08 project quality management

66
MBA, PMP, B.Sc.(Civil Eng.) : PMO manager EWU - DIU

Upload: omer-alsayed

Post on 08-May-2015

462 views

Category:

Business


2 download

TRANSCRIPT

Page 1: 08 project quality management

MBA, PMP, B.Sc.(Civil Eng.) : PMO manager EWU-DIU

Page 2: 08 project quality management

1890 John Mackintosh & his wifec r e a t e d a n e w k i n d o f s w e e t f r o m

i n e x p e n s i v e l o c a l i n g r e d i e n t s s u c h a s m i l k , s u g a r b e e t a n d e g g s

Page 3: 08 project quality management

• identifying quality REQUIREMENTS &/ STANDARDS

• how the project will demonstrate COMPLIANCE with quality requirements.

8.1 Plan Quality Management

• AUDITING the quality requirements and the results from QC measurements to ENSURE that appropriate quality standards and operational definitions are used.

8.2 Perform Quality Assurance

• MONITORING and recording results of executing the quality activities to ASSESS performance and recommend necessary changes.

8.3 Control Quality

Page 4: 08 project quality management

Knowledge Area Initiating Planning Executing M& C Closing

4. Project Integration Management4DevelopProject Charter

4.2 Develop ProjectManagement Plan

4.3 Direct & Manage Project Work

4.4 Monitor & Control Project Work4.5 Perform Integrated Change Control

4.6 Close Projector Phase

5. Project Scope Management

5Plan Scope Management5.2 Collect Requirements5.3 Define Scope5.4 Create WBS

5.5 Validate Scope5.6 Control Scope

6. Project Time Management

6Plan Schedule Management6.2 Define Activities6.3 Sequence Activities6.4 Estimate Activity Resources6.5 Estimate Activity Durations6.6 Develop Schedule

6.7 Control Schedule

7. Project Cost Management7Plan Cost Management7.2 Estimate Costs7.3 Determine Budget

7.4 Control Costs

8. Project Quality Management 8Plan Quality Management8.2 Perform Quality Assurance

8.3 Control Quality

9. Project Human Resource Management

9.1 Plan Human ResourceManagement

9.2 Acquire Project Team9.3 Develop Project Team9.4 Manage Project Team

10. Project Communications Management

10Plan Communications Management 10.2 Manage Communications 10.3 Control Communications

11. Project Risk Management

11Plan Risk Management11.2 Identify Risks11.3 Perform Qualitative Risk Analysis11.4 Perform Quantitative Risk Analysis11.5 Plan Risk Responses

11.6 Control Risks

12. Project Procurement Management

12Plan Procurement Management 12.2 Conduct Procurements 12.3 Control Procurements12.4 Close Procurements

13. Project Stakeholder Management

13IdentifyStakeholders

13.2 Plan StakeholderManagement

13.3 Manage StakeholderEngagement

13.4 Control StakeholderEngagement

OSO OCT 2013

Page 5: 08 project quality management

Quality• as a delivered

performance or result is “the DEGREE to which a set of inherent characteristics fulfill REQUIREMENTS” (ISO 9000)

• quality level that fails to meet quality requirements is always a problem

Grade• as a design intent

is a CATEGORYassigned to deliverables having the same FUNCTIONAL use but different technical characteristics.

• low grade of quality may not be a problem.

Page 6: 08 project quality management

Accuracy

measure of exactness

Precision

assessment of

correctness

Page 7: 08 project quality management

Customer satisfaction.

• Understanding, evaluating, defining, and managing requirements to meet customer expectations.

Prevention over inspection

• Quality should be planned, designed, and built into—not inspected into

Continuous improvement

• The PDCA (plan-do-check-act) Shewhart /Deming.

• Total Quality Management (TQM), Six Sigma, and Lean Six Sigma

Management Responsibility

• to provide suitable resources at adequate capacities

Cost of quality (COQ)

• total cost of the conformance work and the nonconformance work that should be done as a compensatory effort

Page 8: 08 project quality management

identifying quality requirements and/or standards for the project and its deliverables

documenting how the project will demonstrate compliance with relevant quality requirements.

provides GUIDANCE and direction on how quality will be managed and validated throughout the project

Page 9: 08 project quality management

Inputs

Project management plan

Stakeholder register

Risk register

Requirements documentation

Enterprise environmental factors

Organizational process assets

Cost-benefit analysis

T&T

Cost of quality

Seven basic quality tools

Benchmarking

Design of experiments

Statistical sampling

Additional quality planning tools

Meetings

Outputs

Quality management plan

Process improvement plan

Quality metrics

Quality checklists

Project documents updates

Page 10: 08 project quality management
Page 11: 08 project quality management

8.1.1.1 Project Management Plan

Scope baseline

Schedule baseline

Cost baselineOther

management plans

Page 12: 08 project quality management

• identifying those stakeholders possessing a particular interest in, or having an impact on, quality.

