zonal placement changes zonal placement slides a… · 16 19h northwest iowa power cooperative...
TRANSCRIPT
SPP Staff Proposal on TO Zonal Placement
April 20, 2017
Outline
• I. Background of the Staff’s Proposal – Paul Suskie
• II. Examples of New TO additions – Carl Monroe
• III. SPC Motion & Updated Staff Proposal– Charles Locke
• IV. Staff’s Recommendation to Move Forward – Paul Suskie
• V. Q&A – All
• VI. Next Steps – Mike Wise
2
Background of the Staff’s Proposal Paul Suskie
3
Staff Internal Team
• Carl Monroe, EVP & COO
• Paul Suskie, EVP & GC
• Pat Bourne, Director Transmission Policy
• Mike Riley, Associate General Counsel
• Charles Locke, Lead Regulatory Analyst
4
Zonal Placement Meetings
SPP Org Group Meetings June 2016 – RTWG
October 2016 – SPC
January 2017 – SPC
Individual Stakeholder Outreach by SPP Staff
December 2016 –
2 calls with KCPL & MJMEUC
January 2017 –
4 calls with KCPL; MJMEUC; and Gridliance
February 2017 –
8 calls with: KPP; KCPL; Gridliance; OG+E; AEP; MJMEUC; NPPD; Basin
Ad Hoc Stakeholder Meetings March 1, 2017 – 1st Draft
March 10, 2017- 2nd Draft
SPC Special Meeting
March 21, 2017 – Staff Proposal
Additional Stakeholder Outreach by SPP Staff
April 3-10, 2017 –
Contacts with OG+E; AEP; MJMEUC; Gridliance; NPPD; Basin; KPP; and KCP&L
5
Transmission Owner Changes1. ETEC in AEP (1/1/2007)
2. ITC Great Plains in MKEC (8/18/2009)
3. OMPA in AEP (1/1/2010)
4. OMPA in OGE (1/1/2010)
5. Transcos in AEP (7/1/2010)
6. Prairie Wind (4/1/2011)
7. Prairie Wind (4/1/2011)
8. Kansas Power Pool in Westar (12/20/2011)
9. Tri-County in SPS (4/1/2012)
10. Coffeyville in AEP (7/1/2013)
11. Transource MO (1/1/2014)
12. Lea County in SPS (4/1/2014)
13. CNPPD in NPPD (1/1/2015)
14. City of Independence in KCPL (6/1/2015)
15. Tri-State in NPPD (1/1/2016)
16. AECC in AEP (7/1/2016)
17. AECC in OGE (7/1/2016)
18. Integrated System (10/1/2015) 6
1
2
3
45
7
6
8
12
16
15
14
13
9
11
Transmission Owner Placed in Tariff
10
16
17
Stars do not indicate exact placement of Facilities
18
UMZ Additions
7
19a Western-UGP
19b Basin Electric Power Cooperative
19c Heartland Consumers Power District
19d Missouri River Energy Services - Total
19d (i) Missouri River Energy Services
19d(ii) Moorhead Public Service
19d(iii) Orange City Municipal Utilities
19d(iv) City of Pierre, South Dakota
19d(v) City of Sioux Center, Iowa
19d(vi) Watertown Municipal Utility Department
19d(vii) Denison Municipal Utilities
19d(viii) Vermillion Light & Power
19e East River Electric Power Cooperative, Inc.
