project description report -...
TRANSCRIPT
Otter Creek Wind Farm Limited Partnership
Project Description Report
Prepared by:
AECOM
201 – 45 Goderich Road 905 578 3040 tel
Hamilton, ON, Canada L8E 4W8 905 578 4129 fax
www.aecom.com
Date: May, 2017
Project Number: 60504082
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017)
Statement of Qualifications and Limitations
The attached Report (the “Report”) has been prepared by AECOM Canada Ltd. (“AECOM”) for the benefit of the Client (“Client”) in
accordance with the agreement between AECOM and Client, including the scope of work detailed therein (the “Agreement”).
The information, data, recommendations and conclusions contained in the Report (collectively, the “Information”):
is subject to the scope, schedule, and other constraints and limitations in the Agreement and the qualifications
contained in the Report (the “Limitations”);
represents AECOM’s professional judgement in light of the Limitations and industry standards for the preparation of
similar reports;
may be based on information provided to AECOM which has not been independently verified;
has not been updated since the date of issuance of the Report and its accuracy is limited to the time period and
circumstances in which it was collected, processed, made or issued;
must be read as a whole and sections thereof should not be read out of such context;
was prepared for the specific purposes described in the Report and the Agreement; and
in the case of subsurface, environmental or geotechnical conditions, may be based on limited testing and on the
assumption that such conditions are uniform and not variable either geographically or over time.
AECOM shall be entitled to rely upon the accuracy and completeness of information that was provided to it and has no
obligation to update such information. AECOM accepts no responsibility for any events or circumstances that may have
occurred since the date on which the Report was prepared and, in the case of subsurface, environmental or geotechnical
conditions, is not responsible for any variability in such conditions, geographically or over time.
AECOM agrees that the Report represents its professional judgement as described above and that the Information has been
prepared for the specific purpose and use described in the Report and the Agreement, but AECOM makes no other
representations, or any guarantees or warranties whatsoever, whether express or implied, with respect to the Report, the
Information or any part thereof.
Except (1) as agreed to in writing by AECOM and Client; (2) as required by-law; or (3) to the extent used by governmental
reviewing agencies for the purpose of obtaining permits or approvals, the Report and the Information may be used and relied
upon only by Client.
AECOM accepts no responsibility, and denies any liability whatsoever, to parties other than Client who may obtain access to the
Report or the Information for any injury, loss or damage suffered by such parties arising from their use of, reliance upon, or
decisions or actions based on the Report or any of the Information (“improper use of the Report”), except to the extent those
parties have obtained the prior written consent of AECOM to use and rely upon the Report and the Information. Any injury, loss
or damages arising from improper use of the Report shall be borne by the party making such use.
This Statement of Qualifications and Limitations is attached to and forms part of the Report and any use of the Report is subject
to the terms hereof.
AECOM: 2015-04-13
© 2009-2015 AECOM Canada Ltd. All Rights Reserved.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017)
Authors
Report Prepared By:
Mir Ahsan Ali Talpur, BSc, CPT
Environmental Planner
Report Reviewed By:
Mark van der Woerd, MES, EP
Senior Project Manager
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017)
Table of Contents
page
1. Introduction ................................................................................................ 1
1.1 Name of Applicant ............................................................................................................. 1
1.1.1 Summary of Project Description Report Requirements ........................................... 1
1.2 Project Location ................................................................................................................. 2
1.3 Land Ownership ................................................................................................................. 2
1.4 Description of Energy Source, Nameplate Capacity and Class of the Facility .................... 4
1.5 Contact Information............................................................................................................ 5
1.6 Other Approvals and Authorizations Required ................................................................... 5
1.6.1 Provincial Permits and Authorizations .................................................................... 5
1.6.2 Municipal Permits and Authorizations ..................................................................... 6
1.6.3 Federal Permits and Authorizations ........................................................................ 6
2. Project Components and Ancillary Facilities ........................................... 8
3. Project Activities ...................................................................................... 10
3.1 Project Schedule .............................................................................................................. 10
3.2 Pre-Construction .............................................................................................................. 10
3.3 Construction .................................................................................................................... 10
3.4 Operations and Maintenance ........................................................................................... 11
3.5 Decommissioning ............................................................................................................ 11
3.6 Construction Materials, Waste Generation and Transportation ........................................ 12
3.7 Toxic / Hazardous Materials ............................................................................................. 12
3.8 Air Emissions ................................................................................................................... 13
3.9 Sewage ............................................................................................................................ 13
3.10 Stormwater Managements / Erosion and Sediment Control ............................................. 13
3.11 Water-taking Activities ..................................................................................................... 13
3.11.1 Temporary Water Takings during Construction .................................................... 14
3.11.2 Long Term Water Takings during Operation ......................................................... 14
4. Description of Potential Environmental Effects ..................................... 15
4.1 Cultural Heritage (Protected Properties, Archaeological and Heritage Resources) .......... 15
4.1.1 Existing Conditions ............................................................................................... 15
4.1.2 Potential Effects, Mitigation Measures and Net Effects ......................................... 16
4.2 Natural Heritage Features ................................................................................................ 16
4.2.1 Existing Conditions ............................................................................................... 17
4.2.1.1 Wetlands and Vegetation Communities ............................................................ 17 4.2.1.2 Birds ................................................................................................................... 17 4.2.1.3 Bats .................................................................................................................... 18
4.2.2 Potential Effects, Mitigation Measures and Net Effects ......................................... 18
4.3 Surface Water and Groundwater...................................................................................... 22
4.3.1 Existing Conditions ............................................................................................... 22
4.3.1.1 Surface Water .................................................................................................... 22
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017)
4.3.1.2 Groundwater ...................................................................................................... 22 4.3.1.3 Physiography and Topography.......................................................................... 22
4.3.2 Potential Effects, Mitigation Measures and Net Effects ......................................... 24
4.3.2.1 Surface Water .................................................................................................... 24 4.3.2.2 Groundwater ...................................................................................................... 28
4.4 Emission to Air, including Odour and Dust ....................................................................... 30
4.4.1 Existing Conditions ............................................................................................... 30
4.4.2 Potential Effects, Mitigation Measures and Net Effects ......................................... 30
4.5 Noise ............................................................................................................................... 31
4.5.1 Existing Conditions ............................................................................................... 31
4.5.2 Potential Effects, Mitigation Measures and Net Effects ......................................... 31
4.6 Local Interests, Land Use and Infrastructure .................................................................... 34
4.6.1 Existing Conditions ............................................................................................... 34
4.6.2 Potential Effects, Mitigation Measures and Net Effects ......................................... 35
4.7 Other Resources .............................................................................................................. 38
4.7.1 Existing Conditions ............................................................................................... 38
4.7.1.1 Landfills .............................................................................................................. 38 4.7.1.2 Aggregate Resources ........................................................................................ 38 4.7.1.3 Forest Resources .............................................................................................. 38 4.7.1.4 Petroleum Resources ........................................................................................ 38
4.8 Public Health and Safety .................................................................................................. 38
4.8.1 Potential Effects ................................................................................................... 38
4.8.1.1 Stray Voltage ..................................................................................................... 38 4.8.1.2 Structural Hazards ............................................................................................. 38 4.8.1.3 Ice Throw ........................................................................................................... 39 4.8.1.4 Low Frequency Sound, Infrasound and Vibration ............................................. 39 4.8.1.5 Electric and Magnetic Fields.............................................................................. 39
4.8.2 Potential Effects, Mitigation Measures and Net Effects ......................................... 39
4.9 Areas Protected under Provincial Plans and Policies ....................................................... 40
5. Summary and Conclusions ..................................................................... 41
6. References ................................................................................................ 42
List of Figures
Figure 1-1: Project Location .................................................................................................................................. 3
List of Tables
Table 1-1: Adherence to Project Description Report Requirements under O. Reg. 359/09, as
Amended ............................................................................................................................................. 1
Table 1-2 : General Limits of the Project Location ................................................................................................ 2
Table 1-3: Summary of Key Project Information .................................................................................................. 4
Table 1-4: Ontario Authorizations and Permits .................................................................................................... 5
Table 1-5: Municipal Authorizations and Permits ................................................................................................. 6
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017)
Table 1-6: Potential Federal Authorizations and Permits .................................................................................... 7
Table 2-1: Description of Project Components .................................................................................................... 8
Table 2-2: Description of Temporary Project Components .................................................................................. 9
Table 3-1: Estimated Project Milestones ........................................................................................................... 10
Table 4-1: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to
Generalized Candidate Significant Wildlife Habitat Resulting from Construction and
Decommissioning .............................................................................................................................. 19
Table 4-2: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to
Significant Wildlife Habitat Resulting from Construction and Decommissioning .............................. 20
Table 4-3: Mitigation Measures, Net Effects and Monitoring Plan Associated with Significant
Woodlands Resulting from Construction and Decommissioning ...................................................... 20
Table 4-4: Mitigation Measures, Net Effects and Monitoring Plan Associated with Generalized
Candidate Significant Wildlife Habitat Resulting from Operations .................................................... 21
Table 4-5: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to
Significant Wildlife Habitat Resulting from Operations ..................................................................... 21
Table 4-6: Mitigation Measures, Net Effects and Monitoring Plan Associated with Significant
Woodlands Resulting from Operations ............................................................................................. 21
Table 4-7: Summary of MOECC Water Well Record Information ...................................................................... 23
Table 4-8: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to
Surface Water Resulting from Construction and Decommissioning ................................................. 25
Table 4-9: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to
Surface Water Resulting from Operations ........................................................................................ 27
Table 4-10: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to
Groundwater Resulting from Construction and Decommissioning ................................................... 29
Table 4-11: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to
Groundwater Resulting from Operations .......................................................................................... 29
Table 4-12: Mitigation Measures, Net Effects and Monitoring Plan Associated with Emissions to Air
Resulting from Construction and Decommissioning ......................................................................... 30
Table 4-13: Mitigation Measures, Net Effects and Monitoring Plan Associated with Emissions to Air
Resulting from Operations ................................................................................................................ 31
Table 4-14: Mitigation Measures, Net Effects and Monitoring Plan Associated with Noise Resulting
from Construction and Decommissioning ......................................................................................... 33
Table 4-15: Mitigation Measures, Net Effects and Monitoring Plan Associated with Noise Resulting
from Operations ................................................................................................................................ 33
Table 4-16: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to
Local Interests, Land Use and Infrastructure Resulting from Construction and
Decommissioning .............................................................................................................................. 37
Table 4-17: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to
Local Interests, Land Use and Infrastructure Resulting from Operations ......................................... 37
Table 4-18: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to
Public Health and Safety Resulting from Operations ....................................................................... 40
Appendices
Appendix A Legal Descriptions
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017)
Acronyms and Abbreviations
BMPs ..................... Best Management Practices
CDA ....................... Construction Disturbance Area
CMOH ................... Chief Medical Officer of Health
EEMP .................... Environmental Effects Monitoring Plan
EIS ........................ Environmental Impact Study
ELC ....................... Ecological Land Classification
EMF ....................... Electromagnetic Field
EOS ....................... Evaluation of Significance
ESC ....................... Erosion and Sediment Control
FRP ....................... Flood Response Protocol
GHGs .................... Greenhouse Gases
HONI ..................... Hydro One Networks Inc.
IESO ...................... Independent Electricity System Operator
km ......................... Kilometres
kV .......................... Kilovolts
m ........................... Metres
m2 .......................... Metres squared
m/s ........................ Metres per second
MBCA .................... Migratory Birds Convention Act
MNRF .................... Ontario Ministry of Natural Resources and Forestry
MOECC ................. Ontario Ministry of the Environment and Climate Change
MTCS .................... Ontario Ministry of Tourism, Culture and Sport
MTO ...................... Ontario Ministry of Transportation
MW ........................ Megawatts
NHA ....................... Natural Heritage Assessment
Otter Creek............ Otter Creek Wind Farm Limited Partnership
O. Reg. .................. Ontario Regulation
OEB ....................... Ontario Energy Board
OWES ................... Ontario Wetland Evaluation System
PDR ....................... Project Description Report
Project ................... Otter Creek Wind Farm
REA ....................... Renewable Energy Approval
RES Canada ......... Renewable Energy Systems Canada
SARA ................... Species at Risk Act
RoW ...................... Right-of-Way
SCADA .................. Supervisory Control and Data Acquisition
SCRCA ................. St. Clair Region Conservation Authority
SFL ........................ Sustainable Forest Licence
SWH ...................... Significant Wildlife Habitat
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 1
1. Introduction
1.1 Name of Applicant
In May, 2009, the Government of Ontario passed the Green Energy and Green Economy Act and Ontario
Regulation (O. Reg.) 359/09, as amended. Under the amended O. Reg. 359/09, the Otter Creek Wind Farm Project
(the Project) will require a Renewable Energy Approval (REA). The REA integrates previous requirements under
the Environmental Assessment Act with provincial rules and standards under the Environmental Protection Act.
The Project is being proposed by Otter Creek Wind Farm Limited Partnership (Otter Creek), a partnership of
Renewable Energy Systems Canada (RES Canada), Boralex Inc., and Walpole Island First Nation. The Project is
also grateful to have received support from the Municipality of Chatham-Kent which has been granted an option to
participate in the Project after commercial operation commences.
This Project has been proposed in response to the Government of Ontario’s plan to integrate more renewable
energy into the province’s power grid. This Project Description Report (PDR) has been prepared in accordance with
Item 10 of Table 1 in O. Reg. 359/09, as amended.
1.1.1 Summary of Project Description Report Requirements
The requirements for the PDR defined under O. Reg. 359/09, as amended, are outlined in Table 1-1. Information
about the requirements of the reports identified in Table 1-1 is also provided throughout this report.
Table 1-1: Adherence to Project Description Report Requirements under O. Reg. 359/09,
as Amended
Requirement Completed Corresponding Section
Description of any energy sources to be used to generate electricity at the renewable
energy generation facility.
Yes Section 1.4
Description of the facilities, equipment or technology that will be used to convert the
renewable energy source or any other energy source to electricity.
Yes Section 2
The class of the renewable energy generation facility. Yes Section 1.4
Description of the activities that will be engaged in as part of the renewable energy
project.
Yes Section 3
The nameplate capacity of the renewable energy generation facility. Yes Section 1.4
The ownership of the land on which the Project Location is to be situated. Yes Section 1.3; Appendix A
Description of any negative environmental effects that may result from engaging in the
Project.
Yes Section 4
An unbound, well-marked, legible and reproducible map that is an appropriate size to
fit on a 215 mm by 280 mm page, showing the Project location and the land within
300 m of the Project location.
Yes Figure 1-1 of this Report
This PDR, along with the rest of the draft REA reports was provided to Municipality of Chatham-Kent 90 days in
advance of the second public meeting. It was also provided to First Nations and Aboriginal communities,
government agencies and the public for review 60 days in advance of the second public meeting. These timelines
align with the requirements outlined in O. Reg. 359/09, as amended.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 2
1.2 Project Location
Under O. Reg. 359/09, as amended, the Project Location is “a part of land and all or part of any building or
structure in, on, or over which a person is engaging in or proposes to engage in the project and any air space in
which a person is engaging in or proposes to engage in the project”. As described therein, the Project Location
consists of the construction disturbance area (CDA) and the blade swept area of the turbines. The CDA identifies
the location of permanent and temporary Project components.
Otter Creek is proposing to develop a wind energy project located north of the community of Wallaceburg in the
Municipality of Chatham-Kent, Ontario. The location of the Project was determined based on interest expressed by
local landowners, municipal support for the Project, the availability of wind resources, and the availability of existing
infrastructure to facilitate a connection to the electrical grid.
The Project is generally bounded by Whitebread Line and Kent Line to the north, Payne Road to the west, Stewart
Line and McCreary Line to the south and Mandaumin Road / County Road 44 to the east. Figure 1-1 shows a map
of the Project Location.
