vesda commissioning guide - janusfiresystems.com3 pre-commissioning 7 3.1 beforegoingtothesite 7 3.2...

34
VESDA Commissioning Guide December 2012 Document: 10195_06 Part Number: 30005

Upload: others

Post on 28-Feb-2020

11 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDACommissioning Guide

December 2012

Document: 10195_06

Part Number: 30005

Page 2: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:
Page 3: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA by Xtralis VESDA Commissioning Guide

www.xtralis.com i

Intellectual Property and CopyrightThis document includes registered and unregistered trademarks. All trademarks displayed are the trademarks oftheir respective owners. Your use of this document does not constitute or create a licence or any other right to usethe name and/or trademark and/or label.

This document is subject to copyright owned by Xtralis AG (“Xtralis”). You agree not to copy, communicate to thepublic, adapt, distribute, transfer, sell, modify or publish any contents of this document without the express priorwritten consent of Xtralis.

DisclaimerThe contents of this document is provided on an “as is” basis. No representation or warranty (either express orimplied) is made as to the completeness, accuracy or reliability of the contents of this document. The manufacturerreserves the right to change designs or specifications without obligation and without further notice. Except asotherwise provided, all warranties, express or implied, including without limitation any implied warranties ofmerchantability and fitness for a particular purpose are expressly excluded.

General WarningThis product must only be installed, configured and used strictly in accordance with the General Terms andConditions, User Manual and product documents available from Xtralis. All proper health and safety precautionsmust be taken during the installation, commissioning and maintenance of the product. The system should not beconnected to a power source until all the components have been installed. Proper safety precautions must be takenduring tests and maintenance of the products when these are still connected to the power source. Failure to do soor tampering with the electronics inside the products can result in an electric shock causing injury or death and maycause equipment damage. Xtralis is not responsible and cannot be held accountable for any liability that may arisedue to improper use of the equipment and/or failure to take proper precautions. Only persons trained through anXtralis accredited training course can install, test and maintain the system.

LiabilityYou agree to install, configure and use the products strictly in accordance with the User Manual and productdocuments available from Xtralis.

Xtralis is not liable to you or any other person for incidental, indirect, or consequential loss, expense or damages ofany kind including without limitation, loss of business, loss of profits or loss of data arising out of your use of theproducts. Without limiting this general disclaimer the following specific warnings and disclaimers also apply:

Fitness for PurposeYou agree that you have been provided with a reasonable opportunity to appraise the products and have madeyour own independent assessment of the fitness or suitability of the products for your purpose. You acknowledgethat you have not relied on any oral or written information, representation or advice given by or on behalf of Xtralisor its representatives.

Total LiabilityTo the fullest extent permitted by law that any limitation or exclusion cannot apply, the total liability of Xtralis inrelation to the products is limited to:

i. in the case of services, the cost of having the services supplied again; orii. in the case of goods, the lowest cost of replacing the goods, acquiring equivalent goods or having the goods

repaired.

IndemnificationYou agree to fully indemnify and hold Xtralis harmless for any claim, cost, demand or damage (including legal costson a full indemnity basis) incurred or which may be incurred arising from your use of the products.

MiscellaneousIf any provision outlined above is found to be invalid or unenforceable by a court of law, such invalidity orunenforceability will not affect the remainder which will continue in full force and effect. All rights not expresslygranted are reserved.

Page 4: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA Commissioning Guide VESDA by Xtralis

ii www.xtralis.com

ScopeThe VESDA Commissioning Guide outlines the commissioning process for the VESDA system. It will guideyou through the commission process and the completion of commissioning documentation. The guide alsoprovides information on the approval and handover of commissioned VESDA systems.

The Commissioning Guide helps with the commissioning andmanagement of the VESDA system.

This guide assumes that you have attended accredited VESDA training on commissioning and areknowledgeable about the VESDA product range. This guide also assumes that you have an understanding ofthe various aspects of an aspirating smoke detection system and are fully aware of the local codes andstandards.

To commission the VESDA system youmust have the necessary certification issued by Xtralis or anauthorized distributor. Commissioning before you receive the appropriate trainingmay void the warranty.

Document ConventionsThe following typographic conventions are used in this document:

Convention DescriptionBold Used to denote: emphasis. Used for names of menus, menu options,

toolbar buttons

Italics Used to denote: references to other parts of this document or otherdocuments. Used for the result of an action.

The following icons are used in this document:

Convention DescriptionCaution: This icon is used to indicate that there is a danger toequipment. The danger could be loss of data, physical damage, orpermanent corruption of configuration details.

Warning: This icon is used to indicate that there is a danger of electricshock. This may lead to death or permanent injury.

Warning: This icon is used to indicate that there is a danger of inhalingdangerous substances. This may lead to death or permanent injury.

Contact UsThe Americas +1 781 740 2223

Asia +86 21 5240 0077

Australia and New Zealand +61 3 9936 7000

UK and Europe +44 1442 242 330

Middle East +962 6 588 5622

www.xtralis.com

Page 5: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA by Xtralis VESDA Commissioning Guide

www.xtralis.com iii

Codes and Standards Information for Air Sampling Smoke DetectionWe strongly recommend that this document is read in conjunction with the appropriate local codes and standardsfor smoke detection and electrical connections. This document contains generic product information and somesections may not comply with all local codes and standards. In these cases, the local codes and standards musttake precedence. The information below was correct at time of printing but may now be out of date, check with yourlocal codes, standards and listings for the current restrictions.

FCC Compliance StatementThis equipment has been tested and found to comply with the limits for a Class B digital device, pursuant to part 15of the FCC Rules. These limits are designed to provide reasonable protection against harmful interference in aresidential installation. This equipment generates, uses and can radiate radio frequency energy and, if not installedand used in accordance with the instruction, may cause harmful interference to radio communications. However,there is no guarantee that interference will not occur in a particular installation. If this equipment does causeharmful interference to radio or television reception, the user is encouraged to try to correct the interference by oneor more of the following measures; re-orientate or relocate the receiving antenna, increase the separation betweenthe equipment and receiver, connect the equipment to a power outlet which is on a different power circuit to thereceiver or consult the dealer or an experienced radio/television technician for help.

