the yorkshire and humber (ccs cross country pipeline
TRANSCRIPT
.
DO
CU
ME
NT
7.6
Construction Report The Yorkshire and Humber (CCS Cross Country Pipeline) Development Consent Order Under Regulation 5(2)(q) of the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009
June 2014 Application Reference: EN070001
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report i
The Yorkshire and Humber CCS Cross Country Pipeline
Contents
1 Introduction 1 1.1 National Grid Carbon 1 1.2 The Project 1 1.3 Purpose of this Report 3
2 Construction Overview 5 2.1 Contract Strategy 5 2.2 Detailed Design 6 2.3 Design Standards 8 2.4 Safety in Design 8
Control of Major Accident Hazards 10 Construction Design and Management 10
2.5 Limits of Deviation 11 Horizontal Limits of Deviation 11 Vertical Limits of Deviation 13 Land Drainage Areas 13 Additional Temporary Land Take 13 Above Ground Installations 17 Accesses to the Public Highway 17
2.6 Pipeline Route Description 18 White Rose to Camblesforth 18 Camblesforth to Tollingham 19 Tollingham to Dalton 20 Dalton to Skerne 21 Skerne to Barmston Pumping Station 21
2.7 Above Ground Installations Description 22 Drax PIG Trap AGI (Work No. 1A) 22 Block Valve Sites 23 Camblesforth Multi-junction (Work No. 4A) 23
2.8 Barmston Pumping Station Description 24
3 Construction of Pipelines 25 3.1 General Pipeline Construction Methodology 25
Background 25 Pre-construction Works 27 Temporary Construction Compounds 27 Working Width Preparation 28 Fencing 29 Topsoil Stripping 30 Temporary Access Roads 30 Pipe Delivery, Stringing and Bending 31 Welding, Non-destructive Testing and coating 32 Trench Excavation 32 Lower and Lay 33
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report ii
The Yorkshire and Humber CCS Cross Country Pipeline
Backfilling 33 Post Construction Drainage 34 Reinstatement 34 Integrity Testing and Inspection 35 Pipeline Markers 35 Types of Marker Posts 36
3.2 Special Crossings 37 Open Cut Crossings 37 Trenchless Crossings 38
3.3 Depths of Cover 39 Cross Country Pipelines 39 Highways 39 Third Party Services 39 Watercourses – Main Rivers 40 Ordinary Watercourses 40 Rail Crossings 40
3.4 Duration of Crossings 41 3.5 Pipeline Testing Procedure 41 3.6 Commissioning 42 3.7 Condition Monitoring 43
Corrosion Protection 43 In-line Inspection 44
3.8 Programme of Pipeline Construction 44
4 Constructing Pipeline Installations 45 4.1 Construction of Above Ground Installations 45
Phasing of Multi-junction Construction 45 Temporary Construction Compound 46 AGI Access for Construction 46 AGI Construction Process 47 Programme 47
4.2 Constructing Barmston Pumping Station 48 Phasing of Pumping Station Construction 48 Temporary construction compound 49 Access for Construction 49 Construction Process 49 High Voltage Electricity Connection 52 Programme 52
5 Landfall Construction 53 5.1 Introduction 53 5.2 Landfall Temporary Working Area 53 5.3 Design Standards 54 5.4 Geology 54 5.5 Tunnel Option 56
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report iii
The Yorkshire and Humber CCS Cross Country Pipeline
Drive Shaft Installation 56 Tunnelling 57 Pipe Installation 57 Reception Shaft and Tie In 58 Spoil 59
5.6 Horizontal Directional Drill Option 60 HDD Bore 60 Drilling Compound Installation 61 Pipe Installation 61 Reception Pit and Tie In 61 Spoil 61 Construction Access to the Beach 62 Third Party Services 62 HDD Programme 62
5.7 Testing 63
6 References 64
7 Glossary of Terms 67
Appendix A – Main Crossings 71
Appendix B – Special Crossing Methods 78
Appendix C – Consents Management Strategy 86
Figures 3.1 – 3.11 Scheme Layout 98
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report iv
The Yorkshire and Humber CCS Cross Country Pipeline
ABBREVIATIONS
A645 A Class Road
AGI Above ground installation
AOD Above Ordnance Datum
B1248 B Class Road
BGS British Geological Survey
BH Borehole
BSI British Standards Institution
c. Circa / approximately
CCP Carbon Capture Plant
CCS Carbon Capture and Storage
CDM Construction (Design and Management) Regulations
CLX Canal Crossing
CO2 Carbon Dioxide
COMAH Control of Major Accident Hazards Regulations
CP Cathodic Protection
CIPS Close Interval Potential Surveys
DC Direct Current
DCO Development Consent Order
DEFRA Department of Environment Fisheries and Rural Affairs
DX Ditch Crossing
EA Environment Agency
eg. For example
EIA Environmental Impact Assessment
EMP Environmental Management Plan
EPCM Engineering Procurement Construction and Management Contract
ERYC East Riding of Yorkshire Council
ES Environmental Statement
etc Etcetera (and so on)
FBE Fusion Bonded Epoxy coating
FEED Front End Engineering Design
ha Hectares
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report v
The Yorkshire and Humber CCS Cross Country Pipeline
HDD Horizontal Directional Drill
HDPE High Density Polyethylene
HGV Heavy Goods Vehicle
HSE Health and Safety Executive
IDB Internal Drainage Board
ie Such as
ILI In Line Inspection
IP Intersection Point (where pipeline route changes direction)
km Kilometres
kV Kilovolts
LLFA Lead Local Flood Authority
LoD Limits of Deviation
LWS Local Wildlife Site
m Metres
MAHP Major Accident Hazard Pipelines
MAPD Major Accident Prevention Document
MDPE Medium Density Polyethylene
MHWM Mean High Water Mark
MLWM Mean Low Water Mark
mm Millimetres
MMO Marine Management Organisation
mt Million Tonnes
NGR Ordnance Survey National Grid Reference
No. Number
NPPF National Planning Policy Framework
NTS National Transmission System
NYCC North Yorkshire County Council
OS Ordnance Survey
PIG Pipeline Internal Gauge / Pipeline Inspection Gauge
PINs Planning Inspectorate
PSR Pipeline Safety Regulations
RDX Road Crossing
Ref Reference
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report vi
The Yorkshire and Humber CCS Cross Country Pipeline
RIGS Regionally Important Geological and Geomorphological Sites (Geodiversity Site)
RLX Railway Crossing
RVX River Crossing
SSSI Site of Special Scientific Interest
SUDS Sustainable (Urban) Drainage System
TBC To Be Confirmed
TCA Temporary Construction Area
TBM Tunnel Boring Machine
TPO Tree Preservation Order
UK United Kingdom
UXO Unexploded Ordnance
UXB Unexploded Bomb
VSD Variable Speed Drive
WFD Water Framework Directive
YWT Yorkshire Wildlife Trust
% Percent
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 1
The Yorkshire and Humber CCS Cross Country Pipeline
1.1 NATIONAL GRID CARBON
1.1.1 National Grid plc owns and operates the national high-pressure gas transmission pipeline network in the UK and operates the national electricity grid in the UK. National Grid Carbon Limited (referred to in this report as “National Grid”) is a non-regulated independent subsidiary of National Grid plc, created to develop Carbon Dioxide transportation and storage infrastructure in the UK. National Grid will be drawing on its expertise in building and running safe and effective pipelines to develop Carbon Capture and Storage (CCS) Projects.
1.2 THE PROJECT
1.2.1 The Project is a Carbon Dioxide transportation and storage system to support the provision of CCS technology in the Yorkshire and Humber Region. The Project, in its entirety, is known as The Yorkshire and Humber CCS Transportation and Storage Project (“the Project”). It will comprise the construction of a Cross Country Pipeline and sub-sea pipeline for transporting Carbon Dioxide captured from power projects in the region to a permanent geological storage site beneath the North Sea. The Project includes both onshore and offshore elements which are subject to separate consenting regimes (the “Onshore Scheme” and the “Offshore Scheme”).
1.2.2 The onshore elements of the Project are collectively termed the Yorkshire and Humber CCS Cross Country Pipeline (shortened to the “Onshore Scheme”) and are proposed to comprise the construction of a buried welded steel Cross Country Pipeline and associated infrastructure including Pipeline Internal Gauge (PIG) Traps, a multi-junction, three block valves a pumping station (collectively termed “Above Ground Installations” or “AGIs”) and any necessary interconnecting local pipelines and associated works. These are illustrated in the high level schematic below (Figure 1).
1.2.3 As the length of the proposed Cross Country Pipeline will exceed 16.093km it constitutes a nationally significant infrastructure project (“NSIP”) pursuant to the Planning Act 2008. This requires an application to be made to the Planning Inspectorate (“PINs”) for a Development Consent Order (“DCO”).
1 Introduction
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 2
The Yorkshire and Humber CCS Cross Country Pipeline
1.2.4 The Cross Country Pipeline will have an external diameter of up to 610mm and will be sized to accommodate up to 17 million tonnes (mt) of Carbon Dioxide emissions per year. The multi-junction will enable the connection of multiple pipelines from regional Carbon Dioxide emitters to the Project. At present one installation for the capture of Carbon Dioxide streams, the White Rose CCS Project adjacent to Drax Power Station at Selby, being promoted by Capture Power Limited, will connect into the Cross Country Pipeline. An interconnecting pipeline between the White Rose CCS Project and the multi-junction will form part of the DCO application for the Onshore Scheme.
1.2.5 Pipeline Internal Gauge (PIG) Traps will be sited at the start and end of each pipeline to launch PIGs. These facilities are required to support the periodic inspection of pipelines as part of National Grid’s planned pipeline inspection and maintenance programme. Block Valves will be required at regular intervals along the length of the pipeline to allow sections of the pipeline to be isolated for safety or maintenance, and a pumping station is to be constructed near to the coast to re-pressurise the Carbon Dioxide before it is transported offshore.
Figure 1 Schematic of the Onshore Scheme
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 3
The Yorkshire and Humber CCS Cross Country Pipeline
1.2.6 The offshore elements of the Project are collectively termed the Yorkshire and Humber CCS Sub-sea Pipeline and Geological Storage Site (shortened to the “Offshore Scheme”) and are proposed to comprise the construction of a 90km sub-sea pipeline to a geological storage site. These are subject to a separate consenting regime requiring authorisation by the Petroleum Act 1998 and the Energy Act 2008 respectively.
1.2.7 The sub-sea pipeline will have an external diameter of up to 610mm and will be sized to accommodate up to 17mt Carbon Dioxide emissions per year. The geological storage site will comprise the permanent storage of captured Carbon Dioxide in a saline aquifer located approximately 1000m below the seabed. National Grid has secured an agreement to lease area 5/42 in the southern North Sea from the Crown Estate for the purpose of geological storage of Carbon Dioxide. The capacity of the storage site is expected to accommodate at least 200mt of captured Carbon Dioxide. Once this site has reached capacity further storage sites would be identified and utilised.
1.2.8 The Onshore and Offshore Schemes will be joined at the Mean Low Water Mark using appropriate landfall techniques; this is also the juncture of the onshore and offshore consenting regimes.
1.3 PURPOSE OF THIS REPORT
1.3.1 National Grid is making an application for a Development Consent Order (DCO) to construct and operate the Onshore Scheme, a Cross Country Pipeline and associated infrastructure which includes the following elements:
• Pipeline up to 324mm external diameter from White Rose CCS Project to Drax PIG Trap (approximately 0.25km length)
• Drax PIG Trap Above Ground Installation (AGI); • Connecting pipeline up to 324mm external diameter from Drax PIG
Trap AGI to Camblesforth Multi-junction (approximately 5.6km length);
• Camblesforth Multi-junction installation; • Yorkshire and Humber CCS Cross Country Pipeline up to 610mm
external diameter (approximately 67km length); • 3 Block Valve AGIs at Tollingham, Dalton & Skerne; • Barmston Pumping Station; • Offshore pipeline up to 610mm external diameter, Barmston Pumping
Station to landfall at mean low water mark (approximately 1km). • Temporary construction compounds/ offices; • Temporary pipe storage yards;
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 4
The Yorkshire and Humber CCS Cross Country Pipeline
• Temporary accesses and laydown/works areas; • Permanent accesses for above ground installations; • Land drainage.
1.3.2 The purpose of this report is to describe what the development is and how it will be delivered. This report provides an overview of how the Onshore Scheme, including the landfall for the sub-sea pipeline, will be constructed.
1.3.3 This document forms part of a suite of DCO application documents and should be read in conjunction with those drawings and documents referenced in this document.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 5
The Yorkshire and Humber CCS Cross Country Pipeline
2.1 CONTRACT STRATEGY
2.1.1 The Construction Contract Strategy has yet to be finalised however at this stage it is anticipated that the following strategy would be adopted.
2.1.2 National Grid would appoint up to four Engineering Procurement Construction and Management (EPCM) contractors to provide and manage the detailed design, procurement, construction and commissioning of the Onshore Scheme. This strategy assumes the pipeline and certain AGIs would be constructed using two EPCM contractors:
• Contract 1 to include Drax PIG Trap AGI, approximately 5.6km of connecting pipeline up to 324mm external diameter, Camblesforth Multi-junction, approximately 31km of cross country pipeline up to 610mm external diameter and Tollingham Block Valve;
• Contract 2 to include approximately 36km of cross country pipeline up to 610mm external diameter and Dalton and Skerne Block Valves;
2.1.3 The Pumping Station would be constructed by a separate EPCM contractor; and the landfall for the sub-sea pipeline would be part of the construction contract for the Offshore Scheme.
2.1.4 Following the appointment of the EPCM contractors, design and construction of the Onshore Scheme would take place in phases over a 4 year period. The main construction tasks and the indicative construction programme are set out below.
Year 1 Year 2 Year 3 Year 4 Detailed design
Pipeline construction
AGI construction
Pumping Station construction
Landfall construction
Commissioning
2 Construction Overview
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 6
The Yorkshire and Humber CCS Cross Country Pipeline
2.2 DETAILED DESIGN
2.2.1 Prior to Contractor appointment Front End Engineering Design (FEED) work would be completed. To inform the DCO to an appropriate level of detail, certain FEED work has already been completed. This has comprised the completion of desk based studies supplemented by engineering surveys (e.g. borehole surveys) to identify (following consultation) an alignment for the proposed pipelines. This process has also been informed by the outcome of environmental surveys. In addition site selection studies have been conducted and consulted on to identify the preferred locations for above ground installations. Engineering general arrangement drawings, elevations and profiles have been prepared for the selected Drax PIG Trap, Block Valves and Multi-junction sites together with planting proposals for approval through the DCO.
2.2.2 The proposed Camblesforth Multi-junction has been designed to accommodate up to four incoming pipeline connections (4 PIG Traps) and one outgoing connection (1 PIG Trap) into the Cross Country Pipeline. The general arrangement drawings, elevations and profiles prepared for the DCO show an initial design for two PIG Traps to accommodate an inlet PIG Trap for the pipeline connection from the White Rose CCS Project and an outlet PIG Trap to the Cross Country Pipeline; and “Area B”. Area B, as defined within Camblesforth Multi-junction Planning Arrangement Drawing No. 10-2574-GA-01-0316 (Document Reference 2.25) and draft DCO Schedule 3, has not yet been designed in detail as the capacity and rate at which the area is built out will depend on when third party connectors come forward and the direction from which they enter the facility. Capacity has been provided for three PIG Traps within Area B of the Multi-junction. The parameters of Area B are set out within the draft DCO and secured through a Requirement (draft DCO Schedule 3, Requirement 6).
2.2.3 In the case of the proposed Barmston Pumping Station, conceptual designs have been included in the DCO application for information and a parameter plan showing the maximum dimensions of buildings and apparatus has been submitted for approval. A Design and Access Statement (DAS) (Document Reference 7.3) has been submitted with the draft DCO providing guiding principles (including an indication of materials) and setting the parameters that will be used for the detailed design, the approval of which will be subject to a Requirement under the DCO (draft DCO Schedule 3, Requirement 5).
2.2.4 Further FEED design work is programmed for 2014/15 to fulfil DCO requirements; the compilation of contract documentation; and the procurement of equipment and materials.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 7
The Yorkshire and Humber CCS Cross Country Pipeline
2.2.5 The Onshore Scheme would be subject to specific requirements set out in the DCO and certain statutory consents and agreements; some of which would be provided through the DCO; and others to be obtained separately from the relevant authority or organisation. Appendix C Consents Management Strategy, sets out the consents required for the Project and the proposed approach to obtaining those consents.
2.2.6 During the detailed design phase, the contractors will produce Method Statements, as required for the preparation of necessary further consents and licence applications for example for crossings including watercourses, roads, railways, gas pipelines other services. In addition mitigation measures, through written schemes of investigation will be developed for areas with archaeological potential; and appropriate licences and management strategies for ecologically sensitive areas and protected species. Methodologies will be developed by the appointed contractors in consultation with National Grid and approved by the appropriate consenting authority in accordance with Requirements specified in the DCO.
2.2.7 The appointed contractors will also be responsible for the production of a Project specific Environmental Management Plan (EMP) to control and monitor environmental performance throughout the project. National Grid’s proposed Code of Construction Practice (CoCP) (Document Ref. 7.5), submitted as part of the DCO application material will form the basis of the Contractors’ EMP along with the Schedule of Environmental Commitments (Chapter 16 of the Environmental Statement, Document Reference 6.16).
2.2.8 Specific Environmental Management Strategies will be developed for Pollution Control, Waste Management, Water Management, Emergency Response and Traffic Management. The entire workforce will receive training about relevant environmental issues, including pollution control, before commencing work on site.
2.2.9 The contractors will also be responsible for the production and implementation of the Project Health and Safety Plan in accordance with Construction (Design and Management) Regulations 2007 (CDM). All personnel working on site will be required to have completed Cross Country Pipelines Health Safety & Environment training (known as the Safety Passport) as well as project specific induction training.
2.2.10 National Grid and the contractor(s) will employ suitably qualified personnel to monitor the design and construction of the pipeline and above ground installations, ensuring compliance with the Method Statements / methodologies and appropriate management of safety, quality and environmental concerns. Additionally National Grid will employ Agricultural
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 8
The Yorkshire and Humber CCS Cross Country Pipeline
Liaison Officers to ensure landowners are kept fully informed before, during and post–construction.
2.2.11 For the Offshore Scheme, a conceptual design has been completed to date. The FEED study and nearshore surveys will be carried out during 2014/15 to inform the technique to be employed for construction. The FEED for the Offshore Scheme will also be tasked with finalising the construction technique for the landfall, although the proposed DCO Order Limits (set to Low Mean Water Mark) set the parameters for construction activity in this area.
2.3 DESIGN STANDARDS
2.3.1 The design, construction and operation and maintenance of the proposed onshore pipelines will be in accordance with the approved British Standards Institution (BSI) published document PD 8010:Part 1:2004 Code of Practice for Pipelines – Steel Pipelines on Land.
2.3.2 The above ground installations will be designed in accordance with PD 8010:Part 1 and the American Society of Mechanical Engineers piping code ASME B31.3 on Process Piping.
2.4 SAFETY IN DESIGN
2.4.1 The Pipelines Safety Regulations (PSR) 1996 applies to all pipelines in Great Britain (England, Scotland and Wales), and to all pipelines in territorial waters and the UK Continental Shelf. The regulations provide general duties for the safe management of all pipelines in the UK, relating to design, construction, operation, maintenance and decommissioning. The guide to PSR (HSE 1996) includes the statement ‘…the Regulations, by ensuring that a pipeline is designed, constructed and operated safely, provide a means of securing pipeline integrity, thereby reducing risks to the environment.’
2.4.2 In addition, PSR specifically defines Major Accident Hazard Pipelines (MAHPs), which are pipelines that convey dangerous fluids and for which the consequences of failure would present a major accident resulting in significant danger to people. Additional duties are defined for these pipelines, including notifications, preparation of a Major Accident Prevention Document (MAPD), development of emergency procedures, and arrangements and the provision of information to Local Authorities for inclusion in the Emergency Response Plan. Liquid (dense phase) Carbon Dioxide is not classified as a dangerous fluid in PSR but National Grid has taken an appropriate precautionary approach and elected to design and operate the pipeline as if Carbon Dioxide were classed as a dangerous
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 9
The Yorkshire and Humber CCS Cross Country Pipeline
fluid. The primary requirements for compliance with UK legislation is the application of UK codes and standards. Code of Practice PD8010 Part 1 as applied to Carbon Dioxide pipelines addresses the system requirements for MAHPs.
2.4.3 Section 4 of the Safety Statement (Document Reference 6.4.7) addresses the likelihood of unplanned releases from the pipelines or at the AGIs. The Safety Statement concludes that the proposed pipelines of up to 324mm and up to 610mm diameter and AGIs are designed to avoid failures (for example from leaks or ruptures) and such events are very unlikely for the 324mm pipeline and extremely unlikely for the thicker 610mm diameter pipeline and on the AGIs associated with the pipeline system proposed. The proposed pipelines will be designed in accordance with recognised codes and the prevailing legislation to ensure that unplanned releases due to leaks and ruptures are very unlikely to occur. The principal requirement in assuring safety of the public and avoiding damage to property or the environment is to reduce the potential for a major pipeline accident to occur so the design developed by National Grid ensures that the probability of failure due to any cause is very unlikely. By ensuring pipeline integrity it also reduces the risks to the environment.
2.4.4 The proposed pipelines are routed predominantly in agricultural land and avoid centres of population. The proposed routes also minimise the number of major crossings (combined crossings are used where practicable) and avoid areas liable to landslip, subsidence or other instability, as far as practicable.
2.4.5 The proposed pipelines will be of all welded construction to ensure a high integrity system and to minimise the likelihood of any fugitive emissions, i.e.
• The proposed pipelines will be buried out of sight (minimum 1.2 metres down) to minimise the likelihood of damage by unauthorised excavation work in close vicinity to the pipeline;
• Pipe and other materials will be inspected during its manufacture and at all stages of construction;
• Every weld joining each section of pipe is examined; • Following welding and weld inspection of the pipe joints it will be
necessary to complete the pipe coating at the joint areas to prevent external corrosion;
• The pipelines will be pressure tested with water to a pressure above the maximum operating pressure following construction to check the pipes integrity; and
• Pipeline markers are provided along the routes of the pipelines to highlight their presence.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 10
The Yorkshire and Humber CCS Cross Country Pipeline
2.4.6 Pipelines are protected against external corrosion through the application of corrosion protection coatings, and the utilisation of Cathodic Protection which provides protection in the event of coating damage. National Grid has extensive experience in the rigorous and successful management of external corrosion on the natural gas pipeline system. The systems and procedures applied to the natural gas pipeline system will be applied to the Onshore Scheme.
2.4.7 The pipelines and AGIs will be inspected and maintained in accordance with best practice, which will typically include the following activities:
• The proposed pipelines will be monitored around the clock, 365 days a year, by a fully staffed Control Room;
• Aerial or walking surveillance of the pipeline routes to check for activities taking place close to the pipelines;
• The proposed pipelines and AGIs will be subject to planned maintenance to ensure their continued reliability;
• Scheduled internal inspection (referred to as ‘ILI’ or ‘pigging’) to check for corrosion and any damage present;
• Scheduled communication with landowners, local authorities and the emergency services in the area; and
• Planned pipeline awareness programmes involving landowners, occupiers, communities, utilities, local authorities and the emergency services, which is key to preventing damage and ensuring safety.
Control of Major Accident Hazards
2.4.8 Carbon Dioxide is not classed as a dangerous substance, under Schedule 1 of the Control of Major Accident Hazards (COMAH) Regulations 1999 (as amended 2005); the COMAH Regulations therefore do not apply.
Construction Design and Management
2.4.9 The main legislation for construction safety (along with design management issues) in Great Britain is the Construction (Design and Management) (CDM) Regulations 2007 (as amended). CDM covers the design of the pipeline and above ground installations in so far as the design should take into account the safety of those carrying out the construction and any subsequent maintenance work. The CDM Regulations also cover the safety management of those involved in the construction during the construction stage. The Pipeline Safety Regulation 1996 (PSR) also place duties on the design, structural integrity and operation of the pipeline to ensure it safe operation.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 11
The Yorkshire and Humber CCS Cross Country Pipeline
2.4.10 The CDM Regulations apply offshore only to those structures that are not already covered by PSR and the Offshore Installations (Safety Case) Regulations. They do not therefore apply to offshore pipelines. The extent of applicability of the CDM Regulations to the offshore pipeline construction and design is limited to the landfall section. (See Section 5 Landfall Construction).
2.5 LIMITS OF DEVIATION
Horizontal Limits of Deviation
2.5.1 For the purposes of the DCO application and to accommodate unexpected issues in pipeline routeing once the Project is being constructed, a tolerance is being applied for, either side of the proposed pipeline route. The extent of the tolerance is known as the ‘limits of deviation’ or LoD. These provisions allow the pipeline to be routed anywhere typically within a c.100m wide LoD.
2.5.2 For a 610mm external diameter pipeline the normal working width applied by National Grid (i.e. area within which construction activities to lay the pipeline will be undertaken) is 36m. This comprises 15m on the left side of the pipe trench (to accommodate the storage of trench material/subsoil) and 21m on the right (to accommodate topsoil storage, running track, pipe welding and laying activities) working from Drax towards the coast. Within this area works include but are not limited to establishment of temporary working area, fencing, pre-construction drainage, topsoil stripping, pipeline stringing, pipeline bending, welding, coating, testing, dewatering, trench excavation, trenchless crossings, lower and lay, backfill, tie-ins, re-grading of subsoil, post construction drainage, subsoil cross-ripping and topsoil reinstatement and pipeline testing. The normal working width provides sufficient area for a running track, to perform the linear pipeline construction, top soil storage and separate subsoil storage and enables the trench to be excavated safely (taking into account the angle of repose). Refer to Figure 2 Pipeline Construction.
2.5.3 A slightly wider working width is needed for constructing crossings, for example road, railway, watercourse and service crossings. The working width could increase by 7.5m beyond the 36m working width on both sides to provide an area typically 51m wide, with a setback distance of 1.5 times the length of the crossing or 30m, whichever is the greater. These are referred to as ‘box out’ areas. The dimensions applied are based on National Grid custom and safe working practise and are required to accommodate excavations, a laydown area for pipe, materials storage and equipment and safe access for vehicles. At road crossings the box out area
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 12
The Yorkshire and Humber CCS Cross Country Pipeline
also provides off-road parking for construction vehicles. For special crossings such as the River Ouse and River Hull larger working areas will be required (see Additional Temporary Land Take below). Horizontal Limits of Deviation are shown on the Works Plans Drawings No. 10-2574-GND-01-05-0030 to 0055 and Figures 3.1 – 3.11 of this report.
2.5.4 The proposed c.100m Limits of Deviation is necessary in the DCO to allow for deviation from the proposed pipeline alignment without having to seek additional permission /consent that may otherwise be required for route amendments. National Grid has extensive experience in pipeline construction and from experience recognises that the following can influence the need for flexibility:
• Ground Conditions – it will not be possible to understand all ground conditions until construction commences. It may be necessary to deviate from the proposed pipeline alignment to avoid certain ground conditions such as groundwater, historic mining excavations or unstable soils, localised potentially contaminated land, unregistered landfill sites, pockets of highly compressive soils (such as peat), pockets of very hard and/or shallow rock head and karstic features.
• Ecology – detailed surveys have been carried out within the scoping corridor however ecological conditions within the LoD may change between submission and determination of the DCO and as such the most appropriate means of mitigating or minimising the environmental effect may be a minor re-route of the pipeline.
• Archaeology – whilst the geophysical surveys carried out along the proposed pipeline alignment indicate relatively few archaeological remains, there is still the potential for undiscovered archaeological features to be present which may necessitate avoidance through minor re-routes to minimise effects on cultural heritage or programme.
• Third Party Services – a number of services run adjacent to or fall within the Order Limits, which will need to be crossed by the pipeline. Whilst these have been identified, detailed design work, will be needed to agree crossing arrangements.
• Landowner requirements – once on site some minor changes to the proposed pipeline alignment may be requested by landowners to further minimise effects on access, drainage or other aspects of their agricultural business; or for new development that has gone through planning between submission and determination of the DCO.
• Variation in crossing techniques – National Grid is currently considering the range of crossing techniques available to cross roads, railways and watercourses encountered along the proposed pipeline alignment. Detailed design will require further information on ground conditions etc. in order to identify the most appropriate
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 13
The Yorkshire and Humber CCS Cross Country Pipeline
crossing techniques and detailed location. Minor re-routes may therefore be needed.
Vertical Limits of Deviation
2.5.5 Whilst the pipeline will be buried the above ground vertical limits of deviation for the authorised development include a 3m tolerance. This is to allow for the installation of aerial marker posts at field boundaries, and post and rail fencing reinstatement where required.
2.5.6 Below ground the draft DCO allows for the pipeline to be installed at any depth as may be found to be necessary or convenient. The pipeline will be constructed not less than 1.2 metres below ground surface, not less than 1.7metres below ordinary watercourses, not less than 2m below the true clean bottom of main rivers and canals; and not less than 2 metres below public highways. (See Section 3.3 Depths of Cover).
Land Drainage Areas
2.5.7 In constructing a pipeline pre and post-construction drainage is required to protect existing drainage systems and control surface run-off. It may not be possible to accommodate the works and outfalls required for this drainage within the LoD. Drainage surveys have been undertaken on the majority of the land required for the Onshore Scheme and in these areas it is clear where drainage will be installed. In addition the majority of landowners have provided information on the existing drainage infrastructure.
2.5.8 Areas where the location of drainage is uncertain and subject to further investigations, have been defined as “Flexible Drainage Areas” and the DCO will only permit works associated with drainage in these areas. A Drainage Report and Drainage Design drawings (Document Reference 7.7) accompanies the DCO application, which describes among other things, the approach to the location and construction of land drains.
Additional Temporary Land Take
2.5.9 In addition to Limits of Deviation included in the draft DCO, there are areas where more temporary land take will be required during construction for access, temporary construction areas including pipe lay down areas, contractor’s compounds etc. The DCO Order Limits incorporate the land required for Temporary Construction Areas, access, maintenance, mitigation works, drainage, and temporary construction compounds.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 14
The Yorkshire and Humber CCS Cross Country Pipeline
2.5.10 In total there are eight Temporary Construction Areas (TCAs). These are described in Table 2.1 and are shaded pink on Figures 3.1 to 3.11 Scheme Layout.
Table 2.1: Temporary Construction Areas
TCA Location
TCA 1
This TCA is located between Drax PIG Trap and the Multi-junction adjacent to the west of Main Road at Woodcock Wood. This TCA is required to facilitate the crossing of Main Road and the disused railway to the west.
Additional land is required to accommodate laydown area and excavations and spoil storage for a trenchless crossing under Main Road and to accommodate pipe and equipment required for the two trenchless crossings (Main Road and disused railway); also to allow construction vehicles safe access and parking off the public road.
TCA 2
This TCA is located between Camblesforth Multi-junction and the A645. This TCA is required to facilitate the crossing of the A645.
Additional land is required to accommodate the working width, laydown area and excavations for trenchless crossings under the A645, of two adjacent pipelines (including pipe, equipment and spoil storage); safe access and egress from the A645 and Wade House Lane for the pipelines and multi-junction works, including parking off the public road.
TCA 3
This TCA is located between Camblesforth Multi-junction and Tollingham Block Valve, south of the River Ouse. This TCA is required to facilitate the crossing of the River Ouse.
Additional land is required to accommodate the laydown area for the Horizontal Directional Drill (HDD) of the pipeline under the River Ouse including drilling equipment, the management system for the drilling fluid and arisings, control cabin and welfare cabin. In addition, a long section of pipe has to be laid out above ground and welded, of sufficient length for the whole crossing.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 15
The Yorkshire and Humber CCS Cross Country Pipeline
Table 2.1: Temporary Construction Areas
TCA Location
TCA 4
This TCA is located between Camblesforth Multi-junction and Tollingham Block Valve, north of the River Ouse. This TCA is required to facilitate the crossing of the River Ouse.
Additional land is required to accommodate the laydown area for the Horizontal Directional Drill (HDD) of the pipeline under the River Ouse including drilling equipment, the management system for the drilling fluid and arisings, control cabin and welfare cabin.
TCA 5
This TCA is located between Tollingham Block Valve and Dalton Block Valve adjacent to the south of the A1079 (Arras Hill). This TCA is required to facilitate the crossing of the A1079.
Additional land is required to accommodate laydown area and excavations for trenchless crossing under the A1079 (including pipe, equipment and spoil storage). This is also likely to be the interface between two pipeline contractors; a laydown area will be required for the mobilisation of plant for one contractor and demobilisation of plant for the other; space will be required to allow safe access and egress from the A1079 for both contractors, including parking off the public road, temporary storage of pipe, equipment, plant and materials after delivery to or prior to removal from site; welfare cabins etc.
TCA 6
This TCA is located between Skerne Block Valve and Barmston Pumping Station to the south of the River Hull and Main Drain. This TCA is required to facilitate the crossing of Main Drain, the River Hull, Driffield Canal and B1249 Frodingham Road in one go.
Additional land is required to accommodate laydown area and excavations for the trenchless crossing (including pipe, equipment and spoil storage). Ground investigation surveys have identified that extensive de-watering will be required in this area, additional land is therefore required to accommodate a water management system including wells, pumps, water storage and settlement lagoons to allow the controlled dewatering and discharge of ground water.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 16
The Yorkshire and Humber CCS Cross Country Pipeline
Table 2.1: Temporary Construction Areas
TCA Location
TCA 7
This TCA is located between Skerne Block Valve and Barmston Pumping Station to the north of the River Hull and the Driffield Canal. This TCA is required to facilitate the crossing of Main Drain, the River Hull, Driffield Canal and B1249 Frodingham Road in one go.
Additional land is required to accommodate temporary laydown area and excavations for the trenchless crossing (including pipe, equipment and spoil storage). Ground investigation surveys have identified that extensive de-watering will be required in this area, additional land is therefore required to accommodate a water management system including wells, pumps, water storage and settlement lagoons to allow the controlled dewatering and discharge of ground water. Safe access and egress from the B1249 for construction vehicles, including parking off the public road.
TCA 8
This TCA is located around Barmston Pumping Station and the landward end of the landfall for the offshore pipeline. This TCA is required to facilitate the construction of the pumping station, facilitate the construction of the landfall of the offshore pipeline, and will also coincide with the end of the Cross Country Pipeline contractor’s works.
Additional land is required to accommodate:
- a temporary construction compound for Barmston Pumping Station;
- a temporary construction compound for the offshore pipeline contractor;
- a laydown area for the landfall of the offshore pipeline to facilitate a trenchless crossing under the cliffs (including excavations; pipe, equipment and spoil storage; spoil management system and lagoons; cabins; and a laydown area for the welding of pipe);
- a temporary laydown area for the onshore pipeline;
These will include safe access and egress for construction vehicles, parking off the public road, temporary storage of pipe, equipment and materials delivered to site, welfare cabins etc.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 17
The Yorkshire and Humber CCS Cross Country Pipeline
Above Ground Installations
2.5.11 For the AGIs a greater or lesser degree of design flexibility is required. For the Drax PIG Trap, the three block valves at Tollingham, Dalton and Skerne and Camblesforth Multi-junction the authorised development will be constructed in general accordance with those drawings submitted as part of the draft DCO. Within Area B at the Camblesforth Multi-junction and Barmston Pumping Station more flexibility is required. For those aspects of the Onshore Scheme that still require design flexibility, the DCO application has been based on parameters.
2.5.12 For Area B of the Camblesforth Multi junction a maximum height of 4m above existing ground level has been adopted. For the Barmston Pumping Station a maximum height of 9m above current ground level has been adopted.
Accesses to the Public Highway
2.5.13 Temporary accesses for construction traffic onto the pipeline working width from the public highway will be created at road crossings. The exact location of these access points within the limits of deviation for the pipeline will be determined during detailed design. Plans showing a generic layout for these temporary junctions have been discussed with the Highways Authorities and submitted with the DCO application (Document Reference 2.52 and 2.53). The relevant highways authority will be consulted once the locations of temporary site access points are known.
2.5.14 Where the location of temporary accesses are known such as for the temporary construction compounds, planning arrangement drawings (Document Reference 2.54, 2.62 and 2.63) and swept path analysis drawings (Document Reference 2.64, 2.70 and 2.71) have been prepared in discussion with the relevant highways authorities and submitted with the DCO application.
2.5.15 Permanent accesses for the above ground installations have also been identified and planning arrangement drawings (Document Reference 2.55 – 2.61) and swept path analysis drawings (Document Reference 2.65 – 2.69) have been prepared in discussion with the relevant highways authorities and submitted with the DCO application.
2.5.16 Detailed design drawings for permanent access junctions and public road modifications will be submitted to the relevant highways authority for approval prior to construction. Drawings in accordance with the Council’s standard details will show design specifications and materials to be submitted for approval by the relevant local highways authority.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 18
The Yorkshire and Humber CCS Cross Country Pipeline
2.6 PIPELINE ROUTE DESCRIPTION
2.6.1 The following text describes the pipeline route in sections between above ground installations. The annotation RDX is used to represent road crossings.
2.6.2 The pipeline alignment (centreline) and LoD are illustrated on Figures 3.1 – 3.11 Scheme Layout. The following description applies to the c. 100m LoD corridor which in places has been reduced to avoid constraints. For simplicity the term ‘pipeline route’ has been used.
