the succes story on r m

Upload: sienlangphioo

Post on 08-Aug-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/22/2019 The Succes Story on R M

    1/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 1 of 37

    SUCCESS STORY

    ON R, M & U WORKS OF UMIAM STAGE II HEPP,

    Meghalaya Power Generation Corporation Limited, UMSUMER

    Umiam Stage II Hydroelectric Power Plant is located at Umsumer in Meghalaya State of India,

    which is 36-km from Shillong, the capital of the State. The project site is at an elevation of 729-meters above

    mean sea level at around latitude 25.6 N, longitude 91.5E and is surrounded by hills. The maximum

    ambient temperature experienced has been 32.5C and the minimum temperature has been 5C outdoors and

    9C indoors, respectively.

    MeECL has been controlling following five hydro electric power plants in the Umiam-Umtru

    river basin.

    (a) Umiam Stage I Hydroelectric Power Plant, (4 x 9 MW) Commissioned in 1965

    (b) Umiam Stage II Hydroelectric Power Plant, (2 x 9 MW) Commissioned in 1970

    (c) Umiam Stage III Hydroelectric Power Plant, (2 x 30 MW) Commissioned in 1980

    (d) Umiam Stage IV Hydroelectric Power Plant, (2 x 30 MW) Commissioned in 1992

    (e) Umtru Hydroelectric Power Plant (4 x 2.8 MW), Commissioned in 1957 & 1970

    The total installed capacity of the system in the basin is 185.2 MW.

  • 8/22/2019 The Succes Story on R M

    2/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 2 of 37

    Fig. 1

    The Umiam Stage II Hydroelectric Power Plant was commissioned in 1970. Both the hydro

    turbines and generators of the power plant were manufactured by Toshiba Corporation, Japan. After

    operation of approximately 40 years, some problems have occurred on the generating units. Because of the

    importance of Umiam Stage II Hydroelectric Power Plant for coordinated economic operation of the above

    mentioned Power Stations of MeECL located at the downstream cannot be ignored in the context of draw

    down water from Umiam reservoir for running the downstream power stations. If this power station ceases to

    operate, all other stations will starve because of a cascade generation system. As such, Renovation of Umiam

    Stage II Hydroelectric Power Plant was necessitated.

    In the month of May 2003, Meghalaya State Electricity Board (MeSEB), now Meghalaya

    Energy Corporation Limited (MeECL) approached Japan Bank for International Cooperation (JBIC) for

    financial assistance for the complete R&M works of the Umiam Stage-II Power Plant. In response, the

    JBIC arranged the technical team TERI (The Energy & Resource Institute) to conduct a survey about themachine condition for R&M. Soon after, JBIC entrusted a consultant firm, TEPSCO (Tokyo Electric

    Power Services Company, Japan) which carried out a feasibility study under the team (SAPROF) Special

    Assistance for Project Formation) after which a report was submitted on September 2003. The report

    recommended for the renovation and modernization work on the generating Units for Umiam Stage-II

    Power Plant including 132 kV Switchyard Equipments and Generator Transformers.

    In 2005, Joint Venture of Tokyo Electric Power Services Company (TEPSCO) Limited and

    the Tokyo Electric Power Company (TEPCO) signed contract for the consultancy services for the RM&U

    works of Umiam Stage-II HEPP with MeECL.

    In 2009, after the bidding, MeECL contracted RM&U works for the project with the

    following company on December 4, 2009:-

    Toshiba Corporation, Japan (Toshiba)(for design & supply of hydro turbine, generator & control/protection system).

    Toshiba Plant System Corporation, India (TPSC)(for design & supply of BOP and installation & commissioning works).

    Toshiba Technical Services International Corporation, Japan (TTSI)(for dispatching installation & pre-commissioning technical supervisors).

    The work for Renovation and Modernisation started in May 2011 with the disassembling,

    replacement and repair works for the existing equipment/parts and continued until October 2011. Later,

    pre-commissioning test and commissioning tests were performed by the contractors. The project was

    finally commissioned on January 6, 2012 (25 monthly form the commencement date of the contract).

    The following were the major works carried out.

    1.1.Hydraulic Turbine1.1.1. General

  • 8/22/2019 The Succes Story on R M

    3/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 3 of 37

    Prior to R,M and U work the turbine in Umiam Stage II HEPP had a capability of unit output of

    10.5MW. However, the turbine could not output 10.5MW due to the limitation of the generator

    capacity of 10.6MVA with a power factor of 0.85. The project had the total capacity of 2 x 9MW

    only since the original commissioning. In this R, M & U Works, in order to enable the turbine to

    output 10.5MW, the generator is designed to have as capacity of 12MVA with a power factor of

    0.9.