The Project Location encompasses approximately 820 acres of land that is predominantly designated for
agricultural use according to the Municipality of Chatham-Kent’s Official Plan (2016) and Zoning By-law (2015). The
area surrounding the Project also consists of fragmented areas of forest and riparian habitat associated with the
Sydenham River, which bisects the Project in a north-south direction, as well as other small creeks and/or farm
drains. The following co-ordinates define the general limits of Project Location:
Table 1-2 : General Limits of the Project Location
Direction Easting Northing
North 390526 4720434
South 391633 4717628
East 395682 4719362
West 381309 4718791
1.3 Land Ownership
The majority of the Project will be located on privately owned land with some components (e.g., collector lines)
being placed along public Right-of-Way (RoW). Otter Creek has entered into agreements with private land owners
of the land parcels where the Project will be located. Legal descriptions of the land parcels to be used for the
Project are provided in Appendix A.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 3
Figure 1-1: Project Location
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 4
1.4 Description of Energy Source, Nameplate Capacity and Class of the Facility
The Project will use wind to generate energy through the use of wind turbine technology. The proposed wind
turbine for this project is the Enercon E-141. The Project’s nameplate capacity is up to 50 megawatts (MW) and the
wind farm will consist of 12 turbines. The Project is categorized as a Class 4 wind facility and will be in compliance
with the requirements outlined for such facilities.
A summary of key Project information is presented in Table 1-3 below.
Table 1-3: Summary of Key Project Information1
General Project Name: Otter Creek Wind Farm Project
Project Ownership and Operation: Otter Creek Wind Farm Limited Partnership
Anticipated Project Lifespan (Commercial Operation): 20 years (or longer if possible)
Project Nameplate Capacity: Up to 50 MW
Project Location Area
Location of Project: Privately-owned land and public road allowances in the Municipality of Chatham-Kent
Total Project Location Area Approximately 820 acres
Wind Turbine Generators
Make and Model: Enercon E-141
Total Number Permitted: 12 turbines
Approximate Number Constructed: 12 turbines
Nominal Turbine Power: Up to 4.2 MW
Number of Blades: 3
Blade Length: 66.7 metres (m)
Hub Height: 129 m
Rotor Diameter: 141 m
Cut-in Wind Speed: 2.5 metres per second (m/s)
Cut-out Wind Speed: 28.0 m/s (reduced mode up to 34.0 m/s)
Swept Area: 15,614.5 metres squared (m2)
Foundation Dimensions: Approximately 30 m diameter
Access Roads During Operations (approximate range includes shoulder, travel width and ditch):
5 to 12 m
During Construction (approximately, with shoulder): 20 m
Temporary Land Use (Construction
Phase)
Turbine Working Area(total approximate area per turbine): 2.5 acres
Laydown Area (s) (approximate total area constructed for laydown):
10 to 20 acres
1. Dimensions are near approximations.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 5
1.5 Contact Information
Applicant:
The contacts for the Project are as follows:
Asier Ania
Project Manager, Development
Boralex Inc.
201-174 Mill Street, Milton, ON L9T 1S2
Phone: 1-844-363-6430 ext.6432
Email: [email protected]
Consultant:
Mark van der Woerd
Senior Project Manager
AECOM
45 Goderich Road, Hamilton, ON L8E 4W8
Phone: (905) 390-2003
Email: [email protected]
Project:
Project Phone: 1-844-330-9061
Project Email: [email protected]
Project Website: www.ottercreekwindfarm.ca
1.6 Other Approvals and Authorizations Required
1.6.1 Provincial Permits and Authorizations
Based on the requirements of the Green Energy and Green Economy Act, the Project may require provincial
authorizations. Table 1-4 provides a list of the potential provincial authorizations that may be required.
Table 1-4: Ontario Authorizations and Permits
Permit / Authorization Administering Agency Rationale
Renewable Energy Approval
Application - Ontario Regulation 359/09
MOECC Renewable energy project approval
Archaeological Clearance* Ministry of Tourism, Culture and
Sport (MTCS)
Archaeological and heritage resources
Natural Heritage Assessment* MNRF Natural heritage resources
Notice of Activity for Newly Listed
Species and Wind Facilities Operations
MNRF Species at risk and their habitats that may be affected by
construction or operation of the wind project
Fill, Construction & Alteration of
Waterways Development, Interference
with Wetlands and Alterations to
Shorelines and Watercourses –
Ontario Regulation 169/06
St. Clair Region Conservation
Authority (SCRCA)
Work within floodplains, water crossings, river or stream
valleys, hazardous lands and within or adjacent to
wetlands
Encroachment Permit Ministry of Transportation (MTO) Crossing of provincial highways
Land use Permit MTO Project works undertaken within 180 m of a Ministry of
Transportation controlled intersection
Commercial Access Permit MTO Ingress / egress from provincial highway
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 6
Table 1-4: Ontario Authorizations and Permits
Permit / Authorization Administering Agency Rationale
Change of Access & Heavy / Oversize
Load Transportation Permit
MTO Compliance with provincial highway traffic and road safety
regulations
Special Vehicle Configuration Permit MTO Use of non-standard vehicles to transport large components
Notice of Project Ministry of Labour Notification to the Ministry of Labour before construction
Leave-to-Construct Ontario Energy Board (OEB) Development of a high-voltage transmission facility
Generator’s Licence OEB Generator Operation Permit
Transmitter Licence OEB Transmission of electrical power to interconnect with
provincial grid
Customer Impact Assessment Hydro One Networks Inc. (HONI) Evaluation of potential effects to existing electrical
customers
Connection and Cost Recovery
Agreement
HONI Definition of responsibilities for connection facilities for
Hydro One and Otter Creek with regard to the Project
System Impact Assessment Independent Electricity System
Operator (IESO)
Potential effects of integrating the Project within provincial
transmission system
Approval of Connection IESO Electrical interconnect with IESO regulated network
Connection Assessment IESO Integration of Project with IESO-controlled transmission
system
Certificate of Inspection Electrical Safety Authority Ensure work complies with the Ontario Electrical Safety
Code
Note: * Permits covered under REA process.
1.6.2 Municipal Permits and Authorizations
In addition to the provincial requirements listed in the table above, the Project will require a number of municipal
permits and approvals. Although the list is not exhaustive, Table 1-5 lists a number of the permits and approvals
that may be required from the Municipality of Chatham-Kent prior to construction.
Table 1-5: Municipal Authorizations and Permits
Permit / Authorization Rationale
Entrance Permit Ingress / egress from municipal roads
Drainage Permit Required for crossings of municipal drains
Building Permit Compliance with Ontario Building Code
Road Occupancy Permit Required for work in municipal road allowances
Consent / Severance Application Required if easements over private lands are required
Road Cut Permit May be required for access roads off of county roads or works to county roads
Supporting Information / Plans for General
Engineering to Support the Project
Supporting information / plans that may be required by the Municipality of
Chatham-Kent
1.6.3 Federal Permits and Authorizations
The Project may require a number of permits and approvals from the federal government prior to construction. The
following table lists federal authorizations and permits that may be required for the Project. These authorizations
and permits will be determined through the REA process and will be obtained, if required. An environmental
assessment under the Canadian Environmental Assessment Act is not anticipated to be required as wind projects
are not on the list of designated projects under the Act (Government of Canada, 2013).
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 7
Table 1-6: Potential Federal Authorizations and Permits
Permit Authorization Administering Agency Rationale
Aeronautical Obstruction Clearance Transport Canada - Aviation Division Required for turbine marking and lighting
Land Use Clearance NAV Canada Required for aeronautical safety mapping and designation
In addition, the Project to obtain an authorization or permit associated with the Species at Risk Act (SARA),
Fisheries Act and Migratory Birds Convention Act (MBCA).
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 8
2. Project Components and Ancillary Facilities
A description and listing of Project components and temporary Project components are outlined below in Table 2-1
and Table 2-2, respectively.
Table 2-1: Description of Project Components
Component Description
Wind Turbine
Generators
The Project will include wind turbines with a project total nominal power up to 50 MW. The turbine nacelle includes the
electric generator, wind direction and speed sensors and auxiliary equipment. These components are located at the top
of a supporting tower and are connected to three blades and a hub.
Wind Turbine
Foundation
Each turbine tower is anticipated to have a concrete foundation. The land base of each turbine foundation will be
dependent on subsurface conditions determined during geotechnical investigations. Following geotechnical
investigations, it may be determined that spread-footing type foundations may be suitable for certain locations;
otherwise alternative foundation designs will be considered (e.g., Deep foundations).
Collector
Transformers
A collector transformer will be located inside the turbine tower. This transformer ‘steps-up’ the electricity generated by
the wind turbine to a common electrical collector line voltage, likely 34.5 Kilovolts (kV).
Wind Turbine
Access Roads
During construction and operation of the proposed Project, roads are required in order to access wind turbine locations.
Access roads will be constructed within the CDA and developed to accommodate cranes and transportation equipment
used to deliver wind turbine components.
Collector Lines Collector lines carry the electricity from the collector transformers to the Project electrical substation (described below).
The collector lines will likely be 34.5 kV standard utility generator lines located within the CDA on private property and
within the public RoW until it reaches the Electrical Substation.
The underground collector lines will be buried in accordance with Electrical Safety Authority standards. This depth will
likely be deeper than 0.75 m below ground surface. If above ground electrical collector lines are required, they will be
constructed on wood, steel or concrete pole structures.
Where two or more underground collector lines must be connected together, a junction box may be installed either below
or above ground. Junction boxes may contain equipment related to splices, junctions, cable splices and disconnect
switches. They will be located either on private lands or within the ROW and contained within the CDA.
Electrical
Substation
An electrical substation is required to bring together all of the underground and aboveground electrical collector lines. The
collected power will be transformed from the electrical collector line voltage (34.5 kV) to a transmission voltage (115 kV).
Electrical substation equipment may include an isolation switch(es), circuit breaker(s), step-up power transformer(s),
distribution switch-gear(s), instrument transformers, capacitor banks, communication equipment which may include a
communication tower, Supervisory Control and Data Acquisition equipment, protection and control equipment,
grounding transformers, grounding grid, revenue metering (conforming to the Independent Electricity System Operator
(IESO) market rules), substation grounding, parking, emergency generator, service transformer and a control building.
A secondary containment system may be installed at the transformer constructed at the substation to prevent soil
contamination in the event of a leak if petroleum products are used within the equipment installed.
Communication
Tower
A Communication tower used for communication purposes may be constructed within the substation CDA and/or the
interconnection station location. If required, the Communication tower may be up to 100 m tall. Height, soil conditions
and space requirements will determine whether the tower will be steel-lattice or guyed.
Meteorological
Towers
One or more permanent meteorological towers, up to approximately 129 m in height, may be constructed using cranes
and secured with guy wires tied off to anchors.
Access roads may be constructed to access meteorological tower locations and the site may be surrounded by a chain
link fence. The towers will be connected to the Project power and communication infrastructure.
There is a possibility of using the meteorological tower to host communications equipment to serve the purpose of the
communications tower.
Interconnection
Station
(Connection to
Electrical Grid)
The point of interconnection will require modifications to the existing transmission line and may include circuit breakers,
isolation switches, transmission switchgear, instrumentation, grounding, metering equipment and other equipment
typical of such systems.
There will be an interconnection line from the transformer to the POI.
The interconnection plan for any wind project is subject to study, design, engineering and approval by the IESO which
manages the province’s electricity grid and HONI which owns the transmission lines.
Operations and
Maintenance
Building
An operations and maintenance building may be constructed. This building may accommodate offices, maintenance
work areas, control facilities and a parking area and will likely be located within the Project Location.
An access road to the operations and maintenance building from a municipal or privately owned road would be used to
access the operations and maintenance building during the operation of the Project.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 9
To facilitate the construction of the proposed Project, a number of temporary construction components are required.
These temporary components, described further in Table 2-2 below, include turbine working areas and construction
laydown area(s).
Table 2-2: Description of Temporary Project Components
Laydown Areas Approximately 10 to 20 acres of land area may be constructed for the temporary storage of
construction material/equipment/components and as a site(s) for the construction office trailers, staff
vehicle parking and other construction related needs.
Following clearing and grubbing of any vegetation, the topsoil at the temporary laydown area will be
removed and a layer of clean compacted crushed gravel will be imported, as needed.
A temporary electrical service line may be connected to the existing distribution line for the purpose of
providing power to the construction office trailers.
Turbine Working
Area
Temporary working areas will be constructed at the same time as the access roads and will be located
adjacent to the turbine locations.
Crane pads will be constructed in tandem with wind turbine access roads and after topsoil and subsoil
are removed from the areas. The Turbine Working Areas will consist of left over subsoil and may be
filled with varying mixtures of granular base material and/or crushed gravel depending on site specific
conditions.
Crane mats will be used to stabilize cranes during their operation.
The total turbine working area will be approximately 2.5 acres.
After the turbine erection is complete, the crane mats, granular base materials and crushed gravel will
be removed, native topsoil replaced, and working areas returned to their pre-construction condition, at
the discretion of the landowners. A small gravel pad will be left in place at the base of the turbine
around the turbine foundation for maintenance truck access and circulation.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 10
3. Project Activities
The following sections outline the anticipated activities for the pre-construction, construction, operation and
decommissioning phases of the Project. Further information relating to Project activities will be provided in the
Construction Plan Report, the Design and Operations Report and the Decommissioning Plan Report and will be
submitted, under different covers, as part of the Project’s REA Application.
3.1 Project Schedule
The schedule below in Table 3-1 outlines the anticipated timelines for the Project:
Table 3-1: Estimated Project Milestones
Project Milestone Estimated Date
Host Public Meeting #1 Summer, 2016
Complete Environmental Studies and Reporting Summer/Fall, 2016
Host Public Meeting #2 Winter, 2017
Submit REA Application Winter, 2017
Obtain Pre-Construction Permits Spring/Summer/Fall, 2017
Start Construction Spring, 2018
Commence Operations and Maintenance Late 2018 or 2019
3.2 Pre-Construction
During the pre-construction phase of the Project, primary activities include optioning of lands, preliminary
engineering, geotechnical assessment and site surveys of the final turbine locations, procurement of turbine and
substation equipment, permitting and detailed design. Otter Creek will continue to communicate and engage
landowners, First Nations and Aboriginal communities, and the Municipality of Chatham-Kent, as required, during
this phase of the Project.
The REA process is the primary approval requirement in the pre-construction phase of the Project. For the permits
and authorizations listed in Section 1.6, Otter Creek will work directly with the respective federal, provincial and
municipal authorities to ensure all applicable requirements are met.
3.3 Construction
Construction of the Project is scheduled to begin in spring 2018 and is planned to be completed by late 2018 or
2019. During site preparation and construction of the proposed Project, the following key activities may be
undertaken:
Land clearing;
Construction of access roads;
Construction of laydown area(s);
Construction of turbine working area(s);
Delivery of equipment;
Construction of wind turbine foundations;
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 11
Wind turbine assembly and installation;
Construction of Electrical Collector System;
Construction of Electrical Substation and Interconnection station;
Construction of Operations and Maintenance Building;
Construction of Permanent Meteorological Tower(s) (up to approximately 129 m in height);
Installation of Communication Tower (up to approximately 100 m in height); and
Site clean-up and reclamation.
3.4 Operations and Maintenance
Operation of the Project is expected to begin in late 2018 or 2019. The operational lifespan of the Project is
approximately 20 years, but may be extended. The operation of the proposed Project may require up to four trained
technical and administrative staff, including turbine maintenance technicians and a site supervisor.
During this phase, the following key activities will be undertaken:
Preventative and unplanned maintenance of Project components;
Otter Creek staff transport;
Meter calibrations;
Remote operation of the wind turbines; and
Grounds maintenance in the vicinity of Project components.
On-site activities will be limited primarily to scheduled maintenance of the Project components.
3.5 Decommissioning
During the decommissioning phase of the Project wind turbine structures will be removed to the base of the
foundation and portions of the foundations will be excavated and backfilled with subsoil and topsoil to allow
agricultural activities to continue. Access road removal will be dependent on the requirements and agreements in
place with the individual landowner. Impacted lands will be restored to pre-construction state at the discretion of
landowners. Decommissioning procedures will be similar, but in reverse order to those carried out in the
construction phase.
