PRESENTATION TO THE SELECT PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION MONITORING OF JOB CREATION PROJECTS PROJECTS Presentation by Head: Transport Presentation by Head: Transport Mr. Chris Hlabisa Mr. Chris Hlabisa 02 August 2011 02 August 2011

Upload: mairi

Post on 07-Jan-2016

35 views

Category:

Documents


1 download

DESCRIPTION

PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS. Presentation by Head: Transport Mr. Chris Hlabisa 02 August 2011. Overview. Introduction Road Infrastructure Programmes Zibambele Road maintenance programme - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

PRESENTATION TO THE SELECT PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE:COMMITTEE ON PUBLIC SERVICE:MONITORING OF JOB CREATION MONITORING OF JOB CREATION

PROJECTSPROJECTS

Presentation by Head: Transport Presentation by Head: Transport

Mr. Chris HlabisaMr. Chris Hlabisa

02 August 201102 August 2011

Page 2: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

Overview• Introduction• Road Infrastructure Programmes

– Zibambele Road maintenance programme– Vukuzakhe emerging contractor development

programme– Pothole programme strategy

• Departmental monitoring processes• Expanded Public Works programme(EPWP)

– Institutional Arrangements– Monitoring structures– Monitoring Processes

• Conclusion

Page 3: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

3

StatsSA RSA KZN %

Area (km2) 1,219,207 92,307 7.6

Population 49,991,300 10,645,400 21

STATS 2001 RSA KZN

Gini Coefficient 0.69 0.71

Poverty Index 49.8% 54.3%

Rural population 44% 55%

Unemployment rate 26.4% 27.9%

Page 4: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

1. Introduction

The Kwazulu-Natal Department of Transport has been the pioneer in various developmental and labour

absorptive programmes that has lead to job creation and poverty

eradication.

Page 5: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

2.Road Infrastructure Programme

• The development and management of the road network is now implemented under the Sihambasonke Programme

• The key focus areas among others being:– Development and management of key arterial

routes – Efficient use of labour absorptive methods– Know your network– Safe road environment through eradication of

potholes etc.

Page 6: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

3. Construction

Projects are undertaken through the following programmes:

•African Renaissance Road Upgrading Programme (ARRUP)

•Operation Kushunquthuli– Community Access Roads

• Police Station• Clinics• Schools• Areas with high potential for agriculture activities

– Pedestrian Bridges

•Roads of National Importance (RNI)

Page 7: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

4. Maintenance

Maintenance activities undertaken on the road network:•Conserving the higher order roads

– Rehabilitation and Reseals

•Preventative Maintenance– Re-gravelling

•Routine Maintenance– Blading, drain cleaning

•Safety Maintenance– Potholes, guardrails

•Special Maintenance– Bridge handrails

Page 8: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

5. Zibambele Road maintenance programme

• It was launched 1998 , modelled around the Kenyan lengthman system

• It is a labour intensive road maintenance programme

• It is a poverty alleviation programme targeting women headed household

• Permanent contracts for routine maintenance are allocated to the poorest of the poor

Page 9: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

6. Zibambele Investments  FINANCIAL YEAR

  1999/00 2000/01 2001/02 2002/03 2003/04 2004/05 2005/06 2006/07 2007'08 2008/09 2009/10 2010'11

Total investments to Zibambele Contractors (R Millions) R 10.0 R 8.1 R 42.0 R 54.6 R 66.6 R 87.0 R 122.4 R 143.9 R 187.2 R 204.0 R 225.6 R 231.39

No. of Zibambele contractors (Person years) 1,031 6,031 9,856 14,910 17,104 23,451 27,531 32,076 36,366 39,930 39,997 39,049

Length of roads maintained by contractors 1,186 3,920 6,406 9,692 11,118 15,423 17,895 20,148 23,638 27,863 27,998 24,405

Zibambele training projects (R millions) R 1 R 1 R 3 R 3 R 4 R 3 R 2 R 4 R 4 R 4 R 4 R 3.5

Monthly salary paid to Zibambele contractors R 250 R 250 R 334 R 334 R 350 R 370 R 390 R 390 R 410 R 450 R 470 R 510

Total investments to date of R1.383 billion and contractors have saved R12 million

Page 10: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

7. Vukuzakhe emerging contractor development

programme• It is an economic empowerment programme targeting the

previously disadvantaged groups.

• It is aimed at addressing anormalities within the

construction sector by addressing the economic

inequalities of the past

• Contractors are graded in line with the CIDB grading

• Contractors receive targeted training and mentorship

support

Page 11: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

8. Vukuzakhe InvestmentsNumber of contracts

NUMBER OF CONTRACTS

FINANCIAL YEAR (Millions)

1998/99 1999/00 2000/01 2001/02 2002/03 2003/04 2004/05 2005/06 2006/07 2007/08 2008/09 2009/10 2010/11 2011/12

