wednesday, october 3, 2007 panel presentation cppc forum 2007, calgary
Post on 20-Dec-2015
217 views
TRANSCRIPT
Wednesday, October 3, 2007
Panel PresentationCPPC Forum 2007, Calgary
Panel Presentation
Who is CCDC? Introduction to the “new” CCDC-2 Panel Presentation – Key Risks Q&A
Terry Brown – Contractor & CCA Rep
Gregory Hersen – Lawyer & Bar Assoc. Rep
Ron de Vries – Owner Rep
Who is CCDC?
Canadian Construction Association
Royal Architectural Institute of Canada
Association of Consulting Engineers of Canada
Construction Specifications Canada
Who is CCDC?
Public Sector Owners
Legal Representation Member - Canadian Bar Association
Private Sector Owners
CCDC Mandate
“CCDC is responsible for the development,
revision and improvement of Canadian
standard construction documents used by
Owners, Consultants, Contractors and other
participants in both public and private
sectors throughout Canada.”
Why Use CCDC Documents?
Relied on as industry standards. Provide balance, uniformity and
standardization for bidding and contract procedures.
Fair allocation of risks and protects the rights of all parties equitably.
Developed in collaborative environment. Unbalanced contracts increase risk of claims
and disputes. Industry wide endorsement - CCDC sells over
50,000 documents annually.
Document Development
1. Draft is prepared by working group
3. Draft is submitted to constituent organizations
2. Reviewed in detail by Committee
4. Final document issued for endorsement
What’s special about CCDC Documents?
CCDC Documents have endorsement from all of the constituent member organizations and are applicable to a broad range of construction industry use.
CCDC Documents CCDC 2 - 1994 Stipulated Price Contract CCDC 3 - 1998 Cost Plus Contract CCDC 4 - 1982 Unit Price Contract CCDC 9a & 9b - 2001 Statutory Declaration CCDC 11 - 1996 Contractor’s Qualification CCDC 12 - 1994 Project Financial Info CCDC 18 - 2001 Civil Works Contract CCDC 20 - 1994 Guide to Use of CCDC 2
CCDC Documents CCDC 21 - 2000 Guide to Construction
Insurance CCDC 22 - 2002 Guide to Construction
Surety Bonds CCDC 23 - 2005 Guide to Calling Bids and
Awarding Contracts CCDC 24 - 1996 Guide to Model Forms and
Support Documents CCDC 40 - 1994 Rules for Mediation and
Arbitration of Construction Disputes
CCDC Documents
CCDC 43 - 1998 Guide to Use of CCDC 3 CCDC 48 - 2002 Guide to Use of CCDC 18 CCDC 220 – 2002 Bid Bond CCDC 221 - 2002 PerformanceBond CCDC 222 - 2002 Labour & Material
Payment Bond
Documents Under Review CCDC 2 – Stipulated Price Contract CCDC 4 – Unit Price Contract CCDC 5A & 5B – Construction
Management Contracts CCDC 14 – Design-Build Contract CCDC 15 – Design-Builder/Consultant
Contract CCDC 20 – Guide to use of CCDC-2 CCDC 45 – Guide to Construction
Management CCDC 46 – Guide to Design-Build
CCDC Documents
Introduction to the new CCDC - 2
Overview:
Editorial updates to the 1994 version. Significant changes to key provisions.
Indemnification Waiver of Claims
Roll-out by end of 2007 CSC Training Sessions
CCDC 2: Stipulated Price Contract
Introduces concept of mutual indemnification between Owner and Contractor.
Consultant removed. Introduces limits of liability.
GC 12.1: Indemnification
CCDC 2: Stipulated Price Contract
Owner/Contractor Indemnify and hold harmless each other against
Nature of
the Claims
Monetary Limitation
Time Limitation
Direct Claims Insured and uninsured claims
Contract Price, but
no less than the greater of $2M and the insurance limit, and no more than $20M
Shorter of 6 yrs from the date of Substantial Performance of the work and provincial limitation statute
Third-Party Claims Relating to bodily Injury or Property Damage
Insured
Claims
No Limit
Uninsured Claims
No Limit
CCDC 2: Stipulated Price ContractEXCEPTIONS
Owner Indemnifies the Contractor
Nature of the Claims
Monetary Limitation
Time Limitation
Toxic/Hazardous Substances
Presence prior to the Work
No limit No time limitation
Infringement of a patent of invention
Supplied to the Contractor
No limit No time limitation
Lack of or defect in title
No limit No time limitation
CCDC 2: Stipulated Price Contract
GC 12.2: Waiver of Claims
Concept of mutual waiver Waiver period limit established – 6 days
before expiry of the lien period. Now Substantial Performance vs. Final
Certificate for Payment. Exceptions
Claim for which a lien may be asserted and others …
Panel Presentation – Key Risks
Contractors Perspective Timely & Full payment. Owner’s Consultant Team Contract Security & Insurance Mould Indemnification & Waiver of Claims
Panel Presentation – Key RisksLegal Perspective Qualified bids. Inappropriate use of supplementary
conditions to CCDC. Failure to keep proper documentation for
dispute resolution. Insufficient or inappropriate contract
security. Non-compliant bids. Inappropriate use of bidding processes, ie.
RFP’s v. Tenders
Panel Presentation – Key RisksOwner Perspective Quality of bid documents. Accuracy of estimates. Funding uncertainty and phasing. Attracting bidders. Qualified or non-compliant bids. Contractor performance – quality & time. Construction site safety – “constructor”. Contract changes. Contract completions.
Panel Presentation – Key RisksOwner Perspective Quality of bid documents.
Enhanced communication with A&E firms during the preparation of contract documents.
Bid-ability & build-ability reviews before tender.
Restricted amendments within 5 days of closing.
Panel Presentation – Key RisksOwner Perspective Accuracy of estimates. Funding uncertainty and phasing.
Currently a serious risk. Must factor in market conditions. Build in alternates to ensure award. Retain professional quantity
surveyors/estimators. Build in contingencies to project funding. Better understanding of the accuracy of
estimates.
Panel Presentation – Key RisksOwner Perspective Attracting bidders.
Ensuring adequate funds are available. Appropriate packaging of work. Using bid documents that are familiar to
the industry. Maintaining productive relationships. Ensuring payment. Track response to bids and follow-up with
plan-takers to find out why they did not bid. Provide bid documents to Association Plans
Rooms.
Panel Presentation – Key RisksOwner Perspective Qualified or non-compliant bids.
Waiver of non-compliance clause. Use industry standard documents. Ensure terms and conditions are appropriate
to the target industry. Pre-tender site visits and briefings.
Panel Presentation – Key RisksOwner Perspective Contractor performance – quality & time.
On-site inspections and QA program. Pre-qualification for specialized work. Bond or security for all contracts >$100K Mandatory schedule with progress
payments. Aggressive completion performance targets. Contractor Performance and Evaluation
Review (CPER) on 100% of contracts. Restricted bidders list.
Panel Presentation – Key RisksOwner Perspective Construction site safety – “constructor”.
Safety section in the contract documents to clearly define responsibilities.
Safety inspectors. Work closely with provincial authorities.
Panel Presentation – Key RisksOwner Perspective Contract changes.
Currently average 11% of contract award value.
Part of corporate performance measure. Rigorous scope management. Includes extension of time & costs if
warranted.
Panel Presentation – Key RisksOwner Perspective Contract completions.
Establish realistic completion dates in the contract.
Set corporate targets for timeliness of substantial and final completions.
Rigorous monitoring of schedule. Progress payments tied to schedule reviews. Early intervention for problem contracts. Use of contract funds to complete
deficiencies.