Key decommissioning activities associated with the proposed Project include:
Disassembly and removal of wind turbine infrastructure (hubs, nacelles, blades and towers, collector
transformer);
Reclamation of agricultural land (at the discretion of landowners);
Removal of all electrical collectors above ground infrastructure (at the discretion of landowners). Where
the underground collector lines come to the surface, the collector lines will be cut and excavated to a
minimum depth of 0.75 m below grade;
Turbine foundations will be removed to a depth of approximately 1 m;
Disconnection of the electrical substation and removal of the connection line;
Disassembly and removal of the electrical substation, communication and meteorological towers, if
required, and transmission and grid connection infrastructure (foundations will be removed to a depth
of approximately 1 m); and
Disassembly and removal of the operations and maintenance building infrastructure (at the discretion
of the landowners and if required).
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 12
3.6 Construction Materials, Waste Generation and Transportation
Materials brought to the Project during construction and installation will include equipment / component packaging,
scraps, fuels and lubricants. Packing frames for the wind turbine components and cabling spools will be returned to
their respective vendors or may be recycled. Plastics from other containers and packaging will be disposed of
through the local landfill and recycling facilities, where appropriate. Construction materials and scrap metals (e.g.,
copper wiring and conductors) will be removed and may be sold to a local scrap metal dealer. Oils, fuel and
lubricants used in maintenance and operation of construction equipment will be stored temporarily in accepted
containment systems and will subsequently be removed by a licensed contractor. The licensed contractor will be
required to dispose of these wastes through conventional oil and hazardous waste disposal streams.
In addition, concrete wash out of empty cement trucks will adhere to applicable regulations. Sanitary sewage
collected in portable toilets and wash stations will be transported to an off-site facility by a licensed hauler. Small
amounts of spoil material from borehole drilling during geotechnical surveys may be redistributed on disturbed
areas at respective drill sites. Topsoil and/or subsoil stripped from access roads, foundations and temporary
storage / laydown areas may be re-used on-site, where feasible, or otherwise removed to an appropriate location.
If any grubbing of the site is required prior to construction activities, the grubbing materials (e.g., vegetation,
branches and tree stumps) will likely be removed but may remain on-site and/or possibly buried within CDA. During
construction of the wind turbine foundation, electrical substation and other infrastructure, excavated subsoil and
topsoil will likely be stored in piles on-site at each temporary storage / laydown area until they are replaced during
clean-up and reclamation activities. As required, stockpiles will be covered following best management practices
(BMPs) to prevent erosion and propagation of noxious weeds. Any excess subsoil will be distributed with landowner
input or taken off-site, and excess clean topsoil will be redistributed to adjacent lands as appropriate. If
contaminated soil is encountered during the course of excavations, this soil will be disposed of in accordance with
the current appropriate provincial legislation.
Disposal and recycling of materials and waste generated will likely require the use of flatbed and large dump trucks
that are capable of transporting heavy loads. The type and number of truck trips necessary will be determined by
the licensed construction contractor prior to the construction and installation of the Project. Disposal and recycling
of waste will occur throughout the construction and installation of the Project since there are no plans for long-term
storage of waste in the CDA.
3.7 Toxic / Hazardous Materials
Machinery used to dismantle and remove Project components will require the use of oils, fuels and lubricants. In
addition, waste lubricants will be recovered during the dismantling of Project components, including the electrical
substation, wind turbine generators and operations and maintenance building (if required). An imbiber bead
containment system, an oil-water separator containment system, or another type of system may be installed. If an
oil-water containment system is used it would likely be connected to the drainage system through an oil water
separator that will likely be buried below grade. These materials will be disposed of through conventional waste-oil
and hazardous waste disposal streams in a manner outlined by regulatory agencies, if required, at the time of
decommissioning.
Overhead collector lines, if required, for the Project may be constructed on a wooden, steel or concrete monopole
structure. If wooden monopole structures are used, these poles typically use a chemical-treated exterior. Otter
Creek will discuss the recycling of wooden poles with a licensed facility, which would likely involve stripping the
chemically-treated exterior, disposing of this chemically-infused wood in a landfill, and re-milling the remaining
wood core for alternative end uses.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 13
3.8 Air Emissions
During each phase of the Project, activities requiring the use of motorized vehicles (e.g., transportation of
maintenance personnel to turbine sites) will have infrequent, short-term, and low levels of emissions of greenhouse
gases (GHGs) and other compounds. These emissions will be negligible compared to normal operation of
motorized vehicles in and around the Project Location. Section 4.4 of this Report outlines potentially negative
effects to air quality relating to the Project and identifies mitigation measures proposed.
Project noise emissions will adhere to the requirements of O. Reg. 359/09, as amended. Project activities are not
anticipated to generate significant odour emissions as a result of the construction and operation of the Project.
3.9 Sewage
During site preparation and construction, portable toilets will be used and a licensed contractor responsible for
waste removal will be engaged. The operations and maintenance building, if built for the Project, may include
washroom facilities that will be constructed and serviced in accordance with required regulations.
Potable water may be supplied by a well(s) or through the municipal water system and a septic bed will be
constructed for the disposal of sewage. Otter Creek will be responsible to ensure proper maintenance of the septic
system. The operations and maintenance building, septic system and water supply would be constructed and
operated in accordance with all applicable (e.g., municipal and provincial) standards.
3.10 Stormwater Managements / Erosion and Sediment Control
To effectively manage runoff during the operation of the Project, drainage channels may be constructed. The
decision of the need for and location of drainage channels will be made during the detailed design stage of the
proposed project. No additional sedimentation control measures are anticipated to be required during operation
since sedimentation from these roads is predicted to be lower than that from agricultural fields where the roads are
constructed.
A graveled area around each wind turbine foundation will receive any precipitation runoff from wind turbine towers
and allow for infiltration into the ground. Runoff from the tower section of wind turbine generators is expected to be
negligible compared to the existing runoff within the Project Location.
3.11 Water-taking Activities
Water takings for the purposes of providing dry working conditions during turbine foundation construction, collection
line installation, road construction, dust suppression and general maintenance activities may be required during
construction of the Project. Any water taking conducted during the construction phase or the operations phase of
the Project is subject to the REA application and as such does not require a separate Permit to Take Water
(PTTW).
A desktop hydrogeological assessment was completed for the purpose of providing a high level review of existing
hydrogeological conditions within the vicinity of the Project Location. The assessment identified potential
groundwater taking needs of the Project during construction and operation, outlined potential effects of the Project
on groundwater resources, and provided a mitigation strategy and contingency measures to negate any adverse
effects. The following section provides an overview of the Hydrogeological Assessment and Effects Assessment
Report for the Project. The full report can be found in Appendix C of the Design and Operations Report (available
under separate cover).
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 14
3.11.1 Temporary Water Takings during Construction
During construction, dewatering will be required for the construction of the wind turbine foundations. Dewatering for
this activity is expected to exceed 50,000 L/day; however this is dependent on the design of the wind turbine
foundation, surficial material being excavated, the depth to the groundwater and other hydrogeological
characteristics which will all be determined during future geotechnical analysis.
During construction, water may be required to support general construction activities and water demands are
expected to have peak volumes up to 50,000 L/day. Actual daily demands will vary and will typically be lower in
volume than the estimated peak volume. The following general construction activities are examples of some of the
activities that may require water taking during construction:
Dust suppression;
Directional drilling; and
Site clean-up and reclamation.
Any water taking conducted throughout the Project (including construction phase) is subject to the REA application
and as such does not require a separate Permit to Take Water (PTTW).
3.11.2 Long Term Water Takings during Operation
Groundwater takings during the operations phase of the Project may be required to provide a non-potable water
source for regular personnel requirements of full-time employees and general operational maintenance at the
operations and maintenance building, should one be constructed. If a well is required, water takings are expected
to be up to approximately 4,500 L/day and are not expected to exceed 50,000 L/day.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 15
4. Description of Potential Environmental Effects
The following section provides a summary of the potential environmental effects that may result from the
construction, operation and decommissioning of the Project. The following assessment of potential environmental
effects is preliminary and has been completed in accordance with the requirements of O. Reg. 359/09, as
amended. The description of environmental effects addresses the following environmental considerations:
Cultural Heritage (Protected Properties,
Archaeological and Heritage Resources);
Natural Heritage;
Impacts on Surface Water and Groundwater;
Emissions to Air, including Odour and Dust;
Noise;
Local Interests, Land Use and Infrastructure;
Other Resources;
Public Health and Safety; and
Areas Protected under Provincial Plans and
Policies.
Each subsection provides a summary of existing conditions followed by a preliminary assessment of potential
environmental effects, including mitigation measures, as a result of construction, operations and decommissioning
of the Project.
For each potential effect, performance objectives were developed to describe a desired outcome of mitigation.
Next, mitigation measures were proposed to achieve the performance objectives. Net effects, which are those
effects that remain following the application of mitigation measures and monitoring commitments, were then
assessed based on professional judgment as well as previous project experience. Where possible, the significance
of adverse net effects has been described based on the following:
Magnitude .......... the size or degree of the effect compared against baseline conditions; and
Likelihood .......... the probability that the effect will occur.
Finally, where monitoring commitments have been identified, they are intended to verify that the mitigation
measures achieve performance objectives. Should the monitoring during the construction and operation of the
Project reveal that the mitigation measures are not achieving the intended results; the identified contingency
measures will then be implemented.
4.1 Cultural Heritage (Protected Properties, Archaeological and Heritage Resources)
4.1.1 Existing Conditions
Stage 1 and 2 Archaeological Assessments (AECOM, 2016a, AECOM, 2016b and AECOM, 2016c) were conducted to
identify the presence of archaeological resources within the CDA. The Stage 1 Archaeological Assessment consists of
an initial desktop archaeological study within 1 kilometre (km) of the CDA. The study determined there was
archaeological potential for both pre-contact Aboriginal and historic Euro-Canadian sites in the CDA.
The Stage 1 Archaeological Assessment was submitted to the MTCS on August 8, 2016, was filed with MTCS on
August 17, 2016 and AECOM received the acceptance letter from MTCS on September 13, 2016. The Stage 2
Archaeological Assessments was submitted to the MTCS in the fall of 2016 for review and acceptance into the
Ontario Public Register of Archaeological Reports.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 16
The Stage 2 Archaeological Assessments of the CDA were conducted between May and November of 2016
(AECOM, 2016b and AECOM, 2016c). The assessments were conducted in accordance with the 2011 Standards
and Guidelines for Consultant Archaeologists (MTCS, 2011). These assessments involved a combination of the
pedestrian survey and test pit survey methods across portions of the study area that are proposed to be impacted
by the project, including turbine locations, access roads, electrical substations, collector lines, operations and
maintenance buildings, meteorological and Communication towers, and turbine working areas. The Stage 2
Archaeological Assessments evaluated the Project CDA, including privately-owned properties and parts of the
municipal ROW of McCreary Line, Richardson Road, and Forhan Street.
The Stage 2 Archaeological Assessments resulted in the identification of two (2) archaeological locations, the first
was identified as a collection of 20th century refuse with a small inclusion of 19
th century glass. The second location
was identified as an isolated pre-contact First Nation findspot. Neither of these locations meets the criteria for
registering with the MTCS as archaeological sites according to Section 7.12, Standard 1 of the Standards and
Guidelines for Consultant Archaeologists (MTCS, 2011). The remaining land was found to be absent of any
archaeological sites or materials.
A Heritage Impact Assessment (AECOM, 2017b) was also completed to identify heritage resources including
cultural heritage features and cultural heritage landscapes of cultural heritage value or interest. All work was carried
out in accordance with O. Reg. 359/09, as amended and included assessing CDA as well as adjacent lots to the
CDA. The report identified three (3) potential heritage properties within the CDA and six (6) potential heritage
properties adjacent to the CDA. The investigation also identified one (1) potential cultural heritage landscape, the
abandoned CSX railway line which crosses through the CDA.
AECOM concluded that there are no direct or indirect impacts of the proposed undertaking on any cultural heritage
resources as part of construction and therefore no mitigation strategies are recommended.
4.1.2 Potential Effects, Mitigation Measures and Net Effects
Construction and Decommissioning
No areas of archaeological interest were identified during the Stage 2 assessments and no potential effects to 10
potential cultural heritage resources within or adjacent to the CDA are anticipated, therefore, no mitigation
measures or monitoring are proposed during construction or decommissioning phases.
Operation
No areas of archaeological interest were identified during the Stage 2 assessments and no potential effects to 10
potential cultural heritage resources within or adjacent to the CDA are anticipated, therefore, no mitigation
measures or monitoring are proposed during operations.
4.2 Natural Heritage Features
The potential effects, mitigation measures, residual effects and monitoring commitments regarding Significant Natural
Heritage Features were identified and evaluated in the Natural Heritage Assessment (NHA) and Environmental Impact
Study (EIS) Report (AECOM, 2017c). Both reports were prepared based on the Natural Heritage Assessment Guide
for Renewable Energy Projects (MNRF, 2012) and submitted to the MNRF for review and sign-off.
Following the completion of the Records Review and Site Investigation for all natural heritage features located in or
within 120 m (or 50 m from collector lines) of the Project Location, an Evaluation of Significance was conducted to
identify any features that required an EIS.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 17
4.2.1 Existing Conditions
The NHA Records Review, Site Investigation and Evaluation of Significance and EIS Reports were completed in
2016/2017. All reporting has been completed in accordance with applicable natural heritage guidelines, including:
Natural Heritage Assessment Guide for Renewable Energy Projects, 2nd Edition (Ontario Ministry of Natural
Resources and Forestry (MNRF, 2012), Birds and Bird Habitats: Guidelines for Wind Power Projects (MNRF,
2011a) and Bats and Bat Habitats: Guidelines for Wind Power Projects (MNRF, 2011b).
For the purposes of completing the NHA, a 50 m Area of Investigation for collector lines located within Public RoW
and a 120 m Area of Investigation for all other infrastructure types were applied to the Project Location. These
distances are based on the requirements of O. Reg. 359/09 and the Natural Heritage Assessment Guide for
Renewable Energy Projects (MNRF, 2012), hereafter referred to as the Natural Heritage Assessment Guide. The
Area of Investigation encompasses the Project Location and an additional 50 m or 120 m surrounding the Project
Location, measured from the Project Location boundary as described above. Going forward, areas in or within 50 m
of the collector lines located within Public RoW (Roadside Collector Project Location) as well as areas in or within
120 m of turbines (Turbine Project Location) and all other Project infrastructure (Remaining Project Location) will be
referred to as the Area of Investigation. As part of the REA process, features located within the Area of
Investigation must be investigated and evaluated to determine whether they are significant or provincially
significant, in order to ascertain whether development prohibitions apply as per O. Reg. 359/09 the Natural Heritage
Assessment Guide.
The following section outlines some of the existing conditions in the Project Location.
4.2.1.1 Wetlands and Vegetation Communities
A total of 1.97 ha of wetland was identified as occurring within the Area of Investigation. A single wetland, a shallow
marsh with a total size of 1.97 ha was identified within the Area of Investigation. The wetland is less than 2 ha in
size and therefore does not require evaluation under Ontario Wetland Evaluation System (OWES).
During the Site Investigation it was determined that areas within the Area of Investigation are largely represented
by agricultural crops such as corn, winter wheat or soy. Through Ecological Land Classification (ELC) surveys in
areas of natural vegetation, it was noted that Open Aquatic was the most frequency occurring ELC community, due
to the large number of agricultural drains and two large ponds. Meanwhile, the most frequently occurring terrestrial
community within the Area of Investigation is a complex of Cultural Meadow and Cultural Thicket, each a total of
8.07 ha and 6.92 ha, respectively. Further information on the identified wetlands and vegetation communities within
the Project Location can be found within the Site Investigation and the Evaluation of Significance reports for this
project (both available under separate cover).
4.2.1.2 Birds
Waterfowl Stopover and Staging Areas (Terrestrial and Aquatic) were the only candidate and/or generalized candidate
Significant Wildlife Habitats (SWH) for birds identified within the Area of Investigation during the Site Investigation.
