tractbele report version 7 - ofgem...tractebel uk concludes that the lack of wareness of the a...

48
This document is the property of Tractebel Engineering Limited. Any duplication or transmission to third parties is forbidden without prior written approval TRACTEBEL Engineering Limited 1st Floor Chertsey House, 61 Chertsey Road, Woking, Surrey GU21 5BN - UNITED KINGDOM tel. + 441483550859 [email protected] www.tractebel-engineering-gdfsuez.com FINAL REPORT Our ref.: I/RA/14189/13.035/WGO Your ref.: Pro memoriam Date: 31 May 2013 RESTRICTED Employer : Ofgem Project : LINCS Offshore Wind Farm Subject : Review of the export cable installation costs Smart & Sustainable Infrastructure CCS TLM trading under the brand name Tractebel Engineering Limited – Incorporated in England (registration number 7117985) with registered office 5-9 Eden Street, Kingston Upon Thames, Surrey KT1 1BQ, United Kingdom. VAT No: GB 992 5309 89

Upload: others

Post on 04-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el E

ngin

eerin

g Li

mite

d. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

TRACTEBEL Engineering Limited 1st Floor Chertsey House, 61 Chertsey Road, Woking, Surrey GU21 5BN - UNITED KINGDOM tel. + 441483550859 [email protected] www.tractebel-engineering-gdfsuez.com

FINAL REPORT

Our ref.: I/RA/14189/13.035/WGO

Your ref.: Pro memoriam

Date: 31 May 2013 RESTRICTED

Employer : Ofgem

Project : LINCS Offshore Wind Farm

Subject : Review of the export cable installation costs

Smart & Sustainable Infrastructure CCS TLM trading under the brand name Tractebel Engineering Limited – Incorporated in England (registration number 7117985) with registered office 5-9 Eden Street, Kingston Upon Thames, Surrey KT1 1BQ, United Kingdom. VAT No: GB 992 5309 89

Page 2: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el E

ngin

eerin

g Li

mite

d. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

TABLE OF CONTENTS

1. EXECUTIVE SUMMARY .................................................................................................... 5

1.1. Cost evaluation ............................................................................................. 6

1.2. Connection point ........................................................................................... 6

1.3. Project Planning............................................................................................ 7

1.4. Cable installation and consents .................................................................... 7

2. INTRODUCTION ............................................................................................................. 8

3. APPROACH ..................................................................................................................... 8

4. CABLE ROUTE AND INSTALLATION ................................................................................. 9

4.1. Cable route and connection point ................................................................. 9

4.2. Conclusions ................................................................................................. 13

4.2.1. ‘The Wash’ site surveys ........................................................................... 15 4.2.2. Consents 19 4.2.3. Conclusions ............................................................................................ 20

4.3. Project management .................................................................................. 21

4.3.1. Contingency planning .............................................................................. 21 4.3.2. Project decision making ........................................................................... 22 4.3.3. Managing contractors .............................................................................. 22 4.3.4. Participating contractors .......................................................................... 22 4.3.5. Conclusions ............................................................................................ 24

5. CABLE INSTALLATION WORKS ....................................................................................... 25

5.1. Introduction ................................................................................................ 25

5.1.1. Summary of events ................................................................................. 25

5.2. 2010 Nearshore cable installation using HDD ............................................ 26

5.2.1. Conclusions ............................................................................................ 27

5.3. Chain Trenching and installation with rollers 2011 .................................... 27

5.3.1. Cable Float in .......................................................................................... 28 5.3.2. All-terrain Vehicle .................................................................................... 29 5.3.3. Use of Rollers ......................................................................................... 30 5.3.4. Roller spacing ......................................................................................... 30 5.3.5. Conclusions ............................................................................................ 31

5.4. Chain Trenching and float-in installation 2012 .......................................... 31

Page 3: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el E

ngin

eerin

g Li

mite

d. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

5.4.1. Standby UR101 ....................................................................................... 31 5.4.2. Flume Pipe installation in 2011 & 2012 ..................................................... 32 5.4.3. Conclusions ............................................................................................ 32

5.5. Main cable installation ................................................................................ 33

5.5.1. Plough-incident ....................................................................................... 33 5.5.2. Spare Export Cable Storage ..................................................................... 33 5.5.3. Anchor trials ........................................................................................... 34 5.5.4. Conclusions ............................................................................................ 34

5.6. Jointing works and post lay burial .............................................................. 35

5.6.1. Conclusions ............................................................................................ 35

5.7. Cable supply by Contractor ......................................................................... 35

5.7.1. Delay of Supply ....................................................................................... 36 5.7.2. Storage costs spare cable ........................................................................ 37 5.7.3. Conclusions ............................................................................................ 37

6. OVERVIEW OF CLAIMS .................................................................................................. 38 6.1.1. Conclusions ............................................................................................ 38

7. PROJECT COSTS ............................................................................................................ 39

7.1. Breakdown indicative transfer value July 2011 ........................................ 39

7.2. Breakdown status November 2012 ............................................................ 39

7.3. Examples of variation orders ...................................................................... 41

7.4. Conclusions ................................................................................................. 41

8. GENERAL CONCLUSIONS ............................................................................................... 41

8.1. Connection point ......................................................................................... 42

8.2. Project organisation ................................................................................... 42

8.3. Installation methods and consents ............................................................ 42

8.4. Outstanding claims ..................................................................................... 43

8.5. Cost evaluation ........................................................................................... 43

9. RECOMMENDATIONS ..................................................................................................... 44

10. REFERENCES ................................................................................................................. 45

11. APPENDICES – ALL APPPENDICES REDACTED ................................................................. 47

Page 4: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of
Page 5: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 5/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

1. EXECUTIVE SUMMARY

The scope of this review was confined to the Lincs Export Cable installation costs and involved:

• An examination into the investigations undertaken as part of the pre-construction works regarding the options considered for the connection point, and an independent view on rationale for the selection of the connection of Walpole;

• An outline of where export cable installation costs have increased since the indicative valuation was set in July 2011;

• A rationale for each of the costs increases since the indicative was set in July

2011, and an independent view on the justification of these cost increases; and

• A summary and description of outstanding claims and contract variations that have arisen outside of the basic contract price and a view on the claim levels in relation to the work and efficiency of the project management of the contract works.

The analysis covers documentation provided to the consultant between 21 December and 28 January 2013. In addition there were follow up discussions facilitated by OfGem with Centrica and a telephone conversation with Natural England. The events generated further documentation to which commentary has been added in this report. During the review Tractebel UK engaged closely with the developer and there was a constant communication and data-exchange between both parties.

Having taken into account all of the information and data provided, Tractebel UK’s analysis concludes that £ xxxx m of the project’s cable installation cost overruns are not economic and efficient.

This is based upon

(1) The incorrect choice of Horizontal Directional Drilling (HDD) for cable installation in 2010 with the known geology of the Wash Area and

(2) The lack of detailed planning prior to commencement of the 2011 work which we believe could have resulted in the work being completed that year.

This high level figure has been derived even after some of the cost variations documentation had been provided. A detailed reconciliation, including whether any of the overrun costs had been successfully recovered through insurance claims has not been carried out in the agreed timescale.

Page 6: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 6/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

1.1. Cost evaluation

Tractebel UK concludes that although a high level project risk assessment was conducted, the developer should have undertaken more detailed contingency planning to evaluate whether different cable installation methods could have been chosen for the project and/or mitigations set in place. The undertaking of HDD installation without an intrusive survey was accepted by the developer. Unfortunately the 2010 Subocean HDD works were not successful. . If the original HDD installation method had been abandoned earlier (with a contingency plan already in place) the cable installation works which ran into 2012 could have been completed within the original 2011 planned timeframe. Therefore the duration and cost are not economically and efficiently incurred.

The July 2011(Indicative Transfer Value) budget for the cable installation work was £85.4m and during the period of construction costs increased by £26.7m.

The Subocean 2010 HDD costs equal to £ xxxx and the 2012 shore end works equal to £ xxxx totaling more than £16.6m but without agreement to carry out a detailed variation order analysis it has not been possible to reach a final figure.

We therefore conclude that £15m of the £26.7m cost overrun can be classed as inefficient.

Tractebel UK recommends that further documentation needs to be provided and assessed to identify whether further cost increases can be challenged.

Furthermore there are some insurance claims with various contractors which have yet to be resolved which could be in the developer’s favour. A view on the outcomes of these claims has not been part of this report and has not been included in the supportable (or not) cost overrun.

These should be discussed between Ofgem and the developer.

1.2. Connection point

Tractebel UK reviewed a report prepared for the developer by RPS Energy [36]. This focussed on the project’s onshore and offshore cable route options, grid connection considerations and the associated implications for the project’s costs. The report considered briefly the offshore cable installation but did not consider this in depth when evaluating the preferred connection point.

The report considered 3 wind farms (Lincs Wind Farm (250MW), Race Bank (500MW) and Docking Shoal (500MW)) as a joint investment. The options for each project’s cable landing was not fully analysed and hence the most cost effective choice for each project individually may have not been identified.

The developer suggests that a cable route investigation and development for the Lincs Wind Farm only would have been less economical for the project because:

• Survey costs could be shared • Safety of navigation was considered as i) cables would be in one location; ii)

the cables could all be located in the deep channel in the centre of the Wash thereby reducing the risk of anchor snagging

• There would be fewer fisheries exclusion zones

Page 7: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 7/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

• There would be fewer landowners and therefore fewer commercial agreements.

The 2006 study suggests that the key factor for grid connection was the availability of capacity in 2010. It is noted that at the time of awarding the cable installation scope (April 2010) the project’s time frame had scheduled to connect to the Grid by mid 2011 due to delays in the planning process after the application was submitted for consent.

1.3. Project Planning

The project’s offshore cable goes through ‘The Wash’ and a nearshore saltmarsh which, in particular, created significant challenges for the project. Tractebel UK concludes that a detailed local site conditions assessment focusing in on the offshore cable installation route through the saltmarsh should have been undertaken at an early stage in the project. Although Natural England did not permit an intrusive survey in the saltmarsh, Tractebel UK concludes that the local site conditions were not considered in detail when the project’s connection point was finalized.

Tractebel UK notes that there seemed to be little or no contingency planning, risk assessment or mitigation procedures in place as the cable installation procedures commenced. An important example of this is the original consent only permitted a Horizontal Directional Drilling (HDD) approach to be undertaken. The known risks associated with such an approach including the effect of the local site conditions were not identified at an early stage in the project planning and a contingency plan was not created and implemented.

Successful project processes were in operation by completion of the project, for example, controlling project changes [12, 13] and managing contractor interfaces [39, 40, 41],

1.4. Cable installation and consents

The project faced strict consenting arrangements imposed by the Marine Management Organisation (MMO) and Natural England. Nearshore works could only take place between 15 May and 31 of August and access on the saltmarsh would only be allowed with the explicit permission of Natural England. The project’s original consent was for a single installation approach based on HDD. This choice whilst imposed on the project ruled out assessing alternative installation methods. Tractebel UK concludes that the lack of awareness of the nearshore soil conditions in the saltmarsh was a contributing factor to the failure of the HDD approach. The project was forced to review the installation methodology with chain trenching being the eventual selected method, which required modifications to the consent with Natural England. The failure of the HDD and subsequent changes to the installation methodology led to additional costs being incurred by the project.