FDAThis VESDA product incorporates a laser device and is classified as a Class 1 laser product that complies with FDAregulations 21 CFR 1040.10. The laser is housed in a sealed detector chamber and contains no serviceable parts.The laser emits invisible light and can be hazardous if viewed with the naked eye. Under no circumstances shouldthe detector chamber be opened.

FM Hazardous Applications3611 Hazardous Approval Warning: Exposure to some chemicals may degrade the sealing of relays used on thedetector. Relays used on the detector are marked “TX2-5V”, “G6S-2-5V” or “EC2-5NU”.

VESDA detectors must not be connected or disconnected to a PC while the equipment is powered in an FMDivision 2 hazardous (classified) location (defined by FM 3611).

FM Approved ApplicationsThe product must be powered from VPS-100US-120 or VPS-100US-220 only.

ONORM F3014ONORM F3014, transport times for all tubes (including capillaries) must not exceed 60 seconds from any hole. Thismeans that the pre-designed pipe networks that include capillaries cannot be used.

AS1603.8The performance of this product is dependent upon the configuration of the pipe network. Any extensions ormodifications to the pipe network may cause the product to stop working correctly. You must check that ASPIRE2approves alterations before making any changes. ASPIRE2 is available from your VESDA ASD distributor.

AS1851.1 2005Maintenance Standards. Wherever this document and the AS1851.1 differ, AS1851.1 should be followed inpreference to this document.

European InstallationsThe product must use a power supply conforming to EN54: Part 4.

Page 6: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA Commissioning Guide VESDA by Xtralis

iv www.xtralis.com

This page is intentionally left blank.

Page 7: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA by Xtralis VESDA Commissioning Guide

www.xtralis.com 1

Table of Contents1 Introduction to VESDA Commissioning 3

2 The Commissioning Process 5

3 Pre-Commissioning 73.1 Before going to the Site 73.2 VESDA Commissioning Form - Prerequisites 73.3 Once on Site 7

4 System Configuration and Setting Thresholds 94.1 Generic Configuration (VLC, VLS, VLP) 94.2 Detector Specific Configuration Steps (VLC, VLS, VLP) 114.3 VESDA VFT-15 Detector Configuration 154.4 VESDA VLF Configuration 164.5 Documenting Configuration and Thresholds 16

5 System Integrity Test 195.1 Performance-based Smoke Testing 195.2 Testing Relay Function 235.3 Testing Devices 235.4 Documenting Test Results 23

6 Hand Over 25

Index 27

Page 8: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA Commissioning Guide VESDA by Xtralis

2 www.xtralis.com

This page is intentionally left blank.

Page 9: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA by Xtralis VESDA Commissioning Guide

www.xtralis.com 3

1 Introduction to VESDA CommissioningCommissioning is the final stage of any VESDA system installation. It forges together the elements ofdesigning and installing a pipe network, installing the detectors, cabling for power and communications, andthe powering up of the system. Your objective and outcome of the commissioning process is to provide a fullyfunctional VESDA system that matches your customers specification.

Page 10: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA Commissioning Guide VESDA by Xtralis

4 www.xtralis.com

This page is intentionally left blank.

Page 11: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA by Xtralis VESDA Commissioning Guide

www.xtralis.com 5

2 The Commissioning ProcessThe commissioning process is a step by step process designed to systematically check and validate all theoperational aspects of the VESDA system. The process benchmarks the performance levels tailored for eachsite and generates necessary documentation for the effectivemanagement andmaintenance of the system.The steps required in a typical commissioning are listed below.

Table 2-1: Commissioning process steps

Commissioning Step Action1. Pre-Commissioning (Before going to the customersite)

Gather site information

Obtain a copy of:

l Pipe network design recordsl Pipe network installation forml Site plans and pipe layout plans

Start to fill in:

l Commissioning formsl Any regulatory forms required

2. Pre-Commissioning (Once you are on site) l Check cablesl Power up systeml Preliminary system check

3. Configuration & Thresholds l Configure the systeml Set thresholdsl Record in commissioning form:

o Settingso Pipe network specifications (or attach a

copy of the ASPIRE2 Installation DataPack)

4. Test the System l Sampling pipe network integrityl Relay functionl Detectorsl Ancillary Devicesl Record resultsl Performance tests

5. HandOver l Complete commissioning forms andattachments

l Forward copies along with attachments to allrelevant persons

Page 12: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA Commissioning Guide VESDA by Xtralis

6 www.xtralis.com

This page is intentionally left blank.

Page 13: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA by Xtralis VESDA Commissioning Guide

www.xtralis.com 7

3 Pre-CommissioningPre-commissioning is split into two parts. The first set of tasks can be performed before you visit thecustomer site. Gathering the information first will save you time once you reach the site as you will only visitthe site when you have all thematerials required to complete the commissioning process.

3.1 Before going to the SitePrior to starting the commissioning process, the commissioning engineer should study any design andinstallation considerations for the site. Properly maintained pipe network design and installation recordsshould assist in providingmost of the information. Youmust ensure that you have a copy of:

1. The site layout plans.2. The "As Installed" drawings for the site.3. Pipe network design records.4. Pipe network installation record.5. Relevant product and installation guides.6. A set of VESDA commissioning forms.7. Other forms required by the local codes and standards.8. An LCD Programmer or a PC/Laptop with Xtralis VSC software and High Level Interface/Serial lead to

configure and commission the system. Where the PC/Laptop does not have a serial port, an RS232 toUSB converter is required.

9. Material for conducting an acceptable smoke test. Refer to Section 5.1.10. Optional: Digital manometer (if sample hole pressure is required to bemeasured).

l Wide Bore networks:Max range 3kpal Narrow Bore networks: 0.20kpa at the end of the recommended length of Microbore Tube.

Youmust be aware of the local codes and standards as applicable to the customer site.

3.2 VESDA Commissioning Form - PrerequisitesDuring the pre-commissioning stage you should complete the client and the site details in the CommissioningForms (Xtralis document number 12678).