During which time, a total of seven features were identified and delineated. Waterfowl Stopover and Staging Areas
(Terrestrial and Aquatic) Evaluation of Significance (EOS) surveys must be undertaken in the early spring, which was
before the confirmation of the Project Location and as such, all seven features whether determined to be candidate or
generalized candidate SWH underwent EOS surveys. Subsequent surveys were conducted in accordance with the
methods described in the Birds and Bird Habitats Guidelines for Wind Power Projects (MNRF, 2011a). Following
which the results of the surveys were compared to the evaluation of significance criteria as outlined in the Significant
Wildlife Habitat Criteria Schedules for Ecoregion 7E (MNRF, 2015) and none of the features were found to be
significant. Consequently none of the features were carried forward to the EIS.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 18
4.2.1.3 Bats
A total of three potential bat maternity roost habitats were identified and delineated during the Site Investigations
within the Area of Investigation; however, none of these are located within 120 m qualifying infrastructure, (i.e., a
turbine) nor were any located within an area where vegetation removal was proposed to be undertaken.
Consequently, these features were carried forward to the EIS as generalized candidate SWH.
4.2.2 Potential Effects, Mitigation Measures and Net Effects
The purpose of the NHA EIS Report is to identify, assess and mitigation negative environmental effects; while the
Environmental Effects Monitoring Plan (EEMP) describes the post-construction monitoring plan for bird and bat
mortality and related mitigation and contingency measures, in accordance with MNRF requirements. The report
findings are summarized below.
Construction and Decommissioning
Table 4-1 provides mitigation measures and net effects for potential effects related to Generalized Candidate SWH
and Natural Heritage Features.
Table 4-2 provides mitigation measures and net effects for the potential effects related to the SWH for Plant SOCC.
Table 4-3 provides mitigation measures and net effects for potential effects related to Significant Woodlands.
Operations
Table 4-4 provides mitigation measures and net effects for potential effects related to Generalized Candidate SWH
and Natural Features.
Table 4-5 provides mitigation measures and net effects for potential effects related to SWH for Plant SOCC.
Table 4-5 provides mitigation measures and net effects for potential effects related to Significant Woodlands.
Where monitoring determines that the mitigation measures are not working as anticipated, contingency measures
are described to address any adverse effects.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 19
Table 4-1: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to Generalized Candidate Significant Wildlife Habitat Resulting from Construction and Decommissioning
Potential Effect Performance
Objectives Mitigation Measures
Likelihood and Significance
of Residual Effects Detailed Monitoring Plan and Contingency Measures
Accidental intrusion into
generalized candidate SWH
resulting in damage to trees.
Avoid accidental
intrusion into SWH.
For collector lines located within Public RoW, vegetation removal (if any) will be kept to a minimum and will be
limited to the road RoW. Trees within the RoW will be pruned through implementation of proper arboricultural
techniques, under supervision of a qualified Arborist or Forester.
Where construction occurs within 30 m of SWH, install and maintain protective fencing to clearly define the
construction area and prevent accidental damage to vegetation.
Where excavation for construction of collector lines is conducted within the rooting zone of trees (e.g., within 5
m of the dripline), implement proper root pruning measures to protect tree roots.
Accidental intrusion will be avoided through
clear delineation of boundaries and
protective fencing as well as root pruning
measures.
Negligible residual effects.
Undertake site inspections by an Environmental Monitor during construction events to
ensure that only specified trees are removed, protective fencing is intact and that there is
no damage caused to remaining trees during construction.
Contingency Measures:
Repair protective fencing if damaged.
Any damaged trees will be pruned through implementation of proper arboricultural
techniques, under supervision of a qualified Arborist or Forester.
In the event that other vegetation is damaged, habitat restoration will occur utilizing
native species suited to the habitat within the area where vegetation was damaged.
Damage to vegetation while
operating equipment.
Minimize damage
to vegetation.
Damage to vegetation avoided through
application of mitigation measures.
Negligible residual effects.
Increased erosion and
sedimentation resulting from
clearing and grubbing,
excavation, backfilling and
stockpiling.
Minimize erosion
and sedimentation
to SWH.
Develop and implement an erosion and sediment control (ESC) plan before commencement of construction as
per Ontario Provincial Standard Specifications (OPSD 219.130).
Utilize erosion blankets, sediment control fencing, straw bales, siltation bags, silt socks (i.e., Flitrexx Soxx), etc.
for construction activities within 30 m of SWH, as appropriate to mitigate potential excessive erosion and
sedimentation.
Extra ESC materials will be kept on hand (i.e., heavy duty silt fencing, straw bales).
Schedule clearing and grubbing, excavation and/or backfilling within 30 m of SWH to avoid times of high runoff
volumes wherever possible. Temporarily suspend work if high runoff volume is noted or excessive flows of
sediment discharges occur until mitigation measures are in place.
Store any stockpiled materials at least 30 m away from SWH.
Keep sediment and erosion control measures in place until disturbed areas have been stabilized (i.e., re-
vegetated).
Erosion control equipment will be removed once it is determined that the threat of erosion no longer exists.
Previously vegetated areas (e.g. grassy lawns and roadsides) will be re-vegetated, where required, using an
appropriate seed mix.
Erosion and sedimentation avoided or
minimized through application of mitigation
measures.
Low likelihood and limited magnitude of
effect as a result.
Contractor to check that erosion control measures are in good repair and properly
functioning prior to conducting daily work and re-install or repair as required prior to
commencing daily construction activities.
Monitor on-site conditions (i.e., ESC, spills, flooding, etc.) where construction occurs
within 30 m of a feature on the following basis:
Regularly during active construction periods;
Prior to, during and post forecasted large rainfall events (>20 millimetres in 24 hours)
or significant snowmelt events (i.e., spring freshet);
Daily during extended rain or snowmelt periods;
Monthly during inactive construction periods, where the site is left alone for 30 days or longer.
Contingency Measures:
Suspend work if excessive flows of sediment discharges occur until additional
mitigation measures are in place (e.g., install the extra ESC materials kept on site,
such as heavy duty silt fencing, straw bales, etc.).
Report the details of a flooding event to MOECC, including a description of any
assessment and remediation undertaken.
Removal/ disturbance of topsoil
and increased soil compaction
from manoeuvring of heavy
machinery, excavation and
backfilling.
Minimize removal/
disturbance of
topsoil and
increased soil
compaction.
Minimize vehicle traffic on exposed soils, avoid compacting or other hardening of natural ground surface, and
avoid the movement of heavy machinery on areas with sensitive slopes.
Removal/disturbance of topsoil and increased
soil compaction avoided or minimized through
application of mitigation measures.
Low likelihood and limited magnitude of
effect as a result.
See erosion and sedimentation above.
Increased erosion and
sedimentation resulting from
directional drilling.
Minimize erosion
and sedimentation
to SWH.
Conduct all drilling by licensed drillers in accordance with Regulation 903 under Ontario Water Resources Act,
R.S.O. 1990.
Set back drill entry and exit pits at least 30 m from SWH.
Monitor SWH for signs of surface disturbance.
Develop “Frac-Out” Contingency Plan outlining steps to contain any chemicals or to avoid contamination of
adjacent SWH including:
Immediately stop all work, including the recycling of drilling mud / lubricant.
Contain any sediments and/or deleterious materials originating from the “frac-out”.
Notify the MOECC Spills Action Centre of the “frac-out” event and the response taken to contain the spill.
Monitor clean-up procedures to ensure they do not result in greater damage than leaving the mud in-place.
If the spill affects a SWH feature, seed or replant the area using the same species to those in the adjacent
area, or allow to re-grow from existing vegetation.
Increased erosion and sedimentation
avoided or minimized through application of
mitigation measures.
Low likelihood; if accidental damage
occurred, negative effects may be
measurable but would likely represent a
small change relative to existing conditions.
See erosion and sedimentation above.
Monitor directional drilling for the duration of such activities by an Environmental Monitor
to ensure that “frac-out” or accidental intrusion does not occur, and if it does, to ensure
that there are no effects on SWH features.
Contingency Measures:
In the event of a “frac-out”, implement the “Frac-Out” Contingency Plan.
Soil or water contamination by
release of pressurized drilling
fluids into SWH from fractures in
substrate (also known as a
‘frac-out’).
Minimize soil or
water
contamination.
Risk of soil or water contamination avoided
or minimized through application of
mitigation measures.
Low likelihood; if accidental damage
occurred, negative effects may be
measurable but would likely represent a
small change relative to existing conditions.
Disturbance and/or mortality to
terrestrial wildlife during
vegetation removal.
Minimize
disturbance and/or
mortality to
terrestrial wildlife.
Time vegetation removal to avoid periods of habitat use to the extent possible, particularly to avoid sensitive life
stages (e.g., breeding season for migratory birds, March 31 to August 31). Undertake active nest surveys by a
qualified Biologist in areas defined as simple habitat* if clearing of vegetation must take place during this
period.
*Note: Environment Canada defines simple habitats refer to habitats that contain few likely nesting spots or a
homogenous community where identification of active nests can be completed with confidence. For instance,
sparsely vegetated habitats may be considered simple habitats, depending on site-specific vegetation cover.
Disturbance and/or mortality to terrestrial
wildlife avoided or minimized through
application of mitigation measures.
Low likelihood and limited magnitude of
effect as a result.
Undertake monthly site inspections by an Environmental Monitor to ensure that only specified
trees are removed, protective fencing is intact and that there is no damage caused to the
remaining trees during construction and undertake active nest surveys by a qualified Biologist
in areas defined as simple habitat* if clearing of vegetation must take place during this period.
Contingency Measures:
Prune any damaged trees through implementation of proper arboricultural techniques,
under supervision of a qualified Arborist or Forester.
If it is determined that additional contingency measures are necessary, further
mitigation measures will be developed and MNRF will be consulted.
Should an active nest be located apply and maintain an appropriate buffer, selected by
a Biologist, based on species specific characteristics until the nest is no longer active.
*Note: Simple habitats refer to habitats that contain few likely nesting spots or a
homogenous community where identification of active nests can be completed with
confidence. For instance, sparsely vegetated habitats may be considered simple habitats,
depending on site-specific vegetation cover.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 20
Table 4-1: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to Generalized Candidate Significant Wildlife Habitat Resulting from Construction and Decommissioning
Potential Effect Performance
Objectives Mitigation Measures
Likelihood and Significance
of Residual Effects Detailed Monitoring Plan and Contingency Measures
Disturbance to or loss of wildlife
habitat, including active bird
nests.
Minimize vegetation
removal and
destruction of bird
nests.
Vegetation removal minimized and
destruction of active bird nests avoided
through application of mitigation measures.
Low likelihood and limited magnitude of
effect as a result.
Soil or water contamination by
oils, gasoline, grease and other
materials from construction
equipment, materials storage
and handling.
Avoid
contamination of
SWH.
Develop and implement Spill Prevention and Response Plan (SPRP) outlining steps to contain any chemicals
or to avoid contamination of adjacent SWH features, and train staff on associated procedures.
Locate site maintenance, vehicle washing and refuelling stations where contaminants are handled at least 30 m
away from SWH. Use spill collection pads for vehicle refuelling and maintenance.
Ensure machinery is maintained free of fluid leaks.
Store any stockpiled materials at least 30 m away from SWH.
Dispose of any waste material from construction activities by authorized and approved off-site vendors.
Contamination avoided or minimized through
application of mitigation measures.
Low likelihood and limited magnitude of
effect as a result.
Contractor to conduct routine inspections of construction equipment for leaks / spills.
Develop an emergency spills plan.
Contingency Measures:
Immediately stop all work until the spill is cleaned up.
Notify MOECC Spills Action Centre of any leaks or spills.
If a spill enters SWH, monitor daily until cleanup is completed. In the event that
vegetation is damaged, habitat restoration will occur utilizing native species suited to
the habitat within the area where vegetation was damaged.
Changes in surface water
drainage patterns.
Minimize changes
in surface water
drainage patterns.
Ensure BMPs are used to maintain current drainage patterns, including:
Implement infiltration techniques to the maximum extent possible.
Minimize paved surfaces and design roads to promote infiltration.
Limit changes in land contours.
Changes in surface water drainage patterns
avoided through mitigation measures.
Low likelihood and limited magnitude of
effect as a result.
Inspect locations within 30 m of SWH features following completion of construction by an
Environmental Monitor to ensure no changes in drainage patterns.
Contingency Measures:
If surface water drainage alterations are detected, undertake corrective measures to
restore drainage pattern.
Table 4-2: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to Significant Wildlife Habitat Resulting from Construction and Decommissioning
Potential Effects Performance
Objectives Mitigation Measures
Likelihood and Significance of
Residual Effects Monitoring Plan and Contingency Measures
Refer to potential effects on
generalized Candidate SWH in
Table 4-1 above.
Refer to
performance
objectives in Table
4-1 above.
For collector lines located within public RoW, vegetation removal (if any) will be kept to a minimum and will be
limited to the road RoW. Construction activities may be undertaken within the full limits of the RoW as he
portions of these features which extend into the RoW are considered disturbed by road operation activities.
Refer to mitigation measures in Table 4-1 above.
Refer to likelihood and significance of
residual effects in Table 4-1 above.
Refer to monitoring plan and contingency measures in Table 4-1 above.
Contingency Measures:
If it is determined that additional contingency measures are necessary, further
mitigation measures will be developed and MNRF will be consulted.
Table 4-3: Mitigation Measures, Net Effects and Monitoring Plan Associated with Significant Woodlands Resulting from Construction and Decommissioning
Potential Effects Performance
Objectives Mitigation Measures
Likelihood and Significance of
Residual Effects Monitoring Plan and Contingency Measures
Intrusion into Significant
Woodlands resulting in damage to
trees.
Avoid intrusion
into Significant
Woodlands.
Where construction occurs within 30 m of Significant Woodlands, install and maintain protective fencing to
clearly define the construction area and prevent accidental damage to vegetation.
Where excavation for construction of collector lines is conducted within the rooting zone of trees (e.g., within 5
m of the dripline), implement appropriate root pruning measures to protect tree roots.
For collector lines located within public RoW, vegetation removal (if any) will be kept to a minimum and will be
limited to the road RoW. Trees within the RoW will be pruned through implementation of proper arboricultural
techniques, under supervision of a qualified Arborist or Forester.
Damage to the woodlands will be avoided
through clear delineation of boundaries and
protective fencing as well as root pruning
measures.
Negligible residual effects.
Undertake site inspections during the construction activity by an Environmental Monitor
to ensure that protective fencing is intact and that there is no damage caused during
active construction of collector lines.
Contingency Measures:
Repair protective fencing if damaged.
Any damaged trees will be pruned through implementation of proper arboricultural
techniques, under supervision of a qualified Arborist or Forester.
In the event that other woodland vegetation is damaged, habitat restoration will occur
utilizing native species suited to the habitat within the area where vegetation was damaged.
Soil or water contamination by oils,
gasoline, grease and other
materials from construction
equipment, materials storage and
handling.
Avoid
contamination of
Significant
Woodlands.
Develop and implement emergency spills plan outlining steps to contain any chemicals or to avoid
contamination of adjacent Significant Woodland features, and train staff on associated procedures.
Locate site maintenance, vehicle washing and refuelling stations where contaminants are handled at least 30
m away from Significant Woodlands. Use spill collection pads for vehicle refuelling and maintenance.
Ensure machinery is maintained free of fluid leaks.
Store any stockpiled materials at least 30 m away from Significant Woodlands.
Dispose of any waste material from construction activities by authorized and approved off-site vendors.
Contamination avoided or minimized through
application of mitigation measures.
Low likelihood and limited magnitude of
effect as a result.
Contractor to conduct routine inspections of construction equipment for leaks / spills.
Develop an emergency spills plan.
Contingency Measures:
Immediately stop all work until the spill is cleaned up.
Notify the Ministry of the Environment and Climate Change (MOECC) Spills Action
Centre of any leaks or spills.
If a spill enters a Significant Woodland, monitor daily until cleanup is completed. In the
event that woodland vegetation is damaged, habitat restoration will occur utilizing
native species suited to the habitat within the area where vegetation was damaged.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 21
Table 4-3: Mitigation Measures, Net Effects and Monitoring Plan Associated with Significant Woodlands Resulting from Construction and Decommissioning
Potential Effects Performance
Objectives Mitigation Measures
Likelihood and Significance of
Residual Effects Monitoring Plan and Contingency Measures
Increased erosion and
sedimentation resulting from
clearing and grubbing, excavation,
backfilling and stockpiling.
Minimize erosion
and sedimentation
to Significant
Woodlands.
Develop and implement an ESC plan before commencement of construction as per Ontario Provincial
Standard Specifications (OPSD 219.130).