    The major parts of turbine except the existing turbine shaft, guide vanes and embedded parts (draft

    tube liner, stay ring, bottom ring) are replaced with the new ones based on the latest design. The

    main inlet valves, governor system and the related mechanical equipment also are replaced with

    the new ones.

    1.1.2. Hydraulic Turbine1.1.2.1.Type and Rating

    (1) Number installed : Two (2)

    (2) Type of Turbine : Vertical Shaft Francis Type

    (3) Elevation

    a) Reservoir water level

    - Maximum : EL. 804.02 m (2,638 ft.)

    - Minimum : EL. 801.58 m (2,630 ft.)

    b) Tail water level

    - Maximum : EL. 725.08 m (2,379 ft.)

    - Minimum : EL. 722.34 m (2,370 ft.)

    c) Centerline of turbine distributer : EL. 722.16 m(4) Net Head

    - Maximum : 78.50 m

    - Design : 77.67 m

    - Minimum : 75.00 m

    (5) Turbine Output

    - at Maximum net head : 10,500 kW

    - at Design net head : 10,500 kW

    - at Minimum net head : 9,980 kW

    (6) Rated Turbine Discharge : 15.47 m3/s (per unit)

    (7) Rated Speed : 428.5 min-1

    1.1.3. Pressure Relief Valve (PRV)All reused parts of Pressure Relief Valve such as the valve body, cylinder, cylinder cover, valve,

    piston were repaired and/or machined in shop and the embedded part (lower body) were

    repaired at site. All other parts for PRV were replaced with the new ones and self-lubricated

    bearings were applied to all bearing portions for PRV.

    1.1.4. Governor System including Oil Pressure & Compressed Air Supply Systems(1) Type and Rating

  • 8/22/2019 The Succes Story on R M

    4/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 4 of 37

    a)Number of Governor : Two (2)b)Type of Governor : Digital PID electro-hydraulic type

    (2) System Description

    The existing governor actuators were replaced with the latest designed ones, and oil pumping

    sets and oil pressure tanks, air compressors, air tank, oil & air piping, electrical cables and their

    accessories were replaced with the new ones except the existing oil sump tanks. The existing

    governor regulators were removed. In the Contractors governor design, the governor regulator

    functions were accommodated in the unit control cubicle. The oil pressure supply system for

    each unit is commonly used for operation of the guide vane, PRV and MIV.

    The oil pumps and air compressors for the system are automatically controlled by the new

    Motor Control Center (MCC), which was installed on the Generator Floor.

    Compressed Air Supply System:

    The Compressed air supply system is commonly used for generator brake operation, governor

    system of both units.

    1.1.5. MIV and By-pass Valve

    (1) Type and Rating

    a) Number of MIV : Two (2)b) Type of MIV : Thru-flow typec) Nominal diameter : 1,700 mmd) Maximum flow : 15.47 m3/se) Operation of MIV :Oil pressure (2 servomotors for each MIV)

    (2) Description of MIV

    The existing MIVs were removed and the new MIVs were designed, manufactured by

    FOURESS ENGINEERING (INDIA) LIMITED. Each new MIV is operated by two (2) oil

    operated servomotors mounted on the top of MIV. The oil pressure of MIV servomotors is

    supplied from the oil pressure supply system commonly used for the governor & MIV.

    1.1.6. Cooling Water Supply System & Drainage/Dewatering System(1) System Description

    The existing equipment, parts, devices and piping (excluding embedded piping) for the

    cooling water supply system and drainage/dewatering system were removed and all new

    system were installed. Cooling water for the generating units is taken from the penstock and

    cooling water is filtered through the strainer mounted on the line between the penstock and

    water head tank and, after that, cooling water is filtered again through the strainer mounted

    on the line between the head tank. The automatic water strainers and their sand discharge

    valves are controlled by the new Motor Control Center (MCC) with detecting a differential

    pressure between the outlet and inlet of strainer and/or timer. The drainage pumps for the

  • 8/22/2019 The Succes Story on R M

    5/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 5 of 37

    drainage/dewatering system are controlled by the new Motor Control Center (MCC) with

    detecting the water level in the drainage pit.

