scope of work mt ut bhn inspection
DESCRIPTION
ScopeTRANSCRIPT
BHN/U.T./MAGNETIC PARTICLE INSPECTION 26-JANUARY-2012
Page 1 of 9
SCOPE OF WORK
NON-DESTRUCTIVE INSPECTION
HARDNESS, U.T. and MAGNETIC PARTICLE INSPECTION OF WATER INJECTION
LINE AND COUPLING
DATE January 26, 2012
PREPARED BY:
Neil Scott …………………………………………..
Reliability Group
BHN/U.T./MAGNETIC PARTICLE INSPECTION 26-JANUARY-2012
Page 2 of 9
TABLE OF CONTENTS
SCOPE OF WORKS .................................................................................................................. 3
GENERAL REQUIREMENTS ...................................................................................................... 5
SPECIFICATIONS ..................................................................................................................... 7
MATERIALS AND EQUIPMENT ................................................................................................. 8
NOTES ................................................................................................................................... 9
BHN/U.T./MAGNETIC PARTICLE INSPECTION 3
INVITATION TO BID REGENERATION- NON-DESTRUCTIVE INSPECTION
ACTIVITIES
Petrojam Limited wishes to carry out Non-Destructive Inspection (Hardness/U.T., and
Magnetic Particle inspection) on it Process pipeline during its Emergency shutdown
January 2012 at its 96 Marcus Garvey Drive Kingston location.
1. SCOPE OF WORK
The contractor is required to supply all the materials, except as stated, quality assurance,
supervision, labour, transportation, tools, equipment, and other services, necessary to
execute the minimum requirements for magnetic particle inspection of ferromagnetic
materials and components, Hardness Testing and Ultrasonic Thickness Inspection as
follows:
Coupling and Reformer Feed Outlet Line to F-2
Magnetic Particle Inspection
1. Scaffolding will be erected around the equipment to facilitate access to the
couplings.
2. Ultrasonic Thickness inspection to be conducted as per ASME Section V on the
Reformer Feed Outlet Line to F-2.
3. Perform Ultrasonic Thickness and Wet Fluorescent Magnetic Particle
Examinations (MT) of the heat affected zones as per ASME Section V on the
connecting weld between Reformer Feed Outlet Line and both couplings.
4. Final magnetic particle inspection shall be performed after completion of all weld
repair operations that can generate surface or near surface discontinuities.
5. The stages in the repair process (i.e. root pass and at the completion of the repair)
where magnetic particle inspection is performed should be specified in the
welding specification and/or in the referencing codes.
6. The inspection contractor shall perform Brinnell Hardness Testing to ensure that
it is within the detection requirement of less than 225.
7. The tangential flux density shall be at least 1.0 T. The adequacy of the flux
density and/or field strength shall be verified on the surface under examination,
in each magnetizing direction, prior to or during the examination.
8. A flux density of 1,0 T is generally achieved with a tangential field strength from
2 kA/m to 6 kA/m, dependent upon the magnetic permeability of the material
being inspected.
9. The continuous method of application shall be used.
BHN/U.T./MAGNETIC PARTICLE INSPECTION 4
10. The powder shall be applied immediately prior to and during magnetization.
11. Magnetization shall be continued for at least two seconds after the application
has ceased to allow indications to build up and excess powder to be removed.
Ultrasonic Thickness Inspection
12. The thickness shall be checked or compared with the standard step block
thickness by placing the transducer/probe on standard step block after applying
couplant or thick lubricating oil/grease before taking measurement on the pipe.
13. Visual inspect and/or UT scan pipeline surface at location(s) where excessive
corrosion is/are observed at lower elevations where possibilities of collection and
stagnation of carry over water, acid condensation, SO2 or H2S flow exist.
