p120-project estimating requirements gsa 2007

Upload: adrian-calin-jurubescu

Post on 06-Feb-2018

244 views

Category:

Documents


2 download

TRANSCRIPT

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    1/92

    GSA Public Buildings Service

    P-120

    projectestimating

    requirementsforthepublicbuildingsservice

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    2/92

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    3/92

    P-120

    projectestimating

    requirementsforthepublicbuildingsservice

    U.S.GeneralServicesAdministration

    OfficeoftheChiefArchitect

    January2007

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    4/92

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    5/92

    tableofcontentsintroduction iii

    documentorganization iv

    acknowledgements v

    1 generalrequirementsandprinciples 11 generalphilosophy 3

    2 estimatorqualificationandethics 45

    requirementsindependentgovernmentestimate(IGE)

    ethics duediligenceexpectations penalties

    3 costestimatingandmanagementpractices 67

    costmanagementprinciples estimatingformats

    4 estimatingrequirements 817

    generalwarmlitshellversustenantimprovement(TI)costestimates

    contentsanddegreeofdetailcostestimatingandcostmanagementtools

    2 prospectuslevelprojectsproduct/deliverablerequirements 251 preliminaryplanningandprogrammingprojectrequirements 2728

    projectplanningguidelevelandformatrequirements

    2 designandconstructionphasecostestimating 2946

    basicconcept:forallphasescostestimatesandsummaries

    market survey costgrowthreport spacetypecostanalysis lifecyclecostanalyses valueengineeringstudies budget analysis

    requirementsforbidsubmissionconstructionawardbidanalysisforprospectuslevelprojects

    cost database constructionmodificationsandclaimsanalysisvalueengineeringchangeproposals(VECPs)

    risk management occupancyagreementsandtenantimprovementspricing

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    6/92

    table of contents (continued)

    3 deliverymethodsanddeliverables 491 overview 51

    requirementsforestimates

    2 deliverableflowchartsbydelivery 5457

    a appendices 59a estimatingformats 6170

    uniformatlevel15costelements

    masterformatcostelements(2004version)

    b estimatetrackingsheets 71c uniformatprojectcostsummary 72

    d buildingcostanalysisforms 7475

    e sample2630/2631formsfordesignandmaintenance/inspectionservices 7677

    f acronyms/glossaryofterms 7879

    listoftables1 requirementsforcostestimatingateachdesignphase 14

    2 standardsiteanddesigncontingencyguidelines 14

    3 costestimatingtaskingmatrix 5457

    listoffigures

    1 calculationofmarkups,contingencies,andescalation 17

    2 generalconstructioncostreviewguide(GCCRG) 19

    3 exampleofaPCEProjectCostSummary 204 PCEcostestimatedetailexcerptforaconceptdesignestimate 21

    5 uniformatdesigndevelopmentestimatereportexcerpt 22

    6 masterformatdesigndevelopmentestimatereportexcerpt 23

    ivprojectestimatingrequirementsP120

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    7/92

    introduction

    This costestimating and costmanagement criteria document supports building constructionprogramswithinthePublicBuildingsService(PBS)oftheU.S.GeneralServicesAdministration

    (GSA). Thisdocument presents thetechnicaland administrativerequirementsforroutine cost

    estimatingandcostmanagementtasksinvolvedinaconstructionprojectsplanningandexecution

    stages, and defines costestimating practices and standards for professional services. This

    documentreplacesthepreviouslyissuedGSAHandbookP3440.5andallassociatedversions.

    Theinstructionsandcriteriainthisdocumentareapplicabletoprogramming,design,construction

    management, and other professionalservices contracts that involve costestimating andcostmanagement tasks.Thecriteria forpracticesand documentationrequirementsapply toall

    professionalservicesactivities,whetherprovidedthroughcontractorbyinhouseGSA/PBSstaff.

    Thecostestimatingtasksaddressedinthisdocumentmustestablishaccurateprojectcosts,ensure

    thattheyarebasedonprogrammingrequirements,keepcostswithinauthorizedlimits,andcollect

    GSAcostdatatorefinebusinesspracticesandfuturecostestimates.

    Sinceprojectdeliverymethodsaffecthow,andtosomedegreewhen,costmanagementpractices

    areapplied,thisdocumentexplainsthebasicrequirementsassociatedwitheachdeliverymethod.

    introductionv

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    8/92

    documentorganization

    Thisdocumenthasthreemajorchapters:

    1 generalrequirementsandprinciples

    Thischapterpresentsthegeneralestimatingpracticesandstandardsrequiredforallestimating

    services. Itcoversqualificationsofestimatorsandestimatingfirms,principlesofeffectivecost

    management, different types and formats of estimates, approaches to estimating, and the

    variouscostestimatingandmanagementtoolsavailable.

    2 prospectusprojectrequirements

    This chapter defines the estimating service required for prospectus projects, including

    deliverablesinthecontextofplanning,design,andconstructionstages.

    3 deliverymethodsanddeliverables

    Thischapter explainswhen thedeliverablesdefined inChapter2must beprovidedfor the

    followingfourdeliverymethods:

    Traditional(DesignBidBuild)

    DesignBuildPerformance

    DesignBuild(Bridging)

    ConstructionManagerasConstructor(CMc)

    Table3inthischaptershowsthecostestimatingtaskingrequirementsforthedeliverymethods

    bysizeandtypeofproject.

    viprojectestimatingrequirementsP120projectestimatingrequirementsP120

    documentorganization

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    9/92

    acknowledgementsThispublicationwaswrittenas acollaborativeeffortof theOfficeoftheChiefArchitect (OCA)

    of GSAs Public Buildings Service costexperts, regional PBScostexperts,andthe consulting

    firmFaithfulandGould,acostmanagementconsultant(formerlyHanscomb,FaithfulandGould).

    SpecialthanksareduetoLesShepherd,AIA,ActingGSAChiefArchitect,andDavidEakin,PE,

    formerChiefEngineer,whoprovidedtheirmanagementsupportinthedevelopmentandpublication

    ofthisdocument.

    The following individualscontributed theirknowledgeandexpertise inwriting andediting this

    document:

    gsanationaloffice,officeofthechiefarchitectCharlesMatta,Director CenterforFederalBuildingsandModernizations

    GregorySegal CenterforFederalBuildingsandModernizations

    CurtSmith CenterforConstructionExcellenceandProjectManagement

    DonaldC.Cobb CenterforBorderStationsPrograms

    StevenJ.McGibney CenterforFederalBuildingsandModernizations

    gsaregionalexpertsLoriJ.Anderson Region1

    AnnaRaykis Region2

    AnthonyR.DellArciprete Region3

    WilliamH.Hunt Region4

    StephenR.Wallace Region5

    KevinW.Livingston Region6

    ElbertEGodwin Region7

    FaramarzM.Jafarzadeh Region8

    FrederickL.Jang Region9SonnyNeumiller Region10

    GeneM.Ransom Region11

    consultantfaithful & gould (formerly hanscomb, faithful & gould)TomWiggins SeniorAssociate

    ScottW.Cullen VicePresident

    acknowledgements vii

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    10/92

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    11/92

    generalrequirementsandprinciples

    1

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    12/92

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    13/92

    11 generalphilosophy

    The Federal Acquisition Regulation (FAR) 36.203 requires that every Governmentestimate be

    prepared as though theGovernment were competingfor theaward. Therefore,all coststhat a

    prudent and experienced contractor would incur must be included in project cost estimates.

    Alistingof knownfacts,constructiontasks,andsupplemental judgmentsformthebasisofthe

    estimateateachstageofdesign.Thisprovidesarealisticapproachtoestimating,anditcreatesa

    historyofprojectcostdevelopment.

    P100, Facilities Standards for the Public Buildings Service, lists the estimating deliverablerequirementsforeachdesignphase,buttheyareclarifiedhere.

    generalrequirementsandprinciples

    section1.13

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    14/92

    2 estimatorqualificationandethics1 requirements

    Capital project estimate submissions must be prepared by professional cost estimators

    unaffiliatedwiththedesignteamortheConstructionManagerasContractor(CMc).Certification

    asacostengineerbytheAssociationfortheAdvancementofCostEngineering(AACE),orasa

    certifiedprofessionalestimatorbytheAmericanSocietyofProfessionalEstimators(ASPE),is

    supportingevidenceofanestimatorsqualifications,althoughitisnotrequired.

    2 independentgovernmentestimate(IGE)TheFARrequiresthatanIGEbepreparedforallcontractsexceeding$100,000.Whenlifecycle

    costingor othereconomicanalysesarerequiredto supporta designdecision,professional

    estimators must establish construction cost estimates forall options if any one of themis

    expectedtohaveafirstcostinexcessof$100,000.

    Thefinalcostestimatesubmittedforthe100%constructiondocumentsphaseisusedasthebasis

    forthefinalIGE,whichthecontractingofficerusestodeterminewhetheranofferorsproposedpriceisfairandreasonableandreflectsanunderstandingoftheprojectrequirements.

    A qualifiedGovernmentemployee whose major responsibility iscreating or approving cost

    estimatesforGSAmustsignandapprovetheIGE,whichservesasthebasisforcommitmentof

    fundsbeforethesolicitationisissued

    3 ethics

    ThestandardsofpracticedescribedintheCanonsofEthicspublishedbytheAACEandtheASPE,andavailableonboththeirWebsites,applytoallestimatingservices.