White Rose to Camblesforth
2.6.3 From the Gas Processing Unit within the proposed White Rose CCS Project site at Drax Power Station a pipeline of up to 324mm external diameter will run South East to cross Carr Dike before entering the Drax PIG Trap AGI located adjacent to the proposed White Rose CCS Project site.
2.6.4 From the Drax PIG Trap AGI the route for the connecting pipeline, of up to 324mm external diameter, runs North crossing Carr Dike and running to the immediate West and North of Drax Augustinian Priory Scheduled Monument, avoiding the schedule site. It then turns East South East crossing Lendall Drain to the North of Drax Abbey Farm before turning South to cross Pear Tree Avenue (RDX1) to the West of Old Lodge. The pipeline route continues South and crosses Carr Lane (RDX2) to the East of New Close Wood before turning East to cross a dismantled railway. Trees along the railway embankment are protected by Tree Preservation Order (TPO); a non-open cut method is proposed to install the pipeline under the dismantled railway, thus avoiding the TPO. After running to the North of Woodcock Wood, the pipeline route turns South East to cross Main Road (RDX3) immediately North of Woodlands, Drax.
2.6.5 Deflecting South, the pipeline route runs to the East avoiding playing fields and crosses Church Dike Lane (RDX4) to the East of Drax village before turning South West to cross Hales Lane track, and West to cross Brickhill Lane (RDX5), to the South of Drax village avoiding Castle Hill Moated Site Scheduled Monument.
2.6.6 The pipeline route deflects South West then South South West crossing the A645 (RDX6) South East of Wade House Lane and to the West of Brock Holes Fish Pond, avoiding this local wildlife site (LWS), before entering the proposed multi-junction site at Camblesforth.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 19
The Yorkshire and Humber CCS Cross Country Pipeline
Camblesforth to Tollingham
2.6.7 From the proposed Camblesforth multi-junction site the pipeline route for the up to 610mm external diameter Cross Country Pipeline heads North crossing the A645 (RDX7) to the South East of Wade House Lane and to the West of Brock Holes Fish Pond (avoiding the LWS). It then turns East crossing Brickhill Lane (track), and passing to the South of Caste Hill moated site Scheduled Monument, before turning North Eastward and crossing Hales Lane (track) and Church Dike Lane (RDX8). Thereafter the pipeline route runs to the North West of Scurff Hall avoiding the Scheduled Monument, before crossing the River Ouse.
2.6.8 From the River Ouse the pipeline route continues North East towards Asselby crossing Gateland Field Lane (track) and Lowfield Drain and deep field ditches. It crosses three existing gas pipelines, a dismantled railway and Barmby Road (RDX9) to the West of Asselby.
2.6.9 The pipeline route continues North East, crossing an existing gas pipeline, Asselby Marsh Drain, Old Derwent (culvert), New Drain, and an adjacent track before crossing the A63, Hull Road (RDX 10) and Black Dyke between Newsholme and Newsholme Parks.
2.6.10 The pipeline route continues North Eastward, crossing a multi-fuel pipeline before crossing a railway to the West of Brind Crossing and Brind village. The pipeline route then crosses Brind Lane (RDX11) and passes immediately to the South of Brindley’s Plantation LWS (outside the woodland but within the current LWS boundary).
2.6.11 Crossing the B1228 Wood Lane (RDX12) to the North of Brind and North of Brickyard Farm the pipeline route then trends East. It runs parallel to Featherbed Lane (a local wildlife site) initially on the North side before crossing to the South. The proposed crossing point of Featherbed Lane is within the LWS boundary.
2.6.12 The pipeline route then crosses back to the North of Featherbed Lane to the West of Rose Villa Farm. Heading North East then East it crosses the A614 Holme Road (RDX 13) to the South of Ivy House and the North of Avian Pastures. The pipeline route then heads North East, crossing the River Foulness and then Bursea Lane (RDX14), to the North of Bursea and to the South of Bursea Lane Farm.
2.6.13 The pipeline route continues North Eastward, crossing Drain Lane (RDX 15) to the North West of Grange Farm and Throlam Plantation, and on into the Tollingham Block Valve site.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 20
The Yorkshire and Humber CCS Cross Country Pipeline
Tollingham to Dalton
2.6.14 From the Tollingham Block Valve site the pipeline route continues North East and crosses Skiff Lane (RDX16) between Skiff Farm and Tollingham Cottages.
2.6.15 The pipeline route continues North Eastward to cross Lock Lane (RDX17) to the East of High Garth. It then heads East, crossing Back Delfin Drain and the disused Market Weighton Canal to the South of Sand Lane. The pipeline route then crosses Sand Lane (RDX 18) to the West of Oakwood and heads North East, towards Market Weighton.
2.6.16 To the South of Market Weighton the pipeline route crosses Cliffe Road (RDX19), to the South of Long Lane. It then heads in a North Easterly direction, avoiding a small reservoir at Crossfields Farm, before crossing the A1034, Sancton Road (RDX20) and the putative line of a Roman Road.
2.6.17 From here the pipeline route enters the Yorkshire Wolds (an Area of High Landscape Value). Through this area the terrain rises and in the interest of construction safety the routeing process has sought to minimise the need for working on side slopes.
2.6.18 The pipeline route passes between Weighton Wold House and High Wold Farm (avoiding a cluster of prehistoric burial mounds to the East of High Wold Farm). It then crosses the A1079 on Arras Hill (RDX21).
2.6.19 From the A1079 the pipeline route continues North East. The route crosses within the boundary of a Regionally Important Geological and Geomorphological Site (RIGS) although the main part of the site has been avoided. It crosses an existing ethylene pipeline before crossing Kiplingcotes Lane.
2.6.20 After crossing Kiplingcotes Lane (RDX 22) due East of Goodmanham Lodge Farm, the pipeline route turns North to cross the Hudson Way (disused railway) to the East of Station House, Kiplingcotes Station avoiding a disused quarry which is a RIGS. (The Hudson Way is a long distance footpath, a Local Nature Reserve and LWS. The crossing point is constrained by the quarry and property to the West and by a Scheduled Monument (a prehistoric burial mound) on the North side of the disused railway, to the East.)
2.6.21 From this crossing the pipeline route heads North, crossing Kiplingcotes Road (RDX23), and Kiplingcotes Racecourse Road (RDX24) and Park Road (RDX25), avoiding the Dalton Estate plantations to the East and paralleling a minor road to the West. The pipeline route then crosses
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 21
The Yorkshire and Humber CCS Cross Country Pipeline
Holme Wold Road (RDX 26) and turns to run East North East across Great West Field into the Dalton Block Valve site.
Dalton to Skerne
2.6.22 From the Dalton Block Valve site the pipeline route heads North East, crossing Lund Wold Road (RDX 27) to the West of Corporation Farm and Middleton Road (RDX28) to the North West of Lund. Passing to the North of Lund and South East of Middleton-on-the-Wolds the pipeline route crosses the B1248 Lund Road (RDX 29) due North of Lund and to the South of East Field. It then continues North Easterly crossing Middleton Road (RDX30) to the immediate South East of Lund Chalk Quarry, then crossing Bracken Beck to the East of Poultry Houses. Here the pipeline is routed through a pinch point between woodland which is LWS and a plantation.
2.6.23 The pipeline route then passes to the North West of the small settlement of Bracken, before continuing North East through agricultural fields towards Hutton Cranswick, crossing an unnamed Northward extension of Bracken Lane (RDX31), due North of Bracken and Burnbutts Lane (RDX32) to the West of Burn Butts Farm and Cottages. The pipeline route then passes between Bustardnest Fox Covert and Bustard Nest Farm before turning East then North East.
2.6.24 To the West of Hutton Cranswick the pipeline route crosses Southburn Road (RDX33), the A164, Beverley Road (RDX34), and Jenkinson Lane (RDX35) between Allotment Gardens to the South and Old Gawdy Hall to the North. It then crosses Northfield Beck, due North of Hutton.
2.6.25 From here the pipeline route runs in a more Easterly direction, crossing a railway line South of Knorka Dike. It then crosses Knorka Dike itself, and Ricklepits (RDX36), West and North respectively of Rickle Pits Farm.
2.6.26 From Ricklepits the pipeline route heads East, running to the South of Skerne between blocks of woodland into Skerne Block Valve site.
Skerne to Barmston Pumping Station
2.6.27 From the Skerne Block Valve site the pipeline route continues North and then North East towards Wansford where it crosses Main Drain, the River Hull, Driffield Canal and B1249 Frodingham Road (RDX37) to the South of Wansford, between Wansford Bridge and Snakeholm Bridge. The land between Main Drain and the River Hull is part of a Yorkshire Wildlife Trust (YWT) Nature Reserve and the River Hull is a SSSI. The pipeline has been routed to the shortest crossing point, to minimise environmental disturbance
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 22
The Yorkshire and Humber CCS Cross Country Pipeline
and the technical complexity of the crossing and to avoid the settlement of Wansford to the North West and the Trout Farm to the South at Snakeholm Bridge. A non-open cut method of pipeline installation is proposed to cross under Main Drain, the YWT site, River Hull SSSI, Driffield Canal and B1249 in one crossing.
2.6.28 From the crossing the pipeline route continues North East, crossing fields with numerous drains (including Nafferton Highland Stream and White Dike) before passing between South Cattleholmes and Fox Covert where it crosses Kelk Beck (SSSI).
2.6.29 Running eastward the pipeline route crosses Main Street (RDX38) between Great Kelk and Gembling. From Main Street the pipeline route heads East then North to Barf Hill (LWS) where it turns East North East to cross Gransmoor Drain avoiding the LWS and Gransmoor Quarry to the North and the sand and gravel pits and Lissett Wind farm to the South.
2.6.30 From Gransmoor Drain the pipeline route continues East North East, crossing Gransmoor Road (RDX39) South East of Manor Farm. It then turns North East to cross Burton Drain at Carr Hill, and East to run between Stone Hills to the North and Spring Hill, before crossing the A165, Bridlington Road (RDX40) to the North of Quintin Garth. From the A165, the pipeline route runs East then North East to the proposed Barmston Pumping Station site, to the North West of Hamilton Hill, North of Barmston.
2.6.31 To the East of the proposed Barmston Pumping Station site the pipeline route for the offshore pipeline heads South East and then East, to a landfall point North East of Hamilton Hill. The pipeline route for the Onshore Scheme terminates at the Low Mean Water Mark (See Section 5. Landfall Construction).
2.7 ABOVE GROUND INSTALLATIONS DESCRIPTION
Drax PIG Trap AGI (Work No. 1A)
2.7.1 A PIG Trap will be located at the beginning of the connecting up to 324mm external diameter pipeline between the White Rose CCS Project site at Drax Power Station and the Yorkshire and Humber CCS Cross Country Pipeline. The purpose of a PIG Trap is to provide a facility to launch and receive pipeline internal gauges (PIGs) used to clean, gauge and inspect the pipeline.
2.7.2 The PIG Trap installation would comprise a compound 35m x 41m (c. 0.14ha) in size, surrounded by a weldmesh security fence, a 2m sterile strip and landscape planting area. The compound will accommodate an
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 23
The Yorkshire and Humber CCS Cross Country Pipeline
instrument building, PIG Trap arrangement and above and below ground pipework. The Pig Trap will require a permanent road access through the White Rose Project site.
Block Valve Sites
2.7.3 The new Block Valve AGIs will be located at intervals along the proposed Cross Country Pipeline at Tollingham (Work No.6A), Dalton (Work No.9A) and Skerne (Work No. 11A). The purpose of Block Valves is to enable sections of the pipeline to be isolated in the event of an emergency or for planned maintenance.
2.7.4 The Block Valve installations will comprise a compound 37m x 28m (c.0.1ha) in size, surrounded by a security fence (typically weld mesh with 3 strands of barbed wire at the top), a 2m sterile strip and landscape planting area. The compound will accommodate an instrument building and above and below ground pipework.
2.7.5 Each Block Valve installation will require a permanent road access to the public highway as follows:
• Tollingham Block Valve – new access road along eastern edge of fields from Skiff Lane (adopted highway, unclassified road), new junction onto public highway;
• Dalton Block Valve – new access road along eastern edge of field from Lund Wold Road (adopted highway, unclassified road), new junction onto public highway;
• Skerne Block Valve - upgrading of existing unnamed road through Church Farm, Skerne (adopted highway, unclassified road) and track to Copper Hall; between Main Street, Skerne (adopted highway, unclassified road) and the installation. Modifications to existing junction of public highway and may require bridge modifications.
Camblesforth Multi-junction (Work No. 4A)
2.7.6 A Multi-junction installation is required to allow the connection of pipelines carrying Carbon Dioxide from emitters. Initially the site would accommodate a connection from the White Rose CCS Project (up to 324mm external diameter pipeline). An installation compound of 154m x 73m (c.1.1ha) is required for a Multi-junction. This would be surrounded by a security fence (weld mesh with 3 strands of barbed wire at the top) and a 2m sterile strip and landscape planting area.
2.7.7 The installation compound would accommodate an instrument building, two PIG Trap arrangements and above and below ground pipework with
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 24
The Yorkshire and Humber CCS Cross Country Pipeline
sufficient space in Area B to accommodate three further PIG Traps to be built at a later date.
2.7.8 A permanent road access will be required. This will involve a new access road from Wade House Lane (adopted highway, unclassified road), around the western edge of a field to cross an existing track before entering the multi-junction site. This will require a new junction onto the public highway and modification of the existing public highway junction between Wade House Lane and the A645.
2.8 BARMSTON PUMPING STATION DESCRIPTION
2.8.1 A Pumping Station is required both to maintain the pressure of liquid Carbon Dioxide within the pipeline for transportation offshore and to enhance the volumes of Carbon Dioxide that can be transported by the pipeline for offshore storage. The design assumptions are that the design pressure of the in-coming onshore pipeline will be up to 150 bar gauge and the design pressure of the out-going offshore pipeline will be up to 200 bar gauge.
2.8.2 The Pumping Station will be designed to accommodate future demand, however, not all the components will need to be constructed straight away.
2.8.3 The conceptual design shows that the Barmston Pumping Station would occupy a 14.4 hectare site including an installation compound surrounded by a security fence (weld mesh with 3 strands of barbed wire at the top), a 2m sterile strip and landscaped planting areas. The installation would accommodate (but not be limited to) an administration and control building, workshop, pump units and variable speed drives, PIG Trap arrangements and above and below ground pipework, filtering and metering equipment, cooling system, analyser building, air and nitrogen receivers, nitrogen and instrument air building, vent stack and electricity sub-station.
2.8.4 A permanent road access will be required. This will involve upgrading Sands Road (adopted highway, unclassified road/ track) and a new access into the pump station site. This will require a new junction onto the public highway at Sands Road which is currently an unsurfaced track, some upgrading and modification of the public highway may be required. This will be subject to agreement with the Highways Authority.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 25
The Yorkshire and Humber CCS Cross Country Pipeline
3.1 GENERAL PIPELINE CONSTRUCTION METHODOLOGY
Background
3.1.1 Cross-country pipeline construction is a well-established technique that can be applied to all welded steel pipelines whether they carry natural gas or Carbon Dioxide. Construction is undertaken on a “production line” basis i.e. by a series of different specialist ‘crews’ who each perform a specific function and move along the pipeline route in order (see Figure 2 Pipeline Construction). Individual operations can move forward at a rate of 500 m to 1 km a day depending on the ground conditions and in the case of welding, the pipe diameter. The detailed make-up of the workforce has yet to be determined, but in general terms the following crews will be employed for the construction of a pipeline including but not limited to:
• survey (to peg the route and locate and mark existing services); • working width preparation; • fencing; • pre-construction drainage; • topsoil strip; • archaeological surveys and watching brief; • levelling and benching; • breaking up of rock (if encountered); • pipe stringing (lay out the pipe along the working width); • field bending (i.e. pipes bent to angles previously determined by the
bending engineer); • welding and inspection (end preparation, front end welding, back end
welding, fabrication welding); • non-destructive weld testing; • joint coating; • dewatering (well-point de-watering, pumping and discharge); • trench excavation; • lower and lay; • backfill (sand padding); • pipeline tie-ins; • re-grading of soil;
3 Construction of Pipelines
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 26
The Yorkshire and Humber CCS Cross Country Pipeline
• post-construction drainage; • reinstatement (cross-ripping of subsoil and reinstatement of topsoil,
boundary walls, hedges and fences); • hydrostatic testing and final tie-ins (swab and gauge pipeline test
sections, fill, test and dewater); and • commissioning (final gauge plate and calliper surveys, drying and
commissioning) . 3.1.2 In addition, special crews will be established for operations such as
crossings (e.g. road, rail, river, canal). These activities are normally carried out independently of the normal sequence of works.
Figure 2 Pipeline Construction
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 27
The Yorkshire and Humber CCS Cross Country Pipeline
3.1.3 The following sections describe normal pipeline construction methodology.
Pre-construction Works
3.1.4 Ahead of construction, the route will be surveyed and pegged out. This will establish the precise alignment, particularly in relation to field boundaries, mature trees and environmentally sensitive sites. Where practical use will be made of existing gaps in hedgerows, mature trees, springs, seepage lines and rocky outcrops will be avoided. Water supplies fed by springs or wells used for farming processes or domestic supplies will be surveyed and monitored before, during and after construction, as necessary.
3.1.5 Prior to construction the location and condition of existing land drainage will be established and a record of condition compiled. Where necessary, new field drains will be installed to:
• enable the farmer’s current drainage system to continue working throughout the period of pipeline construction;
• help prevent damage to the soil structure; and • aid recovery from construction activity.
3.1.6 A specialist drainage contractor will carry out the work. Permanent records of the land drainage locations will be produced.
3.1.7 In addition a number of engineering surveys will be carried out including surveys to locate existing services and geotechnical surveys to establish ground conditions using trial pits and boreholes.
3.1.8 Prior to construction Pre-entry Meetings will be held with landowners/farmers to seek to agree requirements for land drainage, temporary fencing, accesses, monitoring of water supplies, temporary water supplies and reinstatement.
3.1.9 If appropriate, bio-security measures will be implemented through liaison with the Department for Food and Rural Affairs’ (DEFRA) Animal Health and Veterinary Laboratories Agency.
3.1.10 Where practical National Grid will seek to agree the measures set out above with the landowners/occupiers through the appointed Agricultural Liaison Officer.
Temporary Construction Compounds
3.1.11 Prior to construction each contractor will set up a temporary construction compound (pipe store and office area) of approximately 4.0ha. The area
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 28
The Yorkshire and Humber CCS Cross Country Pipeline
estimated is based on National Grid custom and safe working practise and is required to accommodate:
• site office, welfare and security facilities; • power supplies; • enclosures; • pipe, equipment and fittings storage; • plant storage; • fabrication area; • waste storage areas; • spoil storage areas; • internal haul roads; • access parking; • vehicle maintenance area including washing facilities; and • water management areas.
3.1.12 Locations for temporary construction compounds for the pipeline contractors have been identified at:
• Tollingham Industrial Estate (comprised in Work No.7 of Schedule 1 of the draft DCO(Document 3.1))
• Driffield Barracks (comprised in Work No. 12 of Schedule 1 of the draft DCO (Document 3.1))
3.1.13 Post construction, temporary construction compounds will be reinstated to the conditions which prevailed at the commencement of the works.
Working Width Preparation
3.1.14 All construction activities will normally be undertaken within a fenced strip of land, known as the working width. This will generally be 36m wide although this may be narrowed in areas with particular constraints or to minimise impacts to sensitive sites. A reduced working width can be used for short sections where for example storage of topsoil or trench material can be accommodated in adjacent sections where the working width is wider.
3.1.15 A wider working width is necessary at some locations for example road, watercourse, railway and service crossings, in areas of side slopes, at some hedge crossings and at some intersection points (Ips) where the pipeline route changes direction, in order to facilitate safe working, storage, manoeuvring and parking.
3.1.16 At special crossings, the working width would be increased to 51m (on both sides of the crossing) so as to provide a laydown area for pipe The length of
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 29
The Yorkshire and Humber CCS Cross Country Pipeline
the widened section of working width will be 1.5 times the width of the crossing, with a minimum length of 30m. For special crossings such as the River Ouse and River Hull larger working areas will be required.
3.1.17 Access points will be created onto the working width at road crossings. The access opening at road crossings will generally be a double gate width of approximately 12m. This width, together with a set-back, will provide adequate turning radii for HGV’s at access points to the right-of-way. Areas of hardcore will be provided to allow parking for construction vehicles off public roads.
3.1.18 Working width preparation involves the clearance of field boundaries and the ‘fluming’ or bridging of watercourses. The cleared section of hedges or walls will be less than the total working width. The length of the gap will depend on the angle of the boundary to the working width. At field boundaries this will typically be 20m where hedgerows are crossed at right angles and greater where hedges are crossed at an angle. At major roads approximately 25m will be required where access is required for pipe and plant delivery, however, a 15m gap is more likely at small road crossings. Hedgerows and scrub within the working width will be removed or flailed / coppiced in winter to deter nesting birds.
3.1.19 Existing third-party services will be located and marked. Warning posts and barriers will be erected for overhead cables and temporary crossing points indicated.
3.1.20 If appropriate, ditches / small streams will be flumed by the installation of temporary pipes and ramped over to create a continuous running track for construction vehicles and allow continuous flow of water within the ditch, with permission of the relevant regulatory authority (Environment Agency/ Internal Drainage Board / Lead Local Flood Authority as appropriate). Where necessary, imported materials will be laid on geotextile sheet to facilitate their removal at the end of construction.
Fencing
3.1.21 The temporary working width will be clearly marked with demarcation fencing or stockproof fencing will be erected in areas grazed by livestock.
3.1.22 Stiles, gates or gaps will be incorporated into the temporary fencing to maintain access to farm tracks and, where required, to maintain access to public rights of way as agreed with local authorities. Where feasible, additional access points will be provided to allow access across the pipeline and thereby mitigate field severance.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 30
The Yorkshire and Humber CCS Cross Country Pipeline
3.1.23 Where hedge lines have been removed, at road crossings and accesses, temporary gates will be installed to prevent unauthorised vehicle access to the working area. These gates will be maintained by the contractor throughout the construction period and will only be open for access.
3.1.24 Before breaking into existing fences, walls and hedges, all temporary fencing shall be securely tied into existing fences, walls and hedges. Sections of strained wire fence shall be removed and restrained.
3.1.25 Throughout this project, National Grid will seek to agree the measures set out above with the landowners/occupiers.
Topsoil Stripping
3.1.26 The topsoil will be stripped across the working width, using appropriate earth moving equipment. The width of topsoil to be stripped should generally be that required to contain the trench, the pipe sections, the excavation plant, the temporary running track and the width required for stacking the subsoil. The full depth of the topsoil will be stripped and stored carefully to one side of the working width in such a way that it is not mixed with subsoil or trafficked over by vehicles or plant. Typically the topsoil bunds will be 8 m wide and up to 4 m high to avoid compaction from the weight of the soil. Storage time will be kept to a practicable minimum to reduce the risk of physical damage and compaction. Gaps are left in the topsoil heap to prevent flooding and ponding. Uncultivated soil, for example topsoil stripped from hedgerow banks, conservation road verges, the banks of watercourses or woodland strips will be stored separately from other excavated material.
3.1.27 Following topsoil stripping, some areas of the working width may be benched (levelled) or graded to enable safe working.
Temporary Access Roads
3.1.28 In general, access will be restricted to the fenced working width and vehicles will use the running track. Access will be gained to and from the public highway at road crossings. Where the proposed pipeline route crosses a public road a temporary access will be created. (See Typical Temporary Access from Highway Drawings No. 10-2574-STD-01-0314 and 0315).
3.1.29 In some areas along the proposed pipeline route however, temporary access roads between public highways and the working width may be required to aid the movement of machinery and materials.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 31
The Yorkshire and Humber CCS Cross Country Pipeline
3.1.30 The method of construction for temporary access roads will be dependent on the particular ground conditions. This can vary from stripping the topsoil to allow vehicles to run on the subsoil, to bogmats or a thickness of crushed stone overlaying a geotextile membrane.
3.1.31 At site accesses suitable supervision will be provided to ensure that traffic is controlled at access points to the pipeline and AGIs during construction (e.g. banksman checking road traffic and controlling construction vehicle movements) and mud deposits on the roads are minimised. Where required traffic signals (in accordance with New Roads and Street Works Act (NRSWA)) or stop-go boards will be used to control road traffic. Road signs will conform to Chapter 8 (Traffic Signs Manual 2009) and NRSWA.
Pipe Delivery, Stringing and Bending
3.1.32 The pipe storage yards will be located at the Temporary Construction Compounds at Tollingham and Driffield, at temporary construction yards associated with the AGIs and near the landfall. The pipe will be delivered from the pipe manufacturer to the pipe storage yards prior to construction. The pipe will be manufactured in approximately 12m and 18m lengths.
3.1.33 The pre-coated pipe will be delivered by lorry to designated road access points to the working width. Pipe sections will then be delivered to their final location along the working width where they are placed on wooden supports or skids along a line parallel to the trench line in preparation for welding and lowering into the trench.
3.1.34 At agreed crossing points, gaps will be left in the stringing of the pipes to permit the passage of the landowners or occupier’s equipment and/or livestock across the working width.
3.1.35 If ground conditions are soft or rough the pipe will be off-loaded at designated crossings, and transported along the working width using pipe carriers.
3.1.36 The contractor will prepare a Traffic Management Plan that will be discussed and agreed with the relevant Highway Authorities.
3.1.37 Generally where bends are required for changes in direction or topography, they will be made from the new pipe on site with a bending machine. This is called field bending.
3.1.38 In some cases, however, such as deep crossings, factory-manufactured bends may be required. These will be transported to site and placed in position.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 32
The Yorkshire and Humber CCS Cross Country Pipeline
3.1.39 In proximity to residential areas, and in other areas as appropriate such as road, rail, waterway and ditch crossings, and where ground conditions dictate, thicker-walled pipe will be utilised where required by the design code (PD 8010:Part 1 2004).
Welding, Non-destructive Testing and coating
3.1.40 The pipe lengths will be delivered pre-coated externally with a factory applied fusion bonded epoxy (FBE) coating. Following stringing, the pipeline sections will be welded together. All the welds will be ultrasonically tested and any faults will be repaired or the weld replaced and the weld re-tested. Less typically, x-ray (in accordance with the Ionising Radiation Regulations 1998) may be used to test welds. All x-ray testing must be carried out in safe areas away from site. The weld will then be cleaned and an approved protective coating applied over the weld. Works will be planned to avoid welding / coating in close proximity to watercourses. However where this is unavoidable, sheeting will be used where a weld coincides with a watercourse to prevent the inert shot blast or coating materials entering the watercourse. Prior to installation the integrity of the coating will be electronically checked (Holiday detection). Welding and testing will only be undertaken by fully qualified and approved staff.
Trench Excavation
3.1.41 The pipe trench will be dug either with trenching machines or mechanical excavators straddling or standing alongside the pipeline centreline. The depth will be variable but will allow a minimum reinstated cover of 1.2 m over the top of the pipeline in agricultural land (see Section 3.3 Depths of Cover).
3.1.42 The material excavated from the pipe trench will generally be stored on the opposite side of the working width from the topsoil to prevent mixing of subsoil and topsoil, which might hinder reinstatement. If during the excavation of the trench, the upper layers of the subsoil are of significantly better quality than the lower layers, the layers will be excavated and stored separately to allow them to be replaced in the same position as prior to removal.
3.1.43 The pipe trench will be left open for the minimum length of time as is practicable.
3.1.44 Approximately 25% of the pipeline route has bedrock close to the surface (predominantly Cretaceous Chalk). The excavation of the trench through soft or fractured rock, or (if encountered) harder rock near the surface, will
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 33
The Yorkshire and Humber CCS Cross Country Pipeline
need operations to break up and loosen it enough to be excavated prior to stringing of the pipeline.
3.1.45 Areas of angular gravels, flint and chert have been identified along the route. In areas where angular rocks or sharp stones are encountered, the pipe will need to be bedded on and surrounded by sand or similar material to prevent damage to the pipe and coating. Where practicable screened / crushed excavated materials will be used to provide the bedding.
3.1.46 Should ground conditions warrant it, trench supports and close sheet piling along the sides of the pipeline trench would be used to aid construction and provide a safe working environment.
3.1.47 In some wet areas, or areas of high water table, de-watering of the pipe trench and excavations may be required. De-watering and discharge of water will be carried out to the requirements and statutory regulations of the Environment Agency. Current estimates based on initial groundwater monitoring indicate that up to a third of the route will require some form of groundwater control for temporary works. Further ground investigation surveys and groundwater monitoring will be undertaken to inform the detailed design.
3.1.48 Drainage cut by the trench or other drains not intercepted by the pre-construction drainage will be marked for later replacement.
Lower and Lay
3.1.49 Following trench excavation the welded pipe sections will be carefully lowered into the trench in a continuous operation using sideboom tractors or equivalent plant. The lengths of pipeline are welded together to form a continuous pipe string ready for hydro-testing operations.
Backfilling
3.1.50 The pipe trench will then be backfilled, where possible with the material taken from the trench in the reverse order in which it was excavated. Sand (or similar material) padding and surround may be used to protect the pipe if the backfill material is particularly unsuitable and in areas of rock. An ‘ozzie padder’, or similar equipment, will be used to screen excavated material to produce suitable fine-grained fill for pipe surround and bedding.
3.1.51 The backfilled materials will be consolidated in layers by tamping or rolling to ensure consolidation comparable with the adjacent subsoil. Any excess material may be spread within the working width, and to ‘crown’ the trench to allow for settlement and to aid consolidation.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 34
The Yorkshire and Humber CCS Cross Country Pipeline
3.1.52 Where necessary, outfall drains will be re-connected across the trench as part of the backfill operation.
Post Construction Drainage
3.1.53 Where necessary additional post construction drainage will be laid within the working width to ensure that the integrity of the drainage infrastructure affected by construction is adequately restored. Detailed drainage design will have regard to soil type, existing drainage systems and land levels. Where drains have to cross the working width drainage pipes will be adequately supported across the reinstated trenchline.
3.1.54 Where there is a risk of the trench itself acting as a drain, with the risk of undermining the pipe, impermeable barriers will be installed to prevent water migration along the trench line. These barriers may be tied into the post construction drainage scheme if necessary.
3.1.55 Throughout this project, National Grid will seek to agree land drainage matters with the landowners/occupiers.
Reinstatement
3.1.56 After re-grading of the working width to reflect the original profile, subsoil will be ripped to relieve compaction and stones (greater than 50mm) and debris will be removed prior to topsoil replacement. Topsoil will be re-spread across the working width to its former depth. After replacement, the topsoil will be cultivated and stone picked as necessary. The separately stored topsoil from uncultivated areas including hedgerow banks and banks of watercourses will be spread back over the areas from which they were taken.
3.1.57 Agricultural areas will be returned to their former land-use as rapidly as possible. Generally on arable land the fences are taken down to allow the cultivation of the field as a whole whereas on permanent pasture the fences are retained in order to restrict access to livestock until the re-seeded sward has sufficiently recovered to withstand grazing pressures. National Grid will seek to agree these procedures with the landowner/occupier before work begins.
3.1.58 All temporary materials such as bog mats, road fill, temporary culverts and geotextile membrane, etc. will be removed during the reinstatement works.
3.1.59 The replacement of field boundaries is important to reduce the visual impact of the pipeline. Fences will be reinstated to meet the landowner/occupier’s requirement using materials that match the existing fence where
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 35
The Yorkshire and Humber CCS Cross Country Pipeline
appropriate. Gaps in hedges and other woodland features will be replanted using a mix of native woody species to match the adjacent hedge or woodland. Replanting will be undertaken using either container grown stock or quality open grown stock, and followed by good maintenance and weed control. Where appropriate replanted areas and hedgerows will be protected with rabbit-proof fencing to protect the new growth from grazing and browsing animals. Vegetation along the banks of watercourses will be reinstated, as necessary and in accordance with the requirements of the Environment Agency/ Internal Drainage Board/ Lead Local Flood Authority, as appropriate.
Integrity Testing and Inspection
3.1.60 The pipeline will be internally cleaned in sections to ensure removal of all debris. It will then be hydrostatically tested to prove its integrity in accordance with the relevant specifications. Water required for testing will be sourced and discharged from the same catchment location or sourced from groundwater and discharged with the agreement of the Environment Agency and the quality of the water being discharged will be monitored. All necessary licenses and consents will be obtained. (See Section 3.5 Pipeline Testing Procedure).
Pipeline Markers
3.1.61 During the reinstatement of boundaries, pipeline markers will be installed to indicate the route for future monitoring by air and line-walking. Boundary marker posts will be supplemented by aerial marker posts. Marker posts will be located at all boundaries and other strategic locations for example main rivers, road and rail crossings. Cathodic protection system test posts will also be installed, and located so as to minimise interference with agricultural activities. (Cathodic protection is a method of protecting the pipeline from corrosion using an impressed current and/ or sacrificial anode system. See Section 3.7 Corrosion Protection.)
3.1.62 The local environment shall be taken into account when positioning marker posts. Ground conditions, terrain (eg. Hilly/flat areas) and trees/shrubs/crops shall be considered when positioning marker posts so that they do not cause an obstruction in the line of sight.
Visibility of Marker Posts
3.1.63 A general principle for visibility is that from any location along the pipeline route at least one marker post shall be clearly visible in both directions.
3.1.64 In rural areas, to minimise disruption to Landowners, Tenants and the Farming Community, marker posts should be sited at field boundaries. The
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 36
The Yorkshire and Humber CCS Cross Country Pipeline
posts should be sited sufficiently clear of natural boundaries such as hedges and shrubs to avoid becoming overgrown and obscured.
3.1.65 The route of a pipeline through a road, rail, or other crossing, should be marked so that the pipeline position is clear to anyone carrying out works in the vicinity. This may be achieved using a combination of aerial markers and field boundary markers to supplement the general route marking.
3.1.66 The position of a pipeline entering an Above Ground Installation, including smaller sites such as block valve compounds, should be clearly marked against the installation fence.
Types of Marker Posts
3.1.67 According to National Grid Specification NGC/SP/PIP/31 – Specification for Carbon Dioxide Pipelines Marker Posts, there are principally 3 types of marker posts.
Aerial markers
3.1.68 Aerial markers are typically a 100mm diameter white plastic post which stands approximately 2m above ground level with a label which identifies the presence of a high pressure pipeline and provides the emergency contact. Aerial marker posts are located at suitable intervals along the pipeline route of the pipeline with a maximum spacing of 1 km. They are also typically placed either side of river crossings and as near as practicable to any change in direction of the pipeline route or at the nearest boundary crossing.
Boundary Marker Posts
3.1.69 The majority of boundary markers are typically manufactured using concrete or High Density Polyethylene (HDPE) and stand approximately 0.6m above ground. Boundary marker posts have a faceplate which identifies the presence of a high pressure pipeline and provides the emergency contact number.
Cathodic Protection Posts
3.1.70 Cathodic protection posts are similar in design to the boundary markers but are made of Medium Density Polyethylene (MDPE) or concrete, stand approximately 0.6m above ground and have a hollow section to accommodate remote logging equipment and enable cables attached to the pipeline cathodic protection (CP) system to be brought into the posts for monitoring the levels of the pipeline’s CP. The posts are usually situated at easily accessible locations.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 37
The Yorkshire and Humber CCS Cross Country Pipeline
3.1.71 For cross country pipelines, test points should be at approximately 1 km separation.
3.1.72 Test facilities should also be located at the following locations:
• Areas that may be affected by stray direct current (DC) earth currents.
• Metallic sleeves. • Insulation joints. • Crossing points with other cathodically protected structures i.e. other
pipelines. • Where sheet piling is to be left in situ following construction. • Road, rail and river crossings. • Bond connections.
3.1.73 Additional test points may be required to facilitate close interval potential surveys (CIPS), a test used to detect CP defects (in accordance with National Grid Procedure NGC/MP/ELEC/03 Management Procedure for the Maintenance and Monitoring of Cathodic Protection for Carbon Dioxide Steel Pipeline Systems).
3.2 SPECIAL CROSSINGS
3.2.1 The trenching methodology described in Section 3.1 is modified for road, railway, river, canal, ditch and service crossings. Typical methods of construction fall into two categories, open cut and non-open cut (or trenchless), both of which are described in Appendix B.
3.2.2 The adopted methods of construction will depend on topography, existing services, and site investigation information and on the requirements of the appropriate consenting authorities.
Open Cut Crossings
Watercourses – Dry Open Cut
3.2.3 Most minor watercourse/ditch crossings will be carried out using a dry open cut trench methodology. In dry open cut methods water flow is maintained by damming and over pumping or using temporary “flume” pipes installed in the bed of the watercourse. Details of these methods are outlined in Appendix B.
