road (0.15 ha) creek crossing (0.56 ha)...reference: google earth, 05-02-2016. wheal ellen site...
TRANSCRIPT
Wheal EllenCree
k
Z
Job No: 52798
Client: Department of Lands
Version:
Drawn By: BC
Date: 08-Jun-2017
Checked By: RD
Scale
Coor. Sys. GDA 1994 MGA Zone 50
FIGURE: 4
0 30 60
metres
Lot 1146
Temporary TSF Site (6100m²)
Sediment Pond (300m²)
Topsoil Stockpile (800m²)
Proposed Contractors Site Office &Facilities
Extent of Works
Existing Site Access Road
Proposed Site Access & Haul Road(1500m²)
Ephemeral Watercourse (ApproximateAlignment)
File Name: 52798_04Reference: Google Earth, 05-02-2016.
Wheal Ellen SiteNorthampton, WA
Northampton Temporary StockpileFacility – Summary Report
TSF FEATURES
1:3,000
Legend:
DRAGE STREET
Note: All locations indicated are approximate.
AC
CE
SS
RO
AD
FROM
DRAG
ESTR
EET
PROPOSED STREAM CROSSING
PROPOSED CLEARING AREAS
TEMPORARY TSF (0.56 Ha)
PROPOSED HAUL ROAD (0.15 Ha)
CONTRACTORS SITE OFFICE
AREA (0.13 Ha)
PROPOSED CREEK CROSSING
EXISTING FEATURES AT WHEAL ELLEN SITE THAT MAY IMPACT ON CONSTRUCTION OF THE
TEMPORARY TSF
EXISTING SHAFT ADJACENT TO EXISTING ACCESS TRACK
EXISTING DEEP EROSION GULLIES CLOSE TO SITE ENTRANCE
EXISTING ACCESS TRACK
EXISTING SHAFT
TEMPORARY TSF
1
Ludwig, Sheri-lynn
From: Weighell, Simon <[email protected]>
Sent: Monday, 27 March 2017 11:42 AM
To: Ludwig, Sheri-lynn
Cc: Wong, Grace; Bramwell, Emma
Subject: RE: Clearing enquiry - Northampton Lead Tailings Project
Follow Up Flag: Follow up
Flag Status: Flagged
Hi Sheri-lynn
It appears that the only clearing exemption that may be available in this case is regulation 5, item 1 of the
Environmental Protection (Clearing of Native Vegetation) Regulations 2004. An excerpt for this exemption from our
guide to the exemptions is included below.
Key things to note are:
• The exemption doesn’t allow clearing of riparian vegetation and based on the map and photos supplied
there is a watercourse running through the property with riparian vegetation present
• The comment/explanation box below provides guidance regarding what a building is in relation to a
transportable building
• An engineered containment cell is likely to be considered a structure
Any other general earthworks across the site are unlikely to be exempt.
After consideration of the above, if there is any clearing unlikely to be exempt you should include this in the works
approval/licence application form (provide a clear map of the area, size, purpose of clearing etc.).
Once received, the Industry Regulation section of DER will refer the clearing component to us (Clearing Regulation)
and we will assess and provide a recommendation back to Industry Regulation for the final decision (if everything
was proposed to be approved you would be granted a works approval/licence with conditions allowing the clearing
of native vegetation).
Let me know if you have any further questions.
Regards
Simon
Simon Weighell
Senior Clearing Regulation Officer
Department of Environment Regulation
Ph 9333 7492 | [email protected]
2
The linked image cannot be displayed. The file may have been moved, renamed, or deleted. Verify that the link points to the correct file and location.
The linked image cannot be displayed. The file may have been moved, renamed, or deleted. Verify that the link points to the correct file and location.
This email, together with any attachments, is intended for the addressee only. It may contain confidential or
privileged information. If you are not the intended recipient of this email, please notify the sender, delete the email
and attachments from your system and destroy any copies you may have taken of the email and its attachments.
Duplication or further distribution by hardcopy, by electronic means or verbally is not permitted without permission.
From: Ludwig, Sheri-lynn [mailto:[email protected]]
Sent: Thursday, 23 March 2017 10:32 AM
To: NVP
Subject: Clearing enquiry - Northampton Lead Tailings Project
Hello,
The next phase of the Northampton Lead Tailings Project (NLTP Phase 2 Part A) will include the removal of lead
tailings and tailings impacted soil from a number of residential properties within the townsite of Northampton, WA.