    4 duediligenceexpectations

    GSAexpectsproperdiligenceinthepreparationofestimates,whichwillgrowsteadilymore

    accurateasthedesignprogresses.Whiletheestimatormayneedtomakemanyassumptions

    inpreparingtheconceptdesignestimate,oncetheconstructiondocumentsphasehasbegun,

    4projectestimatingrequirementsP120

    section1.2

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    15/92

    1estimates will no longer contain major assumptions. The project team will designate one

    persontocomparesuccessiveprojectestimatesandprepareanorderlyandcomprehensive

    reconciliation.

    Thearchitectengineer(AE)mustworkcloselywithGSAsindependentestimatortocoordinate

    the estimates with design submissions and the scope of work, to review assumptions

    concerningexclusionsandinclusions,andgenerallytoensurethattheestimatereflectsGSAs

    intent.Theseestimatorsmusthaveathoroughunderstandingofthemarketplaceinwhichthe

    projectislocated,researchmarketprices,andobtainpricequotesforspecialtyitems.

    5 penaltiesGSAcontractorsareadvisedtobeawareof18UnitedStatesCode1001,whichdealswiththe

    FalseStatementsAct.Thiscodestates,inpart:

    whoever, in any matter within the jurisdiction of the executive, legislative, or judicial

    branch of the Government of the United States, knowingly and willfully -

    (1) falsifies, conceals, or covers up by any trick, scheme, or device a material fact;

    (2) makes any materially false, fictitious, or fraudulent statement or representation; or

    (3) makes or uses any false writing or document knowing the same to contain any materially

    false, fictitious, or fraudulent statement or entry;

    shall be fined under this title, imprisoned not more than 5 years or, if the offense involves

    international or domestic terrorism (as defined in section 2331), imprisoned not more than

    8 years, or both.

    generalrequirementsandprinciples

    section1.25

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    16/92

    3 costestimatingandmanagementpractices1 costmanagementprinciples

    designwithinbudget

    Unlessotherwisespecifiedindesigncontractdocuments,theAEmustdesigntheproject

    sothatconstructioncostswillnotexceedthefundinglimitationsestablishedastheBasis

    ofFeeNegotiation.FAR36.6091requiresthattheAEredesigntheprojectat thefirmsownexpensetoensurethataresponsiveconstructionbidamountwillbewithinfunding

    limitations.

    prospectusauthorization/appropriation

    InaccordancewiththePublicBuildingsActof1959(PL86249),asamended,theUnited

    StatesCongressmustauthorizethescopeandbudgetofeachmajorcapitalconstruction

    project before design begins. Once Congress has approved a projects construction

    budget,itcannotbeincreased,sothedesignteammustapproachprospectusfundingasanabsolutelimit.

    pursuitofconstructionservices

    Constructionbidsmaybesolicitedonlyif theEstimated Costof Constructionat Award

    (ECCA) amount at final construction documents is within congressionally authorized

    prospectuslimits.

    itemizedcostmanagement

    Whenprojectfundsaresecuredfromdifferentagenciesor areprovidedasa dedicated

    allowance fora specific program goal, independentestimates must be made foreach,

    allowingseparatetrackingofexpenditures.Fundingallocatedforsuchprojectsistracked

    toconfirm that expendituresare apportionedaccordingto amounts authorized byeach

    agency,soasnottoexceedthededicatedallowance.

    independentestimates

    TheGovernmentrequiresthirdpartyestimatorsformajorconstructionprojectstoverify

    6projectestimatingrequirementsP120

    section1.3

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    17/92

    1thattheprojectsscopeandcostarewithinbudget.Theseestimatesarepreparedbyan

    independentcostestimatorwhoisnotaffiliatedwiththedesignfirmortheConstruction

    ManagerasContractor(CMc).Thedesignteamprovidesallrequireddocumentationfortheestimatortoprovideestimatesfor,ataminimum,thefollowingphases:

    FinalConceptDesign

    FinalDesignDevelopment

    90%ConstructionDocuments

    100%ConstructionDocuments

    2 estimatingformatsUsingstandardestimatingformatsforcostestimatingandcostmanagement:

    Ensures a uniform costcontrol framework throughoutthe various stages ofproject

    development.

    Definesaproperlevelofdetailtosetexpectationsfortheestimatingeffort.

    Servesasachecklisttoensurecompletecoverageofprojectscope.

    Providesforastandardizedhistoricaldatabaseorlibrary.

    spacetypeestimates

    Thisformat,usedprimarilyfornewconstructionprojects,appliesspacetypeunitcoststo

    plannedspaceneeds,resultinginasetofspacerelatedconstructioncosts.Thesecosts

    maybeadjustedbyaddingknowncostsforspecialrequirementsdefinedthroughother

    estimatingformats.Thesumofspacetypecostsandspecialrequirementcostsequalsan

    EstimatedConstructionCost(ECC)fortheproject.

    SinceGSAsGeneralConstructionCostReviewGuide(GCCRG)usesspacetypeestimates,costestimatorsmust be familiar with this technique (seeChapter 1, Section 4.4foran

    explanationofGCCRG).

    uniformatestimates

    Uniformatestimatingappliesunitcostdatatobuildingsystemandcomponentsiteelements.

    Thissystemsapproachusesahierarchicalstructureofcostelements,beginningatLevel

    1withbasicsystems,suchasSubstructure,ExteriorEnclosure,andInteriorConstruction,

    generalrequirementsandprinciples

    section1.37

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    18/92

    andproceedingtosuccessivelymoredetailedsubdivisionsofthesesystemsatLevels25.

    Theresultinglevelsofdetailnotonlyservetostructurecostinformationbutalsofacilitate

    estimatestowhateverlevelofdetailthedesignteamcanprovideastheprojectisdevelopedthroughthedesignsubmissionphases.Forexample,bythefinalconceptdesignphase,

    thedesignteamandestimatormayhaveLevel4 informationonSubstructure,butonly

    Level2detailforInteriorConstruction.

    Although the construction industry usesseveralvariations on the Uniformat concept,

    GSArequiresthatcostestimatorsuseitsparticularversion,forconsistencyinuseand

    maintenanceofGSAscostdatabases.GSAsUniformatestimatingformatisillustratedin

    Appendix A: Estimating Formats.masterformatestimates

    MasterFormat,a productof theConstructionSpecifications Institute (CSI),is themost

    widely used standard for organizing buildingproject specifications and detailed cost

    estimatingdataintheU.S.Itisusedparticularlywhendrawingsandspecificationsare

    sufficientlydetailedtoallowmaterialandequipmentquantitytakeoffs,anditistypically

    alignedwithageneralcontractorsapproachtopreparingabid.Visitthe Construction

    SpecificationsInstituteWebsite(www.csinet.org)formoreinformation.workitemestimates

    GSARepairandAlterations(R&A) projects tend toutilizescopedescriptionsandcost

    estimatesorganizedbyworkitems.Whileworkitemsmayvarysignificantlydependingon

    thenatureoftheproject,asdefinedbyGSAprogramofficesandclientrequirements,the

    followinglistreflectsatypical,butnotcomprehensive,workitemclassificationforR&A

    projects:

    Buildingexterior Electrical Buildinginterior Lifesafety

    Accessibility Elevators

    Structural Hazardousmaterialsabatement

    Mechanical Roofing

    Plumbing Security

    8projectestimatingrequirements

    section1.3

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    19/92

    1Traditionally,R&Aprojectshaveusedtheworkitembasisbecauseitallowstheremoval

    oradditionofprojectscopetomeetbudgetarylimitationsandallowances.GSAassigns

    alphabeticalcodestotheworkitemswhendescribingtheprojectanditscostsforeachR&Aprospectus,asrequiredbytheOfficeofManagementandBudget(OMB)andCongress.

    SeeChapter2forfurtherdescriptionofnonprospectusprojects.

    otherformats

    GSAmayrequirethatestimatesbeformattedinadditionalways.Forinstance,itmaybe

    necessarytosubdivideestimatesforindividualbuildingsandothercomponentsintonew

    constructionandmajorrenovation.

    WorkitemsonnonprospectusprojectsfrequentlyevolvefromBuildingEvaluationReports

    (BERs),andestimatesfortheseprojectsmayfollowaWorkBreakdownStructure(WBS).

    SituationsthatmightrequireaWBSinclude:

    Differingfinancialcommitmentsofmultipletenantsofaproject,requiringseparate

    contractsforeachtenantswork.

    Theneedforseparatecontractsforbuildingsandtheirsitework,suchasatborder

    stations.

    Phased renovation projects requiring swing space for a variety of tenants ordepartments.

    Projectstobefundedovermorethanoneyear.

    Separationofaprojectintobasecontractworkandoptionsoralternates.

    Projectsbelow$100,000maybeexecutedunderlineitemorjobordercontracts,forwhich

    costestimatesarederivedfromlineitemdatabases.Costproposalsfortheservicesofthe

    AEsestimatorandtheindependentgovernmentestimatormustbesubmittedtoGSAon

    Form2630/2631,showninAppendixE.

    generalrequirementsandprinciples

    section1.39

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    20/92

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    21/92

    14 estimatingrequirements

    1 general

    TheGovernmentrequirescostestimatesfor,ataminimum,thefollowingphasesofdesign

    Establishinganinitialprojectbaseline.

