process improvement and standardisation in it - a telecoms organisation example david evans
TRANSCRIPT
Process Improvement and Standardisation in IT -
A Telecoms Organisation Example
David Evans
The Challenges Project variance was unpredictable with
project overrun often resulting in a 40% + overspend with invoicing erratic and unchallenged.
Due to the lack of process and a time and materials engagement model suppliers were being rewarded for poor quality via the ability to ‘bill’ additional time to resolve issues
The suppliers were seen to be ‘in-control’ and perceived to treat their client as an ATM or ‘cash-cow’
ObjectiveThe initiative was underwritten by four objectives:
1. Improve the quality of the deliverables2. Have a clear, repeatable process that is to
be followed by all suppliers3. To gain control of the project spend creating
predictability and certainty4. Assign accountability for project overruns
The method Define the target high-level goals and
methods supporting the capability behind the ability to deliver projects
Measure the existing capability in order to: A: Define a resolution roadmap B: Objectively evidence that objectives have
been met Analyse the results and set a remediation
activity plan Implement the improvement plan Re-Measure the capability and implement a
continuous improvement plan
The Measure CMMI was formally implemented to measure
the current capability and the results shared across the organisationSample for Test
Execution
Sample for a Development Team
The Analysis The CMMI process measurements enabled the
team to develop a prioritised roadmap based upon an agreed Target Operating Model and Timeline.
Target Operating Model Test Execution, Environment and CRM Development
must be in a position to offer up a standardised SDLC/ Project Methodology that represents a CMMI Level 3 maturity level
The Timeline All teams are to be re-measured on an 18 month
timeline observing both process maturity availability and adherence
The Implementation A new process based SDLC was developed on
a team by team basis over a 12 month and € 1M budget that reflected: Whole Lifecycle
The Implementation A new process based SDLC was developed on
a team by team basis over a 12 month and € 1M budget that reflected: The Project Phase
The Implementation A new process based SDLC was developed on
a team by team basis over a 12 month and € 1M budget that reflected: All Tools & Templates
The Results CRM Development, Test Execution, Test Environment
& the Billing Development Team achieved:
Full Process Documentation within 12 Months and all suppliers both following and being assessed against process adherence
All Teams achieved CMMI Level 3 ratings within 14 months Project Slippage & budget variance reduced by 30% Insight into quality issues doubled Root cause analysis resulting from the process work
enabled both future improvement initiatives but also helped to foster a culture of continuous improvement
A standardised process model enabled the transition from time and materials to a fixed cost model
Fixed Cost Model Objective:
To transition the delivery model from a supplier Time & Materials to a Fixed Cost model with the objective of achieving
Reduced project delivery costs Assigned Accountability Predictable cash movements and project funding Variance managed through sponsor approved change
only Further leverage of the defined process roadmap
Fixed Cost Methodology Considerations
The implementation must be timely It needs to accommodate all projects/ suppliers at a single point
in time The entry point was to align with a release management
structure Note. For non-release managed projects tollgate timings were used
To succeed it needs to represent a win-win between supplier and customer The supplier needs to benefit from early completion
SOW’s were requested, reviewed, renegotiated and accepted by the supplier
The customer needs to benefit from late completion/ poor quality Overruns were born by the supplier unless the root cause was the
suppliers at which point a formalised change request process was to be utilised
Fixed Cost Methodology Considerations (continued)
Competition is essential Before each project commenced an RFP was issued to
all five suppliers The responses were reviewed and workshops were held to
answer questions where all suppliers attended to ensure an even playing field
Once a project was accepted the suppliers were expected to adhere to the terms of business
Fixed Cost Implementation All suppliers were addressed as one where it was
made clear that if they did not wish to participate they were free to end their engagement
All suppliers participated in the process formation Purchasing and legal were engaged at day one All existing contracts were placed on notice New contracts were draw under the same terms
of reference for each supplier The supplier-side management team was
retrained in order to be in a position to effectively assess the SOW’s and to engage in and manage the change management process
Results Behind Fixed Cost Transition The transition for all suppliers was completed in six
weeks Non-approved project variance was removed
completely Invoicing became end-of phase only and variances only
paid where approved change requests were available and signed by the project sponsor/ budget holder
The organisation was able to forecast cash movements on a predictable cycle enabling better use of funds
Variance from schedule was reduced and quality rose as suppliers were accountable for their own variances
The fixed cost model enabled a full transition to a full, outsourced managed service delivery model after 24 months.