PUBLIC SAFETY BUILDING FINDINGS MEETING. August 7, 2014. History What H as C hanged? Introduction of Committees Introduction of MOCA. Background. Community Involvement Site Selection Programming Project Definition Systems Approach to Cost Model. Process. Community Involvement. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: PUBLIC SAFETY BUILDING FINDINGS MEETING

PUBLIC SAFETY BUILDING FINDINGS MEETING

August 7, 2014

Page 2: PUBLIC SAFETY BUILDING FINDINGS MEETING

Background

HistoryWhat Has Changed?

Introduction of CommitteesIntroduction of MOCA

Page 3: PUBLIC SAFETY BUILDING FINDINGS MEETING
Page 4: PUBLIC SAFETY BUILDING FINDINGS MEETING

Process

Community InvolvementSite SelectionProgramming

Project DefinitionSystems Approach to Cost Model

Page 5: PUBLIC SAFETY BUILDING FINDINGS MEETING

Community Involvement

Page 6: PUBLIC SAFETY BUILDING FINDINGS MEETING

Community Involvement

Cost 83 20.85%Location 53 13.32%Designed for Future Growth 22 5.53%Building Function / Efficiency 19 4.77%Safety 18 4.52%Design Appealing / Fit Local Architecture 16 4.02%Bonding / Funding / Budget 16 4.02%Appropriately Designed 15Durable Building - Last Long Time 14No Tax Increase 13Size ? 12Build in Seqt'l Phases 11Community Involvement (pavers-tile)(vote) 11Build to City's needs (Fire, PD, Court) 11Support / Build-it / Get it Done 8Renovate Current City Owned Prop. 6Build w/o Bonds 6Need? 6Quality Design 5Build it Right 5City / Community Pride 4Current Building Works 3Public Informed 3Build on Pipe Plant Prop. 3Invest in City Response Equip. & Vehicles 3Focus on City Road Infrastructure First 3

Revitalize Downtown 2Not at 100E & S. Center 2Open to Community - Gathering Place 2Use Satellite Locations on City-Owned Prop. 2Provide Option for Communities to Select 2Current City Debt Future Debt 2Location / Not Historic Building 1Keep Current Location 1Replace Rec Bldg w/ New Gather Place 1Design in Seqt'l Phases 1Small Mtg space for City Group 1Preserve Historical Bldgs 1Avoid Eminent Domain 1Build w/o Public Funding/Money 1Unify Infrastructure to better serve City 1Sustainable Community 1Design Frills 1Design & Const. by Professional Business 1Occupancy Fire & Police Only 1Building Maintenance 1Effectiveness 1Combined Use 1Community Acceptance 1

Page 7: PUBLIC SAFETY BUILDING FINDINGS MEETING

Community Involvement

Page 8: PUBLIC SAFETY BUILDING FINDINGS MEETING

Site Selection

Page 9: PUBLIC SAFETY BUILDING FINDINGS MEETING

Site Selection

Page 10: PUBLIC SAFETY BUILDING FINDINGS MEETING

Site Selection

Downtown - 50 East 100 South

Pipe Plant - 300 West 400 North

Page 11: PUBLIC SAFETY BUILDING FINDINGS MEETING

Site SelectionMain Street

200

Sout

h

100

Sout

h

100 East

Page 12: PUBLIC SAFETY BUILDING FINDINGS MEETING

Programming

COMBINED TOTAL

Staff & Square Footage

Description Existing Space

Current Need Future Need

Previous Program

Police 7,140 12,120 13,875 16,672 Fire 11,882 17,439 18,185 21,670 Courts 1,633 4,561 5,853 6,883

Subtotal Net Square Footage 20,655 34,120 37,913 45,225

Grossing Factor - 30% 6,197 10,236 11,374 13,566

TOTAL SQUARE FOOTAGE 26,852 44,355 49,286 58,791

Page 13: PUBLIC SAFETY BUILDING FINDINGS MEETING

Programming

Summary - Police DepartmentVCBO

Description Staff Space Staff Space Staff Space Program Effi ciencies Comments

Private Offi ces 10 1,004 12 1,824 820 14 2,088 264 2,000 88 Workstations 25 1,381 30 1,536 155 47 2,280 744 1,774 506 Support Spaces 2 2,760 4 8,760 6,000 8 9,507 747 12,898 (3,392)

