southern regional power committee bangalorebond(annexure-a). accordingly, apc is provisionally taken...
TRANSCRIPT
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
Southern Regional Power Committee Bangalore Agenda for the 157th Meeting of Operation Coordination Committee
to be held on 08.07.2019 at SRPC, Bengaluru
1 Confirmation of the Minutes of the 156th Meeting of OCC of SRPC conducted on 11th
June 2019 at SRPC Bengaluru.
2 MAJOR ISSUES
2.1 Renewable forecasting
As requested by OCC forum SRLDC is presenting forecast, actuals and forecast
errors for wind and solar for the previous month in the OCC Meeting. All states
were requested to furnish the implemented forecast, day ahead forecast & actuals also. It was noted that this data was being sought by higher forums and other entities. SRLDC had informed that they are developing web application for
this and the figures are to be entered directly by the states.
Presentation and status by SRLDC. 2.2 Auxiliary Power Consumption of M/s NTECL Vallur for 2019-24
NTECL, Vallur vide letter dated 08.04.2019 had requested to consider Auxiliary
Power Consumption of 7.19% for the period 2019-24 and furnished Indemnity
Bond(Annexure-A). Accordingly, APC is provisionally taken as 7.19%, subject to the condition that NTECL obtain necessary Regulatory Order for APC rate of 7.19%
expeditiously.
Subsequently, TANGEDCO vide their letter dated 20.06.2019(Annexure-B) had informed that the APC 6.69% is provisionally considered in the April, 2019 invoice
and additional amount is deducted from the claim till the submission of CERC Order
to consider Auxiliary Power Consumption as 7.19%.
The matter may be further discussed in the meeting.
2.3 Frequent tripping of HVDC Talcher-Kolar poles
SRLDC vide letter dated 21.06.2019(Annexure-C) had informed that number of trippings/forced outages of Talcher – Kolar +/- 500 kV HVDC system in the recent
times had been increased due to various reasons. Details of trippings during the
period 31.05.2019 to 12.06.2019 is as tabulated below:
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
HVDC TALCHER - KOLAR HVDC LINES & POLES - TRIPPING DETAILS Sl. No
Line/POLE Description Outage - Date & Time
Synchronisation - Date & Time
Reason
1 LINE HVDC 500 KV-Talcher -Kolar_DC-1 (Line)
31-05-2019 18:30 31-05-2019 20:14
HVDC Line Fault
2 POLE HVDC 500 KV Kolar_DC Pole 1
31-05-2019 18:30 01-06-2019 00:09
HVDC Line Fault
3 POLE HVDC 500 KV Kolar_DC Pole 1
05-06-2019 18:53 06-06-2019 00:37
Receipt of “ESOF” signal from Talcher
4 POLE HVDC 500 KV Kolar_DC Pole 2
05-06-2019 19:01 05-06-2019 22:08
Due to tripping of all 400 kV HVDC - Talcher feeders at NTPC end
5 LINE HVDC500KV-Talcher-Kolar_DC-1(Line)
05-06-2019 19:01 06-06-2019 00:37
Due to tripping of all 400 kV HVDC - Talcher feeders at NTPC end
6 LINE HVDC500KV-Talcher-Kolar_DC-2 (Line)
05-06-2019 19:01 06-06-2019 00:37
Due to tripping of all 400 kV HVDC - Talcher feeders at NTPC end
7 POLE HVDC 500KV Kolar_DC Pole 1
08-06-2019 12:10 08-06-2019 13:01
Receipt of “ESOF” signal from Talcher
8 POLE HVDC 500KV Kolar_DC Pole 2
12-06-2019 12:24 12-06-2019 13:13
Disturbance in 24V DC system
The following had been noted:
(i) During the trippings associated SPS gets triggered and results in load shedding and generation backing down at Talcher Stage II
(ii) Karnataka/Kerala system had faced severe line loading and low voltage issues in their 400 kV stations during the outage
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
(iii) Critical 400 kV lines in the corridor, namely NP Kunta – Kolar, Gooty – Somanahally and Gooty – Nelamangala were subjected to high loading
affecting the reliability & security of the SR/All India Grid.
SRLDC requested POWERGRID to kindly analyze the root cause of the problem
and initiate remedial actions to prevent frequent tripping of Talcher – Kolar +/- 500
kV lines/poles.
2.4 Generation control during ICT -1 S/D at Tuticorin -1
SRLDC in its agenda furnished for 157th OCC had informed that RTAMC SR-II have
sent email on 26.06.2019 to regional wind generators connected to Tuticorin PS,
requesting to restrict the generation of regional wind generators during ICT -1 S/D
at Tuticorin -1
In this regard the following may be noted :
ICT- I at Tuticorin GIS 400 KV (POWERGRID) station is under OCC planned shutdown w.e.f. 10:02 hours of 26.06.2019 and the approval was up to 18:00
Hrs of 26.06.2019.
As per Clause 6.5.16 of IEGC, in the event of bottleneck & limitation in the transmission system necessitating reduction in generation, the appropriate
RLDC (SRLDC) revise the schedules of the regional entities involved which
shall become effective from the 4th Time Block, counting the time block in
which the bottleneck in evacuation of power has taken place to be the first
one.
CPCC SR2 has to inform any loading issues to SRLDC on real time which will be taken up by SRLDC depending on real time conditions as per IEGC
SRLDC desired that any direct real time instructions to Regional Entities (
generation control instructions) may please be strictly avoided in the future
2.5 Infirm power injection of MEPL Unit III Phase II
SRLDC vide letter dated 28.06.2019(Annexure-D) had informed that as per CERC Order on Petition No.6/MP/2019 dated 17.01.2019 MEPL Unit III Phase II which
was first synchronized to grid on 10.02.2018 is allowed to inject infirm power only
upto 30.06.2019 only. SRLDC requested MEPL to take up with CERC to get the
approval to inject infirm power from 01.07.2019 onwards.
2.6 Post facto revision of the net schedule of KSEBL for 31st May & 1st June 2019
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
KSEBL vide letter dated 15.06.2019(Annexure-E) had furnished the following: DSM Bill for the week 27.05.2019 to 02.06.2019 levied Rs . 26,63,297 against sign
change violations(3 violations on 31.05.2019 -19:00 hours to 24:00 hours & 1
violation on 01.06.2019 – 00:00 hours to 01;30 hours) whereas per SLDC SCADA
there is no violations. The real time operations on 31.05.2019 were based on Revision No. 218 of the net
schedule of KSEBL whereas SRPC computation was based on revision No. 223
revised on 05.06.2019 at 10:30 hours. The real time operations on 01.06.2019 were based on Revision No. 234 of the net
schedule of KSEBL whereas SRPC computation was based on revision No. 248
revised on 10.06.2019 at 16:24 hours. SLDC operations are based on real time revisions and post facto revision of the
schedule has huge commercial impact on the utility. On 31.05.2019 there was tripping of Talcher-Kolar at 18:30 hours. Levying violation
charges based on revised schedules will totally change the true spirit of operation
done by KSEBL in real time.