Enter the following details:

l Customer Namel Site address (formerly called a site zone)l Installer’s Namel Installer’s Addressl Type of Installationl Your name and address

Note: Commissioning Forms are available in ASPIRE2 for supported detectors.

3.3 Once on SiteOnce you have completed all the tasks required above you are ready to go to the site and complete thecommissioning.

3.3.1 Checking Cabling and Initial PowerupBefore commencing with the commissioning, check the electrical and VESDAnet cabling for the system.Ensure that all electrical wiring is securely terminated at the relevant VESDA devices maintaining the correctpolarity. The product guides contain the details of how to correctly wire each detector. The system should beconnected to a power source supplying 24 VDC.

Caution: The VESDA system will not operate when the supply is reversed. Operating the VESDA devicewhen DC supply voltage is outside the voltage range of 18 VDC and 30 VDC may causedamage to the device.

Page 14: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA Commissioning Guide VESDA by Xtralis

8 www.xtralis.com

Check that all electrical installations meet the requirements of local electrical codes and standards.

Data communication between detectors is done through VESDAnet. The communication between devicesconnected to VESDAnet is bidirectional. The polarity must bemaintained throughout the network. It isrecommended that RS 485 (Belden 9841 - 120 ohm) twisted pair cables (or similar) be used. Youmust ensurethat the VESDAnet is appropriately wired for a closed or an open-ended loop. Refer to the VESDACommunications Guide for further information.

You should now powerup the system.

l The system takes approximately 15 seconds to power upl If the system or any detector on the VESDAnet fails to power up, re-check that all power wires are

securely connected to their respective terminals and the polarity is correctly maintainedDuring power up different things will occur on different detectors at different times:

l For all detectors, the aspirator starts to spin and suck airl VESDA VLP and VESDA VLS detectors that have the LCD Programmermodule fitted will display the

word VESDAl VESDA VLP, VESDA VLS or VESDA VLC detectors that have a display module fitted or remotely

mounted will have the following indicators lit:l Fire alarm threshold indicatorsl Smoke threshold levels on bar graph (if there is sufficient background levels)l Two digit numerical displayl Various fault Indicators if there are any faultsl System OK indicator if there are no faults

l VESDA VLF detectors:l First the Power and Fault lights appearl Next, all parts of the display will light upl Finally, just the Power light will be left on

l VESDA VLC detectors:l Will light up and cycle LEDs on and offl If a fault has been detected the FAULT LED indicator will remain litl If the system is functioning normally the OK LED indicator will remain lit

The detector(s) may show faults immediately after power up and this is normal. Reset the detector(s) tounlatch the relays and fault LEDs. The fault LEDs on any display connected to the system will light up (this isnormal).

If any of the above does not happen, refer to the product guide for that detector and check that the detectorand VESDAnet have been correctly installed.

3.3.2 Preliminary Systems CheckConduct a preliminary systems check before you begin commissioning. The check can be conducted byusing a LCD Programmer or using Xtralis VSC software. The preliminary systems check should includeconducting a VESDAnet communications check for each detector.

At power up or when changing site requirements a range of faults will be generated. This is normal. To silencethe faults you can accept the factory defaults, but youMUST remember that you still need to configure thedetector to suit the customer site. For further information see the product guide for the detector or the VESDATroubleshooting Guide.

Change the settings to suit site requirements:

l Normalizing the air flow - Normalize the air flow using the LCD Programmer or Xtralis VSC Softwarel Create smoke at the farthest sampling hole from the Detector to confirm that the detector registers the

presence of smoke within the time anticipated by ASPIRE2 but also within themaximum time accordingto local codes and standards. This test should be conducted for each pipe to ensure that there is noblockage or leakage in any of the sampling pipes

The LCD Programmer Guide and the Xtralis VSC Software Online Help explains how to carry out thefunctions. For information on smoke tests please refer to Section 5.1.

Page 15: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA by Xtralis VESDA Commissioning Guide

www.xtralis.com 9

4 System Configuration and Setting ThresholdsDifferent detectors are configured in different ways.

For VESDA VLP, VESDA VLS and VESDA VLC please use the instructions for Generic Configuration inSection 4.1. Once you have completed these steps you can configure the settings specific to each detector.

The VESDA VLF was designed with ease of configuration in mind. No specialized hardware or software toolsare required to configure this detector as it will autolearn about its environment once it is installed.

The VESDA VFT-15 is covered in Section 4.3 on page 15.

4.1 Generic Configuration (VLC, VLS, VLP)When the system is powered up for the first time, any LCD Programmer or PC Software connected toVESDAnet will register all the detectors and display modules as unconfigured. All other VESDA laser range ofproducts will appear under ancillary devices. Each laser device has a built in unique number and this numberis displayed next to the device.

For detailed explanation of the LCD Programmer Screens, and the Xtralis VSC Forms and Tabs mentioned inthe table below, please refer to the LCD Programmer Guide and the Xtralis VSC Online Help respectively.

Setting Date and Time

l For LCD Programmer: See LCD screen 144l For Xtralis VSC: See VESDAnet Form Clock Set Tab

Setting Units

l For LCD Programmer: See LCD screen 157 and select SI (for International System of Units) or US (forUS Imperial measurements)

l For Xtralis VSC: See VESDAnet Form Units TabConfiguring a Detector to a VESDA Zone

For LCD Programmer:

l See LCD screen 4 to select a detectorl See LCD screen 21, 41 & 91 to assign a VESDA zone number to the detectorl See LCD screen 22, 4, 2, 92 to assign an address name and/or location

More experienced technicians prefer to use the Drag and drop function.