All tailings removed from the townsite will be temporarily placed in stockpiles at the former Wheal Ellen minesite
(Reserve 52194, Lot 1146 on DP 321889), located off Drage Road (please refer to Attached site figures and photos).
The stockpiled material will be placed within a temporary Category 62 disposal facility in accordance with a technical
specification. To establish this facility, some infrastructure will be established at the site (site office, amenities,
3
bunded stockpiling pad and associated infrastructure). Final disposal of all tailings waste will be in an engineered
containment cell (Category 65), which will require establishment of more infrastructure and significant earthworks.
A site selection study completed in 2015, identified the Wheal Ellen site as the most suitable site for the
containment cell to contain all tailings generated from the NLTP remedial works. A large portion of the site is already
disturbed from historical mining activities, with large stockpiles of unmanaged tailings and abandoned
infrastructure. It is proposed that the temporary stockpiling facility is situated in an already disturbed area of the
site. Any clearing of native vegetation will be well under 5 hectares.
The vegetation in the less or non-disturbed areas of the site is sparse and intact, but not interconnected. The 2015
site selection study included a desktop review and some site investigation which identified several National and
State flora and fauna receptors were present on the site (no EPBC threatened species). Further flora and fauna
environmental surveys required, and at this stage it is proposed that these surveys will take place prior to temporary
stockpiling works.
Given the above information, we are seeking clarification as to whether the temporary stockpiling works may fall
under a limited clearing exemption (infrastructure)? Also, can you please advise on next steps – particularly with
respect to the DER Licensing Works approval and Licence application for the Category 62 temporary stockpiling
facility. We are planning on submitting a concurrent application but we are not sure whether the application should
include a clearing permit.
Please do not hesitate to contact me if you have any queries or require any further information.
Kind Regards, Sheri-lynn Ludwig | Project Manager, Northampton Lead Tailings Project | LAMS Department of Lands | Level 2, 140 William Street | Perth, WA 6000 T 08 6552 4442 | F (08) 6552 4417 | M 0472 872 051 E [email protected] | W www.lands.wa.gov.au
The linked image cannot be displayed. The file may have been moved, renamed, or deleted. Verify that the link points to the correct file and location.
The Department of Lands has a new Post Office Box. PO Box 1221 West Perth WA 6872. Please update your records accordingly. Thank you DISCLAIMER: The information contained in this email (including attachments) is intended only for the use of the person(s) to whom it is addressed as it may be confidential and contain legally privileged information. If you are not the intended recipient you are hereby notified that any perusal, use, distribution, copying or disclosure is strictly prohibited. If you have received this email in error, please immediately advise us by return email and delete the email document. This email and any attachments to it are also subject to copyright and any unauthorised reproduction, adaptation or transmission is prohibited. This notice should not be removed.
1
Ludwig, Sheri-lynn
From: ORMSBY, Warren <[email protected]>
Sent: Monday, 18 May 2015 3:39 PM
To: Cramer, Jonathan; MORRIS, Paul
Cc: Ruther, Eduardo; HALL, Charlotte
Subject: RE: Proposed Containment Cell Location - NLTP
Attachments: Wheal Ellen_V1.pdf; Wheal Ellen_Xsection.pdf
Hi Jon,
My group has had a good look at the Wheal Ellen option with a view to finding out whether the remediation of the
existing tailings and addition of other material at the same site would be an issue for any future exploration or
mining at the site – refer to the attached map and cross section.
We did not know about and have not assessed the ‘Commonage’ site.
We also understand that the Wheal Ellen site needs remedial work, thus preference for this site rather than a new
one elsewhere that could require relocation of these tailings.
For example, the southern and easternmost parts of adjoining reserve R7671 and all of R263 is well away from the
previous mining and there would be no issues in locating tailings in these areas from an exploration/mining
perspective.
We found that if in the future mining was to resume at Wheal Ellen, that it would most likely be underground due to
the nature of the mineralization and the near-surface mining that has already taken place. Provided the tailings do
not backfill the existing underground workings, these could be accessible for re-opening. We also considered likely
drilling locations for future deeper exploration beneath the existing workings. From this we found that any deeper
drill holes are most likely to be sited further to the west of the existing tailings area.
So our finding was that we would have no serious exploration/mining access issues with continuing to use the
existing tailings site at Wheal Ellen provided the existing workings are not backfilled or in jeopardy and the area
occupied is not substantially larger than the existing tailings footprint..
However, we note that this area (and probably the ‘Commonage’ site as well) now lies within a current exploration
licence (E66/87), held by Buxton Resources Ltd.
