SOUTHERN REGIONAL POWER COMMITTEE
BENGALURU
Agenda for the 50
th Meeting of Protection Coordination Sub-Committee of
SRPC to be held on 29.12.2015 (Tuesday)
1. Introduction
2. Confirmation of Minutes of last PCSC meeting
Confirmation of minutes of 49th
Protection Coordination Sub-Committee meeting
held on 30.11.2015.
3. Grid Occurrences
3.1 Grid Disturbance (GD), Grid Incidences (GI), and trippings due to failure of Auto-
reclosing (A/R), and Mal-operation of PLCC equipment that occurred during the period November - December, 2015 given at Annexure-I would be discussed in
the PCSC meeting
Constituents are requested to furnish the following information in respect of the
above grid occurrences to have fruitful discussions in the PCSC forum.
(a) Single line diagram of the station with switching devices, CT, PT and relay
details.
(b) Cause of the tripping & Remedial Action taken
(c) Relay setting details
(d) Deficiencies / Observations as perceived by the Utility which needs PCSC’s
intervention.
Constituents are requested to bring/ give full particulars of the tripping events
pertaining to their system.
3.2 In compliance of Regulations 5.2 (r) of IEGC, the Constituents are required to
furnish the following information in respect of Grid Occurrences:
(a) First Information Report (FIR)
(b) Event Logger (EL) output
(c) Disturbance Recorder (DR) output
(d) Trip event analysis report (with pre and post fault system conditions)
Non-furnishing of tripping details including Disturbance Recorder/Sequential
Event logger output has been brought to Constituents attention vide SRPC letter
letter No. SRPC/ SE-III/ PCSC-50/ 2015/ 8687-719 dated 03-12-2015. The non-
compliance in this regard would be discussed in the meeting.
4. Submission of reports/compliance by Constituents
4.1 Status of pending Protection Coordination Sub-Committee (PCSC)
Recommendations
Status of the pending PCSC recommendations (from 30th
PCSC to 49th
PCSC) given at Annexure-II may please be sent latest by 25.12.2015.
Agenda for the 50th Protection Coordination Sub Committee Meeting to be held on 29-12-2015 Page 2
4.2 Remedial measures for "Transmission Line under Forced Outage"
The constituents are requested to send the remedial measures/ actions taken by them for the tripping events as circulated vide our emails. (Annexure-III)
The trip events are based on the daily reports at SRLDC website
http://srldc.in/DailyReport.aspx under the menu: Reports->Daily-> "TL under
Forced Outage")
4.3 Certificate for Healthiness of Batteries
As per the MoP direction given in pursuant to recommendations of the
Enquiry Committee (NEW grid disturbance on 30th
& 31st July, 2012), RPC’s
are required to obtain from their respective Constituents the monthly
certificate for healthiness of batteries, installed at 220 KV and above voltage
level Substations (for power supply to Relays, RTUs and PLCC equipment)
and furnish the same to CEA/ MoP.
With reference to above, the Constituents are requested to submit the
certificate on healthiness of batteries on monthly basis (i.e. on 7th
day of the
month) to SRPC.
The sought status for the month of November, 2015 is still awaited from the
following SR-Constituents:
APGENCO (Thermal), APTRANSCO, TSGENCO (Thermal), KPTCL,
TANGEDCO, PED, NTPC (Kayamkulam), MAPS, NTECL, NTPL, SEL,
CEPL & MEPL.
5. Network Configuration changes
As per the information furnished by SR-Constituents to the OCC forum in their 113th
meeting held on 06.11.2015 (Minutes circulated on 30.11.2015), the following network
configuration changes (additions/ deletions/ modifications of transmission elements) took
place in the southern grid during the month of October, 2015.
COD 220 kV Appayyadorapalem (ADR Palem) in Vizianagaram district was
commissioned on 15.10.2015 by APTRANSCO
220/132 kV Miyapur S/s of 1x160 MVA Transformer Capacity was augmented to
2x160 MVA Transformer Capacity on 07.09.2015 by TSTRANSCO.
220 KV D/C XLPE UG Cable from 220 kV Moulali SS to 220 KV GIS at Osmania
University in Hyderabad of ckm 17.926 was commissioned on 14.10.2015 by
TSTRANSCO.
220 KV line on Narrow Based Multi Circuit Towers with 4 Circuits for LILO of both
Circuits of Dindi - Chandrayangutta 220 KV D/C Line to the proposed 220 kV SS,
Bonguloor of ckm 2 was Commissioned on 31.10.2015 by TSTRANSCO.
LILO of 220kV Ramagundam- Mandamarry circuit-I to 220/6.6kV LI SS Murmur in
Karimnagar district of 3.9 ckm was commissioned on 21.10.2015 by TSTRANSCO.
220 KV 2nd ckt stringing from 220 KV RSS 220 KV Mandamarry (34 KM) in
Karimnagar of 34 ckm was commissioned by 20.10.2015 by TSTRANSCO.
LILO of 220kV Ogulapur- Durshed to 220/6.6kV LI SS Bommakal in Karimnagar
district of 0.108 ckm was commissioned on 27.10.2015 by TSTRANSCO.
Agenda for the 50th Protection Coordination Sub Committee Meeting to be held on 29-12-2015 Page 3
220/132 KV GIS Osmania University in Chilakalaguda, Hyderabad was
commissioned on 14.10.2015 by TSTRANSCO.
220/6.6KV Murmur LI substation in Karimnagar district was commissioned on
21.10.2015 by TSTRANSCO.
220/6.6KV Bommakal LI substation in Karimnagar district was commissioned on
27.10.2015 by TSTRANSCO.
220/6.6KV Mallaram LI substation in Medak district was commissioned on
31.10.2015 by TSTRANSCO.
220/132 KVSS Bonguluru in Ranga Reddy Dist. (originally charged with
1x100MVA) was commissioned on 31.10.2015 by TSTRANSCO.
PGCIL vide their letter dated 16.10.2015 informed that consequent to the successful
completion of Trial Operation, Transmission system associated with Kaiga 3 & 4
(2x235 MW) Project (Mysore-Kozhikode 400 D/C line along with new 400/220 kV
S/S with 2x315 MVA ICTs and 2x50 MVAR switchable line reactors at Kozhikode and
associated bay equipment at Mysore Substation) had been put under COD w.e.f 00:00
hours of 16th October 2015 in terms of Clause 4 of CERC(Terms and Conditions of
Tariff) Regulations 2014.
6. Compliance of Hon’ble CERC Orders.
6.1 Petition No. 146/MP/2013 with I.A. 36/2013: Order dated 20.02.2014
Compliance of Regulations 5.2 (r) of the Grid Code: Issue regarding non-
furnishing of FIR / Trip Analysis Report, EL, DR, etc. was also
highlighted. It is pointed out that the above reports are to be submitted /
uploaded on SRLDC web application within 24 hours as mandated under
IEGC / CEA Regulations.
Implementation of Phase-I and Phase-II of Protection Audit
Recommendations: All the constituents are requested to submit the updated
status of the compliance (those who have not completed recommendations
mentioned in the Phase I and Phase II) to SRPC Secretariat at the earliest.
Compliance of Regulations 5.2 (e) & 5.2 (l) of the Grid Code and Regulation
3(1)(e) of CEA Grid Standards: The constituents are requested to strictly
comply with these provisions by ensuring standard protections systems having
the reliability, selectivity, speed and sensitivity to isolate the faulty equipment
and protect all components from any type of faults, within the specified fault
clearance time and providing protection coordination
Ensuring proper maintenance of transmission lines and adopting best O&M
practices: The constituents are requested to conduct line patrolling regularly
as per the SRPC transmission line patrolling guidelines (available under the
menu item "All Uploads Operation Miscellaneous Transmission Line
Patrolling Protocol / Guidelines for Southern Region" on SRPC website).
(http://www.srpc.kar.nic.in/website/2014/operation/patrolling.pdf).
6.2 Petition No. 167/Suo- Motu/2012: Order dated 22.02.2014
The Constituents are requested to follow approved protection philosophy
ISTS licensees are requested to submit details of updated distance protection relay
setting of all inter-regional lines to POSOCO & RPCs.
All SLDCs are requested to install/activate sound recording system in their control
rooms within three months from the date of issue of this order.
The Constituents are requested to submit the progress of implementation to
SRPC and SRLDC as specified in the Hon'ble CERC Order.
Agenda for the 50th Protection Coordination Sub Committee Meeting to be held on 29-12-2015 Page 4
6.3 Petition No. 263/MP/2012: Order dated 19.12.2013
Constituents are requested to implement the quantum of relief by AUFR and df/dt
relays by identifying additional feeders and keep them functional within one month
of issuing this order.
SLDCs are also requested to map these relays on their respective SCADA
system within three months of issuance of this order.
The Constituents are requested to submit the progress of implementation to
SRPC and SRLDC as specified in the Hon'ble CERC Order.
6.4 APTRANSCO’s Petition No.95/MP/2015: Date of hearing 09-04-2015
It was noted in the Analysis and Decision part of the Order that:
“8. Noting the submissions of the petitioner, SRPC and SRLDC and activities
initiated by the petitioner for procurement of materials required for
implementation of the remarks of protecting audit, we allow time to the
petitioner till 31.12.2015 for completion of our directions in Order dated
19.12.2013 in Petition No. 146/MP/2013.”
“9. SRPC is directed to monitor the status of completion of works relating to
protection audit remarks in respect of 7 nos 400 kV sub-stations and 11 nos
220 kV sub-stations of APTRANSCO, protection audit remarks in Protection
Coordination Sub-Committee (PCSC) meetings and coordinate the periodic
protection audit to be carried out in Southern Region after deliberation in
SRPC and submit bi-monthly report to the Commission.”
6.5 TSTRANSCO’s Petition No.83/MP/2015: Order dated 14-05-2015
It was noted in the Order that:
“12. Noting the submission of the petitioner, SRLDC and SRPC and
considering the actions already initiated by the petitioner for implementation
of works relating to protection audit, we allow time till 31.10.2015 and
31.8.2016 for implementation of Phase-I and Phase -II works respectively.
The petitioner is directed to submit affidavit confirming the completion of
Phase I of protection audit remarks by 31.10.2015 and Phase-II of protection
audit remarks by 31.8.2016.
13. SRPC is directed to monitor the status of completion of remarks in these
substations vis-à-vis protection audit remarks in Protection Coordination Sub
Committee (PCSC) meetings. SRPC is further directed to coordinate the
periodic protection audit to be carried out in Southern Region after
deliberation in SRPC.”
6.6 Order in Petition No. 86/MP/2014 and 374/MP/2014: Order dated 18-08-2015
The time-lines given to the various SR-Constituents for completion of Phase-I and
Phase-II activities of Protection Audit Recommendations are given below:
(A) KSEBL:
18. Noting the submission of KSEBL, SRLDC and SRPC and considering the actions
already initiated by KSEBL for implementation of remarks of protection audit, we
allow time till 31.12.2015 and 31.3.2016 for implementation of Phase-II works
and R&M works at Idduki HEP respectively.
Agenda for the 50th Protection Coordination Sub Committee Meeting to be held on 29-12-2015 Page 5
(B) TANTRANSCO: 21. After considering the submissions of TANTRANSCO, SRLDC and SRPC, it is noted
that TANTRANSCO`s request for time till 31.5.2015 for implementation of Phase–I
activities of providing numerical relays for feeder protection and Auto transformer
protection is already over. We allow time till 30.6.2016 for other Phase-I activities
such as provision of line VT, 5 core CT, Time synchronizing with GPS, Disturbance
recorder & event logger and Phase-II activities. According to SRLDC, total
implementation period is 15 to 16 months for items which involve major
procurement, design changes with major site modification/civil activities.
Accordingly, we allow 16 months time i.e up to 30.11.2016, for Renovation and
Modernization of Singarpet, Singaperumalkoil, Salem and Tondiarpet 230 kV sub-
stations from the issue of the order.
(C) NLC:
22. NLC has sought time upto 31.12.2014 and 31.3.2015 for completion of Phase-I work
of Numerical Relay Retrofitting and for Phase-II works of providing second battery
bank of PLCC respectively. It is noted that the completion dates for Phase-I and
Phase-II of protection audit remarks as requested by NLC are already over.
Therefore, no direction is required in this regard. However, we direct NLC to file a
confirmation report regarding completion of protection audit works for Phase-I and
Phase-II.
(D) KPTCL:
23. …
…
Considering the submission of KPTCL and SRLDC, we allow time to KPTCL time till
15.01.2016 for completion of Phase-I and Phase-II of protection audit remarks. No
further extension shall be granted in this regard.
(E) KPCL:
24. …
… Considering the submission of KPCL and SRLDC, we allow time to KPCL till
31.10.2015 and 31.12.2015 for completion of Phase-I for Phase-II of protection
audit remarks respectively. No further extension shall be granted in this regard.