    (2) Construction of Cooling Water Supply System

    a) Water head tank (existing one) : One (1)b) Automatic motor-operated water strainer

    - between the penstock and water head tank : Two (2)

    - between the water head tank and generating unit : Two (2)

    c) Shaft seal strainer : Two (2)d) Automatic motor-operated valve : Two (2)

    3) Construction of Drainage/dewatering Systema) Drainage pump (submergible type) : Two (2)b) Water level switch (float type) : One (1)

    1.1.7. Motor Control Center (MCC)The new Motor Control Center (MCC) is installed on the Generator floor. The MCC controls

    the following auxiliary equipment of the generating units.

    (1) Oil Pumps for Governor SystemTwo (2) oil pumps (one for normal use and other for stand-by) for each unit are installed on

    the turbine floor. The oil pumps are controlled by detecting oil pressures and oil levels in the

    oil pressure tank.

    (2) Generator Space HeatersThree (3) Generator Space Heaters were installed in the generator air housing and they arecontrolled by detecting temperature inside the generator air housing.

    (3) Air Compressors for Compressed Air Supply SystemTwo (2) oil pumps (one for normal use and other for stand-by) for each unit are installed on

    the turbine floor. The oil pumps are controlled by detecting oil pressures in the oil pressure

    tank.

    (4) Drainage Pumps for Drainage/Dewatering SystemTwo (2) submergible drainage pumps are installed in the drainage pit. The drainage pumps

    are controlled by detecting water levels in the drainage pit.

    (5) Automatic Motor-operated Water Strainers and Sand Discharge ValveTwo (2) automatic strainers (one for normal use and other for stand-by) is installed on the

    line between the penstock and water head tank and other two (2) automatic strainers (one for

    normal use and other for stand-by) are installed on the line between the water head tank and

    generating units. The automatic strainers are controlled by detecting a differential pressure

    between the inlet & outlet of strainer and/or timer. Each strainer is equipped with an

    automatic sand discharge valve and water after filtering in the strainer is discharged to the

    tailrace through the sand discharge valve.

    (6) Automatic Motor-operated Valves

  • 8/22/2019 The Succes Story on R M

    6/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 6 of 37

    Two (2) automatic valves (inlet from the penstock to water head tank and outlet from the

    water head tank to the generating units) are installed on the line of cooling water supply

    system. The automatic valves are opened before starting the generating unit and closed after

    stopping the generating unit.

    1.2.Generator1.2.1. General

    The existing generator in Umiam Stage II HEPP with capacity of 10.6MVA at a power factor

    of 0.85 (lagging) was upgraded to a capacity of 12MVA at power factor of 0.9 (lagging) so

    that turbine could deliver maximum output of 10.5MW in this R, M & U Works.

    The major parts of generator except the existing generator main shaft, rotor rim, stator frame,

    bearing brackets, and base block for stator, are replaced with the new ones based on the latest

    design. The air cooler, oil cooler, excitation system and the related mechanical and electrical

    equipment also are replaced with the new ones.

    1.2.2. Generator1.2.2.1.Type and Rating

    (1) Number installed : Two (2)

    (2) Type of generator : Vertical shaft, Francis Turbine driven, and

    alternating current synchronous generator

    (3) Rated output : 12.0 MVA

    (4) Rated power factor : 0.9 lagging

    (5) Rated frequency : 50 Hz(6) No. of phases : Three (3)

    (7) Rated voltage : 11.0 kV

    (8) Rated speed : 428.5 min-1

    (9) Direction of rotation : Clockwise viewed from top

    (10) Runaway speed : 780 min-1

    (12) Stator winding connection : Star (Y)

    (15) Maximum cooling water temperature : 25

    (16) The value of I22t capacity of the generator : not less than 20

    (17) Required flywheel effect : not less than 123 t-m2

    (18) Excitation system

    - Excitation ceiling voltage : 110 %- Ratio of ceiling voltage to rated excitation voltage : 211.8 %- Excitation system nominal response : 0.06 sec-1

    (19) Type and Cooling method

    - Type of generator : Suspended Type

    -Cooling method : By air

    1.3. Excitation System

  • 8/22/2019 The Succes Story on R M

    7/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 7 of 37

    1.3.1. Type and Rating(1) Applied standard : IEC

    (2) Ratings of excitation system

    a) Type of excitation system : Brushless excitation system

    b) Rated capacity : 69.5 kW

    c) Rated voltage : 151 V

    d) Rated speed of AC exciter and rotating rectifier : 428.5 min-1

    e) Rated frequency

    - Input and output of excitation transformer : 42.9 Hz

    - Output of AC exciter : 42.9 Hz

    (3) Parameters and performances of excitation system

    a) Ceiling voltage : 225 V

    b) Ratio of ceiling voltage to rated excitation voltage : 200 %

    c) Flashing current and duration period for excitation system : 6 A15 sec.