8.1.1.2 Stakeholder Register

• information on threats and opportunities that may impact quality requirements.

8.1.1.3 Risk Register

• captures the requirements that the project shall meet pertaining to stakeholder expectations. The components of the requirements documentation

8.1.1.4 Requirements Documentation

Page 13: 08 project quality management

8.1.1.5 Enterprise Environmental Factors

Governmental agency regulations;

Rules, standards, and guidelines (application area)

Working or operating conditions of project / deliverables

Cultural perceptions about quality.

8.1.1.6 Organizational Process Assets

Organizational quality policies, procedures, and guidelines.

management approach;

Historical databases; and

Lessons learned

Page 14: 08 project quality management

The primary benefits :

less REWORK

higher PRODUCTIVITY

lower COSTS

increased S/H SATISFACTION

increased PROFITABILITY.

Page 15: 08 project quality management

• all costs incurred over the life of the

product by investment in

• nonconformance to requirements,

PREVENTING

• the product or service for conformance to requirements,

APPRAISING

• to meet requirements (rework).

FAILING

Page 16: 08 project quality management

Co

st o

f C

on

form

ance Prevention Costs

• Training

• Document process

• Equipment

• Time to do it right

Appraisal Costs

• Testing

• DTL

• InspectionC

ost

of

No

nco

nfo

rman

ce Internal Failure3

• Rework

• Scrap

External Failure4

• Liabilities

• Warranty

• Lost of Bus.

Money spent DURING project

to AVOID failures

Money spent DURING/AFTER

BECAUSE OF failures

Page 17: 08 project quality management
Page 18: 08 project quality management

Staff

• Non-motivation

• Working condition

• Rewards & recognition

• Skills

• Attitude

Materials

• Supply

• Manufacturing

Machine

• Efficiency

Page 19: 08 project quality management
Page 20: 08 project quality management

organize facts in a manner that will facilitate the effective collection of

useful data about a potential quality problem.

gathering attributes data while performing

inspections to identify defects.

EX. data about the frequencies or

consequences of defects collected in

check-sheets are often displayed using

Pareto diagrams.

Page 21: 08 project quality management

#

Problem Sun Mon Tues. WedThur

s.Sum

1 Phones aren’t answered quickly enough. 3 3 4 3 2 15

2 Staff seem distracted and under pressure. 2 1 1 1 1 6

3 Engineers don’t appear to be well 1 0 1 1 1 4

4 Engineers don’t know what time they’ll arrive.This means that customers may have to be in all day for an engineer to visit.

1 0 0 0 1 2

5Service center staff don’t always seem to know what they’re doing.

6 6 6 6 6 30

6When engineers visit,the customer finds that the problem could have been solved over the phone.

4 4 4 4 5 21

Page 22: 08 project quality management

#

Problem Cause Score

1

Phones aren’t answered quickly enough. Too few service center staff.15

2

Staff seem distracted and under pressure. Too few service center staff.6

3

Engineers don’t appear to be well Poor organization and preparation.4

4

Engineers don’t know what time they’ll arrive.This means that customers may have to be in all day for an engineer to visit.

Poor organization and preparation. 2

5

Service center staff don’t always seem to know what they’re doing.

Lack of training. 30

6

When engineers visit,the customer finds that the problem could have been solved over the phone.

Lack of training. 21

Page 23: 08 project quality management

• identify the VITAL few sources that are responsible for causing MOST of a problem’s effects.

• The categories shown on the horizontal axis exist as a valid probability.

• The relative frequencies of each specified cause decrease in magnitude until the default source named “other”.

• Typically organized into categories that measure either frequencies or consequences

Page 24: 08 project quality management

• (items 5 and 6) – 51 complaints.A: Lack of training

• (items 1 and 2) – 21 complaints.B: Too few service center staff

• (items 3 and 4) – 6 complaintsC: Poor organization and preparation

• Items (xx) - 2 complaintsD: Others

51

7278 80

64%

90%98% 100%

0%

20%

40%

60%

80%

100%

120%

0

10

20

30

40

50

60

70

80

90

A B C D

freq

uen

cy

cause

Page 25: 08 project quality management

• describe the central tendency, dispersion, and shape of a statistical distribution.