19f Corn Belt Power Cooperative
19g NorthWestern Corporation (South Dakota)
19h Northwest Iowa Power Cooperative
19i Harlan Municipal Utilities
19j Central Power Electric Cooperative
Upper Missouri Zone – Total
Upper Missouri Zone Information
8
Number from
Zonal
Placement
Changes
Map
Zone
Number
from
Attachment
H
Transmission Owner Effective Date Resolution
16 19 Upper Missouri Zone – Total
16 19a Western-UGP 10/1/2015 As Filed
16 19b Basin Electric Power Cooperative 10/1/2015 Settled
16 19c Heartland Consumers Power District 10/1/2015 Settled
16 19d Missouri River Energy Services - Total 10/1/2015 Settled
16 19d (i) Missouri River Energy Services 10/1/2015 Settled
16 19d(ii) Moorhead Public Service 10/1/2015 Settled
16 19d(iii) Orange City Municipal Utilities 10/1/2015 Settled
16 19d(iv) City of Pierre, South Dakota 10/1/2015 Settled
16 19d(v) City of Sioux Center, Iowa 10/1/2015 Settled
16 19d(vi) Watertown Municipal Utility Department 10/1/2015 Settled
16 19d(vii) Denison Municipal Utilities 2/1/2107 In Settlement
16 19d(viii) Vermillion Light & Power 2/1/2017 In Settlement
16 19e East River Electric Power Cooperative, 10/1/2015 Settled
16 19f Corn Belt Power Cooperative 10/1/2015 In Settlement
16 19g NorthWestern Corporation (South Dakota) 10/1/2015 Settled
16 19h Northwest Iowa Power Cooperative 10/1/2015 Settled
16 19i Harlan Municipal Utilities 10/1/2015 As Filed
16 19j Central Power Electric Cooperative 10/1/2015 In Settlement
9
New Transmission Owner Information
New Transmission Owner (TO)
& Docket Number
Existing
Zone
Placement
Effective
Date
Requested
Zonal
ATRR
(Schedule
9)
Existing Zonal
ATRR Before
New
Transmission
Owner
% Increase
of
Requested
Zonal
ATRR to
Zone
FERC
Approved
Zonal ATRR
(Schedule 9)
% Increase
from FREC
Approved
Zonal ATRR
to the Zone
Resolution
1 ETEC ER07-396 AEP 1/1/2007 3,750,884 $88,681,579 0.47% no change no change As Filed
2 ITC Great Plains ER10-45 MKEC 8/18/2009 $673,368 $5,947,002 11.32% no change no change As Filed
3 OMPA ER10-273 AEP 1/1/2010 $748,647 $150,913,384 0.50% no change no change As Filed
4 OMPA ER10-273 OGE 1/1/2010 $106,268 $81,045,221 0.13% no change no change As Filed
5 Transcos ER11-2198 AEP 7/1/2010 $6,400 $133,972,249 0.005% no change no change As Filed
6 Prairie Wind ER11-3455 Regional 4/1/2011 No Sch 9 N/A 0.00% No Sch 9 N/A As Filed
7 Prairie Wind ER11-3455 Regional 4/1/2011 No Sch 9 N/A 0.00% No Sch 9 N/A As Filed
8 Kansas Power Pool ER12-140 Westar 12/20/2011 $528,917 $122,022,353 0.43% $350,243 0.29% Settled
9 Tri-County ER012-959 SPS 4/1/2012 $1,982,840 $110,464,906 1.79% $0 0.00% Hearing
10 Coffeyville ER14-418 AEP 7/1/2013 $391,790 $183,137,376 0.21% no change no change As Filed
11 Transource MO ER14-236 Regional 1/1/2014 No Sch 9 N/A 0.00% No Sch 9 N/A As Filed
12 Lea County ER14-1225 SPS 4/1/2014 $462,556 $109,581,048 0.42% $388,000 0.35% Settled
13 CNPPID ER15-279 NPPD 1/1/2015 $536,767 $47,541,737 1.13% $450,000 0.95% Settled
14 City of Indepedence ER15-1499 KCPL 6/1/2015 $7,237,454 $35,262,529 20.52% $3,000,000 8.51%
Settled-Phase
In
1/1/2017 $38,973,963* $3,750,000 9.62%
Settled-Phase
In
1/1/2018 $38,973,963* $5,000,000 12.83%
Settled-Phase
In
15 Tri-State ER16-204 NPPD 1/1/2016 $8,127,996 $45,213,710 17.98% Pending ??? In Settlement
16 AECC ER16-1546 AEP 7/1/2016 $584,186 $218,568,931 0.27% Pending ??? In Settlement
17 AECC ER16-1546 OGE 7/1/2016 $433,586 $93,307,022 0.46% Pending ??? In Settlement
* The % increase is based on the Schedule 9 ATRR for the Existing Zone’s TO at the time of the Phased-In ATRR for the New TO
FERC Cases on Zonal PlacementSPP Case:
Tri-State/NPPD Case (Docket No. ER16-204):
* FERC Administrative Law Judge’s order -- dated February 23, 2017.