KSEBL requested SRLDC to revise the schedule accordingly for 31st May & 1st June
2019 and SRPC may kindly revise the DSM Bill for the week from 27.05.2019 to
02.06.2019. 2.7 Implementation of CERC Order in Petition No. 261/MP/2017 dated
06.11.2018(Kudgi)
As per the Order the annual transmission charges of the associated transmission
system(Kudgi - Narendra, Narendra-Madhugiri & Madhugiri-Bibadi and associated
bays and substations as determined or adopted by the commission needs to
considered in PoC mechanism corresponding only to the units under Commercial
operation. CTU issued operationalization of LTA from the date of completion of
ATS, 24.09.2019. Accordingly assets of the ATS needed to be covered partially
under PoC mechanism and partially under bilateral billing mechanism at different
periods.
In the 41st Meeting of Commercial Committee held on 20.06.2019 constituents had
expressed concern regarding the delay in compliance of this part of the Order.
SRPC vide letter dated 27.06.2019(Annexure-F) had taken up this issue with
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
NLDC nad had requested to furnish the necessary details to facilitate SRPC to
proceed further.
POSOCO,NLDC vide letter dated 28.06.2019(Annexure-G) had intimated that Implementation agency had carried out the PoC rate recomputation exercise in line
with the CERC Order and had submitted to CERC vide letter dated 15.04.2019 and
the revised PoC rates Order is pending with CERTC. It is suggested that SRPC
may proceed further upon issuance of CERC revised PoC Order. 2.8 Energy Scheduled inside the region and outside the region from REs
CE(RPM) division, CEA vide letter dated 03.06.2019 had requested for the details -
"Energy Scheduled inside the region and outside the region from RE generating
station which has been given connectivity & LTA on Green Energy Corridors (both
Central & State)".
Sub stations under Green Energy Corridor, WPDs/SPDs connected to these sub
stations along with Installed Capacity (MW) details & corresponding schedules and
actuals (From April 2019 to June 2019) needed to be submitted and entities had
agreed to furnish the information by 18.06.2019. Subsequently on monthly basis
Installed capacity, schedule and actual information for the previous month may be
furnished along with OCC data.
No information had been received from any of the entities(KSEBL had informed
that at present they don’t have any WPD/SPD installed under GEC).
2.9 LI projects grid integration
In view of the existing & expected addition of huge quantum of LI projects,
TSSLDC/APSLDC was again suggested to look into the frequency response, MVAR control for voltage management, MW scheduling (for 96 blocks), ramp management, SCADA integration etc.(the same was highlighted in the SC Meeting held on 10.06.2019). KPTCL was requested to check up with their ESCOMs and come up in the next OCC Meeting with more details regarding the capacity available at present, likely addition etc.
2.10 Feedback on transmission/voltage issues in SR Grid
I. High Voltage at KKNPP
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
KKNPP had been requested to absorb to the extent possible by Unit I and
restrict the MVAR injection of Unit II at the lowest level at voltages above 410
kV so that net effect of injection will be kept at minimal.
KKNPP was requested to check the tap position and Vref and revert back and
adjust the Vref accordingly so that changeover will happen at around 410 kV.
Unit II shut down is planned in November 2019 during which generator
replacement would also be taken up.
II. High Loading of Hiriyur- Nelamangala
KAR SLDC was again requested to give a feedback to KPTCL (STU) with a copy to SRPC/SRLDC- Hiriyur- Nelamangala, C N Halli and other identified
system needs to be prioritized.
SR II had informed that Hiriyur-Mysore line would be commissioned by
September 2019. In 19 kMs (67 kMs pending of 205 kMs) severe ROW issues
are faced.
2.11 Frequent Failure of Transmission Towers A. Narendra-Guttur D/C line (156.5 kM) (SR II) Tripped on operation of distance protection on 06.06.2019 at 02:00 hours.
B. Raichur-Sholapur Line – II(RSTCL) Tripped due to heavy wind on 03.06.2019.
C. 400 kV Nellore PS-Gooty line I & II (SR I) Ttripped at 01:34 hours on 27.05.2019
Status updates of revival of the lines by SR I, SR II POWERGRID & RSTCL 2.12 Wind Generation Loss in Tamil Nadu
In the 156th OCC Meeting the incidence of reduction of 700 MW wind generation
occurred in Tamil Nadu at 23:06 hours on 28th May 2019 had been deliberated. It was agreed that TANTRANSCO will furnish all wind generation data(REMC)
from 22:00 hours to 24:00 hours for 28th May 2019 and SRLDC/SRPC team will
analyse the cause for wind generation reduction.
TANTRANSCO has submitted the information(Wind Generation, State -Schedule, Drawal, UI and Demand)
2.13 Additional schedule required for carrying out LRSB during technical minimum
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
NTECL vide E-mail dated 04.06.2019 had requested for enhancement of Technical
Minimum of NTECL Units to 380 MW for 5 hours duration every 15 days to
carrying out LRSB (cleaning process- dislodge the accumulated clinkers on the
heating surfaces of the boiler).
After deliberations it was decided that the issue will be discussed further in next
OCC Meeting. All beneficiaries were requested to come back with their views.
NTPC Simhadri vide letter dated 14.06.2019(Annexure-H) had requested for giving a schedule of 380-400 MW once in fifteen days for each unit for around 5
hours continuously.
2.14 TSTRANSCO request for on line information regarding URS availability of other regions
TSTRANSCO had reiterated the request to provide on line availability of URS to
SR beneficiaries for ER ISGS.
In the156th OCC Meeting, SRLDC had informed that the issue has been taken up
with ERLDC to make the provision and once the provision is made entry can be
done directly.
Status update by SRLDC 2.15 All India Correspondence-Action Points-Review of National Power Portal
(NPP) In the Review Meeting of National Power Portal(NPP) held in Ministry of Power
(MoP) on 27.03.2019 under the chairmanship of Secretary(Power) it was noted in
the minutes that “Availability of the transmission lines for State Transmission
Utilities should also be included in the portal by CEA”. RPCs are requested to
discuss the matter with the State Transmission Utilities(STUs) and State Load
Despatch Centres (SLDCs) of respective region for appropriate action in the
matter which may be communicated to GM Division, CEA.
All concerned (State SLDCs to collect from STUs) to initiate action to kindly kindly enter the availability in the NPP.