For Xtralis VSC:

1. Press insert, then drag and drop the devices into their respective addresses2. Select Address name/location tab and enter a suitable name/location for the detectorAssigning a display module to a detector

For LCD Programmer: See LCD screen 110

1. Select the relevant display module.2. Give it the same address number as the assigned detector3. Enter the address name/location of the displayFor Xtralis VSC: Select Device Tree/Menu

1. Select the display on the device tree2. Select address Configuration Tab to enter the address number3. Select address name/location tab and enter respective address name/locationReference detector configuration

For LCD Programmer: See LCD screen 28, 67, 97

1. Give a reference address number or enter 255 if there is no reference detector.2. Set the dilution factor3. Set the delay time

Page 16: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA Commissioning Guide VESDA by Xtralis

10 www.xtralis.com

For Xtralis VSC: Select Devices Menu/Tree - Detector Form Reference Tab

1. Give a reference address number or enter 255 if there is no reference detector.2. Set the dilution factor3. Set the delay timeAutoLearn

For LCD Programmer: See LCD screen 20, 59, 90

l Enter the length of time you want to run AutoLearnFor Xtralis VSC: Select Devices Menu/Tree - Detector Form - Autolearn Tab

l Enter the length of time you want to run AutoLearnFilter

For LCD Programmer: See LCD screen 27, 66, 96

l Enter the filter service intervalFor Xtralis VSC: Select Devices Menu/Tree - Detector Form

l Enter the filter service intervalCommunications

For LCD Programmer: See LCD screens 39, 78, 104, 121, 130, 137, 155.

l Set the network delayl Set the preferred portl Set the health checkl Set the open-ended Loop (not available in System/All Device - Screen 155)l Set the network delayl Set the preferred communications port.

For Xtralis VSC: Select VESDAnet Form - Communications Tab

l Set network delayl Set the Health Check periodl Set the preferred communications port. Select the end of chain port if the detector is at the end of an

Open-ended Loop.General Purpose Input

For LCD Programmer: See LCD screens 40, 79, 105. Select the required GPI function from:

l Mains OKl Standby Model Remote Isolate (not available for VESDA VLC)l UseNight-time Threshold (not available for VESDA VLC)l Reset/Isolate Functionl Inverted Reset Function (not available for VESDA VLC)l Reset (not available for VESDA VLC)

For Xtralis VSC: Select Devices Menu/Tree andGPI Inputs Tab to set:

l Mains OKl Standby Model Remote Isolate (not available for VESDA VLC)l UseNight-time Threshold (not available for VESDA VLC)l Reset/Isolate Functionl Inverted Reset Function (not available for VESDA VLC)l Reset (not available for VESDA VLC)

UL Version

For LCD Programmer: See LCD screens 40, 79, 105, 131, 157. The UL Versionmay be selected or de-selected from theMiscellaneous Screen.

Page 17: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA by Xtralis VESDA Commissioning Guide

www.xtralis.com 11

4.2 Detector Specific Configuration Steps (VLC, VLS, VLP)Refer to the LCD Programmer Guide for Screen Numbers and details. Refer to the Xtralis VSC softwareOnline Help for details on Configuration forms and tabs.

You have now configured the generic components of the detector. You should now proceed to configure thesettings that are specific to the detector:

To complete the configuration of a VESDA VLC, refer to the VESDA VLC commissioning form.

To complete the configuration of a VESDA VLS, refer to the VESDA VLS commissioning form.

To complete the configuration of a VESDA VLP use the following steps:

4.2.1 VESDA VLP ConfigurationBefore performing these steps you should complete the Generic Configuration steps on page 9.

Setting Air Flows

For LCD Programmer: See LCD screen 23 & 62.

1. Select Air Flow and then select flow threshold, flow control, OR normalizing air flow2. See LCD screen 24 & 63. Flow Threshold - Set airflow values to suit the customer site or accept the

defaults3. Select the pipes in use4. Set the delay time for the air flow threshold5. See LCD screen 25 & 64. Flow Control - Select the pipe in use and aspirator speed6. See LCD screen 26 & 65. Normalize the airflowFor Xtralis VSC: Select devices menu/tree -detector form

1. Select air flow tab to set airflow values to suit the customer site or accept the defaults.2. Set the delay time for the air flow threshold3. Flow Control - Select the pipe in use4. Aspirator - set the aspirator speed5. Normalize the airflow by highlighting the detector, then click Device and select Normalize AirflowSetting Smoke Thresholds

For LCD Programmer: See LCD screens 12-19

1. Select screen 12: Select the smoke threshold and set: Day Thresholds, Night Thresholds, Alarm Delays,Change-Over Times, Weekend, Holidays, and Smoke Change

2. Select screen 13 and set the Day Thresholds for Fire 2, Fire 1, Action and Alert3. Select screen 14 and set new Night Thresholds for Fire 2, Fire 1, Action and Alert4. Select screen 15 and set the time (in seconds) that should elapse once a threshold is crossed and the

Alarm is generated for Fire 2, Fire 1, Action and Alert5. Select screen 16 and set the Day Period and Night Period6. Select screen 17 and check the days considered as Weekend7. Select screen 18 and enter the start/end dates for holiday periods8. Select screen 19 and set the change in obscuration rate. Also set theminimum time period for this change

to be recorded in the event Log. The simultaneous/cumulative and instantaneous Fire thresholds are setin the delays screen and NOT in the Smoke Change Screen.

For Xtralis VSC: Devices Menu/Tree - Detector Form

1. Select the Smoke Threshold Tab to set new values for Day Thresholds, Night Thresholds, Change-OverTimes, and Smoke Change.

2. Select theWorkdays Tab and set the working days of the week. Also enter the start/end dates for holidayperiods.

Page 18: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA Commissioning Guide VESDA by Xtralis

12 www.xtralis.com

Relay Setup

For LCD Programmer: See LCD screens 32-35

1. Select screen 33 and set the relays to Energized or De-energized. Relay 3 is energized and cannot bechanged.

2. Select screen 34 and set the relay conditions. The isolate function is set to Unlatch and cannot be altered.3. Select screen 35 and set the relay assignments. Relays 3 and 6 are permanently fixed as Urgent Fault

and Fire 1 respectively. All relays can be assignedmultiple functions.For Xtralis VSC: Devices Menu/Tree - Detector Form

1. Use the Relays Tab to set the relay conditions to energize or de-energize when an event occurs. Relay 3is energized and cannot be changed.