MISO Case:
MISO/City of Rochester, MN/NPS-Xcel Case(Docket Nos. ER15-
277 & ER14-2134):
* FERC order -- dated December 30, 2014; FERC conditionally approve a
request by MISO and the City of Rochester “to make proposed revisions to . . . the MISO [Tariff] … subject to refund” and set the issues/dockets for hearing and settlement judge procedures.
FERC 206 Docket (Docket No. EL17-44):
* In a rehearing Order in MISO/Rochester Docket – dated February 3, 2017, FERC “institute[d] a proceeding pursuant to section 206 of the Federal Power Act (FPA) to examine the Joint Pricing Zone Revenue Allocation Agreement (JPZ Agreement) for Zone 16 of the MISO Tariff.”
* The first round of comments in the FERC investigation were due March 16th.
10
Examples of New TO AdditionsCarl Monroe
11
3 Scenarios of New TO Additions
(1) New Transmission Owner is already taking Network transmission service – Has Load in SPP.
(2) New Transmission Owner is not taking Network transmission service – Adds New Load to SPP.
(3) New Transmission Owner that will take no transmission service – Adds no load to SPP.
12
Scenario 1:New Transmission Owner is already taking Network transmission service
Scenario can include a municipality or cooperative that is a Network transmission customer of SPP and requests to place its transmission assets under SPP tariff.
Cost impacts in the following slide assume that the transmission facilities are placed in an existing zone where the entity is already taking Network Service.
13
(1) Example of New T.O. with Current Network Load
14
Before Transfer After Transfer Cost Shift
Tariff Revenue Requirement
Existing 100,000,000$ 100,000,000$
Transferring Facilities -$ 4,000,000$
Total 100,000,000$ 104,000,000$
Load Ratio Share
Load of Existing TO 98% 98%
Load of New TO 2% 2%
Sch. 9 Charges
Load of Existing TO 98,000,000$ 101,920,000$
Load of New TO 2,000,000$ 2,080,000$
Total 100,000,000$ 104,000,000$
Total Costs
Load of Existing TO - Sch. 9 98,000,000$ 101,920,000$ 3,920,000$
Load of New TO
Sch. 9 2,000,000$ 2,080,000$
Transferring Facilities 4,000,000$ -$
Total 6,000,000$ 2,080,000$ (3,920,000)$
Scenario 2:New Transmission Owner is not taking Network transmission service - Adds New Load to SPP.
Scenario can include a municipality or cooperative that is not a Network transmission customer of SPP and requests to place its transmission assets under SPP tariff.
Cost impacts in the following slide assume that the transmission facilities are placed in an existing zone and the entity begins taking Network Service at the time of asset transfer.
15
(2) Example of New T.O. with New Network Load
16
Before Transfer After Transfer Cost Shift
Tariff Revenue Requirement
Existing 100,000,000$ 100,000,000$
Transferring Facilities -$ 4,000,000$
Total 100,000,000$ 104,000,000$
Load Ratio Share
Load of Existing TO 100% 98%
Load of New TO 0% 2%
Sch. 9 Charges
Load of Existing TO 100,000,000$ 101,920,000$
Load of New TO -$ 2,080,000$
Total 100,000,000$ 104,000,000$
Total Costs
Load of Existing TO - Sch. 9 100,000,000$ 101,920,000$ 1,920,000$
Load of New TO
Sch. 9 -$ 2,080,000$
Transferring Facilities 4,000,000$ -$
Total 4,000,000$ 2,080,000$ (1,920,000)$
Scenario 3:New Transmission Owner that will take no transmission service - Adds no new load to SPP.