Tractebel UK concludes that awareness of the nearshore soil conditions should have led to the choice of a float–in technique being adopted in the first instance. Moreover a float-in cable landing is a standard offshore practice, which mitigates risks when the soil conditions pose concerns or are insufficiently known. When this methodology was eventually implemented on the project by another contractor the installation was successfully completed.

Page 8: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 8/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

2. INTRODUCTION

Ofgem are in the process of setting a Final Transfer Value (FTV) for the Lincs Offshore Transmission Assets. An Indicative Transfer Value (ITV) was set by Ofgem in July 2011. Since then the project has experienced an increase in the export cable design, supply and installation costs. As a consequence, Ofgem appointed Tractebel UK to undertake a technical review of the export cable cost increases.

Tractebel UK has also investigated the project’s connection point evaluation, export cable route choice, the developer’s approach to project management and risk assessment, and the export cable installation nearshore and further offshore.

During installation of the export cables for the Lincs Wind Farm (2010-2012) a number of events and delays occurred, mainly taking place in the nearshore section of the export cable route. In addition there were events and delays during the main cable installation, which took place further from shore, for example, jointing works and incidents during the load-out of the export cable and storage of a spare cable piece. (For detailed timeline see Appendix C).

It should be noted that the original contractor for the export cable installation (Subocean) suffered insolvency (in the beginning of 2011). This resulted in different contractual parties to be sought for the cable installation works.

A number of the incidents occurred during the export cable installation which resulted in insurance claims. The outstanding claims are discussed in the report and an overview is provided of the status of the claims at the time of writing this report.

The events that occurred during the export cable and supply installation were analysed further to form an independent view of where the costs have increased since July 2011 and if these increases are economic and efficient. Where possible an estimate of the impact of the events on the cost of the project was made. A review of the developer’s cost template was undertaken. A full breakdown of the cost movements was not provided by the developer. This report is based on information provided by the developer and subsequent discussions that took place involving Ofgem and the developer.

Tractebel UK concludes that a further detailed technical and financial review is recommended in some areas of cost increase [e.g. the revised Technip costs for Export Cable Installation of £ xx m and the transfer of non-OFTO costs to OFTO costs of £ xx m]. This could allow a fuller and complete understanding of all of the cost variations which occurred.

3. APPROACH

This review was primarily based on information provided in the developer’s data room up to January 28th 2013, as well as information or clarifications received by e-mail, during telephone conference calls and face-to-face meetings, specifically covering:

• The latest cost template from the Lincs project (November 2012); • Relevant data room contents;

Page 9: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 9/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

• Centrica’s briefing on the Installation of the Lincs Offshore Wind Farm Subsea Export Cables – A brief history [34]; and

• Additional information provided by Ofgem and the developer during the duration of the work programme.

• Current costs were compared to the ITV which was set in July 2011, and based on the project’s November 2012 costs.

• A phone conversation with Natural England and Centrica facilitated by Ofgem.

4. CABLE ROUTE AND INSTALLATION

4.1. Cable route and connection point

For the purposes of this report Tractebel reviewed the RPS Engineering report dated 22nd May 2007 (EOR0515-1 rev 5: Cable Route Alternatives Study for Lincs, Race Bank and Docking Shoal Offshore Wind Farm Developments, [36]).

The report describes the Lincs Wind Farm connection to the onshore grid.

The report is based on information available only between January and March 2006.

Tractebel UK notes that at the time of writing the report the developers goal was to have the wind farm operational in 2010 (to meet the Government’s 2010 targets for 10% of electricity supplied in the UK to be provided from renewable sources). This meant that the grid connection had to be available within that timescale.

The RPS report considered three wind farms (Lincs Wind Farm, Race Bank and Docking Shoal, ‘Round 2 projects’) with a total capacity of 1250MW, of which 250MW was required for the Lincs project. The developer’s desire was for the offshore export cables of the three wind farms to be combined in an onshore corridor of 50 m. Tractebel UK concludes that considering the Lincs Wind Farm in isolation may have resulted in a more optimal offshore routing outcome for that location. For example, a landing point for Lincs to the West near the landing of the Inner Dowsing and Lynn, while the cable landing for Race Bank and Docking Shoal could be chosen East of the Wash and should have been assessed in further technical detail taking into account the cable installation difficulties that could be expected in the Wash.

The developer has explained that a cable landfall close to Lynn and Inner Dowsing was not feasible as:

• There was no capacity within the existing Distribution Network Operator’s network

• A new 400kV substation would be required and would not be delivered in time. Furthermore this would involve around 50-60km of overhead lines which would be unlikely to receive consent

• To route to Walpole from a Skegness landfall would involve a significant consents from of landowners. The eventual cable route involved only 10 onshore landowners

Page 10: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 10/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

The developer added that the solution to aggregate the Lincs, Race Bank and Docking Shoal cables would result in shared development costs; minimal environmental impact; minimal disruption to fishermen, shipping; and synergies with onshore landowners.

Following discussions The Environmental Impact Assessment [44] was provided but does not generate any supporting arguments for this decision.

In addition to the RPS report, the developer undertook further studies which considered the project’s connection options. The Econnect Consulting report [45] reviewed, amongst other things, the RPS report as well as the electrical studies performed by Mott MacDonald [46], [47] and a construction report by Mott MacDonald. The analysis focussed on the electrical and grid connection issues (including electrical losses).

The RPS report [36] recommended that further analysis should be conducted for the most feasible connection option based upon technology, infrastructure requirements and environmental factors. In addition this report commissioned by the developer considered 11 route options, (see Appendix A), where next to the availability to connect to the Grid, the following factors were mainly considered:

• the costs of the offshore and onshore cables related to the size and length, • the complexity of the cable laying (mainly onshore), • the possible network reinforcement works needed onshore to allow for a

connection in 2010

Table 1 provides a high level overview of the routes that were considered with a description and the conclusions that were reached on each of these options.

Table 1: Description route alternatives

Option Description of route Onshore distance (km)

Offshore distance (km)

Total distance (km)

Summary RPS Evaluation of the route

1

Landfall North of Skegness, running to Bicker Fenn Station (underground cables)

44.31 12.55 56.86

-Bicker Fenn Substation extension was indicated to be needed to accept all 3 Wind Farms (1,25GW). Unclear what additional needs were for LINCS only (250MW) -possible long delays in connection offers were not seen as a driver to dismiss this option, rather traffic delays and cable lengths losses being less economically viable

2

Landfall South of Skegness, running to Bicker Fenn Station (underground cables)

44.31 12.55 56.86 Same remarks as option 1 (see above)

Page 11: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 11/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

Option Description of route Onshore distance (km)

Offshore distance (km)

Total distance (km)

Summary RPS Evaluation of the route

3

Landfall North of Skegness, connection to National grid in Skegness and running to Bicker Fenn Station via overhead lines

- - - Not applicable for Lincs Wind Farm

4

Landfall South of Skegness, connection to National grid in Skegness and running to Bicker Fenn Station via overhead lines

44.31 12.55

-Similar remarks as for options 1 and 2 (see above), overhead lines and a new 400kV substation at Skegness would need to be constructed. - Offers posed risk of late connection (2012)

5 Cable route through the Wash, running to Walpole substation

10.07 40.41 50.48

-This is the shortest onshore route, but has a large offshore section through the Wash internationally designated area. -Walpole substation can accommodate the full 1,25GW from Lincs, Race Bank and Docking Shoal

6 Running the offshore cables North towards the Humber

0 56.22 56.22

-construction of new substation required along the River Humber -cable length losses were indicated as making this option less economically viable

7

Landfall at North Norfolk Coast (vicinity Weybourne) and onshore route towards Sall substation

18.89 56.84 75.73

-No available grid capacity at Sall substation. -Construction of additional overhead lines appeared needed and it was expected that the public would object.

8

Landfall at North Norfolk Coast (vicinity Thornham) and onshore route towards Kings Lynn

17.65 28.06 45.71

Existing 132kV Kings Lynn station would need upgrading and the need for overhead lines was indicated

9

Landfall at North Norfolk Coast (vicinity Weybourne) and onshore route towards Walpole substation

69.81 56.84 126.65 Long cable lengths resulting in high electrical losses

10

Landfall at North Norfolk Coast (vicinity Weybourne) and onshore route towards a new substation

69.81 56.84 126.65

Major reinforcement needed to ensure grid connection, moreover also the length of the cables would lead to high electrical losses

Page 12: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 12/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

Option Description of route Onshore distance (km)

Offshore distance (km)

Total distance (km)

Summary RPS Evaluation of the route

11

Landfall at North Norfolk Coast (vicinity Hunstanton) and onshore route towards Walpole substation

54.74 28.06 82.8

The main driver to dismiss this route was the additional engineering through onshore marshland (areas with high water table) and the longer cable lengths

11*1

Landfall at North Norfolk Coast (vicinity Hunstanton) and onshore route towards Walpole substation

34.58 28.06 62.64 This is an alternative from route 11

One of the key issues discussed in the RPS report [36] is the availability of a grid connection in 2010, which was assessed on capacity being available at Walpole, Bicker Fenn, Sall and Kings Lynn. For the connections around Skegness (closest option for Lincs), Central Network East (CNE) stated that they did not have sufficient capacity to accommodate any of the developer’s projects. The developer had applied for connections to the National Grid, but it was indicated that this would require the construction of a new 400kVsubstation at Skegness, which may take some time to progress given the extent of consents required. This was considered as a limiting factor since a connection would be needed prior to 2010. Therefore, a connection towards Skegness was not considered further by the developer.

At Walpole sufficient capacity was available without the need for reinforcement of the substation or additional scope of works. All other options considered were indicated to require upgrades to the substations or the substation’s electricity connection. Route option 5 (through the Wash) was the chosen route. The report confirms that the Walpole substation provided the grid availability by 2010 for all 3 wind farms without reinforcement works and the cable route being the shortest distance. The RPS report suggested that if there would be a need to minimize the length of the offshore route through the Wash, option 11/11* provided the best alternative. However, a risk assessment on choosing to minimize the length of the offshore cable route was not provided.

EVALUATION OF ROUTES

The onshore routes for Options 5 and 11/11* are discussed in the [RPS report. Options 1 and 2 were not further assessed due to cable transmission losses analysis [47]. A solution to this could have been a larger, but more expensive and maybe later delivered cable. This would have the advantage of a shorter less expensive offshore routing. The financial and technically assessment of this architecture choice was not carried out.

1Route 11 runs further inland (Eastern option), while route 11* runs parallel to the coastline

Page 13: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 13/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

Tractebel UK concludes that the options 1 and 2 appear suitable for the Lincs Wind Farm (250MW) only as the Lynn and Inner Dowsing projects have their offshore cables on land nearby. In addition the project team would have benefited from the experience and lessons learnt from works previously undertaken in that area.

When assessing route 11*, it appears that the landing points that were investigated were Hunstanton and Brancaster. However, due to the environmental sensitivity of the coastline, the eroding nature in the vicinity of Holme, this option was considered unsuitable for cable burial.