2.16 Relocation of SPS schemes 156th OCC Updates: SR-I & SR-II had confirmed that all the new DTPCs have been commissioned
at the identified locations (in 152nd OCC).
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
TN informed that (except Karaikudi) all the works have been completed.
KSEBL informed that wiring works are over and testing is to be carried out.
KPTCL had taken up the issues with SCADA and RT wing and requested to
complete the pending works by June end.
SRLDC requested all to furnish the signal wiring diagram- where the signal is
received from PGCIL and to where it is extended. (SR I and SR II submitted)
The following activities to be carried out: Carryout the pending works (refer Annexure No.V of 77 PCSC MOM).
Carryout the mock drills in coordination with PGCIL and SRLDC.
Carryout the mapping of the feeders in coordination with SRLDC.
Furnish the revised list of feeders along with load reliefs under various SPS.
Communicate the compliance report in this regard to SRPC / SRLDC.
2.17 Reliability of SPS Schemes
In compliance of Commission’s Order dated 26th March 2018 in Petition No.
09/SM/2015, the list of SPS in SR had been communicated to all concerned.
SRLDC was to furnish the details of ISTS SPSs and SLDCs for other intra state
SPSs. This information is to be submitted along with OCC on monthly basis.
156th OCC update:
HVDC Talcher - Kolar Pole I had tripped on 31st May 2019 at 18:30 Hrs. SPS Trip
Signal-1 and Trip Signal-2 had been triggered.
APTRANSCO had informed that the loads of Madanapalli feeders are being fed
from 220 kV Madanapalli S/s and these feeders were kept idle charged from
Kalikiri S/s. Trip signal at Ananthapurm S/s was not received which will be
examined. The RE fed feeders were being identified and would be removed from
the scheme. A compliance report will be communicated.
KSEBL had informed that counter at Madakkathara and Kanjirode had not
increased and stated that trip signal had not reached. SR-II confirmed that Kolar
counter had increased. It was decided to carry out a complete checking and testing on 14.06.2019. (KSEBL and PG SR-II & PG Kolar to co-ordinate for the test under intimation to SRLDC).
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
TANTRANSCO had informed that SPS signal (TK-1) was not received at 230 kV
Unjanai substation from Kolar. It was decided that a one to one SPS signal testing may be carried out (on 14.06.2019) from Kolar to 230 kV Unjanai in Tamil Nadu for Talcher - Kolar SPS Signal-1 (TANTRANSCO, PG SR-II & PG
Kolar to co-ordinate for the test under intimation to SRLDC.
Subsequently KSEBL vide letter dated 22.06.2019(Annexure-I) had informed that in coordination with PGCIL team KSEBL had conducted channel testing from
Kolar to Madakkathara and no signal had been received at Madakkathara DTPC
and Kanhirode DTPC due to communication issue between PDH and DTPC
which was rectified on 16.06.2019. KSEBL requested for arranging necessary
steps to test the Talcher Kolar Trip Signal II & III.
SRLDC E-mail dated 24.06.2019 informed KSEBL that the SPS mock test (end to
end test) may be carried out in consultation with Powergrid Kolar S/s. Suitable
date and time may be decided based on both end (KESB & PG) convenience.
Signal transmission may be checked from Kolar to respective load points in
Kerala without actual load shedding (trip wires to load to be removed during test
and restored once testing is completed). Intimation may be given to SRLDC
control room. A report of the SPS signal testing may be furnished to SRPC &
SRLDC
APTRANSCO communication dated 12.06.2019 regarding SPS operation on
05.06.2019 is at Annexure- J. HVDC Talcher - Kolar pole I tripped on 8th June 2019 at 12:10 hours. SPS trip
signal-I operated and load shedding details as furnished by respective states is
given below:
TRIP SIGNAL -1
PLANNED LOAD RELIEF (IN MW)
TRIP SIGNAL -1 ACTUAL LOAD RELIEF (IN MW)
Andhra Pradesh 230 150 Karnataka 250 350 Tamil Nadu 395 276
Total 875 776
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
Load Relief in Andhra Pradesh and Tamil Nadu are observed to be less
than the designed value.
2.18 Rectification of OF cable between HSR to NIMHANS and EDC to HAL In the 156th OCC Meeting, KPTCL informed that the agency has been identified
to carry out the works and will be rectified by June end. Update by KPTCL
2.19 4th link to SRLDC (through Hebbal) In the 156th OCC Meeting SR-II had informed that 4th link to SRLDC (through
Hebbal) had been established. SR-II was requested to give a written communication in this regard and testing may be carried out on 14.06.2019 in coordination with SRLDC.
SRLDC vide letter dated 28.06.2019(Annexure-K) had informed that as per agreed practice in the Special Communication Meeting held on 13.03.2018, the
routing diagram of the link is not yet furnished by SR II. SRLDC requested SR II
to kindly furnish the latest routing diagram of all the four links to SRLDC and also
finalize a date for carrying out the testing of the 4th Link as agreed in the 156th
OCC Meeting.
Update by SR II/SRLDC
2.20 REMC facility installed at SRLDC 156th OCC Updates:
Project is in the advanced stage of commissioning.
Software & Hardware FAT completed
All vendor side site trainings completed
System powered on and System configuration under progress
ICCP connection established with TN REMC, AP REMC & SRLDC SCADA
User registration & static details of pooling stations / developers configured
Forecasting started for N P Kunta & GIREL
Mock scheduling under testing
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
Custom display under preparation
SAT started by May end and under process
PGCIL to expedite to complete the pending works like hardware supply etc.
2.21 REMC Project in SR-Non readiness of space by KPTCL In the 156th OCC Meeting, KPTCL had informed that LVS erection work is in
progress. OSI is installing the server on 11.06.2019.
Update by SR II/KPTCL
2.22 Scheduling of Solar parks:
156th OCC Updates: Pavagada Solar UMPP:
SRLDC had informed that Pavagada mock scheduling had been commenced
from December 2018. As on 06.06.2019, out of 2000 MW capacity of Pavagada
Solar park, for 1400 MW contracted quantum user registration had been carried
out and mock scheduling had been commenced.
t was however noted that all the SPDs have not registered as users(balance 600
MW yet to be registered) and actual injection/drawal of all SPDs was not being
furnished to bring out mock accounts.
KPTCL/KSPDCL was requested to include Pavagada also in DSM accounting and expedite the actions to transfer the scheduling to SRLDC.
KPTCL to expedite the actions to transfer the scheduling to SRLDC. Ghani Solar Park : It was noted that Ghani Solar Park was an UMPP and
scheduling would need to be carried out by SRLDC. APTRANSCO had informed
that the issue was not discussed at SLDC with SPDs due to some changes in
management. The scheduling would be with SRLDC. Meeting will be scheduled shortly.