26. We direct SRPC to (a) submit status of protection audit remarks in respect of
APGENCO, NTPC (SR), Talcher, Puducherry, PGCIL (SRTS I & II), MAPS and
TANGEDCO, (b) monitor the status of completion of remarks of protection audit in
respect of all constituents of Southern Region in Protection Coordination Sub-
Committee (PCSC) meetings, and (c) to coordinate periodic protection audit to be
carried out in Southern Region after deliberation in SRPC. All the constituents of
Southern Region are directed to file their status with SRPC on regular basis to
facilitate proper monitoring in PCSC meetings. SRPC is directed to submit bi-
annually status report to the Commission confirming the completion of Phase-I,
Phase-II and R&M works of protection audit remarks of the constituents of Southern
Region.
Agenda for the 50th Protection Coordination Sub Committee Meeting to be held on 29-12-2015 Page 6
7. Other Protection Issues, if any, with the permission of the Chair
8. Sending Agenda items for the PCSC meetings
As per the Guidelines of CEA/MOP, it has been decided to conduct the PCSC
meetings on monthly basis. It is requested that Agenda Items for the PCSC meetings,
if any, may please be sent latest by 5th
working day of the month to SRPC Secretariat to
compile and circulate the same so as to have fruitful discussions in the PCSC
meetings.
9. Date of next PCSC meeting
The 51st PCSC meeting would be conducted on 27.01.2016 (Wednesday) at
Trivandrum, Kerala.
*******
Grid Occurrences
For all tripping events involving failure of substation equipment, Constituents are
requested to kindly furnish the SLD or equivalent pictorial representation showing
(i) Location of the fault, and (ii) Bus-bar arrangement/ Configuration of feeders and
other connected equipment with proper CB positions (OPEN/ CLOSE) at the time of
occurrence of the fault.
1. ग्रिडडडस्टर्बन्स / ग्रिडइन्सडन्टकावििरण - Details of Grid Disturbances:
Sr. No.
क्र.सं. घटनाकावििरण /
Details of Event
तारीख/ Date &
समय /Time कारण / Reason
टटप्पणी /Remarks
शे्रणी/ Category
1
Complete outage of
220kV Somanahalli
substation of
KPTCL
27-11-2015
at 18:47 hrs
Bus bar protection got operated
due to wrong bus bar zone
selection resulting in tripping of
both the 220kV bus at 220kV
Somanahalli substation
Load loss : 650MW
GD-1
2. ग्रिडडडस्टर्बन्स / ग्रिडइन्सडन्टकावििरण - Details of Grid incidents:
Sr. No.
क्र.
सं.
घटनाकावििरण / Details
of Event
तारीख/ Date &
समय /Time कारण / Reason
टटप्पणी /Remarks
शे्रणी/ Category
1
Tripping of 220kV
Ambewadi-Ponda
line-2 04-11-2015at
13:09 hrs Line tripped on operation of
DEFR protection
2
Tripping of 400kV
Alamathy-
S.V.Chatram line-2 08-11-2015
at 10:48 hrs
Line tripped on D.T. receive on
CHANNEL-2 at SV.Chatram end
when the operator at
ALAMATHY S/S end tried to
close Alamathy-SVChatram-1&2
Feeder Tie Breaker. Suspected
DC earth fault had caused the
initiation of direct trip.
3
Tripping of
400/220kV ICT-2 at
Chitoor substation 10-11-2015
at 00:53 hrs ICT-2 tripped on operation of
overflux protection
4
Tripping of ICT’s-1,
2, 3 & 4 at Salem
substation
10th Nov
2015 at
02:29hrs, 349
hrs, 3:53
hrsand 11th
Nov 2015 at
4:42 hrs
ICT’s tripped on operation of
overflux protection
5
Tripping of 400kV
NPS-NELLORE
line-1 10-11-2015
at 15:37 hrs line tripped due to suspected DC
earth fault at Nellore end and sent
direct trip was sent to NPS
6 Tripping of HVDC
Bhadrawati pole-2
11-11-2015
at 5:35 hrs
HVDC bhadrawati pole-2 tripped
due to non-valid tap code alarm. GI-2
7 Tripping of 400kV
Kolar-Hoody line-1
11-11-2015
at 15:39 hrs
Line tripped on operation of over
voltage protection and pole
discrepancy at Hoody end and
Annexure-I
Page 1 of 4
direct trip was received at Kolar.
8
Tripping of 400kV
Gooty-
Neelamangala line
12-11-2015
at 00:20 hrs
R-phase toearth fault had occurred
in Line. Line did not auto-reclose
from both ends. It was mentioned
that Y&B pole breakers at
Neelamangala tripped on
operation of pole discrepancy and
backup impedence protection for
line reactor got operated.
9
Tripping of Unit-
3&4 at Simhapuri
power station
12-11-2015at
13:51 hrs
Unit-3 and Unit-4 got tripped due
to operation of Local Breaker
Backup (LBB) protection in both
GT-3 and GT-4 Bays
10
Tripping of
765/400kV ICT-2 at
Nellore pooling
station
14-11-2015at
1:03 hrs
765/400kV ICT-2 at Nellore
pooling station tripped due to
maloperation of PRD-OLTC
Pressure High Trip Bph
11
Tripping of 400kV
Neyveli TS2-Pugalur
line
14-11-2015at
4:01 hrs
Line tripped on operation of over
voltage protection at Pugalur end.
However from DR it was
observed that the voltages were
below the O/v stg-1 threshold
limits
12
Tripping of 400kV
Nellore-Tiruvelam
line-1
14-11-2015
at 14:04
hrsand at
12:12 hrs on
24-11-2015
line tripped due to suspected Mal-
operation of Line reactor PRD at
Nellore end
13
Tripping of 400kV
Nellore-NPS line-1
16-11-2015
at 17:28 hrs
and 17:52 hrs
line tripped due on protection
system mal-operation due to
heavy rain at Nellore
14
Tripping of 220kV
Chitoor-Tiruvelam
18-11-2015
at 11:20 hrs
During testing of DC earth
leakage, DC got extended to bus
bar protection relay. Hence bus
bar protection operated and
tripped the 220KV BUS
connected transformers and
feeders.
15
Tripping of
400/220kV ICT-3 at
Udumalpet
substation
27-11-2015
at 11:21 hrs
ICT-3 Bus Voltage selection
Relay 75B and 75D Y ph contacts
failed to operate . Due to that the
over flux relay of ICT 3 operated
and initiated the Group A and B
relays. T
16
Tripping of 400kV
Alamathy-
S.V.Chatram line-
1&2
27-11-2015
at 15:35 hrs
400KV Aalmathy-S.V.Chatram
line-2 Line tripped on R-phase to
earth fault. Line autoreclosed at
S.V.Chatram and failed to auto-
reclose at S.V.Chatram end.
17
Tripping of
400/230kV
Udumalpet ICT-3
27-11-2015
at 17:26 hrs
400/230kV Udumalpet ICT-3
Tripped due to the operation of
230KV CB LBB protection at 230
KV bus (TNEB) of Udumalpet
station.
Annexure-I
Page 2 of 4
Sr. No.
क्र.
सं.
घटनाकावििरण / Details
of Event
तारीख/ Date &
समय /Time कारण / Reason
टटप्पणी /Remarks
शे्रणी/ Category
18
Tripping of 400kV
UPCL-Hassan line-2
and running Units-
1&2 at Udupi power
station
30-11-2015
at 17:22 hrs
400kV Hassan-Udupi line-2
tripped on Directional earth fault
protection with Y-E fault and
direct trip was sent to Udupi end.
Directional Earth fault feature of
Main-2 relay at hassan gave 3
phtrip after 2.6 seconds and fault
current in Y-phase was 1.1 kA.
The distance as well as DEF
protection for 400kV UPCL-
Hassan line-2 at UPCL end did
not sense the fault. The generator
transformer backup earth fault
protection (51N) had sensed the
fault and tripped both the running
units at UPCL leading to
generation loss at UPCL power
station. Back up directional earth
fault protection at 220kV side of
400/220kV ICT’s at UPCL did
not sense the high resistance fault
in line-2
Generation loss : 1100 MW
GI-2
19
Tripping of 400kV
Bus-2 at Kalpakka,
400kV Sinhadiri-
Kalpakka-4, 400kV
Vemagiri-Kalpakka-
2, ICT-2 at Kalpakka
10-12-2015
at 15:20 hrs
While testing new 400kV Hinduja
Power station feeder bay in the
yard, trip pulse got extended to
Bus-2 of Busbar protection and all
connected feeders to Bus-2 got
tripped
GI-2
3. Failure or non-operation of Auto reclose during transient fault
Sr. No.
Element Date & Time
Reason
1
Tripping of 400kV Gajwel-
Shankarapalli line-1
02-11-2015 at
11:33hrs and 12:22
hrs
Line tripped on a R-phase to earth
fault and fault was persistent.
From PMU data it was observed
that the breaker tried two auto-
reclose attempts after dead time.
2
Tripping of 220kV
Kaniambeta-Kadakola line 04-11-2015at 12:38
hrs Line tripped on a B-phase to earth
fault. There is no provision for
auto-reclose for line
3
Tripping of 220kV Ambewadi-
Ponda line
11-11-2015 at
11:32hrs
Line tripped on a B-phase to earth
fault. There is no provision for
auto-reclose.
Annexure-I
Page 3 of 4
4
Tripping of 400kV NCTPS-
S.V.Chatram line-1 16-11-2015 at
17:24 hrs Line tripped on a Y-phase to earth
fault. Line auto-reclosed at
S.V.Chatram and failed to auto-
reclose at NCTPS. It was
mentioned in FIR of NCTPS that
the tie breaker was under
shutdown.
5
Tripping of 400kV
Krishnapatnam-Chitoor line-1
16-11-2015 at
18:49 hrs Line tripped on a permanent fault
in R-phase. Chitoor end attempted
for auto-reclose however
krishnapatnam end went for a 3
phase trip and did attempt for
auto-reclose.
6
Tripping of 220kV
Gumidipoondi- Sulurupeta line
03-12-2015 at
09:05hrs
Line tripped on a Y-phase to
ground fault. There is no
provision for auto-reclose for line.
4. Lines tripping due to tripping at one end/PLCC mal-operation
Sr. No.
क्र.
सं.
घटनाकावििरण / Details
of Event
तारीख/ Date &
समय /Time कारण / Reason
टटप्पणी /Remarks
शे्रणी/ Category
1 Tripping of 400kV
Pugalur-Karaikudi 8-11-2015 at
13:51hrs
line tripped at Karaikudi and was
holding from Pugalur due to
suspected PLCC mal-operation at
Karaikudi end.
2
Tripping of 400kV
Krishnapatnam-
Chitoor line-2
21-11-2015at
7:18 hrs
Line tripped at Krishnapatnam
end only on pole discrepancy
operation
*****
Annexure-I
Page 4 of 4
Meeting
No /
Index
Details of
Event
Date Reason PCSC Recommendations Utility
Responsible
for
implementat
ion
Status of Recommendations
as on 14-12-2015
Remarks
45/II/14 Tripping of
400/220 kV
ICT-1&2 at
Gooty
substation
31-05-2015at
06:37 hrs
As per FIR, ICT-1&2 tripped on
operation of directional overcurrent
and earth fault protection. It was
reported that there was fault in
220kV APTRANSCO system
1. APTRANSCO to check resistive reach of the
distance relays on 220 kV Gooty SS – Gooty
RS line
2. APTRANSCO to check time coordination of
distance relay on Gooty SS – Gooty RS line at
Gooty SS with Gooty ICT’s (1 & 2) back-up
protection.
APTRANSC
O
Yet to be informed Pending
APTRANSC
O
APTRANSCO to furnish a report on the
tripping of 400 kV Vemagiri – Sattenapalli line
along with relevant DR & EL showing clearly
the successful operation of A/R followed by T-
LBB/ OVR, Stage-I operation.
Pending Implementation of PCSC Recommendations (30th to 49th)
Andhra Pradesh42/II/3 Outage at
Regulapadu
station of
APTRANSC
O
21-02-2015
at
00:49 hrs
Y-Ph Metering PT failed at 220KV
Ragulapadu Substation. Fault got
cleared
by tripping of lines from remote
ends.
APTRANSCO to furnish the remedial
measures taken in consequent to the tripping
incident along with the status of bus bar
protection and bus coupler at Regulapadu S/s.
A/R feature to be enabled on Regulapadu –
Alipuira 220 kV inter-state line.
APTRANSC
O
Mail recieved on 22-08-2015:
APTRANSCOhas planned to commission ABB make ETL-41 type
PLCC terminal along with NSD-50 type protection coupler at
Ragulapadu end towards Alipura. vide our Ltr Dt 23-07-2015, it is
requested KPTCL to arrange ABB make ETL-41 cabinet with NSD-
50 type protection coupler for establishing PLC communication
between Alipura- Ragulapadu.
Pending
B-phase to earth fault had occurred
in line. From Vemagiri end D.R,
three phase trip and Tie-CB LBB
operated was observed.
Sattenapalli end had auto-reclosed,
however breaker at Satenapalli
tripped 8 sec after A/R on receipt
of DT from Vemagiri as observed
from EL of Satenapalli station.