Utilize erosion blankets, sediment control fencing, straw bales, siltation bags, silt socks (i.e., Flitrexx Soxx),
etc. for construction activities within 30 m of a Significant Woodland, as appropriate to mitigate potential
excessive erosion and sedimentation.
Extra ESC materials will be kept on hand, (i.e., heavy duty silt fencing, straw bales).
Schedule clearing and grubbing, excavation and/or backfilling within 30 m of Significant Woodlands to avoid
times of high runoff volumes wherever possible. Temporarily suspend work if high runoff volume is noted or
excessive flows of sediment discharges occur until mitigation measures are in place.
Store any stockpiled materials at least 30 m away from Significant Woodlands.
Keep sediment and erosion control measures in place until disturbed areas have been stabilized (i.e., re-
vegetated).
Erosion control equipment will be removed once it is determined that the threat of erosion no longer exists.
Previously vegetated areas (e.g. grassy lawns and roadsides) will be re-vegetated, where required, using an
appropriate seed mix.
Erosion and sedimentation avoided or
minimized through application of mitigation
measures.
Low likelihood and limited magnitude of
effect as a result.
Contractor to check that erosion control measures are in good repair and properly
functioning prior to conducting daily work and re-install or repair as required prior to
commencing daily construction activities.
Monitor on-site conditions (i.e., ESC, flooding, etc.) where construction occurs within 30
m of a significant woodland feature on the following basis:
Regularly during active construction periods;
Prior to, during and post forecasted large rainfall events (>20 millimetres in 24 hours)
or significant snowmelt events (i.e., spring freshet);
Daily during extended rain or snowmelt periods;
Monthly during inactive construction periods, where the site is left alone for 30 days or longer.
Contingency Measures:
Suspend work if excessive flows of sediment discharges occur until additional mitigation
measures are in place (e.g., install the extra ESC materials kept on site, such as heavy
duty silt fencing, straw bales, etc.).
Report the details of a flooding event to MOECC, including a description of any
assessment and remediation undertaken.
Table 4-4: Mitigation Measures, Net Effects and Monitoring Plan Associated with Generalized Candidate Significant Wildlife Habitat Resulting from Operations
Potential Effects Performance
Objectives Mitigation Measures
Likelihood and Significance of
Residual Effects Monitoring Plan and Contingency Measures
No effects on Generalized
Candidate SWH during
operation.
None required.
None required.
None. No monitoring or contingency measures required.
Table 4-5: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to Significant Wildlife Habitat Resulting from Operations
Potential Effects Performance
Objectives Mitigation Measures
Likelihood and Significance of
Residual Effects Monitoring Plan and Contingency Measures
No effects during operation
anticipated due to proximity of
features to Langstaff Road.
None required. None required. None. No monitoring or contingency measures required.
Table 4-6: Mitigation Measures, Net Effects and Monitoring Plan Associated with Significant Woodlands Resulting from Operations
Potential Effects Performance
Objectives Mitigation Measures
Likelihood and Significance of
Residual Effects Monitoring Plan and Contingency Measures
Risk of contamination from oil,
gas, etc. during maintenance of
collector lines immediately
adjacent to Significant
Woodlands.
Avoid
contamination of
Significant
Woodlands.
Develop and implement an emergency spills plan outlining steps to contain any spills during maintenance
activities to avoid contamination of Significant Woodlands, and train staff on associated procedures.
Ensure machinery is maintained free of fluid leaks.
Site maintenance, vehicle washing and refuelling stations where contaminants are handled at least 30 m away
from Significant Woodlands.
Contamination will be avoided or minimized
through application of mitigation measures.
Residual effects considered negligible.
No monitoring required.
Contingency Measures:
Immediately stop all work until the spill is cleaned up.
Notify MOECC Spills Action Centre of any leaks or spills.
If a spill enters a Significant Woodland, monitor daily until cleanup is completed. In the
event that woodland vegetation is damaged, habitat restoration will occur utilizing
native species suited to the habitat within the area where vegetation was damaged.
Accidental damage to
Significant Woodlands resulting
from maintenance of vegetation
near overhead collector lines.
Avoid accidental
damage to
Significant
Woodlands resulting
from maintenance of
vegetation near
overhead collector
lines.
Remove overhanging vegetation in a manner that branches fall away from the Significant Woodland to reduce
damage to adjacent vegetation.
Carry out removal of overhanging vegetation under supervision of a qualified Arborist or Forester.
Time vegetation removal to avoid the breeding season for migratory birds (March 31 to August 31).
Only apply herbicides (if required) when wind speeds are low and no significant precipitation is expected (does
not apply to agricultural practices).
Only use herbicides (if required) approved for use adjacent to water bodies, riparian buffers, or woodland edges
(does not apply to agricultural practices).
Residual effects considered negligible. Removal of overhanging vegetation to be under supervision of a qualified Arborist or
Forester.
Contingency Measures:
Any damaged trees will be pruned through implementation of proper arboricultural
techniques, under supervision of a qualified Arborist or Forester.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 22
4.3 Surface Water and Groundwater
4.3.1 Existing Conditions
4.3.1.1 Surface Water
According to Section 1.1 of the O. Reg. 359/09, as amended, a water body is defined as:
“A lake, permanent stream, intermittent stream and a seepage area but does not include:
a) grassed waterways;
b) temporary channels for surface drainage, such as furrows or shallow channels that can be tilled
and driven through;
c) rock chutes and spillways;
d) roadside ditches that do not contain a permanent or intermittent stream;
e) temporary ponded areas that are normally farmed;
f) dugout ponds; and
g) artificial bodies of water intended for storage, treatment or recirculation of runoff from animal
yards, manure storage facilities and sites and outdoor confinement areas.”
In accordance with the O. Reg. 359/09, background review and site investigations were conducted to identify and
characterize all aquatic features within 120 m of the Project Location. These investigations determined each water
body’s REA water body status as per Section 1.1 of the O. Reg. 359/09. The results of this assessment are
provided in the Water Body Assessment Report (AECOM, 2017c). A total of 34 watercourses and drainage features
and two ponds were assessed and 16 of these water bodies were confirmed as REA water bodies. The results of
the impact assessment of the project on the identified REA water bodies can be found in the Water Body Report
(AECOM, 2016f).
4.3.1.2 Groundwater
An important environmental effect to consider is the potential for the Project to interfere with existing uses of a
water resource.
The following section provides an overview of the Hydrogeological Assessment and Effects Assessment Report
(AECOM, 2017a) for the Project. For further details please refer to the Hydrogeological Assessment and Effects
Assessment Report in Appendix C of the Design and Operations Report.
4.3.1.3 Physiography and Topography
The Project lies within the Chatham Flats, a sub-region of the St. Clair Clay Plains physiographic region (Chapman
and Putnam, 1984). The Chatham Flats is described as a low relief extensive clay plain that slopes gently to the
west toward Lake St. Clair. In the Municipality of Chatham-Kent, a shallow sand layer is found to overlie the
predominantly clay soils (Chapman and Putnam, 1984). According to MOECC water wells records, the sand layer
can be up to 5 m thick in certain areas.
Land use across the Study Area is dominated by a mixture of crop cultivation and livestock agriculture, which has
been made possible by the installation of dredged ditches and tile under-drains to provide satisfactory moisture
conditions within the imperfectly drained soils. Chapman and Putnam (1984) classify the soils of the Chatham flats
as considered highly fertile, producing cash crops in addition to corn and soybeans. Ground surface topography
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 23
within the Study Area is characterized as possessing low relief, with minor undulations commonly associated with
local surface water features. For Study Area, refer to figures in Appendix C (Hydrogeological Assessment and
Effects Assessment) in Design and Operations Report.
Bedrock Geology
Surrounding the Project, thick successions of Upper Devonian aged Paleozoic sedimentary rocks subcrop beneath
the overburden soils. The Project is underlain by bedrock of the Kettle Point Formation, which can be described
generally as a brown to black, laminated, organic-rich shale and siltstone (Armstrong, D.K., and Dodge, J.E.P.,
2007).
Depth to bedrock across the entire Study Area was assessed through a review of Drift Thickness mapping
published by the Ontario Geological Survey, as well as MOECC water well record information. Based on this
review, overburden thickness within the Study Area has been shown to range between approximately 13 m and
43 m, with an average thickness of about 24 m.
Overburden Geology
Thick overburden deposits consisting of both fine and coarse textured glacial sediments and fluvial deposits occur
across the Study Area. The Project is situated within an abandoned lacustrine plain that consists of numerous
alluvial features which were deposited in high level post-glacial and non-glacial lakes which historically occupied
the St. Clair basin. Where the Thames River entered the glacial lakes, deltaic sediments of sand and gravel were
deposited.
Groundwater Resources
Within the Municipality of Chatham-Kent, water for municipal supply is provided from both surface water and
groundwater facilities (Chatham-Kent, 2016) however there are no municipal surface water intakes and/or
groundwater supply wells physically located within the Study Area. Municipal water supply distribution mapping was
not available at the time of report preparation. It is assumed that the majority of the properties within the Project
Location are not serviced by a municipal water supply and therefore the primary potable water source is private
water supply wells owned and operated by individual property owners. Table 4-6 is a record of the wells within the
Study Area provided by MOECC. Available well records indicate that 38% of groundwater use in the Project
Location is for domestic purposes. Agricultural supply use (i.e., irrigation and livestock) accounts for 22% of the
MOECC water well records, followed by commercial and/or industrial (2%), and public sources (i.e., school) (<1%).
Approximately 32% of MOECC water well records did not specify the well use and therefore are classified as
‘Unknown’. Approximately, 6% of the MOECC water well records indicate the well is not used, accounting for
decommissioning records and dry wells.
Table 4-7: Summary of MOECC Water Well Record Information
Primary Water Use Number of Well
Records
Well Depth
(m) Primary Well Type
Commercial/Industrial 7 21.3 to 37.2 1 Overburden, 6 Bedrock
Domestic 150 6.4 to 45.7 54 overburden, 94 bedrock, 2 unknown
Irrigation/Livestock 89 14.9 to 43.9 41 overburden, 48 bedrock
Public 3 21.3 to 31.4 3 bedrock
Municipal 0 N/A N/A
Not Used 22 16.2 to 35.4 3 overburden, 10 bedrock, 9 unknown
Unknown 127 3.4 to 46.3 22 overburden, 83 bedrock, 22 unknown
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 24
4.3.2 Potential Effects, Mitigation Measures and Net Effects
4.3.2.1 Surface Water
Construction and Decommissioning
Table 4-8 identifies potential effects on surface water resources that could occur during the construction and
decommissioning phases of the Project and identifies mitigation strategies and a monitoring plan.
Operations
Table 4-9 identifies potential effects on surface water resources that could occur during the operations phase of the
Project and identifies mitigation strategies and a monitoring plan.
Where monitoring determines that the mitigation measures are not working as anticipated, contingency measures
are described to address any adverse effects.
Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to Surface Water Resulting
from Construction and Decommissioning
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 25
Table 4-8: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to Surface Water Resulting from Construction and Decommissioning
Potential Effect Performance Objectives Mitigation Strategy Net Effects Monitoring Plan
Increased erosion, sedimentation, and
turbidity resulting from removal of
vegetation and exposure of soils.
Excess suspended sediment that is
carried downstream during the
installation and removal of temporary
structures.
Minimize erosion,
sedimentation and turbidity.
Minimize transfer of sediment
downstream via stream flow.
Develop an ESC Protocol to minimize the potential for construction related sediment release into
nearby water bodies (ESC Guideline), and prepare ESC condition reports as part of the
monitoring and maintenance plan.
Remove construction debris from the site and stabilize it to prevent it from entering the nearby
water bodies.
Avoid construction during high volume rain events, as determined in consultation with an
Environmental Monitor, and significant snow melt/thaw events, where possible, and resume once
soils have been stabilized or mitigation measures have been installed (e.g., heavy-duty silt
fences, coir logs, or straw mats around any soil stockpiles) to avoid risk of erosion, soil
compaction or the potential for sediment release into nearby water bodies.
Monitor ESC systems frequently for effectiveness, repairing deficient controls in a timely manner and
using an adaptive management approach when deemed appropriate.
Time clearing, grubbing, and grading activities to avoid seasonally wet periods, where possible.
Develop a Flood Response Protocol (FRP) to deal with on-site flooding in order to mitigate any
possible effects to the aquatic environment.
The application of the ESC Plan and maintenance of ESC
systems will prevent impacts to water bodies from
increased erosion, sedimentation, and turbidity due to the
removal of vegetation. In addition, the removal of
vegetation will be localized.
Monitor on-site conditions (i.e., ESC measures, spills, flooding)
Weekly during active construction periods
During and after forecasted rain events or significant snowmelt
events, as determined in consultation with an Environmental
Monitor
Monthly, where needed, during inactive construction periods
where mitigation measures remained installed
As detailed in the ESC Plan, SPRP, and FRP
Monitor meteorological conditions from Environment and Climate
Change Canada
Daily review of weather forecasts during active construction
periods
Degradation of water quality from
contamination by oils, gasoline,
grease, and other materials due to
accidental spills, as a result of the
proximity of construction vehicles and
machinery to water bodies.
Changes in water chemistry resulting
in decreased water quality by
accidental spills of oils, gasoline,
grease, and other materials.
Minimize water contamination
Minimize soil contamination.
Operate construction equipment (e.g., cranes, back hoes) in a manner that minimizes disturbance
to the water body banks and stays outside of the water body and bank area. Machinery should
arrive on site in clean condition.
Frequent checks and maintenance should ensure that no fluid leaks occur. Machinery must be
refuelled, washed, and serviced a minimum of 30 m away from all water bodies and other
drainage features to prevent any deleterious substances from entering a water body.
Store fuel and other construction related materials securely away from any drainage features and
locate construction staging areas 30 m away from any water body, where possible.
Develop a SPRP prior to commencement of construction that provides a detailed response
system to deal with events such as the release of petroleum, oils and lubricants or other
hazardous liquids and chemicals. Keep a spill kit on site at all times and train on-site workers in
the proper use of this kit and to be fully aware of the SPRP.
Remove construction debris from the site and stabilize it to prevent debris from entering the
nearby water bodies.
Remove and dispose of any waste generated from the site appropriately off-site according to
provincial standards.
Horizontal directional drilling should be executed at a depth that limits the potential impacts
associated with the possibility of a ‘frac-out’ (i.e., the escape of drilling mud and/or fluids into the
environment as a result of a spill, drilling tunnel collapse or rupture of mud to the surface due to
excessive pressure from an obstruction within the borehole). A minimum depth will be provided on
design drawings and will be included in discussions relevant agencies, where required.
Restrict construction equipment to designated, controlled vehicle access routes to minimize the
potential for soil compaction.
Potential impacts to a water body associated with the
unforeseen spill of drill fluid will be mitigated through the
application of a SPRP and an emergency ‘frac out’
response plan.
Emergency ‘frac-out’ response plan will mitigate any
potential impact to water bodies.
Changes in water quality are highly unlikely and related
only to spills. Following the SRP and locating machine
fuelling and maintenance activities away from water bodies
will prevent contamination of water bodies.
Conduct daily inspections of construction equipment for leaks/spills
Implement the following contingency measures in the event of a spill:
Immediately stop all work until the spill is cleaned up.
Install a spill collection pad for refuelling and maintenance.
Notify MOECC’s Spills Action Centre of any leaks or spills.
Assess and remediate affected soils and water by using a spill kit
kept on site.
Monitor daily to ensure proper cleanup is completed.
Implement any other general water quality parameters as required by
to MOECC Policy 2 standards for discharging to a waterbody
Soil compaction as a result of heavy
machinery and the stockpiling of heavy
materials (i.e., soils) reducing the
permeability of soils and their ability to
retain water during rain/snow melt events
resulting in an increase in surface water
runoff which could increase the erosion
potential and the amount of sediment
being transported into adjacent water
bodies. Soil compaction can restrict re-
vegetation of construction and temporary
lay down areas.
Increase in impervious surfaces and
increased surface runoff down a steep
slope (i.e., a valley, or steep side
slopes of municipal drains), resulting
from re-grading of land and resulting in
increased potential for erosion and
downstream sedimentation.