Options 9 and 10 considered a landfall immediately 30 kilometres east of Brancaster. These options were considered unviable due to the cable length being in excess of 100 kilometres for the Lincs Wind Farm. Tractebel UK notes that a cable landing in between Brancaster and Weybourne was not further investigated.

The RPS report concludes that a section of the Norfolk Coast is accreting (as also stated in the Appendix B describing the regional physical constraints) and landfall in the vicinity of Brancaster or slightly East of Brancaster would not have encountered erosion. Although the coast between Brancaster and Weybourne also provides challenges, there are roads cutting through to the shore end side, indicating possibilities for an onshore cable route. Although the shorter route would have resulted in a more difficult landfall the important cable burial would have not been impossible.

The remaining routes to be considered were thus option 5 and 11. Route option 11 concentrated on a landfall between Hunstanton and Heacham and this option was detailed and weighed against route option 5 via an impact assessment. Route option 5 scored better, as it was stated that the cable installation would have a smaller negative impact since there would be a shorter onshore cable route. The option 11 route also scored less positive mainly due to the fact that an archaeological site was present on the onshore route. For option 5, the vicinity of an offshore archaeological site was not mentioned in the assessment.

The developer has explained that options 1 and 2 involved a 2015 grid connection which was too late for the Lincs project. Option 11 was not selected as various stakeholders requested that the cables should be located in the deep navigation channel in the centre of the Wash to avoid interaction with anchors and fishing activities.

4.2. Conclusions

Following the analysis of the RPS report Tractebel UK notes that the offshore cable installation and the related risks are not described as a major concern in this report.

However, in Offshore Wind projects, Tractebel UK notes that offshore cable installation (including landfall and Offshore Substation Platform works) is typically the package where the majority of the construction incidents, delays occur and is the main cause of cost overruns.

Page 14: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 14/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

The offshore cable installation works are complex in nature and are more than other disciplines dictated by the experience level of the contractor performing these works. Moreover, dedicated cable installation vessels and barges are heavily booked during the good weather periods and day rates are high. The latter results in the fact that any delays encountered have a high cost impact, especially in comparison with onshore works. Onshore cable works apply well known techniques, are less weather dependent and avoid vessel/barge standby costs when facing an unexpected delay.

SELECTED ROUTE

Option 5 was chosen as the route selected to link the 3 wind farms Lincs, Race Bank and Docking Shoal to land as this was the shortest export cable installation route to the substation at Walpole. This route runs through ‘The Wash’ with strict consenting arrangements, the presence of a shipping lane as well as dedicated anchoring areas.

If in the initial stage and based on the known challenges of working in a saltmarsh area, the offshore cable routes had been further investigated and risk assessed, a route option avoiding the many challenges of an offshore cable installation through ‘The Wash’ could have been chosen in order to mitigate the overall project’s risk.

The Lincs Wind Farm project was considered in conjunction with Race Bank and Docking Shoal and a key factor was the availability of a grid connection in 2010. However, at the time of awarding the cable installation scope to Subocean on 22/04/2010, the project’s time frame had scheduled completion of the cable installation and connection to the grid by mid 2011 due to delays in other parts of the consenting process.

Tractebel UK has not seen any review or analysis of risk weighting between the on shore and offshore cable routes selections.

RISK ASSESSMENT

As the offshore cable is the critical connection from a Wind farm to the Grid, the offshore cable installation works should be well planned and risk assessed to minimise construction difficulties. Tractebel UK notes that the project’s cable installation risks appear to have not been taken into consideration during the analysis of the different onshore connection points.

For an offshore cable the management of the installation is much more difficult than for an onshore cable, since the risks are much higher. For example:

• Day rates of onshore equipment are much lower than day rates of offshore vessels; and

• Offshore works involve consideration to tidal, currents and wave impacts that can complicate installation and lead to standby costs which can lead to significant project cost increases.

Given the specific site conditions along the envisaged cable route through ‘The Wash’ (in a saltmarsh) the shipping lanes, the anchorage areas, the presence of firing ranges (and thus risk of unexploded ordnance in the vicinity), an early risk identification and mitigation plan would have been necessary. Such analysis may have minimised cable installation difficulties and reduced the project’s cost overruns.

Page 15: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 15/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

Compared to a detailed onshore route investigation, Tractebel UK has been presented with little detail describing the risks related to the offshore cable installation. It is unclear how these risks were evaluated in the design stage of the project and whether mitigations were put in place by the developer when signing the installation contracts with the different contractors.

Tractebel UK is unable to locate an early project risk assessment that considers the offshore cable installation, this is of concern given that the export cable installation is typically the cause of budget overruns on wind farm projects.

PREVIOUS EXPERIENCES

Tractebel UK notes that the nearby Lynn and Inner Dowsing projects land their export power cable close to Skegness with a short offshore cable installation route. Tractebel UK was advised (but without documentation) that even for the single Lincs project connection these routes (options 1 and 2) were rejected by the developer due to lack of capacity.

Previous experience is an important factor which should have been included in the evaluation of the cable routing especially for the Lincs project in isolation. Knowledge was gained and lessons-learned were available from these already executed cable installations. Awareness about the previous experience with the already installed wind farms would have been valuable and does not appear to have been utilised during the planning or implementation.

OFFSHORE CABLE ROUTE INVESTIGATION

For option 11 the erosional sedimentary regime at the onshore landing site was seen as non viable and therefore this route was rejected.

However later investigation performed by the developer indicated that an archaeological exclusion zone and that the River Nene channel was mobile in vicinity of the offshore cable corridor for the selected route option 5. This could result in cable exposure if the channel would pass over this cable route. This information was further examined in documents [48], [49] and [50], but was not considered in the earlier RPS engineering document and therefore could have altered the cable route assessment outcome.

4.2.1. ‘The Wash’ site surveys The project’s site surveys which were available (in the data room, later uploaded or mentioned in other documents) before and during the construction phase of the export cables of the Lincs Offshore Wind Farm are chronologically listed in Table 2, followed by a brief summary of these documents.

Page 16: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 16/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

Table 2: Overview of site surveys

Title report Author Date

Geophysical Survey For Proposed Lincs Offshore Wind Farm

EMU Ltd May-05

Geophysical Investigations at the Proposed Race Bank & Docking Shoal Wind Farm Sites with associated cable route corridors – Section 4: Greater Wash area cable route survey2

EMU Ltd

May 2007

Saltmarsh Walkover Survey Centrica January 08

Interim Report 1: Lincs Offshore Wind Farm - (Saltmarsh and Landfall Sections)

Harrison Geotechnical Engineering

August-08

Acoustic Surveys for the Proposed Lincs Offshore Wind Farm Sites3

EMU Ltd October 08

Geotechnical report LINCS wind farm export cable route survey laboratory and in situ data final report

Fugro March-09

Geotechnical Design Report Ramboll Wind September-09

Geotechnical Interpretative Report Export Cable Shore Approach4

Geomarine Ltd December-09

Export route sediment transport study HR Wallingford March-10

HDD Works – Trafficability Assessment Geomarine Ltd /Subocean

October-10

DESCRIPTION OF DOCUMENTS

• By May 2005, a preliminary geophysical survey was conducted by Emu Ltd. Geophysical investigation methods entail the techniques to acquire soil information without making physical contact with the soil itself (e.g. seismic investigation, bathymetric soundings and magnetometer survey). This covered the Lincs Wind Farm site in the offshore area between ‘The Wash’ and the Humber. This report focuses on the wind farm and export cables. The survey of the export cable trajectories did not come closer to shore than KP2, since marine spreads were used to conduct the investigation.

2Uploaded on 24/01/2013, detailed review within the timescale of the project no more possible

3Uploaded on 24/01/2013, detailed review within the timescale of the project no more possible

4Uploaded on 30/01/2013, reviewed after issuing draft report

Page 17: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 17/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

• In January 2008 a saltmarsh walkover survey was performed by the developer. Information about this survey, other than a map, could not be found in the data room. After consulting with the developer they confirmed that the survey could not be traced. This is an important document since it provides details about the site conditions at an early stage of project development.

• The report by xxxxxxxxxxxx (2008) concentrates on the Saltmarsh and landfall sections. This investigation consists of a desk study, a geophysical, and an intrusive investigation. The latter gathering soil information by sampling from boreholes and/or trial pits.

• The geotechnical report by xxxx was completed in March 2009 and focused on the export cable route. This comprised of 51 piezocone penetration tests (PCPTs) at 41 locations and 18 Vibrocores at 17 locations. Cone penetration testing is a method to determine geotechnical soil parameters (e.g. resistance, friction,..) in order to determine the soil stratigraphy, whereas vibrocoring is a procedure for obtaining long, well-preserved cores. These soil samples can be further investigated in laboratories. The sample VC/CPT 02 was found closest to shore, located approximately 3.5 km from the first sea defence.

• In September 2009, xxxxxxx prepared a preliminary geotechnical design report, for the development of the Lincs Offshore Wind Farm. This report investigated the 69 wind turbine generator locations.

• The geotechnical interpretative report prepared by xxxxxxxxx (2009) investigated the section of the proposed route that lies on the intertidal area consisting of 4 km of saltmarsh and mudflats. They were contracted to focus in particular on the section KP0.67 - KP3.0. xxxxxx carried out 7 cone penetration tests, 4 ballcone penetration test and 6 trial pits. Additionally, they compared their findings with the xxxxx (2008) and xxxx (2008) reports

• xxxxxxxxx report (2010), referred to a geotechnical assessment of the bearing capacity of the soils with reference to all-terrain vehicles (ATV) tests carried out on the mudflats and the potential settlement of proposed vehicles. The considered area extended from KP 1 to KP 3.

• The report prepared by xxxxxx (2010), investigated historical bathymetrical data and survey data for the landfall section to advice on route selection in the cable corridor between KP 3.5 and KP 8. The purpose of this report was to investigate the risks of cable exposure as a consequence of sea bed level changes and channel migrations.

EVALUATION OF DOCUMENTS

Tractebel UK considered the site investigation reports listed above, in particular, the reports which considered the nearshore section (KP0 - KP 1). Xxxxxxxxx report of August 2008, explains that three investigation methods were undertaken: a desktop study; a geophysical investigation, (comprising resistivity tomography, seismic reflection and magnetic/metal detection) ; and an intrusive investigation, existing of laboratory testing (chemical, geotechnical and thermal resistivity) of borehole samples.

Based on this analysis, the following conclusions were reported in relation to the directional drilling beneath the Saltmarsh / landfall section (see table 3 below):

Page 18: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 18/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

Table 3: Geotechnical considerations/hazards [17]

The stratigraphy thus consists of variable alluvial deposits, underlain by alluvial sands. At around -12 to - 15m aOD (above Ordnance Datum), a layer of Glacial Till (slightly gravelly clay) was identified.

In view of the planned HDD works the report identified the presence of a variety of soil types: the Alluvial Sand characterized by saturated collapsible soils and the Glacial till, comprising very stiff soils and gravelly cohesive deposits (occasionally cobbles). These conclusions were based on the sampling from a total of five cable percussion holes (BH2, BH9, BH11, BH12 & BH13) and a single trial pit (TP1) located in the landfall area (see Appendix H). In the saltmarsh area, indicated as a zone unavailable for access and thus for intrusive investigation methods, findings were based on remote geophysical investigation techniques (i.e. resistivity tomography and seismic reflection, see Appendix I).