A D C B

51

26

21

freq

uen

cy

cause

Unlike the control chart, the histogram does not consider the influence of time on the variation that exists within a distribution.

Page 26: 08 project quality management

• used to determine whether or not a process is stable or has predictable performance.

• Upper and lower specification limits are based on requirements of the agreement.

• They reflect the maximum and minimum values allowed.

• There may be penalties associated with exceeding the specification limits.

• Upper and lower control limits are different from specification limits.

• The control limits are determined using standard statistical calculations and principles to ultimately establish the natural capability for a stable process.

• The project manager and appropriate stakeholders may use the statistically calculated control limits to identify the points at which corrective action will be taken to prevent unnatural performance.

• The corrective action typically seeks to maintain the natural stability of a stable and capable process.

Page 27: 08 project quality management

A process is considered out of control when:

(1) a data point exceeds a control limit;

(2) seven consecutive plot points are above or below the mean

1

2monitor various types of output variables.

track repetitive activities required for producing manufactured lots,

to monitor cost and schedule variances, volume, and frequency of scope changes, or other

Page 28: 08 project quality management

• plot ordered pairs (X, Y) seek to explain a change in the dependent variable, Y, in relationship to a change observed in the corresponding independent variable, X.

• The direction of correlation may be :– proportional (positive correlation),

– Inverse (negative correlation), or

– a pattern of correlation may not exist (zero correlation).

• If correlation can be established, a regression line can be calculated and used to estimate how a change to the independent variable will influence the value of the dependent variable

Page 29: 08 project quality management

0

2

4

6

8

10

12

0 5 10 15 20 25

PM

Ski

lls

Years of Experiences

PM SKILLS Linear (PM SKILLS)

Page 30: 08 project quality management

• comparing actual or planned project practices to those of comparable projects to identify best practices, generate ideas for improvement, and provide a basis for measuring performance.

Benchmarked projects may exist

within the performing organization

or outside of it, or can be within the

same application area.

Benchmarking allows for analogies

from projects in a different

application area to be made

Page 31: 08 project quality management

• statistical method for identifying which factors may influence specific variables of a product or process under development or in production.

DOE may be used during the Plan Quality Management process to determine the number and type of tests and their impact on cost of quality.

Page 32: 08 project quality management

• plays a role in OPTIMIZING products or processes.

• used to reduce the SENSITIVITY of product performance to sources of variations caused by environmental or manufacturing differences.

• provides a statistical framework for systematically changing ALL of the important factors.

• provide the OPTIMAL conditions for the product or process, highlight the factors that influence the results, and reveal the presence of interactions and synergy among the factors

Page 33: 08 project quality management

• choosing part of a population of interest for inspection

• Sample frequency and sizes should be determined during the Plan Quality Management process so the cost of quality will include the number of tests, expected scrap, etc.

There is a substantial body of

knowledge on statistical

sampling.

Page 34: 08 project quality management

• used to generate ideas

Brainstorming.

• diagrams of the forces for and against change.

Force field analysis.

• used to allow ideas to be brainstormed in small groups and then reviewed by a larger group.

Nominal group technique.

• used to link and sequence the activities identified

Quality management and control tools

Page 35: 08 project quality management

project manager; project sponsor; selected team

members;

Selected stakeholders;

anyone with responsibility for

Quality Management

others as needed

Page 36: 08 project quality management

• how the organization’s quality policies will be implemented. It

• how the project management team plans to meet the quality requirements set for the project.

• Should be reviewed early in the project to ensure that decisions are based on accurate information.

Review :

• a sharper focus on the project’s

value proposition

• reductions in costs and in the

frequency of schedule overruns that

were caused by rework.

Page 37: 08 project quality management

Quality Roles and Responsibilities

Roles Responsibilities

Quality Assurance Approach:

Quality Control Approach:

Quality Improvement Approach:

Project Title: Date Prepared:

Page 38: 08 project quality management

Details the steps for analyzing project management and product development processes to identify activities that enhance their value.

Process boundaries.

• Describe the PURPOSE of the process,

• the start and end ,

• inputs & outputs,

• owner,

• stakeholders

Process configuration.

• Provides a GRAPHIC depiction of processes, with interfaces identified,

• used to facilitate analysis.

Process metrics.

• Along with control limits,

• allows analysis of process EFFICIENCY.

Targets for improved performance.

• GUIDE the process improvement activities.

Areas to consider include:

Page 39: 08 project quality management

• Specifically describes a project or product attribute and how the control quality process will measure it.

• A measurement is an actual value.

• The tolerance defines the allowable variations to the metric.