For 400k Vemagiri-Kalpakka line
at Vemagiri end, Tie LBB
operation and Grp-A/B trip was
observed and direct trip was sent to
Kalpakka end
25-10-2015
at 10:56 hrs
Tripping of
400kV
Vemagiri-
Sattenapalli
line and
400kV
Vemagiri-
Kalpakka line
49/II/8 PendingYet to be informed
Annexure-II
Page 1 of 24
49/II/13 Tripping of
running Units
1 & 3 at
Rayalaseema
TPS of
APGENCO
31-10-2015
at 03:30 hrs
While synchronizing Unit-5 with
grid, BBP of 220kV Bus-1
operated which resulted in de-
energization of 220kV Bus-1. This
resulted in tripping of running Unit-
1&Unit-3, 220kV lines Pulivedula-
1, Yeralaguntla-1, Chinakampalli-
1, Timmapura
In view of the availability of 25AX,
APGENCO shall keep synchronizing facility in
auto-mode after getting it’s operation verified
by its OEM, M/s BHEL.
APGENCO Yet to be informed Pending
49/III/4 Tripping of
400kV
Krishnapatna
m-Chittoor
line-1
19-10-2015
at 07:49 hrs
R-phase to earth fault had occurred
in line. Chittoor end tried for auto-
reclose. However, due to persistent
fault, breaker at Chittoor end
tripped. Krishnapatnam end relay
did not try for auto-reclose and
gave a 3 phase trip as observed
from D.R
• APGENCO to make A/R functional on all
lines emanating from Krishnapatnam TPS by
10th December, 2015.
APGENCO Yet to be informed Pending
44/III/2 Tripping of
400kV
Ghanapur-
Mamidapalli
line
15-04-2015
at 2:03 hrs
Line tripped at Mamidapalli end
only and was holding at Ghanapur.
Overvoltage protection had
operated at Mamidapalli
TSTRANSCO to make DR
functional at Mamidipalli
TSTRANSC
O
TSTRANSCO informed vide their mail dated 24.06.15 that the
existing relays would be replaced with numerical relays in DPR
works.
Pending
Telangana
Annexure-II
Page 2 of 24
48/II/5 Tripping of
400kV
Nagarjunsaga
r-
Mahboobnaga
r line
07-09-2015
at 2:58 hrs
Line tripped on operation of OV
protection at Mahboobnagar and
DT received at N’sagar station. DT
receive was observed in DR and
EL of N’sagar station. D.R/EL of
Mahboobnagar was not furnished
to validate the overvoltage tripping
TSTRANSCO to furnish a detailed report on
the tripping event along with remedial
measures taken to PCSC forum.
TSTRANSC
O
Yet to be informed Pending
48/III/4 Tripping of
220kV
Gajwel-
Shankarapally
line
20-09-2015
at 2:24 hrs
line tripped at Gajwel end on R-
Phase to ground fault. Reason for
non-auto reclose could be
established as DR and EL of both
ends were not furnished
• TSTRANSCO to furnish a detailed report on
the tripping event along with remedial
measures taken to PCSC forum.
TSTRANSC
O
Yet to be informed Pending
47/I/1
(GD)
Disturbance
in Srisailam
left bank
power station
18-08-2015
at 15:25 hrs
PendingYet to be informedTSGENCO1. TSGENCO to check the reclaim time of A/R
and set it at 25 sec at KTPS.
2. TSGENCO to carry out PLCC end-to-end
testing in coordination with PGCIL (SR-I) for
KTPS – Khammam
line-2; retrofitting of Protection Coupler may
be carried out based on the test results.
Y-phase to earth fault had occurred
in line. From Khammam end DR it
was observed that the relay after
dead time tried for auto-reclose.
The fault was persisting and relay
gave a single phase
trip instead of a 3 phase trip after
1.25sec. R& B pole voltage dip
after 2 sec possibly due to
operation of pole discrepancy.
Auto-reclose close command
observed after 2.5 seconds
and all poles got closed.
30-07-2015
at 6:08 hrs
PendingYet to be informedTSGENCO1. TSGENCO to disable sensitive earth fault
protection provided as supplementary to static
bus-bar
protection at Srisailam LB (GIS).
2. TSGENCO to set the current setting for
phase-to-ground faults for numerical bus-bar
protection at a suitable value so that the
prominent high-resistance earth faults
occurring within the bus-zone are
covered at Srisailam LB (GIS).
Tripping of
400kV
Khammam-
KTPS line-2
400kV Srisailam-Mamidapalli line-
2, 400kV Srisailam- Satenapalli
line-2 and 400 kV Srisailam-
Kurnool line tripped during
multiple tripping at Srisailam
power station. 400kV Srisailam-
Mamidapalli-1 and 400kv
Srisailam-Satenapalli-1
was kept out of service due
over-voltage conditions. There was
no generation at Srisailam left bank
power station. Triggering incident
was failure of CT in 400kV
Srisailam- Satenapalli line-2 at
Srisailam end.
47/II/6
Annexure-II
Page 3 of 24
34/III/1 400kV
Raichur-
BTPS line
26-06-2014 Transient fault in R-phase.
Line did not auto reclose
A/R at BTPS end to be made operational
within one month
KPCL 1. A/R for 220kV lines enabled already.
2. Shut down of lines availed to commission the auto reclosing schme
for 400 kV line at BTPS.
Mail recieved on 21-10-2015:
Timer relays have been received at site. A letter has been addressed to
M/s Alstom to complete the work on priority basis.
Mail recieved on 23-11-2015:
Commissioning of Autorecloser planned on 14, 15 & 16th of Dec-
2015 subject to availability of LC.
Pending
Karnataka30/I/A RTPS
Tripping
incidents and
the Spl
meeting held
at RTPS on
13th and 14th
March 2014
Mar-14 Spl meeting held at RTPS on 13th
and 14th
March 2014
The PCSC forum recommended for
replacement of existing electromechanical
relays with Numerical relays.
KPCL Mail recieved on 21-10-2015 and 23-11-2015:
1) Replacement of Old electromagnetic relays with Numerical relays
has been completed for RTPS-BTPS line & commissioned on
18.03.2014.
Raichur-PG1 & Raichur-PG2 lines have already retrofitted with
numerical relays.
2. Job order placed on 26.06.2015 on M/s Alstom T&D India Ltd.
Chennai for retrofitting of relays for all 220kV lines at RTPS.
3. Retrofit of existing bus bar(CAG-34) with numerical version–
Budgetary offers obtained and is under process.
38/GD/3.
5
GD-1 at
Kadra and
Kodasalli
hydro power
station
13-11-2014
at 19:31hrs
A fault had occurred in 220 kV
Kadra and
Kodasalli. As A result, de-
energization of
220kV bus occurred at Kadra and
Kodasalli.
1. The PCSC forum requested KPCL to speed
up the installation of Numerical Distance
Protection relay in Kadra –Kaiga and
Kodasalli –Kaiga.
2. The PCSC forum requested KPCL to submit
the implementation status of PSAG-10
recommendations within a week’s time.
KPCL Mail recieved on 21-10-2015:
NIT floated on 5.5.15 through e-portal. Bid evaluation completed.
LOA's issued to M/s Schneider Electric Infrastructure Ltd. on
08.10.2015.
Mail recieved on 23-11-2015:
LOA's issued to M/s Schneider Electric Infrastructure Ltd. on
08.10.2015. Engineering work is in progress.
Pending
Pending
Annexure-II
Page 4 of 24
38/GD/3.
2
GD-1 at
Guttur
Substation of
KPTCL
05-11-2014
at 11:42 hrs
Circuit breaker of 400kV Guttur-
Hiriyur
line-1 failed at Guttur end while
availing
shutdown for replacement of CVT.
The
failure of breaker caused bus fault
at Guttur.
KPTCL was requested to expedite the early
implementation of pending recommendations
of:
1. Protection Audit (Phase-I & Phase-II)
2. PSAG-4, PSAG-5, and PSAG-8
KPTCL Mail received on 27-05-2015 & 29-07-2015:
Latest satus of implementatin of Phase-1 &2 recommendations,
PSAG 4,5 and 8 is being obtained from field. The Status will be
updated witin a weeks time.
Pending
39/I/5 Tripping of
400/220kV
ICT-2 at
Hoody
substation of
KPTCL
01-12-2014 Suspected mal-operation of 220kV
side Rphase
over current relay
1. PCSC forum recommended KPTCL to
replace the relay with a different make.
2. KPTCL was also requested to train the
O&M personnel adequately before performing
any maintenance works to avoid such unwanted
trippings.
KPTCL Mail received on 27-05-2015 & 29-07-2015:
C&R panels of 500MVA ICT 1&2 will be replaced under
scheduled R&M works. O&M personnel are instructed to take
sufficient care in order to avoid unwarrented trippings.
Pending
34/I/6 400/220 kV
ICT-1 & 2 at
MUNIRABA
D
16-07-2014 As reported directional over
current relay of ICT’s operated
due to snapping of line jumper
in 220kV Lingapur line.
1. Bus bar protection shall be provided by
asset owner ( i.e KPTCL).
2. Settings for main distance protection &
Overcurrent protection shall be examined and
reviewed.
3. Time synchronization of the Substation
shall be ensured.
4. Correct DR shall be submitted to the SRLDC
for trip analysis.
KPTCL Mail recieved on 27-05-2015 (KPTCL):
1. KPTCL has taken action to provide bus bar protection to 220kV
buses.
2. Over current relay Settings of ICTs to be reviewed by PGCIL.
Mail received on 29-07-2015 (KPTCL):
Initial Tendering stage
Pending
38/GD/3.
1
GD-1 at
Mahalingapur
a Substation
of KPTCL
25-10-2014 Fault had occurred in 220kV
Mahalingapura-Narendra line-2.
Due to the
failure of relay operation at
Mahalingapura,
breakers at remote end tripped
which
resulted in bus dead condition.
1. PCSC forum recommended KPTCL to
replace the old static distance protection
relays with numerical relays.
2. PCSC forum also requested KPTCL to
provide a broken conductor alarm indication in
Control Room.
3. Standing instruction needed to be given to
the all substation personnel for not changing
the relay settings without approval of RT/MRT
wing.
KPTCL Mail received on 27-05-2015 (KPTCL) & 29-07-2015:
1.Existing Back up relays will be replaced by numerical type
distance relays.Procurement is in tendering stage. Remaining
observations were attended.
Pending
Annexure-II
Page 5 of 24
40/IV/1 220kV Sedam-
Tandur line
20-12-2014
at 22:20 hrs
Line tripped on Yphase to earth
fault from both the ends
KPTCL was requested to explore the
possibility of providing A/R feature to this
line and submit the remedial measures to the
PCSC forum.
KPTCL Mail recieved on 29-07-2015:
Carrier protection is being restored for 220kV Sedam-Tandoor line at
Sedam end. After restoring the carrier protection , AR will be
enabled.
Pending
40/I/1 GD-1 at
220kV
Ambewadi
Station of
KPTCL
22-12-2014
at 21:22 hrs
Triggering incident was B-phase to
earth fault in 220kV Ambewadi-
Nagzari line-1. B-pole of breaker
did not open at Ambewadi end.
LBB protection not available at
Ambewadi end. All elements
tripped on Zone-2 from remote
ends.
1. Till the completion of R&M works for bus
bar and LBB protection, KPTCL shall explore
the possibility of having split bus operation
at Ambewadi and submit the details of the
same to PCSC forum.
2. KPTCL shall provide the details of the
tripping of Supa hydro station connected
downstream from 110 kV bus.
KPTCL Mail recieved on 29-07-2015:
Action is being taken by KPTCL for operating Ambewadi in split bus
mode. Problem in bus coupler breaker is attended.Isolator
overhaulling work is completed.PTs are already provided to 220kV
Bus-II. After commissioning of Bus-II PTs, Ambewadi can be
operated in split bus mode. Pending works will be completed within a
months time.
Pending
Mail received on 28-05-2015:
1. Main-2 relays already installed and commissioned.
2. DC fuses are intact. Till date no such incidence occurred.
3. Possibility of DC-1 & DC-2 arrangement and splitting of DC will
be reviewed.
Mail received on 07-07-2015 , 21-10-2015 and 23-11-2015:
1. Completed.
2. Completed.
3. Possibility of DC-1 & DC-2 arrangement and splitting of DC will
be reviewed.
Pending41/I/1 GD-1 at
220kV Kadra
power Station
of KPCL
16-02-2015
at 12:56 hrs
Triggering incident was B-phase to
earth fault had occurred in 220kV
Kadra-Kodasalli line. Line tripped
from Kodasalli end only. 220kV
Kaiga-Kadra tripped in Zone-3
from Kaiga end. Tripping of
evacuating lines caused bus shut
down at Kadra hydro station.
1. KPCL to make functional the Main2
(EPAC) relay with the help of KPTCL at the
earliest.
2. KPCL to investigate the reason for DC
fuse fail during transient fault in 220kV Kadra-
Kodasalli line including the testing/ checking
of DC supply cables, breaker control cables,
and trip coils.