We recommend consultation with the exploration licence holder before proceeding.
Regards,
Warren Ormsby | Manager Land Use Geoscience | Resources, Geological Survey
Department of Mines and Petroleum
Tel: +61 8 9222 3571 | Mob: 0457 780 869 | [email protected]
www.dmp.wa.gov.au
From: Cramer, Jonathan [mailto:[email protected]]
Sent: Monday, 18 May 2015 2:31 PM
To: MORRIS, Paul; ORMSBY, Warren Cc: Ruther, Eduardo
Subject: RE: Proposed Containment Cell Location - NLTP
Hi Paul and Warren,
2
Im just chasing up whether there has been any formal assessment of the below request and what DMP’s
recommendations/ findings may be on this matter?
Just so you are aware, DoL has recently put out a tender to have a site suitability assessment and a preliminary
design with costs estimations for the containment cell undertaken by engineering consultants focusing on two
preferred sites in Northampton; one being the Wheal Ellen Site and the other being a large unmanaged reserve to
the west of the town known as the Commonage site. Both house tailings. The tender has not been awarded yet.
Obviously any information that DMP can provide as part of the below assessment will form an important piece of
information (possibly identify show stoppers) regarding the suitability of the Wheal Ellen site for building a
containment cell.
Kind regards,
Jon
Jonathan Cramer | Manager | Contaminated Sites Department of Lands | Level 2, 140 William Street | Perth WA 6000 T (08) 6552 4684 | F (08) 6552 4417 | M 0477 301 906 E [email protected] | W www.lands.wa.gov.au
DISCLAIMER: The information contained in this email (including attachments) is intended only for the use of the person(s) to whom it is addressed as it may be confidential and contain legally privileged information. If you are not the intended recipient you are hereby notified that any perusal, use, distribution, copying or disclosure is strictly prohibited. If you have received this email in error, please immediately advise us by return email and delete the email document. This email and any attachments to it are also subject to copyright and any unauthorised reproduction, adaptation or transmission is prohibited. This notice should not be removed.
From: MORRIS, Paul [mailto:[email protected]]
Sent: Thursday, 9 April 2015 7:28 AM To: ORMSBY, Warren; FLINT, Don
Cc: Cramer, Jonathan; Cramer, Jonathan; ROGERSON, Rick; TYLER, Ian; GRIFFIN, Tim Subject: FW: Proposed Containment Cell Location - NLTP
Hi Warren
As you may know, the assessment phase of the Northampton lead tailings investigation (NLTI) has been completed,
and subsequent phases involving remediation of affected properties is being planned. A part of this is the
construction of a containment cell for tailings removed from the townsite. At a recent meeting of the NLTI
committee, there was some discussion about the location of the cell, and the site of former mining in the area
(Wheal Ellen) was suggested. I commented that before any decision was made on any location of the cell, DMP (and
more specifically, GSWA) should be contacted to ensure that any cell location did not effectively sterilize an area
with mineralization potential: I have, therefore, forwarded Jon Cramer’s email (below) to you for comment.
Thanks
Paul
Paul Morris | Chief Geochemist | Geoscience Mapping, Geological Survey
3
Department of Mines and Petroleum
Tel: +61 8 9222 3345 | [email protected]
www.dmp.wa.gov.au
From: Cramer, Jonathan [mailto:[email protected]] Sent: Wednesday, 8 April 2015 4:50 PM
To: MORRIS, Paul
Subject: Proposed Containment Cell Location - NLTP
Hi Paul,
I picked up on a comment made by you and reported in the latest NLTP steering committee minutes (which I wasn’t
able to attend) regarding the need to speak with DMP about the proposed location of the containment cell to
determine if there was a desire from DMP to keep that area unencumbered for future resource deposit
opportunities.
The preferred site to be investigated is the former mine site Wheal Ellen. Ive attached a map and some
photos. There are several open shafts on the site that appear to follow a linear formation suggesting they were
targeting/following a seam running through the site.
Can you please let me know how you would like to work through this “approval” or whatever format it may be
required to be Ok’d by DMP?
Thanks mate,
Jon
Jonathan Cramer | Manager | Contaminated Sites Department of Lands | Level 2, 140 William Street | Perth WA 6000 T (08) 6552 4684 | F (08) 6552 4417 | M 0477 301 906 E [email protected] | W www.lands.wa.gov.au
DISCLAIMER: The information contained in this email (including attachments) is intended only for the use of the person(s) to whom it is addressed as it may be confidential and contain legally privileged information. If you are not the intended recipient you are hereby notified that any perusal, use, distribution, copying or disclosure is strictly prohibited. If you have received this email in error, please immediately advise us by return email and delete the email document. This email and any attachments to it are also subject to copyright and any unauthorised reproduction, adaptation or transmission is prohibited. This notice should not be removed.