Minimize the increase of
impervious surfaces and
surface runoff.
Minimize soil compaction.
Time clearing, grubbing, and grading activities to avoid seasonally wet periods, where possible.
Operate construction equipment (e.g., cranes, back hoes) in a manner that minimizes disturbance
to the water body banks and stays outside of the water body and bank area.
Confine construction equipment to designated, controlled vehicle access routes to minimize the
potential for soil compaction.
Avoid construction during high volume rain events, as determined in consultation with an
Environmental Monitor and significant snow melt/thaw events, where possible, and resume once
soils have been stabilized or mitigation measures have been installed (e.g., heavy-duty silt
fences, coir logs, or straw mats around any soil stockpiles) to avoid risk of erosion, soil
compaction or the potential for sediment release into nearby water bodies.
If insufficient time is available in the growing season to establish vegetative cover, apply
overwintering treatments such as erosion control blankets, fibre matting, rock (i.e., large, clean
angular rocks) reinforcement/armoring or equivalent to contain the site over the winter period.
Previously vegetated areas (e.g. grassy lawns and roadsides) will be re-vegetated, where
required, using an appropriate seed mix.
Change in flow patterns, flooding, erosion and
sedimentation are highly unlikely following the application
of the ESC Plan.
The reduction of soil permeability and infiltration capacity
as a result of heavy machinery and stockpiling of heavy
materials is minimal, localized, and temporary in nature is
highly unlikely. Stockpiling of material and the use of heavy
machinery is expected to be localized and temporary in
nature.
Stockpiles of debris will be removed from the site and
stabilized according to the ESC Plan. Change in flow
patterns, flooding, erosion and sedimentation are highly
unlikely following the application of the ESC Plan.
See erosion and sedimentation above.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 26
Table 4-8: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to Surface Water Resulting from Construction and Decommissioning
Potential Effect Performance Objectives Mitigation Strategy Net Effects Monitoring Plan
Stockpiles of construction related
materials, such as soil, shrubs, trees
and root wads in or near a waterbody
can result in debris or sediment
entering the water body if the
stockpiles are not properly contained.
Minimize disturbance to local
drainage patterns and
flooding.
Minimize erosion and
sedimentation, and water
quality impairment.
Schedule construction activities near water (within 30 m) to occur within the low flow period of the
late summer months, where possible, to avoid or minimize impacts.
Remove construction debris from the site and stabilize it to prevent debris from entering the
nearby water bodies.
Remove and dispose of any waste generated from the site appropriately off-site according to
provincial standards.
Avoid construction during high volume rain events, as determined in consultation with an
Environmental Monitor and significant snow melt/thaw events, where possible, and resume once
soils have been stabilized or mitigation measures have been installed (e.g., heavy-duty silt
fences, coir logs, or straw mats around any soil stockpiles) to avoid risk of erosion, soil
compaction or the potential for sediment release into nearby water bodies.
FRP to deal with on-site flooding in order to mitigate any possible effects to the aquatic environment.
Stockpiles of debris will be removed from the site and
stabilized according to the ESC Plan.
See erosion and sedimentation above.
Minor, isolated, short term dewatering
of shallow groundwater from
excavation areas required when
excavation intercepts an area of
shallow groundwater table conditions.
Minimize short term
dewatering activities when
possible.
Dewatering discharge rates should be evaluated as to not result in erosion and sedimentation to
receiving water body.
If discharging to a municipal storm sewer system, ensure that groundwater quality meets the
objectives of the municipal storm sewer by-law prior to discharge. To mitigate potential effects
associated with the discharge, sample for total suspended solids (TSS) prior to discharge to
ensure the water is suitable for discharge and will not result in an impact to the receiving water
body. If the groundwater is not suitable for discharge, identify alternate disposal locations or carry
out adequate treatment.
To mitigate potential effects associated with the discharge, sample for TSS prior to discharge to ensure
the water is suitable for discharge and will not result in an impact to the receiving water body. If the
groundwater is not suitable for discharge, identify alternate disposal locations or carry out adequate
treatment. The success of all mitigation will be verified though groundwater quality sampling.
Install an in-stream sediment filter (e.g., Siltsoxx or Filtersoxx) downstream of a water containment
structure so that dewatering discharge is dissipated (i.e., splash pads, sand bags, hay bales etc.)
which may require splitting discharge to more than one location.
The extent of dewatering will be localized and minimal.
Impacts to water levels due to dewatering activities are
highly unlikely. Monitoring water levels immediately
before, during and after dewatering activities will help to
mitigate any impacts.
Monitor water quality (TSS) prior to discharge, where required, during
construction.
Monitor end point of dewatering discharge for water quality and
erosion.
Completion of In-water Work
Requiring In-stream Dewatering and
the Construction of Temporary Dykes
or Cofferdams
Release of suspended sediment that
is carried downstream during the
installation and removal of temporary
structures.
Minimize erosion and
sedimentation, and water
quality impairment.
Limit in-stream construction time to a minimum and maintain a vegetative buffer zone, three
metres from the water’s edge, until immediately prior to in-stream excavation. To avoid
contamination of water, construction equipment is not permitted to travel along the bed of a
watercourse and fording of streams should not take place unless approved by MNRF and the
conservation authority.
Install an in-stream sediment filter (e.g., Siltsoxx or Filtersoxx) downstream of a water
containment structure so that dewatering discharge is dissipated (i.e., splash pads, sand bags,
hay bales etc.) which may require splitting discharge to more than one location.
Dewatering discharge rates should be evaluated as to not result in erosion and sedimentation to
receiving water body.
Following completion of a water crossing, the stream channel must be restored to a state similar
to pre-existing conditions. All temporary structures and construction debris/materials must be
removed and the stream morphology must be reshaped to its original or approved configuration.
Bank stabilization, even if temporary, must occur within 10 days of stream bed back-filling and
the banks should be re-contoured to their original shape.
If required, perform in-water work in dry conditions. If this is not possible, short-term isolated
dewatering will be required. Prior to dewatering, isolate the work area with the installation of a
temporary water containment structure. The structure should form an impermeable enclosure that will
prevent debris and sediment from escaping into the surrounding water body. Construct a by-pass
channel to maintain flow through the water body and prevent back flooding, which could ultimately
overtop the water containment structure. Additional permits may be required for in-water work.
If in-water work is required (e.g., for culvert installation and or collector lines installation), adhere
to required timing windows confirmed through consultation with regulatory agencies.
If dewatering is required, isolate the work area and establish a by-pass channel to maintain flow
quantity through the water body.
Dewatering discharge rates should be evaluated as to not result in erosion and sedimentation to
receiving water body.
Collect and relocate fish to a suitable location, preferably downstream and away from the
construction area, prior to surface water dewatering. This should be executed through the
development of a Fish Salvage Plan and by a qualified fisheries biologist.
The disruption of surface drainage patterns associated
with in-water works will be temporary and is not
anticipated to have residual impacts on surface water.
Working within the appropriate timing window will help to
mitigate any impacts to fish and fish habitat.
The release of excess suspended sediment downstream
is unlikely and may occur only during in water work.
Performing in water work in the dry and isolating the work
area will prevent increases in suspended sediment if in
water work is required.
Monitor end point of dewatering discharge for water quality and
erosion.
Daily erosion checks during discharge of water.
Monitor water quality (TSS) prior to discharge, where required,
during construction.
Other general water quality parameters as required by to meet
MOECC Policy 2 standards for discharging to a water body
Monitor by-pass channel, where applicable.
Perform daily checks of the channel to ensure it is functioning
appropriately and water is flowing through as designed.
Monitor to ensure that fish displaced as result of dewatering activities
are returned to the watercourse in good condition.
Consult with MNRF to determine additional contingency measures if
necessary.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 27
Table 4-8: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to Surface Water Resulting from Construction and Decommissioning
Potential Effect Performance Objectives Mitigation Strategy Net Effects Monitoring Plan
Degradation of water quality from
contamination drilling frac-out.
Minimize disturbance to
aquatic habitat as a result of
potential frac-outs.
If in-water work is required (e.g., for collector lines installation), adhere to required timing
windows confirmed through consultation with regulatory agencies, including the MNRF.
Locate drilling entry/exit shafts beyond the top of bank, at a distance that allows the minimum
depth, as identified on design drawings, to be reached while below the water body. This distance
should be agreed upon with relevant agencies, where required.
Develop and implement an emergency ‘frac-out’ response plan including steps to contain,
monitor and clean-up in response to the event.
Potential impacts to a water body associated with the
unforeseen spill of drill fluid will be mitigated through the
application of a SPRP and an emergency ‘frac out’
response plan.
Emergency ‘frac-out’ response plan will mitigate any
potential impact to water bodies.
Monitor aquatic habitat at drilling locations, if required (i.e., potential
frac-out).
Continuous monitoring by an Environmental Monitor, during drilling
operations underneath a water body, to identify frac-out (if it occurs).
Table 4-9: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to Surface Water Resulting from Operations
Potential Effect Performance Objective Mitigation Strategy Net Effects Monitoring Plan and Contingency Measures
Vegetation Control and Increased Vehicle Use:
Degradation of water quality from contamination by oils,
gasoline, grease, and other materials due to accidental
spills, as a result of the proximity of construction vehicles
and machinery to water bodies.
Increase in surface runoff resulting from clearing of
vegetation, increase in impervious surfaces, and soil
compaction from vehicles accessing the site, resulting in
increased erosion and sedimentation.
Minimize erosion, sedimentation and turbidity
resulting from clearing of vegetation.
Minimize water contamination.
Store fuel and maintenance related materials at least 30 m away
from any drainage features, where possible.
Implement a SPRP to provide a detailed response system to deal
with events such as the release of petroleum, oils and lubricants or
other hazardous liquids and chemicals. A spill kit must also be kept
on site at all times and on-site workers must be trained in the use of
this kit and be fully aware of the SRP.
Develop an ESC Protocol that will minimize the potential for
operations related sediment release into nearby water bodies (ESC
Guideline).
Confine vehicles to designated controlled access routes to minimize
the potential for soil compaction.
Spills during the operational phase are rare. The
application of a SPRP will mitigate any potential
impact to water bodies.
The increase in impervious surfaces is minimal and
highly localized. Vehicles will be confined to
designated access routes.
The application of the ESC Plan and maintenance
of ESC systems will prevent impacts to water
bodies from increased erosion, sedimentation, and
turbidity due to the removal of upland riparian
vegetation, increased impervious surfaces, and soil
compaction.
No monitoring or contingency measures required.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 28
4.3.2.2 Groundwater
Construction and Decommissioning
Table 4-10 identifies potential effects on groundwater resources that could occur during the construction and
decommissioning phases of the Project and describes mitigation strategies and a monitoring plan.
Operations
Table 4-11 identifies potential effects on groundwater resources that could occur during the operations phase of the
Project and describes mitigation strategies and a monitoring plan.
Where monitoring determines that the mitigation measures are not working as anticipated, contingency measures
are described to address any adverse effects.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 29
Table 4-10: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to Groundwater Resulting from Construction and Decommissioning
Potential Effect Performance Objectives Mitigation Strategy Net Effects Monitoring Plan and
Contingency Measures
Temporary reduction in groundwater flow to
natural features (waterbodies, watercourses and
wetlands) during groundwater dewatering
activities associated with turbine foundation
construction.
Minimize reduction of groundwater
contribution to nearby natural
features.
Direct dewatering discharge to the downgradient watercourse
(following sediment and erosion control practices) to negate the
potential that groundwater drawdown will decrease base flow into
streams and groundwater discharge into wetlands.
Limit duration of dewatering to as short a time frame as possible.
Implement groundwater cut-offs, where practical, to limit groundwater
taking quantities.
Reduction in groundwater quantity and quality minimized through
application of mitigation measures.
Low likelihood and negligible magnitude of long term effects based on
the amount of dewatering required and the duration of expected
dewatering activities.
Should groundwater dewatering activities be expected to exceed
50,000 L/day, the following measures will be implemented:
Inlet pump head shall be surrounded with clear stone and filter
fabric.
The discharge shall be regulated at such a rate that there is no
flooding in the receiving water body and that no soil erosion is
caused that impacts the receiving water body.
Dewatering effluent shall be discharged more than 30 m from a
watercourse or receiving water body.
The discharge shall be treated for temperature and suspended
sediment to ensure that dewatering discharge quality is equal to or
better than water quality in the receiving watercourse or waterbody
as to not result in additional sediment input.
Dewatering effluent discharged to a receiving waterbody shall be
free of hydrocarbons and/or other visibly detected contaminants.
Temporary reduction in groundwater quantity and
quality to existing groundwater users (private
water wells) during groundwater dewatering
activities associated with turbine foundation
construction.
Minimize reduction of groundwater
quantity and quality to existing
groundwater users.
Limit duration of dewatering to as short a time frame as possible.
Implement groundwater cut-offs, where practical, to limit groundwater
taking quantities.
Reduction in groundwater quantity and quality minimized through
application of mitigation measures.
Low likelihood and negligible magnitude of long term effects based on
the amount of dewatering required and the duration of expected
dewatering activities.
Should groundwater dewatering activities exceed 50,000 L/day and a
private water well becomes dry or water quality is impaired as a likely
result of such activities based on a qualified expert’s opinion, a
temporary potable water supply will be provided to the property owner
and a qualified expert (P.Eng or P.Geo) will establish a contingency
plan to include remedial measures to resolve any impacts to the
affected well.
Contamination of groundwater resources due to
accidental spills or releases of contaminants (i.e.,
fuel, lubricating oils and other fluids) during the
refuelling, operation or maintenance of Project
equipment.
Prevent contaminant discharge to
the environment.
Develop a spill response plan and train staff on procedures and
protocols.
Refuel Project equipment and vehicles on spill collection pads and/or
in designated areas.
Dispose of any waste material from construction activities by
authorized and approved off-site vendors.
Groundwater contamination minimized through application of
mitigation measures.
Low likelihood and limited magnitude of effects on groundwater.
Routine inspections performed by the contractor of construction
equipment for leaks and spills.
In the event of a contaminant spill all work will stop until the spill is
cleaned up.
Notify MOECC’s Spill Action Centre, where appropriate, of any leaks
or spills.
Reduction in groundwater quantity from an
increase in impervious area created by turbine
foundations and access roads resulting in
reduced infiltration to unconfined aquifers (coarse-
textured lacustrine deposit)
Minimize the increase in impervious
areas.
Direct runoff from the constructed impervious surfaces to ground
surface to prevent any decrease in infiltration and recharge.
Minimize vehicle and construction equipment traffic on exposed soils
to avoid compaction and a reduction of water infiltration.
Reduced infiltration near groundwater recharge areas minimized
through application of mitigation measures.
Low likelihood and limited magnitude of effects based on surface area
of turbine foundations and the primary land use of surrounding area.
No monitoring or contingency measures required.
Table 4-11: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to Groundwater Resulting from Operations
Potential Effect Performance Objective Mitigation Strategy Net Effects Monitoring Plan and Contingency Measures
Contamination of groundwater resources due to accidental
spills or releases of contaminants (i.e., fuel, lubricating oils
and other fluids) during the refuelling, operation or
maintenance of Project equipment.
Prevent contaminant discharge to the
environment.
Develop a SRP and train staff on procedures and protocols.
Refuel Project equipment and vehicles on spill collection pads
and/or in designated areas.
Dispose of any waste material from construction activities by
authorized and approved off-site vendors.
Groundwater contamination minimized through
application of mitigation measures.
Low likelihood and limited magnitude of effects on
groundwater.
Routine inspections performed by the contractor of construction
equipment for leaks and spills.
In the event of a contaminant spill all work will stop until the spill is
cleaned up.
Notify MOECC’s Spill Action Centre, where appropriate, of any
leaks or spills.
Reduction in groundwater quantity from an increase in
impervious area created by turbine foundations and access
roads resulting in reduced infiltration to unconfined aquifers
(coarse-textured lacustrine deposit)
Minimize the increase in impervious areas. Direct runoff from the constructed impervious surfaces to ground
surface to prevent any decrease in infiltration and recharge.
Minimize vehicle and construction equipment traffic on exposed
soils to avoid compaction and a reduction of water infiltration.