APTRANSCO to update/reply to SRLDC letter in this regard.
2.23 Simhadri Islanding scheme
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
In the 156th OCC Meeting APTRANSCO had informed that studies are being
carried out/reviewed and they will revert back by June end. APTRANSCO to update
2.24 Request for assistance of 50-60 MW to Yerandahalli by KPTCL
KPTCL vide E-mail dated 22.04.2019 had informed that Tamil Nadu is restricting
the flow on 230 kV Hosur - Yerandanahalli line to 25 MW Bengaluru has
requested to restore the earlier assistance of 50-60 MW to Yerandadahalli station
from Hosur.
156th OCC
KPTCL had informed at Hosur station bay is to be commissioned. Line works
are over. At Udanappalli s/s testing is going on. Shoolagiri end tower erection
and realignment works are pending. In the SC Meeting held on 10.06.2019 it
was noted that the line would be charged by June 2019 end and power will be
extended to Yerandahalli. There are three ICTs of 315 MVA at Shoolagiri end
(normal load 120 MW and peak load 400 MW) and another 120-140 MW may
be easily accommodated.
TANTRANSCO informed that after commissioning of the line system study
would be carried out and decision will be taken.
Status update by KPTCL/TANTRANSCO 2.25 Raising of GT Tap position
NLC TS II had requested permission to increase the tap position of Unit IV from 4
(235 kV) to 5 (230 kV-Nominal tap) to avoid more MVAR injection. In the 156th
OCC Meeting after deliberations, SRLDC/TANTRANSCO agreed for raising the
tap position.
Update by NLCIL In the 156th OCC Meeting, TANTRANSCO had informed that 150 MW plant is
coming in TN system (by M/s Nagar Power, Power injection to Thiruvarur 230 kV
S/S, Plant location –Nagapattinam)
TANTRANSCO to update on the progress 2.26 ICT Failure at UPCL
156th OCC update:
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
315 MVA, 400/220 kV ICT I failed on 06.06.2019. KAR SLDC requested UPCL to
expedite the works.
UPCL had informed ICT is expected after two months.
OCC noted that 315 MVA ICTs at Kozhikode/Narendra are available and in case
of delay in commissioning of UPCL ICT, using this ICT (or any other ICT) may be
thought off.
UPCL had informed that the faulty ICT has already been dispatched to M/s TELK,
Kerala may reach by 10.07.2019, after opening of the ICT, exact assessment of
the damage can be evaluated.
UPCL had requested for a visit Powergrid sub stations at Kozhikode and
Narendra to check the physical dimension and technical feasibility of spare ICTs.
If found feasible and in case repairing time of our ICT is high, UPCL may go for
using the spare ICT which will minimize the restoration time.
Subsequently the visit by UPCL officer had been planned on
29.06.2019(Kozhikode/Narendra)
Update by UPCL/SR II
2.27 Taking over of 2 Nos of bays at Edamon in respect of Kayamkulam-Edamon DC line- Replacement of existing conventional equipments with Hybrid switch gear modules at 220 kV S/s, Edamon(Edappon and Kundara bays) under PSDF scheme by KSEBL.
156th OCC Meeting: KSEBL had stated that they will forward the communication (request to SR II to
furnish the depreciated value) to SR II again and SR II may furnish the
depreciated value and accordingly after Board approval the depreciated amount
would paid to SR-II.
SR-II had informed that after receiving the concurrence from KSEBL and after
approval of CERC the depreciated value will be communicated to KSEBL.
Update by KSEBL/SR II 2.28 Status of 220 kV Bays at PGCIL, Kochi S/S to receive 2 Nos 220 kV feeders
from Aluva
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
In the 156th OCC Meeting, SR II had informed that technical bid & financial bids
had been opened and within one month award will be placed.
Update by SR II 2.29 Communication Audit
Adhering the Communication Audit Procedure as prepared in consultation with
Stake holders and as approved in 34th SRPC Meeting, Communication Audit had
been carried out by Audit Team (SRPC, SRLDC, PGCIL and States ) in S/Ss at
Tamil Nadu on 12th & 13th of June 2019 . Audit Report at TANTRANSCO S/Ss(400
kV Sriperumbudur, 400 kV Almathy and 230 kV S P Kovil) is at Annexure-L Subsequently stations of TSTRANSCO (400kV Sankarapally and 220kV
Erragadda) /SR-I (765 kV Maheshawaram, 400 kV Ghanapur ) had been audited
on 20th and 21st June 2019 and Audit report is under preparation.
2.30 Sale of power from NLC TPS-I
The Power Sale Agreement with TN in respect of NLC TPS-1 has expired on
31.03.2019. As per IEGC Clause 6.4.2(a), NLC TS I would come under the control
area of SRLDC and TS I Station may need to be scheduled by SRLDC from
01.04.2019.
156th OCC
NLCIL had informed that formalities like user registration, metering scheme
approval, real time SCADA etc were under advanced stage. At present NLCIL
is continuing the power sale to TN on OA and as and when TN stops
purchasing power scheduling will be transferred to SRLDC. NLCIL bays will be
ready by the month end.
TANTRANSCO had informed that after commissioning of HTLS lines to TS-II
switchyard, the balance 230 kV lines will be shifted to new TANTRANSCO SS
from TS-I switchyard (within two months).
Update by NLCIL/TANTRANSCO 2.31 Regular interaction between CERC and RPCs
A Meeting with Chairman & Member Secretaries of each was held on 24.06.2019
at CERC office, New Delhi..
2.32 Flexibilization of Thermal Plants: Units identified by APGENCO
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
APGENCO had informed that they are in touch with BHEL for
implementation/pilot tests of its Rayalseema Unit I for flexible operation.
TSGENCO vide letter dated 19.06.2019(Annexure-M) had informed that they have identified KTPS Unit VI(600 MW) for conducting pilot test for flexible operation.
2.33 Deviation in drawals by states
SRLDC vide letters dated 11.06.2019(Annexure-N) had communicated to APTRANSCO, TSTRANSCO, KPTCL and TANTRANSCO regarding the deviation
in drawals beyond the limits during the period from 13.05.2019 to 03.06.2019.
In the meetings SRLDC/SRPC had requested all concerned entities to take
appropriate action in real time to curtail sustained UD/OD and UI / OI on violation
messages being issued by SRLDC and report necessary compliance. The huge
quantum of deviation displays the lack of real time action which is threatening for
Grid Security.
2.34 Status of Implementation of the revised FGD Installation/ESP Up-gradation Plan
CEA is seeking updated information in respect of implementation of revised FGD
installation/ESP Up-gradation Plan. Status update is to be furnished in a time
bound manner. CPCB time lines needed to be strictly followed.