    d) Voltage setting range

    - for AVR setter (90R) : 80 % - 110% rated voltage

    - for Manual voltage setter (70E) : 30 % - 110% rated voltage

    e) Excitation system nominal response : less than 0.06 sec-1

    f) Excitation system voltage response time : less than 1.0 sec

    g) Excitation control accuracy : 2 %

    h) Maximum generator voltage rise at full load rejection : 30 % rated voltage

    i) Power frequency withstand voltage for 1 minute- Circuits electrically connected with generator rotor winding : 1500 V

    - Circuits not connected with generator rotor winding : 1500 V

    - Control and detection circuits : 1500 V

    (4) AC exciter

    a) Type : Three phase, rotating armature type

    b) Number of poles : 12

    c) Rating of AC exciter

    - Rated capacity : 74 kVA

    - Rated voltage : 114 V

    - Rated speed : 428.5 min-1

    - Rated frequency : 42.9Hz

    - Insulation class (armature and field winding) : Class F

    - Temperature rise (armature and field winding) : 80 K

    - Power frequency withstand voltage for 1 minute : 2 kV

    Existing DC exciter was completely replaced by brushless AC excitation system as shown in

    Fig. 2 Outline of AC Excitation System. In the drawing collector ring is for resistance

    measurement during site commissioning test.

  • 8/22/2019 The Succes Story on R M

    8/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 8 of 37

    Fig. 2 Outline of AC Excitation System

  • 8/22/2019 The Succes Story on R M

    9/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 9 of 37

    1.4. Main Transformer1.4.1. General

    The existing main transformers in Umiam Stage II HEPP were replaced by new main

    transformer with rating of 3-phase step-up oil immersed with external heat exchangers

    suitable for outdoor services in the climate conditions at site as given in Special Conditions

    of Contract, and ONAF rating , and ONAN rating when the transformer is operated with the

    power less than 80 % of the rated capacity.

    1.4.2. Main transformer1.4.2.1.Type and Rating

    (1) Number installed : Two (2)

    (2) Type of transformer : Three (3) phase, outdoor, two (2)

    winding, natural-air-cooled, step-up,

    oil-immersed-type, generator transformer

    (3) Ratings

    a) Operating duty : Continuous

    b) Rated capacity

    - High-voltage winding : 9600/12000 kVA

    (ONAN/ONAF)

    - Low voltage winding : 9600/12000 kVA

    (ONAN/ONAF)

    c) Rated frequency : 50 Hz

    d) Rated voltage- High-voltage winding : 132 kV

    - Low voltage winding : 11 kV

    f) Tapped winding capacity : 12,000 kVA

    i) Maximum temperature rise

    - Windings (Resistance method) : 55 K

    - Top oil (Thermometer) : 50 K

    j) Connection of windings

    - High voltage side : Grounded Y

    - Low voltage side : Delta

    - Phase displacement : YNd11

    (4) Temperature rises at rated operating conditions- Windings (average) : 55 K- Oil (top) : 50 K

    (5) Temperature at rated operating conditions- Thrust bearing : 70- Upper guide bearing : 70- Lower guide bearing : 70

  • 8/22/2019 The Succes Story on R M

    10/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 10 of 37

    1.4.2.2.Technical Data of Main Transformer(1) Applied standard : IS 2026

    (2) Type and cooling method

    - Type of main transformer : 3-phase oil immersed outdoor type

    - Cooling method of main transformer : ONAN/ONAF

    (3) Ratings

    a) Operating duty : Continuous

    b) Number of phases : 3

    c) Rated capacity

    - High voltage winding : 12,000 kVA

    - Low voltage winding : 12,000 kVA

    d) Rated frequency : 50 Hz

    e) Rated voltage

    - High voltage winding : 132 kV

    - Low voltage winding : 11 kV

    f) Connection and phase displacement : YNd11

    1.5. 11 KV Metal-enclosed Switchgear and Service Transformers1.5.1. General

    11kV Metal Enclosed Switchgears are composed of 11kV Generator incoming cubicle, 11kV

    Link cubicle, 11kV VCB cubicle, 11kV Station service transformer cubicle and NGR cubicle.

    The existing 11kV Metal Enclosed Switchgears and Service Transformers were replaced withnew ones. New 11kV Metal Enclosed Switchgears and Service Transformers were

    manufactured by C&S EFACEC MV INDIA PVT.LTD in India. The 11kV Metal Enclosed

    Switchgears were transported inland with all accessories including supporting structures,

    spares, and all other equipment making the 11kV system.