Based on the review of all site survey reports provided, Tractebel UK concludes that the xxxxxxx report (2008) is the only report which described the area where the HDD operations failed. This geotechnical survey covered the land route including both sea defence structures by means of intrusive investigation techniques; however, there was no consent available from Natural England for vehicular access or intrusive investigation of the saltmarsh. Consequently only remote (resistivity and seismic) survey techniques were undertaken on the saltmarsh. These kinds of analysis have a limited penetration depth (seismic) and limited accuracy (resistivity) and should be confirmed by borings.

An important finding of the xxxx report however is the description of the presence of collapsible soils and cobbles. This is indicated in the map of the Saltmarsh Walkover Survey (January 2008) where a short (but important) description of the soil conditions is given (Appendix J). The soil is described as soft to very soft mud with a shallow anoxic layer.

In relation to the placement of the rollers in 2011 by xxxxx no more information is available, since the closest location where geotechnical investigation was done, other than the Harrison study, is at 3.5km from the seaward sea defence xxxxx.

Page 19: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 19/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

Xxxxxx (2009) produced longitudinal soil profiles of the planned cable trajectory based on the xxxxx (2008) and xxxxx (2008) reports and their own soil investigations. As illustrated in the figure below, Tractebel UK notes the lack of information between landfall (KP0) and KP1. Whereas the spacing between explorative locations is 500m or less in section KP1-KP4, the zone (KP0-KP1) meant to be crossed by HDD only contained soil information around the landfall (4 BHs), KP0.67 (CPT) and KP1.0 (CPT and trial pit). Thus in the zone where HDD attempts failed, there was no existing soil information. Like the other geophysical/technical reports, Geomarine reported also the consent restrictions of Natural England: “Trial pits were excavated where possible, no trial pits were permitted on the Saltmarsh as it is a site of Special Scientific Interest (SSSI)”.

Given that xxxx was in the possession of both xxxx and xxxx findings which could be field-tested by them, Tractebel UK concludes that xxxxx were best placed to judge the risks associated with a HDD solution. However, the report didn’t investigate the feasibility of the HDD itself. The report discussed the geotechnical aspects of (1) cable trenching options including jetting and ploughing; (2) use of a jack up platform at the HDD exit, (3) provision of a hold back anchor should an HDD rig or pull winch be located on the jack up platform; (4) grounding of the cable barge on the mudflats at some point between the HDD exit and KP3 and (5) tracking and manoeuvrability of earthmoving plant on the mudflats.

4.2.2. Consents For the chosen cable route the landfall of the two export cables of the Lincs Offshore Wind Farm is located east of the mouth of the river Nene in the Wash. The export cables cross a saltmarsh area with an approximate length of 1 km and further an inter-tidal area is present. Both areas are environmentally protected zones with important vegetation, mammals etc and is used as a resting area for migrating birds.

This resulted in strict rules being put in place regarding the installation and operation of the two export cables, especially in the 1 km long saltmarsh area, such as

• Minimal disturbance on animal life • Minimum impact on creeks and gullies

Page 20: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 20/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

• Minimal spatial and temporal presence • Minimal machinery and personnel passage. • Work to be limited to the amended annual consent period between May until

early September.

With these limitations, installation via HDD was a mandated choice from an environmental point of view.

The original FEPA Licence (33574/08/0, [4]) indicates that directional drilling should be used to install the drilled ducts under the sea defences at the landfall. It however does not dictate that directional drilling was to be done under the saltmarsh: "The two export cables will be buried approximately 50m apart as far as the intertidal area and reduce to 5m at the landfall through drilled ducts under the sea defences. The drilled ducts at the landfall will be constructed using directional drilling. The depth of the cable will be approximately between 1-3m depending on ground conditions.

The main restrictions of the CPA consent (33574/08/0/CON, [5]) are that works can only take place between 15 May and 31 of August and that any access (by foot or vehicle) on the saltmarsh during cable installation work including directional drilling will only be allowed with the explicit permission of Natural England. These restrictions are also mentioned in the FEPA consent.

The relevant clauses from the FEPA consent are as follows:

• 9.58 The Licence Holder will only undertake cable installation operations within the inter-tidal area between 15 May and 31 August

• 9 59 The Licence Holder must ensure that access (by foot or vehicle) on the saltmarsh within the Wash SSSI during cable installation work, including directional drilling, will only be allowed with the express permission of Natural England.

It is unclear what the developer applied for when seeking consents from the relevant Authorities. Tractebel UK notes that only a consent for the HDD to cross the saltmarsh and the sea defences was initially granted.

4.2.3. Conclusions The selection of HDD without detailed knowledge about the local, but known to be challenging, geology created a risk which the developer implicitly accepted and which contributed to the resulting project delay and cost outcomes.

A more extensive site investigation during the pre cable installation period may have led to an initial cost increase, but it is clear that with more comprehension of the site conditions some events would have been anticipated and mitigated. This should have been prudent practice and becomes even more important when HDD is considered.

To be able to perform more geological investigations, the initial consents needed to be challenged further. This would have required further efforts before commencing the installation works, Tractebel UK concludes that this may have avoided project delays and increased costs.

Page 21: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 21/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

Tractebel UK notes the difficulties that the project faced and that the consenting arrangements imposed by Natural England created additional complexities.

4.3. Project management

When managing a project of this kind which involves an offshore cable installation with many challenges, early risk identification and the development of contingency plans including mitigations are of high importance. Furthermore, the decision making process within the project management structure when dealing with changes which have a cost impact is vital.

Tractebel UK requested information on the project management structure and decision making processes. Responses are discussed below.

4.3.1. Contingency planning Tractebel UK notes that the project did not have in place a contingency plan for failure of the HDD cable installation campaign. The reason given for this by the developer was that only the HDD works were consented. Following the failure of HDD in 2010 Natural England modified their requirement to allow alternative installation methods to be performed.

Tractebel UK asked the developer for an insight in the original method statements and the initial contingency plans in place prior to start of the cable installation works. One emergency and contingency plan was uploaded in the data room by the developer on 24/01/2013 (“Lincs Export Cable Inter-tidal Works: Emergency and Contingency plans,”[11]).

The version that was provided and reviewed by Tractebel UK is the updated version for the 2012 cable installation works. The previous, original document is dated 11/07/2011., which was after the first attempt to install the rollers and before repositioning them (see chronological overview Appendix C). At that time (11/07/2011) floating the cable had not been considered, which suggests that the document made available had undergone revisions. The original document was not made available; therefore, it is not possible to comment further on what was considered in the original contingency plan.

Another example of the lack of contingency planning is for the roller installation. After the incident of the nearshore export cable loop, the offshore marine equipment was demobilised from site to enable the contractor to prepare contingency arrangements. Tractebel UK concludes that a float-in technique which is common in export cable landings should have been prepared during the risk assessment stage as a potential alternative to avoid a shift in planning.On 24/01/2013 a mitigation plan was uploaded in the data room [14]. This document refers to the onshore cable installation only. Mitigation plans for the offshore cable installation were not made available. This was pointed out to the developer when receiving this document but no additional information in this respect has been provided.

Page 22: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 22/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

4.3.2. Project decision making The decision making process for project changes were discussed during a conference call with the developer on 16/01/2013. Consequently, a number of documents were uploaded in the data room (controlling changes procedure [12] and controlling changes flowchart [13], see Appendix D). The objectives of these documents are described as follows:

• changes to the project scope, deliverables / interfaces, timescales, budgets or resources are formally defined, evaluated and approved prior to implementation

• the appropriate design documents and supporting information are updated and made available for reference

The structure of these documents shows that a good project control system is currently in place. However, these documents date from 27/04/2012 and 18/09/2012, after most of the critical decisions on the project had been made. It is unclear how and when these processes were developed but is clear that the process evolved as the cable installation was being performed. The following was also communicated by the developer in a separate communication on the follow up, but also this does not provide clarity on the status at the start of the project:

After the developer had reviewed the report, a controlling changes flowchart and procedure dating from 05/02/2009 was uploaded in the data room (on 26/03/2013). These documents are similar to the above mentioned documents of 2012.

4.3.3. Managing contractors Tractebel UK was informed by the developer that interface meetings were held regularly between the participating contractors (xxxxxxxxx).

Additional documents were made available (managing interfaces procedure [40], managing interfaces flowchart [41] and managing interfaces strategy document [39]). These documents are general documents that apply not only for the Lincs Wind Farm project. The objectives of these documents are described as follows:

To ensure the delivery of a wind farm in which all interconnecting and/or interdependent subsystems and components connect together efficiently and effectively, thus enabling the operation of the wind farm systems.

Like the project control change documents mentioned above, a good system appears to eventually have been put in place. However, Tractebel UK concludes that it is unclear whether these documents dates 15/11/2012 and 01/05/2012 are revisions of an older document. For the documents no earlier versions have been seen.

4.3.4. Participating contractors A short overview of the project’s participating contractors is provided below.

Xxxxxx scope

The scope for the installation of the export cables (and array cables) was awarded to xxxxxx after a tender process.

Page 23: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 23/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

The scope of work of xxxxx was divided into 3 work packages (Contract xxxxx [38]):

• WP1: Management, Engineering, Collection, Installation and Testing of Main Section of the Export Cables (KP8 to KP48), Collection & Installation of Collector and Array Cables, Construction of Transition Joint Bay and jointing to onshore cables, jointing the Nearshore section and the Main section of the Export Cables (KP8), pre-installation surveys, route clearance, pre-lay grapnel runs, cable protection, post installation surveys and cable storage facilities

• WP2 -a: 2 x 1000m Sea defence/saltmarsh Ducts, installed by Horizontal Directional Drilling (HDD)

-b: Marine Support for HDD Operations

• WP3: Collection, Installation and Testing of Sea Defence and Nearshore sections of the Export Cables(from Sea Defence to KP8)

WP1 and WP2a were Lump Sum based, while for WP2b and WP3 a Provisional Sum was set (within which bought items to be charged at cost plus). Taking into account the uncertainties and challenges in the nearshore work and that the methodology was not fully developed at the moment of closing the contract, WP2 and WP3 were agreed to be subject to a combined cost cap.

Initially the following schedule for completion was foreseen:

• WP2: end of August 2010 • WP3: end of August 2011 • WP1: end of January 2012

Using the information in Appendix F, it has been possible to compare in detail the planned versus actual planning (status 24/06/2012) for the project. The first export cable was installed and tested by March 2nd 2012 (planned July 31st 2011), the second export cable was installed and tested by late 2012 (planned August 20th 2011).

Xxxxxx scope

After the insolvency of xxxxxxxx , xxxx took over the contract scope and a new cost plus (rather than lump sum) contract was signed on 7/03/2011.

As a result of changes in the installation methods (abandoning HDD works, installation by chain trenching) part of the xxxxx scope was taken over by xxxx in 2011. When changing the export cable onshore pull-in method to floating, a new contract was signed with xxxxx Offshore.

The installation of the second nearshore export cable in 2012, was awarded following a tender process to xxxxx. The cable trenching contract was subject to an amendment to the contract with xxxxxx.