    Preliminaryconceptdesign,withmultipleschemesofdesign

    Finalconceptdesignprecedingvalueengineering

    Finalconceptdesign Designdevelopmentprecedingvalueengineering

    Finaldesigndevelopment

    75%constructiondocuments

    90%constructiondocuments

    100%constructiondocuments

    Theestimate must includeall elementsof theproposed projectwork (including all designcontract modifications), regardless of the design phase. The estimate must all include

    verificationandcontinuity ofcostbudgets inthetransfer fromestimate to thecontractors

    scheduleofvalues.Wherecostsareincludedfordetailsnotindicatedonthedrawingsand

    specifications, the independent governmentestimator must include designassumptions to

    completethescope.Theestimatormustcheckallcostestimatecalculationsforaccuracyand

    completeness, including assessingwhetherestimatescompletely and accurately represent

    designfeaturesandquantities.

    Lumpsumpricingisnotacceptablewithoutdescriptionandquantification.

    2 warmlitshellvs.tenantimprovement(TI)costestimates

    GSAspricingpolicy callsfor a separatetenantimprovementbreakdownof all tenantspace

    fitout,identifiedbyagency.YoucanfindGSAspricingpolicyandtherelatedmodificationsand

    clarificationsatthefollowingexternalWebsite: http://www.gsa.gov/rentpricingpolicy

    generalrequirementsandprinciples

    section1.411

    http://www.gsa.gov/rentpricingpolicyhttp://www.gsa.gov/rentpricingpolicy
  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    22/92

    For further inquiries, contact BethLemanski, David C. Baker, or Kelly Juarez of PBS Real

    PropertyAssetManagement.

    Theagencyhousingandsupportingfloorplansmustbeusedtoorganizetheestimatedetailby:

    Warmlitshell

    Tenantagencyfitout

    Securityupgrades

    3 contentsanddegreeofdetail

    Table1illustratestheformatsandminimumlevelofdetailrequiredforcostestimatesateach

    designphase.

    unitpricing

    Unitprice cost estimates are based on detailed design documents and developed by

    addingupthedirectcostsofmaterialsandsupplies,labor,andconstructionequipment

    foreachindividualtaskofconstructionwork.Thebasisfortheseunitcostsmustbewell

    documentedandincludedinthesupportingdataoftheestimate.Tothesedirectcostsare

    addedapplicableindirectcosts,suchasoverheadandprofitatasubcontractorlevel,to

    reflecttheinplaceconstructioncostperunitofworkrequired.

    Forconceptdesignestimates,itisacceptabletouseunitpricescombininglabor,materials,

    andequipmentcostsinasinglefigure.Forestimatespreparedatthedesigndevelopment

    andconstructiondocumentsphases,GSArequiresseparatelabor,material,andequipment

    unitpricing.

    Items that are a significant percentage of the total projects cost require the greatest

    estimatingeffort.Forsuchitems,indirectcostsandothermarkupsassociatedwitheachtaskorwork itemmustbe separatelyidentifiedandconsidered.Onaprojectbyproject

    basisGSArequiresquotesfromsuppliersorspecialtycontractorstodocumentthecostsof

    suchmajoritems,andtheestimatormustbepreparedtodiscussthemwithGSA.

    Documentation of unitprice data for smaller items could include price quotes, audits,

    catalogcuts,andhistoricalcoststoclarifypricebasesandassumptionsmadewhenother

    information is not available. The independent government estimator provides a general

    12projectestimatingrequirementsP120

    section1.4

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    23/92

    1statementdescribingthesourcesofunitcostsandquantitiesusedforeachcostdivisionor

    category,butindividualsourcereferencesforeachitemizedcostelementarenotrequired.

    generalconditionsandprofit

    Feasibility Studies, Program Development Studies, and Concept Design

    A percentage allowancean overall percentage allowance for theGeneralContractors

    generalconditions,bonds,insurance,andcorporateoverheadandprofitisappropriate

    if theprojectinvolvesnounusual coordination, site preparation, orspecializedsupport

    services.

    Design Development and Construction Documents

    Itisappropriatetoestimatethesecostswithtwobreakdowns:

    General Conditions: Comprised of itemized general requirements and jobsite

    supervision.

    MarkUps: Comprised of generalandadministrativecosts(including state and

    localtaxes),profit,bonds,andinsurance.

    siteanddesigncontingencies

    Contingencies are an integral part of the total estimated costs of a projectand cover

    coststhatmayresultfromincompletedesign,unforeseenandunpredictableconditions,

    oruncertaintiesconcerningprojectscope.The amountof thecontingencywilldepend

    on thestatusof design, procurement, andconstruction,aswell as thecomplexity and

    uncertaintiesofthecomponentpartsoftheproject.Contingencyisnottobeusedtoavoid

    makinganaccurateassessmentofexpectedcost.GSAmaychoosetosetasideseparate

    contingencies for major schedule changes, unknown design factors, unanticipated

    regulatorystandardsorchanges,additionstoprojectscope,forcemajeuresituations,or

    congressionalbudgetcuts.

    Contingenciesmust always be separately identified so that themagnitudeof a contin-

    gencysimpactisclear.Forexample,theIndependentGovernmentEstimatormaynever

    addcontingencybyconcealingitwithinunitpricingorquantityestimatesortakeoffs.

    Siteanddesigncontingenciesstartat10%duringtheprogrammingandplanningstages

    andarereducedtozeroasthedesigndevelops(seeTable2).

    generalrequirementsandprinciples

    section1.413

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    24/92

    table1.requirementsforcostestimatingateachdesignphase

    ProjectPhase EstimateWBS Detai lLevel SummaryLevel EstimateBasis TI/Shel l

    ConceptDesign GSAUniformat III IIParameterandQuantification

    Yes

    Design GSAUniformat IV;Note5 III QuantificationandParameter

    YesDevelopment CSIMasterformat Note1&5 Note1

    75%CDGSAUniformat

    CSIMasterformat

    N/A

    Note2&5

    IIIQuantification Yes

    Note3

    90%CDGSAUniformat

    CSIMasterformat

    N/A

    Note4&5

    IIIQuantification Yes

    Note3

    100%CDGSAUniformat

    CSIMasterformat

    N/A

    Note4&5

    IIIQuantification Yes

    Note3

    Note1.Ifthedetaileddrawingsandoutlinespecificationsareavailable,providetheCSIMasterformatcostestimateatthegreatestdetailthatthedrawingsandspecificationswillsupport.

    Note2.ThelevelofdetailofthecostestimateinCSIMasterformatcorrespondstoUniformatLevelIV,asdefinedinthisdocument.

    Note3.ThesummaryofthecostestimateinCSIMasterformatcorrespondstoUniformatLevelIII,asdefinedinthisdocument.

    Note4.ThelevelofdetailofthecostestimateinCSIMasterformatcorrespondstoUniformatLevelV,asdefinedinthisdocument.

    Note5.Unitpricesarebrokendownintolabor,materials,andequipment.

    table2.guidelinesforstandardsiteanddesigncontingencies

    ESTIMATECATEGORY %

    Program/Planning 10%

    ConceptDesign 7%10%

    DesignDevelopment 5%7.5%

    IntermediateConstructionDocuments 2 5%

    FinalConstructionDocuments 0%

    14projectestimatingrequirementsP120

    section1.4

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    25/92

    1escalation

    EscalationistheanticipatedincreaseintheprojectsEscalationistheanticipatedincrease

    intheprojectscostduetoinflationbetweenthetimetheestimateispreparedandwhentheprojectisfinished,sinceinflationcontinuesduringprojectconstruction.Forsimplicity,the

    estimatormustassumethathalfoftheworkwilloccurbeforethemidpointofconstruction

    andhalfafter.Therefore,theestimateisescalatedtothemidpointofconstructiontoreflect

    thecontractorsprovisionforinflationinitsbid.

    Intheplanningstage,escalationratesaretakenfromtheGCCRG.Asthedesignprogresses,

    theAEandGSAmustagreeonanannualconstructioncostescalationcompoundingrate,

    basedonamarketsurveypreparedbytheAE,foruseinalldesignestimatesandcost

    analyses.ItistheresponsibilityofthedesignAEtocontrolthecostoftheprojectsothatwhentheECCAbudgetisreducedbytheforecastedescalationrate,theresidualbudget

    amountequalsthecurrentvalueoftheproject.

    artinarchitecture

    Theartinarchitecturesetasideamountis0.5%ofECCA.

    constructioncontingency

    The construction contingency is an allowance for cost growth that may occur during

    constructionasaresultofunexpectedcircumstancesorincompletedesigndocuments.