• Quality objective :• stay within the approved budget by ±

10%, • Quality metric:

• measure the cost of every deliverable and determine the percent variance from the approved budget

on-time performance

defect frequency

test coverage

cost control

failure rate

availability

reliability

Quality metrics are used in

Page 40: 08 project quality management

ID Item Metric Measurement Method

Page 41: 08 project quality management

• component-specific structured tool, used

to verify that a set of required steps has

been performed.

• Quality checklists should incorporate the

acceptance criteria included in the scope

baseline simple or complex.

standardized.

From professional associations

From commercial service providers.

Checklists

Page 42: 08 project quality management
Page 43: 08 project quality management
Page 44: 08 project quality management

it facilitates the improvement of quality processes

Page 45: 08 project quality management

Inputs

Quality management plan

Process improvement plan

Quality metrics

Quality control measurements

Project documents

T&T

Quality management & control tools

Quality audits

Process analysis

Outputs

Change requests

Project management plan updates

Project documents updates

Organizational process assets updates

Page 46: 08 project quality management
Page 47: 08 project quality management

8.2.1.1 Quality Management Plan

• Describes the quality assurance and continuous process improvement approaches for the project.

8.2.1.2 Process Improvement Plan

• QA activities should be supportive of and consistent with the performing organization’s process improvement plans.

8.2.1.3 Quality Metrics

• provide the attributes that should be measured and the allowable variations.

8.2.1.4 Quality Control

Measurements

• QCM are the results of control quality activities.

• analyze and evaluate the quality of the processes against the standards of the organization or the requirements specified.

• validate actual measurements to determine their level of correctness.

8.2.1.5 Project Documents

• influence QA work and should be monitored within the context of a system for configuration management.

Page 48: 08 project quality management

• similar to mind-mapping techniques in that they are used to generate ideas that can be linked to form organized patterns of thought about a problem.

creation of the WBS may be enhanced by using the affinity diagram to give structure to the decomposition of scope.

Page 49: 08 project quality management

• Used to understand a goal in relation to the steps for getting to the goal.

• The PDPC is useful as a method for contingency planning because it aids teams in anticipating intermediate steps that could derail achievement of the goal.

Page 50: 08 project quality management

• An adaptation of relationship diagrams provide a process for creative problem solving in moderately complex scenarios that possess intertwined logical relationships for up to 50 relevant items.

developed from data generated in other tools such as the affinity diagram, the tree diagram, or the fishbone diagram

Page 51: 08 project quality management

• used to represent decomposition

hierarchies such as the WBS, RBS,

and OBS

• useful in visualizing the parent-to-

child relationships in any

decomposition hierarchy that uses a

systematic set of rules that define a

nesting relationship.

useful for establishing an expected value for a limited number of dependent relationships that have been diagramed systematically

Page 52: 08 project quality management

• Identify the key issues and the suitable alternatives to be prioritized as a set of decisions for implementation.

Criteria are prioritized and weighted before being applied to all available alternatives to obtain a mathematical score that ranks the options

Page 53: 08 project quality management

• include both Activity On Arrow & Activity On Node formats of a network diagram.

• ANDs are used with project scheduling methodologies (PERT, CPM, PDM).

Page 54: 08 project quality management

• used to perform data analysis within the

organizational structure created in the

matrix.

seeks to show the strength of relationships between factors, causes, and objectives that exist between the rows and columns.

Page 55: 08 project quality management

• a structured, independent process to determine if project activities comply with organizational and project policies, processes, and procedures.

• The objectives of a quality audit may include: increase in sponsor or customer acceptance.

reduced cost of quality

scheduled random,

conducted by internal

external auditors.Quality audits can confirm the implementation of approved

change requests including updates, corrective actions, defect repairs, and preventive actions.

Identify all good and best practices being implemented;

Identify all nonconformity, gaps, and shortcomings;

Share good practices introduced or implemented in similar projects in the organization and/or industry;

Proactively offer assistance in a positive manner to improve implementation of processes to help the team raise productivity; and

Highlight contributions of each audit in the lessons learned repository of the organization.

Page 56: 08 project quality management

• follows the steps outlined in the process improvement plan to identify needed improvements.

• examines

– problems experienced,

– constraints experienced,

– non-value-added activities

• Process analysis includes root cause analysis—a specific technique used to identify a problem, discover the underlying causes that lead to it, and develop preventive actions.

Page 57: 08 project quality management

• to allow full consideration of the recommended improvements.

