sns operational experience
TRANSCRIPT
SNS Operational Experience
Project X Workshop April 12, 2011
Kevin Jones – on behalf of the SNS team
2 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
SNS Accelerator Complex
The Front-End produces a 60 Hz, 1 ms long chopped H- beam
Accumulator Ring: Compress 1 msec long pulse
to 700 nsec
2.5 MeV
Superconducting LINAC Front-End
RTBT
HEBT
Injection Extraction
RF
Collimators
945 ns
1 ms macropulse
Cur
rent! mini-pulse
Chopper system makes gaps
Current!
1ms
Liquid Hg Target
~1000 MeV
1 ms macropulse 1 ms
<1 µsec
186 MeV
Warm Linac
• The SNS accelerator is the highest power pulsed hadron linear accelerator
• Uses superconducting RF for acceleration
• Storage Ring to compress the 1 ms linac beam into a 1 µs “short-pulse” on the neutron production target
3 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
Beam Power History
• Running at ~ 1 MW for ~ 1.5 years • Present operational power is dictated by budget allowance
– Not limited by equipment or beam loss!
Equipment / Availability Limit Operational budget
limited
Bea
m P
ower
(kW
)
1000 1 MW beam power on target achieved in routine operation after 3 years
Ion Source, LEBT
Stripper foil
Target CMS leak
HVCM
4 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
SNS has demonstrated reliable operation at ~1 MW
5 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
Since 2006 operational performance improvement at SNS has been dramatic
6 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
Our ramp-up goals were adjusted to meet user expectations and match budgets
• Beam power: kept up initially, but leveled off at ~ 1 MW after fall 2009
!"
#!!"
$!!"
%!!"
&!!"
'!!!"
'#!!"
'$!!"
'%!!"()*+!%"
,)-+!%"
./0+!1"
234+!1"
()*+!1"
,)-+!1"
./0+!&"
234+!&"
()*+!&"
,)-+!&"
./0+!5"
234+!5"
()*+!5"
,)-+!5"
./0+'!"
234+'!"
()*+'!"
!"#$%&"#'%!()
"*%+$
,-%
6478/9":;/9"
<-=3/9">)0?;0@/4-)"
!"#!!#$"#$!#%"#%!#&"#&!#'"#'!#
(""#
)*+,"$#
-*.,"$#
/01,"%#
234,"%#
)*+,"%#
-*.,"%#
/01,"&#
234,"&#
)*+,"&#
-*.,"&#
/01,"'#
234,"'#
)*+,"'#
-*.,"'#
/01,("#
234,("#
)*+,("#
!"#$
%&'#()#*()(+,%-.
/%
546708#9:08#
;.<308#=*1>:1?04.*#
(Peak power attained)
• Availability is a more difficult goal, and stronger driver for operational parameters
• We could run at higher powers, but the availability may suffer
7 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
Initial and ongoing operation revealed system weakness that have been substantially addressed
FY07-FY10 Downtime by group
0
50
100
150
200
250
300
350
400
450E-
HVCM
Ion
Sour
ce RFTa
rget
E-M
agPS
E-ch
oppe
rCo
ntro
lsVa
cuum
Co
olin
g E-
othe
rCr
yo APPr
ot. S
ys.
Fac.
/Mec
h. S
ys. BI
Ops
Mis
c./M
ag/R
S/ES
HNe
ut. I
nst.
System
Hou
rs o
f do
wnt
ime
FY07 FY08 FY09 FY10
System FY07 FY08 FY09 FY10E-HVCM 379.4 421.2 309 240.0Ion Source 394.7 142.2 101.8 113.5RF 162.3 230.2 226.4 126.3Target 140.1 158.9 12 140.5E-MagPS 78.6 162.2 68.1 88.5E-chopper 241.8 50.3 58.3 30.4Controls 161.3 58 90.4 24.1Vacuum 90.2 124 33.7 11.4Cooling 165.2 31.2 27.5 24.3E-other 85.9 45.6 40 36.1Cryo 15.2 4.7 38.9 21.1AP 19 27.3 20.2 7Prot. Sys. 19 9.4 26.4 13.6Fac./Mech. Sys. 5.7 3.1 31.7 2.9BI 15.2 8.4 16.2 0.6Ops 8.8 13.4 6.6 5.1Misc./Mag/RS/ESH 7.1 2 3.8 1.4Neut. Inst. 0.2 2 0 0Total 1989.7 1494.1 1111 886.8
8 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
SNS reliability compares favorably with other moderate to high-power facilities
• Facilities with the fewest long outages have the highest availability
Data compiled at the 2008 ICFA High Brightness workshop, Nashville TN
100
10
1
0.1
< 1 minute
Trip Frequency per day
>1 minute, < 1 hour
>1 hour, < 3 hours
> 3 hours
9 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
Linac Activation History
• Superconducting Linac activation is not increasing, despite significant increase in power and operational hours
• Beam loss is not a limiting factor (at least for 1 MW beam)
10 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
How Much Beam is Lost in the SNS SCL ???