    GSAcurrentlyrecommends7%fornewconstructionprojectsand10%forrenovations,but

    maydirecttheuseofdifferentfiguresonaprojectbyprojectbasis.

    applyingmarkups,contingencyandescalation

    Figure1demonstrateshowmarkups,contingencies,andescalationshouldbecalculated

    andappliedtoprojects.

    reviewingandreconcilingestimatesOnprojectsfor whichGSArequiresthe preparationofanIGE,the AEis responsiblefor

    designatingamemberofitsteamtoreconciletheIGEwithitsownestimateinanorderlyand

    comprehensivemanner.

    costmanagementrequirements

    AccurateestimatingisanimportantcomponentofGSAscostmanagementprocess,as

    wellasanimportantdecisionmakingtoolforthedesignteaminitsselectionofsystems

    generalrequirementsandprinciples

    section1.415

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    26/92

    andmaterials.Inordertoservethesepurposes,carefulconsiderationmustbegiventothe

    following:

    CostelementcomparisonsPreparedateachmilestonetocomparethecurrentestimatetothepreviousmilestoneestimateandtotheoverallbudgetandtothe

    baselineestimatetoascertainwhetherdesignorscopechangeshavebeenmade

    orneedtobemade.RefertotheestimatetrackingsheetsinAppendixB.

    EarnedvalueaccountingUsedinconjunctionwithcostelementcomparisons,

    theearnedvalueprocessallocatescostasitiscommitted,orasapartoftheproject

    iscompleted.Decisionsregardingcontingencyandescalationareimportantinthis

    process.Foradditionalinformation,seetheWholeBuildingDesignGuidewebsite

    atwww.wbdg.org.

    Lifecyclecostanalysis Used toevaluatethe implicationsof decisionsmade

    duringthedesignprocessnotonlyoninitialcostbutalsoonlifecyclecosts.Issues

    considered typically include energyutilization, sustainability, maintenance, and

    operations.SeeChapter2,Section2.2fordetails.

    Shell and core, security upgrades, and tenant improvement (fitout) GSA

    requires subdividing the estimate into costs for the shell and core and tenant

    improvements,includingtheassociatedprofessionalservicescostsincludedinthe

    occupancyagreementbetweentenantsandGSA.BoththeAEsestimatorandthe

    independentgovernmentestimatormustsubmittheircostproposalsforprofessionalservicestoGSAusingForms2630and2631.SeeAppendixEforsampleforms.

    Phasing/schedulingpackagesUsedforprojectworkdividedintomorethanone

    constructionphase.Separatecostestimates,accompaniedbyanoverallproject

    ECCAsummary,supporteachphase.Forphasednewconstruction,aconstruction

    management (CM) firm hiredbyGSAmust prepare a postaward construction

    costanalysisforeachphase.Aftercontractawardofthelastconstructionphase,

    a combined postaward construction analysis for the composite project bid is

    prepared.

    Multistructure projects Projects involving more than one structure require

    separateestimatesforeachstructure.Separatesiteconstructioncostestimates

    mustbeassociatedwiththeestimatesforeachstructureinvolved.ACMfirmhired

    byGSAmust preparea constructioncost analyses foreachstructure andsite

    developmentafterthemultistructureprojectisawarded.

    BidalternatesandoptionsACMfirmhiredbyGSAmustprepareseparatecost

    estimates forthe basebidandfor eachindividualalternateor optionwhen the

    projectrequiresthem.

    projectestimatingrequirementsP120

    section1.416

    http:///reader/full/www.wbdg.orghttp:///reader/full/www.wbdg.org
  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    27/92

    figure1. calculationofmarkups,contingencies,andescalation 1

    generalrequirementsandprinciples

    section1.417

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    28/92

    benchmarking

    Benchmarkingmaybe requiredtoassess andverifythe costof a projectbyreference

    toestablishedcostsforsimilarfacilities.GSAhasaccesstoa numberof toolsuseful toestimatorsinvolvedinbenchmarking.

    4 costestimatingandcostmanagementtools

    gsacostestimatingtoolsandspreadsheets

    GCCRG

    GSA developed the General Construction Cost Review Guide (GCCRG) to assist estimating in

    the planning phase of new construction projects. Figure 2is an example of a GCCRG estimate.

    Project Cost Estimate (PCE)

    The PCE wasdesigned forprogramming andpredesign estimates. Applicationsmay

    includeBERs,feasibilityand programdevelopmentstudies, siteacquisitionand Market

    Surveystudies,anddesign. Figure3isanexampleofaPCEtoolsummary,Figure4isan

    excerptofamoredetailedestimatesheet.

    Building Life-Cycle Cost (BLCC) and Life-Cycle Cost (LCC) Spreadsheets

    SeeChapter2,Section2.2fordetails.

    costestimatingsystems

    GSAencouragesbutdoesnotrequiretheuseofcomputerbasedcostestimatingprograms

    tomitigatemanualcalculation errors andfacilitate changes. Therequirementsdefined

    in this documentcan be easily met byusing various commercially availablecomputer

    software programsand spreadsheets. Genericspreadsheetsallowuser adaptationand

    offerflexibilityinapplyingdifferentcostdatabases.

    Figure5isanexcerptfromaUniformatstructuredestimatereportfromacostestimatingsystemusedatthedesigndevelopmentphase.Itillustratestherequirementtobreakdown

    unitpricesintolabor,materials,andequipment.ThereportusestheUniformatlevelsto

    organizetheestimateanddefinethedetailoftheunitpriceitems.

    Figure6isanexcerptfroma MasterFormatstructuredestimatereportdevelopedat the

    design developmentphase. It illustratestherequirement tobreakdownunitpricesinto

    labor,materials,andequipment.

    projectestimatingrequirementsP120

    section1.418

    1

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    29/92

    figure2. generalconstructioncostreviewguide(GCCRG) 1

    generalrequirementsandprinciples

    section1.419

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    30/92

    figure3. exampleofaprojectcostsummary

    projectestimatingrequirementsP12020

    section1.4

    1

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    31/92

    figure4.PCEcostestimatedetailexcerptforaconceptdesignestimate 1

    generalrequirementsandprinciples

    section1.421

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    32/92

    figure5.uniformatdesigndevelopmentestimatereportexcerpt

    22projectestimatingrequirementsP120

    section1.4

    1

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    33/92

    figure6.CSImasterformatdesigndevelopmentestimatereportexcerpt 1

    generalrequirementsandprinciples

    section1.423

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    34/92

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    35/92

    prospectuslevelprojects

    product/deliverablerequirements

    2

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    36/92

    2

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    37/92

    21preliminaryplanningandprogramming

    projectrequirementsThischapterdealswithGSAsrequirementsforcostestimatingduringthedesignandconstruction

    phasesofaproject.Itdefinesanddescribesthescopeandlevelofdetailrequiredforeachpotential

    deliverableandproductrequired,inthecontextofeachphaseoftheproject.Forinformationon

    thefeasibilitystudyandprogramdevelopmentstudy(PDS)phasesofacapitalproject,seeGSAs

    ProjectPlanningGuide,availableinPDFformatat www.gsa.gov,whichisbrieflydescribedbelow.

    1 projectplanningguide

    GSA developed the Project Planning Guide to assist participants in the Capital Program

    developmentprocess inevaluating,developing,andimplementingFederalfacilitiesprojects.

    Theguideoutlinestheprojectdeliveryprocessandofferssomekeystosuccess.

    Theguideisdividedintofivesectionsandseveralappendices:

    Overview of GSAs Capital Program Outlines GSAs basic capital program

    developmentplanningprocessandthefundamentalrolesof thefeasibilitystudyandtheprogramdevelopmentstudy.

    WhatsImportantandWhenDiscussesGSAsprimarybusinessandprogramgoals

    aspresentedinthefeasibilitystudyandthePDS.

    PrePlanningPhaseDescribestheroleplayedbyGSAsdailymanagementoffacility

    requirements, customer needs,and portfolioplanning in theprojectdevelopment

    process.

    Feasibility Study Phase Outlines the process for beginning, conducting, andcompleting a feasibility study, a process that ends with the submission of the

    prospectuspackageforsiteanddesignfunding.Thissectiondescribestheprocess,

    deliverables,andkeystosuccessfuldevelopmentofasoundprojectandsite/design-

    fundingrequest.

    ProgramDevelopment Study (PDS)Phase Outlines theprocess forevaluating

    thefeasibilitystudyasthefoundationforthePDS,digestingnewinformation,refining

    theproject,anddirectingtheprojectsdesignandconstructionstrategy.Thissection

    projectestimatingrequirementsP120

    section2.127

    http:///reader/full/www.gsa.govhttp:///reader/full/www.gsa.gov
  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    38/92

    discusses the process, deliverables, and keys to successfully supporting a sound

    designstartandconstructionfundingrequest.

    AppendicesIncludeprocesschecklists,aglossary,worksheetsonteamroles,and

    resourcesformoreinformation.

    2 levelandformatrequirements

    RefertotheconceptdesignphaseestimatingrequirementsinTable1,Chapter1forthetype

    ofestimaterequiredatthepreliminaryandplanningphases.

    See Section 2.2of thischapter for a discussion of Market Surveysrequired duringthe

    Planningphase.