3. KPCL to ensure supply for Main-1& Main-
2 protections, Trip Coils (TC1, TC2) from
separate battery banks.
KPCL
PendingMail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final
tendering stage.
2. Action is being taken to restore the carrier protection for 220kV
Sedam-Tandoor line. AR will be enabled after restoration of PLCC.
KPTCL 1. KPTCL to provide Bus bar and LBB
protections for 220 kV bus at Sedam S/s.
2. KPTCL to implement A/R feature on 220
kV Sedam-Tandur inter-state line.
R-Phase to ground fault occurred
on 220kV Sedam-Shahpur line.
Fault not cleared from Sedam end
due to stuck-breaker condition.
While the Sedam- Sahapur line
tripped from Shahapur end in Zone-
1, the other 220 kv lines from
Sedam tripped at remote ends in
Zone-2. This caused complete
outage of 220kV Sedam substation.
27-01-2015
at 8.00 hrs
Complete
outage at
220kV Sedam
Substation of
KPTCL (GD-
1)
41/I/4
Annexure-II
Page 6 of 24
42/I/1
(GD)
Complete
outage of
220kV Sedam
substation of
KPTCL
15-02-2015
at 14:24 hrs
Fault occurred in 220kV Sedam-
Shahpur line
1. KPTCL to provide Bus Bar protection and
LBB protection at Sedam S/s and furnish
the status of their implementation to PCSC
forum.
2. KPTCL to implement A/R feature on 220 kV
Sedam-Tandur inter-state line.
KPTCL Mail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final
tendering stage.
2. Action is being taken to restore the carrier protection for 220kV
Sedam-Tandoor line. AR will be enabled after restoration of PLCC.
Pending
42/I/2
(GD)
Complete
outage of
220kV
Ambewadi
substation of
KPTCL
12-03-2015
at 7:51 hrs
Fault in 220kV Ambewadi-
Nagjheri line-2
1. KPTCL shall provide A/R feature on
Ambewadi – Ponda 220 kV D/C inter-state
line.
2. Till the completion of R&M works for bus
bar and LBB protection, KPTCL shall explore
the possibility of having split bus operation at
Ambewadi and submit the details of the same
to PCSC forum.
KPTCL Mail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final
tendering stage.
2. Action is being taken to restore the carrier protection for 220kV
Sedam-Tandoor line. AR will be enabled after restoration of PLCC.
Pending
42/II/2 Tripping of
220kV
Chikodi-
Talandage
and
Mudshingi
line
20-02-2015
at
06:40 hrs
Lines tripped during test charging
220kV
Chikodi-Belgaum line-2 from
Chikodi
end.
1. KPTCL to provide A/R feature on the 220
kV Chikkodi – Talandage, and 220 kV
Chikkodi –Mudashinge inter-state lines.
2. KPTCL to carry out E/F relay coordination
for Chikkodi - Talandage and Chikkodi –
Mudashinge lines in coordination with
Maharashtra.
KPTCL Mail received on 29-07-2015:
Action is taken for enabling AR for Mudashinge and Talandage lines.
Work is scheduled during first week of August 2015.
Pending
PendingMail received on 29-07-2015:
1. Procurement of Bus bar and LBB protection is in the final
tendering stage.
2. Action is being taken to restore the carrier protection for 220kV
Sedam-Tandoor line. AR will be enabled after restoration of PLCC.
KPTCL 1. KPTCL to provide Bus bar and LBB
protections for 220 kV bus at Sedam S/s.
2. KPTCL to implement A/R feature on 220
kV Sedam-Tandur inter-state line.
R-Phase to ground fault occurred
on 220kV Sedam-Shahpur line.
Fault not cleared from Sedam end
due to stuck-breaker condition.
While the Sedam- Sahapur line
tripped from Shahapur end in Zone-
1, the other 220 kv lines from
Sedam tripped at remote ends in
Zone-2. This caused complete
outage of 220kV Sedam substation.
27-01-2015
at 8.00 hrs
Complete
outage at
220kV Sedam
Substation of
KPTCL (GD-
1)
41/I/4
Annexure-II
Page 7 of 24
43/II/14 Tripping of
400/220kV
ICT-1 at
BTPS
14-01-2015
at 1:09
hrs
ICT tripped due to operation of
Over current and Earth fault relay
KPCL to check the possibility of providing line
differential protection between RTPS and
Yermarus stations.
KPCL Mail received on 07-09-2015 , 21-10-2015 and 23-11-2015:
Revised relay settings are awaited from KPTCL.
Revised relay settings furnished by KPTCL will be incorporated in co-
ordination with KPTCL shortly.
Pending
45/III/12 Tripping of
400kV
Raichur-
BTPS line
01-06-2015
at 01:02 hrs
line tripped on R-phase to earth
fault. Line did not auto-reclose
KPCL to make A/R operational on 400 kV
RTPS – BTPS S/C line at both ends.
KPCL Mail recieved on 23-11-2015:
Completed at RTPS end.
Pending
44/II/3 Tripping of
220kV
Kaiga-
Kodasalli
and 220kV
Kodasalli-
Nagjheri line-
1
22-04-2015
at
20:28 hrs
220kV Kodasalli-Nagjheri line-1
tripped from Kodasalli end on
operation of distance protection,
zone-2.
220kV Kodasalli-Nagjheri line-
1&2 is kept opened from Nagjheri
end, hence fault
could not be cleared with carrier
aided protection. Backup earth
fault relay at Kaiga end got
operated during the event and
resulted in tripping of 220kV
Kaiga- Kodasalli line from Kaiga
end.
1. KPCL to check the possibility of
implementing Permissive Over Reach (POR)
with Echo feature at Kodasally end.
2. If the above is not possible, KPCL shall
check the possibility of keeping the 220kV
Kodasalli-Nagjheri lines OPEN at Kodasalli
end and idle-charged at Nagjheri end, and
implement the same.
KPCL Mail received on 07.07.2015:
The matter had been discussed with KPTCL. KPTCL recommended
to keep Zone-2 time lever to zero. If this is acceptable, then the same
shall be incorporated immediately.
Mail received on 07-09-2015 , 21-10-2015 and 23-11-2015:
The matter has been discussed with KPTCL. KPTCL recommended to
keep Zone-2 time lever to zero.
If this is acceptable to SRLDC, then the same shall be incorporated
immediately.Reply from SRLDC is awaited.
Pending
PendingMail recieved on 23-11-2015:
1) Completed
3) Two bus operation for 220kV buses : In place of existing CT
switching relays, High speed manual heavy duty change over switch
of sufficient current capacity will be retrofitted to all feeders at 220kV
station and same will be operated manually during changeover of
feeder by one bus to the other and this arrangement may facilitate to
put both buses in service. Time required for this retrofit is around
90days . However, this work will be taken up only after retrofitting of
electromagnetic relays with numerical relays for Main-2 protection of
all 220kV lines, for which work is in progress.
KPCL1. KPCL to check the operation of anti-
pumping relay on 220 kV side and keep it in
healthy condition.
2. KPCL to provide manual reset to the 220 kV
side master trip relay.
3. KPCL to use both the 220 kV buses as main
buses under normal operation, and should go
for single bus operation only during
emergencies.
07-06-2015
at 01:35 hrs
Trippings at
220kV
Raichur TPS
46/II/21
Annexure-II
Page 8 of 24
47/III/8 Tripping of
220kV
Ambewadi-
Ponda line-2
02-08-2015
at 13:20 hrs
Line tripped on a transient fault in
B-phase. There is no
provision for auto reclose.
47/III/10 Tripping of
220kV
Ambewadi-
Ponda line-1
08-08-2015
at 10:51
hrs and 09-
08-2015 at
11:15 hrs
Line tripped on a B-phase to earth
fault. Line tripped as there is no
provision for auto-reclose
47/III/12 Tripping of
220kV
Ambewadi-
Ponda line-1
17-08-2015
at 13:20 hrs
Line tripped on a transient fault .
There is no provision for Auto
reclose.
Complete
outage of
220kV
Peenya
Substation in
Karnataka
48/I/2
(GD)
PendingYet to be informedKPTCL KPTCL to revise distance relay settings at
Nelamangala end for 220 kV Nelamangala –
Hebbal - Peenya line – 1 for the effective line
length of 17 km. These new settings can be
appropriately reviewed as and when the tie-
arrangement at Hebbal is done away with.
All connected 220kV lines and
transformers were taken on 220kV
North bus as South bus was under
shut down for conversion of strung
bus to rigid bus and isolator
replacement under R&M works.
Failure of HV side Y phase CT of
150MVA Transformer-3 occurred
at Peenya Substation which
resulted in operation of Differential
and HV REF protection. The
failure of CT also resulted in a
220kV bus fault in North Bus.
27-09-2015
at 4:23:17
hrs
PendingYet to be informedKPTCLKPTCL to activate non-directional Over
Current protection with a time delay of 600-
800 msec for Fuse
failure condition at Lingasugur.
Till A/R is put into service on Ambewadi-
Ponda line-1, KPTCL to reduce Zone-2 time
setting to zero sec. at Ambewadi end.
KPTCL Yet to be informed Pending
220kV RTPS-Lingasugur line-2
tripped at TPS end on operation of
distance protection zone-1.
400/220kV ICT-2 got tripped on
operation of earth fault protection.
220kV RTPS-Lingasugur line-
1&3 tripped on distance protection
zone-2 and zone-3 respectively.
Due to
tripping of ICT-2, the running units
got overloaded and it was
mentioned that under frequency
occurred as units are on load
control. The Units got tripped
on under frequency.
06-08-2015
at 4:51 hrs
Tripping of
Unit-1&2
along with
400/220kV
ICT-2 at
Raichur TPS
47/II/13
Annexure-II
Page 9 of 24
48/I/3
(GD)
Outage of
220kV
Ambewadi
station in
Karnataka
30-09-2015
at 10:41 hrs
220kV Ambewadi-Nagjheri line-2
tripped on B-phase to earth fault.
This resulted in loss of supply to
220kV Ambewadi bus. 220kV
Ambewadi-Ponda line-1&2 were
hand tripped after deenergization
of bus at Ambewadi.
KPTCL to fast-track providing A/R on all 220
kV lines emanating from Ambewadi SS to
prevent Station shut-down on temporary faults.
KPTCL Yet to be informed Pending
48/I/4
(GD)
Complete
outage of 220
kV HSR
substation of
Karnataka
06-10-2015
at 16:32 hrs
All connected 220kV lines at
220kV HSR substation i.e.
Somanahalli, EPIP, Hoody and
Nagnathapura tripped during the
incident. Triggering incident was
fault in 220kV HSR-EPIP line
KPTCL to review distance relay settings at
Naganathpura SS in view of LILO arrangement
at HSR Lay-out.
KPTCL Yet to be informed Pending
49/II/15 Trippings at
Raichur TPS
12-11-2015
at 00:30 hrs
Running Unit-4, 5 and Unit-8 and
400kV RTPS-Yeramaras TPS
feeder got tripped due to de-
energization of both 400kV Bus-
1&2 at Raichur TPS
1. KPCL to carry out hot-line washing of RTPS-
connected lines regularly to avoid trippings due
to fog and dust.
2. KPCL may see the feasibility of providing
breaker flashover protection at RTPS, and
implement the same if possible.
KPCL Yet to be informed Pending
49/III/5 Tripping of
400kV
Kaniyambeta-
Kadakola line
28-10-2015at
12:08 hrs
Line tripped on a Y-phase to earth
fault. There is no provision for auto-
reclose
• KPTCL to provide A/R on Kadakola –
Kaniyampeta line at Kadakola end.
KPCL Yet to be informed Pending
Pending1. KPCL to provide A/R on all 220 kV lines
emanating from Nagjheri PH.
2. KPTCL to provide A/R on all 220 kV lines
emanating from Ambewadi SS.
220kV Nagjheri-Ambewadi line-1
tripped at 13:33 hrs due to B phase
to earth fault. Ambewadi was
radially fed from Nagjheri power
station through 220kV Nagjheri-
Ambewadi line-2. Tripping of this
line caused 220kV Bus shut down
at Ambewadi and remaining lines
and transformers were hand tripped
29.10.2015
at 14:34 hrs
Complete
outage of
220kV
Ambewadi
Substation of
KPTCL
49/I/1.3
(GD)
Yet to be informedKPTCL
Annexure-II
Page 10 of 24
45/II/12 Multiple
tripping at
400/230kV
Alamathy
substation
25-05-2015at
09:08hrs
As per FIR, failure of R-phase CT
of 230kV Alamathy-Manali feeder
occurred at Alamathy end. Hence
230KV BBP Zone 1 & 2 Operated
at Alamathy substation. All the
230KV feeders, 230KV BC, ICT-3,
4 & 5 LV breakers got tripped.
TANTRANSCO to furnish a detailed tripping
report including reasons for delayed clearance
of fault at Almathy.
TANTRANS
CO
Mail received on 03-09-2015:
The faults were cleared with out time delay at Alamathy SS. Detailed
Tripping report sent vide Lr.No.CE/P&C/SE/D/
EPC4/AEE3/F.SRPC/ D.21/15, dated 14.07.2015.