Subtotal Staff & Square Footage 37 5,145 46 12,120 6,975 69 13,875 1,755 16,672 (2,798)

AdministrationVCBO

Description Staff Space Staff Space Staff Space Program Effi ciencies CommentsPrivate OfficesChief 1 196 1 216 20 1 216 - 220 (4) Captain 1 160 1 144 (16) 1 144 - 180 (36) Lieutenant 1 - 1 144 144 2 288 144 450 (162) Emergency Management 1 135 1 180 45 1 180 - 150 30 *IT/EOC Include space for IT workbenchVictim Service - Victim Advocates 1 68 1 216 148 1 216 - 220 (4) meeting space with victims is included in offi ceAdmin Assistant 1 80 1 120 40 1 120 - 150 (30) admin asst & evidence clerk - 1 current, 2 future

Subtotal Staff & Square Footage 6 639 6 1,020 381 7 1,164 144 1,370 (206)

Workstations- - - *evidence

Subtotal Staff & Square Footage - - - - - - - - - -

Support Spaces

Reception lobby 108 (108) - 333 (333)

*courts, fire, dispatch shown on courts

Training Room/EOC 694 (694) - 1,800 (1,800) * fire shown on fire spreadsheetBreak Rm / Kitchen 266 248 (19) 248 - 250 (3) Quartermaster/Armory 160 400 240 400 - 300 100 secure from offi cersArmory - - 300 (300) combined with quartermasterGun Cleaning Ports 40 40 40 - 40 adjacent to armoryCopy / Workroom 80 80 150 70 180 (30) Storage 300 300 400 100 300 100 Exercise Room - - 400 (400) * fire shown on fire spreadsheetShowers / Restrooms / Locker Area - - 800 (800) * fire shown on fire spreadsheetExecutive conference room 400 400 400 - 330 70

Subtotal Staff & Square Footage - 1,228 - 1,468 240 - 1,638 170 4,993 (3,356)

InvestigationsVCBO

Description Staff Space Staff Space Staff Space Program Effi ciencies CommentsPrivate Offices

Investigative Lieutenant 1 - 1 144 144 1 144 - 144 space for interview room monitoring instead of a separate room

Sergeant (Investigations) 1 180 2 240 60 2 240 - 300 (60) ICAC Offi ce 1 180 180 1 180 - 180 larger size for multiple computers

Subtotal Staff & Square Footage 2 180 4 564 384 4 564 - 300 264

Workstations

Detectives (Investigations) 4 643 7 448 (195) 15 960 512 384 576

* code enforcement, print room

to include code enforcement at full build out. 8x8 workstations

Existing Current Needs Full Build out Needs

Current Needs Existing vs current

Existing Full Build out Needs

Existing Current Needs Full Build out Needs Existing vs current

Current vs full

Full vs VCBO

Existing vs current

Current vs full

Full vs VCBO

Current vs full

Full vs VCBO

Page 14: PUBLIC SAFETY BUILDING FINDINGS MEETING

Programming

Page 15: PUBLIC SAFETY BUILDING FINDINGS MEETING

Project Definition

Page 16: PUBLIC SAFETY BUILDING FINDINGS MEETING

Project Definition

Page 17: PUBLIC SAFETY BUILDING FINDINGS MEETING

Project Definition

Page 18: PUBLIC SAFETY BUILDING FINDINGS MEETING

Project Definition

Page 19: PUBLIC SAFETY BUILDING FINDINGS MEETING

Cost Model

Page 20: PUBLIC SAFETY BUILDING FINDINGS MEETING

Cost Model

Page 21: PUBLIC SAFETY BUILDING FINDINGS MEETING

Springville City

Page 22: PUBLIC SAFETY BUILDING FINDINGS MEETING

Bond Reductions

Page 23: PUBLIC SAFETY BUILDING FINDINGS MEETING

Monthly Property Owner Cost

Page 24: PUBLIC SAFETY BUILDING FINDINGS MEETING

Comment Card

Pleasant Grove Police, Fire & Courts BuildingDo you have enough information to make an informed decision if this issue were to be put on the ballot in November? (circle one) YES NOAdditional Comments: ___________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

Page 25: PUBLIC SAFETY BUILDING FINDINGS MEETING

Conclusion