    1.6. Station Power Supply Facilities1.6.1. General

    Station Power Supply Facilities are composed of Battery, Battery Charger, AC & DC power

    supply boards. The existing Station Power Supply Facilities were replaced with new ones.

    Battery, Battery Charger, DC power supply board were manufactured by Statcon Power

    Controls Ltd. in India. AC power supply boards were manufactured by Larsen & Toubro

    Limited. The Station Power Supply Facilities were transported inland with all accessories

    including supporting structures, spares, and all other equipment making the Station Power

    Supply Facilities.

    1.7. Control and Protection Boards1.7.1. General

  • 8/22/2019 The Succes Story on R M

    11/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 11 of 37

    The existing generator-transformer boards were replaced with new designed Control and

    Protection boards. Control and Protection Boards are composed of two Unit Control Board,

    one 132kV Switchyard Control Board and Recording Board. The Control and Protection

    Boards are integrated type. Unit Control Board has sequence controller, automatic

    synchronizer and HMI (Human Machine Interface). Each unit can connect in parallel with

    power system automatically by using automatic synchronizer. The Control and Protection

    Boards were manufactured by Toshiba in Japan. The Control and Protection Boards were

    transported from Japan with all accessories including supporting structures, spares, and all

    other equipment making the Control and Protection Boards.

    1.7.2. Unit Control Boards(1) Components in board

    a) HMIb) Metersc) Status indicatorsd) Fault indicatorse) Control switchesf) Mimic busg) Test terminalsh) Protection relays for Turbine and Generator

    A compact list of the items replaced or repaired during the Renovation is given in Annexure I.

    andphotos showing before and after R&M is given in Annexure II.

    Pre-commissioning Tests.

    Prior to commissioning of the Units in January 2012, all tests as per contract

    were performed. Besides other tests, Generator Efficiency Test were performed on Unit #2

    and Turbine Index Tests for comparison/confirmation with CFD analysis were performed on

    both Unit #1 and Unit #2.

    Final Acceptance Tests

    All the tests for final acceptance as per contract were performed in for 10th

    December up to

    5th

    December 2012. The tests include the following:

    1. PRV operation check of Unit #1.2. Load Rejection Test of both Unit #1 and Unit #2.3. Output Test of both Unit #1 and Unit #2.4. Heat Run of both Unit #1 and Unit #2.

    The following excerpt from the IEEMAJournal Volume 3-No.9. May 2012, page 112

    During the Annual review meeting held in CEA during March-April 2012 with various utilities, 4 schemes

  • 8/22/2019 The Succes Story on R M

    12/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 12 of 37

    which were earlier scheduled to be completed during XI plan have been shifted to XII plan. However, R&M

    of one scheme namely Umiam Stage II (2X9 MW) of MeECL which was scheduled for XII plan, was

    completed in 2011- 12, Thus, during XII Plan a total of 43 hydro R&M schemes (5 in Central Sector and

    38 in State Sector) having an installed capacity of about 6663 MW at an estimated cost of about Rs. 4433

    Crs. which will accrue benefit of about 3773 MW through uprating, life extension and restoration are

    planned for implementation. One scheme of MeECL namely Umiam St. III (Kyrdemkulai) shall be taken up

    in XII plan and will accrue benefit of 66 MW (6 MW uprating & 60 MW-LE) during plan

    A comparison of Energy generated of Umiam Stage II with reference to Umiam Stage I,

    before and after RM&U of the station is given below:

    Generation of Stage I and Stage II in KWH for the last five years before RM&U of Stage II

    Year Stage I(a)

    Stage II(b)

    % Generation of Stage II w.r.t. Stage I(b/a)x100

    Average

    2006-2007 61642800 27660080 44.87%

    45.37%

    2007-2008 150633800 67267000 44.66%

    2008-2009 107800680 48667500 45.15%

    2009-2010 110320850 51176900 46.39%

    2010-2011 103803640 47519700 45.78%

    Generation of Stage I and Stage II in KWH After RM&U of Stage II

    MonthStage I

    (a)

    Stage II

    (b)

    Average % Generation of Stage II w.r.t. Stage I

    (b/a)x100

    Feb 2012

    toJan 2013

    99022800 48251300 49.57%

    As a result of the R,M&U works on the Umiam Stage-II HEPP, it is observed that the

    percentage generation of Umiam Stage-II with respect to Umiam Stage-I Power Station, shows an

    upliftment by about 4.20 % as compared to the generation before the R,M&U work.