Roads – Open Cut
3.2.4 The majority of roads will be crossed by a non-open cut technique. Open cut methods are proposed to cross the following minor roads:
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 38
The Yorkshire and Humber CCS Cross Country Pipeline
• Pear Tree Avenue, Long Drax (Work No. 3B / ST1- ST2) • Brickhill Lane, Drax (Work No. 3F / ST3 – ST4) • Kiplingcotes Lane, Market Weighton (Work No. 8H / ST5 – ST6) • Kiplingcotes Racecourse Road, Etton (Work No. 8J / ST7 – ST8) • Park Road, South Dalton (Work No. 8K . ST9 – ST10) • Holme Wold Road, Holme on the Wolds (Work No. 8L / ST11 –
ST12) • Unnamed Road from Bracken Lane to Burnbutts Lane, Watton (Work
No. 10F / ST13 – ST14)
3.2.5 These will require a temporary road closure during the crossing works. For the location of these road crossings denoted by “ST” numbers refer to Access, Rights of Way and Temporary Stopping Up Plans Drawing Nos. 10-2574-GND-01-05-0061 to 0062 and 0073 to 0077. For Work numbers refer to Works Plans 10-2574-GND-01-05-0031to 0032 and 0043 to 0048.
Trenchless Crossings
3.2.6 There are several non-excavation construction techniques. These include auger boring, grundoram, tunnelling including pipe-jacks, microtunnelling; direct pipe and horizontal directional drilling. These techniques vary in the method used to install the pipeline without disturbing the surface. Details of these methods are outlined in Appendix B.
3.2.7 Trenchless methods will be used to cross the majority of the roads, live railways, and the main watercourses (see Appendix A). Generally, all non-open cut crossings are constructed at a minimum depth of 1.7 m under small watercourses and ditches, 2 m below roads and main rivers and 4.3 m below railways. However, where applicable, the actual design will be submitted to the appropriate body for approval prior to construction.
Main Watercourses
3.2.8 For main watercourse crossings the Environment Agency (or relevant Internal Drainage Board (IDB) / Lead Local Flood Authority) will be consulted during the detailed design stage to discuss methods and to obtain the relevant consents. For the Onshore Scheme the techniques to be used for the crossing of watercourses have yet to be determined. However all main rivers and where practicable Water Framework Directive (WFD) designated watercourses will be crossed using non-open cut methods and the majority of minor watercourses and ditches will be crossed using dry open cut methods. For a list of Main Rivers and WFD Designated watercourses crossed by the proposed Cross Country Pipeline see Appendix A.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 39
The Yorkshire and Humber CCS Cross Country Pipeline
3.2.9 The River Ouse is likely to be a horizontal directional drill (HDD), this will require a large area of temporary land take on either side of the proposed crossing to accommodate the equipment, drilling fluid management system and laydown area for the pipe. A length of pipe the width of the crossing has to be laid out and welded above ground before being pulled through the drilled bore in one continuous operation.
3.2.10 The River Hull / Driffield Canal is proposed to be a combined crossing. Tunnelling or HDD techniques are currently under consideration for this crossing which would install the pipeline under Main Drain, the River Hull, Driffield Canal and the B1249 Frodingham Road in one operation. Geotechnical bore hole surveys conducted to date have indicated that extensive de-watering would be required to allow excavation of shafts and tunnelling to be carried out in dry conditions. Allowance has been made to accommodate the lagoons and water management systems that would be required within the Order Limits.
3.3 DEPTHS OF COVER
3.3.1 Cross country pipelines are typically laid as close as reasonably practicable to the minimum depths of cover outlined in National Grid Specification NGC/SP/PIP/30 Specification for Carbon Dioxide Pipelines Design.
Cross Country Pipelines
3.3.2 The pipeline will be laid to contour at a depth of cover of not less than 1.2 m from the original surface to the top of the pipe. The trench will be excavated so that pipes are evenly bedded throughout their length. Minor variations in contour will be excavated in order to minimize field bending.
Highways
3.3.3 Highway crossings vary from unclassified public highways to motorways. The minimum depth of cover for a public highway is 2m. The depths of highway crossings are also influenced by third party services and the depth of adjacent ditches present.
Third Party Services
3.3.4 Third party crossings may be crossed using open cut or non-open cut techniques. The crossing methods to be employed will be determined once geotechnical data and trial holes are completed and ground condition have been established. From a cathodic protection perspective the minimum separation distance between the pipe and third party services is 0.6m, however the actual separation distance is determined by the third party requirements (typically greater than 1m separation is required) and ground
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 40
The Yorkshire and Humber CCS Cross Country Pipeline
conditions. The majority of services are located within the first 2m of cover; however this is not wholly inclusive, some infrastructure (sewers for example) can be significantly more. Where infrastructure is greater than 5m deep, the pipeline should cross over the top.
3.3.5 The crossing of third party services will be subject to protective provisions as set out in Schedule 11 of the draft DCO or by separate agreement set up with individual utilities or statutory undertakers.
Watercourses – Main Rivers
3.3.6 Watercourse crossings can be several hundred metres in width requiring specialist crossing techniques such as horizontal directional drill (HDD), pipe-jacking or tunnelling. The depth and length of the crossing is influenced by; the true clean bottom of the watercourse, the ground and groundwater conditions, whether the watercourse is navigable, the Environment Agency’s requirements and the flexibility (bend radius) in the pipe and installation equipment.
3.3.7 For main rivers the pipeline should be located at such a depth as to give a depth of cover of not less than 2 m from the true clean bottom of the water course, after the removal of any silting, to the top of the pipe, and to maintain a depth of cover of not less than 1.2 m in the adjoining fields.
3.3.8 For tunnels the main river crossings will be set back a minimum distance of 10m from river banks / flood defences to comply with Environment Agency requirements. The set back distance will be considerably greater for HDD (typically 100m) to enable the parabolic trajectory of the pipe to reach the required depth under the watercourse.
Ordinary Watercourses
3.3.9 For ordinary watercourse and ditches, the pipeline should be located at such a depth as to give a depth of cover of not less than 1.7m from the true clean bottom of the water course, after the removal of any silting, to the top of the pipe, and to maintain a depth of cover of not less than 1.2m in the adjoining fields.
Rail Crossings
3.3.10 The minimum depth of cover required over the pipeline at railway crossings will be determined by Network Rail requirements specified in the “Design and Construction of Undertrack Crossings” NR/SP/CIV/044 and site specific conditions. Until ground and seasonal groundwater conditions and
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 41
The Yorkshire and Humber CCS Cross Country Pipeline
geotechnical information are known the pipe depth of cover cannot be determined.
3.3.11 According to Network Rail specification NR/SP/CIV/044 pipelines, shall be laid at a minimum depth of 1.8m below the underside of the railway sleeper unless otherwise justified by a risk assessment. Where reasonably practicable, Network Rail recommend the minimum depth for non-open cut crossings methods shall be 4.0 m from the highest part of the undertrack crossing to the underside of the railway sleeper.
3.3.12 Various crossing techniques can be used to cross Network Rail infrastructure. Historically rail crossings have been successfully undertaken using a microtunnel technique on previous National Grid projects. It is therefore likely that a microtunnel using a 1500mm diameter concrete sleeved tunnel housing the 600mm diameter steel pipeline, with a fully grouted annular space, would be designed for both railway crossings.
3.3.13 The crossing design (including the length, depth and crossing method) and construction arrangements will be subject to a basic asset protection agreement between National Grid and Network Rail. The detailed design of the tunnels shall be agreed in the form of an “Approval in Principle” obtained from Network Rail as outlined in Network Rail standard for “Engineering Assurance of Building and Civil Engineering Works” NR/L2/CIV/003 and controlled by form NR/L2/CIV/003/F001.
3.4 DURATION OF CROSSINGS
3.4.1 Estimated duration of works for the following crossings:
River Ouse HDD 2 -3 months
River Hull Microtunnel 3 months
Railways Microtunnel 2 months
Road / Watercourse Auger Bore 2 weeks
Road / Watercourse Open Cut 1 day installation 3 days including preparation
3.5 PIPELINE TESTING PROCEDURE
3.5.1 After the pipeline has been laid it will be cleaned and tested. This will take the form of a hydrostatic test (undertaken in sections) which involves filling the pipeline completely with water and raising the pressure to a pre-specified level for a 24 hour period. Before hydrostatic testing the pipeline will be cleaned and internally checked using air driven cleaning and gauging equipment known as ‘PIG’ (Pipeline Internal Gauge).
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 42
The Yorkshire and Humber CCS Cross Country Pipeline
3.5.2 Typical solid wastes from the pigging operation prior to hydrostatic test will be mill scale, weld splatter, rust and other such debris. Arrangements will be made at the test locations to contain and collect this waste for subsequent disposal to an appropriately licensed waste facility.
3.5.3 The pipeline will be tested in a number of separate sections, which will be determined by the topography of the pipeline route and sources of water for the hydrostatic test. The contractor will consult the Environment Agency to locate an appropriate source of water. This will be considered further at the detailed design stage. Abstraction and discharge licences and consents will be applied for in accordance with Environment Agency requirements.
3.5.4 After successful cleaning, the pipeline is filled with water and pressurised for the designated test period. The pipeline is then depressurised under controlled conditions and the water discharged. Prior to discharge, the water will be analysed to check quality. Filters and break tanks may be used to control the rate of discharge and remove any solids.
3.5.5 The River Ouse has been identified as a potential water source for the southern pipeline sections; potential water sources for the northern pipeline sections have yet to be determined. These will be identified and discussed with the Environment Agency and relevant IDB/LLFA as appropriate. An option is to use water abstracted during de-watering operations required to facilitate safe and dry working conditions for pipeline construction e.g. the special crossing at the River Hull and Driffield Canal.
3.5.6 Water would be abstracted at a rate agreed with the Environment Agency; lagoons may need to be constructed to hold water until sufficient volumes are available to fill test sections. Water will be returned to source after testing. Discharge rates will be agreed with the Environment Agency and measures may be taken to aerate the water and minimise risk of scour to bed and banks in accordance with Environment Agency requirements.
3.6 COMMISSIONING
3.6.1 On completion of hydrostatic testing and discharge of test water the separate test sections will be welded together to form a complete length of pipeline.
3.6.2 A final gauge plate survey is carried out. This involves an aluminium gauge plate being passed through the pipeline with a diameter 5% less than the smallest internal diameter of the pipeline. If the plate is damaged indicating a defect in the pipeline, sections of the pipeline are cut up and re-tested until the damaged section is found. Alternatively a mechanical calliper PIG is used to locate the damage. The calliper survey will give a fingerprint of
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 43
The Yorkshire and Humber CCS Cross Country Pipeline
the pipeline, picking up welds, changes in wall thickness and any dents. (See Section 3.7 In-line Inspection).
3.6.3 It is important at this stage to remove all traces of water to ensure dry Carbon Dioxide is transported on commissioning. The pipeline will therefore be swabbed to remove residual water by passing through specially designed PIGs propelled by compressed air.
3.6.4 This is followed by pre-commissioning, which is the process by which the pipeline is conditioned ready to receive Carbon Dioxide. This is carried out by a specialist contractor, by a combination of air drying and vacuum drying, or other suitable processes.
3.6.5 Air-drying is achieved by the introduction of super dry air along the pipeline in order to carry the residual moisture to a suitable venting point. Vacuum drying involves reducing the pressure within the pipeline by gradual removal of air using a vacuum pump. This lowers the boiling point of the residual water causing it to vaporise and hence be removed.
3.6.6 Once this is achieved, the pressure in the pipeline can be equalised by the use of dry air or nitrogen. After drying, the pipeline may be filled with nitrogen prior to being commissioned with Carbon Dioxide. The nitrogen may be compressed to 60 bar and then vented from the pipeline to allow the pipeline to fill with Carbon Dioxide. Venting will take place offshore.
3.7 CONDITION MONITORING
Corrosion Protection
3.7.1 Two anti-corrosion methods will be used to ensure the integrity of the pipeline. Firstly, the pipe will be coated in the factory with a fusion-bonded epoxy coating system. After testing of the welds, the bare welds are field-coated to an equivalent standard by a specialist field team, using a mobile coating rig. Prior to lowering the pipe into the trench testing is undertaken of the pipeline coating.
3.7.2 The second method is the use of a cathodic protection (CP) system. This system, reverses corrosion currents present in the soil by the creation of a pipe to soil negative potential. There are two types of CP system, sacrificial anode and impressed current. The design of the cathodic protection system will be to National Grid specifications and the recommendation of BS 7361 Part 1, 1991.
3.7.3 Ground beds for the impressed current cathodic protection system will be located within 150m of the block valve sites. Sacrificial anodes will be
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 44
The Yorkshire and Humber CCS Cross Country Pipeline
located at pre-determined places along the route of the pipeline and within AGIs.
3.7.4 A close interval electrical potential survey of the pipeline will be undertaken as soon as possible after commissioning of the cathodic protection system, in order to validate and provide a finger print of the cathodic protection system. The system will be revalidated by subsequent surveys at intervals not exceeding ten years.
In-line Inspection
3.7.5 In-line inspection involves passing an inspection vehicle, known as an intelligent PIG, through the length of the pipeline. This vehicle records, describes and sizes any pipeline defects and also locates them with a high and consistent degree of accuracy.
3.7.6 There will be a complete run through the pipeline by an intelligent PIG in order to produce a ‘finger print’ to give an indication of initial condition within the first twelve months of pipeline operation. Subsequent runs will compare the information recorded against the ‘finger print’ to give an indication of deterioration.
3.7.7 The pipeline will be designed, constructed and tested to the highest standards at every stage before it enters operation but it is also essential to preserve pipeline integrity in order to maintain flow of Carbon Dioxide and to maintain adequate levels of safety. Any deterioration in structural condition must be anticipated and the use of the on-line inspection vehicle is an efficient means of achieving this and ensuring that the pipeline is fit for purpose.
3.8 PROGRAMME OF PIPELINE CONSTRUCTION
Pipeline construction will be programmed for completion in one pipeline construction season (April – end of September). With some preliminary works being undertaken prior to construction such as hedgerow removal which needs to be conducted before March to avoid the bird nesting season.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 45
The Yorkshire and Humber CCS Cross Country Pipeline
4.1 CONSTRUCTION OF ABOVE GROUND INSTALLATIONS
4.1.1 The above ground installations (AGI) will be designed and constructed in accordance with PD 8010:Part 1 2004 Code of Practice for Pipelines – Steel Pipelines on Land and, where appropriate, the American Society of Mechanical Engineers piping code ASME B31.3 on Process Piping.
4.1.2 Descriptions of the above ground installations are provided in the Design and Access Statement (Document Reference 7.3).
4.1.3 This section relates to the construction of:
• Drax PIG Trap (Work No, 1A • Tollingham Block Valve (Work No.6A); • Dalton Block Valve (Work No.9A); • Skerne Block Valve (Work No. 11A); and • Camblesforth Multi-junction (Work No. 4A)
Phasing of Multi-junction Construction
4.1.4 The Camblesforth Multi –junction has been designed on a flexible basis. The site will be large enough to accommodate up to five PIG Trap arrangements, however, initially only two PIG Trap arrangements will be installed. There will be sufficient space within the initial security fence to install the additional three PIG Trap arrangements, without the need to extend the site.
4.1.5 The additional three PIG Trap arrangements can either be installed all together in the same construction period or installed separately depending on requirements. Adequate isolation valves are provided to allow, if required, the following phasing of the Camblesforth Multi-junction:
• Phase 1 – Installation of first two PIG Trap arrangements inlet from Drax and outlet PIG trap to Barmston.
• Phase 2 – Installation of additional 3rd PIG Trap arrangement • Phase 3 – Installation of additional 4th PIG Trap arrangement • Phase 4 – Installation of additional 5th PIG Trap arrangement
4 Constructing Pipeline Installations
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 46
The Yorkshire and Humber CCS Cross Country Pipeline
4.1.6 Phases 2, 3 and 4 can be installed all together or separately depending on requirements.
4.1.7 The landscape proposals have also been designed to allow the main screening elements to be retained during subsequent phases of construction.
Temporary Construction Compound
4.1.8 At each AGI a temporary construction compound and laydown area will be required with an estimated area 2.5 times the size of the installation footprint. The area estimated is based on National Grid custom and safe working practise and is required to accommodate:
• site office, welfare and security facilities; • power supplies; • enclosures; • pipe, equipment and fittings storage; • plant storage; • fabrication area; • waste storage areas; • spoil storage areas; • internal haul roads; • access parking; and • water management areas.
4.1.9 At Drax PIG Trap AGI the construction compound and working area required for the AGI and connecting pipeline sections will overlap with the temporary laydown areas required for the White Rose CCS Project. The construction works will be co-ordinated with that for the White Rose CCS Project to ensure adequate space and access for the construction of both developments. National Grid is in consultation with the White Rose CCS Project and together intend to agree an integrated programme and framework to manage the two construction procedures. Mechanisms will be in place for the co-ordination of those works.
AGI Access for Construction
4.1.10 Temporary access will be required off the public highway during construction. This will either be gained via the pipeline working width; via an existing access track; or via a new access.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 47
The Yorkshire and Humber CCS Cross Country Pipeline
Drax PIG Trap ‐ existing track off New Road; Tollingham Block Valve ‐ pipeline working width / new access
track off Skiff Lane; Dalton Block Valve ‐ pipeline working width / new access
track off Lund Wold Road; Skerne Block Valve ‐ pipeline working width/ existing access
track off Main Street, Skerne; Camblesforth Multi-junction ‐ pipeline working width / new access
track off Wade House Lane/A645.
AGI Construction Process
4.1.11 Construction will follow the following sequence:
• Site preparation / temporary access and laydown areas; • ground works/below ground bases and plinths/ below ground
pipework (piping bridles and by-passes, insulation joints, valves); • civils (concrete base for instrument building, concrete blocks to
support pipework, ducting); • above ground pipework (actuators and thermal relief valves); • instrument building and associated photovoltaic cells and turbine; • electrical and instrumentation installation (instrumentation, electrical
cables, earthing protection, satellite dish, control and telecommunications cables, utility metering);
• service connections (electricity and telecommunications); • cathodic protection; • finishing (vehicular access, turning areas and pedestrian access
surfacing, security fencing); • permanent access road from public highway; • post and rail fencing, landscape works and planting; • demobilisation and reinstatement of temporary works areas; • testing and commissioning.
4.1.12 Post and rail fencing will be installed and the area surrounding the compound will be seeded and planted in the first appropriate season following the completion of construction.
Programme
4.1.13 The construction period for each of the above ground installations is estimated as follows:
• Drax PIG Trap AGI 4 months
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 48
The Yorkshire and Humber CCS Cross Country Pipeline
• Block Valves 4 months • Camblesforth Multi-junction 6 months
4.2 CONSTRUCTING BARMSTON PUMPING STATION
Phasing of Pumping Station Construction
4.2.1 Barmston Pumping Station will be designed on a flexible basis. To achieve an initial capability of 2.6mt per year which would require 2-3 pump units and VSDs, only one pump housing enclosure, the PIG Trap arrangements, filtration, metering and analysers need be installed. The pump housing for additional pump units can be installed at a later date if required, with the buildings designed in such a manner that they can be phased for construction.
4.2.2 The later works can all be installed within the initial security fence, without the need to extend the site.
4.2.3 Adequate isolation valves are provided to allow the following phasing of the Barmston Pumping Station, potentially as follows:
Phase 1
• Installation of PIG Trap arrangements, inlet from onshore pipeline and outlet to offshore pipeline, filters, meters and analysers;
• Installation of pipework (suction and discharge headers and pipework, plus recycle arrangements / cooling); and
• Building for first four pump units. The actual pumps can be installed as and when needed.
Phase 2
• Installation of the pipework (suction and discharge headers / pipework); and
• building for the final four pump units. The actual pumps can be installed as and when needed.
4.2.4 If required phases 1 and 2 can be constructed within the same period. The Pumping Station will be an electric drive station which would initially require a single 66kV connection from the District Network Operator and a substation within the site. Sufficient space will be allowed within the substation design to accommodate additional transformers as future demand requires.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 49
The Yorkshire and Humber CCS Cross Country Pipeline
Temporary construction compound
4.2.5 The first stage would be to establish the temporary construction compound and working area of approximately 10ha. The area estimated is based on National Grid custom and safe working practise and is required to accommodate:
• site office, welfare and security facilities; • utilities and power supplies; • enclosures; • pipe, equipment and fittings storage; • general stores; • fabrication offices; • fabrication area; • mechanical laydown areas; • waste storage areas; • spoil handling and storage areas; • internal haul roads; • access, parking; and • water management areas.
Access for Construction
4.2.6 Access will be required off the public highway during construction. This will either be gained via a track along the route of the pipeline working width or via a new access track from Sands Road. Temporary surfacing will be installed suitable for the construction period.
Construction Process
4.2.7 Construction will involve the following:
• Site preparation (levelling, temporary access and laydown areas); • service connections (water supply works, foul drainage provision,
surface water management system and culverting); • ground works/ below ground pipework (piping bridles and by-passes,
insulation joints, valves), tanks and troughs; • civils (foundations for buildings, concrete blocks to support pipework,
building structures, security fencing, ducts); • earthworks (gabion walls, landform profiling); • pump and VSD installation; • above ground pipework (PIG Traps, meters, filtration and vents);
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 50
The Yorkshire and Humber CCS Cross Country Pipeline
• electrical and instrumentation installation (instrumentation, electrical cables, earthing protection, satellite dish, control and telecommunications cables, utility metering etc);
• finishing (vehicular access, turning areas and pedestrian access surfacing);
• permanent access road from public highway; • post and rail fencing, landscape works and planting demobilisation
and reinstatement of temporary works areas; • testing and commissioning.
Site Preparation
4.2.8 The location, layout and access to the temporary works area will be carefully considered in conjunction with the location and layout of the permanent works. Temporary fencing will be erected around the working area.
4.2.9 Topsoil will be stripped from the temporary and permanent works areas. Most of this topsoil will be used to reinstate the temporary compound area and for the landscape works around the Pumping Station. The full depth of the topsoil will be stripped and stored carefully to one side of the working area in such a way that it is not mixed with subsoil or trafficked over by vehicles or plant.
Groundwork
4.2.10 Groundwork would follow including the preliminary works for the construction of the access roads and hard standings.
4.2.11 Excavation and installation of below ground piping, piping bridles and bypasses, Pumping Station bypass, insulation joints, valves (including non-return valves, isolation valves).
4.2.12 The time excavations are kept open shall be kept to a minimum. The sequence of excavations and storage of spoil on site shall be carefully planned and managed. Spoil removed from the site would be used to landscape the surroundings of the compound.
Civils
4.2.13 Once the excavation works were complete the foundations of the buildings and structures would be constructed. The mounded landforms which encompass the site would be created. The walls and the roofs of the buildings would be constructed followed by the internal works including the installation of the pumps and the electrical installation and controls.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 51
The Yorkshire and Humber CCS Cross Country Pipeline
4.2.14 Civils works include construction or installation of above ground pipe supports, local and remote instrument building and associated photo voltaic cells and turbine, control and administration building, pump housing, air and nitrogen building, sub-station base, switchroom, variable speed drive containers, metering buildings, analyser building, associated bottle store and hard standing, hard standing for temporary generator, backfilled pits and chambers, gated security fence and cameras, pedestrian access, lighting columns, satellite dish, weather station, troughs, trays and ducting.
4.2.15 The sequence of working will be carefully planned and managed for example to ensure construction considers working traffic and access with those civils components furthest from the access locations undertaken first; ensuring stable ground is available for subsequent civils activities.
Above Ground Pipework
4.2.16 Installation of two PIG Trap areas, filtration, meters, analysers, actuators, vents and vent stack, coolers and chillers. Installation of pumps and variable speed drives as required.
Electrical and Instrument Installation
4.2.17 Construction or installation of electricity sub-station HV switchgear, electrical cables, earthing protection, instrumentation, satellite dish, control and telecommunications cables, utility metering, intruder detection systems and closed circuit television, cathodic protection facility including a transformer rectifier kiosk, anode canisters, electrical and cathodic protection cables, utility supplies, meters and cabling, earthing protection, backfilled pits and chambers, troughs, trays, ducting, drainage and drainage attenuation.
Finishing
4.2.18 The final stage would be the surfacing of internal vehicular access routes, turning areas and pedestrian areas. Permanent access road from public highway. The grading/contouring of the site, replacement of topsoil and implementation of the landscape scheme, including ponds, tree, shrub and hedge planting and the erection of protective post and rail fencing.
Testing and Commissioning
4.2.19 For hydrostatic testing some excavations are required to be left open (for draining of valves etc). As a principle as much works as possible should be completed prior to testing, including partial backfill and reinstatement.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 52
The Yorkshire and Humber CCS Cross Country Pipeline
High Voltage Electricity Connection
4.2.20 Construction of a new 66kV electricity connection from the Driffield –Bridlington High Voltage Overhead Power Line approximately 6km to the North to the electricity sub-station within the Barmston Pumping Station site will be carried out by Northern Power Grid.
4.2.21 Routeing of the buried 66kV cable connection will take into account the environmental, socio-economic and technical and safety constraints.
Programme
4.2.22 The construction period for the Barmston Pumping Station is programmed for 24 months.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 53
The Yorkshire and Humber CCS Cross Country Pipeline
5.1 INTRODUCTION
5.1.1 The landfall crossing will be several hundred metres in length requiring specialist crossing techniques. The depth and length of the crossing is influenced by; the low and high water tide marks, the onshore and offshore ground and groundwater conditions (in particular the depth to the chalk) and the flexibility (bend radius) in the pipe and installation equipment.
5.1.2 The coastline in this area of the Holderness coast is characterised by cliffs of unconsolidated glacial till which are susceptible to coastal erosion. Due to the coastal erosion rates a conservative minimum 200m set back distance from the present cliff line has been determined for any onshore works. The landfall crossing depth will be sufficient to ensure the pipeline is not exposed due to variation in beach height and coastal erosion during the life of the project.
5.1.3 The options currently recommended for landfall construction subject to the completion of further surveys are: tunnelling (including direct pipe) and horizontal directional drill (HDD). The identification of the preferred option will be determined through the subsequent FEED design phase. At this stage, however, open cutting the beach cliff has been discounted due to the expected nature of the cliff substrates.
5.1.4 The landfall options consider both a ‘wet tie-in’ location for the connection of the proposed offshore pipeline (beyond the mean low water mark (MLWM)) and a ‘beach tie-in’. For the beach tie-in arrangement a conservative distance of 10m seaward of the cliff for the reception pit has been assumed.
5.2 LANDFALL TEMPORARY WORKING AREA
5.2.1 For the landfall crossing a temporary construction compound and working area capable of supporting either the tunnelling or HDD crossing techniques set up is required onshore. This would be located at the landward end of the landfall crossing.
5.2.2 Typically the construction compound and temporary working area would accommodate the following as appropriate:
• drive shaft,
5 Landfall Construction
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 54
The Yorkshire and Humber CCS Cross Country Pipeline
• tunnel boring / horizontal directional drill rig, • control cabin, • crane working areas, • dewatering systems, • water tanks, • spoil storage, • spoil separators, • settlement lagoons, • materials and pipe storage area, • waste storage area, • workshops and stores, • generators and switchgear, • air receivers and compressors, • oil stores, • welfare facilities, • offices, security, • access to the drive shaft/ drill rig, and • parking.
5.3 DESIGN STANDARDS
5.3.1 The offshore pipeline and landfall crossing will be designed, constructed and operated in accordance with the following approved British Standards Institution (BSI) published documents (in addition to legislative requirements):
• PD8010 “Code of Practice for Pipelines – Part 1: Steel Pipelines on Land”
• PD8010 “Code of Practice for Pipelines – Part 2: Subsea Pipelines”
5.4 GEOLOGY
5.4.1 The published geological records for the area show the site to be underlain by superficial deposits of the Quaternary Period comprising alluvium at the western end of the site approach and glaciofluvial deposits towards the coastal end of the approach. Alluvium is identified in the British Geological Survey (BGS) Lexicon as comprising clay, silt, sand and gravel; the glaciofluvial deposits as sand and gravel.
5.4.2 The superficial deposits are underlain at an unspecified depth by the Rowe Chalk of the Cretaceous period. The Rowe Chalk is described in the BGS Lexicon as “white, flint-bearing chalk with sporadic marl bands”.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 55
The Yorkshire and Humber CCS Cross Country Pipeline
5.4.3 To date 8 boreholes have been undertaken at the landfall location (see Figure 4 below). All of the boreholes initially encountered topsoil, which varied in depth from 0.30 to 0.40m.
5.4.4 Material thought likely to be glaciofluvial in origin were encountered in boreholes BH275 to BH279 to depths of between 1.10m and 3.00m generally becoming thicker towards the coast. The material varied from sandy clay (BH275 proved to a depth of 1.80m), to sand (BH279 to a depth of 3.00m) and sand over gravel (BH278 to a depth of 2.70m).
5.4.5 Gravelly clay presumed to be glacial till was encountered underlying the topsoil in boreholes BH270 to BH274 and underlying the glaciofluvial deposits in boreholes BH275 to BH279. Beds of sand and or gravel were encountered within this horizon at various depths up to 3.20m thick. In general there appears to be a distinct bed of granular material running through the site with a top depth of between 7.80m and 9.80m.
5.4.6 Weathered chalk was encountered at a depth of between 17.40m and 20.70m underlying the till in boreholes BH270 to BH279. In boreholes BH280 and BH281, drilled on the foreshore, the chalk was encountered at a depth of 16.70m. In general this was recovered as gravel and cobble size fragments of chalk with fines. Even when rotary coring was carried out much of the material was recovered as broken fragments of chalk indicative of a highly fractured state.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 56
The Yorkshire and Humber CCS Cross Country Pipeline
Figure 4 Simplified Geotechnical Cross Section of Landfall (Onshore)
5.5 TUNNEL OPTION
5.5.1 The tunnel option would involve the construction of a concrete sleeved tunnel beneath the landfall cliff line within which the Carbon Dioxide transportation pipeline would then be installed.
5.5.2 The tunnel alignment would be identified following the completion of further surveys. In recognition of this some flexibility has been allowed for within the Limits of Deviation shown on the Works Plans.
Drive Shaft Installation
5.5.3 A dewatering system and drive shaft would be constructed. The depth of the shaft would be a function of the cliff height, the depth of burial of the pipeline under the beach and the slope of the tunnel. Upon reaching the required depth a concrete base will be cast to protect the formation, support subsequent activities and act as a base strut.
5.5.4 Upon completion of the drive shaft a concrete thrust wall would be installed on the back wall and hydraulic rams and tunnel boring machine (TBM) lowered in to position to allow the tunnelling to commence.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 57
The Yorkshire and Humber CCS Cross Country Pipeline
Tunnelling
5.5.5 The TBM launch makes use of the back wall (thrust wall) of the drive shaft to provide a reaction to the thrust loads generated by hydraulic rams to push the concrete sections and TBM forward to form the tunnel.
5.5.6 The tunnel would proceed with a near horizontal, slightly upward gradient (typically around 1 degree) to ensure the tunnel minimises the crossing of ground lithology and any localised water encountered flows to the drive shaft for sump pumping and water management.
5.5.7 The tunnelling would be a 24 hour a day operation. Operational 24 hour lighting would be required on the tunnelling option; consideration to lighting and noise will be addressed in the Contractor’s Environmental Management Plan and in consultation with the relevant authority (refer to Code of Construction Practice, Document Reference 7.5). It is anticipated the tunnelling operation could take up to 8 months, depending on the final length and rate of progress in the given ground conditions.
5.5.8 The tunnel spoil would be collected in purpose built settlement lagoons. The heavier clays and rock will be removed by natural settlement. The material retrieved could be treated for use to create a mounded landscape at the pumping station.
5.5.9 The tunnel would be maintenance free whilst in operation with no access provided in the long term.
5.5.10 Upon completion of the tunnel drive the rear wall of the drive shaft would be removed to allow for the pipe installation activities.
Pipe Installation
5.5.11 For the direct pipe, tunnelling and pipeline installation is carried out in one operation. The pipe is welded to the end of the tunnel boring machine and pushed forward by rams which push the microtunelling machine forward together with the pipeline.
5.5.12 For the concrete section tunnel different installation techniques exist for the installation of the product pipeline.
5.5.13 The pipeline could be welded on land and pulled towards the sea, this can be achieved via:
• a slip trench connecting to the drive shaft to allow the pipe to be welded on land and pulled into the tunnel via the slip trench; or
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 58
The Yorkshire and Humber CCS Cross Country Pipeline
• pipe lengths being individually lowered into the drive shaft and welded, as each section is pulled into the tunnel the next pipe section is welded on;
• the welded pipe may be pulled through the tunnel by a vessel located nearshore or by a winch in the reception shaft.
5.5.14 Alternatively the pipe could be welded offshore and pulled towards the land, this can be achieved via:
• pipe lengths being welded on a vessel (shallow bottom barge) as each section is pulled into the tunnel the next pipe section is welded on;
• the welded pipe is floated or supported on barges offshore and a winch located onshore in the drive shaft to pull the pipe through the tunnel.
5.5.15 A dredged channel would be required to enable a vessel and associated winch system to be established of suitable rating to be able to pull the pipe through the tunnel.
Reception Shaft and Tie In
5.5.16 The reception pit may be located within the intertidal zone or beyond the Mean Low Water Mark. The DCO application includes a deemed Marine Licence to cover works within the intertidal zone. The final location of the reception shaft will depend upon the results of nearshore surveys and take account of the seasonal variation in beach height as well as continuing coastal erosion.
5.5.17 The sheet piled (or similar) reception shaft would be sized to enable the safe recovery of the TBM as well as facilitate the connection/tie-in to the offshore pipeline. The TBM would enter the reception pit via a hole cut out of the sheet piled wall.
5.5.18 A cofferdam may be required to provide a channel within which the offshore pipeline can be brought onshore to the tie-in point within the reception pit. This would be of sheet piled construction and have likely dimensions of 6m wide, 200m long and be excavated to a depth of 2.5m. The cofferdam will comprise a “dry section” above the mean low water mark and a “wet” section extending into the nearshore area.
5.5.19 The offshore pipeline would be pulled ashore from a lay barge. The pull ashore would require an appropriately rated winch to be set up within the reception pit and to be suitably anchored.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 59
The Yorkshire and Humber CCS Cross Country Pipeline
5.5.20 After the pull ashore the offshore section of pipeline is welded or connected/tied-in to the onshore section of the pipeline within the reception pit.
5.5.21 Following the tie-in connection the cofferdam will be backfilled and the cofferdam piles will either be cut back to an agreed depth below beach level or preferably removed completely.
5.5.22 A ‘wet’ tie-in location (beyond the mean low water mark) would require a piled reception pit, but no cofferdam or a much shorter cofferdam would be required. It would also avoid the need for works on the beach.
Spoil
5.5.23 The majority of the material excavated from the drive shaft and tunnel would be incorporated into the landscape design for the pumping station if it is suitable. Upon completion of the works material remaining on site that would be classified as suitable fill will be used to backfill the drive shaft structure. Where possible no spoil would be sent to landfill, however this will depend on the TBM used and the nature of the material generated.
5.5.24 Spoil excavated for the reception shaft and/or cofferdam will be stored on the beach adjacent to the cliff.
Construction Access to the Beach
5.5.25 A low section of the cliff line at Low Grounds has been included within the Development Consent Order Limits to facilitate beach access. Access from the public highway would be along the pipeline working width or via the access for Barmston Pumping Station.
Third Party Services
5.5.26 There are no known recorded, public or private utilities between the start of the landfall crossing on land and the beach.
Tunnel Programme
5.5.27 The tunnelling option would typically include the following:
• Mobilise to Site & Establish Compounds • Install Drive Shaft • Install and Commission Dewatering System • Excavate Drive Shaft and Install Support Frames & Base • Construct headwall and base for launch • Set Up and Install Tunnel Boring Machine • Install Reception Shaft
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 60
The Yorkshire and Humber CCS Cross Country Pipeline
• Drive Tunnel to Reception • Survey Tunnel • Install Pipeline Rollers and Brackets • Install Pipeline to tie-in pit • Install cofferdam • Dredge channel • Pull in offshore pipeline to tie-in pit • Tie-in weld • Test Pipeline • Backfill Tunnel, shafts and excavations • Reinstatement • Demobilise
5.5.28 It is anticipated that up to 8 months would be required to complete the landfall crossing using the tunnel technique. It will take around 1 month to mobilise, 1 month dewatering, 3 weeks to establish the drive shaft, 2 months tunnelling (24 hour operation), 2 months for insertion of the pipe and tie in (Direct Pipe technique would only require tie-in), and 1 month to demobilise. Works would take place on the beach for up to 6 months.
5.6 HORIZONTAL DIRECTIONAL DRILL OPTION
5.6.1 The HDD method involves the drilling of an open bore with a diameter greater than that of the pipeline to ensure it can be pulled through.
HDD Bore
5.6.2 HDD involves the drilling of a hole through which the pipeline would be installed. A HDD drilling rig would be set up inland from the cliff and drill towards the connecting/tie-in point which would be located either on the beach or beyond the low tide level for subsea connection.
5.6.3 The HDD option is usually a series of 24 hour operations, commencing with the drilling of a pilot bore, a reamer is then connected to the drill string and the pilot hole is reamed out by progressively larger reamers until the diameter of the hole is sufficiently large to accommodate the pipeline. The hole remains uncased. Pressurised bentonite slurry (bentonite mixed with freshwater) is utilised to assist the drill, flush cuttings from the hole and stabilise the borehole walls.
5.6.4 Bentonite containment will be addressed in the Contractor’s Environmental Management Plan in consultation with relevant authorities. It is anticipated the HDD operation could take up to 3 months, depending on the final length and rate of progress in the given ground conditions.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 61
The Yorkshire and Humber CCS Cross Country Pipeline
5.6.5 The HDD bore is maintenance free on completion with no access provided in the long term.
Drilling Compound Installation
5.6.6 A drilling compound would be set up on the landward end of the drill. Activities may include the casting of anchor blocks to stabilise the HDD rig. Potentially a shallow slip trench would be excavated to facilitate the launch of the HDD.
