who should pay for costly water and sewer infrastructure? the legal considerations

19
Who Should Pay for Costly Water and Sewer Infrastructure? The Legal Considerations TRWA / TWCA Water Law Seminar January 24 – 25, 2013 Austin, Texas Leonard H. Dougal Jackson Walker L.L.P. [email protected](512) 236-2000

Upload: fai

Post on 07-Feb-2016

36 views

Category:

Documents


2 download

DESCRIPTION

Who Should Pay for Costly Water and Sewer Infrastructure? The Legal Considerations. TRWA / TWCA Water Law Seminar January 24 – 25, 2013 Austin, Texas. Leonard H. Dougal Jackson Walker L.L.P. [email protected] • (512) 236-2000. Introduction. Public-Private Efforts in Project Development - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Who Should Pay for Costly Water and Sewer Infrastructure?  The Legal Considerations

Who Should Pay for Costly Water and Sewer Infrastructure?

The Legal Considerations

TRWA / TWCA Water Law Seminar January 24 – 25, 2013

Austin, Texas

Leonard H. DougalJackson Walker [email protected] • (512) 236-2000

Page 2: Who Should Pay for Costly Water and Sewer Infrastructure?  The Legal Considerations

Introduction

• Public-Private Efforts inProject Development

• Revenue Sources: Rates and Impact Fees

• Classes of Service2

Page 3: Who Should Pay for Costly Water and Sewer Infrastructure?  The Legal Considerations

Public-Private Partnerships (P3)• Comprehensive P3 statute adopted in

2011

• Authorizes governmental entities to contract with private parties for qualifying public projects, including:– water supply facilities– public works– waste treatment facilities Tex. Gov’t Code Ch.

2267.

3

Page 4: Who Should Pay for Costly Water and Sewer Infrastructure?  The Legal Considerations

Public-Private Partnerships (P3)• Governmental entity must adopt a resolution

indicating it elects to operate under Ch. 2267

• Before requesting or considering a P3 project, guidelines must be adopted & made available to the public

• May receive solicited or unsolicited proposalsTex. Gov’t Code Ch. 2267.

4

Page 5: Who Should Pay for Costly Water and Sewer Infrastructure?  The Legal Considerations

Public-Private Partnerships (P3)• Comprehensive Agreement for P3 must

include:– Delivery of letters of credit or other security– Delivery of performance & payment bonds– Review & approval of plans & specifications– Maintenance of public liability insurance

policy– Reimbursement to governmental entity for

services provided – Any user fee, lease payment or service

paymentTex. Gov’t Code § 2267.058(a).

5

Page 6: Who Should Pay for Costly Water and Sewer Infrastructure?  The Legal Considerations

Proposed Lake Columbia

6

Page 7: Who Should Pay for Costly Water and Sewer Infrastructure?  The Legal Considerations

Public-Private Project: Example• Lake Columbia

– Proposed new reservoir to supply East Texas

– Partnership of Angelina and Neches River Authority & Tomlin Infrastructure Group

– $330 Million Project

– Grants Tomlin 47% of the lake’s water rights

7

Page 8: Who Should Pay for Costly Water and Sewer Infrastructure?  The Legal Considerations

Friday, January 11, 2013Texas Bills Would Dedicate $2 Billion for Water

8

Page 9: Who Should Pay for Costly Water and Sewer Infrastructure?  The Legal Considerations

Ratemaking Jurisdiction

• TCEQ Original Jurisdiction for IOUsserving outside city limits

• TCEQ Appellate Jurisdiction for:– Districts– WSCs– IOUs serving inside city limits– City customers outside city limits– Wholesale water rates Tex. Water Code §§ 13.042,

13.043.

9

Page 10: Who Should Pay for Costly Water and Sewer Infrastructure?  The Legal Considerations

Rate Appeals – Retail

• Affected customers must file a petition within 90 days of final decision

• Petition must be signed by lesser of 10,000 or 10% of ratepayers whose rates have been changed and who are eligible to appeal

• TCEQ reviews appeals de novo and will order the rates the governing body should have fixed Tex. Water Code § 13.043; 30 TAC §

291.41.