2. Use the Relay Assignment Tab to assign relay functions and to latch or unlatch relays for:

l Isolatel Urgent faultl Minor Faultl Alertl Actionl Fire 1l Fire 2

The Isolate condition is permanently unlatched and cannot be changed. Urgent Fault and Fire 1 arepermanently assigned to relays 3 and 6 and these cannot be changed, however additional assignments maybe set for all relays.

4.2.2 VESDA VLS ConfigurationBefore performing these steps you should complete the Generic Configuration steps on page 9.

Setting Air Flows

For LCD Programmer: See LCD screen 23 & 62

1. Select Air Flow and then select flow threshold, flow control, OR normalizing air flow2. See LCD screen 24 & 63. Flow Threshold - Set airflow values to suit the customer site or accept the

defaults.3. Set the delay time for the air flow threshold4. See LCD screen 25 & 64. Flow Control - Select the pipe in use and aspirator speed5. See LCD screen 26 & 65. Normalize the airflowFor Xtralis VSC: Select devices menu/tree -detector form

1. Select air flow tab to set airflow values to suit the customer site or accept the defaults.2. Set the delay time for the air flow threshold3. Flow Control - Select the pipe in use and set the aspirator speed4. Normalize the airflow by selecting the detector, drop down device. Next, select either Normalize or Drop

down device, then select Normalize AirflowSetting Smoke Thresholds

For LCD Programmer: See LCD screens 48-56

1. Select screen 48: Select the smoke threshold and set: Day Thresholds, Night Thresholds, Change-OverTimes, Weekend, Holidays, and Scanner

2. Select screen 49 and set the Day Thresholds for Fire 2, Fire 1, Action and Alert3. Select screen 50 and set new Night Thresholds for Fire 2, Fire 1, Action and Alert4. Select screen 51 and set the Day Period and Night Period5. Select screen 52 and check the days considered as Weekend6. Select screen 53 and enter the start/end dates for holiday periods7. Select screen 55 and enter the Thresholds, Day Thresholds and Night Thresholds that are the level, as

defined by the adaptive scan threshold, that the unit will start to scan.8. Select screen 56 and set the Sector factor.

Page 19: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA by Xtralis VESDA Commissioning Guide

www.xtralis.com 13

For Xtralis VSC: Devices Menu/Tree - Detector Form

1. Select the Smoke Threshold Tab to set new values for Day Thresholds, Night Thresholds, Change-OverTimes, and Smoke Change.

2. Select theWorkdays Tab

l Set the working days of the weekl Set the start/end dates for holiday periods.

Assigning ancillary devices to a detector

An ancillary device, normally a Programmer, can only be allocated to a VESDA VLS detector. Any otherancillary devices must remain in Address 0.

For LCD Programmer: See LCD screen 110.

1. Select the relevant ancillary device.2. Give it the same address number as the assigned detector3. Enter the address name/location of the displayFor Xtralis VSC: Select Device Tree/Menu

1. Select the Ancillary device on the device tree2. Select address Configuration Tab to enter the address number3. Select address name/location tab and enter respective address name/locationYoumay find it easier to drag and drop instead.

Relay Setup

Latching is when the relay stays in it changed state after the condition has cleared.

For LCD Programmer: See LCD screens 71-74

1. Select screen 72 and set the relays to Energized or De-energized2. Select screen 73 and set the relay conditions. The isolate function is non latching and cannot be altered.3. Select screen 74 and set the relay assignments. Relays 3 and 6 are permanently fixed as Urgent Fault

and Fire 1 respectively. All relays can be assignedmultiple functions.For Xtralis VSC: Devices Menu/Tree - Detector Form

1. Use the Relays Tab to set the relay conditions to energize or de-energize when an event occurs. Relay 3is energized and cannot be changed

2. Use the Relay Assignment Tab to assign relay functions and to latch or unlatch relays for:

l Assign Isolate andMinor Fault functions to relaysl Latch or Unlatch relays when Urgent or Minor Faults occurl Urgent Faults are permanent assigned to Relay 3 and cannot be changed. Isolate function

is set to unlatch and cannot be changed.

3. Select the Scanner Relay Tab to assign relays and set them as Latched or Unlatched for:

l First Alarm Sector 1l First Alarm Sector 2l First Alarm Sector 3l First Alarm Sector 4

4. Select Tabs Sector 1, 2 relay assignment, and Sector 3, 4 relay assignment to assign Alarm levels torelays for Sectors 1 through 4. These Relays may be set to latch or unlatch.

Page 20: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA Commissioning Guide VESDA by Xtralis

14 www.xtralis.com

4.2.3 VESDA VLC ConfigurationBefore performing these steps you should complete the Generic Configuration steps on page 9.

When the system is powered up for the first time, any LCD Programmer or Xtralis VSC software connected toVESDAnet will register all the detectors and display modules as unconfigured. All other VESDA products willappear under ancillary devices. Each laser device has a built in unique number and this number is displayednext to the device.

VLC Relay Only (RO) detectors can only be configured using Xtralis VSC. VN models can be configuredusing the LCD programmer or Xtralis VSC instructions.

For detailed explanation of the LCD Programmer Screens, and the Xtralis VSC forms and tabs mentioned inthe table below, please refer to the LCD Programmer Guide and the Xtralis VSC Online Help respectively.

Setting Air Flows

For LCD Programmer:

1. See LCD screen 94: Flow Threshold - Set airflow values to suit the customer site or accept the defaults.Set the delay time for the air flow threshold

2. See LCD screen 95: Normalize the airflowFor Xtralis VSC: Select devices menu/tree-detector form

1. Select air flow tab to set airflow values to suit the customer site or accept the defaults.2. Set the delay time for the air flow threshold3. Normalize the airflow by highlighting the detector, then click Device and select Normalize AirflowSetting Smoke Thresholds

For LCD Programmer: See LCD screens 87-89

1. Select screen 87: Select the Smoke Threshold and then select Smoke Thresholds, Alarm delays, ORSmoke Change.

2. Select screen 88: Set the thresholds for Alert, Pre-Alarm, Fire and Alert Overlay3. Select screen 89: Set the delays for Alert, Pre-Alarm and Fire. The simultaneous/cumulative delay times

and the instantaneous fire option can be enabled or disabled through this screen.For Xtralis VSC: Select the Smoke Thresholds Tab

1. Enter thresholds for Pre-Alarm and Fire2. Enter delay in seconds for Pre-Alarm and Fire3. Select Instant Fire or Cumulative delays4. Enter the obscuration rate for significant Change5. Select the Units Tab to enable Overlay Alert

Page 21: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA by Xtralis VESDA Commissioning Guide

www.xtralis.com 15

4.3 VESDA VFT-15 Detector ConfigurationThis section identifies some key functions that the user may need to configure using the display panel.