Scenario can include transmission only company (Transco) that requests to place its transmission assets under SPP tariff. This scenario assumes the facilities were not directed to be built by SPP.
Cost impacts in the following slide assume that the transmission facilities are placed in an existing zone.
17
(3) Example of New T.O. withNo Network Load
18
Before Transfer After Transfer Cost Shift
Tariff Revenue Requirement
Existing 100,000,000$ 100,000,000$
Transferring Facilities -$ 4,000,000$
Total 100,000,000$ 104,000,000$
Load Ratio Share
Load of Existing TO 100% 100%
Load of New TO 0% 0%
Sch. 9 Charges
Load of Existing TO 100,000,000$ 104,000,000$
Load of New TO -$ -$
Total 100,000,000$ 104,000,000$
Total Costs
Load of Existing TO - Sch. 9 100,000,000$ 104,000,000$ 4,000,000$
New TO
Sch. 9 -$ -$
Transferring Facilities 4,000,000$ -$
Total 4,000,000$ -$ (4,000,000)$
SPC Motion & Updated Staff ProposalCharles Locke
19
March 21, 2017 SPC Motion
Staff to consider revising the proposal to address:
(1) Planning process review consistent with SPP Tariff Attachment AI;
(2) A symmetrical cost/benefit analysis; and
(3) A phase-in process for regulatory assets that evaluates the time value of money.
20
Current Staff Proposal – Minor Changes
• No change to proposed Mitigation Threshold: (1) After several stakeholder calls, Staff found no consensus regarding mitigation. (2) Addition of an arbitrator-set mitigation was not well supported.
• Planning Criteria for Added Facilities: Staff supports a new & separate stakeholder initiative to consider the application of criteria to Schedule 9 facilities added to SPP rates.
• No addition of an Analysis of Benefits: Transfer of facilities does improve reliability of operations & outage coordination but is challenging to quantify.
• Regulatory Asset Phase-In: If needed, this can be initiated by the Applicant Transmission Owner through its revenue requirement filing.
21
Process Flow Chart – 6 Steps
1. SPP Notified by ATO
2) SPP Requests Data From ATO
3) SPP conducts Analysis
(A) Zonal Placement & (B) Cost Analysis
4) Negotiations – ATO & Zone
5) SPP’s Cost Mitigation Analysis
6) SPP files to revise Tariff
22
If New Zone, Go to Step 6
If Agreement Reached, Step 6
No Agreement File Mitigation
Should SPP adopt a negotiation-only approach without other steps?
No. If Stakeholders do not support a mitigation threshold methodology, SPP Staff proposes to retain Steps 1-4 and 6 of the current Staff Proposal in order to promote information flow and transparency.
23
Why maintain minimum zone size?
• Sch. 9 charges that reflect use of the system
• Sch. 11 Zonal charges (30-40% of all Sch. 11) Reflect use of the system and avoid free riders
Protect small loads from disproportionate charges
• Reduce administrative cost Settlements, OASIS, Att. H, Att. M, Att. T, RCAR, RRR File
• Treat transferring facilities with and without load in comparable manner
• Reduce disparity in zonal rates
• Maintain through-and-out service revenues
24
Why not use cost shift in zonal placement decision?
• Creates equity problems in numerous situations, such as when the smaller cost increase applies to the zone with higher rates
• May be difficult to obtain FERC approval of this approach
• Cost shift should not override electrical and operational considerations including degree of interconnectivity and location of load
• Cost shift as a criterion can increase disparity in:
Zonal rates
Size of Zones
25
Why not include Schedule 11 in baseline costs for rate impact?