The reasons for the delayed clearance of the third fault not
furnished.
Pending
48/I/1
(GD)
Disturbance
in 220kV
Tamilnadu
system
05-09-2015
at 14:04 hrs
Complete outage of 230kV
Palladam, 230 kV
Othakalmandapam S/s, 230 kV
Coimbatore S/s, 230 kV Thudialur
and 230 kV Sadayapalayam S/s
TANTRANSCO to take suitable measures like
installing more stub-towers along 230 kV OK
Mandapam – Myvady line to avoid excessive
sag due to over-loading.
TANTRANS
CO
Yet to be informed Pending
48/II/6 Tripping of
400/220kV
Alamathy
ICT-3,4&5
07-09-2015
at 04:24hrs
Triggering incident was failure of
Y & B phase CT failure in 230kV
Korattur feeder
1. TANTRANSCO to furnish a detailed report
on the tripping event covering the sequence of
events, and the remedial measures taken to
PCSC forum.
2. TANTRANSCO to configure Bus-Bar
protection at Alamathy for instantaneous
operation.
TANTRANS
CO
Yet to be informed Pending
PendingTANTRANSCO vide their mail dated 24.06.15 informed that
different relays in Main-I & Main-II would be ensured at the earliest.
Mail recieved on 24-07-2015:
Different relays in Main-I & Main-II will be ensured.
TANTRANS
CO
TANTRANSCO was requested to swap the
relays between two stations, so that
Main-1 and Main-2 will be of different make at
each station.
Line-2 tripped on R-phase to earth
fault.
Line autoreclosed at SVChatram
end and failed to reclose at
Alamathy end. Bphase to earth
fault in line-1. Line tried for A/r
but due to permanent fault line did
not reclose. ICT tripped on
operation of over flux protection.
29-03-2015
at
15:29 hrs
Tripping of
400kV
Alamathy-
SVChatram
line-1&2
and
400/230kV
ICT
at
S.V.Chatram
43/II/5
Tamil Nadu
Annexure-II
Page 11 of 24
49/II/3 Tripping of
220kV
Edamon-
Tirunelveli
line-1&2
12-10-2015
at 21:30 hrs
220kV Edamon-Tirunelveli lines -
1&2 got tripped due to operation of
Bus Bar protection which was due
to human error
KSEB to furnish reasons for DT not being
sent to the remote end during the tripping event
along with remedial measures taken to PCSC
forum.
KSEB Yet to be informed Pending
49/III/1 Tripping of
220kV
Sabarigiri-
Theni line
09-10-2015
at 16:56 hrs
Line tripped on a R-phase to earth
fault. At Sabarigiri, relay gave a 3
phase trip after 220ms. From Theni
end D.R, auto reclose block was
observed.
KSEB to furnish a report on the tripping
incident along with the remedial measures
taken to PCSC forum.
KSEB Yet to be informed Pending
PendingYet to be informedTANTRANS
CO
1. TANTRANSCO to ensure correctness of
operation of LBB relays at SP Koil.
2. TANTRANSCO & MAPS to furnish their
respective compliance report of the
recommendations of to-be-conducted PSAG-14
meeting at MAPS, Kalapakkam.
Fault had occurred in 230kV
MAPS-S.P.Koil feeder-1. LBB
protection got operated as breaker
of this feeder was under lockout
and resulted in tripping of 230kV
bus at S.P.Koil. Unit-1&2 at
MAPS due to loss of evacuating
feeders i.e. 230kV MAPS-S.P.Koil
feeder-1&2
09-11-2015at
09:33 hrs
Complete
outage of
S.P.Koil
station of
TANTRANS
CO and
generation
loss at
Madras
Atomic
Power
station(MAP
S)
49/I/1.5
(GD)
KeralaMail recieved on 30-10-2015:
1. Purchase procedures is still in progress.
2. Replaced.
3. PLCC equipment Tested and found OK.
Pending
(Recomm
endation
No.1)
44/I/1
(GD)
Complete
outage of
Idukki Hydro
Power Station
(GD-1)
28-04-2015
at 12:30 Hrs
220 kV breaker of unit-3 at Idukki
Power
house flashed and bus differential
protection
acted. All Generators (6Nos.) along
with all
220 kV feeders tripped during the
incident.
1. KSEB to reduce sensitivity of REF
protection appropriately at Idukki PH.
2. KSEB to replace/ repair the faulty breaker.
3. KSEB to check the PLCC equipment at New
Pallam and inform the remedial measures taken
to PCSC forum.
KSEB
Annexure-II
Page 12 of 24
41/III/2 Tripping of
400kV
Udumalpet-
Palakad line-
1& 400
Udumalpet-
Arasur line-2
09-02-2015
at 9:50hrs
PLCC of Udumalpet-Arasur-2 mal-
operated
• PGCIL to furnish remedial measures taken.
• PGCIL to properly tune PLCC panels.
PGCIL Mail received on 25-11-2015:
The issue was referred to BPL and OEM suggested to upgrade the
panels with design modifications. LOA has been placed on BPL for
the same. Work is expected to be completed by Nov'15 end.
Pending
42/II/22 Tripping of
HVDC pole-
1&2
at Gazuwaka
and 400kV
Jeypore
Gajuwaka
line -1
14-03-2015
at
17:12 hrs
HVDC Pole-1 at Gazuwaka tripped
due to
tripping of filter banks and Pole-2
tripped due to operation of
differential protection.
400kV Jeypore-Gazuwaka line-1
tripped on over-voltage from
Gazuwaka end.
PGCIL (SR-I) to furnish the reasons for
Converter Transformer differential protection
operation for Pole-2 along with the remedial
measures taken.
PGCIL Reply received during 46th PCSC meeting:
Operation is in-order as per OEM manual (ABB HVDC)
Pending
PGCIL34/I/7 HVDC
BHADRAV
ATHI POLE
2
18-07-2014 As reported pole-2 tripped due on
5th harmonic alarm.
1. Complete analysis of the faults and
rectification/remedial action taken to avert
similar occurrence in the HVDC Back to Back
station shall be submitted.
2. The PCSC forum recommended PGCIL,
SRTS-I take up the issue with WRTS to submit
the report as per IEGC guidelines.
3. SRLDC is also requested to send a letter to
WRLDC to submit the reports to SR also.
4. Based on the SRTS/SRLDC
correspondences, SRPC would take it up with
WR and PGCIL if the issue is not getting
resolved.
PGCIL Reply received during 46th PCSC meeting:
Being pursued with POWERGRID, WR-1
Pending
Pending42/II/7 Yet to be informedPGCILPGCIL (SR-II) to submit the report of M/s
ABB’s on preventing supply card failures.
HVDC pole-1 got tripped due to
failure
of 4 no. power supply card. HVDC
pole-2 tripped on DC low voltage
trip.
400kV Jeypore-Gazuwaka line-
1&2
tripped due to operation of Over
voltage
protection at Gazuwaka end.
23-02-2015
at
13:34 hrs
Tripping of
400kV
Jeypore-
Gazuwaka
line-
1&2 and
tripping of
HVDC back
to back pole-
1&2 at
Gazuwaka
Annexure-II
Page 13 of 24
42/II/23 Tripping of
HVDC
Bhadravathi
Pole-1
18-03-2015
at
13:55 hrs
Pole tripped due to failure of
auxiliary supply
PGCIL (SR-I) to submit the compliance report
on PSAG-11 recommendations to PCSC
forum.
PGCIL Reply received during 46th PCSC meeting:
Tertiary Transformer charged and auxiliary power for HVDC is being
availed from tertiary widings of ICT.
Pending
Annexure-II
Page 14 of 24
44/I/3
(GD)
765 kV
Raichur-
Sholapur line
1 &
2 tripped
24-05-2015
at 19:19 hrs
Tripped on Overload. 1. PGCIL to provide the status of healthiness of
SPS contact logic in SRLDC’s SCADA.
2. PGCIL to furnish the details of the
implemented SPS-7 scheme including logic
diagram to PCSC forum.
PGCIL Yet to be informed Pending
43/II/2 Multiple
tripping
at 400/230kV
Hosur
substation
of Powergrid
26-03-2015
at 15:40 hrs
230kV Bus-2 at Hosur (PG) got
tripped as spurious initiation got
extended to LBB relay of 230kV
Hosur-Hosur(PG) line at
Hosur(PG) end due to shorting of
contacts in lockout relay.
400/230kV ICT-2, ICT-3, 230kV
Hosur-Vinnamangalam,
230kV Hosur(PG)-Hosur which
were connected to Bus-2 got
tripped along with bus coupler
breaker
PGCIL (SR-II) to check the possibility of
providing re-trip feature in LBB relay.
PGCIL Mail received on 02-09-2015:
The scheme was tested thoroughly found normal.
Pending
PendingYet to be informedPGCILPGCIL (SR-I) to check healthiness of PLCC
panels at Hyderabad SS, and repair/ replace
them, if necessary.
400kV Ramagundam-Hyderabad
line-3 at
ramagundam end only due to DT
receive.
400kV Hyderabad-Malkaram line-
1
tripped at Hyderbad end only and
was
holding from Malkaram end.
400kV Bus-1 at Hyderabad due to
operation of bus
bar protection.
23-04-2015
at
15:11 hrs
Tripping of
400kV
Ramagundam-
Hyderabad
line-3,
400kV
Hyderabad-
Malkaram
line-1 and
400kV Bus-1
at Hyderabad
44/II/4
Multiple
tripping at
Vemagiri
substation of
APTRANSC
O
44/II/6 PendingYet to be informedPGCIL1. PGCIL (SR-I) to enable Auto reclosure
feature at Vijayawada end.
2. PGCIL (SR-I) to check distance relay
settings for Vijayawada – Vemagiri line 3, and
furnish a compliance report to PCSC forum.
400kV Vemagiri-Vijayawada line-
1&3, 400kV Vemagiri-Goutami
line-2, 400kV Vemagiri-
Konaseema line-2 and 400/220kV
ICT-2 at Vemagiri tripped
during the incident. Triggering
incident
was failure of B-phase L.A in
400kV
Vijayawada-Vemagiri line-1 at
Vemagiri end.
25-04-2015
at 10:04
hrs
Annexure-II
Page 15 of 24
44/II/7 Tripping of
765kV
Kurnool-
Tiruvalam
line-1
and 765kV
Kurnool-
NPS-1
25-04-2015
at
18:10 hrs
REF protection of Line reactor of
Nellore-1&2 and Tiruvalam line-1
maloperated
due to DC earth fault
1. PGCIL (SR-I) to submit the action taken
report on the measures suggested by their
OEM.
2. PGCIL (SR-I) to check for the availability of
Chatter Disable feature in P141 and
configure it appropriately to block operation of
REF protection on DC fluctuations.
PGCIL Yet to be informed Pending
44/II/8 Tripping of
400kV
Gooty-NPS
line-2
26-04-2015
at 13:16
hrs
R-phase to earth fault had occurred
in
line. Lines auto-reclosed at gooty
end
and later tripped due to DT receive
from
NPS end.
PGCIL (SR-I) to coordinate STUB protection
settings with the distance protection time
settings at NPS.
PGCIL Yet to be informed Pending
45/II/21 Tripping of
400/220kV
ICT-1 at
Gooty
Substation
03-06-2015
at 12:30 hrs
ICT tripped due to mal-operation
of differential relay
1. PGCIL to follow IS and CEA regulations
while carrying out maintenance work.
2. PGCIL to furnish a report on what caused
the ICT-1 tripping including remedial
measures.
PGCIL Yet to be informed Pending
PendingYet to be informedPGCILTo avoid tripping of transmission lines on
transient faults, PGCIL is recommended to
carry out periodic patrolling of lines, and
ensure their proper maintenance by carrying
out jungle/ bushing clearance and trimming of
tree branches within the RoW of transmission
lines as per the SRPC transmission line
patrolling guidelines (available under the menu
item "All Uploads Operation
Miscellaneous Transmission Line Patrolling
Protocol / Guidelines for Southern Region" on
SRPC website).
Lines tripped on transient fault.
Auto reclose was un-successful. SR
&NEW grid separated due to
tripping of 765kV lines
03-05-2015
at 4:13 hrs
Tripping of
765kV
Raichur-
Solapur line-
1&2
45/II/15
Annexure-II
Page 16 of 24
46/II/1 Tripping of
400/220kV
ICT-2 at
Nagarjunsaga
r Station
16-06-2015
at 18:12
hrs& 19:18
hrs
ICT-2 tripped due to mal-operation
of 86B relay due to suspected DC
earth fault.
PGCIL (SR-I) to furnish a detailed report on
ICT-2& Bus II outage at 19.18 hrs on
16.06.2015 along with the remedial measures
taken.
PGCIL Yet to be informed Pending
46/II/4 Tripping of
400/220kV
ICT-2 at
Gooty
substation
22-06-2015
at 13:06 hrs
At 220kV Gooty Switching
Station, 220KV Gooty Receiving
Station feeder line side Y-Phase
jumper connected between line
isolator to boom resulting in a
220kV Bus fault. This resulted in
tripping of ICT-2 and 220kV
feeders connected to 220KV BUS-
II
PGCIL (SR-I) to furnish a detailed report as to
what caused LBB operation at 400 kV Gooty
SS along with the remedial measures taken.