Main Menu Modes

To enter one of theMainMenuModes follow these steps: 

1. Press MENU2. Use FunctionUP & DOWN buttons (SCAN and ISOLATE buttons) to reach requiredmainmenu item3. Press ENTER (SOUNDER SILENCE button)4. Use ValueUP & DOWN buttons (RESET and ACCEPT buttons) to enter the appropriate Access Code5. Press ENTERNotes:

l Access Code Entry may be aborted by pressing theMENU button.l All of the following settings can be entered using the Xtralis VSC configuration software and a PC. This

can reduce the time taken to enter certain values and parameters.To obtain this software contact Xtralis or visit www.xtralis.com.

l The cover must be removed to gain access to the RS232 port at the side of the detector. It must bereplaced for aminimum of 60minutes prior to flow normalization.

Access Codes

Access to somemodes in theMainMenu and other configuration and control functions require the user toenter an Access Code. There are several levels of access:

1. Operator2. Level 13. Level 24. Level 3Access Code Levels are downwards applicable - for example if a User enters the Level 2 Code, they haveaccess at the Operator Level and Level 1. TheOperator Access Code is changeable as a parameter inConfigurationMode, which requires Level 1 Access. The default Access Codes are shown below.

Table 4-1: VESDA VFT-15 Detector Access Codes 

Access Level Access CodeOperator 0 = not required

Level 1 260

Level 2 693

Level 3 Factory UseOnly

How to Enter an Access Code

When entering an Access Code, the alternative function LEDs above the ACCEPT and RESET buttons willbe lit, enabling these buttons to be used as UP and DOWN buttons to enter a 3-digit number.

If the UP or DOWN buttons are continually pressed, the 'units' digit on the Status Display will be activated,then the 'tens' digit, then the 'hundreds' digit. If the button is released, the flashing digit (units, tens orhundreds) is the one that will change with further use of the UP and DOWN buttons. When the hundreds digitis correct, wait about five seconds for the flashing digit to move to the tens digit, then set the tens to therequired value. Repeat for the units digit.

4.3.1 VESDA VFT-15 Detector Programmable FunctionsOnly some key functions are listed in this section. For more detail, please refer to the product guide.

Setting Units

Minimum Access Code Required: Level 2

Page 22: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA Commissioning Guide VESDA by Xtralis

16 www.xtralis.com

Parameters to change the display resolution for obscuration, language or imperial/metric units are found in theSETUP menu option.

Setting Time and Date

Minimum Access Code Required: Level 1

The time and date settings can be configured through the TIME DATE menu option. The user will be able tosequentially change the date, month and year, then the seconds, minutes and hours.

Setting IP Address and Mask

Minimum Access Code Required: Level 1

To set the IP address andmask, navigate to theWEB menu option. Once logged in at the Level 1 access, theuser will be able to set all the IP configuration details for the detector.

Setting the Modbus Address

Minimum Access Code Required: Level 1

TheModbus address is set through the CONFIGURE menu option using the ADDRESS parameter. Pleaseensure that this address is unique for the connected network.

Setting Air Flows

Minimum Access Code Required: Level 1

All parameters relating to air flow is set through the CONFIGURE menu option. Some of the key parametersare:

l FLOWDEL - Flow Fault Delay (1 to 60 s)l FLOWHI / FLOWLO - High and low air flow limits for declaring a Flow Fault (0 to 200%)

Setting Smoke Thresholds

Minimum Access Code Required: Level 1

Day and night smoke thresholds, trace and delay settings for each sector can be set through the SECTORSALMS menu option. Day start and Night start times are accessed through the CONFIGURE menu option viathe NIGHSTART and NIGHSTOP parameters.

Setting GPI Function

Minimum Access Code Required: Level 2

The 'remote reset' input can be configured for a reset function or an isolate function. Please refer to the RES-ISOL parameter in the SETUP menu option to configure this GPI.

Setting Up I/O Modules

The type of I/Omodule included in the detector must be configured in the SETUP menu option, which has aminimum access of Level 2.

Other options for setting up particular parameters for a I/Omodulemay be achieved through the CONFIGUREmenu option. Theminimum access requirement is Level 1. More detail for specific modules may be found inthe VESDA VFT-15 Product Guide.

4.4 VESDA VLF ConfigurationThe VESDA VLF was designed with ease of configuration in mind. No specialized hardware or software toolsare required to configure this detector as it will autolearn about its environment once it is installed.

4.5 Documenting Configuration and ThresholdsThe relevant sections of the commissioning form should be completed when the thresholds are set and thesystem is being configured. If you are configuring the system using the Xtralis VSC software you can print outmost of the information required in the commissioning forms.

Attach a copy of the ASPIRE2 Installation Data Pack (IDP). Enter the details of any ancillary devices thathave been assigned a VESDA Zone.

Page 23: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA by Xtralis VESDA Commissioning Guide

www.xtralis.com 17

We recommend that ASPIRE2 be used to evaluate the efficiency of the pipe network and its calculations arecompared the actual smoke test results. Significant differences between the ASPIRE2 estimates and the testresults should be investigated to find why the differences have occurred.

Page 24: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA Commissioning Guide VESDA by Xtralis

18 www.xtralis.com

This page is intentionally left blank.

Page 25: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA by Xtralis VESDA Commissioning Guide

www.xtralis.com 19

5 System Integrity TestVESDA systems can be tested in a number of different ways. Most sites will require different types of testingfor different customer environments. Before conducting smoke tests youmust check to see if the local codesand standards specify which type of smoke test is to be performed. Local codes and standards may alsorequire changes to the general instructions below, where local codes and standards are different to theVESDA suggestions, ALWAYS follow the local codes and standards.

