summary of parallel session i-atauchi/talks/acfa-lc03/summary.ffir.pdf · f igu r e 4. 72: b e am...
TRANSCRIPT
T. Tauchi, ACFA-LC03, Mumbai, India, 18 December, 2003
Summary of Parallel Session I-A
- Accelerator related -
!Parallel Session I-A, 16 December, 2003Accelerator related: Detector Accelerator Interface
09:00 - 09:20!! T. Tauchi, KEK, Japan: !!!!!!!!!!!!!!!!!!!!!!!!!!! Interaction region and beam delivery system!09:20 - 09:40!! D. Miller, University College London, U.K.: !!!!!!!!!!!!!!!!!!!!!!!!!! Measuring the Luminosity spectrum !09:40 - 10:00! T. Sanuki, University of Tokyo, Japan: !!!!!!!!!!!!!!!!!!!!!!!!!! Status and future prospect of the GLCTA !!!!!!!!!!!!!!!!!!!!!!!!!! (Global Linear Collider Test Accelarator) !10: 00 - 10:20 G. Blair, RHUL, U.K.: !!!!!!!!!!!!!!!!!!!!!!!!! The Laserwire System at PETRA !
Beam Delivery System (BDS) Layout
4.9. Beam Delivery Section 221
4.9 Beam Delivery Section
4.9.1 Introduction
The electron and positron beams, after exiting from the main linac, before arriving at the interactionpoint (IP), pass through a beam line section which is about 1.4 km long. This section, togetherwith the beamline downstream of the IP is called ‘beam delivery section’. The beam delivery sectionconsists of four parts: switch-yard, collimator, final focus system (FFS), and beam dump. Fig. 4.63shows a schematic layout of the beam delivery section.
CollimatorBypass
Main Linac
Final Focus SystemBeam Dump
IP1
IP2
7 mrad
30 mrad
Switchyard& diagnostics
Figure 4.63: Schematic plan of the beam delivery section.
In addition to making a tiny beam spot at the IP, the beam delivery section serves multiple purposes,as follows:
• Focus the beams at the IP.
• Switch beamlines. (The beam comes from the main linac or from the bypass line and goes tothe first or to the second IP.)
• Create a finite crossing angle at the IP (7 mrad).
• Collimate the beam for eliminating the background for physics experiments.
• Protect the machine from damages due to potential failures.
• Dump the beams after collisions safely.
JLC Project Report, Revised, March 12, 2003, 3:21 P.M.
Roadmap Report,2003
4.9. Beam Delivery Section 229
fraction of the beam energy (more than a few percent). These photons also have to go to thesame water.
Fig. 4.71 shows the magnet layout of the dump line (up to the focal point for diagnostics) togetherwith the last part of the FFS.
Fig. 4.72 shows the beam spot at the diagnostics point. Here, 6 groups of points are shown. Theyrepresent the (x, y) profile of those particles with energy deviations of ε = ∆E/E = 0% (group at thebottom), −0.2%, −0.4%, . . ., −1% (at the top). One finds that the vertical width of each group issmall enough to resolve the energy to an accuracy of 10−4 near ε = 0 and 10−3 near ε = −1%.
Distance from IP (m)0 20 40 60 80 100 120
IP QD1 QF1 FFS FF
SB1B
FFSB
1A
FFSB
1
FFSB
1
FFSB
1
Dump LineQF1
QD1
BH1
BH2
QD2
QF2
BV1
BV2
1.00.5
0-0.5-1.0
(m)
Figure 4.71: Layout of the dump line
Y (m
m)
X (mm)-0.8 -0.6 -0.4 -0.2 0 0.2 0.4 0.6 0.8
0
0.1
0.2
0.3
0.4
Figure 4.72: Beam spot at the diagnostics point in the dump line.
The wasted beam is transported over a few hundred meters and guided to a dump system. Theamount of energy deposit is 11.5 MW (each beam) at ECM=1TeV. This will be cooled by water in
JLC Project Report, Revised, March 12, 2003, 3:21 P.M.
2nd FP at 140mBeam Spotat the 2nd FP
0%-0.2%-0.4%
-0.6%-0.8%-1.0%
Dumpline : Layout (2)
Apertures ?Shields ?Background: neutrons, photons to be estimated by the BDS-SIM.Better with large crossing angle of 20 mrad ?
