quality assurance plan & p a r t n e r s, p l l c

1
S002 QUALITY ASSURANCE PLAN QUALITY ASSURANCE PLAN GENERAL ------- This Structural Quality Assurance Plan identifies the responsibilities of the Contractor and the Special Inspector in performing the testing and inspection of the work required by Chapter 17 of the Building Code that is within the scope of the structural engineering services for this project. Refer to other portions of the Construction Documents for testing and inspections required of architectural, mechanical, electrical, or other building components. CONTRACTOR RESPONSIBILITIES --------------------------- The Structural Testing/Inspection Agency that is to act as the Special Inspector will be hired by the Owner. Contractor shall pay for any additional structural testing/inspection required for work or materials not complying with the Construction Documents due to negligence or nonconformance and shall pay for any additional structural testing/inspection required for his convenience. Contractor is responsible to ensure that the Special Inspector is present for all work requiring special inspection. Any work that requires special inspection and is performed without the Special Inspector being present is subject to being demolished and reconstructed. Contractor has the following responsibilities to the Special Inspector: 1. Provide copy of Construction Documents to the Special Inspector. 2. Notify the Special Inspector sufficiently in advance of operations to allow assignment of personnel and scheduling of tests. 3. Cooperate with Special Inspector and provide access to work. 4. Provide samples of materials to be tested in required quantities. 5. Provide storage space for the Special Inspector’s exclusive use, such as for storing and curing concrete testing samples. 6. Provide labor to assist the Special Inspector in performing tests/inspections. SPECIAL INSPECTOR RESPONSIBILITIES ---------------------------------- Special Inspector shall maintain records of inspections in accordance with Chapter 17 of the Building Code and shall distribute these records to the Building Official, Architect, and Structural Engineer on a weekly basis. At the conclusion of the project the Special Inspector shall submit a written statement that the special inspections during construction have complied with this Structural Quality Assurance Plan and that any discrepancies noted during construction have been corrected. DRILLED PIERS ------------- Special Inspector shall perform the following: 1. Monitor the load test. 2. Record elevation of initial contact with sandstone. 3. Verify drilled piers bearing surface. Record bearing elevation and pier socket length in sandstone. 4. Inspect reinforcing steel and concrete placement. SOILS ----- Special Inspector shall perform the following: 1. Verify structural fill complies with specifications and the project geotechnical report. 2. Observe proofrolling. 3. Perform field density tests to verify compaction of structural fill. As a minimum, perform one test per lift for every 1500 square feet of fill placed. 4. Verify foundation bearing capacity where applicable. CAST-IN-PLACE CONCRETE ---------------------- Contractor shall perform the following: 1. Submit manufacturer’s data for tensile and compressive splicers. 2. Establish concrete mix design proportions per ACI 318, Chapter 5. Submit three copies of the concrete mix designs. Include the following: a. Type and quantities of materials b. Slump c. Air content d. Fresh unit weight e. Aggregates sieve analysis f. Design compressive strength g. Location of placement in structure h. Method of placement i. Method of curing j. Seven-day and 28-day compressive strengths 3. Submit a certification from each manufacturer or supplier stating that materials meet the requirements of the specified ASTM and ACI standards. 4. Submit certification that the ready-mixed concrete plant complies with the requirements of the National Ready Mix Concrete Association. Special Inspector shall perform the following: 1. Verify grade, quantity, location, and placement of reinforcing steel prior to concrete placement. 2. Examine concrete in truck to verify that concrete appears properly mixed. 3. Perform a slump test as deemed necessary for each concrete load. Record if water or admixtures are added to the concrete at the job site. Perform additional slump tests after job site adjustments. 4. Mold four specimens per set for compressive strength testing; one set for each 75 cubic yards of each mix design placed in any one day. For each set molded, record: a. Slump b. Air content c. Unit weight d. Temperature, ambient and concrete e. Location of placement f. Any pertinent information, such as addition of water, addition of admixtures, etc. Perform one 7-day and two 28-day compressive strength tests. (Use one as a spare to be broken as directed by the Structural Engineer if compressive strengths do not appear adequate) 5. Reports of compressive strength tests shall contain the project identification name and number, date of concrete placement, name of concrete testing agency, concrete design compressive strength, location of concrete placement in structure, concrete mix proportions and materials, compressive breaking strength and type of break. STRUCTURAL PRECAST CONCRETE --------------------------- Contractor shall perform the following: 1. Submit certification that the fabricator is registered and approved by the Building Official to perform required work without special inspections. 2. If fabricator is not registered and approved, special inspection of the fabricated items shall be required. Special Inspector shall verify that the fabricator maintains detailed fabrication and quality control procedures that provide a basis for inspection control of the workmanship and the fabricator’s ability to conform to approved construction documents and referenced standards. Special Inspector shall review the procedures for completeness and adequacy relative to the code requirements for the fabricator’s scope of work. 3. Submit a certification from each manufacturer or supplier stating that materials meet the requirements of the specified ASTM and ACI standards. 