structure of presentation 1.introduction 2.the core network and its status discussion 3.investment...

59

Upload: madison-schmidt

Post on 27-Mar-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion
Page 2: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Structure of presentation

1.1. IntroductionIntroduction

2.2. The Core Network and its status The Core Network and its status

DiscussionDiscussion

3.3. Investment programmingInvestment programming

DiscussionDiscussion

4.4. Analysis of sub-sectorsAnalysis of sub-sectors

DiscussionDiscussion

Page 3: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Project organisation

Page 4: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Previous projects

Commission services paper: Commission services paper: "Transport and Energy "Transport and Energy

Infrastructure in South East Europe" (2001)Infrastructure in South East Europe" (2001)

TIRS study (2002)TIRS study (2002)

Page 5: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Pan-European corridors

Page 6: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Proposed core road network

Page 7: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Routes and corridors, roads

Page 8: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Propsed core rail network

Page 9: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Routes and corridors, railways

Page 10: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Proposed core seaports

Seaports

Rijeka

Split

Ploce

Dubrovnik

Bar

Durres

Vlore

Page 11: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Airports

Tirana Tirana

SarajevoSarajevo

ZagrebZagreb

SkopjeSkopje

BelgradeBelgrade

Banja LukaBanja Luka

PristinaPristina

PodgoricaPodgorica

DubrovnikDubrovnik

NisNis

SplitSplit

Page 12: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Proposed core road network

Page 13: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Propsed core rail network

Page 14: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Road Geometry

Page 15: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Road condition

Page 16: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Present technical condition, railways

Page 17: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Ongoing initiatives

Balkan Stability PactBalkan Stability Pact

Southeast European Co-operation Initiative (SECI)Southeast European Co-operation Initiative (SECI)

EU CARDS programmeEU CARDS programme

World Bank Trade and Transport Facilitation inWorld Bank Trade and Transport Facilitation in

Southeast Europe Programme (TTFSE)Southeast Europe Programme (TTFSE)

Page 18: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Road border crossings on Core Network and location of border crossings which are presently or potentially bottlenecks and are not already supported

Page 19: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Rail border crossings on core network and location of border crossings which are presently or potentially bottlenecks and are not already supported

Page 20: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Projected road traffic 2006, moderate economic growth scenario

Page 21: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Projected rail passenger traffic 2006, moderate economic growth scenario

Page 22: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Growth in passenger traffic 2001 - 2025

Alban

ia

Bosni

a an

d Her

zego

vina

Croat

ia

Mac

edon

ia

Serb

ia a

nd

Mon

tene

gro

Car

Rail

Air

0%

100%

200%

300%

400%

500%

600%

700%

800%

900%

Page 23: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Growth in freight traffic 2001 – 2025

Truck

Rail

Inland waterwayAlb

ania

Bosni

a an

d Her

zego

vina

Croat

ia

Mac

edon

ia

Serb

ia a

nd

Mon

tene

gro

0%

100%

200%

300%

400%

500%

600%

Page 24: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

The planning process

Page 25: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

"European" standards

Road:AGRRoad:AGR

80 - 120 km/h80 - 120 km/h

min. 7m asphaltmin. 7m asphalt

Rail: AGC/AGTCRail: AGC/AGTC

Corridor X 160 km/h, double trackCorridor X 160 km/h, double track

other lines: basic modernisation (100-120 km/h)other lines: basic modernisation (100-120 km/h)

Page 26: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Long-term investment requirements:

Roads: 4 Billion EuroRoads: 4 Billion Euro

Railways: 12 Billion EuroRailways: 12 Billion Euro

Page 27: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Location of road investments

Page 28: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Proposed rail modernisation

Page 29: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Short term investment plan

Recommended actions may be:Recommended actions may be:

studies (e.g. feasibility studies)studies (e.g. feasibility studies) designdesign constructionconstruction

All infrastructure projects on the Core Network for All infrastructure projects on the Core Network for which action is recommended before end of 2004. which action is recommended before end of 2004. Covers the period 2004 - 2009Covers the period 2004 - 2009

Projects may be: Projects may be: ongoingongoing committedcommitted newnew

Page 30: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Project screening

Two phases:Two phases:

Collection of project data in the region Collection of project data in the region

=> project fiches=> project fiches

Screening of projects Screening of projects

= ranking with multi-criteria model= ranking with multi-criteria model

Output:Output:

Projects ranked according to scoreProjects ranked according to score

Page 31: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Example of project fiche

Page 32: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Weights of criteria

Criteria-weight

Criterion I: Economic appraisal 0.50

Criterion II: Financial viability 0.20

Criterion III:

Environmental effects 0.05

Criterion IV:

Functionality and coherency of the network

0.15

Criterion V: Readiness of the Authority 0.10

Page 33: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Example of output from screening model

Page 34: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Number of road and rail projects on the Core Network comprised by the quantitative screening