    28projectestimatingrequirementsP120

    section2.1

    2

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    39/92

    22 designandconstructionphasecost

    estimating1 basicconcept:forallphases

    Anydesignsubmissiondeliverablesmayinclude,butarenotlimitedto:

    costestimatesandreports

    marketsurvey

    costgrowthreports

    spacetypecostanalysis

    lifecyclecostanalysis

    valueengineeringstudies

    independentestimatereviews

    budgetanalysis

    constructionawardbidanalysis

    databaseinformationpreparation

    constructionmodifications&claimsanalysis

    valueengineeringchangeproposalsanalysis(VECPS)

    riskanalysisreports

    Thepurposeistoestablishacostmanagementsystemthattracksbudgetsestablishedbased

    on the prospectus in a Uniformat Level II, comparing cost growth and cost modificationsfor all Uniformat Level II elements through design, procurement, construction and project

    completion.

    Asageneralrule,earlyintheprocessUniformatistheprimaryestimateformat,althoughCSI

    MasterFormatmaybeselectedonaprojectbyprojectbasis.GSAusuallyrequiresworkitems

    onmajorrenovationprojectsorwhentheprojectistobeseparatedintomajorcomponentsor

    subbuildings.Thespacetypesummaryisusuallyrequiredatvariousprojectphases.ACost

    prospectusproduct/deliverableP120

    section2.229

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    40/92

    GrowthReportisrequiredatallsubmissions,andaLifeCycleCostAnalysisisrequiredthrough

    design development and potentially during construction documents phases for significant

    items.

    AnindependentpartyhiredbyGSAconductsavalueengineering(VE)workshop,andVEis

    providedinaccordancewiththedesignsubmissionsrequirementsofP100.GSAmayelectto

    conductanadditionalVEstudyattheconstructiondocumentsphaseonaprojectbyproject

    basis.

    WhenGSAcompletesaninternalreviewoftheestimate,orreconcilesanindependentestimate,

    andattheconclusionoftheVEstudy,afinalestimateissubmitted.

    2 costestimatesandsummaries

    summaryofformatrequirements

    Table1inChapter1displaysthetypeofestimatetobepreparedatthevariousdesignstages.

    preliminaryconcepts

    Preconceptestimatinggenerallyrequiresthepreparationofestimatesonthreecompeting

    basicschemes/concepts,allowingGSAtoselectitspreferredscheme.

    For each scheme, the AEs estimator prepares separate estimates for phased work,

    multistructures,andorbidalternates/options.TheAEalsosubmitsestimatesforconcept

    design analyses/studies as specified in designprogramming directives and/or design

    criteriareferences,andacomparisonsheetformultipleconcepts/schemes.

    conceptdesign

    Theseestimatingrequirementsapplytoanyconceptlevelsubmission.Ifaprojectsdesign

    requiresmultipleconceptsubmissions,eachconceptsubmissionmustbesupportedbytheestimatesdescribedhere.

    Estimators must calculate quantities for appropriate systems or apply parameters to

    appropriatebuildingareas.Appliedunitcostsmaybebasedoncombinedmaterialand

    laborcosts. Conceptestimatesmust matchtheestimate formatof thebudgetestimate

    tofacilitatecostbreakdowncomparisons.Forprospectuswork,thistypicallyrequiresthat

    UniformatLevel3 estimates beprepared,delineatingcostelement categoriesshown in

    30projectestimatingrequirementsP120

    section2.2

    2

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    41/92

    2Appendix A.1: Uniformat Level 1-5 Cost Elements.However,certainprojects(suchasnonpro-

    spectusrepairandalterationwork)mayhavehadtheirbudgetaryestimatesdoneinwork

    itemsorCSIMasterFormat.

    Backupworksheetsmust support detailed estimates, coveringall costsensitive project

    data and defining all major assumptions made. Backup estimating data and quantity

    surveyinformationmaybeinanyformat,groupedunderappropriateformatclassification

    headings.

    TheAEisrequiredtoprovidetheIndependentGovernmentEstimatoradvancecopiesof

    allconceptplansanddocumentationearlyenoughtoallowforthepreparationofrequired

    estimatesaspartof theconcept designsubmission.Advancedocumentsmust include

    floorplans,elevations,sections,andperspectiveviewsinsufficientdetailtoallowarealistic

    parametriccostassessment.Inaddition,theAEprovides:

    A statement on the conceptualapproach and general features for each major

    buildingsystem,includinganitemizedlistingofanticipatedtypesandapproximate

    capacities/sizes.Blockloadsforstructural,mechanical,andelectricalsystems.

    Quality levels ofmajormaterialsand systems tobe used, including any special

    design programming or code requirements relating to fire protection, HVAC,

    plumbing,electrical,andstructuralcomponents. A copy of thedesign programtoensurethat theestimator understands goals,

    objectives,anddesigndirectivesthatmaynotyetbereflectedinconceptdesign

    submissiondocuments.

    Toensurethattheprojectisdevelopingonbudget,theAEsestimatormustalsosubmita

    listofcostsavingitemsthatcollectivelywouldreducetheprojectscosttoapproximately

    10percentbelowbudget.

    TheIndependentGovernmentEstimatorisrequiredtoprepareanECCAsummarysheetto

    UniformatLevel2,representingallprojectandestimatedata.EachECCAsummarymust

    comparethedesigncostbreakdownwithanybudgetcostvaluesescalatedtothemidpointof

    construction,includingpersquaremeterorsquarefootcalculationsofoverallprojectcost.

    designdevelopment

    Tosupportdesigndevelopmentestimating,theAEprovidestheIndependentGovernment

    Estimatorthedocumentationnecessarytodescribeproposedtypes,quality,andquantities

    prospectusproduct/deliverableP120

    section2.231

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    42/92

    ofbuildingfeatures,systems,equipment,andmaterials.Projectschedulingmustallowfor

    theearlydeliveryofadvancecopiessothattherequiredestimatescanbeincludedwiththe

    designdevelopmentsubmissions.

    Asaseparatecostsavingtask,theAEsestimatormustalsosubmitalistofcostsaving

    itemsthatcollectivelywouldreducetheprojectscosttoatleast10percentbelowbudget.

    The independent governmentestimatorprepares anECCAestimate forthe basebidand

    separateestimatesforphasedwork,multistructures,and/orbidalternatesoroptions.Anoverall

    projectECCAestimatewillalsobeprepared,incorporatingallprojectsegments,foranalyses

    orstudiesspecifiedindesignprogrammingdirectivesanddesigncriteriareferences.

    Backupworksheets arerequiredtosupport thedetailed estimates, whichrepresentallcostsensitiveprojectdataanddefineallmajorassumptions.Backupestimatingdataand

    quantitysurveyinformationmaybeinanyformat,butmustbegroupedunderappropriate

    formatclassificationheadings.TheEstimateTrackingSheetandElementalCostSummary

    formsmustbesubmitted,includingpersquaremeterorsquarefootcalculations.

    constructiondocuments

    Estimating requirements given here apply to all required construction documents

    submissions75%, 90%, and 100% CDsunless specified as applicable only to final constructiondocuments.

    Ifthe overallprojectsconstructiondocumentsestimateexceeds thebudget,theAEis

    againrequiredtoproposecostsavingmeasurestobringtheprojectwithinbudget,atits

    ownexpense.Toavoidoverbudgetconstructionbids,theAEsestimatormustidentifyat

    leastfiveconstructioncostsavingitems,formulatedasbidalternates,tobringtheprojects

    estimateatleast10percentbelowbudget.

    The Independent Government Estimator prepares an ECCA estimate for the base bid,including separateestimates forphased work, multistructures,and/or bid alternatesor

    options withany addenda.AnoverallprojectECCAestimate isalsoprepared, incorpo-

    ratingallprojectsegments,foranalysesorstudies,asspecifiedindesignprogramming

    directivesanddesigncriteriareferences.

    ECCA estimates are developed using MasterFormat, with detailed material and labor

    breakdownandappropriatesubdivisionsasshowninAppendixA.MasterFormatestimates

    32projectestimatingrequirementsP120

    section2.2

    2

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    43/92

    2arealso summarized inUniformatLevel3 estimates andwork items. Forboth formats,

    backup worksheet estimates are arranged by cost categories, with a summary sheet

    combiningallcategorycosts.The90% and100%ConstructionDocumentestimatesare

    preparedatthesamelevelasrequiredforthecontractorperformingtheconstructionwork,

    inaccordancewiththeFAR.

    Backupworksheets arerequiredtosupport thedetailed estimates, whichrepresentall

    costsensitiveprojectdataanddefineallmajorassumptions.Backupestimatingdataand

    quantitysurveyinformationmaybeinanyformat,butmustbegroupedunderappropriate

    formatclassificationheadings.

    Submissions must follow the formats in Appendix A and provide persquaremeter or

    squarefootcalculations.

    MasterFormatcostestimatesarepreparedtoanequivalentofUniformatLevel5,withunit

    pricesseparatelyrepresentingmaterialandlabor.Costelementlumpsumestimatingfor

    eitherformatsystemmaybeusedonlybypermissionofGSA.Ifcostelementsaretransferred

    fromprevioussubmissionlevels,quantityvaluesmustbeverifiedandunitcostsadjustedto

    reflectescalationtotheconstructiondocumentssubmissiondate.Allowancesfordesign

    contingencies,generalconditionsandprofit,bonds,andconstructionescalationareadded

    tocalculatetheECCAamount.

    3 marketsurvey

    GSA requires that the design AE preparea Market Survey for everyprojectand for each

    submissionindicatedintheTasking Matrix (Table3inChapter3),anddescribedbelow.