4. Submit concrete mix designs and concrete test reports. Special Inspector shall perform the following: 1. Verify precast member bearing dimensions, bearings strips, and locations. 2. Verify that precast connections are in accordance with the approved precast shop drawings. 3. Verify placement of reinforcing steel and anchors where indicated on the drawings. 4. Verify placement of grout as indicated on the precast shop drawings. 5. Verify location of slab penetrations with approved shop drawings. Field modifications or penetrations through precast members shall not be permitted unless indicated on the shop drawings or approved in writing from the precast manufacturer and the Architect/Structural Engineer. ARCHITECTURAL PRECAST CONCRETE ------------------------------ Contractor shall perform the following: 1. Submit certification that the fabricator is registered and approved by the Building Official to perform required work without special inspections. 2. If fabricator is not registered and approved, special inspection of the fabricated items shall be required. Special Inspector shall verify that the fabricator maintains detailed fabrication and quality control procedures that provide a basis for inspection control of the workmanship and the fabricator’s ability to conform to approved construction documents and referenced standards. Special Inspector shall review the procedures for completeness and adequacy relative to the code requirements for the fabricator’s scope of work. 3. Submit a certification from each manufacturer or supplier stating that materials meet the requirements of the specified ASTM and ACI standards. 4. Submit concrete mix designs and concrete test reports. Special Inspector shall perform the following: 1. Verify that precast member bearing locations and details are in accordance with the precast shop drawings and consistent with the information shown on the structural drawings. 2. Verify placement of reinforcing steel, anchors and embeds where indicated on the precast shop drawings. BARRIER CABLES -------------- Special Inspector shall perform the following: 1. Verify tendon quantity, location and support. 2. Verify placement and location of tendon anchors. 3. Verify tendon stressing. 4. Stressing records shall be filled out during the tensioning operation and shall contain the following data: a. Floor number. b. Tendon mark or identification. c. Required elongation maximum and minimum. d. Gage pressure to achieve required elongation. e. Actual gage pressure. f. Actual elongation achieved. g. Date of stressing operation. h. Name and signature of the stressing operator or inspector. i. Serial or identification number of jacking equipment. j. Date of approved shop drawings used for installation and stressing. NON-SHRINK GROUT ---------------- Special Inspector shall perform the following: 1. Compressive strength tests per ASTM C109. 2. Number of Tests: One test for each ten bags of grout used or minimum of one test for each day of grouting. 3. Cube Size: 2-inch x 2-inch 4. Test Schedule: One cube at 3 days, two cubes at 7 days, three cubes at 28 days. CONCRETE MASONRY ---------------- Contractor shall perform the following: 1. Submit a certification from each manufacturer or supplier stating that the following materials comply with the specified ASTM or ACI Standands: a. Concrete masonry units. b. Mortar materials: Portland cement, hydrated lime, and aggregates. c. Grout materials: Portland cement and aggregates. d. Joint reinforcement steel. e. Reinforcing steel. Special Inspector shall perform the following: 1. Verify compressive strength of concrete masonry units, mortar, and coarse grout for every 5,000 sq. ft. of surface area as follows: a. Three (3) concrete masonry units shall be tested in accordance with ASTM C140. b. Six (6) mortar cube specimens shall be tested, three (3) at 7-days and three (3) at 28-days, in accordance with ASTM C109. c. Four (4) coarse grout specimens shall be tested, two (2) at 7-days and two (2) at 28-days, in accordance with ASTM C1019. d. In lieu of individual tests of masonry units, mortar, and grout, perform one (1) prism test (which consists of three prisms) in accordance with ASTM E447. 2. Provide continuous inspection to verify compliance of the following: a. Cleanliness of grout space prior to grouting. b. Placement of grout in reinforced cells. c. Preparation of required grout and mortar specimens. 3. Provide periodic inspection to verify compliance of the following: a. Proportions of site-prepared mortar or grout. b. Construction of mortar joints. c. Quantity, size, location, and support of reinforcing steel. d. Quantity, size, and placement of horizontal joint reinforcement. e. Protection of masonry during cold or hot weather. f. Type, size and location of anchors. T H O M A S, M I L L E R & P A R T N E R S, P L L C A R C H I T E C T U R E I N T E R I O R D E S I G N P L A N N I N G 5 2 1 0 M A R Y L A N D W A Y S U I T E 2 0 0 B R E N T W O O D , T N 3 7 0 2 7 - 5 0 0 8 P H O N E 6 1 5 3 7 7 - 9 7 7 3 F A X 6 1 5 3 7 0 - 4 1 4 7 W W W . T M P A R T N E R S . C O M DATE: JOB NO.: DR. BY: CK BY: REVISIONS: COPYRIGHT ' THOMAS, MILLER & PARTNERS PLLC, ALL RIGHTS RESERVED. UNAUTHORIZED COPYING, SCANNING, PRINTING OR DISTRIBUTION IS PROHIBITED. 2008 P. MURRAY 220 Great Circle Road, Suite 106 Nashville, Tennessee 37228 615.255.5537 615.255.1486 p. f. Structural Design Group SDG Project No. 2008-186.00 2008 GILLETTE, WYOMING CAMPBELL COUNTY MEMORIAL HOSPITAL PARKING GARAGE STRUCTURAL DESIGN GROUP 16-DEC-2008 13:32 davids S:\Sdg-dgn\Projects\2008\2008-186\cad\cad-g CHECKSET - NOT FOR CONSTRUCTION - 12-16-2008