PGCIL Yet to be informed Pending
Tripping of
HVDC
Talcher-Kolar
Pole-2.
45/II/29
PendingYet to be informedPGCIL1. PGCIL (SR-I) to furnish a report detailing
the sequence of events including the remedial
measures taken to PCSC forum.
2. PGCIL (SR-I) to verify and ensure time-
synchronizationof DR& EL with GPS at both
Gooty and NPS.
3. PGCIL (SR-I) to check and resolve,in co-
ordination with APTRANSCO, the professed
Phase-Discrepancy that is found to be
occurring between 400 kV Gooty (PG) SS and
the surrounding 220 kV network of
APTRANSCO in the event of a fault.
Breaker at NPS end tripped on
Direct Trip receipt from NPS end.
After 4 seconds, over voltage
protection operated at NPS end as
observed from EL, and direct trip
was sent to Gooty.
01-07-2015
at 09:59 hrs
Tripping of
400kV Gooty-
NPS line-1
46/II/13
PendingMail received on 25-11-2015:
Major Shut Down of HVDC Bi-pole line for replacement of insulators
in Polluted Streched is planned from 07th 11th January-16 scheduled.
PGCILTo avoid tripping due to transient faults,
PGCIL (SR-I) is recommended to carry out
periodic patrolling of lines, and ensure proper
maintenance of transmission lines by carrying
out jungle/ bushing clearance and trimming of
tree branches within the RoW of transmission
lines as per the ‘SRPC transmission line
patrolling guidelines’ (available under the
menu item "All Uploads Operation
Miscellaneous Transmission Line Patrolling
Protocol / Guidelines for Southern Region" on
SRPC website).
DC line fault26-05-2015
at 17.55 hrs
Annexure-II
Page 17 of 24
47/II/11 Tripping of
HVDC
Bhadrawati
Pole-1
05-08-2015
at 10:53 hrs
Main pump-2 of valve cooling got
tripped during dip in 33kV
auxiliary bus
voltage. Valve cooling flow got
reduced
due to tripping of pump and
resulting in
tripping of pole-1
PGCIL (SR-I) to furnish compliance report on
PSAG-11 recommendations without further
delay to PCSC
forum.
PGCIL Yet to be informed Pending
765 kV
RAICHUR -
SHOLAPUR
1 and 2
04-09-2015
at
19:25 hrs
Sholapur -1 and 2 Feeder got
tripped at Raichur end on operation
of over current
protection in Main-1 distance relay
and holding from Solapur end on
04.09.2015 at
19:24:42 Hrs
765 KV
RAICHUR –
KURNOOL 2
04-09-2015
at
19:25 hrs
Kurnool -II Feeder got tripped on B-
N fault and holding from Kurnool
end (successfully auto-reclosed at
Kurnool end) subsequently tripped
at other end on operation of OV stg-
1 protection at Raichur end on
04.09.2015 at 19:24 Hrs
49/II/4 Tripping of
400kV Gooty-
NPS line-1
13-10-2015at
10:15 hrs
DT was sent to NPS end of line-1
during opening of Main CB of
Gooty-NPS line-2 at Gooty end.
This resulted in tripping of line-1
at NPS and line was holding from
Gooty. OV protection got operated
at NPS end and resulted in tripping
of line
1. PGCIL (SR-I) to configure time scale
resolution in Event Logger to msec. at Nelllore
PS (NPS) and furnish DR corresponding to
OVR, Stag-I operation at NPS end during the
tripping event.
2. PGCIL (SR-I) to ensure time-sync of DR’s
and EL’s with GPS at Gooty & NPS.
PGCIL Yet to be informed Pending
47/II/18 1. PGCIL (SR-I) to check the A/R scheme
implemented through BCU’s at all its GIS/
SAS substations for correct
operation.
2. PGCIL (SR-I) to ensure time-
synchronization of DR & EL of 765 kV
Kurnool SS with GPS.
3. PGCIL (SR-I) to sort out the LEGEND
ISSUE related to tripping of the lines in the
Event Logger of Raichur.
4. PGCIL (SR-I) to check & ensure the
functionality & healthiness of synchronization
facility at Raichur end at
the earliest opportune time.
PGCIL Yet to be informed Pending
46/II/22 PendingYet to be informedPGCIL1. PGCIL (SR-I) to obtain from PGCIL (WR-l)
the reasons for DT receipt from Sholapur end
and furnish thesame along with the remedial
measures taken to PCSC forum.
2. PGClL (SR-I) to verify the logic
implemented of SPS-1 and SPS-7 for the 76S
kV Raichur - Sholapur link byavailing the line
shutdown at the earliest opportune time.
3. PGCIL (SR-I) to furnishthe details of the
implemented SPS-1 and SPS-7 schemes
including their logicdiagrams to PCSC forum.
28-07-2015
at 11.52.22
hrs.
Separation of
SR-grid and
NEW-grid
Annexure-II
Page 18 of 24
41/II/12 Tripping of
400KV
Coastal-
NTPL line
13-02-2015
at 22:54 hrs
Line tripped B-phase to earth fault
and later tripped on R-Y phase
fault. From Coastal end D.R, Y &
B poles of breaker opened first and
R-pole appears to be opened on
Pole discrepancy.
CEPL to check A/R scheme at their end. CEPL Yet to be informed Pending
41/IV/2 400kV
Tuticorin PS-
NTPL line
09-02-2015
at 03:17 hrs
Y-phase to earth fault had occurred
in line. Line auto reclosed at
Tuticorin PS end and failed to
reclose at NTPL end.
NTPL to check A/R scheme at their end. NTPL Yet to be informed Pending
44/III/4 Tripping of
400kV
Coastal
(CEPL)-
Tuticorin
pooling
station
20-04-2015
at 12:35 hrs
Line tripped at Coastal energen end
only and was holding from
TTRNPS
CEPL to furnish a detailed report on this trip
event to PCSC forum.
CEPL Yet to be informed Pending
46/II/3 Tripping of
400kV
Ramagundam-
Dichipalli
line
21-06-2015
at 03:27 hrs
Line tripped on operation of
overvoltage protection at
Ramagundam end and direct trip
was received at Dichipalli. Over-
voltage operation could not be
established with D.R & E.L
submitted by Ramagundam station.
1. NTPC, Ramagundam to investigate the
reasons for OV alongside checking the drop off-
to- pick-up ratio of the OV relay.
2. The tripping is not as per the grading
adopted for OV, Stage-I protection (Grading is
C2: 110% and 6 sec time delay) at
Ramagundam. NTPC, Ramagundam to check
up the same.
NTPC Yet to be informed Pending
47/III/2 Tripping of
400kV
Vemagiri –
GVK (JPD)
line-2
16-07-2015
at 17:02 hrs
R-phase to earth fault had occurred
in line. Line auto reclosed at
Vemagiri end and failed to reclose
at GVK end.
GVK to put A/R into service at GVK
Jegurupadu end on 400 kV GVK (Jegurupadu)
– Vemagiri line-2.
GVK Yet to be informed Pending
48/II/16 Tripping of
400 kV
Hassan -
Udupi line-1
05-10-2015
at 13:33
Line tripped due to B-E fault in Z2.
Main 1 relay tripped in Z2. 3 phase
trip operated at Hassan. AR
successful at other end and line
was charging from other end. Then
OV stage 1 picked up in Main2
relay and operated in OV after the
time delay
UPCL to furnish reasons for delayed operation
of distance relay in Zone-1 at their end, and the
remedial measures taken, if any.
UPCL Mail recieved on 19-11-2015 (UPCL):
The fault was of resistive nature, was sensed from Hassan end in Zone-
2 reach. The DR from UPCL indicates resistive high current prior to
operation of Zone-1 in C Phase. This is seen as development of Zero
sequence voltage and current prior to Zone -1 operation.
The operation of single phase Z1 from UPCL end was correct
followed by successful AR operation.
Pending
Others
Annexure-II
Page 19 of 24
36/II/8 400kV
Raichur-
Munirabad
line
07-09-2014 B-phase to earth fault had occurred
in line.
Line auto reclosed at Munirabad
end and failed to reclose at Raichur
end.
KPTCL:
PD (pole discrepancy) time delay would be
changed.
PGCIL /
KPTCL
Yet to be informed Pending
38/II/5 400kV
Ramagundam-
Hyderabad
line-4
27-10-2014 Line tripped on Bphase
to earth fault.
Line did not auto
reclose at Hyderabad
end due to
PLCCmal-operation.
Planned to replace the PLCC system within a
week's time at both the ends during the
shutdown.
NTPC/
PGCIL
Yet to be informed. Pending
Miscellaneous
39/I/2 Tripping of
400Kv
Ghanapur-
Mamidipally
line
22-12-14
at 10:52 hrs,
24-12-14 at
11:32
hrs,
24-12-14 at
16:16 hrs
Due to PLCC Mal-operation at
HYD S/S end, DT received at
MMPLY end and line got tripped.
PGCIL is requested check up with the
manufacturer to resolve the issue and submit
remedial measures to PCSC forum.
PGCIL/
TSTRANSC
O
Mail received on 26-05-2015 from TSTRANSCO:
On 27-12-2014 PGCIL requested to arrange services of
OEM(Manufacturer)for identifying the problem. TSTRANSCO
arranged the same on 06-01-2015 and the manufacturer testing and
concluded that the problem in not in the newly erected digital
protection coupler at both ends and the issue is related to relay panel
at Ghanapur. [OEM minutes enclosed]
Pending
Annexure-II
Page 20 of 24
40/II/3 Tripping of
400
kV
TALAGUPP
A
– HASSAN
line
01-01-2015
at
13:38 hrs
On account of R-phase to earth
fault, line tripped at Hassan end
due to operation of distance Zone-2
and non-receipt of
carrier. From D.R of Talaguppa
end it is observed that fault had
occurred in Yphase.
1. PGCIL and KPTCL to ascertain the reason
for the phase discrepancy in the relay
operation and take suitable remedial measures.
2. KPTCL to check the PLCC operation at
Talaguppa end and submit the report to the
PCSC forum.
PGCIL/
KPTCL
Mail received on 27-05-2015 (KPTCL) & 29-07-2015:
End to end testing of PLCC has been done and problem in the PLCC
is atttended. Phase
discripancy in the relay operation is to be checked jointly.
Mail recieved on 02-09-2015:
Problem is in identification of phases at Talguppa end. To be rectified
by M/s KPTCL.
Pending
41/I/2 Complete
outage at
220kV
Bahoor
Substation of
Pondicherry
(GD-1)
15-02-2015
at 11:20 hrs
Bus fault occurred in 110kV bus at
230/110kV Bahoor substation due
to failure of Y-phase main bus
strain insulator. 220kV lines
connected to Bahoor (viz., Bahoor-
NLC TPS II and Bahoor – Pondy)
tripped from remote end on
operation of B/U protection.
1. PED to investigate the cause of non-
operation of ICT’s protection system
(differential protection, back-up protection)
and review the relay settings suitably.
2. PGCIL to check the settings of distance
relay and back-up relays for correctness of
operation.
PED/PGCIL Mail received on 02-09-2015 and 25-11-2015:
All the relay settings were checked and found ok
Pending
with
PED.
42/II/1 Tripping of
400kV
Coastal-
Tuticorin PS
line
19-02-2015
at
16:37 hrs
Line tripped at Coastal end only
due to suspected PLCC
maloperation
and was holding from
Tuticorin PS end. Running Unit at
Coastal energen also got tripped
during the event.
PLCC end-to-end testing shall be carried out by
CEPL and Tuticorin PS (PGCIL-SR II) by
06.04.2015.
CEPL/
PGCIL(SR-
II)
Mail received on 02-09-2015 and 25-11-2015:
On 11.06.2015 PLCC testing carried out by M/s ABB Engineer. ABB
suspects that the problem is with frequency interference related issue,
and suggested to change to new frequecies.
Pending
with
CEPL
Annexure-II
Page 21 of 24
43/II/12 Multiple
tripping at
400kV
Raichur(PG)
and RTPS of
KPCL
11-04-2015at
18:04 hrs
400kV Raichur(PG)-Gooty line-2,
400kV Raichur TPS-Raichur(PG)
line-1&2, 400kV Raichur-
Mahboobnagar, Unit#5 at RTPS
tripped during the incident
KPCL, KPTCL and PGCIL (SR-I) to furnish
the action taken report on the
recommendations given by PSAG members
held at Raichur on 22-04-2015 and
23-04-2015.
KPCL/KPTC
L/ PGCIL(SR-
I)
Yet to be informed Pending
Tripping of
Unit 1 at
NCTPS
24-05-2015
at 19:13 hrs
ID Fan trip
Tripping of
Unit 1 at
MEPL
24-05-2015
at 19:13 hrs
Coal Mill tripped
Tripping of
Unit 1 at
Krishnapatna
m
24-05-2015
at 19:17 hrs
Generator Protection operated
Tripping of
Unit-8 at
RTPS
24-05-2015
at 19:19 hrs
Tripped on Overvoltage.