1
Ludwig, Sheri-lynn
From: LAURITSEN Natalie <[email protected]>
Sent: Monday, 15 May 2017 4:04 PM
To: Ludwig, Sheri-lynn
Subject: RE: Northampton Lead Tailings Project - Bed and Banks
Attachments: Access road and stream crossing 20170510.pdf
Hi Sheri-lynn,
The Bowes River and its tributaries occur in the Northampton area and would be the systems that may be affected
by the Northampton Lead Tailings Project. The Bowes River is not a proclaimed surface water area under the Rights
in Water and Irrigation Act 1914, so I can confirm no permit is required for any of the works you have
described. The only circumstance when a permit may be needed is if a person wanted to take water from the river
or tributaries.
DoW does support appropriately engineered design for alterations of bed or banks, and the use of best
management practices when working in or around watercourses, and can provide advice in these areas if required.
Kind regards, Natalie
Natalie Lauritsen
Natural Resource Management Officer
Midwest Gascoyne Region Ph: 9965 7418 l Fax: 9964 5983
94 Sanford St, Geraldton l PO Box 73, Geraldton WA 6531
Work days: Monday to Thursday
From: Ludwig, Sheri-lynn [mailto:[email protected]]
Sent: Monday, 15 May 2017 2:52 PM
To: LAURITSEN Natalie <[email protected]>
Subject: Northampton Lead Tailings Project - Bed and Banks
Hi Natalie,
Thank you for speaking with me today regarding the Northampton Lead Tailings Project (NLTP). As we discussed, we
are currently in the planning stages for Phase 2 of the project which will consist of the remediation and
management of lead tailings and impacted soil on residential properties within the townsite of Northampton. All
tailings and impacted soil removed from the townsite will be transported to the former Wheal Ellen mine site, which
is located at Lot 1146 on Deposited Plan 231889. The site is a now Reserve for Government Purposes
(Reserve 52194). Initially all tailings material will be stockpiled into a temporary tailings storage facility until final
disposal in an engineered containment cell. It is proposed that the temporary tailings storage facility will be situated
within the same footprint as the final containment cell, which will be located in the south-east portion of the site. In
order to access this area, we will require a crossing across an ephemeral creek line which runs east-west through the
site. A culvert is proposed at the approximate location as shown on the attached Figure 1.
As we discussed, given the level of disturbance proposed and as the site is not located in a proclaimed surface water
area, can you confirm that a Permit to Interfere with Bed and Banks is not required in this scenario?
2
Additionally, there are a couple of the townsite properties which require remediation where tailings and tailings
impacted material are present in the adjacent creek bed/drainage lines and surrounding banks. The remedial
Contractor will need to disturb the bed and banks in order to excavate the tailings and tailings impacted material at
these locations. Can you advise if a Permit to Interfere with Bed and Banks is required for this scenario?
Thank you very much for your assistance. Please do not hesitate to contact me with any queries or if you require
further information.
Kind Regards, Sheri-lynn Ludwig | Project Manager, Northampton Lead Tailings Project | LAMS Department of Lands | Level 2, 140 William Street | Perth, WA 6000 T 08 6552 4442 | F (08) 6552 4417 | M 0472 872 051 E [email protected] | W www.lands.wa.gov.au
The Department of Lands has a new Post Office Box. PO Box 1221 West Perth WA 6872. Please update your records accordingly. Thank you DISCLAIMER: The information contained in this email (including attachments) is intended only for the use of the person(s) to whom it is addressed as it may be confidential and contain legally privileged information. If you are not the intended recipient you are hereby notified that any perusal, use, distribution, copying or disclosure is strictly prohibited. If you have received this email in error, please immediately advise us by return email and delete the email document. This email and any attachments to it are also subject to copyright and any unauthorised reproduction, adaptation or transmission is prohibited. This notice should not be removed.
Disclaimer: This e-mail is confidential to the addressee and is the view of the writer, not necessarily that of the Department of Water, which accepts no responsibility for the contents. If you are not the addressee, please notify the Department by return e-mail and delete the message from your system; you must not disclose or use the information contained in this email in any way. No warranty is made that this material is free from computer viruses.