Upload: others

Post on 13-Nov-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

S002

QU

AL

ITY

AS

SU

RA

NC

E P

LA

N

QUALITY ASSURANCE PLAN

GENERAL

-------

This Structural Quality Assurance Plan identifies the responsibilities of the

Contractor and the Special Inspector in performing the testing and inspection

of the work required by Chapter 17 of the Building Code that is within the

scope of the structural engineering services for this project. Refer to other

portions of the Construction Documents for testing and inspections required of

architectural, mechanical, electrical, or other building components.

CONTRACTOR RESPONSIBILITIES

---------------------------

The Structural Testing/Inspection Agency that is to act as the Special Inspector

will be hired by the Owner.

Contractor shall pay for any additional structural testing/inspection required

for work or materials not complying with the Construction Documents due to

negligence or nonconformance and shall pay for any additional structural

testing/inspection required for his convenience.

Contractor is responsible to ensure that the Special Inspector is present for

all work requiring special inspection. Any work that requires special inspection

and is performed without the Special Inspector being present is subject to being

demolished and reconstructed.

Contractor has the following responsibilities to the Special Inspector:

1. Provide copy of Construction Documents to the Special Inspector.

2. Notify the Special Inspector sufficiently in advance of operations to allow

assignment of personnel and scheduling of tests.

3. Cooperate with Special Inspector and provide access to work.

4. Provide samples of materials to be tested in required quantities.

5. Provide storage space for the Special Inspector’s exclusive use, such as for

storing and curing concrete testing samples.

6. Provide labor to assist the Special Inspector in performing tests/inspections.

SPECIAL INSPECTOR RESPONSIBILITIES

----------------------------------

Special Inspector shall maintain records of inspections in accordance with

Chapter 17 of the Building Code and shall distribute these records to the

Building Official, Architect, and Structural Engineer on a weekly basis. At the

conclusion of the project the Special Inspector shall submit a written statement

that the special inspections during construction have complied with this

Structural Quality Assurance Plan and that any discrepancies noted during

construction have been corrected.

DRILLED PIERS

-------------

Special Inspector shall perform the following:

1. Monitor the load test.

2. Record elevation of initial contact with sandstone.

3. Verify drilled piers bearing surface. Record bearing elevation and pier

socket length in sandstone.

4. Inspect reinforcing steel and concrete placement.

SOILS

-----

Special Inspector shall perform the following:

1. Verify structural fill complies with specifications and the project

geotechnical report.

2. Observe proofrolling.

3. Perform field density tests to verify compaction of structural fill. As a

minimum, perform one test per lift for every 1500 square feet of fill placed.

4. Verify foundation bearing capacity where applicable.

CAST-IN-PLACE CONCRETE

----------------------

Contractor shall perform the following:

1. Submit manufacturer’s data for tensile and compressive splicers.

2. Establish concrete mix design proportions per ACI 318, Chapter 5. Submit

three copies of the concrete mix designs. Include the following:

a. Type and quantities of materials

b. Slump

c. Air content

d. Fresh unit weight

e. Aggregates sieve analysis

f. Design compressive strength

g. Location of placement in structure

h. Method of placement

i. Method of curing

j. Seven-day and 28-day compressive strengths

3. Submit a certification from each manufacturer or supplier stating that

materials meet the requirements of the specified ASTM and ACI standards.