Albania

Bosnia and Herzegovin

a

Croatia Serbia and Montenegr

o

FYROMacedoni

a

Total

Highway

9 12 7 19 11 58

Railway 1 7 13 14 8 43

Page 35: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Project costs by corridor/route

1,200

1,000

800

600

400

200

0Tota

l in

vestm

en

t cost

(EU

R m

illion

)

Corrid

or Vb

Corrid

or Vc

Corrid

or VIII

Corrid

or X

Corrid

or Xb

Corrid

or Xc

Corrid

or Xd

Route 1

Route 2

a

Route 2

b

Route 4

Route 8

Route 7

Route 8

Route 1

0

Road projects

Rail projects

Page 36: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Pre-feasibility studies - 19

Criteria for selection of projects:Criteria for selection of projects:

Above 70% of maximum score in screening processAbove 70% of maximum score in screening process

Up-to-date feasibility study is not availableUp-to-date feasibility study is not available

An initial assessment of the project is a precondition An initial assessment of the project is a precondition

for further actionfor further action

Approval or financing of the project is not securedApproval or financing of the project is not secured

Page 37: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Pre-feasibility studies - 19

Focus in pre-feasibility analyses:Focus in pre-feasibility analyses:

Project is compared with a realistic Project is compared with a realistic reference alternativereference alternative

Change in investment, operating and Change in investment, operating and maintenance costs of infrastructuremaintenance costs of infrastructure

Change in travel time Change in travel time

Change in operating costs of rolling Change in operating costs of rolling stock/vehicles and equipmentstock/vehicles and equipment

Change in traffic safetyChange in traffic safety

Page 38: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Location of pre-feasibility studies - Road

Page 39: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Location of pre-feasibility studies - Rail

Page 40: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Basis for Short term Investment Plan General REBIS policy recommendations:General REBIS policy recommendations:

Maintain present infrastructure - rather than Maintain present infrastructure - rather than constructing new links/increase capacityconstructing new links/increase capacity

Concentrate investments on most important Concentrate investments on most important regional connectionsregional connections

Strike a balance between transport modes Strike a balance between transport modes

National priorities are reflectedNational priorities are reflected

Affordable investment level Affordable investment level

Reasonable distribution between countriesReasonable distribution between countries

Results of the screening and pre-feasibility analysesResults of the screening and pre-feasibility analyses

Page 41: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Total investment costs broken down by project status (EUR million)

Data Committed projects

Ongoing projects

New projects

Grand Total

Investment cost

828 791 2,074 3,693

Percentage distribution of investment costs

22% 21% 56% 100%

Number of projects

22 31 79 132

Page 42: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Location of ongoing, committed and new road and airport projects

Page 43: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Location of ongoing, committed and new railway and ports projects

Page 44: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Short Term Investment Plan implications

Timing of investment costs 2004-2009Timing of investment costs 2004-2009

Investments by corridor and routeInvestments by corridor and route

Investments by project status and transport modeInvestments by project status and transport mode

Investments by countryInvestments by country

Page 45: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Investment costs broken down by project status phased over the implementation period (EUR million)

0

200

400

600

800

1,000

1,200

2004 2005 2006 2007 2008 2009

Year

An

nu

al in

vestm

en

t le

vel (E

UR

million

)

New projects

Ongoing projects

Committed projects

Page 46: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Investment costs by transport mode and scope for all projects (EUR million)

AirportBorder Cros-sing

I. Water-ways

Multi-modal

RailRoad Sea

port

Construction

Provision of equipment

Rehabilitation/reconstruction

Upgrading

0

200

400

600

800

1,000

1,200

Page 47: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Investment costs by transport mode and scope for all "New projects" (EUR million)

Construction

Provision of equipment

Rehabilitation/reconstruction

Upgrading

Airport Bordercrossing

Multi-modal Rail Road

Sea port

0

100

200

300

400

500

600

Page 48: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Roads and Rail - phased investment costs broken down by project status (EUR million)Roads

Rail0

100

200

300

400

500

600

2004 2005 2006 2007 2008 2009Year

Million

Eu

r

0

50

100

150

200

250

300

350

2004 2005 2006 2007 2008 2009Year

Million

Eu

rNew projects

Ongoing projects

Committed projects

Page 49: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Investment costs and GDP

  Estimated

GDP

Total GDP Assumed real growth

in period

Estimated investment costs (mill.

EUR)(2003 -prices)

Investment/

GDP

Year 2003 2004-2009 2004-2009 2004-2009 2004-2009

Unit Bn EUR Bn EUR (2003 prices) Real growth (%) Bn EUR (2003 prices)

% of BNP

Albania 5.5 40.9 45% 555 1.4%

Bosnia 6.1 49.2 28% 531 1.1%

Croatia 25.3 206.4 27% 950 0.5%

Kosovo* 1.7 14.7 33% 106 0.7%

Macedonia 3.8 39.3 26% 292 0.7%

Serbia & Montenegro

12.3 108.1 32% 1,258 1.2%

Source: The GDP figures are estimated based on the World Bank's GDP figures for 2001 and projected based on real growth rates between 3.7% and 6.5% per year. The figure for Kosovo is estimated by IMF who assess the GDP to be 3 bn Deutsche Mark corresponding to around 1.5 bn EUR in year 2000.