Pipe Installation
5.6.7 The pipe may be pulled through the open bore via either a winch offshore (on a shallow bottom lay barge or in the reception pit) to pull the pipe towards the sea or; the pipe is floated or supported on barges offshore and a winch located onshore to pull the pipe inland.
Reception Pit and Tie In
5.6.8 The reception pit/ cofferdam may be located within the intertidal zone or beyond the Mean Low Water Mark. The DCO application includes a deemed Marine Licence to cover works within the intertidal zone. The final location of the reception pit will depend upon the results of nearshore surveys.
5.6.9 A cofferdam may be required to provide a channel within which the offshore pipeline can be brought onshore to the tie-in point within the reception pit. This would be of sheet piled construction and have likely dimensions of 6m wide, 200m long and be excavated to a depth of 2.5m. The cofferdam will comprise a “dry section” above the mean low water mark and a “wet” section extending into the nearshore area.
5.6.10 The offshore pipeline would be pulled ashore from a lay barge. The pull ashore would require an appropriately rated winch to be set up within the reception pit and suitably anchored.
5.6.11 A ‘wet’ tie-in location (beyond the mean low water mark) would require a piled reception pit, but no cofferdam or a much shorter cofferdam would be required. The feasibility of a wet tie-in option will be investigated at the next design phase.
Spoil
5.6.12 The bentonite slurry from HDD operations returned to the bentonite lagoons would be screened, dewatered and incorporated into the Pumping Station landscaping, with the appropriate transfer licences in place. This will be
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 62
The Yorkshire and Humber CCS Cross Country Pipeline
addressed within the Contractor’s Environmental Management Plan in consultation with relevant authorities. Where possible no spoil would be sent to landfill, however this will depend on the nature of the material generated.
5.6.13 Spoil excavated for the reception shaft and/or cofferdam will be stored on the beach adjacent to the cliff.
Construction Access to the Beach
5.6.14 The HDD rig could weigh up to 70 tonnes therefore a suitable haul road (width and height) will be constructed from the Pumping Station to the drill site on land and to haul other plant down to the beach.
5.6.15 A low section of the cliff line at ‘Low Grounds’ has been included within the Development Consent Order Limits to facilitate beach access. Access from the public highway would be along the pipeline working width or via the access for Barmston Pumping Station.
Third Party Services
5.6.16 There are no known recorded, public or private utilities between the start of the landfall crossing on land and the beach.
HDD Programme
5.6.17 The HDD Option would typically include the following:
• Mobilise to Site & Establish Compounds; • Establish HDD Anchor Blocks; • Set Up HDD Rig; • Install Reception Pit; • Install Pilot Bore; • Ream Bore; • Weld Pipeline String (onshore or offshore); • Install Winch; • Place Pipeline on Rollers / Offshore Floatation or Barge; • Install pipeline under cliff; • Install reception pit/ cofferdam; • Dredge channel; • Pull in offshore pipeline to tie-in pit; • Tie-in weld; • Test Pipeline;
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 63
The Yorkshire and Humber CCS Cross Country Pipeline
• Backfill excavations; • Reinstatement ; • Demobilise.
5.6.18 It is anticipated that up to 3 months would be required to complete the landfall crossing using the HDD technique. It will take around 3 weeks to mobilise, 6 weeks to complete the crossing, 1 week to insert the pipe and tie in, plus 3 weeks to demobilise.
5.7 TESTING
5.7.1 For the offshore pipeline the hydrostatic testing regime has not yet been determined. It is anticipated that inhibited sea water will be used to test the pipeline. Depending on the construction programme the landfall section may either be tested before it is connected/tied-in to the offshore pipeline or the whole offshore pipeline between the Pumping Station and the offshore installation will be tested together.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 64
The Yorkshire and Humber CCS Cross Country Pipeline
American Society of Mechanical Engineers ASME Code for Pressure Piping B31.3 – 2010 Process Piping
British Geological Survey (BGS) Lexicon of Named Rock Units https://www.bgs.ac.uk/lexicon/
British Standards Institution PD8010:Part1 2004 Code of Practice for Pipelines – Steel Pipelines on Land
British Standards Institution PD8010:Part 2 2004 Code of Practice for Pipelines – Subsea Pipelines
British Standards Institution BS 7361 Part 1, 1991 Cathodic Protection Code of Practice for land and marine applications
Health and Safety Executive A Guide to the Pipelines Safety Regulations 1996. Guidance on Regulations L82. 1996.
National Grid Specification NGC/SP/PIP/30 Specification for Carbon Dioxide Pipelines Design
National Grid Specification NGC/SP/PIP/31 Specification for Carbon Dioxide Pipelines Marker Posts.
National Grid Procedure NGC/MP/ELEC/03 Management Procedure for the Maintenance and Monitoring of Cathodic Protection for Carbon Dioxide Steel Pipeline Systems
Network Rail Specification NR/SP/CIV/044 “Design and Construction of Undertrack Crossings”
Network Rail Standard NR/L2/CIV/003 “Engineering Assurance of Building and Civil Engineering Works” and form NR/L2/CIV/003/F0
Application Documents Referenced
Access, Rights of Way and Temporary Stopping Up Plans Drawing Nos. 10-2574-GND-01-05-0060 to 0085 (Document Ref. 2.4)
Camblesforth Multi-junction Planning Arrangement Drawing No. 10-2574-GA-01-0316 (Document Ref. 2.25)
6 References
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 65
The Yorkshire and Humber CCS Cross Country Pipeline
Code of Construction Practice (CoCP) (Document Ref.7.5)
Design and Access Statement (DAS) (Document Ref. 7.3)
Drainage Report (Document Ref. 7.7)
Drainage Design Drawings (Document Ref. 2.8)
Safety Statement – Environmental Statement Chapter 4 Consultation, Technical Appendix 4.7 (Document Ref. 6.4.7)
Typical Temporary Access from Highway Drawings No. 10-2574-STD-01-1314 and 1315 (Document Ref. 2.52 and 2.53)
Typical Temporary Access From Highway Flumed Ditch Crossing Drawing No. 10-2574-STD-01-1314 (Document Ref. 2.52)
Typical Temporary Access From Highway No Flumed Ditch Crossing Drawing No. 10-2574-STD-01-1315 (Document Ref. 2.53)
Drax Pig Trap Temporary Construction Vehicular Access (New Road) Drawing No. 10-2574-PLN-01-1044 (Document Ref. 2.54)
Camblesforth Multi-junction Permanent Vehicular Access (A645) Drawing No. 10-2574-PLN-01-1045 (Document Ref. 2.55)
Tollingham Block Valve Permanent Vehicular Access (Skiff Lane) Drawing No. 10-2574-PLN-01-1046 (Document Ref. 2.56)
Dalton Block Valve Permanent Vehicular Access (Lund Wold Road) Drawing No. 10-2574-PLN-01-1047 (Document Ref. 2.57)
Skerne Block Valve Permanent Vehicular Access (Main Street, Skerne) Drawing No. 10-2574-PLN-01-1048 (Document Ref. 2.58)
Barmston Pumping Station Permanent Vehicular Access (Sands Road) Drawing No. 10-2574-PLN-01-1049 (Document Ref. 2.59)
Barmston Pumping Station Permanent Vehicular Access (Sands Road) Drawing No. 10-2574-PLN-01-1050 (Document Ref. 2.60)
Widening of Sands Road Between A165 Junction and Site Access Drawing No. 10-2574-PLN-01-1051 (Document Ref. 2.61)
Driffield Construction Compound Temporary Vehicular Access (A614) Drawing No. 10-2574-PLN-01-1053 (Document Ref. 2.63)
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 66
The Yorkshire and Humber CCS Cross Country Pipeline
Drax Pig Trap Temporary Construction Vehicular Access (New Road) Swept Path Analysis Drawing No. 10-2574-PLN-01-1054 (Document Ref. 2.64)
Camblesforth Multi-junction Permanent Vehicular Access (A645) Swept Path Analysis Drawing No. 10-2574-PLN-01-1055 (Document Ref. 2.65)
Tollingham Block Valve Permanent Vehicular Access (Skiff Lane) Swept Path Analysis Drawing No. 10-2574-PLN-01-1056 (Document Ref. 2.66)
Dalton Block Valve Permanent Vehicular Access (Lund Wold Road) Swept Path Analysis Drawing No. 10-2574-PLN-01-1057 (Document Ref. 2.67)
Skerne Block Valve Permanent Vehicular Access (Main Street, Skerne) Swept Path Analysis Drawing No. 10-2574-PLN-01-1058 (Document Ref. 2.68)
Barmston Pumping Station Permanent Vehicular Access (Sands Road) Swept Path Analysis Drawing No. 10-2574-PLN-01-1059 (Document Ref. 2.69)
Driffield Construction Compound Temporary Vehicular Access (A614) Swept Path Analysis Drawing No. 10-2574-PLN-01-1061 (Document Ref. 2.71)
Works Plans Drawings No. 10-2574-GND-01-05-0030 to 0055 (Document Ref. 2.3)
Hedgerow Plans Drawings No. 10-2574-GND-01-05-0140 to 0165 (Document Ref. 2.5)
Legislation
The Construction (Design and Management) Regulations 2007 (as amended) SI 2007 No.320
The Control of Major Accident Hazards (COMAH) Regulations 1999 (as amended 2005) SI 1999 No.743
Energy Act 2008
Petroleum Act 1998
Planning Act 2008
The Pipeline Safety Regulations 1996 SI 1996 No. 825
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 67
The Yorkshire and Humber CCS Cross Country Pipeline
Above Ground Installation
These are structures and engineering such as elements of block valves and pumping stations that will be required to be above the ground.
Actuator System for operating a valve.
Alluvium Material transported by rivers and deposited along its course.
Aquifer A body of permeable rock that is capable of storing significant quantities of water; is undertaken by impermeable material, and through which groundwater moves.
Block Valves Block valves are required for isolation and monitoring of the pipeline. These would include buried pipework, valves, an instrument building and a vent stack.
Carbon capture, transportation and storage
The process whereby Carbon Dioxide emissions from power stations and industrial facilities are captured at the source before being compressed and transported to be injected under high pressure into depleted oil and gas fields or natural saline geological formations, either onshore or offshore.
Cathodic Protection Cathodic protection is a method of protecting the pipeline from corrosion using an impressed current system.
Cofferdam A temporary steel structure constructed to allow the enclosed area to allow the sea water to be pumped out to provide a dry work environment to facilitate work. The arrangement is typically dismantled once the work is complete.
Cul de sac working See Lock-out Section.
Dense Phase Carbon Dioxide in liquid state.
Environmental Impact Assessment
The process by which the impacts of a proposed development upon all aspects of the receiving environment are identified and analysed.
Environmental Statement
Document that reports the findings of an Environmental Impact Assessment.
7 Glossary of Terms
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 68
The Yorkshire and Humber CCS Cross Country Pipeline
Flood Zones Environment Agency (EA) Flood Zones are defined as follows:
Zone 3 High risk - greater than 1 in 100 year risk of river flooding or >1 in 200 year risk of sea flooding)
Zone 2 Moderate risk - between 1 in 100 year and 1 in 1000 year risk of river flooding (1 in 200 year and 1 in 1000 year risk of sea flooding) )
Zone 1 Low risk – less than 1 in 1000 year risk of flooding from river or sea.
Limits of Deviation ‘Limits of deviation’ define the limits within which the proposed pipeline can be routed.
Local Nature Reserve
Statutory designation made under the National Parks and Access to the Countryside Act 1949, and amended by the Natural Environment and Rural Communities Act 2006, by local authorities to maintain and enhance their special wildlife and geology and provide access to nature for local communities.
Lock-out Section. These are also referred to as cul de sac working. These are areas of the development where the working width cannot be continuous due to there being no practicable method of crossing an engineering obstacle, e.g. a railway or large river. The transportation of mechanical equipment avoiding the obstacle – is required to utilise the same access for both access and egress on both sides of the obstacle – resulting in increased traffic through the access and spread.
Multi-junction An above ground facility at the connection point of a number of buried pipelines which accommodates PIG Traps for each pipeline (to allow the inspection and maintenance of the pipeline) and connecting pipework with isolation valves.
National Monuments Record
Unscheduled archaeological sites and features recorded by English Heritage.
National Nature Reserve
Designated areas by Natural England that represent many of the finest wildlife and geological sites in the country.
Navigable In the context of this document, rivers that can accommodate leisure craft and commercial boats.
Oxyfuel A technology that burns oxygen with gaseous fuel
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 69
The Yorkshire and Humber CCS Cross Country Pipeline
PIG trap A pig trap is an above ground horizontally mounted pipework vessel installed at either end of a section of buried pipeline to allow a pipeline internal gauge (PIG) to be inserted into the pipeline for the purposes of cleaning, gauging and inspection. A PIG would be launched from a pig trap at one end of the pipeline and retrieved from a pig trap at the other end of the pipeline.
Pipeline Envelope For the purposes of the Environmental Statement the total area within which pipeline works could take place has been assessed. In the event that the pipeline is eventually laid at the perimeter of the LoD, the working width to construct a pipeline could extend beyond the LoD, 15m to the left side or 22m to right side. The total area identified within which pipeline works could take place is therefore typically 136m. This wider area has been called the Pipeline Envelope. The Pipeline Envelope is wider for ‘box out’ areas at crossings where the total area identified within which pipeline works could take place is typically 151m wide (c.100m + 21m + 15m + 7.5m + 7.5m). The Pipeline Envelope also includes drainage connections and temporary construction areas.
Planning Inspectorate
On 1 April 2012, under the Localism Act 2011, the Planning Inspectorate became the agency responsible for operating the planning process for nationally significant infrastructure projects (NSIPs). The Planning Inspectorate examines the application and will make a recommendation to the relevant Secretary of State, who will make the decision on whether to grant or to refuse development consent.
Pumping Station A pumping station would re-pressurise the Carbon Dioxide to maintain the pressure in the pipeline e.g. before it is piped offshore.
Scheduled Monuments
An archaeological site of national importance, which is included on a schedule compiled by the Secretary of State for National Heritage under the terms of the Ancient Monuments and Archaeological Areas act 1979 (as amended by the National Heritage Act 1983).
Sites of Special Scientific Interest
An area of land of special interest by reason of its flora, fauna, geology or physiographical features notified under section 28 of the Wildlife and Countryside Act 1981.
Stiction Stiction is the static friction that needs to be overcome to enable relative motion of stationary objects in contact. In this case the static friction between the outer surface of the pipe and the sides of the bore that needs to be overcome to get the pipe moving again if the
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 70
The Yorkshire and Humber CCS Cross Country Pipeline
pull is interrupted.
Temporary Construction Areas
Areas required in addition to the Limits of Deviation where more temporary land take will be required during construction for access, temporary construction works including pipe lay down areas, contractor’s compounds etc.
Topography The physical features or configuration of a land surface.
Traffic Management Plan
It sets out how traffic will be managed at all stages during a construction project.
Tree Preservation Order
Tree Preservation Orders are made under the Town and Country Planning Act 1990 and the Town and Country Planning (Trees) Regulations 1999 to protect trees.
Unlikely 1 x 10-2 (1:100 or one in a hundred) to 1 x 10-4 (1:10,000 or one in ten thousand) events per kilometre year of pipeline operation
Very unlikely 1 x 10-4 (1:10,000 or one in ten thousand) to 1 x 10-6 (1:1,000,000 or one in a million) events per kilometre year of pipeline operation
Extremely unlikely < 1 x 10-6 (less than 1:1,000,000 or one in a million) events per kilometre year of pipeline operation
Variable Speed Drive
A variable speed drive is a piece of equipment that regulates the speed and rotational force, or torque output, of an electric motor.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 71
The Yorkshire and Humber CCS Cross Country Pipeline
Public Highways – Road Crossings
Ref Road Name Authority Crossing Type RDX 1 Pear Tree Avenue (Unclassified Road) NYCC Open cut
RDX 2 Carr Lane (Unclassified Road) - NYCC Non Open cut
RDX 3 Main Road (Unclassified Road) NYCC Non Open cut
RDX 4 Church Dike Lane (Unclassified Road) NYCC Non Open cut
RDX5 Brickhill Lane NYCC Open cut
RDX 6 / 7 A645 (A Road) NYCC Non Open cut
RDX 8 Church Dike Lane (Unclassified Road) NYCC Non Open cut
RDX 9 Barmby Road (Unclassified Road) ERYC Non Open cut
RDX 10 A63 Hull Road (A Road) ERYC Non Open cut
RDX 11 Brind Lane (Unclassified Road) ERYC Non Open cut
RDX 12 B1228 Wood Lane (B Road) ERYC Non Open cut
RDX 13 A614 Holme Road (A Road) ERYC Non Open cut
RDX 14 Bursea Lane (Unclassified Road) ERYC Non Open cut
RDX 15 Drain Lane (Unclassified Road) ERYC Non Open cut
RDX 16 Skiff Lane (Unclassified Road) ERYC Non Open cut
RDX 17 Lock Lane (Unclassified Road) ERYC Non Open cut
RDX 18 Sand Lane (Unclassified Road) ERYC Non Open cut
RDX 19 Cliffe Road (Unclassified Road) - ERYC Non Open cut
RDX 20 A1034 Sancton Road (A Road) ERYC Non Open cut
RDX 21 A1079 Arras Hill (A Road) ERYC Non Open cut
RDX 22 Kiplingcotes Lane (Unclassified Road) ERYC Open cut
RDX 23 Kiplingcotes Road (Unclassified Road) ERYC Non Open cut
RDX 24 Kiplingcotes Racecourse Road (Unclassified Road)
ERYC Open cut
RDX 25 Park Road (Unclassified Road) ERYC Open cut
RDX 26 Holme Wold Road (Unclassified Road) ERYC Open cut
RDX 27 Lund Wold Road (Unclassified Road) ERYC Non Open cut
Appendix A – Main Crossings
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 72
The Yorkshire and Humber CCS Cross Country Pipeline
Ref Road Name Authority Crossing Type RDX 28 Middleton Road (Unclassified Road) ERYC Non Open cut
RDX 29 B1248 Lund Road (B Road) ERYC Non Open cut
RDX 30 Middleton Road (Unclassified Road) ERYC Non Open cut
RDX 31 Unnamed road from Bracken Lane to Burnbutts Lane - (Unclassified Road)
ERYC Open cut
RDX 32 Burnbutts Lane (Unclassified Road) ERYC Open cut
RDX 33 Southburn Road (Unclassified Road) ERYC Non Open cut
RDX 34 A164 Beverley Road (A Road) ERYC Non Open cut
RDX 35 Jenkinson Lane (Unclassified Road) ERYC Non Open cut
RDX 36 Ricklepits (Unclassified Road) ERYC Non Open cut
RDX 37 B1249 Frodingham Road (B Road) ERYC Non Open cut
RDX 38 Main Street (Unclassified Road) ERYC Non Open cut
RDX 39 Gransmoor Road (Unclassified Road) ERYC Non Open cut
RDX 40 A165 Bridlington Road (A Road) ERYC Non Open cut Open cut crossings will require a temporary road closure. At each road crossing there will be temporary construction accesses.
Other Accesses off Public Highways
Ref Road Name Authority Access Type Drax Construction access
New Road (Unclassified Road) NYCC Temporary
Camblesforth Multi-junction access
A645 (A Road) / Wade House Lane (Unclassified road)
NYCC Permanent
Gateland Field Lane
Barmby Road (Unclassified Road) ERYC Temporary
Tollingham Block Valve acccess
Skiff Lane, Tollingham (Unclassified road)
ERYC Permanent
Tollingham Construction Compound access
Skiff Lane, Tollingham (Unclassified road)
ERYC Temporary
Dalton Block Valve access
Lund Wold Road (Unclassified road) ERYC Permanent
Skerne Block Valve access
Main Street, Skerne/ Road through Church Farm, Skerne (Unclassified
ERYC Permanent
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 73
The Yorkshire and Humber CCS Cross Country Pipeline
Ref Road Name Authority Access Type roads) & track to Copper Hall
Access between River Hull and Driffield Canal
Road to Skerne (Main Street), Wansford (Unclassified road)
ERYC Temporary
Access between River Hull and Driffield Canal
B1249 Frodingham Road, Wansford (B Road)
ERYC Temporary
Driffield Construction Compound access
A614, Driffield (A Road) ERYC Temporary
Barmston Pumping Station access
Sands Road, Fraisthorpe (Unclassified road) & gated track (adopted public highway)
ERYC Permanent
Landfall Construction access
Sands Road, Fraisthorpe (Unclassified road) & gated track (adopted public highway) Via pipeline working width from Barmston Pumping Station
ERYC Temporary
NYCC= North Yorkshire County Council; ERYC= East Riding of Yorkshire Council
Public Rights of Way
PRoW No. Temporary closure
Authority
Long Drax Footpath no. 35.47/6/1(as diverted)
NYCC
Long Drax Footpath No. 35.47/1/1(as diverted)
NYCC
Long Drax Footpath No. 35.47/8/1
NYCC
Long Drax Footpath No. 35.47/4/1
NYCC Crossing coincides with disused railway – trenchless crossing
Long Drax Footpath No. 35.47/5/1
NYCC Avoidable
Drax Footpath No. 35.26/7/1
NYCC
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 74
The Yorkshire and Humber CCS Cross Country Pipeline
PRoW No. Temporary closure
Authority
Drax Footpath No. 35.26/9/1
NYCC Brickhill Lane Closure of entire length of footpath required
Drax Footpath No. 35.26/13/2
NYCC
Drax Footpath No. 35.26/13/1
NYCC
Newland Footpath No. 35.49/1/2
NYCC
Newland Footpath No. 35.49/2/2
NYCC
Newland Footpath No. 35.49/3/1
NYCC
Newland Footpath No. 35.49/2/1
NYCC
Barmby on the Marsh Footpath No. 3
ERYC Trans-pennine Trail Flood bank – trenchless crossing
Asselby Footpath No. 2, ERYC Track known as Marsh Lane
Asselby Footpath No. 1 ERYC
Wressle Footpath No. 10
ERYC
Wressle Footpath No. 6 ERYC
Wressle Footpath No. 8 ERYC
Wressle Footpath No. 7 ERYC Adjacent to railway – trenchless crossing
Eastrington Bridleway No. 17
ERYC Track known as Featherbed Lane (crossed twice).
Spaldington Footpath No. 12
ERYC
Market Weighton Footpath No. 11
ERYC
Goodmanham Footpath No. 6
ERYC Wolds Way National Trail
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 75
The Yorkshire and Humber CCS Cross Country Pipeline
PRoW No. Temporary closure
Authority
Etton Bridleway No. 5 ERYC Hudson Way Rail Trail Dis-used railway- trenchless crossing
Lund Footpath No. 2 ERYC Closure of entire length of footpath required Access to Dalton Block Valve
Watton Footpath No. 2 ERYC
Watton Footpath No. 20 ERYC
Hutton Cranswick Footpath No. 12
ERYC
Hutton Cranswick Footpath No. 11
ERYC
Hutton Cranswick Footpath No. 18
ERYC
Skerne and Wansford Bridleway No. 7
ERYC Access to Skerne Block Valve
Skerne and Wansford Bridleway No. 8
ERYC
Skerne and Wansford Bridleway and Footpath No. 9
ERYC Adjacent to River Hull / Main Drain, Wansford – trenchless crossing
Foston on the Wolds Footpath No. 11
ERYC
Barmston Footpath No. 2
ERYC
Barmston Footpath No. 3
ERYC
Barmston Footpath No. 4
ERYC
Live Railways Name Owner Location Howden to Wressle Railway
Network Rail Grid Ref 473622, 430740
Beverley to Driffield Railway
Network Rail Grid Ref 502894, 454140
Note: Live railways to be crossed by non-open cut methods.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 76
The Yorkshire and Humber CCS Cross Country Pipeline
Dismantled Railways
Name Location Howden – Drax Dismantled Railway, Long Drax
Grid Ref 467517, 427310
Dismantled Railway, Drax adjacent A645
Grid Ref 467040, 425764
Howden – Drax Dismantled Railway, Asselby
Grid Ref 470815, 428249 Extension of Long Drax railway North of Ouse
Hudson Way Dismantled Railway, Kiplingcotes Station Market Weighton to Beverley railway
Grid Ref 493365, 443780
Canals
Name Notes Location Market Weighton Canal -Disused
There are three watercourses to be crossed at this point, including Back Delfin Drain, Disused Market Weight Canal and another drain
Grid Ref 484312, 437169
Driffield Canal - Under restoration
Driffield Canal Trust Grid Ref 506600, 455819
Main Rivers
Ref Name Location RVX1 River Ouse Grid Ref 469259, 427092
RVX3 Disused Market Weighton Canal Grid Ref 484312, 437169
RVX4 River Hull Grid Ref 506520, 455790
CLX1 Driffield Canal Grid Ref 506600, 455819
DX37/5 Nafferton Highland Stream Grid Ref 507904, 456351
DX37/7 White Dike Grid Ref 508123, 456410
RVX5 Kelk Beck Grid Ref 508982, 456932
Note: All main rivers to be crossed using non open-cut methods.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 77
The Yorkshire and Humber CCS Cross Country Pipeline
Water Framework Directive Designated Watercourses
Ref Name Location DX0/1 DX0/3
Carr Dike (Drain) / Lendall Drain
Grid Ref 466676, 428263 Grid Ref 467004, 428534
DX4/1 & DX7/3
Rusholme Lane Drain/Willow Row Drain
Grid Ref 467942, 425897 Grid Ref 467992, 425891
RVX1 River Ouse Grid Ref 469259, 427092
RVX2 River Foulness Grid Ref 479649, 433897
RVX3 Disused Market Weighton Canal Grid Ref 484312, 437169
DX30/1 Bracken Beck Grid Ref 497683, 450358
DX35/2 Northfield Beck Grid Ref 502323, 453883
DX36/8 Main Drain / Wanlass Drain Grid Ref 506490, 455779
RVX4 River Hull / West Beck Grid Ref 506520, 455790
CLX1 Driffield Canal Grid Ref 506600, 455819
RVX5 Kelk Beck Grid Ref 508982, 456932
DX38/4 Gransmoor Drain Grid Ref 511399, 458772 Note: All WFD watercourses to be crossed using non open-cut methods except Bracken Beck
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 78
The Yorkshire and Humber CCS Cross Country Pipeline
B1 Open Cut Crossings
Watercourses – Dry Open Cut
B1.1 Most minor watercourse/ditch crossings will be carried out using a dry open cut trench methodology. In dry open cut methods water flow is maintained by damming and over pumping or using temporary “flume” pipes installed in the bed of the watercourse. Details of these methods are outlined below.
B1.2 The site is first prepared by stripping the topsoil from the banks and areas adjacent to the river at the crossing point and storing it separately within the working area. If practicable the bed material and a selection of vegetation is stored, for replacement after the pipe has been laid. A flume pipe bridge will be installed, during the preparation of the working width, adjacent to the trenchline flume in order to enable passage of plant and materials along the pipeline route.
B1.3 For dry open cut watercourses / ditch crossings a suitably sized flume pipe will be installed over the point of the proposed crossing ensuring that it extends on each side of the trenchline crossing point for a suitable distance. The flume pipe will then be bedded and packed or surrounded with soil filled sandbags to create a seal or dam across the watercourse, so that the flume pipes take all the flow.
B1.4 Excavation of the watercourse then proceeds beneath the trenchline flume pipe. The excavated material will be stored within the working width separately from the bank material. Trench supports may be used to facilitate safe excavation.
B1.5 If damming and over pumping methodology is adopted then soil filled sandbags are still used to create a seal or dam across the watercourse. However, flume pipes are not installed in the riverbed. Pumps are set up to take the flow from upstream to downstream of the crossing point. The discharge hose(s) will be directed through a filtering medium to limit silt carry over or bed disturbance, before the pumped water is returned to the watercourse.
B1.6 The prefabricated pipeline section is then installed in the trench and checked to ensure that a minimum cover of 2 m (rivers) and 1.7 m (ditches) exists below the true clean bottom of the watercourse and the top of the
Appendix B – Special Crossing Methods
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 79
The Yorkshire and Humber CCS Cross Country Pipeline
pipe. Thicker walled pipe may be used. In some circumstances the pipeline may be further protected by installing it at a greater depth or installation of a thick concrete protection slab over the pipe.
B1.7 Initial backfilling will take place using excavated subsoil free of large stones or other deleterious material. Final reinstatement will use the stored river bed materials.
B1.8 The banks are then reformed to their original profile in accordance with both the Environment Agency / Internal Drainage Board (IDB)/ Local Lead Flood Authority (LLFA) and the landowners’ requirements.
B1.9 The flume pipe and packing or bags are removed once the bed materials and bank profile is reinstated. Final bank reinstatement may require further measures to stabilise the banks and prevent erosion. Geotextiles such as geojute may be used in conjunction with seeding of an appropriate grass mix. Heavier solutions such as the importation of locally sourced large stones or rocks may also be used. Bank stabilisation works will be discussed with the Environment Agency/ IDB / LLFA to ensure that suitable materials and methodologies are being used.
B1.10 Any bank protection, where it is required, will be adequately keyed into both the bed and banks. Materials and methods employed will be in keeping with the surrounding environment, and will be in line with consent requirements.
Roads – Open Cut
B1.11 Minor roads may also be open cut, involving the excavation of the trench across the road. The method is likely to be applied to small single track roads which will typically require a temporary road closure during the crossing works.
B1.12 Where required traffic lights or signals may be used to allow work on alternate halves of the road while maintaining the flow of traffic. After excavating the first half, steel plates are placed across the trench for traffic to pass while the second half of the road is excavated. A prefabricated section of pipe is then threaded through the trench under the steel plates. The trench is then backfilled and the road re-surfaced.
B2 Trenchless Crossings
B2.1 There are several non-excavation construction techniques. These include auger boring, grundoram, tunnelling including pipe-jacks, microtunnelling, and horizontal directional drilling. These techniques vary in the method used to install the pipeline without disturbing the surface. Generally, all
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 80
The Yorkshire and Humber CCS Cross Country Pipeline
non-open cut crossings are constructed at a minimum depth of 1.7 m under small watercourses and ditches, 2 m below roads and main rivers and 4.3 m below railways. However, the actual design will be submitted to the appropriate body for approval prior to construction.
Auger Boring
B2.2 The auger bore is a well proven technique that can be utilised for short and medium length crossings of up to 120m.
B2.3 The technique requires the excavation of pits on either side of the crossing to aid the installation of the pipeline. The depth of the pits depends on the nature of the crossing and the local ground conditions. De-watering and sheet piling etc. may be utilised if required to ensure a safe crossing design.
B2.4 A launch pit is excavated on one side of the crossing, following this a smaller reception pit is excavated on the opposite side of the crossing to receive the bore. Additional land is required on both sides of the crossing to accommodate the excavated material from the pits and the pipe, and to allow for the construction plant associated with the crossing.
B2.5 For auger bore, a pipe string is welded above ground and an auger drill inserted into it. A 'cutting head' is fixed to the auger drill at the front of the pipe string and rails installed in the floor of the pit for the unit to run on. Power is transmitted to the auger drill via a power unit that is temporarily fastened to the rear of the pipe string and attached on to the rails. This pipe string is lowered into the thrust pit and is supported by crane-type side booms. Surveyors then line and level the pipe string to ensure it is installed in the correct location and at the correct depth.
B2.6 A combination of the rotation of the auger drill within the pipe string and a hydraulic thrust located on the power unit installs the pipe string. The excavated material is drawn from the cutting head, down the auger drill flutes exiting from the rear of the pipe string adjacent to the power unit.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 81
The Yorkshire and Humber CCS Cross Country Pipeline
B2.7 Depending on the ground conditions and length of crossing the auger bore
crossing technique is used for non-major highway crossings, ditch crossings, minor river and canal crossings. Ground conditions dictate where this technique can be best utilised. Should ground conditions not be suitable an alternative for short crossings is the Grundoram crossing technique.
Grundoram
B2.8 The Grundoram crossing technique is utilised on short crossings such as minor roads, drains and services. This technique is more suited to soft ground conditions.
B2.9 A pneumatic piston drives the pipe from one pit to a receiving pit at the other side of the crossing. The risk of settlement is low as there is no overcutting of the tunnel when installing the pipeline.
Tunnelling
Pipe- Jack
B2.10 Pipe-jacking uses a hydraulic ram or jack to thrust an open-ended pipe under the obstacle. Miners or mechanical methods are used to remove the soil as the pipe is thrust forward. Closed face, unmanned operations are the preferred methods; manned excavations are avoided as far as possible. The excavated material is removed via the exposed end of the pipe. As each pipe progresses forward then another is welded on and in this manner
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 82
The Yorkshire and Humber CCS Cross Country Pipeline
the pipe is installed. This construction method is generally used on large diameter pipes or to install a concrete carrier sleeve under the obstacle. The concrete tunnel will be of a larger diameter than the pipe (typically 1.5m or 1.8m). The pipe is then welded and installed within the concrete sleeve. Once the pipe has been installed and tested the annulus between the pipe and the tunnel sleeve will be filled with cement grout. Alternatively the annulus may be filled with crushed glass or flooded with water.
Microtunnelling
B2.11 Microtunnelling is a broadly similar technique to pipe-jacking. The method involves the use of steerable remote control pipe-jacking. As with previous methods it requires additional temporary land take for launch and reception pits, drilling fluid management and to accommodate associated equipment.
B2.12 Pre-cast concrete jacking pipes are placed behind a microtunnelling machine with a cutting head lubricated with water or a mud mix. Small quantities of bentonite may also be used to reduce friction. The excavated material is removed with the drill fluid and is returned to the surface via a slurry pipe through the tunnel entrance where the fluid is filtered to remove the cuttings and returned to temporary mud storage tanks for re-use. A thrust wall is constructed at the launch pit from which to jack the pipe forward. As the tunnel progresses new segments of pipe are attached at the launch pit until the microtunnel reaches the reception pit, where the drill bit is detached from the tunnel and removed. The jacked pipe can be the final pipe itself or a sleeve through which a smaller pipe is then threaded. Shafts are often required in place of pits when the pipe is situated at depth.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 83
The Yorkshire and Humber CCS Cross Country Pipeline
B2.13 Equipment associated with microtunnelling will include power units, slurry
separation plant and a control cabin (see Tunnel Option Section 5.5, Landfall Construction).
B2.14 Commonly the microtunnel crossing technique is used to cross infrastructure such as railway lines, major rivers and major highways such as motorways. The microtunnel is a crossing technique that performs well in a variety of ground conditions and gives the best guarantee of little or no settlement. The technique is very accurate and by increasing the depth of such high risk crossings the possibility of settlement is reduced even further.
Direct Pipe
B2.15 The direct pipe technique can be utilised as an alternative to the HDD and microtunnel crossing techniques. This method uses the product pipe directly (rather than a concrete carrier sleeve) which is welded to the end of the microtunnelling machine. It is pushed forward by rams which push the pipe and the microtunelling machine forward together. The microtunnelling machine has interchangeable cutting bits so it can deal with a variety of ground conditions. This technique tends to be used on longer crossings where there may be a number of obstacles to navigate.
Horizontal Directional Drilling (HDD)
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 84
The Yorkshire and Humber CCS Cross Country Pipeline
B2.16 With horizontal directional drilling (HDD) the pipeline is bored under the crossing to emerge at a target point on the opposite side. A large area of temporary land take is required on either side of the proposed crossing to accommodate the equipment, drilling fluid management system and laydown area for the pipe.
B2.17 The directional drilling unit is placed at the start location and is elevated at the rear to the correct entrance angle. The rig is then anchored in position. The drilling operation begins by drilling a pilot hole using the drill bit, the drill head and the pressure injection of drilling fluid. The drilling is carried out continuously in intervals equivalent to one length of drill pipe.
B2.18 Location of the drill bit is monitored using the HDD locating system. An electronic transmitter in the drill head sends information to the locator operator’s receiver. As each drill rod is drilled into the ground the locator operator takes a reading from his equipment and informs the drill operator of the location, pitch and roll of the drill head. From this information the operator knows the location of the drill head at all times. The operator uses the information to maintain the pre-planned path of the bore. The accuracy of the drilling is verified by comparing the co-ordinates of the actual location of the drill bit against the planned drill profile. If there is a major difference between the actual and planned location of the drill bit, the operator is able to correct the actual profile by pulling back to a correct position of the planned profile and begin re-drilling.
B2.19 The hole is then enlarged by a back reamer. When the bore hole has been
reamed out to the correct diameter the back reamer is typically sent back
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 85
The Yorkshire and Humber CCS Cross Country Pipeline
down the bore one or two more times and swabbed in both directions to ensure that the hole is clear of any large objects. The pipe is laid out on the opposite side of the obstacle to the drill rig and welded to form a length long enough to cross the full length of the drill. Once the driller is satisfied that the hole is clear and ready for the pipe, the pull head is connected to the drill string via a swivel. The pipe is then pulled back toward the exit area by the drill rig.
B2.20 All drilling fluids used for HDD will be sampled, analysed and disposed of in accordance with duty of care requirements of the Environmental Protection Act, 1990.