APTRANSCO had informed that Feasibility Report is awaited for Rayalseema Units.
2.35 TTC assessment considering temperature dependent rating of lines/terminal equipment TSTRANSCO/KPTCL (two stations pending) were requested to expedite since it
is a long pending issue.
2.36 Ramp Rates, technical minimum & startup from hot/warm/cold
The following were noted again:
All ISGS stations were requested to give ramp of 0.67%/min in line with the SRPC decision.
All the SLDCs were requested to ensure ramps of at least 0.67%/min in line with the SRPC decision for the state generators.
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
All the entities were requested to take action in respect of ramp rates, technical minimum, start up from hot, warm and cold condition as discussed in the SRPC meeting (noted in the special meeting).
POSOCO had pointed out that enhancing of the ramp rates would result in further savings in the SCED optimization.
It was noted that as per the Tariff Regulations, 2019-24, POSOCO was to come out with a draft procedure on ramps (with incentivization) by June 2019. The draft was under preparation. This was to be implemented from April 2020.
In the 35th SRPC Meeting it was noted that NTPC would come up with expert
view of OEMs with regard to compliance of CEA Regulations of Ramp Rate of
3%/minute in the control range(sustainability for scheduling etc) and also on the
35 hours duration from cold start for super critical units like Kudgi within a month.
This issue was followed up in subsequent OCC Meetings and there was no
tangible update on the same. Noting that next SRPC Meeting being scheduled on
12.07.2019, SRPC vide letter dated 17.06.2019(Annexure-O) had requested NTPC to expedite the views of OEMs
2.37 SCED Procedure -Implementation of SCED pilot
SRPC vide letter dated 05.04.2019, 11.04.2019 & 12.04.2019 had communicated
some of the issues/suggestions regarding SCED scheduling with NLDC. Reply is
awaited.
In the previous OCC Meetings Generators had pointed out regarding instances of
ramp violation, schedules below TM, schedules above DC, delay in informing the
final generation schedules etc. Also it was noted that generators are paying a
huge amount in Crores to the pool in advance and there was considerable delay
in receiving back the money from beneficiaries. Even penalties are very high.
During pilot period some relaxation should be thought off.
OCC forum again requested SRLDC to take up with NLDC to present on performance of SCED (with respect to details of savings, optimization, station wise Up/Down details, Constraints faced if any etc.)
SRLDC/NLDC to update. 2.38 RE Generators for Reactive Compensation & High Voltage
All the states were again requested to kindly examine and ensure voltage based
MVAR interchange for RE generators.
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
156th OCC : APTRANSCO informed that they have issued the following TOO in this
regard:
The RE generators are exempted from payment of reactive charges for
drawal of reactive power at voltages are greater than 392 kV. The RE
generator shall absorb reactive power at voltages above 392 kV and inject
reactive power at voltages below 390 kV so as to maintain 400 kV bus
voltages within limits.
KSEBL had informed that they are already following the same(during the
MVAR injection period as per SLDC instruction, reactive charges are
suspended).
TANTRANSCO had informed that TN SLDC(as recommended by SRPC
Forum) had requested REMC wing to empower SLDC for suspension of
reactive charges if it is as per SLDC instructions
It was again suggested that in real time SLDCs may suspend the reactive
interchange charges in case of system requirements (till the voltage based
reactive billing is in place). Blanket approval in this regard for the same may be obtained from the Higher Management by the SLDCs.
2.39 Daily Load Forecasting by SLDCs
SRLDC to present the error (forecast Vs actual demand) for the month of
June 2019. 2.40 URTDSM project
156th OCC
Relay details to be updated in VADR application – relay details received from SR-1 and SR-2 on 10.06.19.
WAMS diagnostic tool to be installed to rectify errors
Training on Analytical application by IITB pending.
Working group VC held on 16.05.2019. Feedback had been given to IITB and next Meeting is scheduled for 14.06.2019.
SRLDC requested SRPC Protection wing (from PMS) to share the relay
details of ISG Stations.
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
SR II was requested to coordinate for the training on Analytical Application by
IITB as requested by all states.
For PMU at STATCOM at Udumalpet, Hyderabad, Trichy, etc SRLDC was
requested to identify the locations and possibility of shifting will be explored by SR I and SR II.
SRLDC in its agenda for 157th OCC Meeting had furnished the flowing:
URTDSM project in SR was commissioned in Sep 2018. As part of the
project 255 PMU‘s were installed in 68 Sub Stations of SR region. This
project was envisaged and planned in 2012 and PMU locations were
identified based on the power system network prevailing at that time. Now
due to commissioning of new lines, Sub Station and LILO of existing lines
it is desired to optimize the PMU locations to include important renewable
pooling stations, lift irrigation substations and new Sub stations with
FACTS devices like STATCOM & PST etc. to study their impact in grid
and signature of these devices.
During 156th OCC meeting, the forum requested to explore the possibility
of installing PMU’s at SATCOM substations (GHANAPUR, UDUMALPET,
and TRICHY) in SR and other important substations by optimizing the
existing PMU’s available under URTDSM project.
The following are proposed
PMU LOCATIONS IDENTIFIED FOR OPTIMIZATION TO INCLUDE
RENEWABLE INJECTION POINTS SL NO
PRESENT LOCATION
NEW LOCATION
REGION REMARKS
1 KARAIKUDI KARAIKUDI SR-2 4 PMUs installed presently which can connect 8 lines. Presently only 6 lines are connected. May include KAMUDHI feeders
2 NARNOOR (AP)
NARNOOR(AP) SR-1 3 PMUs installed presently which can connect 6 lines. Presently only 5 lines are connected. May include GHANI line & J’MADGU line can be included in place of KRNL as PMU available at KRNL on KRNL-NRNR line
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
3 MAHBOOBNAGAR (TS)
MAHBOOBNAGAR
(TS )
SR-1 1 PMU installed which can connect UVKONDA 1&2 lines in place of NSGAR and RTPS lines as PMUS are present on these lines from FAR end.
PMU LOCATIONS IDENTIFIED FOR SHIFTING FOR STATCOM/ PST/LIFT IRRIGATION
SL NO
PRESENT LOCATION
NEW LOCATION REGION REMARKS
1
TIRUNELVELI (6 PMUS available)
TRICHY (STATCOM)
SR-2 2 PMU panels (Un used - PMU ID 10379 and 10382) previously connected to KDKLM 3 &4 and can be considered for shifting to Trichy & Udamalpet or STATCOM.