Performance testing is done during commissioning andmay be required during service, but is not essential.We highly recommend pipe integrity testing be performed each year.

Note: Some tests create a large amount of smoke, so you should take the necessary precautions before youbegin testing.

5.1 Performance-based Smoke TestingA smoke test is necessary to prove the integrity of the pipe network and tomeasure the response time. Thetype of smoke test required will depend upon the site and the application:

l Warehouses and open areas can use either a smoke pellet test, a polyurethanemat test, or possibly awooden block test. Please check with the local codes and standards to find themost appropriate type oftest for the environment.

l Very sensitive sites can use the electrical overload (PVC coated wire burn test), or the smouldering testcoil test. (UK customers can refer to BS 6266, BFPSA Code of Practice Appendix A for systemperformance test methods).

We recommend that at least two tests are conducted. Youmust allow the environment to return to the normalconditions before beginning the second test.

Record the date and the type of smoke test used on the commissioning or testing forms. Please re-read thedetector manuals if you are unsure of how to interpret smoke levels, Alert, Alarm or Fire1.

At aminimum, testing requires that you conduct pipe integrity smoke testing.

5.1.1 Testing and Stratification ProblemsIn areas with a high roof you can expect the air temperature near the roof to be warmer than the air temperatureat ground level. This can cause the stratification of smoke. Stratification occurs when warm smoke rises untilit reaches a layer of air with the same temperature and then stops rising. This may cause problems as thesmokemay not reach sample points which aremounted on the roof.

As the height of the roof increase you will need a larger distance between the roof and the sampling point tocontinue correctly sampling the air. Heights up to 3m (9 ft) can use standard 25mm (1 in.) standoffs.

Roof Height (M) 1 2 3 4 5 6 7 8 9

Distance from roof (mm) 30 30 30 100 200 300 400 500 600

For testing purposes you can use a 5.8 kW gas burner or electric heater to add heat to the smoke tomake sureit will reach the roof.

Page 26: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA Commissioning Guide VESDA by Xtralis

20 www.xtralis.com

5.1.2 Pipe Integrity Smoke TestingThis test should be used to test pipe integrity in any typical customer site. This method is suitable for thetesting of standard sensitivity fire detection systems. You will need a smoke source, a stopwatch, and a fireextinguisher.

It is easy to see an increase of smoke on detectors that have a display module fitted. VESDA VLC detectorsdo not have a display and will require extra smoke as the detector will need to reach pre-alarm stage beforethey will indicate an increase of smoke.

1. Ensure that the local fire panel is isolated from the external fire reporting equipment and that anyautomatic extinguishing or suppressant systems are also isolated.

2. Introduce smoke directly into the furthest sample hole in the pipe run, and start the timer.3. Stop the timer when the detector registers the smoke and record the results.4. Compare the time expected by ASPIRE2with the actual recorded time. If the actual recorded time is

20% or greater than the expected time, check the pipe for breaks.

5.1.3 Smoke Pellet TestingThis method is suitable for the testing of high and enhanced sensitivity environments. Smoke is produced bylighting a number of small smoke pellets. You will need smoke pellets, a tray, and amethod to time the test. Ifyou are testing in an area with a high roof youmay also require a radiated heater to fix stratification problems.Refer to Section 5.1.1 for further information.

1. Ensure that the local fire panel is isolated from the external fire reporting equipment and that anyautomatic extinguishing or suppressant systems are similarly isolated.

2. Cover ametal tray with kitchen foil.3. Set the heater close to the tray. This is required tomake the smoke rise.4. Put the smoke pellets on ametal tray. The number of pellets to use is determined by the system designer.5. Put something under the tray to protect the floor from damage.6. If you are testing a high roof area turn the heater on.7. Light the pellets with amatch, and start the timer.8. Acceptable detector response time is specified in local codes and standards or as per the system design.

Figure 5-1: Smoke Pellet Testing

For further information on Smoke Pellet Testing, refer to BFPSA or FIA CoP standards.

Page 27: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA by Xtralis VESDA Commissioning Guide

www.xtralis.com 21

5.1.4 Polyurethane Mat Smoke TestingThis method is suitable for the testing of standard sensitivity fire detection systems. A controlled fire isproduced by lighting of flexible polyurethane foammat. This test is suitable for testing smoke detection inopen areas such as warehouses and atriums.

Warning: The burning of polyurethane foam generates toxic gases. We recommend you use appropriateprotective equipment.

1. Ensure that the local fire panel is isolated from the external fire reporting equipment and that anyautomatic extinguishing or suppressant systems are similarly isolated.

2. Cover ametal tray with kitchen foil.3. Put themat into the tray. Multiple mats may be stacked as required by the system designer.4. Put something under the tray to protect the floor from damage.5. Ignite a corner of themat with amatch, and start a stop watch.6. Acceptable detector response time is specified in local codes and standards or as per the system design.

LegendA 500mm (20 in)

B Kitchen foil in tray

C 20mm (0.874 in)

Figure 5-2: PolyurethaneMat Smoke Test

5.1.5 Wire Burn Smoke TestingThis test is performed by using a transformer to overload the power running through twometers of PVC-coated wire. To simulate the early stages of a fire, a length of wire is electrically overloaded so that smoke orvapors are driven off. This method is suitable for the testing of high sensitivity fire detection systems. Thistest may also be undertaken in underfloor spaces or ceiling voids.

Note: The wire used in this testingmust be 1m in length, of 10/0.1 mm strands insulated with PVC to a radialthickness of 0.3mm, the cross sectional area of the conductor being 0.078mm².

Xtralis has developed a test kit to assist field testing of wire burns. For more information please contact yournearest Xtralis office and ask for information on VTT-10000.

These instructions are written assuming that you are using a VTT-10000 test kit.

Warning: This test will burn the PVC coating off the wire. Do not hold the wire during testing. Do notbreath in the smoke as it is harmful to your health. We recommend you remotely turn thetransformer on and use appropriate protective equipment.