Reduced infiltration near groundwater recharge
areas minimized through application of mitigation
measures.
Low likelihood and limited magnitude of effects
based on surface area of turbine foundations and
the primary land use of surrounding area.
No monitoring or contingency measures required.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 30
4.4 Emission to Air, including Odour and Dust
4.4.1 Existing Conditions
The Project Location is dominated by agricultural production activities and typical farm practices, which include the
use of oversized machinery that are driven in fields as well as on rural, typically gravel, roadways. Periodic odours
in rural areas from activities like the spreading of manure as well as increased dust particulate are considered to be
normal nuisances associated with typical agricultural practices (Ontario Ministry of Agriculture, Food, and Rural
Affairs, 2005).
4.4.2 Potential Effects, Mitigation Measures and Net Effects
Construction and Decommissioning
The Project activities associated with the site preparation and construction phase and the decommissioning phase
will lead to emission products, including but not limited to GHGs (e.g., methane, and carbon dioxide), nitrogen
dioxide, sulphur dioxide and suspended particles from vehicles and machinery operation. The emissions levels will
fluctuate through the various construction and decommissioning related activities, with access road construction /
reclamation, site grading, and preparation / reclamation of staging and laydown areas having the highest potential
for emissions because of increased construction or decommissioning equipment activities during this time. In
general these emissions will be temporary and localized.
No emissions of odours are anticipated during construction or decommissioning activities.
Table 4-12 identifies potential effects on air quality that could occur during the construction and decommissioning
phases of the Project and identifies mitigation strategies and a monitoring plan.
Table 4-12: Mitigation Measures, Net Effects and Monitoring Plan Associated with Emissions to
Air Resulting from Construction and Decommissioning
Potential Effect Performance
Objectives Mitigation Strategy Net Effects
Monitoring Plan and
Contingency Measures
Fugitive Dust and
Vehicle Emissions
(including GHGs).
No persistent dust
films (observable
build-up) on nearby
properties or
vegetation.
Limited release of air
emissions.
Implement a speed limit for
construction equipment and
trucks on access roads.
Apply dust suppressants
(e.g., water or environmental
friendly dust suppressants)
to unpaved areas at an
environmental acceptable
rate to minimize the release
of dust.
Re-vegetate cleared areas
as soon as possible.
Limit unnecessary idling of
vehicles.
Implement construction
speed limit on unpaved
roads.
Increased dust and air
emissions minimized
through application of
mitigation measures.
High likelihood of effects
occurring; however, any
dust and air emissions are
short-term and localized so
the magnitude of such
effects will be limited.
Monitoring:
Monitor and track
complaints through the
Project operations staff
contact number according to
the Emergency Response
and Communications Plan
(see Design and Operations
Report).
Monitor dust and debris
control systems at blasting
sites, in the unlikely event that
they are required, to ensure
their proper installation.
Contingency Measures:
Review of proposed
mitigation measures.
Review of speed limit on
access roads.
Reduction in Surface
Water Quality as a
Result of Dust
Emissions.
No persistent dust
films on adjacent
water bodies; no
measurable change
in TSS.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 31
Operations
During the operation of the Project, maintenance activities have the potential to cause infrequent, localized and
short-term fugitive dust and emissions typical to the operation of motorized vehicles. These emissions are expected
to be considerably lower in magnitude than during the construction and the decommissioning activities.
No emissions of odours are anticipated during operations.
Table 4-13 identifies potential effects on air quality that could occur during the operations phase of the Project and
identifies mitigation strategies and a monitoring plan. Where monitoring determines that the mitigation measures
are not working as anticipated, contingency measures are described to address any adverse effects.
Table 4-13: Mitigation Measures, Net Effects and Monitoring Plan Associated with Emissions to
Air Resulting from Operations
Potential Effect Performance
Objective Mitigation Strategy Net Effects
Monitoring Plan and
Contingency Measures
Fugitive Dust and
Vehicle Emissions
(including GHGs).
No persistent dust
films (observable
build-up) on nearby
properties, vegetation
and water bodies.
Limited release of air
emissions.
Minimize impacts to
natural features and
associated wildlife
habitats.
Implement and enforce speed
limits for Project equipment and
trucks.
Apply dust suppressants to
unpaved areas, when
necessary, to suppress dust.
Application frequency will vary,
but will be determined by site-
specific weather conditions,
including recent precipitation,
temperatures and wind speeds.
Properly maintain all vehicles.
Direct project staff to limit the
idling of engines, where
possible.
Emissions of contaminants
from maintenance vehicles
minimized through
application of mitigation
measures.
Dust from vehicular traffic
minimized through
application of mitigation
measures.
o Low likelihood of
occurring and limited
magnitude due to limited
volume of maintenance
vehicles.
Monitoring:
Monitor and track
complaints through the
Project operations staff
contact number according
to the Emergency
Response and
Communications Plan. If
complaints are received by
an Otter Creek operations
staff member then a visual
inspection may be carried
out.
Contingency Measures:
Review of proposed
mitigation measures.
4.5 Noise
4.5.1 Existing Conditions
As mentioned in the above section, land use within the Project Location is primarily agricultural and exposed to
existing farm practices. These practices include the operation of large agricultural machinery at off hours as well as
increased traffic in the region relating to the hauling and storage of crops. Periodic increased noise associated with
regular farm operations is considered to be a normal nuisance associated with typical agricultural practices (Ontario
Ministry of Agriculture, Food, and Rural Affairs, 2005).
4.5.2 Potential Effects, Mitigation Measures and Net Effects
Construction and Decommissioning
The operation of heavy construction vehicles and temporary generators could also result in nuisance noise at
nearby residents or businesses. Noise may be highest during land clearing and other activities that involve
significant levels of material handling (e.g., aggregate laydown for access road construction and preparation for the
installation of underground collector lines).
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 32
Table 4-14 identifies potential effects from nuisance noise that could occur during the construction and
decommissioning phases of the Project and identifies mitigation strategies and a monitoring plan.
Operations
The operation of wind turbine generators and the electrical substation will generate noise that has the potential to
affect local residents. Table 4-15 identifies potential effects from noise that could occur during the operations phase
of the Project and identifies mitigation strategies and a monitoring plan.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 33
Table 4-14: Mitigation Measures, Net Effects and Monitoring Plan Associated with Noise Resulting from Construction and Decommissioning
Potential Effect Performance Objectives Mitigation Strategy Net Effects Monitoring Plan and Contingency Measures
Increased Noise Due to Construction and
Decommissioning Activity.
Adherence to Municipality of Chatham-Kent
Noise By-law no. 41-2004 and amendment
43-2005.
Ensure that construction equipment is frequently maintained
and kept in good working condition.
Ensure that sound emissions from construction equipment
not exceed guidelines specified in MOECC publication NPC-
115 and manufacturer recommendations.
Schedule activities to comply with noise by-laws, where
possible.
Implement construction speed limit on unpaved roads.
In the unlikely event that blasting activities are required
during excavation of wind turbine foundations, the following
mitigation measures are proposed:
Notify the municipality and local emergency services
departments of blasting prior to occurring;
Adhere to the Municipality of Chatham-Kent’s Noise By-law,
unless an exemption is received.
High likelihood of increased sound during construction;
however, the effect will be short-term, localized, and
limited in magnitude.
Monitoring:
Monitor complaints through the Project operations staff contact number according to the
Emergency Response and Communications Plan (see Design and Operations Report).
Contingency Measures:
Repair equipment that is unable to meet noise standards.
If sound complaints are received, conduct an investigation to determine the source of the
problem.
Table 4-15: Mitigation Measures, Net Effects and Monitoring Plan Associated with Noise Resulting from Operations
Potential Effect Performance Objective Mitigation Strategy Net Effects Monitoring Plan and Contingency Measures
Increased Noise Levels Experienced by
Non-Participating Receptors Due to
Turbine Operation.
Noise at all non-participating noise
receptors below 40 dBA.
Monitor equipment and assess the need for repair of
equipment, as required.
Noise levels experienced by non-participating receptors
(residents located on non-participating properties) due to
turbine operation will comply with the applicable noise
regulations and guidelines.
Monitoring:
Monitor wind turbine performance remotely or from the operations and maintenance
building.
Monitor and track complaints through the Project operations staff contact number according
to the Emergency Response and Communications Plan. If complaints are received by an
Otter Creek operations staff member then an on-site inspection may be carried out.
Contingency Measures:
Adjust wind turbine that are unable to meet operational standards.
If sound complaints are received, conduct an investigation to determine the source of the
problem.
Increased Noise Levels Experienced by
Non-Participating Receptors Due to
Substation Operation.
Noise at all non-participating noise
receptors below 40 dBA.
Monitor equipment and assess the need for repair of
equipment, as required.
Noise levels experienced by non-participating receptors
near the substation will be below applicable noise
regulations and guidelines due to setback requirements
and application of mitigation measures.
Monitoring:
Monitor and track complaints and conduct follow-up monitoring (see Complaints Resolution
Process in Emergency Response and Communications Plan).
Contingency Measures:
Repair equipment that is unable to meet operational standards.
If noise complaints are received, conduct an investigation to determine the source of the
problem.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 34
4.6 Local Interests, Land Use and Infrastructure
Local interests, land uses and infrastructure were taken into consideration during the design phase of the Project.
The following section describes the results of the effects assessment for the operations phase of the Project.
Effects on agricultural use, adjacent residences and properties, roads, the local airport, and conservation areas
were included in this assessment. All turbines have been sited to meet or exceed MOECC’s required setbacks.
4.6.1 Existing Conditions
Land Use
The Project is located within the single tier Municipality of Chatham-Kent, Ontario. Chatham-Kent’s Official Plan
(2016) and Zoning By-law (2015) show that land uses in the Project Location are predominantly designated and
zoned for agricultural use. Other land uses within and adjacent to the Project Location include non-farm residential
uses on separate lots created through severances for farm retirement lots and surplus farm dwelling lots.
There is no record of site contamination within the Project Location which was confirmed through a review of the
MOECC’s Records of Site Condition (MOECC, 2016.).
Provincial and Local Infrastructure
As part of the REA process, Otter Creek will consult with the Municipality of Chatham-Kent and MTO to determine
what effects the Project might have on local services and infrastructure. Such issues may include, but are not
limited to, effects to underground water and wastewater infrastructure, roads and traffic, emergency management
and response, and building code requirements.
Adjacent Businesses and Properties
A Property Line Setback Assessment has been prepared to address Section 53 of O. Reg. 359/09, as amended,
(see Appendix D of the Design and Operations Report). This section of the regulation requires the identification of
any impacts to businesses, infrastructure, properties or land use activities resulting from a turbine location being
proposed at a distance equal to or less than the hub height of the turbine from an adjacent property line. Eleven
turbines were identified to require assessment due to their proximity to adjacent property lines. The Property Line
Setback Assessment confirmed that adverse impacts to the adjacent parcels may include damage to field crops in
the unlikely event of a turbine failure. However, this potential impact already exists at a height equivalent to the
height of turbine base to top of hub and is not increased by a decreasing this setback.
Local Airport
The Chatham-Kent Municipal Airport is located approximately 37 km away from the southern extent of the Project
Location. Otter Creek submitted a completed Land Use Proposal Submission Form to NAV Canada to receive input
if the Project layout will cause interference or conflicts associated to Aviation Safety in the area. NAV Canada
confirmed there are no objections related to the Project.
Telecommunication and Weather Towers
Otter Creek has provided Project notices to telecommunication companies in the area to provide details on the
Project. To date, Otter Creek has not received any concerns from these companies.
The closest Environment Canada weather radar tower is located in Exeter, Ontario and such, the Project will not
have any impact on the operations of the weather radar tower.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 35
Conservation Areas
The Project Location is situated within the boundaries of SCRCA. No conservation areas are located within the
Project Location.
Local Roads and Traffic
The Project Location map (Figure 1-1) displays existing local and provincial roads in proximity to the Project
Location. As part of the REA process, Otter Creek is continuing consultation with the Municipality of Chatham-Kent
to determine what effects the Project might have on local services and infrastructure.
Aboriginal or Treaty Interests
To ensure aboriginal or treaty interests were considered, Otter Creek submitted the appropriate documents to the
MOECC in order to receive the Aboriginal Contact List. MOECC confirmed that the following communities may
have an interest in the Project:
Walpole Island First Nation;
Aamjiwnaang First Nation;
Oneida Nation of the Thames;
Chippewas of the Thames First Nation;
Chippewas of Kettle and Stony Point First Nation;
Caldwell First Nation;
Moravian of the Thames; and
Munsee-Delaware Nation.
4.6.2 Potential Effects, Mitigation Measures and Net Effects
Construction and Decommissioning
There will be a temporary loss of agricultural land during construction and installation activities as a result of
temporary Project components, laydown areas and the construction working areas. However, these areas will be
small relative to the total land area within the CDA, and these lands will be returned to a state similar to pre-existing
land use after construction and installation activities are completed, unless otherwise agreed upon with the
landowner. During the construction of access roads and crane mats, as well as the installation of collector lines,
there is the potential to disturb existing agricultural drainage tiles. In the event that a drain would be severed or
damaged, the affected drain will be capped and repaired as soon as reasonably possible to avoid negative impacts
to existing drainage patterns.
The road capacity and local traffic may also be affected during construction related activities. The delivery of
construction equipment and project infrastructure, and construction of new turbine access roads could result in a
temporary increase in slower moving traffic volume on local roads. Construction related activities next to or in road
easements could also result in temporary disruptions to the flow of traffic on some local roads. The changes in
traffic volume are expected to be minimal and no appreciable change to traffic flow is anticipated as a result of the
Project.
Table 4-16 identifies potential effects on land use and infrastructure including local roads that could occur during
the construction and decommissioning phases of the Project and identifies mitigation strategies and a monitoring
plan.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 36
Operations
During the operation of the Project, the road capacity and local traffic could be affected if maintenance activities
involve the replacement of a major wind turbine generator component, since specialized equipment (e.g., cranes)
may be required. The delivery of specialized equipment could result in a temporary increase in slower moving traffic
volumes on local roads. Any maintenance activities adjacent to or in road easements could also result in temporary
disruptions to the flow of traffic on some local roads.
Table 4-17 identifies potential effects on local interests, land use and infrastructure that could occur during the
operations phase of the Project and identifies mitigation strategies and a monitoring plan.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 37
Table 4-16: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to Local Interests, Land Use and Infrastructure Resulting from Construction and Decommissioning
Potential Effect Performance Objectives Mitigation Strategy Net Effects Monitoring Plan and Contingency Measures
Reduction in Agricultural Land. No significant economic reduction in agricultural yields on
lots containing Project Infrastructure.
Minimize length of access roads where possible.
Consult with landowners to design access roads to
minimize impacts to existing land use.
Compensate landowners on CDA as per land lease
agreement.
Minor reduction in usable agricultural land.
High likelihood of effect, however limited magnitude due
to size of overall footprint within the entire CDA.
Monitoring and Contingency Measures:
No monitoring or contingency measures required.
Damage to Local Infrastructure. Minimize damage to local infrastructure. Adhere to BMPs regarding the operation of construction
equipment and delivery of construction materials.
Undertake roads condition survey prior to construction and
post-construction.
In the event that a drain is severed or damaged, the drain
will be capped and repaired as soon as reasonably
possible to avoid negative impacts to existing drainage
patterns.
Damage to local infrastructure minimized through
application of mitigation measures.
Moderate likelihood and magnitude of effects occurring
due to presence of oversize loads during delivery of
turbine components.
Monitoring:
Monitor complaints through the Project operations staff
contact number according to the Emergency Response
and Communications Plan (see Design and Operations
Report).
Contingency Measures:
Return damaged infrastructure to original condition (or
better) where appropriate.
Increased Congestion Due to Increase in Truck Traffic and
Short-term Lane Closures on Local Roads during Delivery of
Project Components.
Minimize disturbances to local traffic patterns. Develop a traffic management plan for the construction
phase and submit to the municipalities for review prior to
construction.
Conduct a survey in conjunction with the Municipality of
Chatham-Kent to determine if the roads and travel routes
within the CDA are capable of accommodating the oversized
vehicles and heavy loads prior to the delivery of Project
components and equipment.
Notify the community in advance of construction delivery
schedules and install signage to notify road users of
construction activity, where appropriate.