Mail received on 26-05-2015 from TSTRANSCO:
It is found that the main-2 ABB make REL316 type distance relay
was defective and same was replaced with MICOM P444 by
M/s.PGCIL on 23.04-2015. After replacement of main-II, DR can be
extracted from this relay. For EL in to service, some field winding is
pending which is being taken up in this month.
Pending
44/I/3
(GD)
1. All Tripped units, viz., Krishnapatinam,
MEPL, Raichur, NCTPS to submit a detailed
report
on this event including the remedial measures
taken to PCSC forum.
2. KPCL to check the excitation system of Unit
8 of RTPS, and submit the remedial measures
taken to PCSC forum.
KPCL/
MEPL/
APGENCO/
TNEB
TANGEDCO vide their mail dated 07.07.2015 informed that as per
the discussion and recommendation of 44th meeting of PCSC held on
28.05.2015, a time delay of 2 Sec had been introduced for the above
tripping for all the ID fans at NCTPS-II.
MEPL vide their mail dated 14.09.2015 informed that they have
implemented 2 seconds delay for under voltage tripping of all Drag
Chain Feeder Conveyors. And this has been done for both the Units.
Pending
with
KPCL,
APGEN
CO
42/II/18 Multiple
tripping at
Raichur
thermal
power station
of
KPCL
09-03-2015
at
06:36 hrs
400kV Raichur TPS-Raichur(PG)
line-
1&2, 400kV Raichur-
Mahboobnagar,
Unit#7 and ICT-2 at RTPS tripped
during the incident. B phase to
earth
fault had occurred in 400kV
Raichur
TPS-Raichur line-1
1. KPCL to review REF setting (DMT or
IDMTL) for unit-7 by first week of April, 2015
and
inform the same to PCSC forum.
2. TSTRANSCO to furnish Mehaboobnagar’s
DR and EL and the reasons for distance relay
operation at their end within a week’s time.
3. PGCIL (SR-I) to rectify the issues relating to
A/R operation, relay reach (Z2), reverse reach
(Z4) and SOTF auxiliary contacts within a
week’s time, and submit the actions taken to
PCSC forum.
KPCL/TSTR
ANSCO/PGC
IL (SR-I)
Annexure-II
Page 22 of 24
Complete
outage of
Krishnapatna
m TPS
47/I/2
(GD)
PendingMEPL vide their mail dated 14.09.2015: informed the following
1. Tan Delta Testing of winding and DGA of Insulating Oil for all
CTs was carried out and normal.
2. Could not find any problem during internal checks hence we are in
touch with ABB for rectification work. Will be done by the end of
15th Oct'15
3. End to end testing of Carrier signals was carried out and found
them healthy.
MEPL/
PGCIL(SR-
I)/ SEL
1. MEPL to ensure healthiness of all CT’s by
carrying out Tan Delta and DGA tests wherever
necessary.
2. MEPL to take suitable action to correct the
operation of tie-CB Bay Control Unit that
caused LBB/ BBP operation.
3. PGCIL (SR-1) to carry out end-to-end
PLCC testing in coordination with MEPL and
ensure that carrier-aided protection on MEPL –
NPS line is in healthy condition.
4. SEL to properly time-coordinate their Over
Current phase and Earth fault relays in
consultation with MEPL.
Y phase CT failure at MEPL led to
tripping of 400kV NPS-MEPL,
400kV SEPL-MEPL line and Unit-
2 at MEPL. Uni-1 was not in
service at the time of tripping
20-05-2015
at 20:38 hrs
Complete
outage of
MEPL power
station
45/I/2
(GD)
Tripping of
220kV Kadra-
Karwar line-
1&2 and
220kV
Kaiga-Kadra
line
47/II/7 PendingYet to be informedKPTCL/
KPCL/
NPCIL
1. KPTCL/ KPCL to see the possibility of
implementing Weak Infeed logic with Echo
feature enabled by Under
Voltage (27) element on Kadra-Karwar lines 1
&2, and implement the same if feasible.
2. NPCIL to time-coordinate Kaiga’s DEFR
settings with (i) Zone-2 settings at Kaiga, and
(ii) primary protections of the lines emanating
from Kadra and Kodasalli.
3. KPCL to ensure time-sync of EL’s, and
healthiness of the Fault Locators at Kadra.
220kV KAdra-Karwar lines-1&2
tripped on earth fault in B-phase in
zone-2.
Kaiga-Kadra line tripped at Kaiga
end only on operation of
directional eath
fault protection.
31-07-2015
at
11:44 hrs
PendingYet to be informedAPGENCO/
PGCIL (SR-
I)
1. APGENCO to furnish to PCSC forum (i) A3-
size SLD of SDSTPS, and (ii) the sequence of
events with time stamp showing the protection
that opened Tie-CB (405) at SDSTPS.
2. APGENCO to review STUB/TEED
protection in all dias at SDSTPS and ensure
that they are configured for instantaneous
operation.
3. APGENCO to properly configure the STATE
of the tripping events so that they get recorded
appropriately like TRIP/ OPERATED in their
corresponding EL.
4. APGENCO to ensure time sync of all DR’s
and EL’s at SDSTPS.
5. PGCIL (SR-I) to provide line differential
protection for 400 kV NPS –Nellore-PG lines 1
& 2.
As per FIR submitted, CT damage
observed in Chitoor-Main bay
(404). Main breakers connected to
bus-1 (401, 404, 407, 410) got
tripped on operation of bus bar
protection. Unit-1 tripped on
operation of MFT. Unit-2 was not
in service
08-09-2015
at 18:20 hrs
Annexure-II
Page 23 of 24
48/III/11 Tripping of
400 kV
Kurnool –
Srisailam line
03-10-2015
at 04:40 hrs
on
Tripped at both ends on Y-Phase to
ground zone-1fault. Attempt for
auto-reclose could not be
established.
TSGENCO/ APTRANSCO to carry-out PLCC
end-to-end testing in co-ordination with
APTRANSCO/ TSGENCO to sort out
reception of signals on 400 kV Kurnool –
Srisailam line.
TSGENCO/
APTRANSC
O
Yet to be informed Pending
49/II/11 Tripping of
400/220 kV
ICT-2 at
Kurnool
Substation
and 400kV
Kurnool-
Srisailam line
26-10-2015
at 14:31 hrs
400kV Kurnool-Srisailam line -
distance protection zone-2 had
operated at Srisailam end.
However from DR, R-phase to
earth fault and zone-2 start were
observed. Breakers at Kurnool end
tripped on direct trip receive from
Srisailam end.
ICT-2 Main-CB tripped due to
operation of bus bar protection,
and Tie-CB tripped due to DT
receipt from Srisailam
1.TSGENCO in coordination with
APTRANSCO to carry out end-to-end testing
of PLCC channels by 15.12.2015 on 400 kV
Srisailam – Kurnool S/C line and 400 kV
Srisailam – Sattenapalli D/C line.
2. TSGENCO and APTRANSCO to make A/R
functional on 400 kV Srisailam – Kurnool line.
3. TSGENCO to resolve configuration
problems with the newly commissioned relays
at Srisailam LB so that unwarranted DT
sending to remote ends is addressed.
TSGENCO/
APTRANSC
O
Yet to be informed Pending
Tripping of
220kV Kadra-
Karwar line-
1&2 and
220kV
Kaiga-Kadra
line
47/II/7
PendingYet to be informedNTPL/ CEPL1. NTPL to ensure (i) proper DATE settings,
and (ii) time-sync with GPS for DR and EL at
NTPL.
2. CEPL to furnish remedial measures taken
regarding PLCC channel failure.
R-phase to earth fault had occurred
in 400kV Coastal NTPL line. Line
autoreclosed
at NTPL end and failed to
reclose at Coatal end. Auto reclose
block was persisting due to PLCC
channel fail. Also running Units-
1&2 at NTPL tripped on operation
of GT
differential protection.
Tripping of
400kV
Coastal-
NTPL line
and running
units
at NTPL
47/II/9 03-08-2015
at
15:43 hrs
PendingYet to be informedKPTCL/
KPCL/
NPCIL
1. KPTCL/ KPCL to see the possibility of
implementing Weak Infeed logic with Echo
feature enabled by Under
Voltage (27) element on Kadra-Karwar lines 1
&2, and implement the same if feasible.
2. NPCIL to time-coordinate Kaiga’s DEFR
settings with (i) Zone-2 settings at Kaiga, and
(ii) primary protections of the lines emanating
from Kadra and Kodasalli.
3. KPCL to ensure time-sync of EL’s, and
healthiness of the Fault Locators at Kadra.
220kV KAdra-Karwar lines-1&2
tripped on earth fault in B-phase in
zone-2.
Kaiga-Kadra line tripped at Kaiga
end only on operation of
directional eath
fault protection.
31-07-2015
at
11:44 hrs
Annexure-II
Page 24 of 24
Sl.No. Element NameOutage
date/time
Revival
date/time
Reason for
OutageSender/ Receiver
Remedial Measures/ Actions
taken
1400 Kv KRISHNAPATNAM -
NELLORE
20-07-
2015/11:27:00
20-07-
2015/12:00:00
BUS -1
TRIPPED :
REASON
AWAITED
APGENCO/
APTRANSCO
APGENCO: BUS-1 was tripped
at Power Grid Sub-
Station(PGCIL), Nellore during
the operation of the Isolators,
which is not pertaining to
APGENCO.
APTRANSCO: Line tripped at
Krishnapatnam end only.Line is
in service from Nellore-AP.
PGCIL (SR-I):
2 220 kV AMBEWADI - PONDA 127-09-
2015/15:53:00
27-09-
2015/16:38:00
DUE TO BUS
DEAD AT
AMBAWADI
STATION
KPTCL/ GOA To-be-discussed
3 220 kV AMBEWADI - PONDA 227-09-
2015/15:53:00
27-09-
2015/18:43:00
DUE TO BUS
DEAD AT
AMBAWADI
STATION
KPTCL/ GOA To-be-discussed
Pending Remedial Measures/ Actions taken
for the Critical Tripping Incidents (as on 14-12-2015)
Annexure-III
Page 1 of 8
4 400 Kv NCTPS - SVCTM-I05-10-
2015/14:31:00
05-10-
2015/15:44:00
TRIPPED ON R-
PH FAULT
TANGEDCO/
TANTRANSCO
TANTRANSCO: Temporary
fault. AR lockout at both ends.
Feeder normalised at 15:43 hrs. on
05.10.2015.
TANGEDCO:
5 400 Kv VTPS - MALKARAM 112-10-
2015/11:40:00
12-10-
2015/16:01:00
TRIPPED ON B-
PH FAULT
APGENCO/
TSTRANSCOTo-be-discussed
6 400 Kv VTPS - MALKARAM 113-10-
2015/12:55:00B-N FAULT
APGENCO/
TSTRANSCOTo-be-discussed
7 400/220 kV ICT-1 AT BTPS30-10-
2015/21:02:00
30-10-
2015/22:42:00TRIPPED KPCL To-be-discussed
8400 Kv GAJWEL - SHANKARPALLY
1
02-11-
2015/11:33:00
02-11-
2015/11:59:00R-N FAULT TSTRANSCO To-be-discussed
9400 Kv GAJWEL - SHANKARPALLY
1
02-11-
2015/12:22:00
02-11-
2015/14:40:00R - N FAULT TSTRANSCO To-be-discussed
10 400/220 kV ICT-2 AT KAIGA03-11-
2015/08:26:00
03-11-
2015/09:49:00
TRIPPED ON
DIFFERENTIA
L
PROTECTION
KAPS To-be-discussed
11 400/110 kV ICT-3 AT SALEM10-11-
2015/03:49:00
10-11-
2015/05:04:00
DUE TO OVER
FLUX RELAY
ACTED
TANTRANSCO
TANTRANSCO:
Due to raise in 400 KV grid
voltage, Over fluxing relay
operated. The Frequency variation
from 49.90 Hz to 50.09 Hz was
recorded during the tripping of all
ICTs.
Annexure-III
Page 2 of 8
12 400/230 kV ICT-1 AT SALEM10-11-
2015/03:53:00
10-11-
2015/04:49:00
DUE TO OVER
FLUX RELAY
ACTED
TANTRANSCO
TANTRANSCO:
Due to raise in 400 KV grid
voltage, Over fluxing relay
operated. The Frequency variation
from 49.90 Hz to 50.09 Hz was
recorded during the tripping of all
ICTs.
13 400/230 kV ICT-2 AT SALEM10-11-
2015/03:51:00
10-11-
2015/04:57:00
DUE TO OVER
FLUX RELAY
ACTED
PGCIL (SR-II)/
TANTRANSCO
TANTRANSCO:
Due to raise in 400 KV grid
voltage, Over fluxing relay
operated. The Frequency variation
from 49.90 Hz to 50.09 Hz was
recorded during the tripping of all
ICTs.