Page 24: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 24/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

The offshore jointing works were undertaken by xxxxx who supplied the marine spread, while xxxxx undertook the jointing work. The transition joint bay was contracted with xxxxxx. (Post lay burial (joint locations and remedial) was performed by xxxxxxxxxxxxx undertaking further burial works to achieve the export cable burial depth.

An overview of the participating contractors related to the different installation works can be found in Appendix G.

4.3.5. Conclusions Tractebel UK concludes that the developer has now established good project management controls. It is also clear that there was an evolution of the developer’s approach to project management during the project.

Tractebel UK notes that the project faced a number of issues which required decision making under time pressures and alternatives were often not examined thoroughly. For example, when HDD and the use of rollers failed, these difficulties could have been prevented if alternatives were set out at an earlier stage with risks being identified and mitigated.

It should be noted that daily activity reports, incident reports, root cause analysis etc, could have provided a clear understanding of the project management during the cable installation and how the board was informed about incidents. Such documents were requested but were not made available during the writing of this report.

The insolvency of xxxxxx and the change in cable installation methodology, led to 4 new contracts (xxxxxxxxxxxxxxx). Tractebel UK notes that the xxxxxxx contract was sourced on a cost plus base, placing more financial risks with the developer.

The scope of the jointing works increased due to incidents offshore and was not part of the original scope of xxxxxx contract (3 unplanned joints were needed, KP18, KP44 and KP 44.4). The increase in contractual parties required additional interface management by the developer. This created additional complexities and risks for the project if one of the contracting parties is unable to keep to their planned timetable.

Although appointing different contractors for different scopes can lower the initial project’s cost, the project management interface will create challenges resulting in high level of interface management. Tractebel UK believes that by this decision the developer has raised the risk on cost increases within the Lincs Wind Farm.

Page 25: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 25/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

5. CABLE INSTALLATION WORKS

5.1. Introduction

During the installation of the export cables of the Lincs Wind Farm (2010-2012) a number of delays and/or incidents occurred. These events mainly took place in the nearshore section of the cable route. This nearshore section runs from a sea defence embankment (Kilometre Point 0, KP0), through a saltmarsh (KP1) over an inter-tidal area which is 8 km long (KP8). The region forms part of 'The Wash' and is of high environmental importance. The planned consent window for the nearshore activities was from 15th May to 31st August but was amended each year (see Appendix C: The Time Line of Events)

A map that gives an overview of the cable corridor can be found in Appendix E.

5.1.1. Summary of events The sequence of the events is described below:

• 2010: To cross the saltmarsh, Horizontal Directional Drilling (HDD) was the chosen installation method to avoid direct impact to the saltmarsh vegetation. After several attempts it seemed that the ground was too soft to have a stable borehole. This installation method was finally abandoned due to the soil conditions. The consent window of that year was lost and moreover the contractor (xxxxxx) faced insolvency, resulting in an early closure of this contract and necessitating the developer to set-up a new contract (xxxxxxx).

• 2011: The consenting authorities (Natural England, MMO), agreed to a revised installation methodology using chain trenching. The installation of the export cable took place on a barge (UR101) with an All-Terrain Vehicle (Nessie V) using rollers tracking over the nearshore area. However, when the ATV started to pull the cable, a loop occurred, due to allowing too much cable to leave the barge while the pulling over the onshore installed rollers faced difficulties. After evaluating the situation, it was decided that the most favourable way to restart the operation was to cross the saltmarsh by floating the cable to shore. This led to preparing a revised methodology (which is a common technique in export cable landings), resulting in new contractors and further cost increases. Tractebel UK notes that due to subsequent delays (for example, the trenching vehicle Nessie III that got stuck) only one of the two nearshore cables could be installed during the consenting window of 2011.

• 2012: For the installation of the second nearshore cable, the developer used the float-in technique that was eventually successful in 2011. These works were undertaken by a different contracting party (xxxxxx xxx). During this installation there were delays caused by a late installation of the flume pipes (to cross creeks).

Page 26: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 26/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

Besides the nearshore installation delays, there were also further delays and incidents during the main cable installation (plough incident) and the jointing works (beam failure during redeployment after jointing works), as well as incidents during the load-out of the export cable (cable damage during the Factory Acceptance Test) and storage of a spare cable.

Furthermore as mentioned above due to the insolvency of the original contractor for cable installation (xxxxxx), different contractors participated in the installation works. This led to a higher level of interface management for the developer and a higher risk for (consequential) delays when one contractual party cannot keep to their planning timetable. All the above have led to cost increases and project delays.

In Appendix C a time-line of the different events is given per activity.

5.2. 2010 Nearshore cable installation using HDD

To install the first 1000m of the export cables which cross the sea defence and the saltmarsh, HDD was the planned methodology, even though no detailed geotechnical investigation data was available in the saltmarsh area. The HDD works were executed by a marine spread with drilling equipment on two barges.

Between April and September 2010, six HDD attempts were performed, with drilling taking place offshore and onshore. These attempts failed in the unexplored saltmarsh zone (hole collapse, drilling rig got stuck , see progress diagram of the HDD works Appendix K, [2], failure of the HDD occurred on each occasion under the saltmarsh).

HDD is a good method of installation when sensitive land areas have to be crossed, without disturbing the surface. However, it is important that soil conditions are well known before commencing such works, since unexpected bottom soil conditions can lead to loss of drill mud and early collapse of the drilled hole. Stability of the drill hole, at least until the power cable is pulled through the predrilled hole, is essential. Execution of HDD without a detailed soil survey to the depth of drilling constitutes a project risk.

This guidance is also confirmed by the later provided reports from xxxxxxxxxxxx [43] where it is stated:

“It is recommended that one borehole should be taken at three different locations along the duct path during ground investigation studies prior to installation in order to establish the exact geotechnical parameters of the local ground conditions.”

And

“It is recommended that at least 3 test bores be undertaken at the salt marsh area as part of the Marine Route Survey prior to drilling. Dependent on the test result data xxxxxxxxx would recommend the use of HDD technology for the Centrica Wash project.”(Tractebel UK underlining)

These reports were made available by the developer on 26/03/2013 and 21/03/2013.

Page 27: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 27/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

After the 3rdattempt to install the drilled duct there was a meeting held between the developer, xxxxxx and Natural England to discuss the installation difficulties. From the minutes of meeting [6], it’s clear that alternative installation methods were suggested by the developer / xxxxxx, however, Natural England confirmed they were unwilling to deviate from a HDD solution. This demonstrates that the developer (and xxxxxxx) took action when it was clear that HDD would fail. Nevertheless, as also indicated in the minutes of the meeting, it was acknowledged by the developer that the request for an intertidal trial (to see if an excavator was non intrusive) in 2010 had been submitted to Natural England, but it was too late to be carried out before the end of that year.

Tractebel UK concludes that early engagement with Natural England to obtain a consent to explore the area by means of intrusive investigation methods could have been a useful precautionary step in managing risks. Tractebel UK notes that the xxxxxx report ([17], see 4.2.2.1) identifies the presence of collapsible soils and cobbles, and therefore could be seen as an early warning for the possible failure of the HDD.

5.2.1. Conclusions Execution of HDD without a detailed soil survey to the depth of drilling constitutes a high project risk. Tractebel UK concludes that the developer could have challenged the consenting authorities to obtain permission for a geotechnical survey. This would have allowed the developer and its contractors to inform the Authorities of the associated installation risks.

Furthermore, since there was no geotechnical information about the saltmarsh available, the risk for an unsuccessful HDD campaign needed to be anticipated and alternative installation methods should have been prepared and discussed with the licensing Authorities up front. Tractebel UK was informed by the developer, that there was no contingency plan for the HDD works since the consent prescribed HDD drilling under the sea defense structure.

Due to the unsuccessful HDD campaign in 2010, a new methodology and thus further engineering needed to be performed which led to a project cost increase. Furthermore with the spread of the drilling equipment on the two barges, the initial cost of xxxxxx increased, costs that later on proved to be excessive.

Cost impacts of the above can be seen in the first row of the overview table under section 5.

5.3. Chain Trenching and installation with rollers 2011

After the failure of the HDD campaign in 2010 and xxxxxx collapse, alternative installation methods were discussed with a number of parties (authorities, contractors). Following several meetings with the licensing Authorities consent was granted for chain trenching. In conjunction with the contractor xxxxxx, modifications were made to an existing cable trenching vehicle (xxxxx) and a new cable laying vehicle was developed (xxxxxx).

Page 28: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 28/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

For the nearshore cable-installation, the xxxxxxx installation methodology was based on rollers to be placed in the inter-tidal area to transfer the cable from the grounded position of the cable lay barge to the xxxxx vehicle.

This new installation method did however not maintain the planned timing of the project and a number of difficulties were encountered, as described below.

5.3.1. Cable Float in The alternative methods focussed on different burial alternatives (see Table 4, [2]).As indicated in Table 4, the Trench Duct was the most favourable option. To transfer the cable from the UR101 (the nearshore cable installation barge), to the xxxxx, however, only the installation of rollers along the route was considered. Tractebel UK was informed by the developer, that the experience of the contractors (xxxxx and xxxxxx) was followed at that point. As mentioned in the history review document, the float-in method and the use of rollers are both widely used for subsea power cable landings. Cable float-in is a typical landfall cable pull-in technique.

Following the failure of HDD a risk matrix was created by the developer for the alternative options as shown below in table 4 [2]:

Table 4: Developer Option Matrix after failed HDD campaign of 2010

Taking into account the difficult work conditions (saltmarsh, very poor surface soil strength) and the fact that a disturbance of/access to the ground was limited by consent arrangements, Tractebel UK concludes that the float-in method should have been considered by the developer at an earlier stage and not only in reaction to the failure of the marine spread with rollers. The float-in method is an environmental more friendly installation approach but it is understood from the developer that it had concerns over whether there was sufficient water depth to facilitate this solution.

Page 29: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 29/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

Furthermore it was mentioned in the history overview [34] that at the time of the loop (July 2011) during the first attempt with the rollers, ‘it had been seen first-hand by both the contractors and the client representatives just how little wave or current action there typically was in the inter-tidal area’. Taking into account that already a year of activities (2010) occurred on site before starting to use the rollers, it seems that the float-in method should have been recommended or at least discussed with the contractors by the developer prior to the start of the works in 2011.The Saltmarsh Walkover Survey of January 2008 (see Appendix J,[3]) also gave an indication of the soft to very soft mud being present.

According to the developer floating of the cable was not considered as the consent window (15/05-31/08) was outside the high tides in Spring/Autumn and it was estimated that there would not be sufficient water along the cable route. It was considered by the developer that floating would be more costly, time consuming and constitutes a greater project risk.

Tractebel UK concludes that the float-in method was prematurely abandoned (it wasn’t even part of a contingency plan). Moreover the Mean High Water level has been indicated on drawings (see Appendix H) to be near to the first embankment, thus providing sufficient floatation means. This was also proven by the fact that the method was eventually successfully performed.

5.3.2. All-terrain Vehicle After the consent for chain trenching was granted, there were trials conducted with the xxxxx. According to the xxxxx contract, first trials were undertaken in Germany. There is no information about the site conditions in Germany, so it’s not possible to evaluate if these trials were of relevance when working in ‘The Wash’ area. Tractebel UK understood these trials were undertaken to demonstrate that the xxxxx was able to cross creeks.