B2.21 The HDD crossing technique can be used for long crossings such as rivers and multiple crossings where trenching or open excavation is not feasible. It gives a good degree of accuracy but due to over cutting of the tunnel a small amount of settlement can be experienced.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 86
The Yorkshire and Humber CCS Cross Country Pipeline
C1.1 The Project would be subject to specific requirements set out in the DCO. During and following the receipt of the DCO and prior to the commencement of construction, National Grid will progress the following:
• Discharge of requirements specified in the DCO; • Finalise landowner / tenant agreements; • Finalise utilities consents and permits for crossing services; • Finalise utilities agreements for connections at AGIs; • Finalise infrastructure crossings agreements/consents (Highways
Authorities (Roads & Public Rights of Way) / Network Rail/ Canal Trusts/ Internal Drainage Boards);
• Obtaining Licences from Natural England to deal with protected species;
• Obtaining other consents such as the Environmental Permits from the Environment Agency;
• Finalise Engineering and Construction Drawings and Specifications; • Building Regulation Approval where necessary; • Driffield – Bridlington High Voltage Overhead Power Line Electrical
Connection Agreement for Barmston Pumping Station (Northern Powergrid).
Appendix C – Consents Management Strategy
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 87
The Yorkshire and Humber CCS Cross Country Pipeline
Consents being sought within the Development Consent Order
Activity Consent Legislation Consenting Authority Draft DCO Provisions Highways Consents Installation of pipeline under public highways
NRSWA Street Works Licence
New Roads and Street Works Act 1991
NYCC Highways ERYC Highways
Article 11 Street Works gives “statutory right” i.e. equivalent of a NRSWA Licence for works listed in Schedule 4 Street Works
Open–cut pipeline installation under public highway requiring temporary road closure
Temporary Traffic Regulation Order
Road Traffic Regulation Act 1984 S14
NYCC Highways ERYC Highways
Article 14 Temporary Stopping Up of Streets gives power to divert traffic from a street as set out in Schedule 6 Part 2.
Temporary Accesses to works Consent for vehicular access across footway or verge
Highways Act s184 NYCC Highways ERYC Highways
Article 15 Access to Works gives power to form, layout, improve means of access as specified in Schedule 7 Access to Works
NRSWA Street Works Licence – ancilliary works
New Roads and Street Works Act 1991
NYCC Highways ERYC Highways
Article 11 Street Works gives “statutory right” i.e. equivalent of a NRSWA Licence for works listed in Schedule 4 Street Works
Sec 278 / Sec 62 Agreement Highway Improvements
Highways Act Sec 62 / Sec 278
NYCC Highways ERYC Highways
Article 12 Power to Alter the layout of streets- gives powers to execute any works to provide or improve sight lines as set out in Schedule 5 Alteration of layout without the need for a S278 / S62 agreement
Permanent Accesses for Block Valves Consent for vehicular access across footway or verge
Highways Act Sec 184
ERYC Highways Article 15 Access to Works gives power to form, layout, improve means of access as specified in Schedule 7 Access to Works
NRSWA Street Works Licence – ancilliary works
New Roads and Street Works Act 1991
ERYC Highways Article 11 Street Works gives “statutory right” i.e. equivalent of a NRSWA Licence for works listed in
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 88
The Yorkshire and Humber CCS Cross Country Pipeline
Activity Consent Legislation Consenting Authority Draft DCO Provisions Schedule 4 Street Works
Sec 278 / Sec 62 Agreement Highway Improvements
Highways Act Sec 62 / Sec 278
NYCC Highways ERYC Highways
Article 12 Power to Alter the layout of streets- gives powers to execute any works to provide or improve sight lines as set out in Schedule 5 Alteration of layout without the need for a S278 / S62 agreement
Wade House Lane / A645 Junction modifications to accommodate permanent access for Multi-junction
Consent for vehicular access across footway or verge
Highways Act Sec 184
NYCC Highways
Article 15 Access to Works gives power to form, layout, improve means of access as specified in Schedule 7 Access to Works
NRSWA Street Works Licence – ancilliary works
New Roads and Street Works Act 1991
NYCC Highways
Article 11 Street Works gives “statutory right” i.e. equivalent of a NRSWA Licence for works listed in Schedule 4 Street Works
Sec 278 / Sec 62 Agreement Highway Improvements
Highways Act Sec 62 / Sec 278
NYCC Highways
Article 12 Power to Alter the layout of streets- gives powers to execute any works to provide or improve sight lines as set out in Schedule 5 Alteration of layout without the need for a S278 / S62 agreement
Sands Road Barmston widening and upgrading of Public Highway Modifications to road layout at junction
Consent for vehicular access across footway or verge
Highways Act Sec 184
ERYC Highways
Article 15 Access to Works gives power to form, layout, improve means of access as specified in Schedule 7 Access to Works
NRSWA Street Works Licence – ancillary works
New Roads and Street Works Act 1991
ERYC Highways
Article 11 Street Works gives “statutory right” i.e. equivalent of a NRSWA Licence for works listed in Schedule 4 Street Works
Temporary Traffic Regulation Order - temporary stopping up
Road Traffic Regulation Act 1984 S14
ERYC Highways Article 14 Temporary Stopping Up of Streets gives power to divert traffic from a street as set out in
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 89
The Yorkshire and Humber CCS Cross Country Pipeline
Activity Consent Legislation Consenting Authority Draft DCO Provisions during road widening works
Schedule 6 Part 2.
Sec 62 Agreement Highway Improvements
Highways Act 1980 Sec 62/ Sec 278
ERYC Highways Article 12 Power to Alter the layout of streets- gives powers to execute any works to provide or improve sight lines/ alter the width of carriageway as set out in Schedule 5 Alteration of layout without the need for a S278 / S62 agreement
Public Rights of Way Consents Temporary closure of footpaths/ bridleways during pipeline / AGI construction
Temporary Closure Order/ Traffic Regulation Order
Highways Act 1980 / Road Traffic Regulations Act 1984
NYCC Highways (PRoW) ERYC Highways (PRoW)
Article 14 Temporary Stopping Up of Rights of Way gives power to prevent persons from passing along a right of way as set out in Schedule 6 Part 1. Subject to consulting highway authority
Marine Licences River Ouse tidal section Permanent pipeline installation/ construction
Marine Licence Marine and Coastal Access Act
Marine Management Organisation
Article 43 Deemed Marine Licence as set out in Schedule10
Landfall construction works below High Mean Water Springs
Marine Licence Marine and Coastal Access Act
Marine Management Organisation
Article 43 Deemed Marine Licence as set out in Schedule10
Nature Conservation Consents & Licences
Pipeline construction in vicinity of River Hull Headwaters SSSI Temporary Construction Access – Kelk Beck Dewatering operations in vicinity of Kelk Beck & River Hull including Discharge of water to Kelk Beck & River Hull (under Environmental Permit)
SSSI Consent for operations likely to damage the special interests of a SSSI Notice of proposal to carry out an operation on a SSSI
Section 28E (1)(a) Wildlife and Countryside Act 1981 (as amended and inserted by section 75 and Schedule 9 of the Countryside and Rights of Way Act 2000)
Natural England Schedule 12 Paragraph 2 of draft DCO provides permission to carry out operations (referred to in sections 28E and 28I(2) of the 1981 Act) that may damage a SSSI
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 90
The Yorkshire and Humber CCS Cross Country Pipeline
Activity Consent Legislation Consenting Authority Draft DCO Provisions Works requiring removal of ‘important’ hedgerows as defined by the Hedgerow Regulations
Hedgerow Removal Notice Hedgerow Regulations 1997 Selby District / NYCC /ERYC
Article 45 gives power to remove any hedgerow without need for hedgerow removal notice under the Hedgerows Regulations 1997 as set out in Hedgerow Plans (Document Reference 2.5) For the purposes of the authorised development the Hedgerow Regulations 1997 are excluded under the Order.
Works to trees protected by Tree Preservation Order
Tree Preservation Orders Town and Country Planning (Tree Preservation) (England) Regulations 2012
Selby District/ NYCC/ ERYC
Article 46 gives power to fell, lop, cut back roots of tree protected by Tree Preservation Order. The permission granted by the article would constitute a deemed consent under a Tree Preservation Order.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 91
The Yorkshire and Humber CCS Cross Country Pipeline
Consents to be progressed outside of the Development Consent Order Activity Consent Legislation Consenting Authority Approach to obtaining consent Water Consents Permanent installation of pipeline under Main River
Flood Defence Consent Water Resources Act 1991 s 109
Environment Agency EA initially advised they would not agree to include consent in DCO (under s 150)1 Statement of Common Ground with EA Detailed design prepare crossing drawings Construction contractor to prepare method statements and supporting material for National Grid to apply for Flood Defence Consent from EA 6 month prior to construction
Temporary works to install pipeline in/over Main River
Flood Defence Consent/ Byelaw Consent
Water Resources Act 1991 s 109/ Yorkshire Land Drainage Byelaws 1980
Environment Agency Statement of Common Ground with EA Detailed design prepare temporary works plan Construction contractors to prepare method statements & apply for EA Consent
Temporary construction access in/over Main River
Flood Defence Consent/ Byelaw Consent
Water Resources Act 1991 s 109 / Yorkshire Land Drainage Byelaws 1980
Environment Agency Statement of Common Ground with EA Detailed design to confirm locations. Construction contractors to prepare detailed list with access type/ flume size & no.
1 During initial consultations with the Environmental Agency they advised that they would not agree to the DCO including a provision under Section 150 of the Planning Act 2008 which would remove the need for EA consents under the Water Resources Act 1991 to be granted. A letter dated 21 May 2014 from the Environment Agency stated that they would now consider requests to dis-apply relevant legislation that may result in a simplification of the consenting process. Upon consideration, National Grid have decided to submit the application without Section 150 provisions.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 92
The Yorkshire and Humber CCS Cross Country Pipeline
Activity Consent Legislation Consenting Authority Approach to obtaining consent apply for EA consent
Temporary works within 8m of Main River Byelaw Consent Yorkshire Land Drainage Byelaws 1980
Environment Agency Statement of Common Ground with EA Detailed design confirm locations Construction contractors apply to EA for consent
Land Drainage outfalls into Main River Flood Defence Consent/ Byelaw Consent
Water Resources Act 1991 s 109 / Yorkshire Land Drainage Byelaws 1980
Environment Agency Statement of Common Ground with EA Detailed design – to submit outfall locations to EA. Construction contractors apply to EA for consent
Well point Dewatering – abstraction Abstraction License Water Act 2003 / Environment Agency Statement of Common Ground with EA Groundwater profiles to be established and levels & quality monitored. Locations to be confirmed. Construction contractors to prepare method statements & apply for EA Consent
Well point de-watering – discharge to surface water
Environmental Permit Environmental Permitting Regs 2010
Environment Agency Statement of Common Ground with EA See above – locations to be confirmed Construction contractors to prepare method statements & apply for EA Consent
De-watering excavations -abstraction Abstraction License Water Act 2003 / Environment Agency Statement of Common Ground with EA Construction contractors to apply
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 93
The Yorkshire and Humber CCS Cross Country Pipeline
Activity Consent Legislation Consenting Authority Approach to obtaining consent for EA consents
Dewatering excavations - discharge Environmental Permit Environmental Permitting Regs 2010
Environment Agency Statement of Common Ground with EA Groundwater monitor water quality 1 year pre-construction Construction contractors to prepare mitigation (Pollution Prevention / Water Management Plan) and apply for EA consents
Hydrostatic test water - Abstraction Abstraction License Water Act 2003 / Environment Agency Statement of Common Ground with EA Sources to be confirmed Construction contractor to agree sources and apply for EA consent
Hydrostatic test water - Discharge Environmental Permit Environmental Permitting Regs 2010
Environment Agency Statement of Common Ground with EA Return to source or agree discharge point with EA Construction contractors to prepare mitigation (Pollution Prevention / Water Management Plan) and apply for EA consents
Surface water run-off – control/ treat & discharge
Environmental Permit Environmental Permitting Regs 2010
Environment Agency Statement of Common Ground with EA Compliance with Pollution Prevention Guidelines Construction contractors to to prepare mitigation (Pollution Prevention / Water Management
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 94
The Yorkshire and Humber CCS Cross Country Pipeline
Activity Consent Legislation Consenting Authority Approach to obtaining consent Plan) and agree measures/ apply for consent with EA
Permanent installation under ordinary watercourse
No mention of under watercourse in LDA- part of consent below
IDB / Lead Local Flood Authority (ERYC)
IDBs want consent application for permanent installation Statement of Common Ground with IDBs/LLFA Detailed design to confirm locations / prepare crossing drawings Construction contractors to prepare method statements and supporting material for National Grid to apply for Consent
Temporary works to install pipeline in/over ordinary watercourse
Flood defence consent Land Drainage Act 1991 s 23 IDB / Lead Local Flood Authority (ERYC)
IDBs have not agreed to include consent in DCO (under s 150), same approach to be taken for ERYC consents. Statement of Common Ground with IDBs/LLFA Detailed design to confirm locations / methods/ prepare temporary works plan Construction contractors to prepare method statements and apply for IDB Consent
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 95
The Yorkshire and Humber CCS Cross Country Pipeline
Activity Consent Legislation Consenting Authority Approach to obtaining consent Temporary construction access in/over ordinary watercourse
Flood defence consent Land Drainage Act s23 / s66 Land Drainage Byelaws
IDB / Lead Local Flood Authority (ERYC)
Statement of Common Ground with IDBs/LLFA Detailed design to confirm locations Construction contractors to provide details of crossings (no./ size of flumes)
Temporary works within 9m of ordinary watercourse
Land Drainage consent Land Drainage Byelaws IDB Statement of Common Ground with IDBs/LLFA Detailed design to confirm locations Construction contractors to apply for consent
Land Drainage outfalls into ordinary watercourse
Land Drainage consent Land Drainage Byelaws IDB Statement of Common Ground with IDBs/LLFA Detailed design – to submit outfall locations to IDBs/LLFA Construction contractors to apply for consent
Sewage discharge to septic tank/cesspit – groundwater soakaway
Environmental Permit Environmental Permitting Regs 2010
Environment Agency Statement of Common Ground with EA Detailed design to confirm sewage discharge requirements. Apply for EA Consent as appropriate
Waste Consents Storage of waste on site – yard / working width Temporary storage prior to recycling/
Environmental Permit / Exemption?
Environmental Permitting Regs 2010
Environment Agency Statement of Common Ground with EA
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 96
The Yorkshire and Humber CCS Cross Country Pipeline
Activity Consent Legislation Consenting Authority Approach to obtaining consent responsible disposal
Construction contractors to apply for Environmental Permit / Exemption
Storage of spoil on site – awaiting reuse Environmental Permit Exemption?
Environmental Permitting Regs 2010
Environment Agency Statement of Common Ground with EA Construction contractors to apply for Environmental Permit / Exemption
Storage of Hazardous Waste on site – transfer to Hazardous Waste Disposal site
Registration as producer of Hazardous Waste
Hazardous Waste Regs Environment Agency Statement of Common Ground with EA Construction contractors to register site as producer of Hazardous Waste
Emissions Consents Transport of CO2 in pipeline – venting of CO2
Greenhouse Gas Emissions Permit / Exclusion
Greenhouse Gas Emissions Trading Scheme Regulations 2012
Environment Agency Statement of Common Ground with EA National Grid to agree Monitoring Plan with EA and apply for permit
Protected Species / Habitat Consents Protection of species during construction European Protected
Species Mitigation Licence Conservation of habitats and Species Regulations 2010
Natural England Draft Licence application submitted to Natural England prior to DCO application Statement of Common Ground/ Letter of no impediment from Natural England Survey and apply for licences prior to construction
Highways Consents Street signage, traffic lights or speed Traffic Regulation Order Road Traffic Regulations Act NYCC Highways Statement of Common Ground
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 97
The Yorkshire and Humber CCS Cross Country Pipeline
Activity Consent Legislation Consenting Authority Approach to obtaining consent reduction measures 1984
ERYC Highways with Highways Authorities
Detailed design to confirm locations National Grid to apply for order.
Other Documents Volume 7: Construction Report Ref 7.6
Construction Report 98
The Yorkshire and Humber CCS Cross Country Pipeline
Figures 3.1 – 3.11 Scheme Layout
SL
T
ra
c
k
D
rain
Path (um
)
P
a
t
h
(
u
m
)
Drain
D
r
a
i
n
E
T
L
Track
Level Crossing
T
r
a
c
k
T
r
a
c
k
D
r
a
i
n
P
a
t
h
T
ra
c
k
D
ra
in
Pond
D
ra
in
P
a
t
h
(
u
m
)
Pond
D
r
a
in
Drain
D
r
a
i
n
Drain
D
r
a
in
Drax Hales
D
r
a
i
n
A
6
4
5
P
a
t
h
Dra
in
Pond
Brock Holes
Dra
in
D
ra
in
W
A
D
E
H
O
U
S
E
L
A
N
E
Pond
Pond
W
illo
w
R
o
w
D
ra
in
The Bungalow
D
r
a
i
n
HALES L
ANE (T
ra
ck)
Pond
D
ra
in
Track
H
a
le
s
F
a
rm
Pond
Pond
Cross Bank
D
r
a
i
n
B
R
IC
K
H
ILL LA
N
E
T
r
a
c
k
T
ra
c
k
D
r
a
i
n
Drain
D
ra
in
P
a
t
h
Pond
HALES LANE
Track
3.7m
Halfway
Council Houses
Drain
Drain
D
ra
in
Houses
Pond
House
D
rain
D
r
a
in
House
D
rain
4.1m
W
illo
w
R
o
w
D
ra
in
4.0m
D
rain
B
R
I
E
R
L
A
N
E
D
ra
in
Pond
Pond
D
rain
Drain
S
E
G
LA
N
E
(T
rack)
D
ra
in
D
rain
Landray
Pond
A
6
4
5
Halfway
H
A
W
D
A
Y
L
A
N
E
(T
ra
ck)
Dra
in
Pond
3.8m
N
E
W
L
A
N
E
D
ra
in
D
ra
in
Drain
Pond
D
rain
D
r
a
in
D
r
a
i
n
T
r
a
c
k
FB
Track
E
T
L
E
T
L
E
T
L
Greenacres
Ponds
1
.
2
2
m
R
H
1
.
2
2
m
R
H
1
.2
2
m
R
H
D
e
f
Tk H
T
k
H
RH
De
f
SD
S
P
1.2
2m
T
k H
Def
SD
SP
D
e
f
D
e
f
T
k
H
SP
Drax Power
SLs
T
h
e
W
ater
A
6
4
5
Cottage
FB
Belmar
D
i
s
m
a
n
t
l
e
d
R
a
i
l
w
a
y
4.6m
W
a
te
r
Westfield
4.7m
Cooling Tower
ET
L
LB
D
r
a
i
n
D
r
a
i
n
Bowling
Station
Hales Lane
M
P
.
5
Golf Course
Club
S
M
Court
Green
SL
SL
S
M
Cooling Tower
Farm
D
r
a
in
L
A
N
E
SM
S
M
Pond
Cooling Tower
W
a
t
e
r
Sluice
D
i
s
m
a
n
t
l
e
d
R
a
i
l
w
a
y
Cooling Tower
R
O
A
D
Tennis
B
u
n
g
a
l
o
w
House
D
r
a
i
n
5.3m
SM
H
A
L
E
S
FB
Station House
C
o
n
v
e
y
o
r
Cooling Tower
N
E
W
4.9m
P
a
t
h
(
u
m
)
W
a
te
r
D
i
s
m
a
n
t
l
e
d
R
a
i
l
w
a
y
Pond
House
D
rain
W
a
te
r
FB
D
ra
in
T
r
a
c
k
Station
W
a
te
r
Weston
Tank
Cooling Tower
Pond
Tank
W
R
E
N
H
A
L
L
L
A
N
E
3.9m
W
a
te
r
Cooling Tower
Tanks
Trav
Station
W
a
te
r
C
ra
n
e
Cooling Tower
Drax Power
Tank
FB
Cooling Tower
Chy
4.3m
Sludge Lagoons
D
ra
in
Tanks
Tank
Tanks
Cooling Tower
ET
L
FB
Chy
Sluice
Tanks
FB
Tank
Sluice
Cooling Tower
Tanks
WB
Tanks
N
E
W
R
O
A
D
Pond
Drain
Drain
Sluice
Cooling Tower
E
T
L
W
a
te
r
E
T
L
C
rane
F
B
FB
T
ra
v
e
llin
g
C
onveyor
4.5m
Drain
TCBs
E
T
L
Pond
D
ra
in
M
I
L
L
L
A
N
E
(
T
r
a
c
k
)
S
T
P
E
T
E
R
'S
Mill House
3.8m
MAIN ROAD
4.9m
D
r
a
i
n
P
a
th
(
u
m
)
5.2m
4.6m
WREN HALL
Pavilion
Drax County
Earthworks
C
o
ts
w
o
ld
LANE
Farm
House
Tennis Court
Briarden
School
D
ra
in
L
o
d
g
e
Drax Hall
Providence
R
E
A
D
C
L
O
S
E
5.0m
P
ath (um
)
CA
ST
LE
H
IL
L L
AN
E
4.4m
Field
Providence Place
Primary School
C
H
U
R
C
H
D
IK
E
L
A
N
E
Castle Hill
Track
TCB
Pond
P
a
th
(u
m
)
Drax
Ponds
Rose Villa
G
D
N
S
Playing Field
Drax Hales
P
a
t
h
The Vicarage
Saints Peter & Paul
Pond
Pond
The Granary
H
o
lm
e
fie
ld
s
Castle
Drain
P
O
P
L
A
R
GP
Playing Field
Cottage
D
r
a
in
Church
B
A
C
K
L
A
N
E
Poultry House
Pond
T
rack
Hall
Chesam
D
i
s
m
a
n
t
l
e
d
R
a
i
l
w
a
y
Silos
Pond
Pond
El Sub Sta
R
O
A
D
Read
Westfields
Pp Ho
D
r
a
i
n
The Norwoods
D
r
a
i
n
Baxter Hall
T
r
a
c
k
Pond
D
r
a
i
n
D
r
a
i
n
Drain
D
i
s
m
a
n
t
l
e
d
R
a
i
l
w
a
y
3.7m
D
r
a
in
4.0m
D
ra
in
W
R
E
N
H
A
L
L
L
A
N
E
D
ra
in
Pond
S
H
A
R
P
H
IL
L
P
a
t
h
(
u
m
)
D
r
a
in
Drain
D
ra
in
CARR LANE
Woodlands
D
r
a
in
D
r
a
in
P
a
t
h
(
u
m
)
D
ra
in
Drain
Drain
D
r
a
i
n
Pond
Drain
Dra
in
4.1m
D
r
a
in
New Close Wood
L
A
N
E
ETL
Wren Hall
D
ra
in
Woodcock Wood
4.4m
GP
B
R
IE
R
4.0m
C
H
U
R
C
H
D
I
K
E
L
A
N
E
4.0m
Dra
in
Moat
D
r
a
i
n
3.8m
R
U
S
H
O
L
M
E
L
A
N
E
T
r
a
c
k
Playing F
ield
4.0m
W
illo
w
4.5m
LA
N
E
Scurff Cottages
S
t
e
v
e
r
t
e
y
C
o
t
t
a
g
e
D
r
a
in
R
o
s
e
C
o
tt
a
g
e
Scurff Hall
FB
R
o
w
D
r
a
i
n
Tra
ck
Mole End
5.5m
(Red Flashing)
Track
BA
NK
FIE
LD
LA
NE
Sluice
The Lodge
FB
4.8m
Bollards
Bollard
Marsh
Drain
Pump House
Drain
Nelliefield Farm
Q
uay
Bollard Bollards
Bollard
P
ath (um
)
Sewage
Beacon
P
a
t
h
(
u
m
)
5.5m
MP
FB
Path (um)
D
r
a
i
n
ETL
B
u
r
r
Red
Bank Field
5.5m
4.3m
Rusholme R
each
Sluice
M
ean H
igh W
ater
W
h
e
e
l
5.5m
R
E
D
H
O
U
S
E
L
A
N
E
R
iv
e
r O
u
s
e
5.5m
Sluice
FB
D
is
m
a
n
t
le
d
R
a
il
w
a
y
MP
Low Field
Works
FB
4.2m
Mud
Black Tom Staith
M
ean H
igh W
ater
Pa
th
(u
m)
Diamond Cottage
D
ra
in
Dra
in
Pond
Beacon
R
u
s
h
o
l
m
e
R
e
a
c
h
Tra
ck
ROMANO
Rusholme Hall
BRITISH FARMSTEAD
Drain
3.8m
P
a
th
(
u
m
)
4.1m
GVC
4.0m
D
ic
k
o
n
F
ie
ld
LANE
T
ra
c
k
D
r
a
in
5.2m
RUSHOLME
3.9m
P
a
th
(u
m
)
M
e
a
n
H
ig
h
W
a
te
r
(Red Flashing)
(site of)
M
e
a
n
H
ig
h
W
a
te
r
R
i
v
e
r
O
u
s
e
G
A
T
E
L
A
N
D
F
IE
L
D
L
A
N
E
Drain
Middle Marsh
D
r
a
in
Red Marsh
Track
GREEN L
ANE
G
A
T
E
L
A
N
D
F
IE
L
D
L
A
N
E
(T
ra
c
k
)
B
A
N
K
F
IE
L
D
L
A
N
E
Path (um) M
e
a
n
P
a
th
(u
m
)
M
e
a
n
H
ig
h
W
a
te
r
G
R
E
E
N
LA
N
E
Gateland Field
R
iv
e
r O
u
s
e
ETL
(
T
r
a
c
k
)
L
o
w
fie
ld
D
ra
in
Holy Croft
R
ush
olm
e
R
e
a
c
h
H
ig
h
W
a
te
r
F
ie
ld
s
D
ra
in
D
r
a
in
(Track)
Pump House
Drain
F
ie
ld
s
HOLYCROFT LANE (Track)
D
rain
Drain
Low Field
Drain
L
o
w
fie
ld
D
ra
in
D
ra
in
7.6m
Track
H
olly
Well
Villa
Primary School
The
House
T
C
B
Kerik
6.1m
St Helen's
Barmby Cutting
T
h
e
O
ld
O
r
c
h
a
r
d
Church
Dunstall
Pond
Warren
F
a
r
m
Track
Works
Drain
Rose
Dra
in
The Paddock
A
c
o
rn
C
o
tta
g
e
MARSH LANE
D
ra
in
Drain
Drain
Solo Marsh
(Track)
SOUTH
H
a
w
th
o
rn
e
V
illa
E
T
L
St H
elen's F
arm
Track
Track
Willow
Path (um
)
D
e
lta
C
o
tta
g
e
Hills Field
Pond
Barmby Marsh
Mill
STR
EET
6.4m
House
Hall
Cottage
Burial
Cottage
B
a
s
s
e
tts
The Old
Railway Station
Lodge
E
a
s
t E
n
d
Vicarage
5.9m
House
Beech Tree
H
e
d
g
e
ro
w
s
Cottage
C
ra
k
e
m
e
r
Sewage
House
Farm
Pond
Drains
Derwent
D
ra
in
The Old
Farm
D
ra
in
Drain
Barmby-on-the-Marsh
Dra
in
T
h
e
C
o
tta
g
e
s
(site of)
Drain
Fair Field
Masondale
Tra
ck
W
in
d
m
ill C
o
tta
g
e
School House
Ground
T
r
a
c
k
Leigh Cottage
Barmby on the Marsh
6.1m
C
h
u
rc
h
V
ie
w
St Helen's
Drain
S
T
A
T
IO
N
L
A
N
E
C
h
u
rc
h
W
a
lk
6.3m
Orchard
Light-house
Lilac House
Cherry
House
Mayfield
MLW
MLW
WE
TH
ER
ALL R
OA
D
PH
FB
Tank
D
ra
in
S
w
im
m
ing P
ool
Pond
The Laurels
T
r
a
c
k
Track
T
ra
ck
DERWENT CHASE
POPLAR
COURT
Thorpecroft
Marren
House
Burghfield House
L Twr
L Twr
L Twr
L Twr
E
T
L
L Twr
Mast (Telecommunication)
Pond
L Twr
L Twr
L Twr
L Twr
L Twr
L Twr
L Twr
L Twr
L Twr
L Twr
L Twr
L Twr
L Twr
L Twr
L Twr
L Twr
L Twr
The
Hayloft
T
r
a
c
k
Corner
House
House
Essex
Oak Tree Farm
T
h
e
O
ld
O
r
c
h
a
r
d
Dove Cottage
West End
Bungalow
Tanks
Pond
Pond
Mast (Telecommunication)
Wind Turbine
Electricity Generating Station
Horsefair Lodge
Tree
Cottage
Cherry
OA
KF
IE
LD
A
VE
NU
E
1.22m
R
H
D
e
f
1
.2
2
m
T
k
H
Def
Def
1
.
2
2
m
R
H
D
e
f
U
n
d
Def
D
e
f
D
e
f
Def
1.22m RH
Def
1
.2
2
m
R
H
Def
S
D
1
.
2
2
m
R
H
1
.2
2
m
R
H
1
.2
2
m
R
H
D
e
f
1
.
2
2
m
R
H
D
e
f
1
.
2
2
m
R
H
S
D
D
e
f
U
n
d
D
e
f
CC
LW
D
e
f
C
o
C
o
n
s
t &
U
A
B
d
y
1
.
2
2
m
R
H
C
o
C
o
n
s
t &
U
A
B
d
y
C
C
L
W
C
C
L
W
C
o
C
o
n
s
t &
U
A
B
d
y
D
e
f
F
ie
ld
s
D
ra
in
D
ra
in
D
r
a
in
Track
Mean High Water
Mean High Water
Holy Croft
Rusholme Grange
Path (um)
R
u
sh
o
lm
e
R
e
a
ch
(Red Flashing)
Path (um)
Beacon
River Ouse
Pond
T
rack
D
rain
Seave Carr Bottoms
Drain
D
rain
Dra
in
Fields D
rain
D
ra
in
Track
Seave Carr
Drain
F
ie
ld
s
D
r
a
in
T
ra
ck
Gas Valve Compound
Track
D
rain
Dra
in
D
r
a
in
Oxen Stang Field
5.9m
Asselby Marsh
6.6m
D
rain
C
l
o
u
g
h
D
r
a
i
n
6.1m
T
rack
Barmby Marsh
Hither Great Field
Drain
5.1m
Dismantled Railway
Asselby Nurseries
Track
E
T
L
Drain
Asselby Marsh Drain
Track
D
rain
The Hawthorns
Orchard Lodge
BAC
K LAN
E
Tamarisk
Drain
Clayfield Drain
Newlands
Track
Track
Drewton
LA
ND
IN
G
LA
NE
D
rain
Ashes
The
Back Lane Farm
Dra
in
Drain
Bridge
Drain
Track
House
View
Drain
M
anderley
MA
RS
H L
AN
E ( T
ra
ck)
A
s
s
e
l
b
y
M
a
r
s
h
D
r
a
i
n
5.4m
Path (um
)
Drain
Lindum
House
6.1m
5.8m
Elf Cottage
Track
TH
E N
U
R
SE
R
IE
S
W
e
lls
C
o
tt
View
The Bungalow
Eel Hall
W
illo
w
L
o
d
g
e
Meml
FB
Box Tree Farm
TCB
5.6m
5.2m
Sheken
Ivy House
Westerby
Track
M
e
lo
d
y
C
o
tta
g
e
Sum
merfield H
ouse
Ro
se
C
otta
ge
Tra
ck
Chestnut
5.5m
So
uth
V
ie
w
Farm
5.0m
West End Farm
Street
Gardens
Birch Tree
E
g
r
i
n
House
5.0m
L
a
u
re
l H
o
u
s
e
Lea
Dismantled Railway
Asch
ileb
i
Muirfield
Derwent
B
o
x
T
r
e
e
C
o
tta
g
e
Springfield Lodge
Railway Cottages
Farm
Ashgrove
Asselby
Gill
Mount Pleasant
Phoenix Farm
Bungalow
Crossing Farm
Linton House
D
rain
Palmers Row
T
h
e
B
u
n
g
a
lo
w
Rose
Manor
M
A
IN
S
T
R
E
E
T
T
ra
c
k
PH
War
Field House Farm
Farm
Kirwood House
East
End
Farm
LB
Cyndene H
ouse
House
Old School House
5.7m
M
AIN
S
TREET
Council Houses
Field
The
Rocklea
Holmefield
Avallonia
Croft
Re
d N
ettle
H
ou
se
Kershout
Ashbourne
Turning Leaf Cottage
FB
Orchard H
ouse
Norton H
ouse
N
o
rd
H
ouse
Linden
C
rainan
C
o
tta
g
e
D
u
G
a
re
Johnsons Barn
Albert
The
Court
Earls
Nook
Lodge
Asselby
Gables
Farm
The
The
Haydn
Apple Tree
Barn
House
Old Stables
The
Elmhurst
Village
Barn
BLA
CK
SM
IT
H LA
NE
SO
UT
H L
AN
E
Old Fold
Yard
Langford
House
Rusholme Wind Farm
Wind Turbine
Wind Turbine
Wind Turbine
Un
d
Co Const & UA Bdy
D
e
f
CCLW
Def
1.22m
R
H
D
e
f
SD
SD
D
e
f
1.22m
R
H
D
e
f
W
a
r
d
B
d
y
S
D
D
e
f
The Old
Sty
P
a
t
h
E
T
L
D
r
a
i
n
Priory
D
r
a
i
n
C
a
r
r
D
i
k
e
D
ra
in
D
r
a
i
n
(Augustinian)
T
r
a
c
k
Pond
P
a
t
h
(
u
m
)
E
T
L
FB
E
T
L
Hook's
D
rain
3.7m
L Twr
Dra
in
C
o
n
v
e
y
o
r
Pond
(
D
r
a
i
n
)
D
r
a
in
Site of
FB
L Twr
Foreman's
D
r
a
in
Cottage
D
ra
in
Stone
D
r
a
i
n
Fields
D
r
a
i
n
Pond
Tanks
E
D
&
W
a
rd
B
d
y
D
e
f
1.2
2m
R
H
Def
Def
1
.2
2
m
T
k
H
D
e
f
1.22mRH
1.2
2m
R
H
Pond
D
r
a
in
T
ra
c
k
Ponds
Sheet 1 of 11
Figure 3.1
National Grid Carbon Limited
31 Homer Road
Solihull
West Midlands
B91 3LT
Co-financed by the European Union's
European Energy Programme for Recovery.
SCHEME LAYOUT
Title
Sheet
Date
Scale
30th April 2014
PINs
PIN's Reference EN070001
Not to Scale
Fig.No.
YORKSHIRE AND HUMBER CCS
CROSS COUNTRY PIPELINE
Background Mapping reproduced from Ordnance Survey Data, with the permission of the
Controller of Her Majesty's Stationery Office. © Crown Copyright & Database Rights(2014).
National Grid Carbon Ltd. Licence - 100055005
Drax PIG Trap
Temporary Construction Area
Temporary Construction Area 1
Temporary Construction Area 2
Camblesforth Multi-Junction
Temporary Construction Area
Temporary Construction Area 3
Temporary Construction Area 4
Inset : Drax PIG Trap
Inset : Camblesforth Multi-Junction
Temporary Construction Area - AGI
Above Ground Installations
Temporary Construction Area- Pipeline
Flexible Drainage Area
Order Limits
Limit of Deviation
LEGEND
Pipeline Centreline
Temporary Construction Compound
A
s
s
e
l
b
y
M
a
r
s
h
D
r
a
i
n
Path (um
)
FB
5.0m
Newsholme Marsh
Newsholme
Houses
Newsholme Farm
Council
GP
GP
6.8m
6.8m
G
R
E
E
N
L
A
N
E
Loftsome Ho
T
r
e
y
a
r
n
o
n
Pond
6.3m
E
T
L
Wyre Oak
B
l
a
c
k
D
y
k
e
G
R
E
E
N
L
A
N
E
E
T
L
5.3m
5.2m
Drain
T
ra
c
k
3.3m
D
r
a
i
n
Yarmshaw
D
ra
in
Newsholme Marsh
White Rail Bridge
3.8m
D
ra
in
Y
a
rm
s
h
a
w
D
ra
in
Drain
Drain
Park Farm
D
r
a
i
n
D
rain
Newsholme Parks
T
r
a
c
k
5.7m
N
e
w
D
ra
in
Warp Farm
Sluice
Pond
D
r
a
i
n
5.0m
Pond
Sluice
Sluice
Green
Black D
yke
Beechtree Farm
Pond
D
ra
in
Drain
A
6
3
D
ra
in
Pond
Pond
T
rack
D
r
a
in
P
a
t
h
(
u
m
)
Sluice
Acres
A
6
3
B
etchw
orth
Red Doors Bridge
TCB
6.9m
5.7m
Rowland Hall
5.8m
MP 24
4.7m
Level Crossing
R
O
W
L
A
N
D
H
A
L
L
L
A
N
E
6.9m
E
T
L
Pond
MP.75
ETL
E
T
L Dumphills
Pp
(
D
r
a
in
)
Pond
The Bungalow
Rowlandhall Crossing
7.0m
B
l
a
c
k
D
y
k
e
5.6m
Rowlandhall
Plantation
Steps
Drain
A
63
D
r
a
i
n
Barn Hill
3.8m
Pond
M
oat
Lay-by
4.2m
Bridge
Dyon
Pond
Duck Swang
D
r
a
i
n
M
o
a
t
Pond
4.1m
Yarmshaw
D
rain
Drain
Yarmshaw Plantations
3.7m
Barnhill Hall
Pond
B
A
R
N
H
IL
L
H
A
L
L
L
A
N
E
Pond
Dra
in
Pond
Pond
P
a
th
(u
m
)
P
a
th
(
u
m
)
Pond
Newsholme Parks
ETL
SP
Brind
Pond
GP
MP.25
Brind Crossing
ETL
P
o
n
d
MP.5
Level C
rossing
Pa
th
(u
m)
Bishopsoil
P
o
n
d
5.0m
5.1m
E
T
L
D
r
a
i
n
Howden Parks
Bishopsoil
D
u
c
k
S
w
a
n
g
D
r
a
i
n
D
r
a
in
D
ra
in
Park Farm
Drain
D
u
c
k
S
w
a
n
g
Park Farm Cottages
E
T
L
D
ra
in
Drain
5.2m
Farm
5.1m
ETL
El Ps
St Mary Magdalen's Chapel
Wynn Cottage
MP.75m
(site of)
Farm
Brind
Bishopsoil
Howden Parks
P
a
th
(u
m
)
Ringstone Hurst
(hermitage)
B
R
IN
D
L
A
N
E
Orchard Farm
Tank
D
r
a
in
E
T
L
SP
Level Crossing
MP.5
Brind
Bungalow
TCB
Village
Tanks
El Ps
The
SP
Drain
T
r
a
c
k
P
a
t
h
(
u
m
)
MP 23
Foot Bridge
T
r
a
c
k
T
r
a
c
k
Pond
Pond
The Old
Lane Farm
Pondside
Parlour
The Farm House
Mill End
Barn
Barn
FBs
Barnhill Farm
T
ra
c
k
T
r
a
c
k
Pond
D
e
f
W
a
r
d
B
d
y
S
D
D
e
f
S
D
CD
D
e
f
Ward Bdy
CD
1
.2
2
m
R
H
W
a
rd
B
d
y
Wa
rd
B
dy
1.5
2m
R
H
C
D
W
a
r
d
B
d
y
1
.