Page 50: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Long Term Investment Programming Investment planning is an on-going and continues Investment planning is an on-going and continues

processprocess

New projects need to be identified and included in the New projects need to be identified and included in the planning process immediately after 2004planning process immediately after 2004

A starting point is REBIS identified projects not A starting point is REBIS identified projects not included in the Short Term Investment Planincluded in the Short Term Investment Plan

A regional monitoring mechanism with access to A regional monitoring mechanism with access to technical back-up is a corner stone for a coherent technical back-up is a corner stone for a coherent development of infrastructure of regional importancedevelopment of infrastructure of regional importance

Page 51: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Long term challenges and requirements Roads:Roads:

Major investments in road capacity only after 2010Major investments in road capacity only after 2010

STIP includes only about 50% of estimated STIP includes only about 50% of estimated investment requirements 2004-2015investment requirements 2004-2015

Page 52: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Long term challenges and requirements Rail:Rail:

Large-scale upgrading of infrastructure to Large-scale upgrading of infrastructure to AGC/AGTC standards is not recommended in the AGC/AGTC standards is not recommended in the first few years, where focus should be on business first few years, where focus should be on business developmentdevelopment

Modernisation should be considered when Modernisation should be considered when rehabilitation of existing lines is plannedrehabilitation of existing lines is planned

STIP includes only about 10% of estimated costs of STIP includes only about 10% of estimated costs of upgrading to European standard 2004 -2015upgrading to European standard 2004 -2015

Page 53: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Long term challenges and requirements Ports and airports:Ports and airports:

Long term requirements are difficult to assess in Long term requirements are difficult to assess in a future competitive environment where user a future competitive environment where user charging will be an important source of financing charging will be an important source of financing

IWW:IWW:

Major investments are needed, especially in the Major investments are needed, especially in the Danube. Type and level will be determined in Danube. Type and level will be determined in upcoming studiesupcoming studies

Page 54: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Management information systems

Infrastructure is an asset which:Infrastructure is an asset which:

needs to be maintained and improvedneeds to be maintained and improved

to ensure maximum value for money of the to ensure maximum value for money of the

infrastructureinfrastructure

needs to build on up-to-date information onneeds to build on up-to-date information on

conditions and usageconditions and usage

Efficient management consists of a managed series of Efficient management consists of a managed series of

works and activities which:works and activities which:

Page 55: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Road management information systems Status:Status: In most countries dataIn most countries data exists, but often in exists, but often in

separate, paper based systems, which are not separate, paper based systems, which are not always updated regularlyalways updated regularly

Needs:Needs: Extension of traffic counting to the entire networkExtension of traffic counting to the entire network Updating of data on structuresUpdating of data on structures Improved bridge management systemsImproved bridge management systems ComputerisationComputerisation of data before unified systems are developed of data before unified systems are developed Improved co-operation between police and road authorities to obtain Improved co-operation between police and road authorities to obtain

better data on accidents in better data on accidents in order to improve road safetyorder to improve road safety

Page 56: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Rail management information systems Status:Status:

Inventories on conditions of structures and Inventories on conditions of structures and

traffic are mainly paper basedtraffic are mainly paper based

Needs:Needs:

Development of computerised systems, which Development of computerised systems, which

will facilitate assessment of needs in a more will facilitate assessment of needs in a more

efficient wayefficient way

Page 57: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Port management information systems Status:Status:

Inventories on conditions of structures are mainly paper Inventories on conditions of structures are mainly paper

based, whereas traffic data more often is recorded in a based, whereas traffic data more often is recorded in a

computerised systemcomputerised system

Needs:Needs:

Development of computerised systems, which Development of computerised systems, which

will facilitate assessment of needs in a more will facilitate assessment of needs in a more

efficient wayefficient way

Page 58: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Airport management information systems Status: Status:

There are generally no management information systems in the There are generally no management information systems in the

airports.airports.

Data are kept in a mix of paper and computerised systems; traffic Data are kept in a mix of paper and computerised systems; traffic

data is most often recorded in computerised systemsdata is most often recorded in computerised systems

Needs:Needs:

Development of computerised systems, which Development of computerised systems, which

will facilitate assessment of needs in a more will facilitate assessment of needs in a more

efficient wayefficient way

Page 59: Structure of presentation 1.Introduction 2.The Core Network and its status Discussion 3.Investment programming Discussion 4.Analysis of sub-sectors Discussion

Inland waterway management information systems

Status:Status:

Croatia and Serbia have computerised their Croatia and Serbia have computerised their

data to some extentdata to some extent

Needs:Needs:

Especially Serbia needs to develop computerised Especially Serbia needs to develop computerised

systems and to update date on traffic and systems and to update date on traffic and

conditions, which will facilitate assessment of conditions, which will facilitate assessment of

needs in a more efficient wayneeds in a more efficient way