-Trichur links with OPGW cable.
54.2 The cost implication towards OPGW laying on the above two lines would be approximately
Rs 10.0 Cr.
TCC deliberations
APTRANSCO had observed that Gooty-Bangalore wrap cable was routed through
Hindupur, which needs to be ensured now also. PGCIL had agreed for the same.
TCC had recommended the proposal of laying OPGW on the two lines for approval of
SRPC.
SRPC deliberations
SRPC approved the recommendation of TCC.
55. SUBSTATION ICT- 3 BAY EXTENSION WORKS AT OUR 400 KV MADURAI
AND TRICHY STATIONS
55.1 PGCIL vide their letter dated 01st August 2016 ( refer Annexure-XXXV) had informed
works of Extensions of 230 kV Main and Transfer Buses in TANTRANSCO Switchyard at
Checkanoorani 230 kV Station (Madurai SS) under SRSS-XXIII and Alunder 230 kV
Station (Trichy SS) under SRSS-XX are yet to be taken up by TANTRANSCO.
55.2 PGCIL is expected to commission ICT-3 at Madurai by September 2016 and at Trichy by
December 2016. TANTRANSCO may kindly expedite the aforesaid works.
TCC deliberations
SR-II, PGCIL had stated that their ICT would come up in September 2016 and as per
their information, works had not been awarded for TANTRANSCO’s scope of work.
CTU had stated that the issue of coordination and downstream network not being ready
would come into picture and charges would be required to borne as per Hon’ble
CERC’s Order.
TANTRANSCO had informed that would furnish the update in SRPC
SRPC deliberations
55.3 Chairman, TNEB assured of necessary action at their end.
56. CALIBRATION TESTING OF SEMS IN SOUTHERN REGION CALIBRATION
TESTING OF SEMS IN SOUTHERN REGION
56.1 PGCIL vide their letter dated 01st August 2016 ( refer Annexure-XXXV) had informed that
as per the CEA metering regulations 2006, Interface meters are to be tested at least once in 5
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 102 of 107
years. Calibration testing of SEMs in the region was discussed in the 31st Meeting of
Commercial Sub-Committee of SRPC held on 22.06.2016. In the said Meeting, it was
concluded that “PGCIL and other utilities were requested to initiate the process of
calibration of testing of meters in the phased manner to meet the regulatory requirement”. In
accordance with the above decision and CEA Metering Regulations, POWERGRID has
initiated the process of Calibration testing of SEMS in the region. After completion of
calibration of SEMs, POWERGRID would approach Hon’ble CERC for reimbursement of
expenditure incurred.
56.2 SRPC noted the above.
57. CONCURRENCE FOR EARLY COMMISSIONING OF 765KV WARDHA –
NIZAMABAD D/C, 400KV NIZAMABAD – DICHPALLI D/C (HTLS) AND
765/400KV NIZAMABAD GIS
57.1 PGCIL vide their letter dated 01st August 2016 ( refer Annexure-XXXV) had informed the
following :
Investment approval for 765kV Wardha – Nizamabad D/C and 400kV Nizamabad –
Dichpalli D/C (HTLS) and 765/400kV Nizamabad GIS has been accorded on 29th
Jan’2015 with commissioning schedule of 40 Months.
In the 19th
meeting of SR constituents held on 29th
Dec’2015, members have agreed for
granting LTOA of 1,000 MW to Telangana from April 2017.
To meet the power deficiency in the state of Telangana and as per the request of
Telangana, all out best efforts are being put in to the project to commission the same
ahead of schedule. It is proposed to commission the said line along with GIS substation at
Nizamabad in January/February 2017.
PGCIL had requested that the Constituents may kindly agree for the same.
TCC deliberations
TCC had recommended for early commissioning of the above assets.
SRPC deliberations
SRPC agreed with recommendation of TCC.
58. SRPC CERTIFICATION TO CLAIM ADDITIONAL ROE FOR LILO OF 400 KV
KADAPA-KOLAR S/C LINE AT NP KUNTA AND ESTABLISHMENT OF 400/220
KV SUB-STATION AT NP KUNTA
58.1 PGCIL vide their letter dated 01st August 2016 ( refer Annexure-XXXV) had informed the
following :
In the Tariff Petition No. 26/TT/2016 for LILO of 400 kV Kadapa-Kolar S/C line at
NP Kunta and establishment of 400/220 kV Sub-station at NP Kunta under
"Transmission System for Ultra Mega Solar Park in Anantapur District, Andhra
Pradesh-Part A (Phase-I)", CERC has not allowed the additional 0.5% ROE due to
non-submission of SRPC certification and suggested to re-submit along with SRPC
certification during truing up.