  • 8/22/2019 The Succes Story on R M

    13/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 13 of 37

    ANNEXURE- I

    The outline of R, M & U Works done for Umiam Stage II HEPP is described in table below.

    Table 2.1-1 Works done for Equipment and Parts

    R: Replacement item with new one O: Overhauling and repairing item X: Removal

    Items Unit 1 Unit 2 Descriptions

    1. Mechanical Equipment

    (1) Turbine and Its Auxiliary

    a) Runner R R

    The runners were replaced with the newly designed

    ones made of 13Cr-high Ni stainless steel material

    based on CFD analysis.

    b) Spiral case & stay ring O OThe hydraulic surfaces of spiral case and stay ring were

    cleaned, repaired and painted.

    c) Guide vanes O O

    The hydraulic surfaces of guide vanes were cleaned

    and painted for both units. The spindles of guide vane

    were machined in shop for applying self-lubricated

    bearing.

    d) Head cover R R

    The head covers were replaced with the newly

    designed ones having self-lubricated bearing and

    separated construction from the bearing housing in

    consideration of ease of maintenance for the shaft seal

    and applying the new type (segment type) guide

    bearing.

    e) Bottom ring O O

    The guide vane bearing portions of bottom ring for

    both units were bored/machined at site for applying

    self-lubricated bearing.

    f) Facing plates and wearing rings R RThe facing plates and wearing rings on the head cover

    and bottom ring were replaced with the new ones.

    g)Guide vane servomotors and

    gate operating mechanismR R

    The guide vane servomotors were replaced with the

    new ones excluding the cylinders and cylinder covers.

    The gate operating mechanisms including guide ring

    were replaced with the newly designed ones having

    self-lubricated bushings.

    h)Guide bearing, cooler and

    bearing housingR R

    The guide bearing and the bearing housing were

    replaced with the newly designed ones (Guide bearing:

    segment type/Housing: separated construction from

    head cover).

    i) Shaft seal and sealing box R R

    The shaft seals were replaced with new designed one

    (Carbon seal type) and also the sealing boxes were

    replaced with the newly designed ones.

  • 8/22/2019 The Succes Story on R M

    14/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 14 of 37

    j)Upper draft tube and draft tube

    linerO O

    The air injection pipes were replaced with the new ones

    and the inner surfaces of upper draft tube liner were

    repaired and painted.

    k)Thru-flow type inlet valve and

    its servomotorR R

    MIVs with its servomotors were replaced with the

    newly designed thru-flow type MIV with servomotor.

    Each MIV has two (2) servomotors.

    l) By-pass valve R RThe by-pass valves were replaced with the newly

    designed ones.

    m) Pressure relief valve (PRV) O O

    The PRVs were overhauled. The existing parts for

    applying self-lubricated bushings were machined in

    shop and some parts were replaced with the new ones.

    The PRV liners were repaired and especially the outlets

    of liners were patched with steel liners.

    Items Unit 1 Unit 2 Descriptions

    n)

    Drain valves and pipes for

    spiral case, draft tube and

    penstock

    R RThe drain valves and pipes for spiral case, draft tube

    and penstock were replaced with the new ones.

    o)Instruments, devices, cables

    and pipingR R

    All existing instruments, device, cables and pipes

    except the embedded pipes were replaced with the new

    ones.

    (2) Governor and Turbine Control

    System

    a) Governor actuator R R The governor systems were replaced with the new type

    governor system with the latest technology, which is

    the digital PID electro-hydraulic type governor.

    The governor regulator functions were accommodated

    in the Main Control Boards.

    b) Governor regulator R R

    c) Turbine control panelR R

    d) Speed Signal Generator (SSG) R R

    (3) Oil Pressure Supply System

    a) Oil pump with motor R R The oil pumps with motors were replaced with the new

    ones and the oil pump motors are controlled by Motor

    Control Center (MCC). All oil pressure tanks with

    accessories, oil pipes and valves were replaced with the

    new ones.

    b)Oil pressure tank, oil piping and

    valvesR R

    (4) Air Compressed Supply System

    a) Air compressor with motor R

    Two (2) sets of air compressor with motor were

    replaced with the new ones and the motors are

    controlled by Motor Control Center (MCC).

    (5) Cooling Water Supply System

    a) Water head tank O The water head tank were cleaned and repaired.