    A Market Survey explores all factors influencingconstructioncosts relevant to thecurrent

    stageofdesign.TheMarketSurveypreparergatherspertinentdatabyinterviewinglocalfirmshavingknowledgeof constructionin thearea.Possiblesourcesinclude,butare notlimited

    to,generalcontractorsandsubcontractors,buildersassociations,localgovernmentofficials,

    architecturalandengineeringfirms,buildersexchangeandconstructionreportingfirms,and

    bankersandcommercialmortgagefirms.Particularemphasismustbeplacedonascertaining

    theavailabilityofmechanicaland electricalsubcontractors andtheassociated skilled labor

    trades. The Market Survey must reflect recent and expected bidding conditions that may

    influencethecostofconstructionandlistallsourcesofdata.

    prospectusproduct/deliverableP120

    section2.233

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    44/92

    ThepersonwhopreparestheMarketSurveyvisitsthesiteandlocalmarketareastodetermine

    thefollowing:

    Availabilityandshippingoriginofmajorprojectmaterials. Capabilityoflocalfabricators,precastyards,concreteplants,etc.

    Availabilityoflaborcraftsnecessaryfortheproject,especiallyskilledlabor.

    Availabilityofspecialerectionequipment.

    Anticipatedcapacityoflocalcontractorsduringbiddingperiod.

    Specialconditionsthatmightinfluencebidding.

    Localescalationexperience.

    Siteaccessibility.

    Batchplantoptionsforconcreteandasphalt.

    Applicablelocaltaxesorgrossreceiptstaxeswheretheprojectwillbeconstructed.

    Costsofremoteness,suchaslaborforlosttime,housingallowance,orrequirementfor

    onsitehousingormaterialdeliverycosts.

    TheMarketSurveyalsoincludes:

    Whowascontacted(person,firm,phone,email).

    Wheretheyarelocated.

    Whencontactwasmade.

    Whytheywerecontacted.

    Whatinformationwasobtained.

    Asummaryassessmentwithspecificrecommendations.

    conceptdesign

    The AEconductsa MarketSurveyas describedabove andas requiredby theTasking

    Matrix (Table3inChapter3).

    designdevelopment

    During the design development phase, the concept design phase Market Survey is

    updated,verified,andrefinedtoincludeallchangesnecessarytoreflectnewinformation

    34projectestimatingrequirementsP120

    section2.2

    2

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    45/92

    2onlocalmarketconditions,suchasregionalbuildingboomsandotherpotentialmajor

    projects withcomparableconstructionschedules.These updated MarketSurveysare

    submittedasrequiredbytheTasking Matrix (Table3inChapter3).

    constructiondocuments

    Atthe90%and100%constructiondocumentsphases,thesurveyprocessintensifies,andall

    datagatheredisreported.Thereportclearlydepictsthelikelybiddingmarket,otherprojects

    likelytobeonthemarket,andhowhungrythemarketislikelytobeatthescheduledtime

    ofbid.Thefinalestimatemustincorporatethesurveysconclusionsandreflectthecurrent

    biddingclimate,includinginformationontheexpectednumberofbiddersforgeneraland

    subcontractors,theamountofcompetitionamongcontractors,andotherconditionsthat

    mayhaveanimpactontheconstructionproject.

    Notethatinthisphasetheprojectsconstructionmanagerasagentwillbepromotingthe

    projectwithintheconstructionindustrytodevelopinterestforgoodcompetition.

    prospectusproduct/deliverableP120

    section2.235

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    46/92

    4 costgrowthreport

    GSA uses the Cost Growth Report (CGR) to track cost growth at each design phase by

    comparisonwiththeprojectbudget.ThisisdonebycomparingthepriorsubmissionsUniformat

    Level2costsforeachcostelementwiththecurrentsubmissionsLevel2costs,andidentifying

    thecauseoflargevariances.TheAEsestimatorpreparesthisreportforeachdesignphase

    submission,usingGSAForm3474,ProjectCostComparisonSummary.SeeAppendix B: Estimate

    Tracking Sheetsforasampleoftheform.

    preliminaryconceptdesign

    Eachdesignconceptconsideredduringthissubmissionmustbewithintheprojectsoverall

    constructionbudget.TheAEwillberequiredtoredesignanyconceptdesignschemenot

    withinthebudgettobringitwithinbudgetconstraintsatitsownexpense.

    Foreach conceptscheme, theAEs estimatorlistscostsaving ideas thatcollectivelywill

    bringprojectcostswithinbudget.TheIndependentGovernmentEstimatorvalidatesthese

    costsavingmeasuresbypreparinganorderofmagnitudeestimateofsavingsforeachofthe

    AEsproposedmeasures.TheAEsubmitsitsCostGrowthReportonGSAForm3474.

    finalconceptdesign,designdevelopment,andconstructiondocuments

    Iftheestimatesfortheconceptdesignanddesigndevelopmentsubmissionsexceedthe

    projectbudget,theAEisrequired,atitsownexpense,toproposecostsavingmeasures

    tobringtheprojectwithinbudget.Justasdescribedaboveforthepreliminaryconcept

    designsCGR,theAEsummarizesthefinalconceptdesignestimateonGSAForm3474

    andcomparesittotheprojectbudget.Thisreportissupportedwithcostestimatesforeach

    proposedcostsavingitem.Theindependentgovernmentestimatorvalidatesthesecost

    savingmeasuresasoutlinedintheparagraphaboveforthepreliminaryconceptdesign

    phase.

    If theestimate for90% constructiondocumentsexceeds theproject budget, theAE is

    requiredtoproposecostreductionsintheformofbidalternatessufficienttoensurereceipt

    ofbidswithinbudgetonthescheduledbiddate.TheIndependentGovernmentEstimator

    validatesthesecostsavingmeasures,asindicatedintheparagraphabove,fortheconcept

    designanddesigndevelopmentsubmissions.

    projectestimatingrequirementsP120

    section2.236

    2

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    47/92

    25 spacetypecostanalysis

    Aspartofanewconstructionprojectcostestimatesubmission,theIndependentGovernment

    Estimatorestimatesconstructioncostsbyspacetypesby:

    Identifyingallprojectspacetypes,consideringatleastthosecategorieslistedinthe

    GCCRG.

    Separatelyitemizingspecialcostsoutsidenormalrequirementsoflistedspacetypes,

    addressingatleastthoselistedintheAppendixasSpecialCostsExcluded.

    6 lifecyclecostanalysis

    Lifecyclecosting(LCC)isthedevelopmentofallsignificantcostsofacquiring,owning,and

    usinganitem,system,orserviceoveraspecifiedlengthoftime.Thetimeperiodusedisthe

    projectedeffective usefullifeof thefacility,anditsdeterminationincludes considerationof

    functionalobsolescenceofmajorcomponentsorsystems.Itisusedtocompareandevaluate

    thetotalcostsofcompetingsolutionsbasedontheanticipatedlifeofthefacilityorproductto

    beacquired.

    Thevalueofanitemincludesnotonlyconsiderationofthecostsofacquiringit,butalsothe

    costsofusingitorthecostofperformanceforaslongastheuserneedsit.Costsofrepairs,

    operations,preventivemaintenance,logisticsupportutilities,depreciation,andreplacement,

    inadditiontocapitalcost,allcontributetothetotalcostofaproducttoauser.

    ForfurtherguidancerefertoFacilitiesStandardsforthePublicBuildingsService(PBSP100)

    andGSAValueEngineeringGuide(PBSPQ250and251).

    7 valueengineeringstudies

    Valueengineering(VE)isconductedduringtheconceptdesignanddesigndevelopmentphases

    toexplorecostsaving/valueenhancingoptionsbeforeselectingfinaldesignfeatures.GSAmay

    conductadditionalstudiesduringthe75%and90%constructiondocumentsphases,andfor

    100%constructiondocumentsifdeemednecessaryduetotechnicalorbudgetaryconstraints.

    Asinglestudymaybeappropriateonsmaller,lesscomplexprojects.Thebasicapproachisto

    considermacrolevelissuesatconceptdesignandmoremicrolevelissuesatdesigndevelopment.

    prospectusproduct/deliverableP120

    section2.237

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    48/92

    Ingeneral,decisionsmadeasaresultofthefirststudywillnotbereconsideredinthesecond

    studyunlesssignificantnewinformationisavailable.Furthermore,designchangesimplemented

    asaresultofthestudieswillgenerallybeconsideredwithintheboundsofthenormaldesign

    process.Exceptionstothiswillbeconsideredonacasebycasebasis.

    baselineprospectus

    TranslatetheapprovedprospectuslineitemsintoUniformatLevelIItobeusedasabasis

    ofcomparisonandcontrolthroughouttheprojectlifecycle.

    designconcept

    Formajorcapitalconstructionandcertainotherprojects,aVEstudywillbeincludedasa

    requirementfortheconceptdesignsubmissions.GSAcontractswiththeVEconsultantdirectly,ratherthanthroughtheAE,buttheAEparticipatesinandreviewsVEproposals

    toaddressproject feasibilityandadherenceto designprogramming requirements.The

    AEscostestimatormustbeavailabletoanswertheVEconsultantsquestionsconcerning

    theoriginof AEconceptdesignestimateunitcostsandinterpretationof workelement

    descriptions. Once GSA determines what VE consultants recommendations are to be

    used,thedesignAEmustincorporatetheserecommendationsintodesigndocumentsas

    partofthescopeofwork.