4.9. Beam Delivery Section 229
fraction of the beam energy (more than a few percent). These photons also have to go to thesame water.
Fig. 4.71 shows the magnet layout of the dump line (up to the focal point for diagnostics) togetherwith the last part of the FFS.
Fig. 4.72 shows the beam spot at the diagnostics point. Here, 6 groups of points are shown. Theyrepresent the (x, y) profile of those particles with energy deviations of ε = ∆E/E = 0% (group at thebottom), −0.2%, −0.4%, . . ., −1% (at the top). One finds that the vertical width of each group issmall enough to resolve the energy to an accuracy of 10−4 near ε = 0 and 10−3 near ε = −1%.
Distance from IP (m)0 20 40 60 80 100 120
IP QD1 QF1 FFS FF
SB1B
FFSB
1A
FFSB
1
FFSB
1
FFSB
1
Dump LineQF1
QD1
BH1
BH2
QD2
QF2
BV1
BV2
1.00.5
0-0.5-1.0
(m)
Figure 4.71: Layout of the dump line
Y (m
m)
X (mm)-0.8 -0.6 -0.4 -0.2 0 0.2 0.4 0.6 0.8
0
0.1
0.2
0.3
0.4
Figure 4.72: Beam spot at the diagnostics point in the dump line.
The wasted beam is transported over a few hundred meters and guided to a dump system. Theamount of energy deposit is 11.5 MW (each beam) at ECM=1TeV. This will be cooled by water in
JLC Project Report, Revised, March 12, 2003, 3:21 P.M.
2nd FP at 140mBeam Spotat the 2nd FP
0%-0.2%-0.4%
-0.6%-0.8%-1.0%
IR: Crossing Angle IssueK.Yokoya
50 vs 16 fs 1.8 vs 0.6at L*=3.5m(Δyo=0.5σy)
7 mrad vs 20 mradPhysics
Stabilization R&D: Support Tube
1
234
567
8
910
1112
13141516
17
18
192021
1
234
56789
1011121314
151617
18 1920
21
1234
5678
9101112
131415161718
192021
1234
567891011121314151617
18
192021
ロク ゙Hz10 100 1E3
1
0.1
0.01
10
1Z:1Z 2Z:1Z 3Z:1Z 4Z:1Z 5Z:1Z 6Z:1Z 7Z:1Z 8Z:1Z 9Z:1Z 10Z:1Z 11Z:1Z 12Z:1Z =>
A: 77.5Hz
○ Results(Taper flange, 12-M6)
B: 90Hz
C: 258Hz
D: 522Hz
AB
CD123456789
G-sensor
Fixed
101112131415161718 1920
21
Fixed
ANSYS- FEM76, 256, 489 Hz
1/10 Model
H.Yamaoka,7/30 2003
SummaryIR studies have been “completed” for L*=2m and 4.3m; as in the “Particle Physics Experiments at JLC”, KEK Report 2001-11, Aug. 2001.
Since the BDS was updated at the "GLC Project", KEK Report 2003-7, Sept. 2003, we are in the process of re-designing the IR and reexamining the relevant issues.
Stabilization R&D has been active on the support tube, FEATHER and Nano-BPM for nanometer-collisions.
Instrumentation R&D has been conducted on the pair monitor, laser wire, ODR, X-SR monitors etc. many of which have been investigated at the KEK-ATF.
4David Miller; Mumbai 16/12/03. Measuring the Luminosity Spectrum
ACFA
current dMW
Heinemeyer et al (hep-ph/0306181)
Why dmt < 100 Mev?
LC’s precision programme!
Measuring the Luminosity Spectrum by D. Miller
9David Miller; Mumbai 16/12/03. Measuring the Luminosity Spectrum
ACFA
Mike Hildreth suggesting “bump” spectrometer insert, upstream, in BDS.Reverts to straight-ahead when currents turned off.Blue discs are bpms on precision movers. Follow the beam as it deflects.Picture is LEP version. LC longer(P.T.),more, smaller bends
Tradeoffs - bpm bandwidth - bpm resolution - length of insertion - bend angle
Emittance dilution
\ urgent.