POWERGRID commissioned the LILO of 400 kV Kadapa -Kolar S/C line and 01 No.
500MVA ICT at NP Kunta substation in April’2016 i.e. within 12 months from date
of investment approval against CERC time line of 30 months for additional ROE.
The total power generated by APSPCL’s 1st phase 250MW solar power plant was
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 103 of 107
transmitted from POWERGRID’s ICT from day one and with commissioning of NP
Kunta substation total power generated by APSPCL’s 1st phase was connected and is
useful for the system in maintaining the grid stability.
58.2 Subsequently PGCIL vide letter dated 23.08.2016 (Annexure-XXXVI) had requested to
consider additional ROE for LILO of 400 kV Kadapa -Kolar S/C line, 03 No. 500MVA ICT
and 01 No. 125 MVAR Bus Reactor.
58.3 The following was noted in the TCC:
Additional ROE for LILO of 400 kV Kadapa -Kolar S/C line was not agreed as line
length was less than 50 kms and it was not applicable as per CERC (Terms and
Conditions of Tariff), Regulations.
PGCIL had informed that 3 ICTs were commissioned on NTPC’s schedule of power
injection of 750 MW. This system was commissioned in record time period of 7
months.
TCC had recommended for approval of SRPC stating that 03 No. 500 MVA ICT and
01 No. 125 MVAR Bus Reactor were beneficial for the regional system and
recommended for Additional ROE.
SRPC deliberations
58.4 SRPC approved the recommendations of TCC.
59. NTPC KUDGI 400/220 KV LOSSES
59.1 A meeting was held on 29.7.2016 between NTPC and KPTCL regarding NTPC Kudgi
400/220 ICT losses. The Minutes of the Meeting are enclosed as Annexure-XXXVII (Ref.
Item No.7 of 29th
SRPC meeting held on 5.3.2016).
TCC deliberations
NTPC had stated that the 400/220 kV losses were to be borne by the beneficiary (ies).
KPTCL too reiterated their stand in this regard.
MS, SRPC had clarified that the accounting would be done on outgoing feeders. 400 kV
side SEMs had been installed by NTPC. 220 kV SEMs would be installed by KPTCL.
SRPC deliberations
59.2 MD, KPTCL said that this issue had already been considered by CEA and they would go as
per decision of CEA. They had sought permission to install the energy meters and NTPC
may kindly allow them to carry out the works.
59.3 NTPC stated that they would allow KPTCL to install the energy meters.
60. NTPC SIMHADRI-II SCHEDULING ISSUES
60.1 NTPC vide letter dt.16.8.2016 (Annexure-XXXVIII) had raised issues regarding scheduling
of Simhadri II units below technical minimum on 15.8.2016.
60.2 The following was noted in the TCC Meeting:
SRPC Secretariat had pointed out that 4th
Amendment of IEGC has been brought out. It
stipulated Technical Minimum of 55 % along with compensation for deterioration in
SHR/AEC. It was clearly spelt out that the same would be implemented from the date
to be notified by Hon’ble CERC. On 14th
& 15th
August 2016 there were certain
instances of schedule being less than Technical Minimum (TM is less than even if one
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 104 of 107
unit is taken out). Schedule of 285-320 MW was given against DC of 950 MW for
more than 20 blocks. NLDC’s procedure on RRAS stipulates that the unit would not be
scheduled below TM but Simhadri II Unit (even one unit) was schedule below TM due
to triggering of Regulation down.
NTPC had stated that running the units below TM involves monetary loss but more
than that safety of equipments is also at risk. Reliability would be affected as it may
lead to frequent breakdowns.
SRLDC had stated that 15th
August was historically a low demand day. The demand of
entire country falls by 20,000-30,000 MW while SR demand falls by about 4,000 -
6,000 MW. The issue had been clearly sensitized to all the entities on 14.08.2016. TN
& Karnataka had given zero requisition to Simhadri II and as per IEGC, SRLDC had to
schedule sum of all contracted sum of requisitions of all the beneficiaries and it has to
be operationally reasonable. There was a clear cut directive from Hon’ble CERC that
incase of low demand, wind generation has to be accommodated first. A number of
Petitions are also there in this regard. On 15.08.2016, there was drop of around 20,000
MW. Due to good wind injection, TM schedule could not be maintained for Simhadri
II. Schedule was furnished suggesting NTPC that unit could be taken out if they so
desired. Simhadri II was selected since it had the highest variable cost. SRLDC had
never suggested TM from 70% to 55% and never talked about RSD. Keeping in view
that one unit would be on bar, schedule had been finalized. SRLDC had ensured that no
wind was backed down. It was not correct on the part of NTPC to expect jacked up
schedules, for commercial reasons, as being done for other 364 days in the year. In the
Grid Disturbance petition Order, it had been stated that NTPC should have complied
with directions of System Operator rather than suggesting alternate solution. Entity
needed to comply with RLDC instructions, even if the results in commercial loss etc.