The first trials performed at the site of Lincs on 17/05/2011 were unsuccessful, since the ground was found to be much softer than anticipated. After recovery of the All Terrain Vehicle (ATV), the support vessel (xxxxxxx) returned to port and contingencies were prepared (18/05/2011). The developer advised of a contingency plan but this was not revealed to Tractebel UK. Nevertheless it took 10 days to be able to resume works (not taking into account the delay due to the advice from Natural England to stop the works until the 6th of June 2011).

During operations on 23/08/2011 at KP1.048, xxxxx got stuck. To provide tow assistance a winch was required on the GKS. Operations were stopped for 6 days. It’s unclear if this was a risk that was taken into account before the start of the operations. Since during trials it was confirmed that the site conditions were very soft, this event should have been anticipated.

Page 30: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 30/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

5.3.3. Use of Rollers A first attempt to place the rollers was made on 08/07/2011. The rollers were placed from the same support vessel (GKS) as the vessel from which xxxx was launched for the trials. The trials with xxxx in the inter-tidal area started on 17/05/2011. The first trial failed and a second (successful) attempt was made between 09/06/2011 and 13/06/2011. Roller placement commenced on the 8th of July 2011, one and a half months after the GKS first came on site. First deployment failed due to the extremely soft soil conditions (after HDD works). After that a route change was agreed and the rollers were repositioned on 15 and 16/07/2011.

Since it was known that the working area provided challenges and access to the inter-tidal area was only consented (prior to negotiated changes) between the 15th of May and the 31st of August, it is not clear why time was lost before starting to place the rollers or why deployment of the rollers and the xxxx was not performed simultaneously.

5.3.4. Roller spacing For the pull-in of the nearshore export cable a roller spacing of 9.5m was used, based on previous experience of xxxxx handling another subsea power cable in Germany.

As mentioned above, when the xxxx started pulling the export cable from the barge (UR101) along the pre-positioned rollers, a cable loop occurred. In the history overview it is mentioned that after the loop the roller spacing was called into question. The cable was allowed to go slack between the rollers, which is the result of paying-out too much cable from the barge while the pulling over the onshore installed rollers faced difficulties. This interface risk should however been mitigated by clear communication between the different contractors. For example, monitoring of the tensioner read-outs and the cable departure angle at the chute of the barge (angle measurement tool at the cable chute, continuous visual check at the chute, etc.) should have led to an all stop being called on the cable installation barge.

One of the documents available in the data-room is a document from xxxxxx describing the cable installation and handling parameters [1]. In this document the expected cable stiffness range and related behaviour is listed. In the same document of xxxx a maximum allowable unsupported cable span is mentioned. For a cable were no tension is applied, centre distance of cable rollers is mentioned to be as short as 1 - 1.5m for the Lincs export cable. It is mentioned in the history overview that during load-out at xxxx a roller spacing was used of 3m (i.e. cable under tension). We understand that the developer’s client representatives were present during the load out, a roller spacing of 10m as suggested by xxxxx should have been followed and insisted upon by the developer during review of the method statements. Tractebel UK has reviewed a report of Longitude Engineering [10] describing simulations that were made of the spread for the pull-in of the cable from the grounded barge at KP2.4 to xxxxxx. The simulations had the goal to investigate cable tensions, bend radius and loads on the cable rollers. A quick review (note that we only received this document amongst others on 24/01/2013) of the report shows that no evaluation was made about the roller set up, nor the stability of the rollers in the Wash area. The set up with roller spacing of 10m was used as input data and was not challenged.

Page 31: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 31/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

5.3.5. Conclusions The float-in method is a standard landfall cable pull-in technique which should have been considered at an earlier stage and not just in reaction to the failure of the marine spread with rollers. Taking into account the difficult work conditions (saltmarsh, very poor surface soil strength) and the fact that a disturbance of/access to the ground was to be limited as much as possible; the float-in method would have been the preferred choice at the start of installation.

Due to the time lost during operations, only one nearshore cable could be installed in 2011. Hence installation works were extended into 2012. This meant additional contracts (e.g. xxxxx ) and an amendment to the xxxxxxx contract.

If detailed planning including risk assessment had been carried out prior to 2011 work being started it is believed that all work could have been successfully completed removing the need for any installation work in 2012

In addition these delays caused the previously planned joint at KP8 of the second export cable (EC2) had to be postponed requiring 2012 mobilisation to complete.

Furthermore due to the second nearshore cable being loaded on the UR101 but not installed , this barge could not be demobilised after installing part of the array cables (winter 2011-2012, see also discussion below).

5.4. Chain Trenching and float-in installation 2012

For the nearshore campaign of 2012 a tender process for the Cable Landing Contractor led to a different contractor (xxxxx instead of xxxxx in 2011) to be appointed. This also resulted in a different grounding barge than the UR101.

5.4.1. Standby UR101 After the installation of the first nearshore export cable in the summer of 2011, the UR101 started the installation of the array cables. It is unclear how long the installation of the array cables took and how long the UR101 was on stand-by before the 2012 export cable campaign (with the second nearshore export cable on board). But in an early summary of variation orders of xxxxx reference is made to variation order 26 (VO 26) referring to UR101 actuals from July to the winter close down. In the project timetable of September 2012 the installation of the inter-array cables with the UR101 is mentioned to be 80% complete. In the timetable of October 2012 it is no longer mentioned.

Further explanation was asked by the developer and apparently not all array cables could be installed during the summer campaign of 2011, since not all cables were supplied (see also section 5.8) Stand-by of UR101 is therefore assumed to have been from December 2011 until March 2012 when preparation towards commencement of outstanding installations could commence.

Page 32: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 32/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

5.4.2. Flume Pipe installation in 2011 & 2012 Installation of the flume pipes at ‘Big Tom’ creek in 2011 was done by the support vessel of xxxxxx (shallow water barge, xxxxxx), together with the deployment of the rollers from that same barge. As mentioned in the storyboard for the Lincs nearshore installation of 17/03/2011 [7], it was the intention to recover this temporary crossing after the second cable installation was completed. Since the second nearshore export cable could not be installed in 2011 (due to closing of the consent window), we assume that the flume pipes were recovered as was foreseen in 2011.

From the presentation to MMO/NE/EA on the 9th of November 2011 [9] it is clear that the initial plan for the 2012 installation of the flume pipes was to install them approximately from the 4 – 7 May. However in the history overview it was stated that unsuccessful attempts to install the flume pipes were undertaken on the 20thand 21st of April 2012, with the eventual installation occurring on 5 June. The reason given for these changes in plan dates was the preference for flume pipes installation around the spring tides.

For the nearshore campaign 2012 other support vessels were used for the trenching operations (xxxxxxxx). As mentioned in the history overview these support vessels were contracted and managed directly by the developer.

Tractebel UK concludes that by contracting directly with the landing vessels risks of delays are transferred from the contractor to the developer.

As such when the support vessels did not complete some works to the schedule stand-by costs for other contractors can be claimed from the developer. Although some costs may be transferred to the support vessel contractor, it is most likely that s an increase in spend will occur in such a situation.

Furthermore following the consent timeout period the remobilizing of the workforce in 2012 meant a loss of delivery momentum.

Finally during operations on the 10thof June 2012 there was also a failure from the tow assist rope of the xxxxxx. It took 9 days before a new tow rope was produced. This seems however another event that should have been anticipated. This scenario however is not described in the Emergency & Contingency Plans for the inter-tidal works of 2012 [11].

5.4.3. Conclusions Compared to the event during the 2010 and 2011 cable installation campaigns, the delivery of the 2012 schedule went with little incident. However xxxxxx left site as a result of the flume pipes not being installed and had to come back at a later stage. Due to reinforcements needed to the flume pipes, installation works were delayed. Some of the Lessons learned from the similar 2011 installation will have been lost since different support vessels were contracted by the developer in 2012.

Page 33: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 33/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

5.5. Main cable installation

5.5.1. Plough-incident The main cable installation was done by simultaneously laying and burying by ploughing. During installation of Export Cable 2 (EC2), the first cable that was installed) a plough incident occurred at KP18.374.

The cause of this incident is not properly controlled cable pay-out rate during a transitional operation, where harder seabed conditions had been encountered. The plough team was reducing the vertical angle of tow wire pull on the plough, meaning a drop in plough speed. When at that specific moment the speed of feeding the cable isn’t dropped simultaneous, there is a risk of the cable getting trapped behind a skid of the plough.

Since speed and tensions both of the plough and the cable are monitored, as well as the entrance angle of the export cable at the plough’s bellmouth, the cause could be evaluated as a human error of the plough operator. This can never be fully excluded during operations and in our opinion can thus be evaluated as an incident. Similar plough incidents have already occurred on other projects as well. Note that the plough incident is also an (outstanding) CAR insurance claim.

5.5.2. Spare Export Cable Storage An ITT was issued only on the 12th October 2011 for the storage of the excess cable lengths (estimated as 3.5km), which appears rather late considering that the installation of the main cable was expected to finish a month later. On the other hand it was not until the 12th of October 2011 that the load out at xxxxx (cable supplier) was finished and thus a good estimation of the excess cable lengths could be made.

The tendering process was relative short and 2 days after ending the installation of the main export cables (18th of November 2011) the xxxx could deliver the cable to the successful bidder xxxxxxx. This fortunately made the standby time for the xxxxxx a minor cost.

The question was raised to the developer why wet storage of the cable was not considered, which is a common technique. The developer replied that since the site was completely dependent on consents this was not an option. However, the windfarm concession area could have been considered and cable storage should have been contractually set from the beginning. Even when taking into account the cable supplier’s length margins and an estimate of the minimum cable length needed (without taking into account cable snaking and with the knowledge that at the cable route alter courses the route cannot exactly be followed thus corners are cut within the cable corridor), a judgement on spare cable lengths could have been made at an earlier stage.

We believe that only in a late phase of the cable installation the storage of a spare cable or excess cable length was considered.

Page 34: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 34/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

For information, we noticed that according to [1] a special made steel reel for holding up to 400m export cable, main section, for transportation and storage was delivered by xxxxxx. We assume that this reel was used to store the 300m spare that was offloaded from the UR101 at Sunderland between 30th March and 31st March 2012 (after transloading the 300m spare from the Discoverer onto the UR101 on the 16th and 17th October 2011). In any case the reel from xxxxx wouldn’t have been sufficient for storage of the excess cable lengths.

5.5.3. Anchor trials The cable corridor which was chosen runs through the Wash and passes anchorage locations as Boston Anchorage, Kings Lynn Anchorage and Sutton Bridge &Wisbech Anchorage. At these locations vessels are allowed to anchor and wait for entering a port in the Wash area. Although originally set forward by the harbour authorities, achieving a cable burial depth of 5m between KP8 to KP20 is highly challenging to impossible. The developer opted to perform anchor trials in order to assess the expected maximum penetration of anchors being deployed. The aim was to demonstrate that a 3m deep export cable burial would suffice in order to avoid anchor damage and achieve agreement from the harbour authorities, since at that time there was a lack of consent for a 3m burial between KP8 and KP20.