2 UDAMALPET (STATCOM)
SR-2
3 WARANGAL/ VIJAYAWADA
GANAPUR (STATCOM)
SR-1 Option – 1: New PMUs proposed under substation package can be shifted to Ghanapur. Option -2 : PMU (10076) at Vijayawada can be shifted as only bus voltage is connected.
4.
VEMAGIRI
KTS-6 (PST)
SR-1 3 PMUs(44031,44025,44034) lying idle on GVK, KNSMA2,GMR1 & GWTHI 2, lines can be shifted
5. RAMADGU (LIFT
IRRIGATION)
SR-1
6. MEDARAM (LIFT
IRRIGATION)
SR-1
The Forum may kindly deliberate and make suitable recommendation for
executing the above proposed changes.
2.41 Issues w.r.t KGS 156th OCC
SEM related issues had been taken up with SR-II vide letter dated
09.04.2019.
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
SR-II had informed that SEM supply was expected by June end and concurrence had been received from Kaiga GS. KGS was requested to facilitate the installation of the same.
Regarding Sirsi-Guttur section of Kaiga-Sirsi, KPTCL had informed that they
have replaced 20 numbers of tension strings. Further replacement of 15
numbers and 22 numbers of insulator strings was planned for line-1 and line-2
for which, the estimation was under preparation.
KPTCL informed that the estimate had been prepared and would be taken up for approval.
Kaiga GS and KPTCL had agreed to coordinate the PLCC communication
issues. KPTCL agreed to take up with their communication wing.
Kaiga GS had taken up RTU issues with SR-II vide letter dated 09.04.2019
Kaiga had provided consent along with requirement. KGS had requested for site visit by PGCIL, for which date needed to be finalized.
KGS vide letter dated 14.06.2019(Annexure-P) had informed that the visit to KGS site by KPTCL officers is not yet materialized and the issues still persists. It
was offered by KPTCL that the issues will be solved by utilizing available spares.
Procurement of EPBAX exchange etc cannot be carried out by KGS alone since
as per Regulation it is the responsibility of Generator and CTU to maintain the
communication equipment to establish redundant communication. Since
communication through PLCC(voice) is a two sided affair and there had to be
modern equipments KGS alone cannot install a device so as to communicate
with Kadra, Kodasalli/Narendra etc . KGS requested KPTCL to review
communication system in all connected switchyards and initiate necessary
procurement for modernizing the systems.
2.42 Request to PGCIL by NLCIL for procuring SEMs for NLCIL
In the 156th OCC Meeting, NLCIL had requested PGCIL to procure SEMs (new specification) for them and payment will be done by NLCIL. SR II had agreed to include the requirement of NLCIL in their procurement plan, NLCIL will
furnish the requirement. Status: NLCIL/SR II
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
2.43 Resource Adequacy Index and Flexibility Index
SRLDC had furnished the procedure for flexibility index calculation. SLDCs were requested to compute the indices to be aware of the adequacy
and flexibility of reserves. SRLDC assured of all assistance in this regard. 2.44 Periodical Audit and Vulnerability Assessment & Penetration Testing(VAPT) of
Infrastructure
CISO MoP vide letter dated 31.01.2019, 20.02.2019 and 22.04.2019 had
requested all stake holders to carry out Cyber Security Audit and VAPT of ICT
Infrastructure, website, web application etc in defined intervals by CERT-in
empaneled cyber security audit agencies to avoid vulnerability and report to CISO
MoP along with the key findings of the audit. The above details may kindly be sent
to [email protected] with a copy to [email protected] . CEA vide letter dated
29.05.2019 has once again requested to kindly provide the report as sought.
156th OCC:
KPTCL had informed that tender had been floated for third party auditing of
Control Centers of SLDC.
KSEBL had informed that Cyber Security Audit will be carried out in June
2019. NTPC informed that regarding SCADA they have AMC with OEM and
every three months tests are being done.
NPCIL, CISO vide letter dated 23.05.2019 had informed that every quarter
cyber security audit are being carried out for their ICT infra-structure.
No communication in this regard is received by SRPC by NPCIL stations in SR. SRPC had requested NPCIL to furnish the dates of these audits as required.
All the concerned were requested to submit the details at the earliest. CERT certified agencies needed to be approached for the audit. NTPC
was requested to coordinate with the CERT Thermal (NTPC) and initiate action accordingly.
KSEBL suggested that officers of CERTin/NCIIPC may be invited to any coming OCC to give exposure on the procedure for VAPT and ICT Cyber Security Audit.
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
Subsequently TSTRANSCO had informed that TSTRANSCO has issued a PO on
C-DAC for conducting Security Audit of TSTRANSCO website and the same is in
progress. The Cyber Security audit and VAPT as part of AMC on SCADA system
had been conducted from 8th to 10th May 2019 by CERTin certified auditor and
reports are awaited.
2.45 Testing of Primary frequency response of generators as per IEGC clause 5.2(g)
It was noted that a Special Meeting had been convened by NLDC on 06.06.2019
at NLDC. RFP document was discussed in length and would be finalized shortly.
SRLDC may update.
2.46 AGC at state Level- Pilot Project identification & Implementation
A Meeting was carried out on 14.03.2019 at SRPC and the minutes of the
Meeting are available at SRPC website.
156th OCC Update: KPCL had informed that a team of officials from PRDC, KPCL and KPTCL SLDC
had visited Sharavathy hydro station on 12.04.2019 and Varahi Hydro station on
11.04.2019 and inputs had been collected from station and SLDC. The target
date of completion of projects at Sharavathy is June 2019 and for Varahi it is
August 2019. KPTCL was requested to verify the requirements at SLDC for the
implementation of the same.
KSEBL informed that AGC implementation work will start at Kuttiadi HES by
December 2019. KSEBL requested for visit of team at Sharavathi/Varahi to study
the requirements etc for the implementation of the AGC which was agreed by
KPCL(by this month end)
APGENCO/APSLDC had informed that works were to be initiated for AGC
implementation at Krishnapatanam and SLDC.
TSTRANSCO had informed that TSGENCO had floated tenders for preparing the
DPR.
TANTRANSCO had informed that the administrative approval yet to be received
and technical specifications are under preparation jointly by TANTRANSCO and
TANGEDCO.
2.47 Installation of 2x125 MVAR bus reactors at UPCL
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
156th OCC: Action needed to be taken for installation of Reactors as per Standing Committee decision.
UPCL/KPTCL to update 2.48 Reactor commissioning at Kaiga GS
156th OCC: Tenders for both the reactors together had been floated and the commissioning of the reactors are expected by March 2020. Tender will be
opened by June end.
KGS to update 2.49 Prolonged Outage -KKNPP Reactor
156th OCC: KKNPP informed that the second reactor and is expected to be commissioned by December 2019.