    Fornewconstructionprojects,thefirststudyatconceptdesignisintendedtoreviewbasic

    designdecisionsthatpertaintoareassuchas:

    Sitingandbuildingorientation

    Buildingform,shape,andmassing

    Layout

    Proportionofoccupiableareatogrossarea

    Designcriteria Buildingsystemsselectionoptions

    Spaceprogramoptions

    Buildingspace/volumeparameters

    Verticalandhorizontalcirculation

    Majormechanicalelectricalplumbing(MEP)considerations

    Overallenergyconsiderations

    projectestimatingrequirementsP120

    section2.238

    2

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    49/92

    2 Siteaccess/egress

    Overallphasing/schedulingplans

    Subsoilconditionsandgeologicaldata

    Utilityavailability

    designdevelopment

    Thesecondvalueengineeringstudyat thedesigndevelopmentphasefocusesonmore

    detaileddesigndecisionsincluding:

    Specificbuildingsystemdesign

    Specificationandperformancerequirements

    Proposeddesigndetails Layoutoptionswithinoverallbuildinggeometry

    SpecificMEPsystemselections

    Sitepaving,grading,andutilities

    Phasingandschedulingplans

    Majorconstructabilityissues

    TheAEmustincorporatetheVEconsultantsrecommendationsapprovedbyGSAintothe

    designaspartofthescopeofwork.

    8 budgetanalysis

    AnECCAsummaryispreparedateachmilestone,usingtheformatsinAppendixB,tocompare

    thecurrentdesigncostbreakdownwiththeprevioussubmissionscostsorthebudget,withall

    valuesescalatedtothecurrentsubmissiondate.Thesummarymustincludeallowancesfor

    designcontingencies,generalconditionsandprofit,andconstructionescalationandyieldan

    overallprojectcostpersquaremeterorsquarefoot.

    9 requirementsforbidsubmission

    Procurementofficialsensurethatthebidpackagesincludealumpsumbidrequirementfor

    eachbidoption,alternate,andunitpricingitem.

    prospectusproduct/deliverableP120

    section2.239

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    50/92

    2

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    51/92

    210constructionawardbidanalysisforprospectuslevelprojects

    bidanalysis

    After the construction contract is awarded, the Independent Government Estimator

    analyzesthebidcost,usingallavailablecostdata,includingthecontractorsbreakdownof

    costssubmittedasthepaymentscheduleformonthlyprogresspaymentsforeachtradeor

    subcontract.

    TheIndependentGovernmentEstimatorreviewsthefinalcostestimateinUniformatLevel

    3andrevisesittoalignwiththeactualbidprice.TheadjustedcostdataisprovidedtoGSA

    informatsfoundinAppendicesCandD.

    Aftercompletionof theabovecost analysis, theestimatoruses a formatsimilar tothat

    foundinAppendixDtoprovideasynopsisoftheprojectspaceplan,efficiency,scope,and

    basicdesignparametermeasures.

    GSAwillprovidetheAEandtheIndependentGovernmentEstimatorthefollowingdata:

    Theabstractofbidsreceivedfortheprocurementwithanindicationoftheaward

    amountandthebidsofferedbyallcontractors.

    Anybreakdownorverificationofcontractororsubcontractorpricesinthecourse

    ofcontractaward.

    Thecontractsapprovedscheduleofpricestobeusedforprogresspayments.

    11costdatabase

    GSAusescostdatacollectedforsimilarbuildingtypestodevelopspacetypecostbenchmark

    toolsto improvebudget developmentfor futureprojects. Therefore, GSAsregionalproject

    managerprovidescost estimates, reconciledestimates,bid analysis,andconstruction cost

    reconciling back to the bid estimate to the regional cost advocate or Central Office costmanagementstafftocompilethisdataintoGSAscostdatabase.

    12constructionmodificationsandclaimsanalysis

    This sectionprovides information,procedures,andguidance forestimatingandprocessing

    constructioncontractmodifications.Contractmodificationsincludechangeorders,contractor

    prospectusproduct/deliverableP120

    section2.241

    l f l l f h h h d k

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    52/92

    claims,formalresolutionofconstructivechanges,theimpactonunchangedwork,suspension

    ofwork,andtimeextension.

    Anindependentestimate forcontract modificationsrequestedbythe Governmentmustbepreparedbeforetheproposalrequestissenttothecontractor.TheIndependentGovernment

    Estimatormustbeprovidedthesamedocumentsconcerningtheproposedmodificationthat

    thecontractorwillbeprovided,orhaveaccesstothem.

    TheIGEpreparedinresponsetoacontractorinitiatedproposalmustbepreparedtothesame

    levelofdetailasthecontractorsproposalandbebasedonthescopeof themodification.A

    copyofthecontractorsproposalwiththecostsdeletedcanbeused.

    RegulationsrequireanIGEforanyprocurementof$25,000ormore.IftheContractingOfficerdeterminesitisnecessary,heorshemayrequireestimatesoflesseramounts.Inthecaseof

    contractmodifications,the$25,000triggerfigureisthesumoftheabsolutevaluesofdecreases

    andincreases.Forexample,amodificationresultingindecreasesof$10,000andincreasesof

    $16,000wouldsumtotheabsolutevalueof$26,000,andanIGEwouldberequired.Adjustments

    inmethodsorformatsfortheprimepurposeofescapingthisrequirementareprohibited.

    Forallnegotiatedprocurements,includingcontractmodifications,regulationsstatethataward

    mustnotbemadeunless:

    ThefinalIGEequalsorexceedsthenegotiatedprice,or

    Inthecaseofreductions,whichmustbeconsideredseparatelyfromincreases,the

    negotiatedcreditisequaltoorexceedsthefinalIGE,and

    The correct final IGE is included in thecontract file, supplemented bya complete

    statementjustifyingtheawardatacostdifferentfromtheestimate,andadequatefor

    subsequentreview.

    Theoverallobjectiveofacontractmodificationnegotiationistoreachanagreementwiththe

    contractorthatisinthebestinterestoftheGovernment.Thelowestpossiblepricedoesnot

    alwaysmeetthisobjectivenorwouldagenerousprice,ifthatpriceoffersmorepaymentthan

    necessarytoincludesufficientincentive.Thenegotiationteamstrivesforsomeintermediate

    point,whichisgenerallyregardedasthelowestreasonablepricetheamountatthebottomof

    thepricerangethatthenegotiatorconsiderstobefairandreasonable.

    projectestimatingrequirementsP120

    section2.242

    2T i t thi i th ti t t t l t ti ll l IGE b d

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    53/92

    To arrive at this price the negotiator must at least partially rely upon an IGE based on a

    detailedanalysisofthechangeinrequirementsandexistingjobconditions.Forthemostpart,

    theestimatemustbesimilarto,andtakeintoaccount,thosesameconditionsandelements

    occurringinthecontract,aseachappliestothechangeorderscope.Inlieuofbetterdata,the

    IGEfor bid evaluation may beused forassistance.The Independent GovernmentEstimator

    mustunderstandthescopeofthechangeandprepareanaccuratequantitytakeoffforeach

    directitemofchange,usinglabor,material,andequipmentcostsandsequentiallyapplying

    appropriateoverhead,profit,andbondcosts.Sincethisformal,approvedIGEisusedtoevaluate

    thereasonablenessof thecontractorsproposal, itmust bepreparedonacomparableand

    realisticbasisbyanestimatorfamiliarwiththemodificationandclaimprocesses.Theestimator

    mustreviewthecostspresentedinthecontractorsproposalforaccuracy,reasonableness,and

    allowableness.Ofthosecostsfoundallowable(seeFAR31.2),eachmustbefurtherreviewed

    forapplicabilitytotherequestedmodification.

    prospectusproduct/deliverableP120

    section2.243

    The Independent Government Estimator must:

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    54/92

    TheIndependentGovernmentEstimatormust:

    Review the change documents and become familiar with the requirements of the

    changedwork.

    Determine the status of construction and how the changed work will fit into the

    constructionschedule.

    Usemethods,capabilities,andlaborratesmatchingthoseofthecontractorperforming

    thework.

    Priceeachitematratesineffectatthetimethechangedworkwillbedone.

    Attempttoagreewiththecontractoronscopeandestimatestructurebeforepreparing

    theIGE.

    Unlessotherwiseagreed,useMasterFormatwithalevelofdetailusedinthecontract

    documents.

    UsethesamelevelofdetailtheGovernmentwoulduseifitwerecompetingforthe

    award.

    Computethenetcostorcreditbysubtractingthetotaloftheoriginalworkfromthe

    totaloftherevisedwork.

    Clearly and adequately describe and identify schedulerelated and impactrelated

    costsasaseparatepartofeachestimate.

    Preparetheestimateinatimelymanner.

    impactcostconsiderations

    Whenamodificationisdirected,settlementincludesnotonlythecostandtimechangeof

    theworkdirectlyaffectedbutalsothecostandtimeimpactontheunmodifiedwork.