14. Report of findings/recommendation to be submitted after inspection.
The location of work shall be in the Processing Unit on the basis of name and details of
Pipeline route as described in the Bill of Quantities below:
NDT Inspection of Process Unit Pipelines
Catalyst Regeneration 2012
Bill of Quantities
Unit Eq/Circ ID Pipeline Description
NDT
Inspection
Method
# of
TML
Points Cost
APS 05-88 REFORMER FEED
OUTLET TO F-2 UT/MT/BHN 4
¾” COUPLING UT/MT/BHN 4
½” COUPLING UT/MT/BHN 4
SUB-TOTAL
SUMMARY
Description Sub-Total
Insurance
Other Charges
Collection Summary
Provisional Sum
Grand Total Cost - Carried to Form of Tender (excl. provisional sum)
BHN/U.T./MAGNETIC PARTICLE INSPECTION 5
2. GENERAL REQUIREMENTS
The detailed specifications given hereinafter are for the items of works described in the
schedule of quantities attached herein, and shall be guidance for proper execution of
work to the required standards. It may also be noted that the specifications are of a
generalized nature and these shall be read in conjunction with the description of item in
the Engineers Bill of Quantities and drawings/sketches provided.
Unless specifically otherwise mentioned, all the applicable codes and standards (API,
ASME etc.), shall govern in all respects of workmanship, quality and methods of testing.
1. All materials and workmanship shall be in accordance with the requirements of
ASME Section V.
2. Examiners performing specific NDE procedures should be trained and qualified
in the applicable procedures in which the examiner is involved as follows:
a. Workers to be qualified to ASNT level 2 or equivalent.
b. Other certifications include American Society for Non-Destructive
Testing SNT-TC-1A or American Welding Society Welding Inspection
certification.
3. The magnetizing equipment shall be the alternating current electromagnetic yoke
type and should be prepared in accordance with standard operating procedures.
4. A function check shall be carried out prior to the inspection to ensure the proper
functioning of the inspection system. NOTE the temperature of the pipe and
coupling should be checked to ensure that it is within the detection media
manufacturer's specified temperature limits.
5. Surfaces to be examined shall be clean and free from scale, oil, grease, machining
marks, heavy paint and any other foreign matter that could adversely affect
inspection sensitivity or the interpretation of indications. Cleaning and
preparation of the surfaces shall not be detrimental to the material, the surface
finish or the detection media.
6. The engineering drawing or referencing document shall indicate the criteria by
which components are judged acceptable during MT. Where acceptance criteria
are not otherwise specified the following criteria shall apply:
a. Linear indications – all linear indications, regardless of length, shall be
cause for rejection of the component.
b. Single rounded indications – a single rounded indication greater than
0.030 inches in diameter shall be cause for rejection of the component.
c. Multiple rounded indications - two or more rounded indications each less
than 0.030 inches in diameter but separated by less than 0.030 inches shall
be cause for rejection of the component.
7. Inspection materials shall meet the requirements in ASTM E 1444.
BHN/U.T./MAGNETIC PARTICLE INSPECTION 6
8. The inspection contractor shall ensure that consistency and reproducibility of the
inspection at the required sensitivity level is maintained.
9. Components should be inspected prior to the application of any coatings.
10. Ultrasonic tests are carried out in accordance with relevant standards and OH&S
requirements.
11. The contractor shall depute a qualified and experienced ASNT level III
technician at site for the supervision of work.
12. Inspection areas as well as the general surface area shall be visually assessed for
the extent of corrosion under insulation, obvious irregularities or discontinuities.
13. In the case of any difference or discrepancy between the specifications and the
description in the schedule of quantities, the schedule of quantities shall take
precedence. In the case of any difference or discrepancy between specifications
and sketches, the specifications shall take precedence.
14. Ultrasonic equipment used for inspection of pipeline and coupling shall be
calibrated in accordance with ASME Section V latest edition. The calibration shall
be performed at following intervals:
a. At the beginning of normal inspection.
b. Every time the running of the systems creates uncertainty on its
efficiency.
15. Equipment(s) belonging to the contractor shall be used for one-off spot checks or
grid checks over areas where an indication was observed.
16. The equipment shall be fitted with a paint spray or automatic marking system
for areas giving ultrasonic or MT indications.
17. Where it is observed that the Ultrasonic data collected is considered erroneous,
the Contractor shall be required to redo same at no cost to the Owner.
18. The contractor shall submit the inspection/test reports in duplicate indicating
summary of recommendations including the condition of old/existing coating.