No significant adverse effects to local roads and traffic are
anticipated during construction and installation activities
following the implementation of a traffic management plan.
Monitoring:
Implementation of the traffic management plan will be
monitored.
Contingency Measures:
To the extent possible, use alternate component delivery
routes.
Table 4-17: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential Effects to Local Interests, Land Use and Infrastructure Resulting from Operations
Potential Effect Performance Objective Mitigation Strategy Net Effects Monitoring Plan and Contingency Measures
Temporary Change in the Flow of Local Traffic Resulting
from Maintenance Activities.
Minimize disturbance to local traffic patterns. Obtain appropriate road occupancy and traffic permits from
provincial and municipal agencies prior to undertaking
maintenance activities, if required.
Notify the community about major Project maintenance
activities.
Changes in traffic flow during the operation of the Project
are expected to be limited to periods when major Project
maintenance activities are required.
o Low likelihood of effect and limited magnitude due to
size of overall footprint within the entire CDA.
Monitoring:
Monitoring complaints through a Project operations staff
contact number according to the Emergency Response
and Communications Plan.
Contingency Measures:
To the extent possible, use alternate maintenance
equipment and/or component delivery routes.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 38
4.7 Other Resources
4.7.1 Existing Conditions
4.7.1.1 Landfills
MOECC’s Large Landfill and Small Landfill Sites records (MOECC, 2014a and MOECC, 2014b) were used to
confirm that there are no active landfills within the Project Location – the closest active landfill being approximately
36 km away. Therefore, no effects on landfills are anticipated.
4.7.1.2 Aggregate Resources
No aggregate pits or quarries have been identified through review of the MNRF’s Pits and Quarries Online
database tool (MNRF, 2015a). Therefore, no effects on aggregate resources are anticipated.
4.7.1.3 Forest Resources
Based on the MNRF’s Sustainable Forest Licences (SFL) database (MNRF, 2015b), there are no SFLs within the
Project Location. Therefore, no effects on forest resources are anticipated.
4.7.1.4 Petroleum Resources
Otter Creek has prepared a Petroleum Resources Report which was completed by a licensed engineer in Ontario.
The report concludes that through continued consultation with oil and gas companies, the Project can be
constructed to avoid impacts to oil and gas resources. It is anticipated that the report will be submitted to the MNRF
in winter 2017.
4.8 Public Health and Safety
4.8.1 Potential Effects
4.8.1.1 Stray Voltage
Otter Creek will ensure that the electrical design conforms and complies with relevant electrical safety standards.
Hydro One has established procedures in place to address stray voltage for off-farm and on-farm sources.
4.8.1.2 Structural Hazards
In the unlikely event of structural collapse or blade detachment, equipment will fall within a very small diameter due
to the weight of the wind turbine components. Wind turbine siting for the proposed Project will meet, at a minimum,
the setback distances from roads (blade length plus 10 m) and non-participating residences (550 m) as outlined in
O. Reg. 359/09, as amended.
A Property Line Setback Assessment (Appendix D of the Design and Operations Report) was conducted in
accordance with O. Reg. 359/09, as amended, to identify the proposed turbines located within the distance
equivalent to the height of the tower from base to top of hub, of an adjacent property line.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 39
Based on the analysis of the eleven turbines requiring justification for the reduced property line setback, there are
no anticipated adverse impacts for the reduced setbacks once the standard preventative measures based on best
management practices have been applied.
4.8.1.3 Ice Throw
Ice throw and ice shed refer to situations where during specific weather conditions, ice may form on wind turbines
and may be thrown or break loose and fall to the ground (Chief Medical Officer of Health (CMOH), 2010). Wind
turbines for the proposed Project will be located on private property and meet, at a minimum, the setback distances
from non-participating residences (550 m) and roads (blade length plus 10 m) outlined in O. Reg. 359/09, as
amended. During the operation of the Project, sensors located on the turbines will detect ice build-up and turbines
will be shut down if deemed unsafe by Otter Creek during operation.
4.8.1.4 Low Frequency Sound, Infrasound and Vibration
Wind turbines have the potential to emit low frequency sound, infrasound and vibration. Low frequency sound
commonly refers to sound at frequencies between 20 and 200 Hz; infrasound commonly refers to sound at
frequencies below 20 Hz (i.e., below the threshold of human perception). Although generally considered inaudible,
infrasound at high-enough sound pressure can be audible to some people (CMOH, 2010 and McCunney et al.,
2014). The “Potential Heath Impacts of Wind Turbines Report” (CMOH, 2010) identified that infrasound and low
frequency sound from modern wind turbines were found to be well below the level where known health effects
occur (50 to 70 dB) in studies of wind turbine noise. McCunney et al. concluded that “infrasound and low-frequency
sound do not present unique health risks”, and “annoyance seems more strongly related to individual
characteristics than noise from turbines” (2014, pp. 108).
4.8.1.5 Electric and Magnetic Fields
Concerns surrounding electromagnetic fields (EMFs) have been raised during other REA consultation processes.
EMFs are a combination of invisible electric and magnetic fields. They occur both naturally (e.g., light is a natural
form of EMF) and as a result of human activity. Nearly all electrical and electronic devices emit some type of EMF
(CMOH, 2010). The generation of electrical fields from underground and above-ground electrical collector lines
from the Project will be shielded by line insulation and the surrounding ground but will still generate magnetic fields.
Associated magnetic fields will be similar to other buried distribution lines in Ontario.
4.8.2 Potential Effects, Mitigation Measures and Net Effects
Construction and Decommissioning
Effects on public health and safety during construction have been described in Section 4.4 (Air, Odour and Dust),
Section 4.5 (Noise), and Section 4.6 (Local Interests, Land Use and Infrastructure).
Operations
To minimize or avoid effects on public health and safety, the turbines are sited according to setback distances
outlined in O. Reg.359/09 and as described above.
Table 4-18 identifies potential effects on public health and safety that could occur during the operations phase of
the Project and identifies mitigation strategies and a monitoring plan.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 40
Table 4-18: Mitigation Measures, Net Effects and Monitoring Plan Associated with Potential
Effects to Public Health and Safety Resulting from Operations
Potential Effect Performance
Objective Mitigation Strategy Net Effects
Monitoring Plan and
Contingency Measures
Impacts on Public
Health and Safety
from Structural
Hazards and/or Ice
Throw.
No public health and
safety incidents.
Adhere to setback
requirements to limit
likelihood of any impacts.
No impacts on public health
and safety from structural
hazards and/or ice throw due
to setback requirements.
o Very low likelihood and
very limited magnitude of
impacts (if any) on public
health and safety due to
setback requirements and
based on existing wind
facility operations.
Monitoring:
Track and respond to all
complaints (see Complaints
Resolution Process in
Emergency Response and
Communications Plan).
Contingency Measures:
Suspend operations during
extreme icing conditions to
minimize the risk of ice shed.
Stray Voltage Effects
to the Public and
Livestock
No health and safety
incidents associated
with stray voltage.
Build and maintain the Project
as prescribed by the
Electrical Safety Authority.
Ensure ongoing regular
maintenance and monitoring
of turbines.
Ensure that all electrical
design conforms and
complies with relevant
electrical safety standards.
Very low likelihood and very
limited magnitude of impacts
(if any) on public health and
safety from stray voltage due
to adherence to electrical
safety standards.
Monitoring:
Track all complaints (see
Complaints Resolution
Process in Emergency
Response and
Communications Plan) and
provide them to appropriate
agencies (e.g., HONI) for
resolution, where appropriate.
Contingency Measures:
No contingency measures
required.
4.9 Areas Protected under Provincial Plans and Policies
The REA requires a determination as to whether the Project is being proposed in any of the following protected or
plan areas:
Protected Countryside or Natural Heritage Systems in the Greenbelt Plan;
Oak Ridges Moraine Conservation Plan Areas;
Niagara Escarpment Plan Area; or
Lake Simcoe Watershed Plan Area.
The Project is not proposed in an area within the jurisdiction of the plans noted above. As such, there will be no
effects on these areas as a result of the Project.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 41
5. Summary and Conclusions
Field work and data collection were undertaken to determine the potential effects of this Project during the
construction, operations and maintenance and decommissioning phases. Mitigation measures to manage these
potential effects have been identified and monitoring and contingency plans proposed to ensure effects are
minimized.
Significant adverse effects have been avoided through careful site selection, facility layout planning and adherence
to all regulatory requirements.
The overall conclusion is that this Project can be constructed, operated, maintained and decommissioned
without any significant adverse net effects to the environment. Post-construction monitoring, including
effects on wildlife such as birds and bats, will be undertaken to confirm this conclusion.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 42
6. References
AECOM, 2016a:
Stage 1 Archaeological Assessment. Otter Creek Wind Farm. Multiple Lots and Concessions, Geographic
Township of Sombra, Lambton County, later Gore of the Geographic Township of Chatham, Historic
County of Kent, now the Municipality of Chatham-Kent, Ontario.
AECOM, 2016b:
Stage 2 Archaeological Assessment. Otter Creek Wind Farm. Multiple Lots and Concessions, Geographic
Township of Sombra, Lambton County, later Gore of the Geographic Township of Chatham, Historic
County of Kent, now the Municipality of Chatham-Kent, Ontario.
AECOM, 2016c:
Stage 2 Archaeological Assessment Additional. Otter Creek Wind Farm. Part Lot 19, Concession 4,
Geographic Township of Sombra, Lambton County, later Gore of the Geographic Township of Chatham,
Historic County of Kent, now the Municipality of Chatham-Kent, Ontario.
AECOM, 2017a:
Hydrogeological Assessment and Effects Assessment. Otter Creek Wind Farm LP.
AECOM, 2017b:
Heritage Impact Assessment. Otter Creek Wind Farm Limited Partnership. Chatham-Kent, Ontario.
AECOM, 2017c:
Otter Creek Wind Farm Environmental Impact Study. Otter Creek Wind Farm LP.
Armstrong, D.K. and J.E.P. Dodge, 2007:
Paleozoic Geology of Southern Ontario, Ontario Geological Survey. Miscellaneous Release Data 219.
Chapman, L.J. and D.F. Putnam, 1984:
The Physiography of Southern Ontario, Third Edition. Ontario Geological Survey, Special Volume: 2. 270p.
Accompanied by Map P.2715 (coloured), scale 1:600,000.
Chief Medical Officer of Health (CMOH), 2010:
The Potential Health Impact of Wind Turbines. May 2010.
Government of Canada, 2013:
Regulations Designating Physical Activities, SOR/2012-147. Canadian Environmental Assessment Act,
2012. Minister of Justice.
Government of Ontario, 2009:
Ontario Regulation 359/09. Ontario: Queen’s Printer.
Government of Ontario, 2009:
Ontario Regulation O. Reg. 9/06, Ontario: Queen’s Printer.
Municipality of Chatham-Kent, 2016:
Municipality of Chatham-Kent Official Plan. Consolidated May 12, 2016.
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 43
Ontario Ministry of Agriculture, Food and Rural Affairs, 2005:
Factsheet: The Farming and Food Production Protection Act (FFPPA) and Nuisance Complaints. Available:
www.omafra.gov.on.ca/english/engineer/facts/05-013.htm#17
Ontario Ministry of Natural Resources and Forestry (MNRF), 2011a:
Bats and Bat Habitats: Guidelines for Wind Power Projects. July 2011. Available online:
http://www.ontario.ca/environment-and-energy/bat-and-bat-habitats-guidelines-wind-power-projects-2011
Ontario Ministry of Natural Resources and Forestry (MNRF), 2011b:
Birds and Bird Habitats: Guidelines for Wind Power Projects. December 2011.
Ontario Ministry of Natural Resources and Forestry (MNRF), 2012:
Natural Heritage Assessment Guide for Renewable Energy Projects. Accessed July 2015. Available:
https://dr6j45jk9xcmk.cloudfront.net/documents/2716/stdprod-101413.pdf.
Ontario Ministry of Natural Resources and Forestry (MNRF). 2015:
Significant Wildlife Habitat Criteria Schedules for Ecoregion 7E. January 2015
Ontario Ministry of Natural Resources and Forestry (MNRF), 2015a:
Aggregate Resources. Accessed June 2016. Available: http://www.ontario.ca/environment-and-
energy/aggregate-resources.
Ontario Ministry of Natural Resources and Forestry (MNRF), 2015b:
Sustainable Forest Licences. Accessed June 2016. Available: https://www.ontario.ca/environment-and-
energy/sustainable-forest-licences.
Ontario Ministry of the Environment and Climate Change (MOECC), 2014a:
Small Landfill Sites. Accessed June 2016. Available: http://www.ontario.ca/environment-and-energy/small-
landfill-sites.
Ontario Ministry of the Environment and Climate Change (MOECC), 2014b:
Large Landfill Sites. Accessed June 2016. Available: https://www.ontario.ca/environment-and-
energy/large-landfill-sites.
Ontario Ministry of Tourism, Culture and Sport (MTCS), 2011:
2011 Standards and Guidelines for Consultant Archaeologists. Ontario: Queen’s Printer. Accessed March
2015. Available: http://www.mtc.gov.on.ca/en/archaeology/archaeology_s_g.shtml.
Ontario Regulation (O. Reg.) 359/09:
Ontario Regulation 359/09. Renewable Energy Approvals under Part V.0.1 of the Environmental
Protection Act.
Appendix A
Legal Descriptions
Appendix A. Legal Descriptions
Description of Parcels Identified As Part of the Project Location Type of Agreement Status of Agreement
Lot Concession Geographic Township
PART OF LOT 4 CON 3 SOMBRA Option to Lease Land Agreement Obtained
PART OF LOT 6 CON 4 SOMBRA Option to Lease Land Agreement Obtained
N1/2 LOT 7 CON 4 SOMBRA Option to Lease Land Agreement Obtained
PART OF LOT 8 CON 4 SOMBRA Option to Lease Land Agreement Obtained
PART OF LOT 6 AND 7 CON 3 SOMBRA Option to Lease Land Agreement Obtained
N1/2 LOT 6 CON 3 SOMBRA Option to Lease Land Agreement Obtained
N1/2 LOT 7 CON 3 SOMBRA Option to Lease Land Agreement Obtained
N1/2 LOT 8 CON 3 SOMBRA Option to Lease Land Agreement Obtained
PART OF LOT 7 CON 3 SOMBRA Option to Lease Land Agreement Obtained
PART OF LOT 8 CON 3 SOMBRA Option to Lease Land Agreement Obtained
PART OF LOT 8 CON 3 SOMBRA Option to Lease Land Agreement Obtained
LOT 9 CON 3 SOMBRA Option to Lease Land Agreement Obtained
PART OF LOT 10 CON 3 SOMBRA Option to Lease Land Agreement Obtained
N1/2 LOT 15 CON 4 SOMBRA Option to Lease Land Agreement Obtained
S1/2 LOT 18 CON 4 SOMBRA Option to Lease Land Agreement Obtained
N1/2 LOT 18 CON 4 SOMBRA Option to Lease Land Agreement Obtained
N1/2 LOT 19 CON 4 SOMBRA Option to Lease Land Agreement Obtained
PART OF LOT 20 CON 3 SOMBRA Option to Lease Land Agreement Obtained
S1/2 LOT 26 CON 4 SOMBRA Option to Lease Land Agreement Obtained
PART OF LOT 27 CON 4 SOMBRA Option to Lease Land Agreement Obtained
PART OF LOT 26 CON 3 SOMBRA Option to Lease Land Agreement Obtained
Otter Creek Wind Farm Limited Partnership
Project Description Report
Cer_04_Project Description Report (05.05.2017) 44
About AECOM
AECOM (NYSE: ACM) is built to deliver a better world. We design, build, finance and operate infrastructure assets for governments, businesses and organizations in more than 150 countries.
As a fully integrated firm, we connect knowledge and experience across our global network of experts to help clients solve their most complex challenges.
From high-performance buildings and infrastructure, to resilient communities and environments, to stable and secure nations, our work is transformative, differentiated and vital. A Fortune 500 firm, AECOM companies had revenue of approximately US $19 billion during the 12 months ended June 30, 2015.
See how we deliver what others can only imagine at aecom.com and @AECOM.
aecom.com