10

Page 11: Who Should Pay for Costly Water and Sewer Infrastructure?  The Legal Considerations

Wholesale Rate Appeals – Bifurcated Process at SOAH

1. Determination of Public Interest• protested rate impairs seller’s ability to continue to

provide service; • protested rate impairs purchaser’s ability to continue to

provide service to its retail customers; or• protested rate evidences seller’s abuse of monopoly

power• protested rate is unreasonably preferential, prejudicial,

or discriminatory, compared to the wholesale rates the seller charges other wholesale customers

2. Determination of Cost of Service• Will rely on any reasonable methodologies set by

contract 30 TAC §§ 291.128-138.

11

Page 12: Who Should Pay for Costly Water and Sewer Infrastructure?  The Legal Considerations

Proposed Transfer of Rate Regulation to PUC• Legislature considering transfer of water and

wastewater rate regulation from TCEQ to PUC

• Recommended by Sunset Advisory Commission

• Would consolidate most utility regulation within one agency

• Proposal for PUC’s Office of Public Utility Counsel to represent customer interests

Sunset Commission Report, Jan. 2013 12

Page 13: Who Should Pay for Costly Water and Sewer Infrastructure?  The Legal Considerations

Impact Fees

“A charge or assessment imposed by a political subdivision against new development in order to generate revenue for funding or recouping the costs of capital improvements or facility expansions necessitated by and attributable to the new development.”

Tex. Loc. Gov’t Code § 395.001(4).

13

Page 14: Who Should Pay for Costly Water and Sewer Infrastructure?  The Legal Considerations

Impact Fees• May be imposed only to pay costs of constructing

capital improvements or facility expansions

• May not be used for:– Construction, acquisition, or expansion of facilities not

identified in the capital improvements plan;– Repair, operation, or maintenance;– Upgrading, expanding, or replacing existing capital

improvements to serve existing development;– administrative and operating costs;– principal payments and interest or other finance

charges on bonds or other indebtedness.

14

Page 15: Who Should Pay for Costly Water and Sewer Infrastructure?  The Legal Considerations

Impact Fees – Adoption • TCEQ Process

– Develop Capital Improvements Plan (CIP)– Adopt resolution requesting approval of Impact Fee– Submit application to TCEQ– Public notice– TCEQ approval if impact fee is “reasonable, equitable,

and necessary”

• Local Gov’t Code Ch. 395 Process– Develop CIP– Public notice and hearing on CIP– Board order approving CIP– Public notice and hearing on Impact Fee– Board order adopting Impact Fee

15

Page 16: Who Should Pay for Costly Water and Sewer Infrastructure?  The Legal Considerations

Classes of Service• Districts may establish different charges

among classes of customers based on any factor the district considers appropriate, including:– (1) similarity of the type of customer to other

customers in the class (e.g. residential, commercial, industrial, out-of-district)

– (2) type of services provided to the customer class;

– (3) cost of facilities, operations, and administrative services (e.g. for security, recreational facilities, or fire protection)

– (4) total revenues received relative to cost of service Tex. Water Code §

49.2122. 16

Page 17: Who Should Pay for Costly Water and Sewer Infrastructure?  The Legal Considerations

Classes of Service• District is presumed to have weighed and

considered appropriate factors and to have properly established charges, fees, rentals, and deposits absent a showing the district acted arbitrarily and capriciously.

• Rates may not be unreasonably preferential, prejudicial, or discriminatory in application to each class of customers.

Tex. Water Code § 49.2122(c).

30 TAC § 291.41.

17

Page 18: Who Should Pay for Costly Water and Sewer Infrastructure?  The Legal Considerations

Improvement Triggers• Water – 85% rule

– System demand at 85% of design capacity; submit planning reportto TCEQ

• Wastewater – 75/90 rule– 75% permitted flow – initiate

engineering and financial planning– 90% permitted flow – obtain

authorization to commence construction30 TAC § 305.126.

30 TAC § 291.93(3).

18

Page 19: Who Should Pay for Costly Water and Sewer Infrastructure?  The Legal Considerations

QUESTIONS?