19. The work site MUST be maintained in a clean and orderly condition while work
is in progress.
20. The contractor shall be responsible for the removal of all materials (finished
couplant tubes, oil containers, waste cloth, tools etc.) upon completion of
Inspection.
21. Garbage must be taken to the municipal landfill.
22. It will be the responsibility of the contractor to acquaint his employees with
Petrojam’s safety instructions and ensure that they adhere to said instructions.
23. If the contractor needs to arrange over-time hours, he must take this into
consideration when preparing his quotation and schedule. Petrojam Limited
must authorize over-time prior to doing any over-time work.
BHN/U.T./MAGNETIC PARTICLE INSPECTION 7
24. A signed HOT WORK permit shall be issued by the Owner’s representative and
must be received by the contractor prior to the commencement of any hot
working procedure.
25. All contractors’ employees shall be issued identification badges by Petrojam
Limited. All contractors and contractors’ employees must have their
identification badges attached to their outer garment in a prominent position, so
that they can be easily identified.
26. Sanitary conveniences are available at the Owner’s premises. The contractor will
make his own arrangements on site for drinking water for his workers.
27. The contractor will make his own arrangements for meals for his workers.
Canteen facilities are available on the Owner’s premises on weekdays between
the hours 7:30 a.m. and 1:00 p.m.
28. The contractor may use the Owner’s portable drinking water and firewater, but
connections will be done by him with the Owner’s approval.
3. SPECIFICATIONS
The following Specifications, Codes and Standards form a part of this document to the
extent specified herein. All documents listed are assumed to be the current revision
unless a specific revision is listed. In the case of conflict between this specification and
the technical requirements cited in other referenced documents, the requirements of this
document take precedence.
1. ASME Section V- Non-Destructive Examination
2. ASTM E 1444 Standard Practice for Magnetic Particle Inspection.
3. SNT-TC-1A Personnel Qualification and Certification in Non-Destructive Testing
4. Pressure vessels – National Board Inspectors Code (NBIC)
5. API 510- Pressure Vessel Inspection Code: In-Service Inspection, Rating, Repair
and Alteration.
6. API- RP 572.
Surface Preparation
Pipe and Coupling Surface
1. All materials, workmanship, and surface preparation shall be in accordance with
the requirements of the SSPC and ASME Section V.
2. Pipe line surface preparation and painting shall meet the requirements of the
following standard
BHN/U.T./MAGNETIC PARTICLE INSPECTION 8
• SSPC – SP 2 – Surface Preparation Specification for Hand Tool Cleaning
3. Inspection areas shall be cleaned and prepared for testing using appropriate
procedures and materials.
4. Preparation processes are carried out in accordance with the relevant Petrojam’s
procedures and OH&S requirements.
5. Petrojam’s Mechanical Engineer or Refinery Inspector will inspect the cleaned
surface areas before the thickness survey commence.
4. MATERIALS AND EQUIPMENT
Owner Supplied
• Fire water
• Scaffolding
Contractor Supplied
All materials and equipment not listed as Owner Supplied to include but not limited to
the following:
• Magnetizing particles
• Alternating current electromagnetic yokes
• Ultrasonic Thickness gauge with through-paint.
• Half round File
• Wire brush
• Grinder, grinding discs and other hand tools
• Couplant
• Measuring Tape
• Pit Gauge
• Safety equipment for all his workmen
• Transportation
BHN/U.T./MAGNETIC PARTICLE INSPECTION 9
5. NOTES
1. The work on the pipeline will be done while the Process Unit is shut-down.
2. The work site must be maintained in a clean, tidy and orderly condition during
the Ultrasonic Inspection process.
3. After completion of the inspection, the work site must be left free from debris
and clean.
4. The contractor will be totally responsible, at all times, for the safety and
warehousing of his equipment, materials and any of the Owner’s materials
entrusted to him.
5. Petrojam Limited will not be held liable for loss or theft of any equipment and/or
materials suffered by the contractor.
6. At the end of the project, the contractor MUST clean the work site to the
satisfaction of Petrojam’s Project Engineer.
7. The workforce shall be comprised of skilled workmen, capable of conducting
work related activities under minimum supervision.