tutor site clearance

19
Building Methods & Construction Technology Site Clearance

Upload: luke-darcy

Post on 09-Apr-2017

69 views

Category:

Education


3 download

TRANSCRIPT

Page 1: Tutor site clearance

Building Methods & Construction Technology

Site Clearance

Page 2: Tutor site clearance

Groundworks

Typical groundwork activities include:

• Site clearance.• Site preparation.• Excavation of foundation

trenches.• Groundwater control.

Page 3: Tutor site clearance

Site Clearance

It is normal practice for any above ground clearance requirements, such as removal of trees, bushes, walls, slabs, buildings etc to be shown on a site plan. This plan may show the position of services, both above and below ground, allowing these to be cleared if necessary or avoided for safety if to be left alone.

Page 4: Tutor site clearance

Site ClearanceConstruction sites vary a great deal, and clearance procedures will, of course, be different on each one.

A Greenfield site out of town may only require soil removal.

Page 5: Tutor site clearance

Site Clearance

Whereas a Brownfield site, having been previously developed, may need extensive demolition and clearance of concrete slabs etc before any excavation can commence.

Page 6: Tutor site clearance

Contaminated Ground

Due to the increase in use of brownfield sites, and regulations imposed by the government, many sites have to be decontaminated before structures can be built on them. This often involves the contaminated soil being totally removed from site and being replaced by clean soil when the site is landscaped.

Page 7: Tutor site clearance

Protection of TreesTrees may have a ‘preservation order’ placed on them by the local authority. This protects the tree from displacement or removal. The removal of other trees generally is subject to agreement with the planning authority before the work on site commences (usually at planning stage).

Page 8: Tutor site clearance

Removal of WasteWaste material can be removed by lorry or skip to a licensed landfill site, or if the waste is inert, such as brick rubble or subsoil, it can be used as ‘fill’ in certain earthworks. This will generally reduce the cost of removal of the waste to the contractor.

Burning of rubbish on building sites is not normally allowed.

Page 9: Tutor site clearance

Removal of WasteOn brownfield sites, where masonry and concrete demolition is required, it is often cost-effective for the material to be crushed and used for hardcore in the contract (if acceptable to the architect and building control).

Page 10: Tutor site clearance

Removal of Vegetable SoilThe Building Regulations Part C states that the ground to be built upon must be reasonably clear of vegetable soil and matter.

This photograph shows the organic vegetable or topsoil layer on top of the lighter coloured subsoil below.

Page 11: Tutor site clearance

Reduced Level ExcavationsGrading and levelling is carried out by the use of any of the following methods:

• Cut.• Cut and fill.• Fill.

‘Cut’ is the process of removal of high ground to produce a level work area. This method results in a solid and compact base.

Page 12: Tutor site clearance

‘Cut and fill’ techniques are used to provide a level base for construction on sloping sites This method requires compaction of filled areas of soil, in layers. The soil for filling may be ‘won’ from the cut areas. The cut area will be already sufficiently compact.

Cut Fill

Natural slope of the land.

Page 13: Tutor site clearance

Trench ExcavationFactors that influence the choice of methods for excavation include:

• Volume of subsoil to be excavated.• Nature of the site.• Type of soil (e.g. stone requires

mechanical excavation).• Time constraints (how much time

available for excavation).• Safety of operatives

Page 14: Tutor site clearance

Trench ExcavationManual or Use of Plant?

Page 15: Tutor site clearance

Or would this be better?

Page 16: Tutor site clearance

Sometimes this may be required.

Page 17: Tutor site clearance

All services below ground should be protected and identified by the

following methods:

Service providers should also have plans and information on where the location of pipes and cables

are before you start digging!

Page 18: Tutor site clearance

Groundwater ControlWater can be classified as either:

• Surface water. • Ground water. • Subsoil water.

Rain, snow etc on the surface

Water table

Upper levelof waterheld in thesubsoil

Surface water –run off from thesurface

Subsoil water –water held in theground belowthe water table

Ground water –water held in thesubsoil

Page 19: Tutor site clearance

Problems Caused by Subsoil Water

The contractor must, therefore, resist the ingress of water into excavations as much as possible. This is typically done by employing pumps.

A vacuum piston pump being used to reduce ground water from an excavation