4. Submit certification that the ready-mixed concrete plant complies with the

requirements of the National Ready Mix Concrete Association.

Special Inspector shall perform the following:

1. Verify grade, quantity, location, and placement of reinforcing steel prior

to concrete placement.

2. Examine concrete in truck to verify that concrete appears properly mixed.

3. Perform a slump test as deemed necessary for each concrete load. Record if

water or admixtures are added to the concrete at the job site. Perform

additional slump tests after job site adjustments.

4. Mold four specimens per set for compressive strength testing; one set for

each 75 cubic yards of each mix design placed in any one day. For each set

molded, record:

a. Slump

b. Air content

c. Unit weight

d. Temperature, ambient and concrete

e. Location of placement

f. Any pertinent information, such as addition of water, addition of

admixtures, etc.

Perform one 7-day and two 28-day compressive strength tests. (Use one as a

spare to be broken as directed by the Structural Engineer if compressive

strengths do not appear adequate)

5. Reports of compressive strength tests shall contain the project

identification name and number, date of concrete placement, name of concrete

testing agency, concrete design compressive strength, location of concrete

placement in structure, concrete mix proportions and materials, compressive

breaking strength and type of break.

STRUCTURAL PRECAST CONCRETE

---------------------------

Contractor shall perform the following:

1. Submit certification that the fabricator is registered and approved by the

Building Official to perform required work without special inspections.

2. If fabricator is not registered and approved, special inspection of the

fabricated items shall be required. Special Inspector shall verify

that the fabricator maintains detailed fabrication and quality control

procedures that provide a basis for inspection control of the workmanship

and the fabricator’s ability to conform to approved construction documents

and referenced standards. Special Inspector shall review the procedures

for completeness and adequacy relative to the code requirements for the

fabricator’s scope of work.

3. Submit a certification from each manufacturer or supplier stating that

materials meet the requirements of the specified ASTM and ACI standards.

4. Submit concrete mix designs and concrete test reports.

Special Inspector shall perform the following:

1. Verify precast member bearing dimensions, bearings strips, and locations.

2. Verify that precast connections are in accordance with the approved precast

shop drawings.

3. Verify placement of reinforcing steel and anchors where indicated on the

drawings.

4. Verify placement of grout as indicated on the precast shop drawings.

5. Verify location of slab penetrations with approved shop drawings. Field

modifications or penetrations through precast members shall not be permitted

unless indicated on the shop drawings or approved in writing from the

precast manufacturer and the Architect/Structural Engineer.

ARCHITECTURAL PRECAST CONCRETE

------------------------------

Contractor shall perform the following:

1. Submit certification that the fabricator is registered and approved by the

Building Official to perform required work without special inspections.

2. If fabricator is not registered and approved, special inspection of the

fabricated items shall be required. Special Inspector shall verify

that the fabricator maintains detailed fabrication and quality control

procedures that provide a basis for inspection control of the workmanship

and the fabricator’s ability to conform to approved construction documents

and referenced standards. Special Inspector shall review the procedures

for completeness and adequacy relative to the code requirements for the

fabricator’s scope of work.

3. Submit a certification from each manufacturer or supplier stating that

materials meet the requirements of the specified ASTM and ACI standards.

4. Submit concrete mix designs and concrete test reports.

Special Inspector shall perform the following:

1. Verify that precast member bearing locations and details are in accordance

with the precast shop drawings and consistent with the information shown on

the structural drawings.

2. Verify placement of reinforcing steel, anchors and embeds where indicated on

the precast shop drawings.

BARRIER CABLES

--------------

Special Inspector shall perform the following:

1. Verify tendon quantity, location and support.

2. Verify placement and location of tendon anchors.

3. Verify tendon stressing.

4. Stressing records shall be filled out during the tensioning operation and shall

contain the following data:

a. Floor number.

b. Tendon mark or identification.

c. Required elongation maximum and minimum.

d. Gage pressure to achieve required elongation.

e. Actual gage pressure.

f. Actual elongation achieved.

g. Date of stressing operation.

h. Name and signature of the stressing operator or inspector.

i. Serial or identification number of jacking equipment.

j. Date of approved shop drawings used for installation and stressing.