2
2
m
R
H
1
.2
2
m
R
H
5.1m
D
r
a
i
n
B
R
IN
D
L
A
N
E
D
r
a
i
n
Pond
4.9m
Pond
Pond
B
r
i
n
d
l
e
y
s
P
l
a
n
t
a
t
i
o
n
T
r
a
c
k
Brind
D
r
a
i
n
5.0m
Brind Common
T
r
a
c
k
Pond
BRIND LANE
Brind Chapel
D
r
a
i
n
D
r
a
in
Brind Common
D
r
a
i
n
5.3m
B
1
2
2
8
5.5m
D
r
a
i
n
Reservoirs
FB
W
a
r
d
B
d
y
1
.2
2
m
R
H
D
ra
in
Tks
Asgard
Woodlands
Tank
Dra
in
Bishopsoil
D
ra
in
Thorpe Common
Works
Pond
S
T
A
T
IO
N
R
O
A
D
Thorncroft
E
T
L
Thorpe Hall Cottage
The Shires
Pond
Thorpe Lodge
Willow Garth
4.4m
West Dene
E
T
L
T
r
a
c
k
4.5m
4.2m
4.1m
Pond
B 1228
Pond
Drain
ST
AT
IO
N R
OA
D
D
i
s
m
a
n
t
l
e
d
R
a
i
l
w
a
y
D
r
a
i
n
Pa
th
LB
Level C
rossing
T
ra
ck
Pond
4.6m
Drain
Level Crossing
MP 22
North Howden
The
D
ra
in
Crows Nest Farm
Drain
Thorpe Common
Dra
in
P
o
n
d
Dra
in
WO
OD
L
AN
E
Station Cottages
4.4m
Track
North Gates
Station View
Pond
D
rain
P
o
n
d
D
R
A
IN
L
A
N
E
(T
ra
ck)
Howden Station
Drain
Pond
Pond
(PH)
B 1228
Bishopsoil
Pond
Pond
Drain
SB
D
ra
in
4.6m
Rosedene
Barnes Wallis
Brenda House
Blackthorn
Pond
P
a
t
h
(
u
m
)
N
e
a
r D
ra
in
D
ra
in
4.5m
SP
MP.25
Howden Common
Dra
in
Drain
SP
M
ID
D
LE
L
A
N
E
(T
ra
ck)
Old Railway Cottage
Newfields
T
r
a
c
k
Cottage
T
ra
c
k
P
o
n
d
6.1m
Pond
T
r
a
c
k
P
o
n
d
Pond
Newfields
Tanks
P
o
n
d
El Sub Sta
Skelton Common
L
U
M
B
Y
L
A
N
E
(
T
r
a
c
k
)
D
r
a
i
n
P
o
n
d
T
H
O
R
P
E
R
O
A
D
P
o
n
d
P
o
n
d
A
6
1
4
Pond
D
r
a
i
n
Bishopsoil
Thorpe Hall
Newfields Farm
Pond
Belby Common
6.0m
6.2m
Thorpe Common
Newfields
MP.5
Skelton Common
6.3m
MP.25
Newfield House
T
ra
c
k
Pond
Bishopsoil
D
ra
in
Thorpe Common
N
e
a
r
D
r
a
in
Howden Common
Caville Bridge
D
R
A
IN
L
A
N
E
(T
ra
c
k
)
P
o
n
d
SP
D
r
a
i
n
P
o
n
d
Pond
P
o
n
d
P
o
n
d
Pond
MP.75
A
6
1
4
6.4m
Pond
Caville Hall Cottages
Level Crossing
5.7m
Tanks
Caville Hall
D
r
a
i
n
R
O
S
E
W
O
O
D
S
Swallow Cottage
The Poplars
Track
Pond
Pond
Caravan Site
Newfields
Newfields Lodge
L
U
M
B
Y
L
A
N
E
W
a
rd
B
d
y
1
.
2
2
m
R
H
1.22m RH
1
.2
2
m
R
H
D
e
f
CD
De
f
1.22m
R
HC
D
1
.2
2
m
R
H
1.2
2m
R
H
U
n
d
Def
1.22m
R
H
1
.2
2
m
R
H
W
ard B
dy
1
.2
2
m
R
H
1
.
2
2
m
R
H
1
.
2
2
m
R
H
1
.
2
2
m
R
H
D
e
f
D
e
f
D
e
f
W
a
r
d
B
d
y
D
e
f
Ponds
Pond
Drain
Club House
5.1m
C
o
m
m
o
n
e
n
d
D
ra
in
o
r F
e
a
th
e
rb
e
d
D
ra
in
GP
B 1228
FB Pond
Spaldington Common
Com
monend D
rain
Ponds
GP
Brickyard Farm
Pond
Ponds
5.3m
5.2m
Pond
Pond
Pond
Brickyard Cottages
5.1m
4.9m
4.7m
4.9m
D
ra
in
B
R
I
N
D
L
A
N
E
D
ra
in
FEATHERBED L
ANE (T
ra
ck)
WO
OD
LA
NE
D
rain
Pond
or F
eatherbed D
rain
Pond
Drain
B
1
2
2
8
Pond
Car Park
Tank
Spaldington Grange
5.3m
Centre
Spaldington
FB
FB
5.4m
Golf
Pond
FB
T
r
a
c
k
Spaldington Common
P
a
t
h
(
u
m
)
Bridge
Pond
The Rush
Drain
Pond
Foot
Foot Bridge
Dra
in
Bishopsoil
Foot Bridge
F
E
A
T
H
E
R
B
E
D
L
A
N
E
(
T
ra
c
k
)
N
e
w
D
r
a
in
C
o
m
m
o
n
e
n
d
D
r
a
in
o
r
F
e
a
th
e
r
b
e
d
D
r
a
in
5.3m
N
e
w
D
r
a
i
n
T
r
a
c
k
Bridge
F
E
A
T
H
E
R
B
E
D
L
A
N
E
(
T
ra
c
k
)
Bishopsoil
Pond
D
r
a
in
C
o
m
m
o
n
e
n
d
D
r
a
in
o
r
F
e
a
th
e
r
e
d
D
r
a
in
Foot
Pond
Old Rush
T
r
a
c
k
FB
D
e
f
1
.2
2
m
R
H
D
e
f
1.2
2m
R
H
Ward Bdy
2.4
4m
R
H
1
.
2
2
m
R
H
2
.5
9
m
R
H
2
.4
4
m
R
H
W
a
rd
B
d
y
W
a
rd
B
d
y
2
.5
9
m
R
H
Sheet 2 of 11
Figure 3.2
National Grid Carbon Limited
31 Homer Road
Solihull
West Midlands
B91 3LT
Co-financed by the European Union's
European Energy Programme for Recovery.
SCHEME LAYOUT
Title
Sheet
Date
Scale
30th April 2014
PINs
PIN's Reference EN070001
Not to Scale
Fig.No.
YORKSHIRE AND HUMBER CCS
CROSS COUNTRY PIPELINE
Background Mapping reproduced from Ordnance Survey Data, with the permission of the
Controller of Her Majesty's Stationery Office. © Crown Copyright & Database Rights(2014).
National Grid Carbon Ltd. Licence - 100055005
Temporary Construction Area - AGI
Above Ground Installations
Temporary Construction Area- Pipeline
Flexible Drainage Area
Order Limits
Limit of Deviation
LEGEND
Pipeline Centreline
Temporary Construction Compound
NE
W C
AR
R L
AN
E
Dra
in
Pear Tree Farm
SLEIGHTS LANE (Track)
Drain
FB
Pond
Bishopsoil
Dra
in
Track
Asselby Grange
FB
Primrose Cottage
Spaldington Outside
C
o
m
m
o
n
e
n
d
D
r
a
i
n
o
r
F
e
a
t
h
e
r
b
e
d
D
r
a
i
n
Violet Grove
Pond
Tra
ck
Drain
Pond
FB
Pond
Dra
in
Drain
B
i
s
h
o
p
s
o
i
l
D
r
a
i
n
o
r
C
a
r
r
D
r
a
i
n
Foot Bridge
Pond
3.9m
Track
Path (um)
D
r
a
i
n
P
a
t
h
(
u
m
)
4.6m
Spaldington Outside
D
r
a
i
n
Tk
Tank
D
ra
in
T
r
a
c
k
B
i
s
h
o
p
s
o
i
l
D
r
a
i
n
o
r
C
a
r
r
D
r
a
i
n
D
r
a
in
Sikes Farm
D
r
a
i
n
D
r
a
i
n
T
r
a
c
k
R
i
v
e
r
F
o
u
l
n
e
s
s
Welamoor
Tk
D
r
a
i
n
Bishopsoil
Moore's Farm
The Carr
D
r
a
i
n
4.2m
A
6
1
4
Sikes
P
o
n
d
T
h
e
B
u
n
g
a
l
o
w
The Croft
Welham Bridge
3.3m
E
T
L
4.7m
3.9m
Welhambridge
Welham Bridge
Pond
Chapel
3.9m
4.1m
D
u
n
n
'
s
D
r
a
i
n
A
6
1
4
Bursea
D
ra
in
Welhambridge West
Cottage
Dra
in
Farm
D
r
a
i
n
D
r
a
i
n
3.4m
River Foulness
5.0m
ET
L
4.6m
D
ra
in
T
r
a
c
k
Welham Bridge Farm
Southgate
El Sub Sta
T
ra
c
k
5.0m
Pond
Pond
D
r
a
i
n
D
r
a
i
n
P
o
n
d
A
6
1
4
Newholme
P
u
m
p
Bursea Lane End Farm
4.2m
D
r
a
i
n
Pond
D
r
a
in
D
r
a
i
n
Pond
D
r
a
i
n
Pond
BURSEA LANE ENDS
3.9m
D
r
a
i
n
H
O
W
D
E
N
R
O
A
D
GP
Common Farm
Pond
4.6m
P
a
t
h
(
u
m
)
Foot Bridge
Pond
(D
ra
in
)
Pond
Pond
4.9m
Park S
ew
er
Drain
Bridge
F
E
A
T
H
E
R
B
E
D
L
A
N
E
(
T
ra
c
k
)
Pond
D
r
a
in
C
o
m
m
o
n
e
n
d
D
r
a
in
o
r
F
e
a
th
e
r
e
d
D
r
a
in
Pond
Foot
Y
o
k
e
D
y
k
e
Bridge
B
i
s
h
o
p
s
o
i
l
D
ra
in
F
e
a
t
h
e
r
b
e
d
D
r
a
i
n
FB
D
r
a
i
n
FB
5.1m
P
a
t
h
(
u
m
)
F
E
A
T
H
E
R
B
E
D
L
A
N
E
Carr Dra
in
C
o
m
m
o
n
e
n
d
D
r
a
in
o
r
Old Rush
Spaldington Common
Foot
(
D
r
a
in
)
4.8m
or
E
a
s
t
G
o
it
S
e
w
e
r
Pond
4.7m
(
D
r
a
i
n
)
Pond
(
T
r
a
c
k
)
E
a
s
t G
o
it S
e
w
e
r
(
D
r
a
in
)
Path (um)
P
o
n
d
Path (um)
P
a
th
(u
m
)
Spaldington Common
D
ra
in
D
ra
in
P
a
th
(
u
m
)
I
N
G
S
L
A
N
E
R
iv
e
r
F
o
u
ln
e
s
s
P
a
t
h
(
u
m
)
Pond
T
r
a
c
k
The Ings
Johnson's Farm
Spaldington Outside
L
o
n
d
e
s
b
o
r
o
u
g
h
D
r
a
i
n
Ponds
D
r
a
i
n
Farm
Poplar
(PH)
Mast
D
r
a
in
Bishopsoil
The Royal Oak
4.6m
Pond
Pastures
D
ra
in
4.7m
4.0m
Albany House
F
e
a
t
h
e
r
b
e
d
D
r
a
i
n
Drain
T
r
a
c
k
Avian
C
o
m
m
o
n
e
n
d
D
r
a
i
n
o
r
4.1m
GP
Pond
Pond
Spaldington Common
5.0m
D
rain
Yokegate
B
i
s
h
o
p
s
o
i
l
D
r
a
i
n
o
r
C
a
r
r
D
r
a
i
n
A
6
1
4
4.7m
F
E
A
T
H
E
R
B
E
D
L
A
N
E
(
T
r
a
c
k
)
Tank
D
ra
in
4.5m
D
ra
in
D
ra
in
Foot Bridge
4.6m
D
ra
in
Rose Villa Farm
4.3m
GP
Pond
Firtree House
D
r
a
i
n
Pond
P
a
t
h
(
u
m
)
The
Firtree
Warham Farm
P
a
t
h
(
u
m
)
G
r
e
a
t
C
o
m
m
i
t
t
e
e
D
r
a
i
n
T
r
a
c
k
P
a
th
(
u
m
)
Stud
A
6
1
4
Ivy House 4.9m
D
r
a
i
n
Coach
C
o
tt
a
g
e
GP
P
ath
(um
)
Chestnut Farm
Spaldington Common
The Ings
D
r
a
i
n
4.5m
T
ra
c
k
Fir Tree Farm
Spaldington Outside
Pond
Pond
Water Tower
House
F
ir
tr
e
e
Path (um)
Arglam
D
r
a
in
R
iv
e
r
F
o
u
ln
e
s
s
T
r
a
c
k
D
r
a
i
n
Pond
G
r
e
a
t
C
o
m
m
i
t
t
e
e
D
r
a
i
n
Warham Plantation
D
r
a
i
n
D
r
a
i
n
The Carr
Spaldington Outside
D
r
a
i
n
FB
Maalkedo House
Pond
FB
4.5m
T
r
a
c
k
Pond
The Bungalow
Taynton Lodge
T
r
a
c
k
T
r
a
c
k
Pond
Pond
Track
D
r
a
i
n
s
T
ra
c
k
Old Rush Farm
3
.
6
6
m
R
H
C
R
3
.6
6
m
R
H
C
R
W
a
rd
B
d
y
2
.5
9
m
R
H
2
.5
9
m
R
H
2
.
7
4
m
R
H
C
R
3
.0
5
m
R
H
3
.
6
6
m
R
H
D
e
f
C
R
D
r
a
in
o
r
6.1m
C
h
u
rc
h
D
ra
in
Pond
C
o
m
m
o
n
e
n
d
D
r
a
in
T
r
a
c
k
The Bungalow
D
ra
in
Pond
D
r
a
in
Bursea Lane
FB
R
iv
e
r
F
o
u
ln
e
s
s
D
r
a
in
Pond
B
U
R
S
E
A
L
A
N
E
The Carr
Dra
in
FB
Drain
C
attle G
rid
6.4m
F
e
a
t
h
e
r
b
e
d
D
r
a
in
Bursea
T
r
a
c
k
B
i
s
h
o
p
s
o
i
l
D
r
a
i
n
o
r
C
a
r
r
D
r
a
i
n
East Bursea Farm
D
r
a
i
n
Cottage
Pond
Bursea Farm
5.1m
D
r
a
i
n
FB
3.9m
4.7m
D
r
a
i
n
D
u
n
n
'
s
D
r
a
i
n
Pond
Bursea Close
Holme Common
D
r
a
i
n
Bursea Lane Farm
Bursea
D
r
a
i
n
D
r
a
i
n
D
r
a
i
n
Pond
D
r
a
in
D
ra
in
D
r
a
in
Pond
D
r
a
i
n
D
r
a
i
n
B
U
R
S
E
A
L
A
N
E
E
T
L
3.7m
D
r
a
i
n
D
r
a
i
n
D
r
a
in
Ponds
D
u
n
n
'
s
D
r
a
i
n
Pond
D
r
a
i
n
T
r
a
c
k
D
r
a
i
n
D
r
a
i
n
D
r
a
i
n
A
6
1
4
FB
D
r
a
i
n
D
r
a
i
n
Pond
The
D
u
n
n
'
s
D
r
a
i
n
Pond
Pond
Willows
Pond
T
r
a
c
k
Hollybush
D
ra
in
D
r
a
in
Sand Gap
D
r
a
in
Pond
R
iv
e
r F
o
u
ln
e
s
s
D
r
a
i
n
D
r
a
i
n
D
r
a
i
n
Pum
p
E
T
L
Bursea House
D
r
a
i
n
Pond
Pond
P
o
n
d
4.9m
5.5m
T
r
a
c
k
4.4m
4.9m
B
U
R
S
E
A
L
A
N
E
P
o
n
d
P
o
n
d
D
ra
in
B
U
R
S
E
A
L
A
N
E
D
r
a
in
5.3m
T
r
a
c
k
Pond
D
r
a
i
n
3.3m
D
r
a
i
n
D
r
a
i
n
D
ra
in
2.9m
D
r
a
i
n
Pond
D
r
a
i
n
D
r
a
i
nD
r
a
i
n
Bursea
D
r
a
i
n
Pond
3.7m
B
U
R
S
E
A
L
A
N
E
3.5m
D
r
a
i
n
D
r
a
i
n
T
r
a
c
k
D
r
a
i
n
D
r
a
i
n
D
r
a
i
n
D
r
a
i
n
Pond
D
r
a
i
n
Bursea
D
r
a
i
n
Grange Farm
D
r
a
i
n
Lodge
Pond
ETL
B
u
r
s
e
a
G
r
a
n
g
e
3.8m
Plump Bungalow
M
a
i
n
D
r
a
i
n
Tollingham
3.7m
D
r
a
in
D
r
a
i
n
Bursea
Pond
D
r
a
i
n
T
h
r
o
l
a
m
D
r
a
i
n
D
r
a
i
n
D
ra
in
Tollingham
FB
D
r
a
in
Bursea
D
r
a
i
n
D
ra
in
D
r
a
i
n
3.2m
2.8m
M
a
in
D
ra
in
Ponds
Ponds
D
r
a
i
n
D
R
A
IN
LA
N
E
D
r
a
in
N
E
W
L
A
N
E
(
T
r
a
c
k
)
Hasholme Hills
3.3m
T
r
a
c
k
Throlam Plantation
Throlam
Pond
S
R
SD
3
.
6
6
m
R
H
C
R
S
D
Sheet 3 of 11
Figure 3.3
National Grid Carbon Limited
31 Homer Road
Solihull
West Midlands
B91 3LT
Co-financed by the European Union's
European Energy Programme for Recovery.
SCHEME LAYOUT
Title
Sheet
Date
Scale
30th April 2014
PINs
PIN's Reference EN070001
Not to Scale
Fig.No.
YORKSHIRE AND HUMBER CCS
CROSS COUNTRY PIPELINE
Background Mapping reproduced from Ordnance Survey Data, with the permission of the
Controller of Her Majesty's Stationery Office. © Crown Copyright & Database Rights(2014).
National Grid Carbon Ltd. Licence - 100055005
Temporary Construction Area - AGI
Above Ground Installations
Temporary Construction Area- Pipeline
Flexible Drainage Area
Order Limits
Limit of Deviation
LEGEND
Pipeline Centreline
Temporary Construction Compound
T
h
r
o
l
a
m
D
r
a
i
n
T
o
l
l
i
n
g
h
a
m
C
o
n
s
t
r
u
c
t
i
o
n
C
o
m
p
o
u
n
d
D
r
a
i
n
Pond
Holme Common
D
R
A
I
N
L
A
N
E
3.8m
Plump Bungalow
M
a
i
n
D
r
a
i
n
3.7m
D
r
a
i
n
D
r
a
in
Northolme
Bursea
D
ra
in
D
r
a
i
n
T
r
a
c
k
D
r
a
i
n
WB
S
K
I
F
F
L
A
N
E
Tank
Tank
T
r
a
c
k
D
r
a
i
n
T
h
r
o
l
a
m
D
r
a
i
n
6.4m
Industrial Estate
D
r
a
in
Tollingham
Holme
Pond
Estate
Clay Hill
El Sub Sta
Drain
S
K
I
F
F
L
A
N
E
T
r
a
v
C
D
r
a
i
n
Pond
T
r
a
c
k
5.7m
Tollingham
D
ra
in
Industrial
3.3m
Track
Tollingham
4.2m
Skiff Lane
D
r
a
in
D
r
a
i
n
Tollingham Warren
T
ra
c
k
Skiff Cottage
Lodge
D
r
a
in
Pond
D
r
a
i
n
T
h
e
D
u
c
k
F
a
r
m
D
ra
in
Warehouse
Rascal Moor
Moor Farm
D
r
a
in
D
r
a
i
n
D
r
a
i
n
7.5m
T
r
a
c
k
T
r
a
c
k
S
K
I
F
F
L
A
N
E
Beverley
Woodlands
D
r
a
i
n
7.5m
8.3m
D
r
a
in
T
rack
D
r
a
i
n
D
r
a
i
n
D
r
a
i
n
Forest Farm
T
r
a
c
k
Pond
6.9m
S
K
I
F
F
L
A
N
E
T
r
a
c
k
6.8m
Pond
D
ra
in
Skiff Farm
D
r
a
i
n
T
r
a
c
k
D
ra
in
Tollingham
Dra
in
Pond
Oakfield
D
r
a
i
n
Dra
in
D
r
a
in
D
r
a
i
n
Cottages
T
h
r
o
l
a
m
D
r
a
i
n
D
ra
in
Drain
D
ra
in
Pond
Holme Common
Pond
Pond
D
r
a
i
n
Drain
Tollingham
Ladies' Parlour
Drain
D
ra
in
Track
L
O
C
K
L
A
N
E
Pond
D
ra
in
Drain
Track
Pond
D
ra
in
B
l
e
n
c
o
Bungalow
P
a
t
h
(
u
m
)
Drain
D
ra
in
D
ra
in
Fernlands
D
ra
in
D
ra
in
K
e
r
r
y
la
m
o
n
t
The
D
ra
in
South Field
D
ra
in
High Garth
9.4m
Highgate
D
ra
in
T
ra
c
k
Lowgate
9.2m
13.5m
Drain
Church Hill
44.9m
Cottage
Church Hill
D
r
a
in
Pond
Middle Field
All Saint's Church
Lych Gate
Beaconfield
T
ra
ck
Graveyard
Observer Corps Post
T
r
a
c
k
D
ra
in
Pond
Beacon Farm
D
r
a
i
n
Pond
D
r
a
in
Pond
Track
Pond
Well
Tollingham Warren
7.3m
D
ra
in
Dra
in
D
ra
in
L
O
C
K
L
A
N
E
D
ra
in
D
rain
D
ra
in
D
ra
in
4.3m
6.4m
Keepers Cottage
Drain
Pond
5.7m
D
r
a
i
n
T
rack
Pond
T
r
a
c
k
Drain
D
ra
in
T
r
a
c
k
Pond
D
ra
in
Track
Pond
D
r
a
i
n
D
r
a
in
6.1m
Woodlands
D
ra
in
9.5m
D
r
a
in
Tank
D
r
a
in
Track
Woodlands Farm
D
r
a
i
n
Pond
D
r
a
i
n
Pond
East Common
Low Plantation
C
L
I
F
F
E
L
A
N
E
Pond
Drain
9.0m
D
r
a
i
n
Pond
D
ra
in
S
u
e
h
e
a
d
D
r
a
i
n
Back D
elfin
L
O
C
K
L
A
N
E
Track
Land of Nod
The Landing
D
rain
B
e
ils
B
e
c
k
D
ra
in
Egrem
ont D
rain
4.5m
D
ra
in
Pond
M
id
d
le
D
r
a
in
D
ra
in
Ponds
(D
rain)
T
r
a
c
k
Track
Pond
D
ra
in
Landing Farm
D
ra
in
Pond
D
ra
in
Pp
D
ra
in
North Cliffe Carr
5.0m
Pond
Drain
D
ra
in
C
L
I
F
F
E
L
A
N
E
W
a
te
r
Pond
E
a
s
t
I
n
g
s
D
r
a
i
n
D
ra
in
D
rain
5.3m
D
ra
in
D
r
a
in
D
r
a
in
Pond
T
ra
ck
Back D
elfin
4.4m
Duck Nest
SAND LANE
(D
rain)
E
g
r
e
m
o
n
t
D
r
a
i
n
Pond
6.2m
Drain
Water
T
ra
c
k
New Farm
T
ra
c
k
B
e
il
s
B
e
c
k
D
r
a
in
Drain
D
ra
in
W
a
t
e
r
B
a
c
k
D
e
l
f
i
n
D
ra
in
D
ra
in
T
r
a
c
k
Weir
(
D
r
a
i
n
)
D
ra
in
Pond
Dra
in
T
ra
ck
B
o
w
m
a
n
D
ra
in
East Ings D
rain
Tanks
Pond
D
r
a
in
Drain
East Ings
Holly Farm
House
N
i
c
i
t
a
The Granary
The Lodge
Track
Tank
Barn
Biddys
Pit
Piggery
Silo
Pond
SD
D
e
f
D
e
f
SD
Def
S
C
D
Co C
onst &
W
ard B
dy
Def
Def
Def
1.22m RH
Co Const & Ward Bdy
1.83m Tk H
Def
D
e
f
1.22m RH
D
ra
in
D
ra
in
Drain
T
ra
c
k
D
ra
in
T
ra
c
k
D
ra
in
D
r
a
in
Tank
Carr Farm
4.6m
4.4m
Boundary Wood
D
ra
in
Pond
Drain
Pond
Drain
5.5m
5.1m
Oakwood
Drain
Top Cottages
SAND LANE
8.1m
Beilsbeck Bridge
Drain
Avenue Farm
Black Clump
T
ra
c
k
T
r
a
c
k
Trevillis
6.6m
B
e
i
l
s
B
e
c
k
4.3m
D
rain
D
r
a
i
n
(disused)
Camp House
D
ra
in
T
r
a
c
k
D
r
a
i
n
Farm
D
ra
in
Burial Ground
L
O
N
G
L
A
N
E
Pond
B
a
c
k
D
e
l
f
i
n
Lock
D
r
a
in
Pond
(
D
r
a
i
n
)
Pond
D
r
a
in
Lock
10.1m
Common Farm
P
a
t
h
(
u
m
)
T
r
a
c
k
Church Farm
R
IV
E
R
L
A
N
E
Pond
Pond
E
l
S
u
b
S
ta
B
o
w
m
a
n
D
r
a
in
B
e
i
l
s
B
e
c
k
Spring
D
r
a
i
n
D
ra
in
Pond
10.2m
SAND LANE
Drain
Manor House
D
r
a
in
Dra
in
North Cliffe Wood
Tank
Cliffe Wood
P
a
th
(
u
m
)
Farm
D
r
a
in
10.1m
P
a
t
h
(
u
m
)
North Cliffe Lodge
Pond
D
ra
in
North Cliffe Common
10.6m
D
ra
in
D
rain
D
ra
in
13.2m
Beilsbeck Farm
B
e
ils
B
e
c
k
11.2m
T
ra
c
k
D
r
a
in
L
O
N
G
L
A
N
E
Compact Farm
D
r
a
in
D
r
a
i
n
D
r
a
in
Deira
13.9m
GP
GP
Dra
in
T
ra
c
k
Honeysuckle Cottage
13.4m
West View
SAND LANE
Rook Cottaqes
GP
16.5m
GP
North Cliffe
Pond
Pond
D
rain
D
r
a
in
E
l
S
u
b
S
ta
(Care Home)
Linden House
T
ra
c
k
Polo Club
White Rose
Tanks
1
.
8
3
m
R
H
U
n
d
D
e
f
1
.8
3
m
R
H
C
o
C
o
n
s
t &
W
a
rd
B
d
y
D
e
f
1
.
8
3
m
R
H
C
S
C
o
C
o
n
s
t
&
W
a
r
d
B
d
y
C
S
C
S
1
.8
3
m
R
H
d
e
f
Sheet 4 of 11
Figure 3.4
National Grid Carbon Limited
31 Homer Road
Solihull
West Midlands
B91 3LT
Co-financed by the European Union's
European Energy Programme for Recovery.
SCHEME LAYOUT
Title
Sheet
Date
Scale
30th April 2014
PINs
PIN's Reference EN070001
Not to Scale
Fig.No.
YORKSHIRE AND HUMBER CCS
CROSS COUNTRY PIPELINE
Background Mapping reproduced from Ordnance Survey Data, with the permission of the
Controller of Her Majesty's Stationery Office. © Crown Copyright & Database Rights(2014).
National Grid Carbon Ltd. Licence - 100055005
Temporary Construction Area - AGI
Above Ground Installations
Temporary Construction Area- Pipeline
Flexible Drainage Area
Order Limits
Limit of Deviation
LEGEND
Pipeline Centreline
Temporary Construction Compound
Tollingham Block Valve
Temporary Construction Area
Inset : Tollingham Block Valve
Temporary Construction Compound
E
T
L
Sewage Works
R
O
M
A
N
R
O
A
D
(
c
o
u
r
s
e
o
f
)
P
ath (um
)
W
e
i
g
h
t
o
n
B
e
c
k
Piggery
Foxhaven Farm
D
r
a
i
n
P
a
t
h
(
u
m
)
Common
Weighton
House
Mile
E
T
L
DIXON CLOSE
23.6m
House
R
O
A
D
D
r
a
i
n
D
r
a
i
n
Drain
D
r
a
i
n
D
ra
in
D
r
a
in
B
o
w
m
a
n
D
r
a
i
n
D
r
a
i
n
SHIPMAN
D
r
a
i
n
Crossfield
Lake
D
ra
in
KE
LS
EY
C
LO
SE
D
r
a
in
D
rain
C
L
IF
F
E
R
O
A
D
Weighton Common
D
ra
in
26.0m
H
A
W
L
I
N
G
R
O
A
D
44.1m
Drain
D
ra
in
Pleasant
D
ra
in
Pond
D
ra
in
D
r
a
in
D
rain
Drain
E
T
L
D
r
a
i
n
Drain
D
r
a
i
n
D
ra
in
A 1079
Pond
K
IR
B
Y
C
L
O
S
E
C
LIF
F
E
R
O
A
D
Drain
W
O
L
D
R
O
A
D
41.7m
Pond
D
r
a
in
D
r
a
in
D
r
a
in
Mount
S
A
N
C
T
O
N
R
O
A
D
E
T
L
26.7m
D
r
a
in
R
O
M
A
N
R
O
A
D
D
ra
in
Sancton Wold
Mask Hall
Mask Plantation
A
1
0
3
4
P
a
th
(u
m
)
M
A
R
K
E
T
W
E
I
G
H
T
O
N
R
O
A
D
D
r
a
i
n
A
1
0
3
4
63.3m
63.1m
G
A
U
F
E
R
H
I
L
L
Old (dis)
51.0m
S
A
N
C
T
O
N
R
O
A
D
D
ra
in
R
O
M
A
N
R
O
A
D
Weighton Wold
Pond
El Ps
(
c
o
u
r
s
e
o
f
)
13.2m
D
r
a
in
L
O
N
G
L
A
N
E
Compact Farm
Pond
Manor Farm
Pond
D
r
a
i
n
P
a
t
h
(
u
m
)
T
r
a
c
k
L
O
N
G
L
A
N
E
Pond
D
r
a
in
Weighton Common
16.7m
D
r
a
i
n
Farm
Deira
B
o
w
m
a
n
D
r
a
in
Pond
Poplar
B
e
i
l
s
B
e
c
k
Pond
R
O
M
A
N
R
O
A
D
(
c
o
u
r
s
e
o
f
)
C
LIF
FE
R
O
AD
22.5m
D
r
a
i
n
S
H
O
R
T
L
A
N
E
D
ra
in
Weighton Common
T
r
a
c
k
D
ra
in
D
rain
D
r
a
in
D
r
a
in
22.6m
L
O
N
G
L
A
N
E
22.2m
C
L
IF
F
E
R
O
A
D
Pond
D
r
a
i
n
24.0m
Drain
D
r
a
i
n
Lodge
D
ra
in
19.5m
R
O
M
A
N
R
O
A
D
Drain
Drain
D
r
a
i
n
22.9m
Lodge Plantation
The White
Drain
Pond
D
r
a
i
n
(
c
o
u
r
s
e
o
f
)
High Common Farm
Sluice
S
a
n
d
W
a
l
k
(
P
a
t
h
)
Weir
FB
Weir
Fish Pond
D
rain
Washdyke
Mill Hill
Fish Pond
36.5m
P
a
t
h
(
u
m
)
Sandwalk Plantation
Cascade Clump
Millhill Plantation
FB
South Park
Pond
Plantation
B
e
ils
B
e
c
k
Pond
36.2m
Bracken Hill
Pond
Drive Plantation
North Lodge
38.6m
Drain
Court
D
ra
in
D
ra
in
Drain
North Park
North Cottage
Swimming Pool
Cattle Grid
S
a
n
d
W
a
l
k
(
P
a
t
h
)
Sandwalk Plantation
D
r
a
in
South Cottage
D
r
a
i
n
D
r
a
i
n
Cattle
D
rain
Drain
25.2m
Cattle Grid
Houghton Hall
Jackson's Plantation
Dra
in
27.6m
T
r
a
c
k
Grid
D
r
a
in
Drain
Cattle Grid
Tennis
42.6m
The Old Vicarage
Hayside
61.6m
lngleborough
47.3m
Sancton
Englefield
Coldwell Spring
Pond
Sandhill
D
r
a
in
Pond
44.7m
Mill Cottage
D
ra
in
Path (um)
House
D
r
a
in
D
ra
in
Santone
House
FB
Presbytery
Pond
H
O
U
G
H
T
O
N
L
A
N
E
HIGH STREET
Goldie
Farm
Summerfield
Pond
Goldie Hill
W
h
it
e
T
ra
c
k
Pond
Houghton Lane Farm
Mill
House
View
H
o
u
s
e
Sancton Grange
Fir Tree
M
A
R
K
E
T
W
E
I
G
H
T
O
N
R
O
A
D
Pond
D
rain
D
ra
in
Jingleton House
P
a
t
h
(
u
m
)
39.9m
Church
R
O
M
A
N
R
O
A
D
Whitegates Plantation
South
The Grove
D
ra
in
D
r
a
i
n
Cottages
Tank
Glen
D
r
a
in
D
r
a
i
n
FB
House
Pond
D
ra
in
Jacobite
50.9m
Russets
All Saints'
Sunnymeade
Hill
D
r
a
i
n
House
Cottages
Grove
Fir Tree
Drain
D
r
a
i
n
45.5m
D
r
a
i
n
S
u
n
n
y
s
id
e
House
Vale
West Winds
ETL
Birch
P
a
th
(
u
m
)
The
T
ra
c
k
D
ra
in
Pump
Farm
Pond
Silverthorn
Church
Pond
Pond
Pond
L
O
W
S
T
R
E
E
T
59.4m
Prospect
Tank
The Old School
House
E
T
L
E
TL
E
T
L
Reservoir
T
r
a
c
k
E
T
L
T
r
a
c
k
El Sub Sta
FB
Jemoon Stud
H
O
U
G
H
T
O
N
L
A
N
E
1
.
8
3
m
R
H
1
.8
3
m
R
H
D
e
f
D
e
f
C
S
1
.8
3
m
R
H
D
e
f
1.83m
R
H
R
H
1
.
8
3
m
T
k
H
S
D
D
e
f
1
.8
3
m
R
H
1
.8
3
m
R
H
1
.