KKNPP to update 2.50 High voltages in Telangana System /Frequent switching of lines / Bus reactors/
MVAR interchange of generators
SRPC had analyzed the nodes of high voltage coupled with MVAR injection during
February 2019 to May 2019 and the following was observed:
Nodes with MVAR injection during V > 103% AP KAR TN TS
Chittoor Nelamangala Tiruneveli Maheshwaram Kadapa Munirabad Karaikudi Hyderabad Kurnool Guttur Alamathy Mehaboobnagar Vijayawada Hoody Pugalur Dichipally N P Kunta Kalavinthapattu Khammam Vemagiri Warangal Shankarapally
All entities are requested to kindly take appropriate action. SRLDC had agreed to take up the issues related to MVAR interchange of
state generators with SLDCs and with ISTS connected generators. 2.51 Certification of Inter-state and Intra-state lines in PoC
All SLDCs were requested to communicate the outage and availability
computations for the applicable lines within one week after completion of month to
SRLDC. SRLDC would communicate the details by 3rd week. SRPC would issue
the certificate by month end.
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
SRPC had requested all states to furnish the availability calculation as a whole
(single availability factor) for entire AC System.
2.52 Compliance of CEA Regulations for Grid connectivity of Renewable Energy Sources
The following is the updated status on RE SCADA availability as noted in the 156th
Meeting of OCC:
State SCADA availability as on 31.05.2019 Mapped I/C
Remarks
AP Wind: 4075/3908 MW (96%) Solar: 3021/2033 MW (67%) Total: 7104/5941 MW (84%)
Pending SCADA availability was for RE connected distribution level and for which action had been taken for compliance.
TS Wind: 100.8/100.8 MW (100%) Solar: 3479/3431 MW (99%) Total: 3580/3532 MW (99%)
Action for balance SCADA availability at 33 kV and below was being followed up and notices had been issued.
KA Wind: 4803/4783 MW (100%) Solar: 5967/5413 MW (91%) Total: 10769/10197 MW (95%)
KE Wind: 70/27 MW (38%) Solar: 93/85 MW (91%) Total: 163/112 MW (69%)
TN Wind: 8746/8571 MW (98%) Solar: 2495/648 MW (26%) Total: 11241/9219 MW (82%)
Notices had been issued for SS under 10(1) for SCADA availability. 100% SCADA availability of wind was likely to be ensured by December 2017. TANTRANSCO (Communication) and TANGEDCO (Metering) had jointly initiated action for Solar SCADA availability and was targeted to be completed by July 2018.
SR Wind: 17795/17390 MW (98%) Solar: 15062/11610 MW (77%) Total: 32858/28999 MW (88%)
2.53 Monitoring of scheme funded from PSDF
The status (as on 30.04.2019) as received from NPC is at Annexure-Q. All the states/entities were requested to kindly furnish the updated status in a time bound
manner.
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
2.54 PSS Tuning of generators
6th Meeting of PSS Tuning had been convened on 27.09.2018. Minutes are
available at SRPC website. Analysis and recommendations are to be referred to
take necessary action. The schedule for next SRT is also mentioned in the
Minutes. All the concerned were again requested to take appropriate action in this
regard. (Refer Table-I). PSS tuning for around 80 units is to be carried out during 2019(by December 2019) and action had to be initiated in this regard .
156th OCC: After the 6th PSS Meeting held on 27.09.2018, upto 156th OCC Meeting, 9
units PSS/SRT test reports were received by SRPC. APGENCO: VTPS units
5 & 6; TSGENCO: Kakatiya TPP units 1 & 2; TANGEDCO: NCTPS Stage II
Unit 2; CGS: NTPC Ramagundam units 5 & 6; Kaiga unit 1; ISTS connected
IPPS: IL & FS unit 2. The damping torque calculation by all of the 9 units has
to be furnished.
SRT data furnished by KPCL for RTPS units 5, 6 & 8; BTPS unit 1 and Kudgi
Unit III also doesn't include damping torque calculation.(data received after
156th OCC Meeting)
14 units PSS/SRT was to be carried out by December 2018 needs to be taken
up this year.
PSS/SRT was never carried out/information not received from 36 Units. This
includes NTPC Kayamkulam and LANCO Stage II & III Units.
2.55 VC Facility at SLDC
In the 155th OCC Meeting, Puducherry had informed that VC facility will be taken
up in this financial year.
2.56 MoP Order dated 28.06.2019: Opening and maintaining of adequate LC as payment Security Mechanism under PPAs by DISCOMs
MoP has approved the proposal to make it mandatory for distribution licensees to
open and maintain adequate Letter of Credit (LC) as Payment Security
Mechanism under Power Purchase Agreements and had circulated Order dated
28.06.2019 in this regard. Distribution Licensees are required to open and
maintain adequate Letter of Credit (LC) as Payment Security Mechanism under
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
Power Purchase Agreements from 1st August, 2019. The step aimed at bringing
discipline and making the sector viable.
The following are highlighted: Quote NLDC & RLDC are therefore directed as follows:
1. In accordance with Section 28 (3) (a), the NLDC & RLDC shall despatch
power only after it is intimated by the Generating Company and /Distribution
Companies that a Letter of Credit for the desired quantum of power has been
opened and copies made available to the concerned Generating Company.
2. The intimation to NLDC and RLDC shall specify the period of supply.
3. RLDC shall dispatch electricity only up to the quantity equivalent of value of
Letter of Credit.
4. The dispatch shall stop once the quantum of electricity under LC is supplied.
5. The concerned generating company shall be entitled to encash the LC after
expiry of grace period, i.e. 45 to 60 days as provided in the PPA.
6. In the event power is not dispatched for any reason given above, the
Distribution licensee shall continue to pay the Fixed Charge to the Generating
Company.
6.0 It shall also be ensured by the Load Despatch Centre that the regulated entity, during the period of regulation, has no access to procure power from the Power
Exchanges and they shall not be granted Short Term Open Access (STOA).
7.0 In case scheduling and despatch of power produced by any generator is not done due to non-opening of Letter of Credit by the Distribution licensee, then the
Distribution licensee would be liable to pay compensation to the generator as per the
terms of Power Purchase Agreement or Power Sale Agreement, as the case may
be, the distribution licensee has entered in with the generator.
8.0 NLDC/ RLDC/SLDC shall carry out such duty cast under Electricity Act, 2003 from 01.08.2019.
3. LGBR for upcoming five months
3.1 TTC/ATC computations
All states were requested to furnish PSSE base case for October 2019.
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
5 months LGB, Converged PSSE base case, ATC/TTC computation to be
furnished to SRLDC. ATC/TTC computation to be posted on SLDC’s website and
Nodal officer details.