Page 28: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA Commissioning Guide VESDA by Xtralis

22 www.xtralis.com

1. Ensure that the local fire panel is isolated from the external fire reporting equipment and that anyautomatic extinguishing or suppressant systems are also isolated.

2. With the power turned off, connect each end of a 1meter (3 ft.) length of the specified wire to the VTT-10000.

3. Ensure that the wire is laid on an insulating board to avoid damage to the floor.4. Check that there are no kinks or crossovers in the wire.5. Connect power to the VTT-10000 and turn the power on for 180 seconds.At this point, there is 6 VAC applied across the test wire, the switch will illuminate and the green indicator onthe timer will begin to flash. The test wire will become hot and a small quantity of smoke will be generated.

6. Turn the unit off after the timed burn period is complete.

Figure 5-3: Wire Burn Test Kit VTT-10000

7. Record the response time of the detector.8. For multiple tests, allow 5minutes (300 seconds) between tests so all smoke can dissipate.

Caution: The test wires will become very hot. Do not touch.

Enter the following results on the commissioning form:

l Transport Time - Introduce smoke at the furthest sampling hole from the detector. The time taken (inseconds) for the smoke to travel to the detector is the transport time. If there is a wide variation betweenthe ASPIRE2 predictions and the test results, the pipe network should be checked for leaks, blockageand to see that the installed pipe network matches themodel used in ASPIRE2.

l Initial Response - This is the total of the time taken for the smoke to travel from the source to thesampling point and the detector first registering the presence of smoke (excluding any alarm delay timesthat may have been set).

l Alert Response - The time taken for initial response and the detector to generate an Alert Alarml Action/Pre-Alarm - The time taken for alert and the detector to generate an Action/Pre-Alarm status

(excluding any delay times)l Fire 1/Fire Response - The time taken for alert and the detector to generate an Fire 1/Fire Response

status (excluding any delay times)l Fire 2 Response - The time taken for alert and the detector to generate an Fire 2/Fire Response status

(excluding any delay times)l Peak Smoke Response - This is the time taken for the detector to record the peak level of smoke

(excluding any delay times). The numerical display of the display module or the LCD Programmer willdisplay the smoke levels. This information can also be extracted from the event log.

Acceptable response times are determined by site requirements, subject to local codes and standards. In theevent the test response times do not meet the acceptable standard the commissioning form should be signedas NOT ACCEPTABLE and recommendations for further work should be recorded on the commissioningform.

Page 29: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA by Xtralis VESDA Commissioning Guide

www.xtralis.com 23

5.2 Testing Relay FunctionA relay on/off test can be performed using a LCD Programmer or Xtralis VSC Software. Refer to the LCDProgrammer Guide and the Xtralis VSC software Online Help for information on testing relays. Anmulti-meteris used to check the relay has changed state. Pressing themode/test button on the display for more than twoseconds will test all the LEDs. If the relays are connected to non-VESDA equipment (such as a fire panel) youneed to check that these tests register on the equipment.

5.3 Testing DevicesDetectors

The detectors can be tested using a diagnostic test from LCD Programmer or Xtralis VSC software. In theLCD programmer select the relevant device, then the diagnostic option. In Xtralis VSC this option is availableby selecting the relevant device then the required test in the Devicemenu. Tests that can be performed usingthis option are:

l Smoke alarm testl Fault testl Airflow fault testl Sector test (VESDA VLS Detectors)

5.4 Documenting Test ResultsThe tests results should be recorded on a copy of the VESDA commissioning forms. Once the forms havebeen completed and signed, they should be forwarded along with relevant attachments to all thosementionedin Chapter 6.

Copies of the commissioning forms are available in the document library at www.xtralis.com (Xtralisdocument number 12678).

Page 30: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA Commissioning Guide VESDA by Xtralis

24 www.xtralis.com

This page is intentionally left blank.

Page 31: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA by Xtralis VESDA Commissioning Guide

www.xtralis.com 25

6 Hand OverYou and the customer should be satisfied that all aspects of commissioning the system have been addressedand thesemeet the required standards. The systemmust be ready for day to day operation prior to hand over.To hand over the system to the client, you should:

l Ensure that the VESDA commissioning forms are complete and all relevant sections have been filled inl If you have used Xtralis VSC select the Device, Address, or VESDAnet then select File | Print to print

out a copy of configuration details and include a copy with the hand over documents.l Obtain the relevant signaturesl Ensure that relevant attachments have been included with the commissioning forml Make copies of the completed commissioning forms and attachments and forward these to:

l Appropriate Xtralis Sales Officel Installing contractorl Designer of the systeml End user of the system

Page 32: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA Commissioning Guide VESDA by Xtralis

26 www.xtralis.com

This page is intentionally left blank.

Page 33: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA by Xtralis VESDA Commissioning Guide

www.xtralis.com 27

Index

A

Air flow normalize 8

Alert Response Test 22

Assigning Ancillary Devices 13

C

Cabling and Initial Powerup 7

Commissioning 5, 19

HandOver 25

Prerequisites 7

Smoke Test 19

System Test 19

Commissioning Form 16

Communications check 8

Configuration and Thresholds 16

Configuring Detector 9

D

Device Testing 23

Devices Assigning 13

Display Module Assigning 9

H

HandOver 25

I

Initial Response Test 22

Integrity Test 19

N

Normalizing the Air Flow 8

P

Peak Smoke Response Test 22

Power UpCommissioning 7

R

Relay Setup 12

Relay Testing 23

S

Setting Date and Time 9

Setting Thresholds 9

Setting Units 9

Smoke Test 19

System Configuration 9

System Test 19

T

Test the System 19

Testing Devices 23

Testing Relay Function 23

Threshold Settings 9

Transport Time Test 22

V

VESDAnet Communications Check 8

Page 34: VESDA Commissioning Guide - janusfiresystems.com3 Pre-Commissioning 7 3.1 BeforegoingtotheSite 7 3.2 VESDACommissioningForm-Prerequisites 7 ... Forms(Xtralisdocumentnumber12678). Enterthefollowingdetails:

VESDA Commissioning Guide VESDA by Xtralis

28 www.xtralis.com

This page is intentionally left blank.