  • 8/22/2019 The Succes Story on R M

    15/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 15 of 37

    b) Water piping and valves R R

    The exposed pipes and valves were replaced with the

    new ones. The strainers were replaced with a motor

    operated automatic strainer controlled by Motor

    Control Center (MCC). Four (4) sets of automatic

    strainers were supplied for the cooling water supply

    system. Two (2) strainers were installed on the line

    between the penstock and the water head tank and

    others were on the line between the water head tank

    and the generating units.

    c) Water flow relays R R

    The water flow relays were replaced with the new

    magnetic flow meters installed at drainage side of

    bearing coolers & generator air coolers

    (6) Dewatering & Drainage System

    a)Submersible water pump with

    motorR Two (2) submersible pumps were installed for

    dewatering and drainage and their operation is

    controlled automatically by Motor Control Center

    (MCC) through detecting the water level.

    b)Water level switches with

    accessoriesR

    c) Necessary piping and valves R

    (7) Auxiliary Machine Control

    a) Motor Control Center (MCC) R R Including auxiliary control

    b) Necessary wiring and cables R R

    (8) Water Depression System

    a)All devices, equipment, pipes

    and valvesX X

    All existing devices, equipment, pipes and valves for

    the system were removed.

    (9) Other Items for Mechanical

    Equipment

    a)Level monitoring devices

    for intake & tailrace water levelR R

    The float type level monitoring devices were installed

    on the intake and tailrace and all level data is

    transmitted to the powerhouse.

    b) Spare parts and special tools R

    R: Replacement item with new one O: Overhauling and repairing item X: Removal

    Items Unit 1 Unit 2 Descriptions

    2. Electrical Equipment(1) Generator and Its Auxiliary

    a) Stator core R R The stator core and the stator winding were replaced

    with new ones for both units. The existing stator frame

    was reused because it is fixed on the concrete

    foundation.

    b) Stator winding with accessories R R

    c)Stator winding main and neutral

    leadsR R

    d)Rotor winding and excitation

    leadsR R

    The following parts were replaced with new ones:

    a) Rotor winding and excitation leads for both units

    b) Rotor pole pieces with damper winding for both

    unitse)

    Rotor pole piece with damper

    windingR R

  • 8/22/2019 The Succes Story on R M

    16/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 16 of 37

    R: Replacement item with new one O: Overhauling and repairing item X: Removal

    Items Unit 1 Unit 2 Descriptions

    f)

    Brake ring & brake /jack

    system R R

    The brake ring was replaced with new one for both

    units.

    All the brakes and jacks were replaced with doublecylinder type brake/jack system that used as brake by

    compressed air injection and as jack by pressurized oil

    for both units.

    g) Upper bearing bracket O OThe upper bearing bracket was overhauled for both

    units.

    h) Thrust bearing pads R RThe thrust bearings were replaced with new ones for

    both units.

    i)Segment type upper guide

    bearing and oil cooler

    R R

    The guide bearings were replaced with segment type

    bearings and the oil coolers were also replaced with

    new one for both units.

    j) Lower bearing bracket O OThe lower bearing bracket was overhauled for both

    units.

    k)Segment type lower guide

    bearing and oil coolerR R

    The guide bearings were replaced with segment type

    bearings and the oil coolers were also replaced with

    new one for both units.

    l) Collector ring X XThe collector ring was removed because of application

    of brush-less type excitation system

    m) Brush and brush holder X XThe brush and brush holder were removed because of

    application of brush-less type excitation system

    n) Air coolers R RAll air coolers for both units were replaced with

    vertical flow type air coolers.

    o) Pipes and valves R R

    p) Instruments and relays R R

    q) Operation lamp R R

    r) Generator housing O O Painting

    s) Terminal boxes R R For instrument, control & alarm cables

    (2) Excitation System

    a) Brush-less type AC exciter R R The existing exciters were replaced with brush-less

    type excitation system for both units.b) Rotating rectifier R R

    c)Protection relays for brush-less

    exciterR R

    d)Automatic voltage regulator

    and excitation cubicleR R

    e)

    Epoxy resin molded self-cooled

    excitation transformer equipped

    with thermometer with alarm

    contacts and adjustable wheels

    R R

    (3) Main Control Boards

  • 8/22/2019 The Succes Story on R M

    17/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 17 of 37

    R: Replacement item with new one O: Overhauling and repairing item X: Removal

    Items Unit 1 Unit 2 Descriptions

    a) Main control board R R The generator-transformer panels for both units were

    replaced with new designed ones.