8
3
m
R
H
D
e
f
D
e
f
1
.8
3
m
R
H
Def
1
.8
3
m
R
H
D
e
f
Tel Ex
2
6
.3
m
House
Bow
PH
L
IN
E
G
A
T
E
W
E
S
T
F
I
E
L
D
R
O
A
D
Hall
Bridge
Works
Bank
Club
M
A
N
O
R
F
I
E
L
D
S
MARKET
WEIGHTON
R
O
A
D
P
a
t
h
(
u
m
)
CROFT
FB
S
ID
E
A
l
l
o
t
m
e
n
t
G
a
r
d
e
n
s
B
r
i
c
k
y
a
r
d
C
o
t
t
a
g
e
Well
ST
AT
IO
N R
OA
D
2
5
.0
m
Surgery
A
V
E
N
U
E
L
O
N
D
E
S
B
O
R
O
U
G
H
R
O
A
D
(P
la
y
g
ro
u
n
d
)
22.6m
The Green
H
u
n
g
a
t
e
24.7m
S
O
U
T
H
G
A
T
E
B
e
c
k
Path
Community Hall
LB
Wold View
Oak Lea
All Saints
S
O
U
T
H
F
I
E
L
D
P
A
R
K
S
P
R
I
N
G
N
O
R
T
H
G
A
T
E
G
R
O
V
E
P
R
O
V
I
D
E
N
C
E
R
O
W
ESS
N
o
v
a
P
O
Library
Sub Sta
G
L
E
N
F
I
E
L
D
25.5m
LB
P
R
I
N
C
E
S
S
R
O
A
D
26.1m
Yard
W
E
S
T
F
I
E
L
D
C
R
E
S
C
E
N
T
TCB
Council
S
A
N
D
F
I
E
L
D
C
L
O
S
E
W
o
r
k
s
PCs
B
e
c
k
P
r
i
n
c
e
s
s
P
a
r
a
d
e
S
k
e
l
f
r
e
y
21.3m
S
A
N
D
W
A
L
K
Area
Play
Church
T
U
R
N
E
R
C
L
O
S
E
FB
The Badgers
A
1
0
7
9
A
1
0
7
9
Weir
El
Track
FB
D
r
a
in
Becklands Park
S
Q
U
A
R
E
Market Weighton
H
o
l
m
e
l
e
a
25.2m
W
e
s
t
f
i
e
l
d
FIN
KLE
S
TR
EE
T
Smithy
PH
Works
B
a
n
k
LB
R
O
A
D
M
A
R
K
E
T
P
L
A
C
E
Gas Pump
Depot
S
T
H
E
L
E
N
'
S
M
e
m
o
ria
l P
la
y
in
g
F
ie
ld
El Sub Sta
D
r
a
i
n
H
O
L
M
E
R
O
A
D
C
o
u
r
t
M
ill
B
e
c
k
24.9m
25.2m
Playing Field
W
e
i
g
h
t
o
n
B
e
c
k
TCB
HALL
C
R
O
F
T
C
L
O
S
E
Paraiso
26.3m
FB
Y
O
R
K
C
L
O
S
E
Y
O
R
K
R
O
A
D
El Sub Sta
T
e
r
r
a
c
e
Infants School
BEECH CLOSE
Tennis Courts
P
H
26.9m
C
H
U
R
C
H
29.2m
Institute
S
C
O
T
T
S
All Saints'
N
O
R
T
H
G
A
T
E
V
A
L
E
Church
PH
H
I
G
H
S
T
R
E
E
T
Bank
T
H
E
A
R
C
H
W
A
Y
Builder's
27.5m
H
A
W
L
I
N
G
R
O
A
D
Yard
H
o
te
l
S
K
E
L
T
O
N
C
R
E
S
C
E
N
T
P
R
I
N
C
E
S
S
C
L
O
S
E
D
r
a
i
n
Play Ground
H
o
lm
e
C
o
u
r
t
Bradley Court
Red
House
V
i
e
w
C
R
O
F
T
V
I
E
W
Court
TCB
ASH GROVE
Gas Gnr
W
I
C
S
T
U
N
W
A
Y
S
T
E
P
H
E
N
S
O
N
C
L
O
S
E
H
A
N
S
O
N
C
L
O
S
E
W
I
L
S
O
N
C
L
O
S
E
P
A
R
K
S
I
D
E
C
R
U
M
P
T
O
N
R
O
A
D
S
T
E
E
L
C
L
O
S
E
SHIPMAN ROAD
S
W
E
E
P
C
L
O
S
E
W
o
o
d
l
a
n
d
s
W
i
c
s
t
u
n
L
o
d
g
e
S
W
E
E
P
R
O
A
D
Tennis Court
B
E
D
A
L
E
R
O
A
D
C
L
O
S
E
C
T
Piggery
Pol Sta
28.0m
L
A
N
G
D
A
L
E
H
U
M
B
E
R
S
T
R
E
E
T
(
T
r
a
c
k
)
D
ra
in
A
1
0
3
4
31.7m
TCB
Fire
D
ra
in
S
A
N
C
T
O
N
R
O
A
D
MEADOW DRIVE
D
r
a
in
C
h
u
rc
h
P
R
IN
C
E
S
S
R
O
A
D
A
1
0
7
9
LY
S
A
N
D
E
R
D
R
IV
E
Sta
37.5m
H
IL
L R
IS
E D
R
IV
E
W
A
L
K
LB
E
l
S
u
b
S
t
a
D
ra
in
L
E
A
C
R
O
F
T
H
IL
L R
IS
E
GLE
BE
LA
ND
S
W
A
L
K
P
A
S
T
U
R
E
N
O
R
T
H
F
I
E
L
D
R
O
A
D
Station
H
ILL R
IS
E
C
LO
S
E
El
(
c
o
u
r
s
e
o
f
)
D
r
a
i
n
L
A
M
B
E
R
T
C
L
O
S
E
E
A
S
T
F
IE
L
D
R
O
A
D
B
E
D
A
L
E
C
T
Dra
in
MILL
C
LIF
FE
R
O
AD
Club
D
ra
in
Orchards
O
L
D
Bowling
ETL
The
S
P
R
I
N
G
R
D
R
O
M
A
N
R
O
A
D
29.1m
(covered)
MS
Tower
D
r
a
in
BEVERLEY R
OAD
W
O
LD
A
V
E
N
U
E
Market Weighton Reservoir
T
H
E
30.1m
Mill Farm
D
r
a
i
n
Green
H
U
M
B
E
R
S
T
R
E
E
T
(
T
r
a
c
k
)
S
O
U
T
H
G
A
T
E
T
H
E
C
L
O
S
E
R
O
A
D
H
IL
L
R
IS
E
C
L
SA
IN
T A
ID
EN
C
LO
SE
C
E
N
T
U
R
IO
N
Pond
31.2m
C
O
R
N
E
L
IU
S
B
E
D
A
L
E
W
A
L
K
25.5m
EBO
R
V
IE
W
Sub
H
U
M
B
E
R
S
T
R
E
E
T
R
IC
H
M
O
N
D
C
L
O
S
E
26.2m
O
R
C
H
A
R
D
Hall
Hall
GP
49.6m
W
EIG
H
TO
N
H
IL
L
W
O
L
D
R
O
A
D
M
iddle
D
ale
R
O
M
A
N
R
O
A
D
A
1
0
7
9
The Bungalow
(disused)
D
ra
in
Pit
107.8m
Wold Cottages
Weighton Wold
(
c
o
u
r
s
e
o
f
)
Pit
89.6m
H
U
M
B
E
R
S
T
R
E
E
T
(T
ra
c
k
)
WEIGHTON HILL
Weighton Wold
Middle Dale
House
Weighton Wold
Reservoir (covered)
50.9m
Pump House
48.7m
S
P
R
IN
G
R
O
A
D
St Helen's Well
GP
S
P
R
IN
G
D
A
L
E
R
O
A
D
47.2m
S
P
R
I
N
G
D
A
L
E
32.5m
G
A
R
T
H
R
O
A
D
S
P
R
IN
G
R
O
A
D
G
O
O
D
M
A
N
H
A
M
45.1m
39.4m
P
a
t
h
(
u
m
)
46.9m
S
P
R
IN
G
D
A
L
E
R
O
A
D
Beck
Weighton Wold
LB
R
E
D
L
A
N
E
R
O
A
D
49.5m
M
ill
R
O
M
A
N
R
O
A
D
28.0m
S
p
rin
g
D
a
le
28.3m
D
is
m
a
n
tle
d
R
a
ilw
a
y
Spring
D
ra
in
D
ra
in
El Sub
50.6m
Sta
DA
LE
Mill House
E
L
L
I
O
T
W
A
Y
S
H
I
P
M
A
M
R
O
A
D
P
O
T
T
E
R
E
l
S
u
b
S
t
a
C
L
O
S
E
PH
S
W
A
L
E
S
D
R
I
V
E
TH
E
M
A
LTIN
G
S
T
r
a
c
k
D
ra
in
T
r
a
c
k
S
o
u
t
h
g
a
t
e
C
o
u
r
t
P
a
t
h
(
u
m
)
Football Ground
R
ip
le
y
P
la
c
e
P
i
n
e
C
o
u
r
t
S
A
N
D
H
O
L
M
E
E
l
S
u
b
S
t
a
Hudson
Lammas
House
Court
Court
Stable
Playground
Tryste House
Court
Day Nursery
ESS
H
olly
beth
H
ouse
FINKLE COURT
Car Park
Finkle
Mews
B
e
a
l
C
o
u
r
t
Masons
Yard
ESS
Ingle Court
S
L
A
T
E
R
C
O
U
R
T
ESS
Superstore
Ps
CHAPEL
CORNER
Y
o
r
k
T
e
r
r
a
c
e
Liby
Wicstun
Centre
ESS
C
ro
s
s
K
e
y
s
C
o
u
rt
Mount Pleasant
Church of England
Voluntary Controlled
Junior School
St Mary's
Market Weighton,
Roman Catholic
Primary School
(Secondary)
The Market Weighton School
Youth Centre
St
1.22m
RH
D
e
f
C
O
C
S
D
e
f
CS
K
IN
G
S
C
O
U
R
T
G
IA
N
T
B
R
A
D
L
E
Y
W
A
Y
Tumuli
Sancton
Wold
(disused)
Anglo-Saxon
Weighton Wold
E
T
L
(sites of)
Pit
Burial Ground
(site of)
T
r
a
c
k
Long Barrow
E
a
r
th
w
o
r
k
E
T
L
Sancton
(disused)
(
c
o
u
r
s
e
o
f
)
Wold
D
a
le
R
o
a
d
(
T
r
a
c
k
)
Pit
Pit
Noddles Hill
(disused)
T
r
a
c
k
1
.
8
3
m
R
H
D
e
f
(site of)
Tumulus
Weighton
MS
(sites of)
Tumuli
Tumuli
(site of)
Tumulus
(site of)
T
ra
c
k
High Wold Farm
Weighton Wold
146.1m
141.6m
Tumulus
Tumulus
Plantation
Tumuli
A
1
0
7
9
Tumulus
W
E
IG
H
T
O
N
H
IL
L
L
a
y
-b
y
(site of)
Callas Wold
T
r
a
c
k
(sites of)
Tumulus
(sites of)
Wold
Wold
Track
Weighton
Noddles Hill
145.4m
Pits
Sancton Wold
127.1m
137.8m
Track
Tumulus
Arras Reservoir
Weighton Wold
A 1079
131.0m
(covered)
MS
(site of)
(disused)
Weighton Wold
T
r
a
c
k
WOLD HOUSE FARM
Masts (Telecommunication)
1
.8
3
m
R
H
1
.
2
2
m
R
H
1.2
2m
R
H
1
.
8
3
m
T
k
H
D
e
f
D
e
f
1
.
8
3
m
R
H
Def
Sheet 5 of 11
Figure 3.5
National Grid Carbon Limited
31 Homer Road
Solihull
West Midlands
B91 3LT
Co-financed by the European Union's
European Energy Programme for Recovery.
SCHEME LAYOUT
Title
Sheet
Date
Scale
30th April 2014
PINs
PIN's Reference EN070001
Not to Scale
Fig.No.
YORKSHIRE AND HUMBER CCS
CROSS COUNTRY PIPELINE
Background Mapping reproduced from Ordnance Survey Data, with the permission of the
Controller of Her Majesty's Stationery Office. © Crown Copyright & Database Rights(2014).
National Grid Carbon Ltd. Licence - 100055005
Temporary Construction Area - AGI
Above Ground Installations
Temporary Construction Area- Pipeline
Flexible Drainage Area
Order Limits
Limit of Deviation
LEGEND
Pipeline Centreline
Temporary Construction Compound
Temporary Construction Area 5
Spring
Springwells Pumping
Snever Dale
39.6m
Spring
Reservoir (covered)
Issues
46.2m
Goodmanham
Station
Crunkhill
Rifle Butts Quarry
(geological reserve)
Dale
Track
Goodmanham
1.22m RH
1.22m
Tk H
Def
Springwell
Wold
Dale
Field
Goodmanham
Guide
T
ra
c
k
D
is
m
a
n
tl
e
d
R
a
il
w
a
y
(disused)
Wold
Track
Pit
The D
ale
Weighton
Post
Goodmanham
G
o
o
d
m
a
n
h
a
m
D
a
l
e
Field
90.5m
50.2m
Wold
Goodmanham
T
ra
ck
96.6m
T
ra
c
k
Springwell
C
R
O
S
S
G
A
T
E
96.3m
T
r
a
c
k
Springwell Field
Round Hill
Pond
Goodmanham Wold
Weighton Wold
47.4m
Dale
51.3m
Goodmanham
Stone
53.1m
Round Hill
50.7m
Pond
(
N
a
t
u
r
e
R
e
s
e
r
v
e
)
Cattle Grid
D
i
s
m
a
n
t
l
e
d
R
a
i
l
w
a
y
T
ra
c
k
Goodmanham
(disused)
Pit
G
o
o
d
m
a
n
h
a
m
D
a
l
e
K
i
p
l
i
n
g
c
o
t
e
s
C
h
a
l
k
P
i
t
P
a
t
h
(
u
m
)
Wold
Allotment Farm
T
r
a
c
k
113.7m
Goodmanham Wold
112.8m
Well
T
r
a
c
k
T
r
a
c
k
Goodmanham Wold Farm
T
r
a
c
k
(c
o
u
rs
e
o
f)
Weighton Wold
77.8m
69.0m
KIP
LIN
GC
OT
ES
L
AN
E
Goodmanham Wold
E
a
rth
w
o
rk
Springwell Field
93.4m
House
42.3m
54.9m
E
a
r
t
h
w
o
r
k
(course of)
Warren Lodge
Springwell Field
(disused)
T
ra
c
k
Weighton Wold
Goodmanham Lodge Farm
Earthwork
40.5m
Pump
46.6m
G
o
o
d
m
a
n
h
a
m
D
a
l
e
44.0m
Kipling Cotes
(disused)
43.7m
63.1m
WB
Dism
antled R
ailway
Ridge Hill
Station
Goodmanham Wold
Station
78.3m
Pit
51.4m
46.7m
K
IP
L
IN
G
C
O
T
E
S
L
A
N
E
Sheep Dip
Farm
Sheep Dip
K
ip
lin
g
C
o
te
s
R
a
c
e
C
o
u
r
s
e
68.9m
(course of)
72.7m
South Dalton Wold
Pump
Course Hill
Earthw
ork
68.9m
Wold
39.8m
Goodmanham Dale
Etton Wold
Common Wold
Pump House
Walk House Farm
Goodmanham
78.5m
Southwold Farm
Dalton
Old Dale
Holme Wold
High Wold Fall
Etton Wold
Wold
K
i
p
l
i
n
g
C
o
t
e
s
R
a
c
e
C
o
u
r
s
e
South
Goodmanham Wold
Track
Tumulus
Kiplingcotes
Money Hill
Path (um)
Etton Wold
T
r
a
c
k
Weighton Wold
Ea
rth
wo
rk
(site of)
Tumulus
77.9m
(co
urse
o
f)
Quarry
Pit
Stone
Ridge Hill
Ridgehill Cottage
Wallis
Grange
79.6m
(disused)
WB
Tumuli
T
ra
c
k
Claphams
(sites of)
68.0m
GP
43.5m
Pond
North Flinders
(sites of)
Etton Wold
(disused)
D
is
m
a
n
tle
d
R
a
ilw
a
y
75.7m
Tumuli
T
rack
(disused)
47.5m
56.9m
Fir Tree Cottage
Etton Wold
63.3m
GP
GP
Stone
60.2m
Common Wold
37.9m
PARK ROAD
Pit
44.0m
Plantation
P
a
t
h
(
u
m
)
50.9m
T
r
a
c
k
58.8m
45.6m
K
ip
lin
g
C
o
te
s
R
a
c
e
C
o
u
r
s
e
60.1m
Old Dale
South Dalton Wold
(disused)
O
l
d
D
a
l
e
77.3m
Golden
Holme Wold
Little Wold
T
r
a
c
k
Stagbush Fall
Wold
80.2m
Track
62.6m
66.9m
Admirals
(disused)
PARK ROAD
Farm
South
Cottage
Money Pot
Kiplingcotes
Kiplingcotes
Cottages
Pit
Wold
58.5m
Moneypot Hill
Dalton
Long
Dale
Valley
T
r
a
c
k
Sheep Dip
(disused)
T
ra
c
k
T
ra
c
k
T
ra
c
k
Etton Wold
Pit
Cat Babbleton
T
ra
ck
Track
(disused)
South Dalton Wold
31.9m
32.1m
31.4m
Well
T
ra
c
k
47.8m
T
ra
c
k
41.0m
41.8m
(disused)
South
Short Dale
T
ra
c
k
Worm Hill Plantation
Raikes Hill
Little Wold
Hanging Grimstone
Nut Balks
T
ra
c
k
T
ra
c
k
Track
Plantation
Raikeshill Plantation
Jackson's
P
A
R
K
R
O
A
D
Dalton
Wold
T
r
a
c
k
Pit
T
ra
c
k
48.9m
T
e
n
n
i
s
C
o
u
r
t
T
r
a
c
k
T
r
a
c
k
1
.
2
2
m
R
H
1.22m R
H
1.2
2m
R
H
Def
D
e
f
Def
Def
1
.
2
2
m
R
H
1.2
2m
R
H
D
e
f
1
.2
2
m
R
H
C
o
C
o
n
s
t &
W
a
rd
B
d
y
1
.2
2
m
T
k
H
D
e
f
C
R
D
e
f
1.22m RH
1.22m RH
C
o
C
o
n
s
t
&
W
a
r
d
B
d
y
1
.2
2
m
R
H
D
e
f
Def
C
o
C
o
n
s
t
&
W
a
r
d
B
d
y
1
.2
2
m
1.42m RH
R
H
D
e
f
1
.
2
2
m
R
H
C
o
C
o
n
s
t
&
W
a
r
d
B
d
y
D
e
f
D
e
f
1
.
2
2
m
R
H
Def
C
o C
onst &
W
ard B
dy
Boundary Stone
D
e
f
1
.2
2
m
T
k
H
1.22m
T
k H
1.42m RH
D
e
f
D
e
f
1.2
2m
R
H
1.4
2m
R
H
1
.4
2
m
R
H
D
e
f
Dalton Park
Sundial
Tennis
31.3m
Fn
Lodge
Court
P
a
th
(u
m
)
Cattle Grid
Bothy
South
Dalton
Wold
Cottage
Cottages
South
Gardener's
P
a
th
(
u
m
)
28.2m
Etton Wold
P
a
th
28.1m
South
(disused)
Cottage
Dalton
Park
Cottage
33.2m
Cottages
R
o
b
in
R
h
e
a
B
a
lk
Laundry
T
r
a
c
k
PARK ROAD
Icehouse
R
obin R
hea B
alk
Dalton Park
T
ra
c
k
Wold
T
r
a
c
k
Dalton Wood
Keeper's
Pit
Bryans Plantation
Dalton Hall
Stable
Reservoir Clump
Cottages
Cattle Grid
37.5m
32.3m
Duck Planting
(disused)
1
.2
2
m
R
H
Oak
Def
F
F
Oak
Oak
D
e
f
S
P
D
e
f
Oak
Sheet 6 of 11
Figure 3.6
National Grid Carbon Limited
31 Homer Road
Solihull
West Midlands
B91 3LT
Co-financed by the European Union's
European Energy Programme for Recovery.
SCHEME LAYOUT
Title
Sheet
Date
Scale
30th April 2014
PINs
PIN's Reference EN070001
Not to Scale
Fig.No.
YORKSHIRE AND HUMBER CCS
CROSS COUNTRY PIPELINE
Background Mapping reproduced from Ordnance Survey Data, with the permission of the
Controller of Her Majesty's Stationery Office. © Crown Copyright & Database Rights(2014).
National Grid Carbon Ltd. Licence - 100055005
Temporary Construction Area - AGI
Above Ground Installations
Temporary Construction Area- Pipeline
Flexible Drainage Area
Order Limits
Limit of Deviation
LEGEND
Pipeline Centreline
Temporary Construction Compound
Bulmers Triangle
Holme Wold
Kiplingcotes 77.3m
Golden
Holme Wold
Little Wold
80.2m
Admirals
South
Cottage
Money Pot
Moneypot Hill
Dalton Valley
T
ra
c
k
South
Short Dale
Raikes Hill
Little Wold
T
ra
c
k
T
ra
c
k
Track
Plantation
Raikeshill Plantation
Jackson's
Dalton
Wold
D
e
f
Field
T
r
a
c
k
52.5m
52.4m
53.0m
Holme Dale
Track
54.8m
Great West
(disused)
Track
Swiftdale
Plantation
Little West Field
Holme Wold
Pit
68.7m
Lund Wold
66.5m
Holme Wold
63.3m
67.9m
61.9m
Middleton Wold
T
ra
c
k
56.3m
Lund Wold
Farm
Woodland Lodge
Prickett's Hollow
Pond
Wold House
74.4m
P
a
th
(u
m
)
76.1m
67.7m
Tra
ck
T
ra
ck
T
ra
c
k
P
a
th
(
u
m
)
P
a
th
(u
m
)
Stone
MS
G
O
O
D
M
A
N
H
A
M
R
O
A
D
T
ra
c
k
T
r
a
c
k
Poultry Packing
T
r
a
c
k
(disused)
A
1
6
3
S
O
U
T
H
S
T
R
E
E
T
53.1m
S
O
U
T
H
D
R
I
V
E
Gate
Pond
Andrew's
Station
St
Church
Office
Westerly
C
h
u
r
c
h
H
ill
F
a
r
m
TCB
B
E
V
E
R
LE
Y
R
O
A
D
House
Pond
P
I
C
K
E
R
I
N
G
P
A
R
K
49.1m
52.7m
G
R
E
E
N
F
I
E
L
D
R
O
A
D
O
R
C
H
A
R
D
D
R
IV
E
West End
4
8
.
4
m
Wr T
54.3m
Pit
House
Pav
F
R
O
N
T
S
T
R
E
E
T
Farm
A
N
D
R
E
W
'S
C
L
O
S
E
Pit
Pond
(disused)
Club
P
a
th
(
u
m
)
Bowling Green
A
l
l
o
t
G
d
n
s
The Old
PH
L
A
N
E
P
a
t
h
(
u
m
)
P
a
th
(
u
m
)
T
ra
c
k
44.7m
PH
PO
Police
Church
Industrial
Estate
Cemetery
Lych
El Sub Sta
Pigeon Cote
School
S
T
Ivy
C
H
A
P
E
L
T
H
O
M
P
S
O
N
D
R
I
V
E
V
I
L
L
A
G
E
F
A
R
M
T
r
a
c
k
Tra
ck
1
7
Angilandy
Tanks
Silo
1
.2
2
m
R
H
1.22m RH
1.2
2m
R
H
D
e
f
Def
South
(disused)
Dalton
R
o
b
in
R
h
e
a
B
a
lk
T
r
a
c
k
Pit
Bryans Plantation
Reservoir Clump
Reservoir
Holme
Wold
Pit
52.1m
House
Whirligig
The Cottage
Holme Wold
(disused)
(covered)
48.7m
Head's Plantation
55.9m
Track
Bulmers Triangle
Lund Wold
52.9m
58.4m
53.0m
R
O
A
D
Stone
Pit
Pit
(disused)
T
r
a
c
k
B
E
V
E
R
L
E
Y
Track
(disused)
P
a
th
(u
m
)
Vicarage Farm
Lund Wold
Piggery
Bath
MS
Disinfectant
Silos
B
E
V
E
R
L
E
Y
R
O
A
D
Vehicular
P
a
th
(
u
m
)
Holme Planting
Smithy
47.1m
EAST STREET
Town End Farm
47.9m
Holme on the
GP
W
r
T
Holme Wold
Harolds Wood
Farm
C
hurc
h L
ane
Elms
S
t P
e
te
r's C
h
u
rc
h
Wolds
LB
47.9m
Village Farm
Graveyard
Business Centre
45.8m
(s
ite
o
f)
48.7m
TCB
29.0m
39.2m
GP
D
r
a
i
n
Pit
Pump
Pond
Farm
Lund Wold
B
1
2
4
8
41.7m
40.6m
38.6m
GP
Corporation
W
EST E
ND
39.5m
47.2m
26.4m
(disused)
House
House
Ivy
Hotham House Farm
Lund Wold
GP
Pit
43.0m
Farm
High Farm
House
Springfield
(disused)
Hall
Lund
B 1248
MS
Field
Pleasant
Well
Pit
Mount
(disused)
T
ra
c
k
Tank
GP
Farm
47.9m
Pond
Church
Pond
Dra
in
All
GP
B
1
2
4
8
35.6m
46.0m
45.7m
G
R
E
E
N
Saint's
40.3m
Playing Field
Track
Sheep Dip
Lockington
C
r
o
s
s
Clematis
Silo
T
H
E
41.1m
44.6m
46.4m
(P
H)
GP
Pits
TCB
View
Manor House Farm
LOCKINGTON ROAD
NO
RT
H R
OA
D
W
ellington Inn
Pond
Chapel
D
ra
in
(disused)
B
1
2
4
8
Pond
29.5m
Pond
Pembroke House
Track
Track
Tennis C
ourt
Pond
Oak House
Lund House
Pond
1.22m RH
D
e
f
Und
1
.2
2
m
R
H
1.2
2m
R
H
Def
1.22m RH
1.22m RH
1
.
2
2
m
R
H
1.2
2m
R
H
1
.
2
2
m
R
H
1
.8
3
R
H
1
.2
2
m
R
H
1.2
2m
R
H
2
.
7
4
m
R
H
1.5
2m
R
H
D
e
f
1.2
2m
R
H
1.2
2m
R
H
Pond
T
r
a
c
k
(disused)
Lair Hill
96.9m
T
ra
c
k
Tra
ck
Warren Dale
D
i
s
m
a
n
t
l
e
d
R
a
i
l
w
a
y
Pond
90.5m
78.9m
Holme Wold
Pit
87.0m
Lund Wold
Pond
83.9m
71.8m
Ledge Hill
Lund Warren
Farm
Warren Dale
Cow Dale
Lund Wold
D
i
s
m
a
n
t
l
e
d
R
a
i
l
w
a
y
Cottages
Pond
Warren House
1
.
2
2
m
R
H
D
e
f
D
e
f
Sheet 7 of 11
Figure 3.7
National Grid Carbon Limited
31 Homer Road
Solihull
West Midlands
B91 3LT
Co-financed by the European Union's
European Energy Programme for Recovery.
SCHEME LAYOUT
Title
Sheet
Date
Scale
30th April 2014
PINs
PIN's Reference EN070001
Not to Scale
Fig.No.
YORKSHIRE AND HUMBER CCS
CROSS COUNTRY PIPELINE
Background Mapping reproduced from Ordnance Survey Data, with the permission of the
Controller of Her Majesty's Stationery Office. © Crown Copyright & Database Rights(2014).
National Grid Carbon Ltd. Licence - 100055005
Temporary Construction Area - AGI
Above Ground Installations
Temporary Construction Area- Pipeline
Flexible Drainage Area
Order Limits
Limit of Deviation
LEGEND
Pipeline Centreline
Temporary Construction Compound
Dalton Block Valve
Temporary Construction Area
Inset : Dalton Block Valve
34.9m
36.3m
Pit
31.2m
Pit
(disused)
34.1m
East
(disused)
MS
Field
T
r
a
c
k
T
r
a
c
k
22.4m
43.4m
28.4m
M
I
D
D
L
E
T
O
N
R
O
A
D
GP
Cottages
25.4m
44.5m
32.4m
D
i
s
m
a
n
t
l
e
d
R
a
i
l
w
a
y
30.5m
A
6
1
4
B
1
2
4
8
39.7m
Railway
33.9m
30.9m
Hornhill Top
Chalk Pit
33.5m
29.5m
B
1
2
4
8
Pond
Horn Hill
Works
Drain
24.3m
20.8m
21.7m
Issues
Poultry
Houses
WB
B
r
a
c
k
e
n
B
e
c
k
Pla
nta
tio
n
Drain
24.7m
19.6m
We
stb
elt
Drain
Old MS
14.9m
GP
15.2m
19.8m
BR
AC
KE
N LA
NE
Bracken Beck
13.9m
Hind
Cattle Grid
Cawkeld Field
Cattle Grid
Cottage
19.3m
Grid
Kilnwick New Farm
18.1m
24.8m
Spring
21.6m
Drain
B
ra
cke
n
B
e
ck
Pond
House
Cattle
29.1m
Bracken
Bracken
21.1m
Cattle Grid
18.5m
Tra
ck
Cawkeld
FB
Post
D
r
a
i
n
Post
17.1m
Cattle Grid
FB
Cawkeld
Cawkeld Sinks
Drain
FB
Drain
FB
Wedding Wood
Watton Beck
Post
FBs
Sluice
Pond
D
r
a
in
Cottages
Folly
C
a
w
k
e
ld
s
in
k
s
P
la
n
ta
tio
n
C
R
A
B
T
R
E
E
L
A
N
E
Post
14.9mBracken Fold
Track
Tennis Court
Track
T
r
a
c
k
Pond
Pond
Pond
Pond
D
e
f
1
.2
2
m
R
H
Co Const & W
ard Bdy
2.74m
R
H
D
e
f
1
.8
3
m
R
H
1
.8
3
m
R
H
1.2
2m
R
H
C
o
C
o
n
s
t
&
W
a
rd
B
d
y
1
.2
2
m
R
H
D
e
f
1
.2
2
m
R
H
Co Const & Ward Bdy
C
o
C
o
n
s
t
1.8
3m
R
H
S
S
&
W
a
r
d
B
d
y
C
o
C
o
n
s
t &
W
a
rd
B
d
y
1.8
3m
F
F
Def
1
.
8
3
m
R
H
Co Const & Ward Bdy
F
F
1.83m RH
1.8
3m
R
H
1
.8
3
m
F
F
1.83m RH
S
S
1
.
8
3
m
R
H
D
e
f
1.8
3m
F
F
1.83m Tk H
1.83m RH
Co Const & Ward Bdy
Co Const & Ward Bdy
D
e
f
1
.
8
3
m
F
F
1
.
8
3
m
R
H
W
ard B
dy
C
o C
onst &
W
ard B
dy
M
ID
D
L
E
T
O
N
R
O
A
D
Bainton Balk Farm
(disused)
GP
Council Houses
48.5m
E
T
L
B
1
2
4
8
42.3m
39.6m
Bainton lodge
GP
S
T
A
T
IO
N
R
O
A
D
Pit
Spring
Pond
37.1m
L
E
A
F
IE
L
D
R
O
A
D
45.7m
32.1m
B 1248
Pit
48.5m
A
6
1
4
(disused)
47.2m
Chalk Pit
O
LD
FIE
LD
L
AN
E
Old Field
T
ra
c
k
(T
ra
ck)
28.2m
Neswick Cottage
27.6m
Pond
E
T
L
Pond
Drain
T
ra
c
k
26.4m
Neswick Gardens
N
E
S
W
IC
K
L
A
N
E
32.3m
Neswick Hall
Pond
29.0m
32.6m
Pond
43.2m
Track
BURNBUTTS LANE
46.8m
41.1m
Dra
in
42.9m
Issues
26.2m
29.0m
E
T
L
35.5m
Pit
Pond
Grid
Cattle Grids
32.7m
Cattle
32.2m
Neswick Farm
39.7m
(disused)
Stackyard House
Pond
Old Field
D
ra
in
26.8m
26.5m
23.1m
BURNBUTTS LANE
(disused)
38.5m
41.0m
41.1m
Burn Butts
Pit
Burn Butts Cottages
Cawkeld Field
D
r
a
in
Bustardnest Fox Covert
Bustard Nest Farm
T
r
a
c
k
D
ra
in
Tank
D
r
a
i
n
The Farm House
Track
T
r
a
c
k
T
r
a
c
k
Track
Track
Pond
1
.2
2
m
R
H
1
.
2
2
m
R
H
Def
1.5
2m
R
H
Def
1.52m RH
D
ef
1.2
2m
R
H
1.22m
R
H
1
.2
2
m
R
H
F
F
1.5
2m
T
k H
D
e
f
1.5
2m
F
F
Def
1.52m
R
H
1
.5
2
m
R
H
1
.5
2
m
F
F
1.52m RH
D
e
f
1
.
2
2
m
R
H
D
e
f
1.2
2m
R
H
1
.
2
2
m
R
H
1.52m RH
1.52m FF
1.52m
R
H
1.52m
F
W
1
.
5
2
m
F
F
FW Def
1.52m
1.52m Tk H
Def
FW
T
k
H
1
.
2
2
m
R
H
1
.
2
2
m
R
H
1
.
2
2
m
R
H
1
.
2
2
m
W
a
r
d
B
d
y
W
a
r
d
B
d
y
W
a
r
d
B
d
y
D
e
f
Def
Drain
Pond
26.6m
BURNBUTTS LANE
23.2m
Drain
D
ra
in
D
ra
in
34.6m
Burnbutts Pits
Swinekeld Field
(disused)
Cawkeld Chalk Pit
(disused)
D
r
a
i
n
Pond
29.7m
Little Bustard Farm
BU
RN
BU
TT
S LA
NE
29.1m
28.9m
27.3m
D
r
a
i
n
Drain
Maple Lodge
Def
1.52m
R
H
Sheet 8 of 11
Figure 3.8
National Grid Carbon Limited
31 Homer Road
Solihull
West Midlands
B91 3LT
Co-financed by the European Union's
European Energy Programme for Recovery.
SCHEME LAYOUT
Title
Sheet
Date
Scale
30th April 2014
PINs
PIN's Reference EN070001
Not to Scale
Fig.No.
YORKSHIRE AND HUMBER CCS
CROSS COUNTRY PIPELINE
Background Mapping reproduced from Ordnance Survey Data, with the permission of the
Controller of Her Majesty's Stationery Office. © Crown Copyright & Database Rights(2014).
National Grid Carbon Ltd. Licence - 100055005
Temporary Construction Area - AGI
Above Ground Installations
Temporary Construction Area- Pipeline
Flexible Drainage Area
Order Limits
Limit of Deviation
LEGEND
Pipeline Centreline
Temporary Construction Compound
Driffield
Construction
Compound
Spring
LB
1
4
2
128
6
7
El Sub Sta
1
3
2
1
2
9
127
LB
G
O
T
T
C
L
O
S
E
A
6
1
4
Pond
Mallard House
Spring
Ponds
5
L Twr
G
O
T
T
C
L
O
S
E
1
3
8
Rugby Ground
L Twr
L Twr
L Twr
53
3
4
2
9
6
8
4
4
Barracks
6
4
Alamein
2
2
1
7
4
5
LB
8
6
Tennis Courts
6
9
L
U
M
S
D
E
N
C
L
O
S
E
L
U
M
S
D
E
N
C
L
O
S
E
1
6
5
1
3
6
1
3
3
1
0
P
o
n
d
El Sub Sta
6
FB
G
i
p
s
e
y
R
a
c
e
5
9
5
5
2
8
18.4m
Spring
1
6
(
D
r
a
i
n
)
1
1
5
0
5
4
3
5
3
9
Spring
Spring
Spring
Hills
Pick
Drain
D
r
a
in
D
r
a
in
C
o
t
t
a
g
e
House
Janus
M
A
I
N
S
T
R
E
E
T
Paddock
The
D
r
a
i
n
St Leonard's
Farm
Church
10.0m
House
D
r
a
i
n
Beech Cottage
T
r
e
e
Leylandii
Drain
1
B
e
e
c
h
Elm Tree Farm
2
9.4m
9.4m
Church
Pond
Pinfold
D
r
a
i
n
D
r
a
i
n
Pick Hills
Pond
D
r
a
in
Driffield
Construction
Compound
D
ra
in
D
r
a
i
n
Pond
21.9m
22.4m
Track
Drain
Pond
D
r
a
in
Southlands
T
r
a
c
k
D
e
f
1
.
