Utilizing High-set Load Shedding Schemes (UHSLSS)
to Replace Responsive Reserve Obligation
Juan S. Santos(512) 248-3139 • [email protected]
Senior Consultant, System PlanningTechnical Operations
Study Scope Review
![Page 2: Utilizing High-set Load Shedding Schemes (UHSLSS) to Replace Responsive Reserve Obligation Juan S. Santos (512) 248-3139 jsantos@ercot.comjsantos@ercot.com](https://reader036.vdocuments.mx/reader036/viewer/2022083005/56649f295503460f94c42da9/html5/thumbnails/2.jpg)
Topics From the Study Scope
• Objective of study
• Method Of Analysis
• Study Approach by tasks
• Report and Criteria for acceptance
• Estimated Cost and Timeline
![Page 3: Utilizing High-set Load Shedding Schemes (UHSLSS) to Replace Responsive Reserve Obligation Juan S. Santos (512) 248-3139 jsantos@ercot.comjsantos@ercot.com](https://reader036.vdocuments.mx/reader036/viewer/2022083005/56649f295503460f94c42da9/html5/thumbnails/3.jpg)
Objective of Study
• The current ERCOT rule allows for 25% of the ERCOT 2300 MW Responsive Reserve
Obligation stability classification, or 575 MW, of interruptible load tripped at 59.6 Hz to be substituted for responsive reserve.
• The objective of this study is to investigate how much of this limit can be increased without significant negative impacts on the ERCOT system.
![Page 4: Utilizing High-set Load Shedding Schemes (UHSLSS) to Replace Responsive Reserve Obligation Juan S. Santos (512) 248-3139 jsantos@ercot.comjsantos@ercot.com](https://reader036.vdocuments.mx/reader036/viewer/2022083005/56649f295503460f94c42da9/html5/thumbnails/4.jpg)
Method Of Analysis
• This study will compare the effects of replacing increasing amounts of responsive spinning reserve with hi-set interruptible loads set to trip by automatic relays with a time delay of not more than 20 cycles.
• Study will monitor, frequency, bus voltage, rotor angles, speed, megawatts, mega-vars, terminal voltage, and exciter field voltage.
• Study will also scan for any out of step conditions.
• A solved load-flow case will be saved and examined for abnormal network conditions at the end of the dynamic simulation period.
![Page 5: Utilizing High-set Load Shedding Schemes (UHSLSS) to Replace Responsive Reserve Obligation Juan S. Santos (512) 248-3139 jsantos@ercot.comjsantos@ercot.com](https://reader036.vdocuments.mx/reader036/viewer/2022083005/56649f295503460f94c42da9/html5/thumbnails/5.jpg)
Task 1 – Assembly And Sanity Check Of Data
• Data of the base models will be provided by TSP’s •2002 spring and summer cases
• Data in PTI PSS/E format will be assembled by ERCOT staff – flat start • Data collection and sanity checking
PowerflowDynamic initialization
Any data questions or problems identified will be brought to the attention of DWG members and resolved with recommended modifications approved by DWG
• Data does not include boiler models (simulations limited to 15 sec)• Loads to used as is without scaling them to match the actual ERCOT loads
on any given day.
![Page 6: Utilizing High-set Load Shedding Schemes (UHSLSS) to Replace Responsive Reserve Obligation Juan S. Santos (512) 248-3139 jsantos@ercot.comjsantos@ercot.com](https://reader036.vdocuments.mx/reader036/viewer/2022083005/56649f295503460f94c42da9/html5/thumbnails/6.jpg)
Task 2 – Development Of Scenarios And Criteria
Four scenarios will be assembled representing increasing levels of HSLSS High Set Load Shedding Schemes
• Base Case – 100% of spinning reserves as “real” generation.
• Case 2 – Use High-Set Load Shedding Schemes (HSLSS) to replace 50% of the Spinning Reserve.
• Case 3 – Use High-Set Load Shedding Schemes (HSLSS) to replace 75% of Spinning Reserve.
• Case 4 – Use High-Set Load Shedding Schemes (HSLSS) to replace 100% of the Spinning Reserve.
![Page 7: Utilizing High-set Load Shedding Schemes (UHSLSS) to Replace Responsive Reserve Obligation Juan S. Santos (512) 248-3139 jsantos@ercot.comjsantos@ercot.com](https://reader036.vdocuments.mx/reader036/viewer/2022083005/56649f295503460f94c42da9/html5/thumbnails/7.jpg)
Task 3 – Add/Modify High Set Load Relays
• Placement of Replacement Reserve Service (RRS) will be set at several different levels:
1. Trip level to be set at 59.7 Hz for 20 cycles.2. Trip level to be set at 59.8 Hz for 20 cycles.3. Trip level to be set at 59.9 Hz for 20 cycles.
• Load RRS to be selected using a non-bias approach based on size and location.
![Page 8: Utilizing High-set Load Shedding Schemes (UHSLSS) to Replace Responsive Reserve Obligation Juan S. Santos (512) 248-3139 jsantos@ercot.comjsantos@ercot.com](https://reader036.vdocuments.mx/reader036/viewer/2022083005/56649f295503460f94c42da9/html5/thumbnails/8.jpg)
Task 4 – Run Full Analysis for Each Scenarios
Case 1 - 25%
Case 2 -50%
Case 3 -75%
Case 4 -100%
Level a:
59.7A1 A2 A3 A4
Level b:
59.8B1 B2 B3 B4
Level c:
59.9C1 C2 C3 C4
![Page 9: Utilizing High-set Load Shedding Schemes (UHSLSS) to Replace Responsive Reserve Obligation Juan S. Santos (512) 248-3139 jsantos@ercot.comjsantos@ercot.com](https://reader036.vdocuments.mx/reader036/viewer/2022083005/56649f295503460f94c42da9/html5/thumbnails/9.jpg)
Report and Criteria
• Working Group members will write report and recommendations
• If any scenario studied fails to meet all of the following criteria,it will be considered unacceptable.
1. No abnormal system conditions leading to cascading outages and system collapse.
2. No firm load will be shed. To ensure this the minimum allowable frequency in the study will be shed for that stage.
3. Maximum frequency deviation based on ANSI/IEEE Standard C37.106-1987, Guide for Abnormal Frequency Protection for Power Generating Plants.
![Page 10: Utilizing High-set Load Shedding Schemes (UHSLSS) to Replace Responsive Reserve Obligation Juan S. Santos (512) 248-3139 jsantos@ercot.comjsantos@ercot.com](https://reader036.vdocuments.mx/reader036/viewer/2022083005/56649f295503460f94c42da9/html5/thumbnails/10.jpg)
Estimated Cost and Timeline
•This study will require each working group member’s time. Time = Money•Will require the formation of working group members who will have to commit a large amount of time.
•4 people 12 days or 384 man – hours •Work group will meet (min.) four times for three days •Report writing will require an additional 160 man-hours