Absolute and Jitter Spectrometer
Jitter within train?
Do precision RF bpms work in a beamline? Will only find out if we try.
10David Miller; Mumbai 16/12/03. Measuring the Luminosity Spectrum
ACFA
Spectral Shape Measurement
* Synchrotron swathes from a pair of bends (downstream only, like SLD WISRD?)
* Laserwire at dispersed focus for spectrum, maybe even upstream so could use all the time, not just pulse sampling?
Spectrometry, continued
Building a collaboration for beam testsTalking to Mike Woods(SLAC), Mike Hildreth(Notre Dame), Eric Torrence(Oregon),Stan Herzbach(Amherst), David Ward(Cambridge) about a test-beam campaignusing SLAC End Station A. Heinz-Jurgen Schreiber(Zeuthen) and collaborators have DESY based plans.
All of us striving for funds to do proper experiments.
11David Miller; Mumbai 16/12/03. Measuring the Luminosity Spectrum
ACFAGoalsWe need a well engineered spectrometry design before theBeam Delivery System is finalised.
It would be wise to prove we can measure mt and mh to the claimed precision before funding agencies send referees to check in 2006, ahead of final approval.
So we had better start the spectrometry testssoon to match progress on Bhabha acollinearity.
We will also need a strategy for Dp/p ~10-5 measurementsbefore anyone will fund a GigaZ upgrade.There are not enough of us; happy if Asia can join in.
03.12.16 T. Sanuki, 6th ACFA WS 8
ATF -> GLCTA
• GLC electron injector complex
+
• GLC 1/5,000 of main linac
Realistic demonstration of GLC accelerator
Status and future prospect of the GLCTA by T.Sanuki
03.12.16 T. Sanuki, 6th ACFA WS 19
Current system
Klystron #1Klystron #2
Acc. Structure
03.12.16 T. Sanuki, 6th ACFA WS 18
Current situation
Ready for operation on October 1st.
03.12.16 T. Sanuki, 6th ACFA WS 11
Construction/power source
03.12.16 T. Sanuki, 6th ACFA WS 15
Accelerating structure
03.12.16 T. Sanuki, 6th ACFA WS 31
Schedule (example)2003 2004 2005 2006
Construction
Test
SLED II
Modulator
PPM Klystron
RF Component
Acc. Complex
GLC demonstration
16th December 2003 G. Blair, RHUL 5
Optical Scattering StructuresOptical Scattering Structures
•• Scanning of finely focused laser beam through electron beamScanning of finely focused laser beam through electron beam•• Detection of Compton photons (or degraded electrons) as functionDetection of Compton photons (or degraded electrons) as function
of relative laser beam positionof relative laser beam position•• ChallengesChallenges
-- Produce scattering structure smaller than beam sizeProduce scattering structure smaller than beam size-- Provide fast scanning mechanismProvide fast scanning mechanism-- Achieve efficient signal detection / background suppressionAchieve efficient signal detection / background suppression
The Laserwire System at PETRA, G. Blair
16th December 2003 G. Blair, RHUL 7
Laserwire for PETRALaserwire for PETRA
16th December 2003 G. Blair, RHUL 16
First Photons 31.07.03First Photons 31.07.03
Laser on Laser off
Photodiode at IP
Q-switch
Calorimeter
16th December 2003 G. Blair, RHUL 30
Results 04.12.03 DataResults 04.12.03 Data
•• Slopy Gaussian approximation of beam shapeSlopy Gaussian approximation of beam shape !!m m =(68 =(68 ±± 3 3 ±± 20) 20) ""m at low currentm at low current
!!m m =(80 =(80 ±± 6 6 ±± 20) 20) ""m at high currentm at high current
Updating the Beam Delivery System (new final focus system with longer L* etc.), interaction region is re-designing together with background re-evaluation.
Especially, (large) crossing angle issue should be carefully investigated from both sides of experimentation and accelerator.
ConclusionsACFA-FFIR subgroup
Worldwide ( in all three regions )Many high energy physicists have played important role in R&D on the stabilization, instrumentation and accelerator, cooperating with accelerator physicists.