3.2 Status Review Bus Reactors and Statcoms
Commissioning of Bus reactors & Statcoms as approved in various meetings &
Standing Committee - Status review.
4 Review of Power Supply Position /Inflows
Constituents/ Generators to furnish the reasons for deviation: a) Actual with respect to anticipated (MW & MU) for availability and requirement. b) Generation variation category wise with respect to MoP targets/LGBR figures. c) Inflows (MU) to major reservoirs: Actual w.r.t. 10 year moving average and w.r.t.
same month last year. d) Reasons for demand -supply gap and its variation
6 Frequency 6.1 High Frequency
Sustained high frequency & UD/OI incidents may be discussed. 6.2 Low Frequency
Summary statement of different violation messages issued by SRLDC.
Sustained low frequency & OD/UI incidents may be discussed. 7. VOLTAGE PROFILE 7.1 Low voltage
SRLDC may furnish the details/issues.
Details of capacitors installed during June 2019. Details of the healthy/faulty
capacitors to be furnished.
7.2 High Voltage SRLDC may furnish the details/issues.
MVAR Interchange
All the SLDCs to kindly monitor VAR absorption/injection of generating units in
their respective control areas in real-time. SRLDC had suggested MVAR tests for
Rayalseema, Kudgi and IL & FS would be taken up.
A Special Meeting to deliberate on MVAR interchange was held out on 26th
September 2018 at SRPC Bengaluru. (Meeting minutes are available at website)
7.3 Status review of Bus/Line Reactors, Line Reactors and STATCOM
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
Status of implementation of Bus / Line Reactors approved in the Standing
Committee / SRPC pending for commissioning by the SR constituents.(Refer table-II)
8 Network Protection/Security issues
8.1 U/F &df/dt Relays Schemes Specific issues, if any may be discussed.
8.2 Status update of SCADA mapping of feeders of AUFR &df/dt schemes State SCADA
mapped % Status
AP 59 ATRANSCO informed that 132 RTUs have been procured and would be commissioned within 6 months- by October 2019(UFR and df/dt mapping and visibility would improve).
TS 79 RTUs reached at site.
KAR 101 KER 119 TN 105 RTUs had been procured partially, installation
started. Pudu 92 2 more RTUs added but mapping to be carried out.
With this 100 % availability will be achieved. SR 94
Status review of AUFR, df/dt & Automatic disconnection of Radial feeders
UFR & df/dt feeder’s validation i) Status of implementation of validation findings can be updated in google
spread sheets already circulated
SRPC had carried out AUFR/df/dt relay inspection in TANTRANSCO
Substations (400 kV Almathy, 230 kV SP Covil & 230 kV Gummidipoondi) on
12th to 14th June 2019. Observations/recommendations had been
communicated vide SRPC letter dated 18.06.2019(Annexure-R). It is requested that the remedial action taken to adhere the recommendations may
kindly be initiated and status may be updated to SRPC. AUFR/df/dt relay
inspectionwere carried out in TSTRANSCO substations (400kV Narsapur,
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
220kV Narketpally, 220kv Medchal) on 18/19.06.2019 for which report is under
preparation. 8.3 RGMO/FGMO
RGMO implementation/ Extension of RGMO status point to SLDC (Refer Table-V
of Appendix).
As per 5th Amendment to IEGC, gas stations above 50 MW Installed Capacity
were also to come under RGMO/FGMO Operation w.e.f. 1st October 2017.
Inadequate response was needed to be taken up by SLDCs with respective
SERC’s in line with Hon’ble CERC Orders in respect of Petition No. 84/MP/2015
and 302/MP/2013.The non-performance of the generators under SRLDC control
would be taken up by SRLDC with the respective generators.
SRLDC had agreed to take up the issues of no response, partial response and reversal response with ISG stations/Regional Entities.
It was noted that FGMO analysis is being reported to CERC. The generators which had not furnished the data were requested to furnish the response to
SRLDC. Else SRLDC data would be considered as final.
All SLDCs are requested to take up with generators in their control area (including IPPs) regarding no/ partial/reverse response of RGMO.
TSTRANSCO vide letter dated 15.06.2019(Annexure-S) had taken up the issue of non-adequate/no response of KTPP I, KTPP II, KTS VI and KTS V with
APGENCO.
8.4 Automatic Demand Side Management Scheme (Petition No. 250/MP/2012) & GSES (Petition No. 265/MP/2012) It was noted that the ADMS relief identified is quite meager as compared to
overdrawal quantum. In the 152nd OCC Meeting all the SLDCs were requested to
revert back on increasing the quantum based on the sustained overdrawal and the
maximum deviation limit. It may also to be seen that whether the tripping can be
done through SCADA. Further, whether frequency logic was to be removed would
be discussed in the 154th OCC meeting. SRLDC was again requested to come up
with the proposal for increase in the ADMS quantum.
Status update
8.5 Grouping of loads (IEGC clause 5.4.2 (e)) Regulations to be complied by all the concerned utilities
-
Agenda for 157th OCC Meeting to be held on 08.07.2019 at SRPC
9 LVRT Implementation Status review of Pending points as discussed in 4th RE/LVRT meeting
(i) Wind and Solar power forecasting by States.
(ii) Ensuring compliance of LVRT/HVRT before commissioning of RE generators.
Real time availability of Wind/Solar generation data 10 Emergency Restoration System (ERS)
As per ERS requirement outlined in MoP letter dated 05.12.2014, status update
on ERS is given at Table IV of Appendix. The same is furnished to CEA vide E-mail dated 08.10.2018 as required by them.
11 SCADA AND COMMUNICATION Any specific issues may be brought to the forum.
12 TRANSMISSION NETWORK ISSUES AND SYSTEM OPERATION ISSUES
13 Black Start Procedure
Mockdrills conducted in June 2019. Mockdrills scheduled for July 2019 and from January 2020 to June 2020. Point to point mock exercise for black start by all constituents TSTRANSCO had informed that TSGENCO was planning to procure DG set
of appropriate capacity for Jurala HEP.
Mock test at Bhadravathi was agreed to be carried out by 2nd week of June
2019. Dates needed to be coordinated by SRLDC in coordination with
WRLDC, NLDC, NTPC and TSTRANSCO.
Subsequently it was suggested to conduct the mock test on 29th June 2019
which was further postponed as per the request from WRLDC (mock drill may be
planned after 15 days in view of recent works at HVDC Bhadrawati).
14 Upcoming Generating Stations Status update of Central sector and State Sector Upcoming generating stations
are at Table VI of Appendix. Declaration of COD letter from SLDC was required to be submitted to CEA, Fuel
Management Division for purpose of coal linkages etc. 15 Any other point with the permission of the Chair.
16 Date and Venue of the next Meeting