It appears that the first anchor trial with the tug boat xxxxxxx (April-May 2011, facing a lot of Weather Down Time), had to be repeated by a dedicated DP2 dive support vessel (DP Reel). These trials appear to be performed at a late stage and were not indicated at the start of the project. However, as this was important not only during the installation stage, but also during the later operation and maintenance phase of these export cables transmitting the full power from the wind farm to the shore, this risk was known from the start when the cable corridor was chosen and should have been mitigated prior to contracting the export cable works.

5.5.4. Conclusions Due to the plough incident a delay of 8 days for the installation of the main export cables occurred. Also additional jointing and post burial needed to be performed. Indirectly this incident also led to another additional joint caused by a beam failure when deploying the jointed cable.

At this moment it is unclear what the impact was of the anchor trials but they were found in a change note for an amount close to 1 million pounds sterling.

Page 35: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 35/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

5.6. Jointing works and post lay burial

Jointing works and post lay burial of the export cables went rather smoothly, although some further burial works had and still have to be conducted to achieve an acceptable level of cable burial. The outstanding area is located along KP 44 (thus inside the wind farm concession area) and burial will be scheduled in 2013. The developer informed us that there is one location along the export cable route where the cable only had a 0.5m cover (chalk area) , while others mostly comprised covers or around 2-2.5m with a target that set the burial originally at 3m. If the authorities do not accept the current burial results, there is a risk of having an additional post-burial campaign along some routes. Where further cable trenching attempts would not be successful, local rock dumping by for instance a fallpipe vessel or mattress installation might be needed.

During jointing operations, there has been one incident at KP18 due to a failure of the cable lifting beam of the xxxxxx while over-boarding the cable after jointing works completion. This resulted in an additional joint (double repair joint), since during the uncontrolled deployment the minimum bending radius (MBR) of the cable was not respected.

This event is an (outstanding) insurance claim and in our opinion can be evaluated as an incident.

5.6.1. Conclusions An estimation of the cost of the burial works that are scheduled around KP 44 at the time of writing this report is indicated in the cost template of November 2012 (see section 5). Section 5 also provides more detail on the additional cost increases of the joints linked to the incidents under CAR evaluation.

Due to the beam failure an extra joint needed to be performed. Also guard vessels were needed due to the fact that burial was not immediately performed due to several delays. Some of these costs are part of the breakdown of the cost template, but could not clearly be appointed.

5.7. Cable supply by Contractor

On 19/02/2008 the contract for the supply of the cables was signed between xxxx and the developer.

The initial requirement for export cable was defined by the developer as:

• 2 x 48,000m lengths of 132kV 630mm² cable (within which any cut point between nearshore and main lay lengths to be advised if required)

• 1 x 400m length of 132kV 630mm² cable as spare • 2 x 865m length of 132kV, 1200mm²Sea Defence Crossing cable

(optionally to be factory jointed to the 630mm²lengths, a similar operation had been undertaken on the LID 33kV export cables).

Page 36: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 36/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

Due to changes in the installation methods, a different cable section to cross the Sea Defence was no longer necessary. Both export cables are of identical cross section with trefoil 132kV AC 630mm²conductors and incorporating a fibre optic bundle under single wire armour and yarn outer sheath.

Both export cables were aimed to be manufactured before the 2nd half of 2010 (according to Approval For Commitment). In January 2009 a first contract amendment set the supply dates for the export cables as follows:

• Landfall section export cable 1 & 2 and main section export cable 1: within period of 60 days commencing on the 14th of July 2010

• Main section export cable 2: within period of 60 days commencing on the 22nd September 2010

In July 2009 a second amendment was made to the contract, changing the key dates from 14/07/2010 to 03/05/2011 and from 22/07/2010 to 15/06/2011.

A third contract amendment (February 2011) changed the supply dates as follows:

• Sea Defence section export cable 1: within a 15 day period commencing on 15/03/2011

• Nearshore section export cable 1: within a 60 day period commencing on 15/04/2011

• Main section export cable1: within a 60 day period commencing on 03/05/2011 • Sea Defence section export cable 2: within a 15 day period commencing on

15/03/2011 • Nearshore section export cable 2: within a 60 day period commencing on

15/04/2011 • Main section export cable 2: within a 60 day period commencing on 15/06/2011

5.7.1. Delay of Supply During load out of main export cables 1 and 2 a cable fault was found. Visual armour damage was noticed. After root cause investigation it was reported that the armour damage was a result of the factory acceptance tests (FAT’s, [23] and [24]). After complete visual inspection of the export cable 1, it was offloaded for a factory repair. For export cable 2 it was decided to perform an offshore joint (initially this would be done by (xxxxxx).

As a result of the discovery of the faults delays occurred in the installation and associated standbys of vessels (xxxxxxxxx). Detailed events of the load out of the cables can be found in the overview in Appendix C. These delays were not only due to these cable faults, but also unavailable load out equipment which was the responsibility of xxxxxxxx.

As far as the cable faults concerned with the Quality Plan of the FAT and the sequence followed during these tests it appears not possible to notice the faults at an earlier stage before load out took place. Also a concern with the manufacturing procedures is that an earlier indication of the damage seems not possible.

Page 37: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 37/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

The Control Plan for Manufacture shows that there are no continuous checks (at 360° around the cable) on the different construction layers of the cable (where the problem had occurred) during manufacture. Only spot examinations were done. It was unclear if a representative of the developer was onsite monitoring the cable manufacturing continuously.

Furthermore the root cause of the damage is not explained in the xxxxx Technical Report on the observed cable damage. There is only an assumption by xxxxx that the AC test has accelerated the burning/melting of the cable which was already faulty. However, it was not explained why, before FAT, there was already a weak point in the bedding (or possibly the semi-conductive PE layer).

It is explained that the AC test during the FAT (even if passed as for EC2) has reached enough voltage to create an arc at the weak point and maintain the melting during the whole duration of the AC test. The question arises why for equivalent design and length, this problem had not occurred and why a system to control continuously the thickness of the different layers during the manufacture cannot be implemented.

5.7.2. Storage costs spare cable xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx

5.7.3. Conclusions The part of the installation of the export cable that was most affected by the above mentioned delays was the scope of the xxxxxxx. Timetable of load out of the cable to this barge shifted from completion on 30/05/2011 to 21/06/2012 and eventually to 09/07/2011. Actual sail off of the xxxxxx from Halden (xxxxxx) was on 05/07/2011 with only one main export cable loaded. Due to the incident, Discoverer had to return second half of September 2011 to load-out the other main export cable.

Also as a result of the cable fault and the delays, UR101 eventually left Halden with only one nearshore cable loaded. Before performing operations the second nearshore cable was spooled to the UR101 when the xxxxxxx arrived in Sunderland. Together with weather downtime another 15 days were lost for the xxxxxxx due to this transpooling.

For the UR101 also some delays were thus encountered. On the other hand in relation to the trenching operations, the UR101 could not start the installation works, since the ATV’s were not ready on site.

Concerning the cable xxxxx there were some outstanding variation orders between the developer and Nexans. These pending variations were settled with a signed agreement (addendum 4 to the contract) in December 2012. However the amount settled for is about £1.7m less than anticipated in the cost template of November 2012 (see section5), thus increasing further the project costs.

Page 38: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 38/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

6. OVERVIEW OF CLAIMS

In relation to the export cable installation the following incidents resulted in insurance claims:

• Plough incident at KP18 of 17/08/2011 • Beam failure during deployment of the joint at KP18 on 18/11/2011 • Pull-in incident nearshore east export cable (EC1) with Nessie V at KP2.2 on

18/07/2011 (cable loop) • Cable damage EC2 that occurred during FAT test and was noticed while the

cable was loaded out on 10/05/2011 (joints KP44). For the plough incident and the beam failure incident full interim payments were received of £440,000 and £588,000. The claims that were set forward towards the CAR insurer were £3.78mand £1.57m, with the costs possibly being reallocated between these two incidents.

The combined interim payments (£1,028,000) are incorporated in the cost template as part of the Jointing Works (see Appendix M).

Concerning the nearshore pull-in incident a value of £2.9m was claimed for. As explained by the developer, the insurers are not convinced that the installation method used with rollers was correct in the given situation and discussions about the final amount are still on-going. The developer informed that an amount of £520,000had been set as possible to achieve.

The EC2 cable damage claim was advised as £ xxxxm. The developer informed that based on the latest discussions with the loss adjuster a payment of xxxx is achievable. Negotiations with the cable supplier xxxxxx were also still ongoing. On 25/01/2012 Tractebel UK received a copy of the final settlement between xxxx and the developer dated from 21/12/2012.xxxxxxxxxxxxxxxxxxxxxxxxx.

In Table 5 an overview of the claims is given. As can be seen currently there is a large difference between what was claimed for and what is expected to be recovered. But negotiation with the CAR insurer is still ongoing.

The developer would also need to breakdown the claimed values in more detail, listing the contractual parties involved and support the costs with a technical background.

Table 5: Table redacted

6.1.1. Conclusions An overestimation of insurance payments is considered likely, which may result in a further cost increase. The exact amount of this increase is still to be determined, since there is not yet a definite settlement of the claims. With the available information we estimate that at least an increase of £xxxx m is to be expected (based on the expectations and the real settlement between the developer and Nexans).

Page 39: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 39/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

Furthermore all contractors have been paid except for Technip where according to the developer final account discussion are on-going and would only relate to a minor amount (estimated as £xxxxx). The developer is thus covering the amount not paid by the CAR insurer at this moment, while it should be challenged whether the contractors themselves should not bear these costs.

7. PROJECT COSTS

7.1. Breakdown indicative transfer value July 2011

Ofgem appointed Grant Thornton as financial advisers to perform an initial forensic accounting investigation to check on the completeness, accuracy and correct allocation of costs for the Lincs Wind Farm.

In its letter of 13/07/2011 to the developer, Ofgem confirmed that the indicative transfer value for the Lincs project would be set on £85.4m for the submarine cable costs, this value was confirmed by Grant Thornton to be derived as indicated in table below (Table 6).Reference is made to “Draft report to Ofgem on the offshore transmission second transition tender round – Ex ante cost review of LincsWind Farm transmission assets”[37].

Table 6: Table Redacted

7.2. Breakdown status November 2012

The cost template received from the developer updated for January 2013 indicates a total value of £ xxxxxx for the submarine cable installation. This is an increase of £ xxx m since the ITV was set for the project. An overview of the cost increases is set out in Table 7.

Page 40: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 40/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

Table 7: Table Redacted

Page 41: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 41/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

7.3. Examples of variation orders

7.4. Conclusions

As indicated in Table 7 Tractebel UK concludes that the HDD works in 2010 and the 2012 shore end works are costs that are not economically and efficiently incurred . At a high level these costs equate already to more than £ xx m of the project’s cable cost increases. This value was derived by summing the xxxx 2010 costs equal to £xxxxx and the 2012 shore end works equal to £ xxxxx

In the pre-development stage of the project a detailed project risk assessment should have been conducted and contingency plans should have been developed. This may have led to different installation methods being chosen and/or mitigations set in place. The 2010 xxxxx works which was the attempted HDD approach did not contribute to the final cable installation and the 2012 works would have remained within the original 2011 planning. Therefore Tractebel UK concludes that these costs are not economically and efficiently incurred. Tractebel UK also concludes that further cost increases are not supported by sufficient documentation and the developer should be further challenged by Ofgem to provide further technical information to support the cost increases which were listed.