• We did not know what to expect – models indicated no loss, but…
• Activation measurements indicate < 1 W/m in the warm sections between our cryo-modules – < 10-4 of the beam throughout the superconducting linac
• Measurements in the 10-5 fractional beam level are difficult – Loss monitors are quite sensitive, but do not tell you much about why you lost
beam
• Laser profile device turns out to be a good way to create controlled beam spills of 10-6 beam – Increases the integrated beam loss about 10% (or we are nominally losing 10-5
throughout the linac)
11 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
!"
!#$"
%"
%#$"
$"
$#$"
&"
&#$"
'"
()*+,-./0123""
()*+,-./0124""
()*+,-./012!""
()*+,-./012%""
()*+,-./012$""
()*+,-./012&""
()*+,-./012'""
()*+,-./0125""
()*+,-./0126""
()*+,-./0132""
()*+,-./0133""
()*+,-./0134""
()*+,-./013!""
()*+,-./013%""
()*+,-./013$""
()*+,-./013&""
()*+,-./013'""
()*+,-./0135""
()*+,-./0136""
()*+,-./0142""
()*+,-./0143""
()*+,-./0144""
()*+,-./014!""
()*+,-./014%""
()*+,-./014$""
()*+,-./014&""
()*+,-./014'""
()*+,-./0145""
()*+,-./0146""
()*+,-./01!2""
()*+,-./01!3""
()*+,-./01!4""
()*+,-./01!!""
!"#$%&'()*
+&
,-.&/01%2&!"#$%2&789:.;"
<=>?@AB>;"
(C>>DE"<=>?"
SNS Linac Transverse Lattice: Design vs. Operation
!"
#$"
#%"
#&"
#'"
#!"
%$"
%%"
%&"
%'"
%!"
(()*+,-./0$$""
(()*+,-./0#$%""
(()*+,-./10#$&""
(()*+,-./10#$'""
(()*+,-./10#$!""
(()*+,-./10##$""
(()*+,-./10##%""
(()*+,-./10%$%""
(()*+,-./10%$&""
(()*+,-./10%$'""
(()*+,-./10%$!""
(()*+,-./10%#$""
(()*+,-./10%#%""
(()*+,-./102$%""
(()*+,-./102$&""
(()*+,-./102$'""
(()*+,-./102$!""
(()*+,-./102#$""
(()*+,-./102#%""
(()*+,-./10&$%""
(()*+,-./10&$&""
(()*+,-./10&$'""
(()*+,-./0&$!""
(()*+,-./0&#$""
!"#$%&'()*
+&
,,-&./0%1&!"#$%1&
3456-7" 89:;<=>:7"
• SCL quads run much lower than design • Warm linac is run close to design
• SCL beam loss is significantly lower for the reduced field settings!!
• Empirically derived
CCL quad fields
!"
#!"
$!"
%!"
&!"
'!!"
'#!"
'$!"
'%!"
'&!"
#!!"
()*+,-./01*2!!"
()*+,-./01*2!#3"
()*+,-./01*2!43"
()*+,-./01*2!$3"
()*+,-./01*2!53"
()*+,-./01*2!%3"
()*+,-./01*2!63"
()*+,-./01*2!&3"
()*+,-./01*2!73"
()*+,-./01*2'!3"
()*+,-./01*2''3"
()*+,-./01*2'#3"
()*+,-./01*2'43"
()*+,-./01*2'$3"
()*+,-./01*2'53"
()*+,-./01*2'%3"
()*+,-./01*2'63"
()*+,-./01*2'&3"
()*+,-./01*2'73"
()*+,-./01*2#!3"
()*+,-./01*2#'3"
()*+,-./01*2##3"
()*+,-./01*2#43"
()*+,-./01*2#$3"
()*+,-./01*2#53"
()*+,-./01*2#%3"
()*+,-./01*2#63"
()*+,-./01*2#&3"
()*+,-./01*2#73"
()*+,-./01*24!3"
()*+,-./01*24'3"
()*+,-./01*24#3"
!"#$%&
'(")&*+,,&-.&/01(23+.#034.5&*-."3&
,89-/:";<=>?@A=:"
12 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
Intra-Beam-Scattering Beam Loss V. Lebedev, FNAL
• Simple estimates indicate this could be a loss contributor at SNS
• Only an issue for H- beams – Considered a proton source experiment to
test this loss mechanism – Now planning on a low energy foil (strip H-
to p) experiment
Collisions between H- in the accelerated bunch can
strip the outer electron
Stripping probability is known :
13 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
Linac Beam Loss Situation • SNS has unexpected beam loss in the SCL
– OK for 1 MW, not acceptable for 10 MW – There is a suite of measurement tools available at SNS – Challenge is to measure the 6-D initial beam distributions down to halo
levels – And understand measured beam loss
• We should use the existing machines to understand the nature of this loss
Low loss tune
Before Matching
After Matching 40 deg tail
Longitudinal BSM, S. Aleksandrov
14 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
SNS Superconducting Linac
• 160 m, 23 cryo-modules, 81 cavities • Operating at 1 MW, 925 MeV, 60 Hz, 5% beam duty cycle
15 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
SNS RF Layout
• One cavity / klystron: easy, flexible, expensive • High voltage drive and transmitters are common-mode failure points though
– Alternatives include hot spare, single power supply / RF source
Beam
16 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
Superconducting Cavity Amplitudes Cavity Design
051015202530
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81
cavity
E0 (M
V/m
)
First Run
05101520253035
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81
cavity
E0 (M
V/m
)
Ring Commissioning Run
05101520253035
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81
cavity
E0 (M
V/m
)
0
5
10
15
20
25
30
35
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 69 71 73 75 77 79 81
E0 (M
V/m
)
Cavity
Sept. 2008
0
5
10
15
20
25
30
35
1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 69 71 73 75 77 79 81
E0 (M
V/m
)
Cavity
Sept. 2010
• SCL cavity gradient levels were not what we expected – We grossly underestimated the gradient variability – But the SCL is operationally quite flexible !!
