    PROJECT QUALITY

  • 7/30/2019 project quality

    2/22

    PERFORM QUALITY CONTROL

  • 7/30/2019 project quality

    3/22

    PERFORM QUALITY CONTROL Perform Quality process is concerned with

    monitoring work results to determine whetherthey comply with the standards defined in thequality management plan.

    This process identifies the causes of poor productquality or processes and makesrecommendations to bring them to requiredlevels.

    Quality Control is practiced throughout theproject to identify and remove the causes of unacceptable result

  • 7/30/2019 project quality

    4/22

    PERFORM QUALITY CONTROL

    Project management plan Quality Metrics Quality checklists Work PerformanceMeasurement Approved change request Deliverables Organizational processassets

    Cause & effect diagrams Control charts

    Flowcharting Histogram Pareto chart Run chart Scatter diagram Statistical Sampling

    Inspection Approved change requests review

    Quality controlmeasurements Validated changes Validated deliverables Organizational Processassets update Change Requests Project ManagementPlan update Project documentUpdates

    INPUTS

    TOOLS &TECHNIQUES

    PERFORMQUALITYCONTROL

    OUTPUTS

  • 7/30/2019 project quality

    5/22

    INPUTS OF PERFORM QUALITYCONTROL

    Perform Management Plan . The projectmanagement plan contains the qualitymanagement plan which is used to carry out theperform Quality Control Process.

    Quality Metrics. These provide the basis formeasuring project or product quality attributes inthe process.

    Quality Checklists . Quality checklists in thisprocess are used to ensure that set of requiredsteps determined in the plan quality process arecompleted

  • 7/30/2019 project quality

    6/22

    INPUTS OF PERFORM QUALITYCONTROL

    Work performance Measurements . Thesemeasurements allow the [project team toevaluate actual versus planned progress in the

    areas of technical performance, scheduleperformance and cost performance.

    Approved Change Requests. ApprovedChange requests are required changes thatwere approved and submitted as an input forimplementation

  • 7/30/2019 project quality

    7/22

    INPUTS OF PERFORM QUALITYCONTROL

    Deliverables . Part of achieving quality is ensuringthat all deliverables are completed successfully.Deliverables will be valuated as part of this

    process. Organizational Process assets . Organizational

    Process assets utilized by this process includes Standards , policies and guidelines relating to quality

    standards. Procedures for reporting and communicating issues

    and defects.

  • 7/30/2019 project quality

    8/22

    INPUTS OF PERFORM QUALITYCONTROL

    Deliverables . Part of achieving quality is ensuringthat all deliverables are completed successfully.Deliverables will be valuated as part of this

    process. Organizational Process assets . Organizational

    Process assets utilized by this process includes Standards , policies and guidelines relating to quality

    standards. Procedures for reporting and communicating issues

    and defects.

  • 7/30/2019 project quality

    9/22

    TOOLS & TECHNIQUES FOR PERFORMQUALITY CONTROL

    CAUSE AND EFFECT DIAGRAM. Also calledfishbone diagrams they show hypothesizedrelationships between potential causes andproblem under study.. Once the C & E diagramis constructed the analysis would proceed tofind out which of the potential causes were in

    fact contributing to the problem

  • 7/30/2019 project quality

    10/22

    TOOLS & TECHNIQUES FOR PERFORMQUALITY CONTROL

    CONTROL CHARTS. These are time sequencedcharts showing plotted values of a statisticincluding a centre line average and one ormore control limits. It is used to ensure thatchanges introduced are in statistical control

    FLOW CHARTS. Give us a logical flow of anactivity or process. Can be applied whilechecking the quality

  • 7/30/2019 project quality

    11/22

    TOOLS & TECHNIQUES FOR PERFORMQUALITY CONTROL

    PARETO CHART. These are named afterVilfredo Pareto who is credited for theorybehind Pareto Chart, also referred as 80:20rule. This rule as applied to quality says that asmall number of causes (20 %)create themajority of problems. Pareto theorized that

    you get the most benefit by spending themajority of time fixing the most importantproblems.

  • 7/30/2019 project quality

    12/22

    TOOLS & TECHNIQUES FOR PERFORMQUALITY CONTROL

    RUN CHARTS. Run charts are used to showvariations in trends in the process over time.They are similar to control charts, thoughwithout a displayed limit. Some otherinformation

    Common causes of variations come about as a

    result of circumstances or situations that arerelatively common the process you are using andeasily controllable at the operational level

  • 7/30/2019 project quality

    13/22

    TOOLS & TECHNIQUES FOR PERFORMQUALITY CONTROL

    RUN CHARTS. Special causes variances that are not common to

    the process Three type of variances that make up causes of

    variances Random variances

    Known or predictable variations Variations that are present in the process

  • 7/30/2019 project quality

    14/22

    TOOLS & TECHNIQUES FOR PERFORMQUALITY CONTROL

    Scatter Diagram . This uses 2 variables , onecalled an independently variable and theother dependent , which is a output. Scatterdisplay the relationships between these twoelements as points on a graph. Therelationship is typically analyzed to prove or

    disaprove cause and effect relationships.

  • 7/30/2019 project quality

    15/22

    TOOLS & TECHNIQUES FOR PERFORMQUALITY CONTROL

    STATISTICAL SAMPLING. This involves taking asample number of parts from the wholepopulation and examine them to determinewhether they fall in acceptable variances. Thequality plan defines how to measure theresults

  • 7/30/2019 project quality

    16/22

    TOOLS & TECHNIQUES FOR PERFORMQUALITY CONTROL

    INSPECTION. Inspection typically involvephysically looking at, measuring, or testingresults to determine whether they conform to

    the requirements or quality standards.Inspection will tell you where problems existsand gives you the opportunities to correctthem, thus leading to quality improvements.

    Inspection might occur after thr final product isproduced or at intervals during the developmentof the product to examine individual components

  • 7/30/2019 project quality

    17/22

    TOOLS & TECHNIQUES FOR PERFORMQUALITY CONTROL

    INSPECTION. Inspections are also known as reviews or peer

    reviews Approved Change Requests Review. Change

    requests that have been approved andimplemented are reviewed to ensure that they

    are implemented correctly

  • 7/30/2019 project quality

    18/22

    OUTPUTS OF PERFORM QUALITYCONTROL

    QUALITY CONTROL MEASUREMENTS. Qualitycontrol measurements include the results of quality control activities performed during theprocess.

    VALIDATED CHANGES. Validated changes arethe results of changes , defect repairs, orvariances that have been inspected andcorrected.

  • 7/30/2019 project quality

    19/22

    OUTPUTS OF PERFORM QUALITYCONTROL

    VALIDATED DELIVERABLES.Validateddeliverables ARE THOSE that have been takenthrough the tools and techniques of this

    process to determine if the deliverable iscorrect and accurate. ORGANIZATIONAL PROCESS ASSETS UPDATE.

    These includes:- Completed checklists Lessons learned documentation

  • 7/30/2019 project quality

    20/22

    OUTPUTS OF PERFORM QUALITYCONTROL

    CHANGE REQUESTS. Change requests to themanagement plan may result from carryingout this process and will be submitted to the

    authorized personnel for approval PROJECT MANAGEMENT PLAN UPDATES .

    Updates to the project management typicallyconsists of changes to the qualitymanagement plan and process improvementplan

  • 7/30/2019 project quality

    21/22

    OUTPUTS OF PERFORM QUALITYCONTROL

    PROJECT DOCUMENT UPDATE. ProjectDocument updates typically include updatesto quality standards.