2
2
m
R
H
W
a
r
d
B
d
y
Allotment
22.4m
Track
Gardens
D
r
a
i
n
D
rain
16.4m
D
ra
in
GP
L
a
y
-b
y
16.3m
D
rain
16.0m
Dra
in
Pumping Station
Old Gawdy Hall
B
E
V
E
R
L
E
Y
R
O
A
D
Gawdy Hall Plantation
FB
MS
GP
FB
Shelter
D
r
a
in
D
ra
in
Northfield
19.8m
17.4m
B
e
c
k
Drain
D
rain
D
r
a
i
n
17.2m
D
r
a
in
16.7m
A
1
6
4
T
ra
c
k
House
Pond
21.1m
Old Fox Covert Plantation
Pond
T
ra
c
k
Old Sunderlandwick
Pond
Keeper's
Whin Plantation
Pond
FB
FB
D
ra
in
Beastman's Cottage
Jubilee Wood
O
L
D
S
U
N
D
E
R
L
A
N
D
W
I
C
K
L
A
N
E
Track
E
T
L
D
r
a
in
15.1m
D
r
a
in
A
1
6
4
D
r
a
in
D
r
a
i
n
T
r
a
c
k
Long Slaper
Tank
T
ra
c
k
Pond
North Lodge
D
r
a
in
Pond
E
T
L
D
r
a
in
Foot Bridge
Pond
Issues
Bar Farm
16.7m
Woodyard Cottages
17.3m
D
r
a
i
n
LB
Weir
D
ra
in
Shepherds Cottage
D
r
a
in
Pond
Path (um)
Tank
Howe Hill
18.9m
D
ra
in
D
r
a
in
Stone
of Sunderlandwick
O
L
D
S
U
N
D
E
R
L
A
N
D
W
I
C
K
L
A
N
E
Sunderlandwick Hall
Club House
19.2m
E
T
L
Pond
T
r
a
c
k
T
r
a
c
k
21.0m
Medieval Village
Driffield Golf Course
The Dower House
D
r
a
i
n
D
ra
in
D
r
i
f
f
i
e
l
d
T
r
o
u
t
S
t
r
e
a
m
Foot Bridge
(site of)
29.4m
Beech Holme
Hutton
Sta
R
O
A
D
North Field
St Peter's Church
Courts
28.4m
JENKINSON LANE
Courts
23.4m
Hutton
Jubilee
El
Pond
Tennis
SP
Pond
12.6m
Farm
12.3m
PIP
ER
View
27.0m
Builder's Yard
19.5m
Rotsea Lane
Elm
GP
B
E
C
K
L
A
N
E
CHURCH LANE
Tree
MP.25
26.3m
Lodge
Low Green Farm
Jenkinson
T
C
B
M
ILL S
TR
E
E
T
H
O
U
S
E
House
Wr T
Tennis
ST PETERS CLOSE
ORCHARD LANE
Vicarage
H
O
W
L
L
A
N
E
Mill
Wolds
MP.75
Northfield
Beck
Gatehouse
Ppg Sta
Drain
GP
(disused)
Mill Street Farm
Path (um)
HUTTON BALK
Farm
MP 17
Wroxton
17.5m
M
A
N
O
R
Silo
Church
Sub
R
O
T
S
E
A
L
A
N
E
14.0m
LC
Windmill
(T
ra
c
k
)
C
H
U
R
C
H
S
T
R
E
E
T
Pond
MP.75
D
ra
in
D
ra
in
N
o
r
t
h
f
i
e
l
d
P
l
a
n
t
a
t
i
o
n
Drain
D
r
a
i
n
Drain
Spring
MP.5
D
ra
in
D
r
a
i
n
K
n
o
r
k
a
D
i
k
e
D
r
a
i
n
Slaper Leys
North Field
D
ra
in
D
ra
in
D
r
a
in
BE
VE
RLE
Y R
OA
D
D
r
a
in
Dra
in
D
r
a
in
FB
Slaperleys Plantation
Pond
D
r
a
i
n
FB
A
1
6
4
A 164
MP.5
E
T
L
D
rain
Track
Track
South
Lodge
Pa
th
(u
m)
G
R
E
E
N
L
A
N
E
Dra
in
MP 18
Track
D
ra
in
Pond
MP.25
Level Crossing
D
r
a
in
SL
(
T
r
a
c
k
)
D
r
a
i
n
T
ra
c
k
D
r
a
in
D
ra
in
A
1
6
4
D
r
a
i
n
N
o
rth
fie
ld
B
e
c
k
Drain
D
rain
9.7m
M
EG
GIS
ON
'S
T
UR
NP
IK
E
Pond
E
T
L
Skerne Bridge
D
rain
S
k
e
r
n
e
B
e
c
k
D
rain
Cranswick Common
10.7m
C
O
R
PSLAN
D
IN
G
R
O
AD
9.6m
11.9m
11.4m
9.7m
GP
N
o
r
t
h
f
i
e
l
d
B
e
c
k
Pavilion
Track
9.6m
10.5m
North Field
10.3m
Recreation Ground
D
r
a
in
9.3m
Drain
11.8m
K
n
o
r
k
a
D
ik
e
Drain
D
ra
in
Spring
T
r
a
c
k
Lagoon
10.0m
D
ra
in
E
T
L
Rickle Pits
D
r
a
i
n
D
r
a
in
Drain
Track
Drain
D
ra
in
Track
D
ra
in
D
ra
in
Winds
D
ra
in
Thornset
Skerne Nook
T
r
a
c
k
11.9m
D
r
a
i
n
Four
D
r
a
i
n
E
T
L
D
r
a
i
n
T
r
a
c
k
D
r
a
i
n
Field House Farm
D
ra
in
13.6m
D
r
a
i
n
D
r
a
i
n
13.6m
10.2m
14.5m
S
k
e
rn
e
B
e
c
k
E
T
L
Dra
in
Pond
Drain
Drain
9.3m
Track
Drain
Drain
Drain
Drain
T
ra
c
k
Spring
Hills
Pond
11.9m
Track
Pick
11.4m
Drain
10.4m
Drain
D
ra
in
Pond
DRIFFIELD
D
r
a
in
(PH)
Farm
Pond
N
e
w
h
a
v
e
n
10.1m
C
o
t
t
a
g
e
N
ic
h
o
ls
o
n
s
9.7m
Yew Tree
Bank
B
A
C
K
S
T
R
E
E
T
Jacani
M
A
IN
S
T
R
E
E
T
The Glen
Cottage
The
Track
Well
Pond
D
r
a
in
C
e
d
a
r
d
a
l
e
V
i
e
w
St Leonard's
Farm
House
Church
F
a
r
m
W
e
s
t
The
S
p
r
in
g
s
id
e
Dra
in
L
i
l
l
y
LB
FB
The
H
i
p
D
ra
in
Southlands
T
h
r
e
e
W
a
y
s
Pond
10.0m
D
r
a
i
n
Beech Cottage
Conyers House
T
r
e
e
Lodge
Eagle Inn
Leylandii
Drain
School
Londesborough
Pond
Cottage
ROAD
B
e
e
c
h
Elm Tree Farm
GP
Ingram
G
a
r
t
h
9.4m
TCB
W
e
ll
H
o
u
se
10.6m
N
u
t
s
h
e
l
l
Beeches
9.9m
D
r
a
i
n
9.4m
10.4m
West End
Holly
Skerne
Church
Pond
Pp
Skerne
T
h
e
W
e
s
t
E
n
d
10.5m
Pinfold
D
r
a
i
n
Grange
D
ra
in
Iv
y
H
o
u
s
e
H
o
u
s
e
D
r
a
i
n
W
e
l
l
s
p
r
i
n
g
s
D
r
a
i
n
D
r
a
i
n
E
T
L
D
r
a
i
n
18.7m
Highgate Hall
21.8m
Drain
D
ra
in
D
r
a
i
n
23.2m
Highfield Farm
S
o
u
th
b
u
r
n
B
e
c
k
23.3m
Pond
Highgate Wood
Inkerman
Pond
E
a
s
tb
u
rn
B
e
c
k
20.6m
Plantation
Driffield
E
T
L
D
ra
in
T
ro
u
t S
tr
e
a
m
21.7m
W
e
lls
p
r
in
g
s
D
r
a
in
T
r
a
c
k
D
r
a
in
24.2m
Pond
Pond
Pond
D
ra
in
D
r
a
in
A
6
1
4
D
ra
in
26.3m
D
r
i
f
f
i
e
l
d
T
r
o
u
t
S
t
r
e
a
m
Track
E
T
L
D
i
s
m
a
n
t
l
e
d
R
a
i
l
w
a
y
Alma Plantation
Pond
Pond
Weir
Track
L
a
y
-b
y
Foot Bridge
Drain
PIN
FO
LD
CLO
SE
Pond
FB
FB
FB
Pond
Pond
Pond
Pond
Pond
Pond
T
ra
ck
T
r
a
c
k
FB
FB
FB
T
r
a
c
k
Track
Rose Cottage
Foxdene
Cottage
Winhill
Pond
F
B
Track
FB
The
School
Old
TH
E O
RC
HA
RD
S
E
T
L
C
O
U
R
T
Wansford
Cottage
Brigham
Cottage
Watton
Cottage
Beswick
Cottage
Mulberry
Cottage
Whin
Lodge
House
Southfield
L Twr
L Twr
Pond
Pond
L Twr
Pond
L Twr
Pond
L Twr
L Twr
L Twr
L Twr
S
o
u
th
w
o
o
d
M
e
w
s
Playground
C
S
1.14m
R
H
D
e
f
C
D
C
D
D
e
f
1.1
4m
R
H
1
.2
2
m
R
H
D
e
f
C
S
C
D
C
S
C
S
S
D
1
.
2
2
m
R
H
C
D
1
.
1
4
m
R
H
S
D
C
S
W
a
rd
B
d
y
W
a
r
d
B
d
y
W
a
r
d
B
d
y
W
a
r
d
B
d
y
Sluice
S
k
e
r
n
e
B
e
c
k
D
r
a
in
Pond
Pond
D
r
a
i
n
Binnings Grass
D
r
a
in
D
r
a
i
n
Dra
in
D
r
a
in
D
r
a
i
n
Pick Hills
Pond
Pond
Pond
Cleaves Farm
8.8m
E
T
L
8.3m
9.1m
9.2m
D
ra
in
8.6m
D
r
a
in
Pond
Pond
T
ra
c
k
Pond
Green Acre Lodge
FB
C
S
P
o
n
d
Track
P
o
n
d
s
FB
M
a
i
n
D
r
a
i
n
P
a
th
(
u
m
)
Bridge
Sluice
Wansford
FB
D
r
a
in
(disused)
P
o
n
d
s
10.5m
Sluices
MP
Trout Farm
Drain
Golden Hill
D
ra
in
D
r
a
in
D
r
a
in
MP
9.9m
Sluice
FB
8.8m
FB
Whinhill
FB
FB
Foot
FB
Overflow
D
r
i
f
f
i
e
l
d
C
a
n
a
l
Lock
River H
ull or W
est B
eck
E
T
L
FB
FB
L
a
y
-
b
y
FB
FB
Ponds
D
e
f
1
.
8
3
m
R
H
D
ra
in
Pond
Pond
Spring
FB
FB
P
a
t
h
(
u
m
)
FB
Pond
Trout Lake
Kelleythorpe
AUCHIN
LECK C
LOSE
KELLYTHORPE ROUNDABOUT
Track
17.0m
Pond
Spring
17.4m
L Twr
FB
LB
Pumping Station
MONTGOMERY SQUARE
M
O
N
TG
O
M
E
R
Y
S
Q
U
A
R
E
Gate Box
El Sub Sta
LB
A
6
14
G
O
TT C
LO
SE
Pond
Kelleythorpe
Pond
A
1
6
4
A
6
1
4
Pond
M
O
N
TG
O
M
ER
Y SQ
U
AR
E
Mallard House
Spring
FB
Cottage
Ponds
L Twr
G
O
T
T
C
L
O
S
E
Rugby Ground
L Twr
L Twr
19.1m
L Twr
L Twr
WB
El
25.4m
Barracks
Alamein
T
r
a
c
k
Store
Store
T
r
a
c
k
LB
Store
Store
Tennis Courts
El Sub Sta
Sta
R
A
M
S
D
E
N
C
L
O
S
E
LU
M
S
D
E
N
C
LO
S
E
Sub
LU
M
S
D
E
N
C
LO
S
E
El
El
P
o
n
d
El Sub Sta
20.3m
R
A
M
S
D
E
N
C
L
O
S
E
Sub Sta
A
U
C
H
IN
L
E
C
K
C
L
O
S
E
FB
G
ip
s
e
y
R
a
c
e
A
6
1
4
A
U
C
H
IN
L
E
C
K
C
L
O
S
E
18.4m
Spring
Springs
(
D
r
a
in
)
TCB
Sub Sta
Play Area
LB
Spring
Spring
Sheet 9 of 11
Figure 3.9
National Grid Carbon Limited
31 Homer Road
Solihull
West Midlands
B91 3LT
Co-financed by the European Union's
European Energy Programme for Recovery.
SCHEME LAYOUT
Title
Sheet
Date
Scale
30th April 2014
PINs
PIN's Reference EN070001
Not to Scale
Fig.No.
YORKSHIRE AND HUMBER CCS
CROSS COUNTRY PIPELINE
Background Mapping reproduced from Ordnance Survey Data, with the permission of the
Controller of Her Majesty's Stationery Office. © Crown Copyright & Database Rights(2014).
National Grid Carbon Ltd. Licence - 100055005
Temporary Construction Area - AGI
Above Ground Installations
Temporary Construction Area- Pipeline
Flexible Drainage Area
Order Limits
Limit of Deviation
LEGEND
Pipeline Centreline
Temporary Construction Compound
Skerne Block Valve
Temporary Construction Area
Inset : Skerne Block Valve
Inset : Driffield Barracks Temporary
Construction Compound
8.8m
8.3m
D
ra
in
Pond
Bridge
Pa
th
(u
m)
FB
6.3m
Weir
Thornham Farm
D
r
a
i
n
Overflow
FB
Pond
Trout Farm
E
T
L
FB
(disused)
7.1m
o
r
Snake Holm
D
r
i
f
f
i
e
l
d
C
a
n
a
l
P
o
n
d
s
Snakeholm Lock
Drain
Sluice
B
a
n
k
5.2m
W
e
s
t
D
r
a
i
n
M
a
i
n
D
r
a
i
n
5.6m
7.0m
H
u
ll
R
iver
Snakeholm
D
r
a
i
n
D
r
i
f
f
i
e
l
d
C
a
n
a
l
D
r
a
i
n
4.7m
5.2m
D
r
a
i
n
D
r
a
i
n
5.8m
5.4m
Hastham
D
r
a
i
n
N
a
f
f
e
r
t
o
n
D
r
a
i
n
Sluice
D
r
a
in
Silos
D
r
a
i
n
The Poplars
D
r
a
i
n
The Grange
D
r
a
i
n
(
D
r
a
i
n
)
P
a
t
h
(
u
m
)
Navigation Drain Bridge
T
r
a
c
k
N
a
f
f
e
r
t
o
n
H
i
g
h
l
a
n
d
S
t
r
e
a
m
D
r
a
i
n
B 1249
4.8m
D
r
a
in
Drain
T
k
D
r
a
in
Foston Carrs
D
r
a
in
D
r
a
in
D
r
a
i
n
T
r
a
c
k
Pond
Nafferton
Carr Hill
D
r
a
in
F
o
s
to
n
B
e
c
k
D
r
a
in
Dra
in
Cruckley
Carr House Farm
Carrs
C
r
e
y
k
e
D
ik
e
N
a
f
f
e
r
t
o
n
D
r
a
i
n
D
r
a
i
n
Turf Carr
W
h
i
t
e
D
i
k
e
LB
Orchard Cottage
Hill
T
ra
c
k
Glory
Fallowfield House
Ch
estn
ut
GP
Drain
Morning
F
o
s
t
o
n
B
e
c
k
Fair
Yew Tree Cottage
Westfield
House
9.9m
The Old Post Office
Neth
erg
arth
Farm
9.0m
View
Craven Cottage
T
r
a
c
k
Farm
Cottages
T
r
a
c
k
Cottage
Drain
Pond
West Field
Cottage
Eastfield Lodge
Wr T
Pond
Danby Hill
Village
Valetta
Pond
Wold
D
rain
17.3m
Nurseries
Pond
Farm
Longacre
East Field
T
r
a
c
k
TCB
Foston Carrs
Pond
Church
Greens
Louvain
Pond
12.2m
Cross Keys
Mole House
Wold Rise
Danby
SH
EEPD
IK
E L
AN
E
The Cottage
Pond
Marton Rise
FB
FB
FB
FB
FB
Pond
FB
T
r
a
c
k
T
ra
c
k
FB
FB
FB
FB
FB
FB
Pond
Tra
ck
Pond
Pond
D
e
f
1
.
5
2
m
R
H
D
e
f
S
C
D
C
D
S
D
D
e
f
1
.
5
2
m
R
H
C
D
1
.
5
2
m
R
H
S
D
1
.
8
3
m
R
H
1
.
5
2
m
R
H
D
r
a
in
Golden Hill
D
r
a
in
FB
8.8m
FB
FB
D
ra
in
12.4m
D
r
a
in
Spittle
Fields
Pond
D
r
a
in
FB
B
1
2
4
9
The
Spring
Pond
R
i
v
e
r
Sluice
The Old Vicarage
Council
P
a
t
h
(
u
m
)
7.0m
D
r
a
in
School House
Melvaig
M
a
i
n
D
r
a
i
n
Lake
V
i
e
w
Lych
7.8m
Mill Croft
D
r
iffie
ld
C
a
n
a
l
W
est B
eck
7.0m
D
ra
in
Finishing Post
Rose Cottage
White House
Orchard House
Green
Gables
Springrise
D
r
a
in
Wansford Bridge
7.1m
Chelidon
D
r
a
i
n
D
r
a
in
Cottage
Trout Inn Farm
Hall
Water
Fern
7.2m
FB
7.0m
Spring
The
7.9m
N
A
F
F
E
R
T
O
N
R
O
A
D
Dra
in
Wansford Lock
Croft Garth
6.7m
FB
Drain
St Mary's Church
D
r
a
in
Houses
Gate
Council
D
r
a
i
n
The Manor
Thyme Cottage
FB
House
M
a
n
o
r F
a
rm
Willow Cottage
Trout Inn
Rowan
Spring
Rafalet
FB
Drain
7.6m
Manor Lodge
8.6m
7.6m
Gean House
N
a
f
f
e
r
t
o
n
B
e
c
k
The Old
D
rain
TCB
R
iver H
ull or
Wansford
CARR LANE
The Bungalow
GP
Spring
Nafferton Carrs
Drain
View
Cross
S
h
e
lte
r
Mill
D
r
a
i
n
7.4m
(PH)
D
r
a
in
THE SQUARE
Houses
The
P
a
th
(
u
m
)
Two Hoots
D
rain
W
a
n
s
fo
r
d
L
a
n
d
in
g
7.4m
7.4m
Farm
Mill Farm
Tythe Farm
B
1
2
4
9
Atlasta House
Highfield
Pleasant Wood
Spring
N
a
f
f
e
r
t
o
n
D
r
a
in
Copperfield
D
r
a
in
Spittle Fields
9.7m
GP
9.9m
C
A
R
R
L
A
N
E
8.4m
D
r
a
in
Pond
D
ra
in
D
ra
in
D
r
a
in
W
A
N
S
F
O
R
D
R
O
A
D
7.5m
D
r
a
i
n
D
r
a
in
Potters' Lodge
D
ra
in
Nafferton Carrs
8.7m
D
r
a
i
n
T
ra
c
k
B
e
c
k
10.7m
Pond
FB
10.8m
D
ra
in
Silos
N
a
f
f
e
r
t
o
n
H
i
g
h
l
a
n
d
S
t
r
e
a
m
D
r
a
i
n
CARR LANE
Drain
D
r
a
i
n
Drain
Drain
D
ra
in
Drain
D
ra
in
D
ra
in
D
r
a
i
n
W
h
ite
D
ik
e
5.1m
C
A
R
R
L
A
N
E
D
ra
in
6.0m
D
r
a
in
(
D
r
a
i
n
)
Whin Hill
5.3m
Cattle Grid
The Cottage
Dra
in
4.8m
5.6m
Nafferton Carrs
6.8m
Sp
rin
g
D
r
a
i
n
D
ra
in
D
r
a
in
Nafferton Carrs
Tanks
The Bungalows
D
r
a
i
n
Drain
H
O
R
D
S
L
A
N
E
D
r
a
in
6.0m
C
A
R
R
L
A
N
E
6.5m
D
ra
in
Guide
6.8m
D
r
a
in
5.5m
5.7m
W
h
ite
D
ik
e
N
a
f
f
e
r
t
o
n
H
i
g
h
l
a
n
d
S
t
r
e
a
m
7.8m
D
ra
in
5.6m
(
D
r
a
i
n
)
D
r
a
in
D
r
a
i
n
Post
D
ra
in
6.0m
D
r
a
in
Carr House
D
ra
in
Poultry Houses
D
ra
in
Drain
D
r
a
in
N
a
f
f
e
r
t
o
n
D
r
a
i
n
5.7m
South
T
rack
D
r
a
i
n
Drain
Drain
Cattleholmes
North Cattleholmes
Drain
Foston Carrs
D
ra
in
FB
Well
D
ra
in
Foot Bridge
Track
Dra
in
F
o
s
t
o
n
B
e
c
k
Drain
W
h
it
e
D
ik
e
Aqueduct
Cattle Grid
FB
D
r
a
in
T
r
a
c
k
Dra
in
K
e
l
k
B
e
c
k
Drain
D
ra
in
D
ra
in
D
ra
in
Pond
D
ra
in
Dra
in
D
r
a
in
Dra
in
Kelk Lynesykes
Pond
D
ra
in
D
r
a
i
n
Drain
Little Covert
T
k
Drain
D
ra
in
T
ra
c
k
Drain
K
elk B
eck
Turkers
D
r
a
in
D
ra
in
D
r
a
in
D
r
a
in
West Field
Over Hills
11.3m
Weir
B
e
c
k
D
r
a
i
n
K
e
l
k
Pond
8.1m
West Field
D
ra
in
D
ra
in
T
ra
c
k
T
r
a
c
k
Markham Dales
D
ra
in
D
ra
in
Pond
West Field
L
Y
N
E
S
Y
K
E
S
R
O
A
D
(tra
c
k
)
D
ra
in
14.1m
T
k
F
O
L
L
Y
B
A
N
K
Dra
in
13.9m
(
T
r
a
c
k
)
K
e
l
k
B
e
c
k
Dra
in
14.7m
New Cottage
Dovedale
South
Lodge
Cattle grid
FB
Waste Transfer Station
LB
Waste Transfer Station
M
a
n
o
r F
a
rm
C
H
A
P
E
L
L
A
N
E
Park House
Markham Dale
Fieldview
FB
Pond
Gate
House
Old Chapel
The Gables
1.5
2m
R
H
1
.
5
2
m
R
H
S
D
1
.8
3
m
R
H
1.52m R
H
S
D
1
.8
3
m
R
H
1
.5
2
m
R
H
1
.
5
2
m
R
H
1
.5
2
m
R
H
C
S
S
D
D
e
f
1
.
5
2
m
R
H
S
D
1
.
8
3
m
F
F
D
e
f
SD
CS
S
D
Tk H
Ward Bdy
C
S
1.83m
C
D
C
S
S
D
1
.5
2
m
R
H
C
S
R
H
C
D
C
S
12.3m
Sheepfold
L
O
N
G
L
A
N
E
D
r
a
in
GP
Northfield
Pond
GP
16.9m
13.4m
10.4m
O
L
D
H
O
W
E
L
A
N
E
13.3m
D
r
a
i
n
P
o
n
d
8.7m
15.0m
H
a
l
l
Pond
15.9m
Pond
D
r
a
in
14.6m
Rose
Pond
C
o
u
n
c
i
l
H
o
u
s
e
s
Cottage
Pond
Gembling Lane End
D
r
a
in
D
r
a
i
n
Pond
Farm Cottages
F
a
r
t
h
in
g
s
Tanks
Green Close
7.7m
LB
Ashlea
Pond
9.6m
Diamond
Cottages
Houses
Hill Farm
Pond
D
ra
in
10.9m
Tanks
Sheepfold
D
r
a
i
n
Pond
Main Street
Wold View
Poultry Houses
South End Farm
The Cottage
D
ra
in
Field House
Tanks
11.4m
Farm
Farm House
Pond
Gembling Green
Southend
Gembling
D
r
a
i
n
The Cottage
D
r
a
i
n
Southfield
Cottages
Pond
M
A
I
N
S
T
R
E
E
T
G
E
M
B
L
IN
G
L
A
N
E
Pond
Wr T
East Field
Centre
13.4m
T
r
a
c
k
Great Kelk
Ponds View
Calm Cottage
Council Houses
Council
7.5m
Blacksmiths
TCB
House
13.1m
Southfield Farm
D
ra
in
Turkey Ville
12.7m
9.6m
Brylees
F
o
r
w
a
r
d
H
ill
P
la
n
t
a
t
io
n
Methodist Church
D
ra
in
Drumlinn
L
Y
N
E
S
Y
K
E
S
R
O
A
D
(
T
r
a
c
k
)
13.5m
The Chestnut Horse
Pond
Orchard Farm
East Field
Great Kelk
D
r
a
i
n
11.6m
T
r
a
c
k
Four Seasons
13.8m
GP
13.1m
Keepers Cottage
LB
West Field
Centre House
D
r
a
in
D
ra
in
East Garth
Pond
D
ra
in
Hall
Soller
13.2m
M
A
I
N
S
T
R
E
E
T
T
r
a
c
k
Manor Farm Cottage
Low Farm
Silo
(PH)
Manor Farm
Breezy Cottage
Track
B
a
r
m
s
t
o
n
M
a
i
n
D
r
a
i
n
8.4m
Gembling House
Pond
D
r
a
in
9.4m
10.9m
D
ra
in
D
r
a
in
Beck Hill
Pond
Pond
Pond
Cattle Grid
D
r
a
in
Pond
9.0m
Cattle Grid
D
r
a
i
n
Pond
O
U
T
G
A
T
E
S
Pond
Pond
Pond
O
U
T
G
A
T
E
S
Pond
D
ra
in
Pond
7.3m
Nutholm
es D
ike
Manor House
Pond
C
O
C
K
E
R
E
L
L
L
A
N
E
Pond
Manor House Cottage
D
r
a
i
n
D
rain
D
r
a
in
7.6m
8.2m
D
r
a
in
Ellison Hill
Southlands
East Field
T
ra
c
k
D
r
a
in
Park House
Barf Hill
N
u
t
h
o
l
m
e
s
D
i
k
e
New Loves
Pond
Pond
Pond
Pond
Sqirrel Lodge
Silos
T
r
a
c
k
M
A
I
N
S
T
R
E
E
T
Primary School
Gembling
D
e
f
Def
1.5
2m
R
H
1.52m RH
Def
1.52m RH
1
.5
2
m
R
H
C
D
CD
Sheet 10 of 11
Figure 3.10
National Grid Carbon Limited
31 Homer Road
Solihull
West Midlands
B91 3LT
Co-financed by the European Union's
European Energy Programme for Recovery.
SCHEME LAYOUT
Title
Sheet
Date
Scale
30th April 2014
PINs
PIN's Reference EN070001
Not to Scale
Fig.No.
YORKSHIRE AND HUMBER CCS
CROSS COUNTRY PIPELINE
Background Mapping reproduced from Ordnance Survey Data, with the permission of the
Controller of Her Majesty's Stationery Office. © Crown Copyright & Database Rights(2014).
National Grid Carbon Ltd. Licence - 100055005
Temporary Construction Area - AGI
Above Ground Installations
Temporary Construction Area- Pipeline
Flexible Drainage Area
Order Limits
Limit of Deviation
LEGEND
Pipeline Centreline
Temporary Construction Compound
Temporary Construction Area 6
Temporary Construction Area 7
No construction works to be undertaken
between the River Hull and the Driffield
Canal. Order Limit allows for access and
installation of a pressure valve.
G
r
a
n
s
m
o
o
r
D
r
a
in
D
r
a
in
M
O
O
R
L
A
N
E
Track
D
r
a
i
n
Track
Southlands
East Field
D
r
a
i
n
G
r
a
n
s
m
o
o
r
D
r
a
in
Barf Hill
8.2m
WB
7.8m
Barfhill Bridge
KELK L
ANE
Gransmoor Low House
G
RANSM
O
O
R L
ANE
Barf
Pond
D
r
a
i
n
7.2m
(disused)
D
r
a
in
G
r
a
n
s
m
o
o
r
D
r
a
i
n
Gransmoor Quarry
Thornham Hill
Pond
Track
Sleight Ings
9.0m
D
ra
in
D
ra
in
D
r
a
i
n
Track
D
rain
9.9m
D
r
a
i
n
Hill
Pit
9.6m
D
r
a
in
7.6m
D
r
a
i
n
Gravel Pit
Gransmoor Wood
Harpham Moor
D
ra
in
Turtle Hill
8.4m
Track
D
r
a
in
11.0m
Wold View
D
r
a
i
n
D
r
a
in
Sand and
11.0m
Track
Burton Agnes Moor
Silos
9.6m
Tra
ck
Danes Graves Wood
11.2m
Tithe
D
r
a
i
n
Plantation
Tra
ck
D
r
a
i
n
Lodge
10.6m
LB
8.7m
T
C
B
D
r
a
in
7.2m
8.7m
7.3m
Manor
M
A
IN
R
O
A
D
GP
7.2m
C
o
t
t
a
g
e
s
View
Gransmoor
T
r
a
c
k
Old Garths
T
ra
ck
Wolds
Foremans House
The Spinney
8.4m
Fourth Farm
Pond
F
o
u
r
t
h
F
a
r
m
D
r
a
in
D
r
a
i
n
D
r
a
i
n
Dra
in
Cottage
WB
Tank
Rose
Pond
D
r
a
in
Track
Manor
Lilac
Cottage
7.7m
Farm
D
ra
in
D
ra
in
Drain
D
r
a
i
n
D
r
a
i
n
D
r
a
in
D
r
a
i
n
D
r
a
in
White Lodge
Woodside Farm
Isle of Man Wood
Pond
Bridge
5.1m
9.7m
GRANSMOOR
Lodge Gates
Gransmoor
Pond
ROAD
Gransmoor
D
ra
in
Gransmoor
10.6m
FB
D
ra
in
T
r
a
c
k
Lodge
11.8m
Silk Holms
D
ra
in
Stone Hills
Hill Farm
Caravan
Park
B
u
r
t
o
n
D
r
a
i
n
Carr Hill
D
r
a
i
n
Lagoon
D
r
a
i
n
D
r
a
in
D
rain
D
ra
in
D
r
a
in
Avalon
Gransmoor
T
r
a
c
k
G
r
a
n
s
m
o
o
r
D
r
a
i
n
Stone Hills
6.7m
D
r
a
i
n
D
r
a
in
Hastem Hills
D
r
a
i
n
5.6m
S
to
n
e
h
ills
D
ra
in
B
u
r
t
o
n
D
r
a
i
n
9.5m
9.6m
Wharram Hill
G
R
A
N
S
M
O
O
R
R
O
A
D
B
a
rm
s
to
n
M
a
in
D
ra
in
Tank
9.8m
T
a
n
k
Tank
Works
G
ra
n
s
m
o
o
r D
ra
in
Red Roofs
10.2m
Silk Holmes
Track
Dra
in
Pond
B
u
r
t
o
n
D
r
a
i
n
Pipe Line
Barmston Fox Covert
Tanks
Warrens
Stone Hills
G
r
a
n
s
m
o
o
r
D
r
a
i
n
Spring Hill
D
r
a
in
D
r
a
i
n
High Stonehills
Plump Hill
D
r
a
i
n
8.7m
East Hill
14.2m
10.6m
14.3m
7.7m
Pond
Stone Hills
Gravel
9.9m
Pit
10.2m
Searchlight Cottage
Pond
12.0m
Spring Hill
Quarry Bungalow
Pond
Treetops
T
r
a
c
k
FB
FB
FB
Pond
Pond
Pond
Pond
Pond
Awali
Corner
Cottage
Cottage
Monument Farm
War Memorial
C
D
CD
1
.
5
2
m
R
H
1.52m
R
H
D
e
f
R
H
1
.5
2
m
R
H
D
ef
D
e
f
1
.
5
2
m
T
k
H
D
e
f
1
.
5
2
m
T
k
H
Def
C
D
C
D
C
D
C
D
C
D
C
D
1.68m
R
H
Carr Hill
Track
D
r
a
i
n
Demming
Track
Low Stonehills
Sheep Dip
The Earl's Dike
Pond
CG
Hill
Stone Hills
Grid
C
a
r
r
D
i
k
e
Cattle
Pond
Drain
9.2m
Water
7.5m
T
r
a
c
k
Drain
6.9m
A
1
6
5
Brickhill Closes
6.8m
Stone Hills
Dra
in
B
R
ID
L
IN
G
T
O
N
R
O
A
D
Bengy Elms
D
r
a
in
D
rain
8.8m
Marr Plantation
Filling Station
D
rain
Pond
Drain
10.6m
D
ra
in
Low
Quintin Garth
9.3m
A 165
9.5m
B
R
ID
L
IN
G
T
O
N
R
O
A
D
D
r
a
in
Stone Hills
Conygarth Hill
T
r
a
c
k
9.9m
Cattle Grid
D
ra
in
11.7m
Stonehills
Pool
9.1m
Cliff Farm
C
o
tt
a
g
e
Farm
10.1m
Caravan Park
G
r
e
y
s
t
o
n
e
s
Church
Pond
9.4m
P
a
n
tile
s
SOUTHFIELD
T
C
B
HA
MILT
ON
H
ILL R
OA
D
8.8m
HA
M
ILT
O
N H
ILL
T
ru
se
y
Pond
The Poplars
Low
Drain
D
rain
Barmston House
R
e
d
R
o
o
f
S
A
N
D
S
L
A
N
E
S
h
e
lt
e
r
Black Bull
House
C
o
t
t
a
g
e
Barmston
House
8.8m
Manor
Whitegates
C
H
A
P
E
L
L
A
N
E
9
.3
m
LANE(Track)
H
O
L
L
Y
C
R
O
F
T
B
R
O
O
M
F
I
E
L
D
W
A
Y
Drain
Pond
R
e
d
R
o
s
e
10.2m
10.3m
10.5m
Farm
Carrs
7.3m
B
la
c
k
s
m
it
h
's
Caravan Park
Red
(PH)
C
o
t
t
a
g
eD
o
v
e
Club
S
and
Yew Lodge
Barmston Beach
V
ie
w
HAMILTON HILL ROAD
Hamilton Hill
6.3m
T
ra
ck
9.5m
S
and
Hamiltonhill
Barm
ston S
ands
14.6m
D
r
a
i
n
12.7m
Mean H
igh W
ater
S
and
Sand
D
r
a
in
T
r
a
c
k
5.7m
24.8m
Drain
Watermill Grounds
Pond
Low Grounds
Farm
Bridlington Bay
B
a
rm
sto
n
S
a
n
d
s
S
and
P
a
th
(u
m
)
M
ean Low
W
ater
M
e
a
n
H
ig
h
W
a
te
r
Barm
ston S
ands
Sand
Mean Low
W
ater
Boulders
Track
S
a
n
d
S
h
in
g
le
S
h
in
g
le
S
a
n
d
a
n
d
S
h
in
g
le
Playground
Coastal Slope
Coastal Slope
LB
Hamilton Lodge
T
h
e
E
a
r
l
'
s
D
i
k
e
Dene
S
A
N
D
S
R
O
A
D
A
1
6
5
D
r
a
i
n
Conygarth Hill
7.9m
Cnoc na Gael
The Poplars
TCB
St Edmund's
T
ra
c
k
8.3m
Pond
Pump
12.0m
Fraisthorpe
Stone Hills
12.1m
The Lodge
Fraisthorpe
Depot
Fraisthorpe Bridge
5.7m
New Bridge
W
estw
ard
H
o
Earthworks
Chapel
D
r
a
i
n
Manor Farm
11.7m
Manor House Farm
Rose
House
Manor
Cottage
Clydesdale
LB
SANDS R
OAD
Mean H
igh W
ater
11.8m
T
h
e
E
a
r
l
'
s
D
i
k
e
(Track)
Barm
ston S
ands
S
and
Track
Watermill Grounds
4.9m
Track
Sa
nd
Dra
in
Sheep Walks
Fraisthorpe S
ands
Bridlington Bay
Fraisthorpe Sands
Sand
Barmston Sands
Mean Low
W
ater
The Hollies
The Old Smithy
Lodge Farm
K-Strat House
Honeysuckle
Cottage
9.5m
D
r
a
i
n
Conygarth Hill
T
r
a
c
k
S
A
N
D
S
R
O
A
D
D
r
a
i
n
7.9m
S
A
N
D
S
R
O
A
D
11.8m
(Tra
ck)
Sheet 11 of 11
Figure 3.11
National Grid Carbon Limited
31 Homer Road
Solihull
West Midlands
B91 3LT
Co-financed by the European Union's
European Energy Programme for Recovery.
SCHEME LAYOUT
Title
Sheet
Date
Scale
30th April 2014
PINs
PIN's Reference EN070001
Not to Scale
Fig.No.
YORKSHIRE AND HUMBER CCS
CROSS COUNTRY PIPELINE
Background Mapping reproduced from Ordnance Survey Data, with the permission of the
Controller of Her Majesty's Stationery Office. © Crown Copyright & Database Rights(2014).
National Grid Carbon Ltd. Licence - 100055005
Temporary Construction Area - AGI
Above Ground Installations
Temporary Construction Area- Pipeline
Flexible Drainage Area
Order Limits
Limit of Deviation
LEGEND
Pipeline Centreline
Temporary Construction Compound
Temporary Construction Area 8
Inset : Barmston Pumping Station