• Make sure there is enough margin in the cavity design gradient
17 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
RF System: Independently Powered Cavities
• One klystron per cavity: conservative but robust
81 x 550 kW klystrons
18 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
Superconducting Cavity Fault Recovery
• A cavity fault recovery scheme is developed to adjust downstream cavity setup, to accommodate upstream cavity changes – Uses a difference technique, with initial beam based measurements – Successfully demonstrated and used at SNS
• Could work in < 1 sec if needed
0
200
400
600
800
1000
1200
1400
1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81
Cavity
Phas
e C
hang
e(de
g)
Final cavity phase found within 1 degree, output energy within 1 MeV
Cavity 3a turned off
-300
-200
-100
0
100
200
300
400
1 7 13 19 25 31 37 43 49 55 61 67 73 79Cavity
Phas
e C
hang
e (d
eg)
-6
-4
-2
0
2
4
6
Mea
sure
d Er
ror (
deg)
Phase ChangeMeasured Error
Turned on cavity 4a, reduced fields in 11 downstream cavities
19 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
High Voltage Power Supply System (HVCM)
• HVCM used new technology (IGBT) – Do not assume success with new technology
• Early on HVCM was a major down time problem – More robust components have greatly helped – For extreme reliability applications, need to consider hot-spare,
independent power supply/klystron, etc.
Initial experience – some “fireworks”
20 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
Ion Source reliability remains a concern
• At SNS the ion source is rising to the top of the reliability concern list – Long-term plan is to incorporate a dual source with a
magnetic LEBT for redundancy
21 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
Ring experience has been very positive Foil bracket issues
• World record intensity for protons accumulated in a Ring
Glowing foil at 1 MW
We have not been limited by: - Beam instabilities - Space charge induced beam loss
“Convoy” electron direct impact
22 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
Ring Injection: More Difficult than Originally Envisioned
H- beam from Linac Thin
Stripping Foil
To InjectionDump
ThickSecondary Foil
pH0
H-Dipole magnets
H- beam from Linac Thin
Stripping Foil
To InjectionDump
ThickSecondary Foil
pH0
H-Dipole magnets
• Need to handle clean transport of injected beam, circulating beam, un-stripped H- beam and partially stripped H0 beam – Not much space – Careful treatment of beam transport through 3-D fields – Fair amount of re-work in this area at SNS – Evaluating laser stripping as a future option
23 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
Clean Extraction from the Ring: No Problem • We have only used second stage chopping for the past
~ one year • 1st chopper stage is slow rise time (~100 nsec) LEBT
chopper • We never implemented a planned “Beam-in-Gap” kicker
to clean the gap • We are running a smaller gap than initially planned (up
to 75% beam vs. 68% beam)
time
Cur
rent
24 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
Ring Activation History
Pow
er (M
W)
1.0
• Activation by the injection stripper foil is the highest in the SNS accelerator
• Close to activation expectations • ~ Monotonic increase with beam power
25 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
Targets, Dumps, Collimators: More trouble than we imagined
• High power operation requires good understanding and control of primary and waste beams
• Redundant safety systems – avoid excessive nuisance trips
Direct measurements (beam position, power density, …) are easier than….
…model based extrapolations from upstream measurements
• Fast beam shut-off systems: – SNS errant beam to turn-off delay is ~ 20 µs – Can not buy these systems: custom hardware / software
< 20 µs
Zoom-in on an errant beam wave-form
26 Managed by UT-Battelle for the U.S. Department of Energy SNS Operational Experience – Project X Workshop
Summary • SNS is running a ~ MW proton superconducting linac
– > 5000 hrs/year operation – Beam loss is not a limitation
• Although we do see unexpected small loss levels – Reliability approaching 90%
• Improving • Still have many more trips than requirements for other applications
– Can use as a test bed for recovery concepts
• New technologies require shake-out periods • A robust, intelligent control system is essential to success • Customer requirements must be fully understood