- Grade 1 126 232 295 488 563 549 521 496 430 535 458 427 452  520

- Grade 2 54 142 106 138 232 222 210 229 172 149 61 99 115  140

- Grade 3 8 17 101 82 78 101 142 131 142 155 151 125 130  150

- Grade 4 0 0 0 18 18 40 47 39 60 45 26 3 3  20

- Grade 5 0 0 0 0 0 0 0 0 0 0 6 1 1  7

- Grade 6 0 0 0 0 0 0 0 0 0 0 3 2 3  5

ALL STAGES 188 391 502 726 891 912 920 895 804 884 705 657 704 842

Page 12: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

9. Vukuzakhe InvestmentsValue of contracts

Value of Contracts

FINANCIAL YEAR (Millions)

1998/99 1999/00 2000/01 2001/02 2002/03 2003/04 2004/05 2005/06 2006/07 2007/08 2008/09 2009/10 2010/11 2011/12

- Grade 1 12 21 24 21 41 44 61 39 97 45 66 52 65 95

- Grade 2 9 15 17 18 49 73 55 79 66 58 27 33 48 60

- Grade 3 6 54 63 67 42 70 74 98 105 112 231 96 102 155

- Grade 4 0 0 0 0 40 153 97 163 250 172 65 9 18 52

- Grade 5 0 0 0 0 0 0 0 0 0 0 40 31 35 29

- Grade 6 0 0 0 0 0 0 0 0 0 0 32 46 40 43

All stages 27 90 104 105 171 340 286 378 517 387 461 267 308 434

All of these empowerment programmes (Zibambele and Vukuzakhe enjoy more than 75% of the CAPEX budget from our baseline allocation

Page 13: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

10. Pothole Programme Strategy

• The Department has implemented a 2 year Pothole Repair Contract commencing in the 2011/2012 financial year to address the backlog of pothole repairs.

• A database comprising of 134 contractors ranging from Grade 1 to Grade 2, has been created per the following regions.– EMPANGENI– LADYSMITH– PIETERMARITZBURG– DURBAN

Page 14: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

11. Pothole Programme Strategy

This programme will have the following benefits of :•A safe road network for the road user;•Reduced road accidents; •Reduced and minimized the road maintenance backlog; •Improved average road network condition; •Reduced pressure on routine maintenance resources due to improved road conditions; •Reduced vehicle operating costs for road users; •Reduced claims against government.

Page 15: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

12. Monitoring process (dept.)• A departmental Monitoring and Evaluation (M & E) unit

exists • All budget allocations are supported by approved business

plans• Regional staff(field support officers, technicians, and

engineers) implement business plans; • Monthly progress reports are sent to M & E for monitoring

outcomes and reporting progress to management, National Treasury and Cabinet clusters

• Site inspections are performed by M & E staff to verify reported outputs as well as the outcomes of projects .

Page 16: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

EXPANDED PUBLIC WORKS PROGRAMME (EPWP)

COORDINATION

Page 17: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

13. Institutional arrangements

• The department of Transport is the overall coordinator of the EPWP in the province of KwaZulu-Natal

• The following structures were established for proper ratification of input:

– Provincial Steering Committee convened by the Department of Transport

– Sector coordinating committees convened by Sector Lead Departments

– M&E Provincial structure convened by coordinating department

Page 18: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

Sector Provincial Lead Sector Departments

Provincial Sector Departments

Infrastructure Department of Transport

-Department of Transport-Department of Public Works-Department of Human Settlements-Department of Cooperative Governance and Traditional Affairs-Department of Health-Department of Education-Municipalities 10 DM + METRO

Social Sector Department of Social Development

-Department of Social Development-Department of Health-Department of Education- Department of Community Safety and Liaison-Municipalities 10 DM + METRO

Environmental & Cultural Sector

Department of Agriculture and Environmental Affairs

-Department of Agriculture & Environmental Affairs and Rural Development-Department of Arts, Culture & Tourism-Department of Sports & Recreation- KZN Wildlife

14. Institutional Arrangements

Page 19: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

15. Monitoring structures Provincial Steering Committee(PSC)

•PSC meetings are convened by DOT on a quarterly basis

•All sector lead departments are represented at the PSC

meetings by senior managers with decision-making powers

•PSC deals with transversal issues relating to policy changes to

the EPWP as well as challenges relating to implementation

across all sectors

Page 20: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

16. Monitoring structure cont..

Monitoring and Evaluation committee:•This structure is responsible for monitoring progress on reporting by public bodies, deploying data capturing capacity where required,

•Responds to reporting challenges and review data from past quarter as well as verifying data before it is captured on WBS.

•Ensure data integrity before it is submitted to NDPW

Page 21: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

17. Monitoring process

• Regular site visits are conducted by the coordinating department

• Regular reporting on labour Intensive methods and EPWP is done to the following high level structures– Cabinet – Premiers Coordinating forum(PCF)– Committee of Heads of Departments (COHOD)

Page 22: PRESENTATION TO THE SELECT COMMITTEE ON PUBLIC SERVICE: MONITORING OF JOB CREATION PROJECTS

18. CONCLUSION

• These programmes are supporting job creation and poverty eradication while stimulating economic growth in the Province of KwaZulu- Natal

• These programmes are very key to the transformation of our society for the better.

• Collaborative efforts by all levels of government as well as civil society are also key to the success and sustainability of these initiatives.