NON-SHRINK GROUT

----------------

Special Inspector shall perform the following:

1. Compressive strength tests per ASTM C109.

2. Number of Tests: One test for each ten bags of grout used or minimum of one

test for each day of grouting.

3. Cube Size: 2-inch x 2-inch

4. Test Schedule: One cube at 3 days, two cubes at 7 days, three cubes at 28

days.

CONCRETE MASONRY

----------------

Contractor shall perform the following:

1. Submit a certification from each manufacturer or supplier stating that the

following materials comply with the specified ASTM or ACI Standands:

a. Concrete masonry units.

b. Mortar materials: Portland cement, hydrated lime, and aggregates.

c. Grout materials: Portland cement and aggregates.

d. Joint reinforcement steel.

e. Reinforcing steel.

Special Inspector shall perform the following:

1. Verify compressive strength of concrete masonry units, mortar, and coarse

grout for every 5,000 sq. ft. of surface area as follows:

a. Three (3) concrete masonry units shall be tested in accordance with ASTM

C140.

b. Six (6) mortar cube specimens shall be tested, three (3) at 7-days and

three (3) at 28-days, in accordance with ASTM C109.

c. Four (4) coarse grout specimens shall be tested, two (2) at 7-days and two

(2) at 28-days, in accordance with ASTM C1019.

d. In lieu of individual tests of masonry units, mortar, and grout, perform

one (1) prism test (which consists of three prisms) in accordance with

ASTM E447.

2. Provide continuous inspection to verify compliance of the following:

a. Cleanliness of grout space prior to grouting.

b. Placement of grout in reinforced cells.

c. Preparation of required grout and mortar specimens.

3. Provide periodic inspection to verify compliance of the following:

a. Proportions of site-prepared mortar or grout.

b. Construction of mortar joints.

c. Quantity, size, location, and support of reinforcing steel.

d. Quantity, size, and placement of horizontal joint reinforcement.

e. Protection of masonry during cold or hot weather.

f. Type, size and location of anchors.

T H

O

M

A

S

,M

I

L

L

E

R

&

P

A

R

T

N

E

R

S,

P

L

L

C

A R

C H

I T

E C

T U

R E

I N

T E

R I

O R

D

E S

I G

NP

L A

N N

I N

G5

2 1

0

M A

R Y

L A

N D

W

A Y

S

U I

T E

2

0 0

B R

E N

T W

O O

D ,

T

N

3 7

0 2

7 -

5 0

0 8

P H

O N

E 6

1 5

3

7 7

- 9

7 7

3F

A X

6

1 5

3

7 0

- 4

1 4

7W

W W

. T

M P

A R

T N

E R

S .

C O

M

DA

TE

:

JO

B N

O.:

DR

. B

Y:

CK

BY

:

RE

VIS

ION

S:

COPYRIGHT ' THOMAS, MILLER & PARTNERS PLLC, ALL RIGHTS RESERVED. UNAUTHORIZED COPYING, SCANNING, PRINTING OR DISTRIBUTION IS PROHIBITED.2008

P.

MU

RR

AY

ISAIAH 53:5 ISAIAH 53:5

ISAIAH 53:5 ISAIAH 53:5

IS

AIA

H 5

3:5

IS

AIA

H 5

3:5

IS

AIA

H 5

3:5

ISAIAH 53:5

ISA

IAH

53:5

IS

AIA

H 5

3:5

ISAIAH 53:5

ISAIAH 53:5

IS

AIA

H 5

3:5

IS

AIA

H 5

3:5

22

0 G

reat

Cir

cle

Ro

ad

, S

uit

e 1

06

Nash

vil

le,

Ten

nessee 3

72

28

61

5.2

55

.55

37

615.2

55.1

486

p.

f.

Str

uctu

ral

Desi

gn

Gro

up

SD

G P

roje

ct

No. 2008-186.0

0

� 2

00

8G

ILL

ET

TE

, W

YO

MIN

G

CA

MP

BE

LL

CO

UN

TY

ME

MO

RIA

L H

OS

PIT

AL

PA

RK

ING

GA

RA

GE

ST

RU

CT

UR

AL

DE

SIG

N G

RO

UP

16

-D

EC

-2

00

8 1

3:3

2

davids

S:\S

dg

-d

gn

\P

ro

jects\2

00

8\2

00

8-1

86

\cad

\cad

-g

CH

EC

KS

ET

- N

OT

F

OR

C

ON

ST

RU

CT

IO

N - 12-16-2008