• The rate effect of transferring existing facilities is the cost shift issue. The issue is not the load’s customer status, which drives Sch. 11 charges
• Application of 30.9 credits in the baseline assumes the ATO’s load is or will be taking Network Service. Therefore, Sch. 11 costs are allocated to all zonal loads in the baseline assumption
• There are benefits to the ATO’s load associated with its share of Sch. 11 charges
• Including Sch. 11 in the baseline blurs the distinction between cost categories that have been separated under the Tariff for allocation purposes
26
Staff’s Recommendation to Move ForwardPaul Suskie
27
Process Flow Chart – 6 5 Steps
1. SPP Notified by ATO
2) SPP Requests Data From ATO
3) SPP conducts Analysis
(A) Zonal Placement & (B) Cost Analysis
4) Negotiations – ATO & Zone
5) SPP’s Cost Mitigation Analysis
65) SPP files to revise Tariff
28
If New Zone,
Go to Step 65
If Agreement Reached, Step 65
File default revenue
requirement
Consider Removing
Staff’s Recommended Options to Move Forward – Decision Points• (1) Retain all other steps of the Current Staff Proposal
Improve transparency
Increase information sharing
Enable the opportunity for a negotiated compromise
NOT INCLUDIING Step 5 (Mitigation)
• (2) Recommend Adding Zonal Placement Criteria to Tariff.
• (3) Consider the removal of the cost shift mitigation threshold from the Current Staff Proposal due to lack of consensus.
If no decision is made by stakeholders, the default is what SPP has done to date.
29
(1) Retain all other steps of the Current Staff Proposal – Except 5.
30
1. SPP Notified by ATO
2) SPP Requests Data From ATO
3) SPP conducts Analysis
(A) Zonal Placement & (B) Cost Analysis
4) Negotiations – ATO & Zone
5) SPP’s Cost Mitigation Analysis
65) SPP files to revise Tariff
If New Zone,
Go to Step 65
If Agreement Reached, Step 65
File default revenue
requirement
Consider Removing
(2) Recommend Adding Zonal Placement Criteria to Tariff.
31
In evaluating the zonal placement of existing facilities, SPP staff is to review the information
provided by the ATO and apply the following criteria in determining whether to place the facilities
in a new Zone:
1. Whether the ATRR of the Transferring Facilities is less than the minimum zonal ATRR
benchmark, as described in the Zonal Placement Analysis Procedures (Appendix B);
2. The extent to which the Transferring Facilities substantively increase the SPP regional footprint;
and
3. The extent to which the load served through the Transferring Facilities received Network Service
or Long-Term Firm Point-To-Point Transmission Service within existing Zones prior to the
transfer.
If the facilities are not placed in a new Zone, SPP staff is to apply the following criteria in
determining which existing Zone the facilities are to be placed in:
1. The extent to which the Transferring Facilities are embedded within an existing Zone;
2. The extent to which the Transferring Facilities are integrated with an existing Zone; and
3. The extent to which the load served through the Transferring Facilities received Network Service
or Long-Term Firm Point-To-Point Transmission Service within each existing Zone prior to the
transfer.
(3) Removal of the cost shift mitigation threshold from the Current Staff Proposal
• (1) After several stakeholder calls, Staff found no consensus regarding mitigation.
• (2) Addition of an arbitrator-set mitigation was not well supported.
• (3) Possible Stakeholder option(s)?
32
In which governing documents should the policy be placed?
If approved, each element of the policy could be placed as follows:
• In the Tariff:
Scope of the zonal placement policy
Description of the steps in the process
Zonal placement key criteria
• In a business practice:
Informational requirements
Zonal placement analysis details
Transferring facilities review
Cost mitigation process, if approved
33
Questions and Next Steps
34