Understanding North Dakota’s

Petroleum Development and

Transportation Dynamics

July 11, 2018

Justin J KringstadGeological Engineer

Director

North Dakota Pipeline Authority

2JJ Kringstad - North Dakota Pipeline Authority 2

Presentation Outline

• Economics

• Current Activity and oil transportation dynamics

• Understanding current and future oil production

• Pricing update

• Activity

• Oil forecasts

• North Dakota natural gas production

• Flaring and gas capture

• Natural gas liquids

• Pipeline construction update

3JJ Kringstad - North Dakota Pipeline Authority 3

Objective

Define where the Bakken/Three Forks system may be economic in the current oil price environment.

Method

Analyze past well performance across the region and estimate well economics for various production levels.

Disclaimer

The goal of this work is not to imply individual company actions or intentions. All view expressed are strictly that of Justin J. Kringstad.

Neither the State of North Dakota, nor any agency, officer, or employee of the State of North Dakota warrants the accuracy or reliability of this product and shall not be held responsible for any losses related to its use.

4JJ Kringstad - North Dakota Pipeline Authority 4

Key Economic Assumptions• $6-$8 Million Well Costs

• $63/BBL & $6.00/MCF Wellhead Pricing

• 1/6 Royalty

• Zero Flaring

• Assumed 10-20% IRR to drill (calculated after production taxes and royalties)

• No Tax Incentives Included

• Production rate is 30-day average

• All Bakken/Three Forks wells drilled in 2008+5JJ Kringstad - North Dakota Pipeline Authority 5

© OpenStreetMap contributors

JJ Kringstad - North Dakota Pipeline Authority 6

Peak Month Minimum - 200 BOPD

3,755 Wells

© OpenStreetMap contributors

7,062 Wells

Three Forks Bakken

$63 Wellhead

© OpenStreetMap contributors

JJ Kringstad - North Dakota Pipeline Authority 7

Peak Month Minimum - 400 BOPD

2,508 Wells

© OpenStreetMap contributors

5,247 Wells

Three Forks Bakken

$63 Wellhead

© OpenStreetMap contributors

JJ Kringstad - North Dakota Pipeline Authority 8

Peak Month Minimum - 600 BOPD

1,371 Wells

© OpenStreetMap contributors

3,097 Wells

Three Forks Bakken

$63 Wellhead

© OpenStreetMap contributors

JJ Kringstad - North Dakota Pipeline Authority 9

Peak Month Minimum - 800 BOPD

666 Wells

© OpenStreetMap contributors

1,505 Wells

Three Forks Bakken

$63 Wellhead

© OpenStreetMap contributors

JJ Kringstad - North Dakota Pipeline Authority 10

Peak Month Minimum – 1,000 BOPD

266 Wells

© OpenStreetMap contributors

706 Wells

Three Forks Bakken

$63 Wellhead

© OpenStreetMap contributors

JJ Kringstad - North Dakota Pipeline Authority 11

Peak Month Minimum – 1,250 BOPD

107 Wells

© OpenStreetMap contributors

266 Wells

Three Forks Bakken

$63 Wellhead

© OpenStreetMap contributors

JJ Kringstad - North Dakota Pipeline Authority 12

Peak Month Minimum – 1,500 BOPD

36 Wells

© OpenStreetMap contributors

98 Wells

Three Forks Bakken

$63 Wellhead

13

Breakeven Summary

JJ Kringstad - North Dakota Pipeline Authority 13

Presentation Outline

• Economics

• Current Activity and oil transportation dynamics

• Understanding current and future oil production

• Pricing update

• Activity

• Oil forecasts

• North Dakota natural gas production

• Flaring and gas capture

• Natural gas liquids

• Pipeline construction update

14JJ Kringstad - North Dakota Pipeline Authority 14

Drilling Activity – 65 Rigs (July 6, 2018)

1515JJ Kringstad - North Dakota Pipeline Authority 15

North Dakota Drilling Activity

1616JJ Kringstad - North Dakota Pipeline Authority 16

17

Statewide Oil Performance

JJ Kringstad - North Dakota Pipeline Authority 17Average BKN/TF Well Performance Statewide

North Dakota Oil Production Forecast

18

1818JJ Kringstad - North Dakota Pipeline Authority 18

Estimated Williston Basin Oil Transportation

19

1919JJ Kringstad - North Dakota Pipeline Authority 19

20

Estimated ND Rail Export Volumes

20JJ Kringstad - North Dakota Pipeline Authority 20

Presentation Outline

• Economics

• Current Activity and oil transportation dynamics

• Understanding current and future oil production

• Pricing update

• Activity

• Oil forecasts

• North Dakota natural gas production

• Flaring and gas capture

• Natural gas liquids

• Pipeline construction update

21JJ Kringstad - North Dakota Pipeline Authority 21

Cushing $73.76

Brent $77.14WTI + $3.38

Crude Oil Prices – July 6, 2018

22JJ Kringstad - North Dakota Pipeline Authority

Pricing Data: Bloomberg &

CME (LLS-Argus)LLS (Argus)WTI + $3.14

JJ Kringstad - North Dakota Pipeline Authority 22

North Dakota Impact of Smaller Discount

• 2016 Weighted Average Discount: $7.71

• June 2017 - April 2018 Wt. Average Discount: $4.66

• $3.05/BBL Improvement Post DAPL Commercial In-Service

• 376,694,561 Taxable Barrels In June 2017 - April 2018

• Wt. Avg. Tax Rate in June 2017 - April 2018: 9.74%

Eleven Month Revenue Impact

• 9.74% x 376,694,561 x $3.05 =

$111+ Million Additional State Revenue

When Compared to Avg. 2016 Discount

Does Not Include Royalty Owner

and Industry Revenue Impact

232323JJ Kringstad - North Dakota Pipeline Authority 23

2424JJ Kringstad - North Dakota Pipeline Authority 24

Williston Basin Oil Production & Export Capacity, BOPD

Production forecast is for visual demonstration purposes only and should

not be considered accurate for any near or long term planning.