The negotiated xxxx contract, which was based on a cost plus base instead of a lump sum did also not include the total original xxx scope for the cable installation (part of the scope went to xxxx ) and led to additional cost increases. Where a lump sum based contract ensures that the contractor is committing to an upfront fixed price and thus stands in for a number of risks, a cost plus based contract does not include this type of contractor’s commitment and the developer will face cost increases each time delays out of the developer’s control are arising

8. GENERAL CONCLUSIONS

The analysis covers documentation provided to the consultant between 21 December and 28 January 2013, updates provided on request during February and March, two meeting held with Centrica and Ofgem in March and a telephone conversation with Natural England regarding the consent processes. During the review there was a constant communication and data-exchange between the Consultant, Ofgem and the developer.

Based on the documentation that was available, following conclusions can be drawn.

Page 42: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 42/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

8.1. Connection point

The route selected to link the 3 wind farms Lincs, Race Bank and Docking Shoal to land and connect to the existing grid, was the shortest total route towards the substation at Walpole.

Considering:

• offshore cable installation as a critical step, • overall project risk assessment, • consideration of the Lincs Wind Farm project as a stand-alone project, • time frame scheduled for being operational, • previous experience with already installed offshore wind farms,

another cable route could possibly have been selected for the Lincs Wind Farm.

8.2. Project organisation

• Concerning risk identification and mitigation or contingency plans based on the information received and the documents that were reviewed, it seems that initially these were not fully in place and only developed during the project. Nevertheless in the documents relating to the end of the installation works it also seemed that only limited events were considered.

• Concerning the decision making process for project changes, it is clear and it was confirmed by the developer that throughout the project changes notes have evaluated from simple documents to more extensive documents in the end.

• For the management of interfaces according to the developer regularly interface meetings were held between the participating contractors. The documents that were made available (just as the documents received concerning above topics) related to later stages of the project.

All together it seems that good project management is currently in place, but it is also clear that there was an evolution of the management during the project. An overall impression is that during the project a lot of decisions had to be and were made under time pressure and alternatives were often not examined thoroughly.

8.3. Installation methods and consents

• It appears that the consents had been very restrictive at the start of the works and in addition there were shortcomings in the performed pre-investigation surveys. It is clear that with more comprehension of the site conditions some events would have been better anticipated and mitigated.

• Execution of the HDD, without a detailed soil survey to the depth of drilling constituted a project risk. When taking that risk alternative installation methods should have been prepared and discussed with the licensing Authorities up front. The initial selection was drilling from offshore to onshore plus the drilling equipment was located on two barges. In both cases these choices increase the installation costs

Page 43: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 43/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

• As a consequence to the unsuccessful HDD campaign in 2010, a new methodology and thus further engineering needed to be performed which led to a cost increase.

• Next to the unsuccessful HDD campaign in 2010, xxxxxxxx entered administration in the first quarter of 2011 and a new contract for the installation of the export cables (and others) needed to be signed. In addition this contract had a cost plus basis instead of a lump sum basis. Although this occurred in the first quarter of 2011 it appears however that this impact was not included in the indicative transfer value which was set in July 2011.

• The installation methodology was reviewed with chain trenching being the eventual method selected (requiring modifications to the consent). The chain trenching was successful but for the pull-in process with the use of rollers another alternative (float-in, a typical landfall cable pull-in technique) was eventually to be used.

• Due to the time lost during operations, only one nearshore cable could be installed in 2011. Hence additional installation works were needed in 2012.

• Compared to previous works, the impact of the 2012 installation works itself were minimal. However it is noted that lessons learnt from the 2011 installation may have been lost since different support vessels and contractors were contracted by the developer in 2012.

• For the main cable installation there was a plough incident, leading to delays and additional jointing and post burial works. There are still some burial works to be performed. This of course also led to cost increases.

• Next to the cable installation there were also some issues with the supply of the cable which have caused delays of the project. Additional costs due to the cable faults were the subject for an agreement between the developer and the cable supplier.

8.4. Outstanding claims

Taken into account the outstanding amounts in the cost template that are indicated as expected to be received, it seems that an overestimation of insurance payments is considered likely and a cost increase is to be expected. The exact amount of this increase is still to be determined, since there is not yet a definite settlement of the claims.

xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx

8.5. Cost evaluation

The original July 2011 budget for the work was £xxxx and during the period of builds the cost increased by £ xxx

More documentation and analysis is needed to assess the full xxxx overrun but on a high level more than £xxx of the increase is considered as costs that are not economically and efficiently incurred . In addition the balance of the pending insurance claims should be further challenged, since the developer currently risks bearing over £ m.

Page 44: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 44/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

9. RECOMMENDATIONS

The review is based on

• The information available in the data room, • A conversation with Natural England facilitated by the developer and

Ofgem • Later information supplied by the developer and Ofgem.

Appendix N gives an overview of the documents that were consulted in the data room.

The available documentation is not complete. To further evaluate the cost increase since July 2011 general documents demonstrating the situation at certain incidents (for instance daily progress reports) as well as documents directly related to the cost templates (variation orders etc.) are missing.

To completely understand each cost increase in detail and to be able to evaluate whether or not specific costs can be justified, it is highly recommended to go into more detail with the developer.

Page 45: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 45/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

10. REFERENCES

1. Installation / handling parameters 630mm² export cables, Nexans, 12/10/2010.

2. Lincs Landfall Options CREL NE meeting 051010 TO USE_LINCS.ppt, Centrica, 05/10/2010

3. Lincs Subsea Export Cables - Preliminary Route Engineering Report, Centrica, 28/09/2010

4. Food And Environmental Protection Act 1985: Part II (As amended) – Deposits in the sea in connection with marine constructions works, 1 January 2009 – Licence 33574/08/0

5. Coast Protection Act 1949: section 34 – Application by Centrica ( Lincs) Ltd installation of export power cable for Lincs Offshore wind farm, 21 October 2008, 33574/08/0/CON

6. Lincs HDD Works Meeting Minutes 18 Aug 10 - FINAL_LINCS 7. Storyboard – crossing inter-tidal area and saltmarshes, 17/03/2011,

Centrica 8. Natural England feedback on Lincs cable one installation works to

inform cable two installation methodologies 9. Storyboard for Planned Lincs Export Western Cable Nearshore

Operations 2012, Centrica, 09/11/2011 10. Lincs offshore wind farm export cable nearshore pull-in, Longitude

Engineering, 05/04/2011 11. Lincs Export Cables Inter-Tidal Works: Emergency & Contingency

Plans, Centrica, 28/11/2011 12. Controlling Changes, procedure, Centrica, 27/04/2012 13. Controlling Changes, flowchart, Centrica, 18/09/2012 14. Mitigation in the event of HDD breakout, Siemens, 04/04/12 (as built) 15. Geophysical Survey For Proposed Lincs Offshore Wind Farm, EMU

Ltd, 05/2005 16. Geophysical Investigations at the Proposed Race Bank & Docking

Shoal Wind Farm Sites with associated cable route corridors – Section 4: Greater Wash area cable route survey, EMU Ltd, 05/2007

17. Interim Report 1: Lincs Offshore Wind Farm (Saltmarsh and Landfall Sections), Harrison Geotechnical Engineering, 08/2008

18. Acoustic Surveys For the Proposed Lincs Offshore Wind Farm Sites 19. Geotechnical report LINCS wind farm export cable route survey

laboratory and in situ data final report, Fugro, 03/2009 20. Geotechnical Design Report, Ramboll Wind, 09/2009 21. Export Route sediment transport study, HR Wallingford, 03/2010 22. HDD Works – Trafficability Assessment, Subocean, 10/2010 23. Lincs Export Cables – Technical note, Centrica (LN-E-EN-020-0117-

000000-008), 20/07/2011 24. Technical Report on the observed cable damage during load out of

Lincs Export Cable 1 and 2, Nexans, 16/04/2012 25. Inspection and test plan – export cables main and near shore section 1

and 2, Nexans, 15/10/2010 26. Inspection and test plan – export cables sea defence crossing section 1

and 2, Nexans, 03/02/2011 27. Inspection and test plan, fibre optical element – export cables,

Nexans, 20/05/2010

Page 46: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 46/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

28. Factory acceptance Test Procedure – Export Cable 1, Nexans, 19/02/2010

29. Factory acceptance Test Procedure – Export Cable 2, Nexans, 16/12/2010

30. Factory acceptance Test Procedure – Export Cables – Sea Defence Crossing Section 1&2, Nexans, 11/02/2011

31. Factory acceptance Test Report – Export Cable 1, Nexans, 24/11/2010

32. Factory acceptance Test Report – Export Cable 2, Nexans, 07/01/2011

33. Factory acceptance Test Report –Sea Defence Crossing Cable, Nexans, 09/09/2011

34. Installation of the Lincs Offshore wind Farm Subsea Export Cables – A Brief History, Centrica, 17/09/2012

35. Lincs Subsea Export Cables – Preliminary Route Engineering Report, Centrica, 28/09/2010

36. Cable route alternatives Study for Lincs, Race Bank and Docking Shoal Offshore Wind Farm developments, RPS Energy, 22/05/2007

37. Draft report to Ofgem on the offshore transmission second transition tender round – Ex ante cost review of LincsWind Farm transmission assets

38. Contract for Offshore Installation of Export, Collector and Array Cables for Lincs Offshore Wind Farm, between Lincs Wind Farm Limited and Subocean Limited, 22/04/2010

39. Management of Interfaces on Renewable Energy Projects – Strategy Document, Centrica, 01/05/2012

40. Managing Interfaces, Centrica, procedure, Centrica, 15/11/2012 41. Managing Interfaces, flowchart, Centrica, 15/11/2012 42. Centrica Round 2 Offshore Wind Farm (Lincs, Docking Shoal, Race

Bank) – A review of export cable installation methodology, techniques and tools, RES/AMEC, 16/08/2006

43. Desk top study Centrica R2 offshore wind farms construction methodology review for submarine cable installation at proposed shore end landing sites, Caldwell Marine International, 27/02/2003

44. Environmental Statement, Volume One: Offshore, RPS Group Plc, January 2007

45. Review of Connection Options for Lincs, Docking Shoal and Race Bank Wind Farms, Econnect Consulting

46. Electrical System Design Studies, Mott MacDonald, 3/02/2006 47. Transmission System Losses Assessment, Mott MacDonald,

21/04/2006 48. Wisbech Seabed Movement Study, HR Wallingford, 11/05/2011 49. Export route sediment transport study, HR Wallingford, January 2010 50. Wisbech channel variation, AMEC

Page 47: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 47/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval

11. APPENDICES – ALL APPPENDICES REDACTED

Page 48: Tractbele report version 7 - Ofgem...Tractebel UK concludes that the lack of wareness of the a nearshore soil conditions in the saltmarsh was a contributing factor to the failure of

RA13035_Ofgem Lincs Cable Installation Cost Review_v8.0 48/48

This

doc

umen

t is

the

pro

pert

y of

Tra

cteb

el U

K En

gine

erin

g S.

A. A

ny d

uplic

atio

n or

tra

nsm

issi

on t

o th

ird p

artie

s is

for

bidd

en w

ithou

t pr

ior

writ

ten

appr

oval