As per provisions of EA the RLDC decisions are to be complied. NTPC had earlier
raised concerns of vibration when schedule was given less than 70% in Ramagundam
and NTPC was more focused on commercial issues. Aggrieved party could approach
CERC if it so desired and SRLDC would justify its stand there.
NTPC had stated that low demand scenario was well known. Operation of machines
below TM was not good for machines and in critical situation Reserve shutdown should
have been directed. No Regulator/System Operator would want machines to operate in
unsafe zone. During partial loadings, both generators and beneficiaries stand to loose.
SRLDC had referred the case of 15.08.2016, but on 14.08.2016 also schedule of 282
and 486 MW had been given.
TSGENCO had endorsed the views of NTPC and stated that whenever unit operates
below TM, oil support is required, which could lead to tube failures. They had
analyzed boiler tube failures during recent past and most of the failures were due to
maintaining the units at TM. Running the unit in non economical and non technical
zone was not advisable. Most of the generators were also of Government, and paid by
consumers and hence SRLDC needs to take an overall view.
NLC had also supported NTPC’s view and stated that for lignite fired boilers on
reduced loading, it is very difficult to maintain fireball. Maintaining 55 % loading is
very difficult and frequent shutdown is not the solution.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 105 of 107
KPTCL had stated that wind generators are must run, but in extreme contingency RE
can also be backed down by SLDCs. Time, frequency, TM, forecast of wind, certainty
of wind, need of thermal generator in coming hours etc are to be considered before
taking any generator out from the grid. SLDC are the entities who have to take such
decision and flexibility had to be given to them to take decisions in overall safety and
security of the grid.
CEA had stated that they have high regard for POSOCO as System Operator. SRPC
forum is a collective operating entity and one should not undermine the SRPC
institution. It is a collective decision to absorb wind and POSOCO is not solely
responsible to ensure that RE is must run. Collective decision of RPC is to be
implemented by POSOCO and decision of RPC cannot be different from what is
stipulated in Regulations. Principle is to be followed but the procedure has to be fair to
all.
SRPC Secretariat had enquired whether any State generator was asked to for shutdown
through SLDC as the situation was well known. Also, during the same period, some of
the other generators were given schedule higher than 70 %.
SRLDC had stated that they are taking care of merit order dispatch of only ISGS and
state generators are under purview of SLDCs. In fact SRLDC had suggested that in
case of schedule below/around TM, NTPC could generate 50-100 MW more. Also in
fact SRLDC had allowed injection of 100-150 MW more than schedule in real time. If
each action is scrutinized it would be very difficult to operate the system in real time.
NTPC had pointed out that as per Revision no 63, zero MW schedule was given for two
blocks and unrealistic schedules of 20 MW, 87 MW etc for Simhadri Stage II. During
contingency SRLDC was empowered to direct shutdown.
TANTRANSCO had stated that guidelines were required to be framed, since even
thermal generators of TN were getting affected. Many a time’s thermal generators are
running on oil support to integrate RE. TANGEDCO had informed that one 600 MW
unit shutdown costs around Rs 8 Crores.
CEA had stated that POSOCO has very rich experience in implementing TM in other
regions like Jajjhar, Gandhar etc. TM was equally distributed among generators. In
recent CERC’s Order on TN’s Petition it was clearly mentioned that TM was to be
ensured for state generators. POSOCO could approach CEA with this issue. Other Grid
Code provisions are also there, while ensuring Must Run status to RE. If the problem
persisted RLDC could approach CERC/CEA to develop a Procedure like TM/RSD etc.
SRLDC had pointed out that generators like CEPL are able to run around 50% on
sustained basis the apprehensions of generators does not appear justified. They have
gone through the Grid Code and nowhere is it mentioned that schedule is to be jacked
upto TM.
60.3 TCC had recommended that advice of CEA could be sought and CEA could be requested to
come out with guidelines which could be adopted by System Operators at RLDC/SLDC.
This would facilitate RE absorption in a well defined manner.
SRPC deliberations
60.4 GM, SRLDC appraised the forum about the situation which had led to lower schedules to
Simhadri II. Both Karnataka and Tamil Nadu had given zero requisition from Simhadri II
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 106 of 107
during night hours (02-04 hours) to accommodate wind. SRLDC had honored the schedule
of technical minimum of one unit and accordingly, schedules were finalized for Simhadri II.