PGCIL (SR-II):
14 400/110 kV ICT-4 AT SALEM10-11-
2015/02:29:00
10-11-
2015/07:17:00
TRIPPED DUE
TO OVER
FLUX
TANTRANSCO
TANTRANSCO:
Due to raise in 400 KV grid
voltage, Over fluxing relay
operated. The Frequency variation
from 49.90 Hz to 50.09 Hz was
recorded during the tripping of all
ICTs.
15 400/230 kV ICT-4 AT SALEM11-11-
2015/04:42:00
11-11-
2015/17:58:00
TRIPPED DUE
TO OVER
FLUX
PGCIL (SR-II)/
TANTRANSCO
TANTRANSCO:
Due to raise in 400 KV grid
voltage, Over fluxing relay
operated. Carried out the
maintenance work and the
overfluxing relay was tested and
healthiness was ensured.
PGCIL (SR-II):
Annexure-III
Page 3 of 8
16 400 kV KAIGA - GUTTUR 213-11-
2015/18:21:00
TRIPPED ON R-
PH FAULTKAPS/ KPTCL
PGCIL-SR2:
Portion of the line in which fault
occured owned and maintained by
M/s KPTCL. May be clarified
from M/s KPTCL
KPTCL:
KAPS:
17 400 kV KAIGA - GUTTUR 215-11-
2015/22:04:00
DISTANCE
PROTECTIONKAPS/ KPTCL To-be-discussed
18 400 Kv NCTPS - SVCTM-I16-11-
2015/17:24:00
16-11-
2015/18:28:00Y -N FAULT
TANGEDCO/
TANTRANSCO
TANTRANSCO: Temporary
fault. Feeder normalised at 18:28
hrs. on 16.11.2015.
TANGEDCO:
19 220 kV CHITTOR - THIRUVALEM18-11-
2015/11:20:00
18-11-
2015/16:18:00
BUSBAR
PROTECTION
OPERATED @
CTR END
APTRANSCO/ TNEB
TANTRANSCO:
There was no tripping of 230kV
Thiruvalam – Chitoor feeder on
18.11.2015 at Thiruvalam end.
APTRANSCO:
20400 Kv KRISHNAPATNAM -
CHITTOOR
21-11-
2015/07:18:00CB PROBLEM
APGENCO/
APTRANSCOTo-be-discussed
21 400 kV KAIGA - GUTTUR 223-11-
2015/13:15:00
23-11-
2015/19:39:00
DISTANCE
PROTECTIONKAPS/ KPTCL To-be-discussed
Annexure-III
Page 4 of 8
22 400 Kv HASSAN - UPCL 223-11-
2015/12:53:00
23-11-
2015/13:14:00
B-PH ZONE-1
DISTANCE
PROTECTION
OPERATED
PGCIL-SR2/ KPTCL/
UPCLTo-be-discussed
23 400 kV KAIGA - GUTTUR 227-11-
2015/15:07:00
27-11-
2015/16:11:00R-G FAULT KAPS / KPTCL To-be-discussed
24 400/220 kV ICT-2 AT BANGALORE27-11-
2015/18:47:00
27-11-
2015/19:26:00
BUS BAR
PROTECTION
ACTED
PGCIL (SR-II) To-be-discussed
25 400/230 kV ICT-3 AT UDUMALPET27-11-
2015/11:25:00
27-11-
2015/11:34:00
TRIPPED ON
MAL
OPERATION
PGCIL (SR-II) To-be-discussed
26 400/230 kV ICT-3 AT UDUMALPET27-11-
2015/17:25:00
27-11-
2015/18:38:00
RELAY
MALOPERATI
ON
PGCIL (SR-II) To-be-discussed
27 400 Kv ALM - SVCTM-II27-11-
2015/15:40:00
27-11-
2015/16:37:00C -G FAULT TANTRANSCO
TANTRANSCO: 400kV
S.V.Chatram - Alamathy -1 feeder
'C' phase jumper got cut at
Loc.No.178 from Alamathy end
and created temporary fault with
400kV S.V.Chatram - Alamathy -
2 feeder 'A' phase jumper. Both
feeders runs on the same tower.
PUTT Trip and AR successful at
S.V.Chatram end. AR lockout at
Alamathy end.
28 220 kV KANIAMPET - KADAKOLA27-11-
2015/09:55:00
TRIPPED ON
DISTANCE
PROTN
KSEB / KPTCL To-be-discussed
Annexure-III
Page 5 of 8
29 400 Kv ALM - SVCTM-I27-11-
2015/15:40:00
SWITCH ON
TRANSIENT
FAULT
TANTRANSCO
TANTRANSCO: AR lockout at
both ends. C-Phase jumper cut at
LOC.NO.178 from Alamathy SS
end was attended. Feeder
normalised on 10.12.2015 at
12:45hrs.
30 400/220 kV ICT-1 AT BANGALORE27-11-
2015/18:47:00
27-11-
2015/19:15:00
BUS BAR
PROTECTION
ACTED
PGCIL (SR-II) To-be-discussed
31 400 kV KAIGA - GUTTUR 128-11-
2015/14:09:00
28-11-
2015/16:20:00B-N FAULT KAPS / KPTCL To-be-discussed
32 400 kV KAIGA - GUTTUR 129-11-
2015/01:04:00
TRIPPED ON R-
N FAULTKAPS / KPTCL To-be-discussed
33 400 kV KAIGA - GUTTUR 229-11-
2015/01:04:00
TRIPPED ON R-
N FAULTKAPS / KPTCL To-be-discussed
34400 kV DICHIPALLY -
RAMAGUNDAM
02-12-
2015/02:46:00
02-12-
2015/04:13:00B-N FAULT TSTRANSCO / NTPC To-be-discussed
35400 kV DICHIPALLY -
RAMAGUNDAM
02-12-
2015/12:40:00
TRIPPED ON B-
Y FAULTTSTRANSCO / NTPC To-be-discussed
36400 kV TALAGUPPA -
NEELAMANGALA
03-12-
2015/16:20:00
TRIPPED ON
LINE FAULTKPTCL To-be-discussed
37 400 Kv NCTPS - SVCTM-I04-12-
2015/03:54:00
04-12-
2015/04:58:00
TRIPPED ON B-
PH FAULT
TANGEDCO /
TANTRANSCO
TANTRANSCO/TANGEDCO:
Temporary fault. AR lockout at
both ends. No visible fault and
feeder normalised on 04.12.2015
at 04:58 hrs.
TANGEDCO:
Annexure-III
Page 6 of 8
38 400 Kv HASSAN - UPCL 106-12-
2015/10:40:00
06-12-
2015/10:56:00
TRIPPED ON R-
N FAULTPGCIL (SR-II) / UPCL To-be-discussed
39400 kV NEYVELI TS 2 - NEYVELI
TS2 EXP
06-12-
2015/20:35:00
06-12-
2015/23:03:00DT RECEIVED NLC To-be-discussed
40400 kV NEYVELI TS2- NEYVELI TS-
I
06-12-
2015/23:12:00
07-12-
2015/00:46:00
MALOPERATI
ONNLC To-be-discussed
41 400/220 kV ICT-3 AT TRICHUR06-12-
2015/13:50:00
06-12-
2015/21:38:00
REF
OPERATEDKSEB To-be-discussed
42 400 Kv NPS - TPCIL 210-12-
2015/03:48:00
10-12-
2015/04:56:00
RELAY
MALOPERATI
ON AT TPCIL
END
To-be-discussed
43400 Kv VIJAYAWADA - NELLORE -
AP -
10-12-
2015/10:51:00
10-12-
2015/11:46:00
TRIPPED DUE
TOBACKIP
IMPEDANCE
RELAY ACTED
To-be-discussed
44 400 kV KALPAKKA - VEMAGIRI 210-12-
2015/15:20:00
10-12-
2015/16:20:00
BUS BAR
PROTECTION
OPERATED @
KLPAKA
To-be-discussed
45 400 kV SIMHADRI - KALPAKKA 410-12-
2015/15:20:00
10-12-
2015/16:30:00
BUS BAR
PROTECTION
OPERATED @
KLPAKA
To-be-discussed
46 400/220 kV ICT-2 AT CHITTOOR11-12-
2015/07:12:00
11-12-
2015/16:23:00
BUCHOLZ
RELAY
OPERATION
To-be-discussed
Annexure-III
Page 7 of 8
47400 kV TRIVENDRUM -
TIRUNELVELI 1
11-12-
2015/04:56:00B-N FAULT To-be-discussed
48400 KV ALAMATHI -
THIRUVALLAM-1
13-12-
2015/22:42:00
Y-PH LA
BLAST @
THVLM END
To-be-discussed
49 400 kV ALAMATHI - VALLUR 213-12-
2015/22:42:00
Y-PH LA
BLAST @
THVLM END
To-be-discussed
Annexure-III
Page 8 of 8
SOUTHERN REGIONAL POWER COMMITTEE
BENGALURU
Additional Agenda for the 50
th Meeting of Protection Coordination Sub-
Committee of SRPC to be held on 27.01.2016 (Wednesday)
1. Grid Occurrences
1.1 Additional Grid Disturbance (GD), Grid Incidences (GI), and trippings due to
failure of Auto-reclosing (A/R), and Mal-operation of PLCC equipment that occurred during the period December, 2015 given at Annexure-IV would be
discussed in the PCSC meeting
Constituents are requested to furnish the following information in respect of the
above grid occurrences to have fruitful discussions in the PCSC forum.
(a) Single line diagram of the station with switching devices, CT, PT and relay
details.
(b) Cause of the tripping & Remedial Action taken
(c) Relay setting details
(d) Deficiencies / Observations as perceived by the Utility which needs PCSC’s
intervention.
Constituents are requested to bring/ give full particulars of the tripping events
pertaining to their system.
1.2 In compliance of Regulations 5.2 (r) of IEGC, the Constituents are required to
furnish the following information in respect of Grid Occurrences:
(a) First Information Report (FIR)
(b) Event Logger (EL) output
(c) Disturbance Recorder (DR) output
(d) Trip event analysis report (with pre and post fault system conditions)
Non-furnishing of tripping details including Disturbance Recorder/Sequential
Event logger output has been brought to Constituents attention vide SRPC letter
letter No. SRPC/ SE-III/ PCSC-50/ 2015/ 9091- 123 dated 18-12-2015. The non-
compliance in this regard would be discussed in the meeting.
*****
1. ग्रिडडडस्टर्बन्स / ग्रिडइन्सडन्टकावििरण - Details of Grid Disturbances:
Sr. No.
क्र.स.ं
घटनाकावििरण /
Details of Event
तारीख/ Date
&
समय /Time
कारण / Reason टटप्पणी /Remarks
शे्रणी/ Category
1
Complete outage of
TPCIL power station 30-12-2015 at
06:02hrs Running units at Thermal Power
tech power Station tripped due to
tripping of 400kV Nellore pooling
station (NPS)-TPCIL line and
400kV Nellore pooling station
(NPS)-NCC line
Gen loss : 1270 MW
GD-1
2.
Complete outage of
230kV Mywadi
station of
TANTRANSCO
21-12-2015 at
6:28 hrs Busbar protection got operated for a
fault in 230kV Mywadi-Anaikadavu
line
0
GD-1
2. डडडस्टर्बन्स / ग्रिडइन्सडन्टकावििरण - Details of Grid incidents:
Sr. No.
क्र.
स.ं
घटनाकावििरण /
Details of Event
तारीख/ Date
&
समय /Time
कारण / Reason टटप्पणी /Remarks
शे्रणी/ Category
1 Tripping of HVDC Bhadrawati Pole-2
06-12-2015 at 07:09 hrs
HVDC pole-2 tripped due to problem
in convertor transformer GI-2
2
Tripping of
400/220kV ICT-3 at
Madakathara
substation
06-12-2015 at
13:50 hrs
B-phase to earth fault had occurred in
220kV Shoranur-Madakathara line
due to snapping of earth wire. ICT-3
at Madakathara tripped on operation
of differential and REF protection for
this through fault.
3 Tripping of 400kV
Vijayawada-
Nellore(AP) line-3 10-12-2015 at
10:51 hrs
Operation of reactor Backup
Impedance protection resulted in
tripping of line. Direct trip was sent
to Nellore (AP)
3. Lines tripping due to tripping at one end/PLCC mal-operation
Sr. No.
क्र.
सं.
घटनाकावििरण / Details
of Event
तारीख/ Date &
समय /Time कारण / Reason
टटप्पणी /Remarks
शे्रणी/ Category
1
Tripping of 400 kV
Neyveli TS2-
Neyveli TS-I (EXP)
and
06-12-2015
at 23:12 hrs lines tripped due to suspected
mal-operation of PLCC
2
Tripping of 400 kV
Neyveli TS 2 -
Neyveli TS2 EXP
06-12-2015
at 20:35 hrs
lines tripped due to suspected
mal-operation of PLCC
3 Tripping of 400kV
NPS-TPCIL line-2
10-12-2015at
3:48 hrs
line tripped due to mal-operation
of PLCC and direct trip was
received at TPCIL end
Annexure-IV