25JJ Kringstad - North Dakota Pipeline AuthorityJJ Kringstad - North Dakota Pipeline Authority 25

Presentation Outline

• Economics

• Current Activity and oil transportation dynamics

• Understanding current and future oil production

• Pricing update

• Activity

• Oil forecasts

• North Dakota natural gas production

• Flaring and gas capture

• Natural gas liquids

• Pipeline construction update

26JJ Kringstad - North Dakota Pipeline Authority 26

27

Natural Gas Capture

Production

• Technology

• Markets

Gathering

• Capacity

• Connections

Processing

• Capacity

• Location

Transmission

• Dry Gas

• Natural Gas Liquids

JJ Kringstad - North Dakota Pipeline Authority 27

28

Natural Gas Capture

Production

• Technology

• Markets

Gathering

• Capacity

• Connections

Processing

• Capacity

• Location

Transmission

• Dry Gas

• Natural Gas Liquids

JJ Kringstad - North Dakota Pipeline Authority 28

29

Statewide Gas Performance

JJ Kringstad - North Dakota Pipeline Authority 29Average BKN/TF Well Performance Statewide

NDPA North Dakota Gas Production Forecast

3030JJ Kringstad - North Dakota Pipeline Authority 30

31

Natural Gas Capture

Production

• Technology

• Markets

Gathering

• Capacity

• Connections

Processing

• Capacity

• Location

Transmission

• Dry Gas

• Natural Gas Liquids

JJ Kringstad - North Dakota Pipeline Authority 31

32JJ Kringstad - North Dakota Pipeline Authority

Solving the

Flaring Challenge

April 2018

© OpenStreetMap contributors

Non-Confidential Bakken/Three Forks/Sanish Only (Wells Flaring 10+mcfd)

JJ Kringstad - North Dakota Pipeline Authority 32

3333JJ Kringstad - North Dakota Pipeline Authority

Days to Connect to Gas Gathering

JJ Kringstad - North Dakota Pipeline Authority 33

34

Natural Gas Capture

Production

• Technology

• Markets

Gathering

• Capacity

• Connections

Processing

• Capacity

• Location

Transmission

• Dry Gas

• Natural Gas Liquids

JJ Kringstad - North Dakota Pipeline Authority 34

35JJ Kringstad - North Dakota Pipeline Authority

Solving the Flaring Challenge

JJ Kringstad - North Dakota Pipeline Authority 35

36

Natural Gas Capture

Production

• Technology

• Markets

Gathering

• Capacity

• Connections

Processing

• Capacity

• Location

Transmission

• Dry Gas

• Natural Gas Liquids

JJ Kringstad - North Dakota Pipeline Authority 36

Major Gas Pipeline and

Processing Infrastructure

WBI Transmission

Whiting

JJ Kringstad - North Dakota Pipeline AuthorityJJ Kringstad - North Dakota Pipeline Authority 37

JJ Kringstad - North Dakota Pipeline Authority 38

Northern Border Pipeline

*Data Source: Northern Border IPS

• 42” Pipeline

• Carries Canadian (Port of Morgan) and Domestic Gas

• Receives Gas From ND Plants, WBI Transmission Interconnections, and WY Pipelines (Bison & Grasslands)

• Midcontinent Deliveries

JJ Kringstad - North Dakota Pipeline Authority

Simplified Example NB CalculationsConclusion: IF no other gas export options open and all other deliveries on other pipelines stay static, ND

gas production could increase 1.43-1.73 BCFD (from Apr-18) before Northern Border is 100% Bakken

production. BTU management becomes increasingly important for Bakken residue gas.

39

Now What?

4040JJ Kringstad - North Dakota Pipeline Authority 40

Regional NGL Infrastructure

Kinder

JJ Kringstad - North Dakota Pipeline Authority 41

North Dakota Captured* NGL’s

4242JJ Kringstad - North Dakota Pipeline Authority 42*Non-flared NGL’s & Assumes 10 GPM

NGL Pipeline Takeaway Options

43

4343JJ Kringstad - North Dakota Pipeline Authority 43

ONEOK Elk Creek NGL Pipeline

Project Highlights

• 900 Miles - 20” Pipeline

• $1.4 Billion

• 240,000 BPD Capacity

• Expandable to 400,000

BPD

• End of 2019 Proposed

Completion

• Y-Grade Transportation

JJ Kringstad - North Dakota Pipeline Authority 44

Presentation Outline

• Economics

• Current Activity and oil transportation dynamics

• Understanding current and future oil production

• Pricing update

• Activity

• Oil forecasts

• North Dakota natural gas production

• Flaring and gas capture

• Natural gas liquids

• Pipeline construction update

JJ Kringstad - North Dakota Pipeline Authority 45

North Dakota Pipeline Construction

46

Sources: NDIC & PHMSA

46JJ Kringstad - North Dakota Pipeline Authority 46

North Dakota Pipeline Construction

47

Sources: NDIC & PHMSA

47JJ Kringstad - North Dakota Pipeline Authority 47

Justin J. Kringstad, DirectorNorth Dakota Pipeline Authority

600 E. Boulevard Ave. Dept. 405Bismarck, ND 58505-0840

Phone: (701)220-6227Fax: (701)328-2820

E-mail: [email protected]

Websites: www.pipeline.nd.gov

www.northdakotapipelines.com

Contact Information

JJ Kringstad - North Dakota Pipeline Authority 48