Even during that period, SRLDC allowed Simhadri II to inject more than the schedule. Out
of 365 days, if for one day, lower schedules are given and the actions of RLDC are
analyzed it would become very difficult to operate the grid. It can be seen from the media
reports that not even a single unit of wind has been backed down in SR due to efforts of
SRLDC. He stated that it could take 3-4 months in case the matter is referred to CEA.
60.5 MS, SRPC suggested that CEA may be approached for getting general principle / statutory
advise.
60.6 Director (GM), CEA said that Chairperson, SRPC in his opening remarks had given very
good guidance. He had stated that renewable were not state/regional resources rather they
were national resources. They should be optimally utilized as national asset. Earlier, Tamil
Nadu was doing its best to maximize wind absorption and now SRLDC is also making
efforts to maximize wind integration. A long term solution with national approach is
required to have clarity on the roles and the responsibilities of various entities.
60.7 Chairperson, SRPC said that while advice of CEA could be sought, preference should be for
wind. In Tamil Nadu, units were being shutdown to absorb the wind since wind power had
become cheap and had other associated benefits. In real time grid operation, SRLDC had the
last call on the matter.
60.8 After deliberations, it was agreed that CEA’s advice would be sought for smoother
facilitation of renewable integration.
61 20-YEAR (2016-36) PERSPECTIVE TRANSMISSION PLAN REPORT
61.1 CEA vide letter dated 29.02.2016 had issued a consolidated perspective report on
Transmission System Requirement for the next 20 years. The report has two parts ie., Part-
A : ‘Advance National Transmission Plan for 2021-22’ and Part-B : ‘Perspective
Transmission Requirement for 2022-36’. Following are the highlights in SR context:
Report (Part-A) on Advance National Transmission Plan for Year 2021-22
SR load is expected to be around 60,120 MW by 2021-22.
Generation addition in SR considered for study was around 29,290 MW (Coal), 1,500
(Nuclear) and 236 MW (Hydro) for the period November 2015-2022.
Deficit may be around 4,872 MW (Q1), 4,732 MW (Q2), 3,662 MW (Q3) and 6,748
MW (Q4). During analysis for sensitivity of 5% generation not available in SR the
deficit may go up to 7,930 MW.
Minutes of the 30th SRPC Meeting held on 27th August 2016 Page 107 of 107
Above analysis and studies indicate that major high capacity transmission corridors
that have already been planned and which are under implementation would be
sufficient to meet import/export of power among various regions in the year 2021-22.
This is based on the assumptions of load growth and generation capacity addition as
stated in this report.
State Transmission Utilities (STU) need to take up planning and implementation of
their respective intra-state systems and its interconnection with ISTS matching with
the schedule of implementation of various ISTS schemes.
Report on Perspective Transmission Requirements for 2022-36
SR Demand could be around 98,210 MW (2026-27), 1,46,700 MW (2031-32) and
2,03,400 MW (2035-36).
SR Generation capacity could be around 1,90,878 MW (2026-27), 2,58,927 MW
(2031-32) and 3,26,548 MW (2035-36).
SR would be importing around 16,200 MW (2026-27), 30,100 MW (2031-32) and
47,700 MW (2035-36).
Transmission corridor capacity requirements have been worked out based on advance
estimates of peak load demand and preliminary assessment of region-wise generation
addition possibility of next 20 years. It is seen that massive transmission corridors may
be needed towards Northern and Southern regions. There is need to enhance hydro
generation capacity in Northern and Southern regions to lessen this massive
transmission system.
It is seen that the renewable energy sources contribute very less towards meeting peak
load requirements. In view of large RE capacity addition being proposed, we would
need to review, explore and adopt different approach to maintain load-generation
balance and operation of grid.
Transmission capacity requirements are sensitive to load growth and generation
addition assumptions, especially when load growth may be in a range of 5-8 % per
annum and location of generation additions of next 20 years cannot be accurately
ascertained. As such, these transmission capacity requirements are only indicative in
nature.
61.2 SRPC noted the above
62 REIMBURSEMENT OF SRPC EXPENDITURE
Statement showing net amount payable by Member Utilities of SRPC for the year 2016 -17,
after adjustment of surplus/deficit for the previous period is furnished in Annexure-
XXXIX.
Members were kindly requested to ensure payment, wherever due.
63 VOTE OF THANKS
Chairperson, SRPC thanked all the Members for their cooperation in smooth conduct of the
Meeting.
64 DATE & VENUE OF THE NEXT SRPC MEETING
KPTCL kindly agreed to host the next SRPC/TCC Meetings. The date and venue would be
decided in due course.
*********