    New main control boards have sequence controller,

    automatic synchronizer and HMI (Human MachineInterface).

    b) Automatic control, recorder and

    protection relay boardsR R

    c) Supervisory control boards X XThe supervisory control panel was removed, because it

    was not used.

    d) 132kV control boards RThe 132kV control boards were replaced with new

    ones.

    e) Synchronizer & Synchroscope RThe synchronizer & synchro-scope were replaced with

    new ones.

    (4) 11kV Metal-Enclosed Cubicles

    a) 11kV Metal-enclosed cubicles

    with accessoriesR R

    The existing 11kV cubicles were replaced with new

    designed 11kV cubicle equipped with vacuum circuit

    breakers for generators.

    (5) Main Transformer

    a)Outdoor-use three phase ON

    transformer with accessoriesR R

    The main transformers were replaced with new

    designed ones.

    b) Terminal boxes R R For instrument, control & alarm cables

    (6) Station Transformer

    a)

    Epoxy resin molded self-cooled

    station transformer with

    accessories

    R R

    The transformers were replaced with new designed dry

    type or resin molded type ones and those were installed

    in the new 11kV cubicle.

    b)Vacuum circuit breaker for

    station service transformersR R

    The vacuum circuit breakers were installed on station

    service transformers circuit instead of existing

    isolators.

    (7) Station Service Low Voltage AC &

    DC Circuit Boards

    a)Station service low voltage AC

    Circuit BoardsR Common use

    b)Station service low voltage DC

    Circuit BoardsR Common use

    (8) Electrical Cable

    a) 11kV power cables R R

    b) Power cables for low voltage R R Including common cables

    c) Control cables R R Including common cables

    (9) Station Battery

    a) Station battery with accessories RThe station battery was replaced with new one.

    (Common use)

    b)Battery charger with

    accessories

    R

    The battery charger was replaced with new one and it

    was equipped with auto changeover function that DC

    supplies to emergency light at AC power failure.

  • 8/22/2019 The Succes Story on R M

    18/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 18 of 37

    R: Replacement item with new one O: Overhauling and repairing item X: Removal

    Items Unit 1 Unit 2 Descriptions

    (10) Other Items for Electrical

    Equipment

    a)

    All paints, sealing materials,

    bolts and nuts necessary for

    overhauling works

    R R Including common use

    b) Spare parts and special tools R Including common use

    Annexure II

  • 8/22/2019 The Succes Story on R M

    19/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 19 of 37

    After R&MDuring R&M

  • 8/22/2019 The Succes Story on R M

    20/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 20 of 37

    After R&MDuring R&M

    before after

  • 8/22/2019 The Succes Story on R M

    21/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 21 of 37

    before after

    before after

  • 8/22/2019 The Succes Story on R M

    22/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 22 of 37

    before after

    before after

  • 8/22/2019 The Succes Story on R M

    23/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 23 of 37

    before after

    before after

  • 8/22/2019 The Succes Story on R M

    24/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 24 of 37

    before after

    Digital typeMechanical type

    afterbefore

  • 8/22/2019 The Succes Story on R M

    25/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 25 of 37

    11KV, 12MVA

    after

    11KV,10.6 MVA

    before

    before after

  • 8/22/2019 The Succes Story on R M

    26/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 26 of 37

    before after

    before after

  • 8/22/2019 The Succes Story on R M

    27/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 27 of 37

    before after

    before after

  • 8/22/2019 The Succes Story on R M

    28/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 28 of 37

    before after

    Before After

  • 8/22/2019 The Succes Story on R M

    29/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 29 of 37

    before after

    before after

  • 8/22/2019 The Succes Story on R M

    30/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 30 of 37

    before after

    before after

  • 8/22/2019 The Succes Story on R M

    31/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 31 of 37

    before after

    before after

  • 8/22/2019 The Succes Story on R M

    32/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 32 of 37

    before after

    before after

  • 8/22/2019 The Succes Story on R M

    33/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 33 of 37

    before after

    Before repair After repair

  • 8/22/2019 The Succes Story on R M

    34/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 34 of 37

    before after

    afterbefore

  • 8/22/2019 The Succes Story on R M

    35/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 35 of 37

    before after

    before after

  • 8/22/2019 The Succes Story on R M

    36/37

    SUCCESS STORY ON R, M & U WORKS OF UMIAM STAGE II HEPP

    Page 36 of 37

    before after

    before after

  • 8/22/2019 The Succes Story on R M

    37/37

    before after

    11/132KV, 10.6 MVA 11/132KV, 12 MVA

    before after