• to take corrective action, preventive action, or to perform defect repair

8.2.3.1 Change Requests

• Quality management plan,

• Scope management plan

• Schedule management plan

• Cost management plan

8.2.3.2 Project Management Plan Updates

• Quality audit reports,

• Training plans, and

• Process documentation.

8.2.3.3 Project Documents Updates

• organization’s quality standards and the quality management system.

8.2.3.4 Organizational Process Assets Updates

Page 58: 08 project quality management

Identifying

• the causes of poor process or product quality

• recommending and/or taking action to eliminate them;

Validating

• that project deliverables and work meet the requirements specified by key stakeholders necessary for final acceptance.

pro

cess

of monitoring

recording results of executing the quality activities

to a

sses

s Performance

recommend necessary changes.

Page 59: 08 project quality management

INPUTS

• Project management plan

• Quality metrics

• Quality checklists

• Work performance data

• Approved change requests

• Deliverables

• Project documents

• Organizational process assets

T&T

• Seven basic quality tools

• Statistical sampling

• Inspection

• Approved change requests review

OUTPUTS

• Quality control measurements

• Validated changes

• Verified deliverables

• Work performance information

• Change requests

• Project management plan updates

• Project documents updates

• Organizational process assets updates

Page 60: 08 project quality management
Page 61: 08 project quality management

Prevention

•keeping errors out of the process

Inspection

•keeping errors out of the hands of the customer

Attribute sampling

• the result either conforms or does not conform

Variables sampling

•rated on a continuous scale that measures the degree of conformity

Tolerances

•specified range of acceptable results

Control limits

• identify the boundaries of common variation

Page 62: 08 project quality management

• contains the quality management plan, which is used to control quality.

• describes how quality control will be performed within the project.

8.3.1.1 Project Management Plan

• describes a project or product attribute and how it will be measured.

• EX: function points, mean time between failure (MTBF), and mean time to repair (MTTR).

8.3.1.2 Quality Metrics

• help to verify that the work of the project and its deliverables fulfill a set of requirements

8.3.1.3 Quality Checklists

• Planned vs. actual technical performance,

• Planned vs. actual schedule performance

• Planned vs. actual cost performance.

8.3.1.4 Work Performance Data

Page 63: 08 project quality management

• Approved change requests may include modifications such as defect repairs, revised work methods, and revised schedule. The timely implementation of approved changes needs to be verified.

8.3.1.5 Approved Change Requests

• any unique and verifiable product, result, or capability that results in a validated deliverable required by the project.

8.3.1.6 Deliverables

• Agreements,

• Quality audit reports and change logs supported with corrective action plans,

• Training plans and assessments of effectiveness

• Process documentation.

8.3.1.7 Project Documents

• The organization’s quality standards and policies,

• Standard work guidelines

• Issue and defect reporting procedures and communication policies.

8.3.1.8 Organizational Process Assets

Page 64: 08 project quality management

•The seven basic quality tools are illustrated conceptually.

8.3.2.1 Seven Basic Quality Tools

•Samples are selected and tested as defined in the quality management plan.

8.3.2.2 Statistical Sampling

• Inspections also are used to validate defect repairs.

8.3.2.3 Inspection (reviews, peer reviews, audits, or walkthroughs).

• to verify that they were implemented as approved

8.3.2.4 Approved Change Requests Review

Page 65: 08 project quality management

8.3.3.1 Quality Control

Measurements

• documented results of control quality activities.

• should be captured in the format that was specified through the Plan Quality Management process

8.3.3.2 Validated Changes

• changed or repaired items are inspected and will be either accepted or rejected before notification of the decision is provided.

• Rejected items may require rework.

8.3.3.3 Verified Deliverables

• A goal of the QC is to determine the correctness of deliverables.

• The results of performing QC are verified deliverables.

• Verified deliverables are an input to Validate Scope for formalized acceptance.

8.3.3.4 Work Performance Information

• performance data collected from various controlling processes, analyzed in context and integrated based on relationships across areas.

• Ex. (causes for rejections, rework required, or the need for process adjustments)

Page 66: 08 project quality management

8.3.3.5 Change Requests

• If the recommended corrective or preventive actions or a defect repair requires a change to the project management plan, a change request should be initiated in accordance with the defined Perform ICC

8.3.3.6 Project Management Plan

Updates

• Quality management plan

• Process improvement plan

8.3.3.7 Project Documents Updates

• Quality standards;

• Agreements

• Quality audit reports and change logs supported with corrective action plans

• Training plans and assessments of effectiveness

• Process documentation

8.3.3.8 Organizational Process Assets

Updates

• Completed checklists

• Lessons learned documentation