    Generallythecontractorfirstpresentsimpactcostsaspartoftheproposalsclaimed

    impactcosts.TheIndependentGovernmentEstimatorlooksforoffsettingcoststoreduce

    theimpacttotheGovernment.Thecontractorisrequiredtosubmitdocumentationto

    support theclaimedcost,suchasnarrativecalculationsandplannedrescheduling.To

    determine theextent of theimpact, the approved costand resourceloadedschedule

    furnishedbythecontractormustbedevelopedtoreflectactualconstructionasaccurately

    aspossible.Themodificationworkissuperimposedon the original scheduleso asto

    44projectestimatingrequirementsP120

    section2.2

    2minimize delay under the given requirements GSA reviews and accepts or requests

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    55/92

    minimizedelay underthe given requirements.GSA reviews andaccepts, or requests

    modificationsto,therevisedschedule.

    The Independent Government Estimator classifies each impact cost claimed as either

    factualor judgmental. Factualcostsare fixed andestablished andcan be determined

    directlyfromrecords,suchasrentalorwagerateagreementsorpurchasedocuments.

    Oncetheitemhasbeendeterminedvalidasafactualimpact,theitemcostmaybedirectly

    calculated.Theamountofcostchangeiseitherstatedonthecertificationdocumentorcan

    bedeterminedfromthescheduledtimechangeoftheconstructionprogressplan.

    Examplesoffactualimpactcostsare:

    Escalationofmaterialprices. Escalationoflaborwagerates.

    Changeinequipmentrates.

    Increaseforextendingthestorageperiodformaterialsandequipment.

    Increaseforextendingthecontractforlaborandsubsistence.

    Increaseforalongerperiodofdirectonsiteoverheadpersonnel,materials,and

    utilities.

    Increaseforalongerperiodofoverheadandprojectofficeservices.

    TheIndependentGovernmentEstimatoridentifiesjudgmentalimpactcosts,whichinclude

    thosethataredependentonvariablefactorssuchasperformance,efficiency,ormethodology

    andcannotbestatedfactuallypriortoactualaccomplishment.Thecontractorsproposal

    mustprovideclearandcrediblesupportforalljudgmentalimpactcosts.

    Examplesofjudgmentalimpactcostsare:

    Changeofefficiencyresultingfromrescheduling. Lossoflaborefficiencyresultingfromlongerworkhours.

    Loss of efficiency caused by disruption of existing orderly processes and

    procedures.

    Lossofefficiencyduringreschedulingofmanpower.

    Inefficiencyincurredfromresubmittalofshopdrawings,samplematerials,etc.

    prospectusproduct/deliverableP120

    section2.245

    The Independent Government Estimator weighs any premium costs allowed in the base

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    56/92

    TheIndependentGovernmentEstimatorweighsanypremiumcostsallowedinthebase

    contractchangeproposalagainstanyadditionalimpactcostsrequested.Forexample,the

    MechanicalContractorsAssociationsproductivityratescanbehigherthanthoseusedin

    competitivelybidwork.Theestimatormustavoidincludingthecontractorsquestionable

    impactcostsintheinitialGovernmentestimateunlesseachhasbeendeemedjustifiable.

    Anyoffsetstoimpactcostsfromdeletedworkmayincreasethecontractorsefficiencyand

    productivity,resultinginacredittoGSA.

    estimatorssupportduringnegotiations

    AftertheIGEforthemodificationhasbeencompleted,approved,anddeliveredtothe

    ContractingOfficer, the Independent Government Estimator continues to support the

    negotiations, as directed by the negotiator. The estimator must become thoroughly

    familiarwithnegotiatingrequirementsandtechniquesbeforeparticipatingaspartof a

    negotiatingteam.HeorshemarksallestimatesFOROFFICIALUSEONLYtopreserve

    balanceduringnegotiations.Theoverallamountmustnotbedisclosedunderanycircum-

    stancespriortoaward.

    13valueengineeringchangeproposals(VECPs)

    VECPsmayrequirepreparationofanIGE.SinceaVECPwillbesupportedbycontractorpricing,theestimatorpreparestheIGEinamannersimilartothatdefinedpreviouslyinConstruction

    ModificationsandClaimsAnalysissection(inChapter2.2).

    14riskmanagement

    TheIndependentGovernmentEstimatorassistsinidentifyingandmeasuringrisks,andthen

    indeveloping,selecting,implementing,andmanagingoptionsforaddressingthoserisks.The

    severaltypesofrisktobeconsideredaspartofariskmanagementmethodologyinclude:

    Schedule

    Cost

    Technicalfeasibility

    Environmentalremediation

    Archaeological

    projectestimatingrequirementsP120

    section2.246

    2 Technical obsolescence

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    57/92

    Technicalobsolescence

    Dependenciesbetweenanewprojectandotherprojects

    Physicaleventsbeyonddirectcontrol Marketandeconomicevents

    GSAusestheConstructionIndustryInstitutes(CII)ProjectDevelopmentRatingIndex(PDRI)

    toidentifyweakareas,whichareineffectarisklist.

    15occupancyagreementsandtenantimprovementspricing

    CostelementsareorganizedinaccordancewithGSAspricingpolicy,whichrequiresaseparate

    tenantimprovementestimateforeachtenant.

    Theagencyhousingplanandthesupportingfloorplansmustbeusedtoorganizetheestimate

    detailby:

    Warmlitshell

    Tenantagencyfitout

    Securityupgrades

    InadditiontotheECCAtheestimatormust,foreachtenantagency,addtheGSArelatedcost

    elementsidentifiedintheSpacePlanningsectionoftheGSA Pricing Desk Guide, (Section

    3.2.10,page 19)andin thePricingImplementationfor Project Managers Guide,Chapter II

    ProjectDevelopmentPhase.

    prospectusproduct/deliverableP120

    section2.247

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    58/92

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    59/92

    3

    deliverymethodsand

    deliverables

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    60/92

    31 overview

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    61/92

    1 overview1 requirementsforestimates

    ThematrixofTable3indicatesthedeliverablestypicallyrequiredbydeliverymethodandby

    sizeofproject.

    matrixrows

    ThematrixrowsareorganizedbythefivedistinctstagesofanyprojectPlanning,Design,

    Construction Procurement, Construction, and Construction Closeout. Within these are

    discretephases,andwithineachphasethereareseveralactivities.Toperformtheactivities,

    severaltaskshavetobecompleted,allasshownonthematricesthatfollows.

    Planning Stage: Theplanningstagehasfourphases:

    1 Preliminaryprojectdevelopment

    2 Feasibilitystudy

    3 Programdevelopmentstudy(PDS)

    4 DesignbuildRFP

    5 Baselining

    Design Stage: TheDesignstagehasthreephases:

    1 Concept

    2 Designdevelopment

    3 Constructiondocuments

    Construction Procurement Stage: Thereisonlyonephaseandoneactivity,buttwotasks

    areidentified.

    Construction Stage: Thereisonlyonephasehere,butitstwomainactivitiesare:

    1 Constructionmodificationsandclaimsanalysis

    2 ValueEngineeringChangeProposal(VECP)

    Construction Closeout Stage: CloseoutistheonlyphaseandactivityintheConstruction

    CloseoutStage.

    deliverymethodsanddeliverables

    section3.151

    matrixcolumns

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    62/92

    Thematrixshowsfourdeliverymethods:

    1 Traditional(DesignBidBuild)

    2 ConstructionManagerasConstructor

    3 DesignBuildwithBridgingorConceptdocuments

    4 DesignBuildpureorperformancebased

    Thematrixfurtherorganizeseachdeliverymethodbyprojecttype:NewConstruction,and

    Repair&Alteration/Modernization.

    Projectsizes,definedbyconstructionvalue,subdivideeachprojecttype.Projectsizesare:

    1 Under$2million

    2 $210million

    3 $1025million

    4 $25millionandabove

    NewConstructiondoesnotusetheunder$2millionprojectsize.

    52projectestimatingrequirementsP120

    section3.1

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    63/92

    2 deliverable flowcharts by delivery

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    64/92

    2 deliverableflow chartsbydeliverytable3. cost estimatingforconstruction in federalbuildings

    tasking matrixtraditional CMc

    DB bridging/concepts

    DB pure/perform. based

    new r&a/mod new r&a/mod new r&a/mod new r&a/mod

    activity task

    $25M+

    $1025M

    $210M

    $25M+

    $1025M

    $210M

    Under2M

    $25M+

    $1025M

    $210M

    $25M+

    $1025M

    $210M

    Under2M

    $25M+

    $1025M

    $210M

    $25M+

    $1025M

    $210M

    Under2M

    $25M+

    $1025M

    $210M

    $25M+

    $1025M

    $210M

    Under2M

    preliminary project development

    BER WorkItem Cost Estimates

    Blast/Prog.Collapse study

    Uniformat or MasterformatCost Estimates

    SeismicstudyUniformat or Masterformat

    Cost Estimates

    NEPAUniformat or Masterformat

    Cost Estimates

    Master PlanUniformat or Masterformat

    Cost Estimates

    SpecialstudiesUniformat or Masterformat

    Cost Estimates

    AEFeeEstimate

    Independent GovernmentEstimate

    feasibility study

    Foreachdevelopmentsubmission

    GCCRG/BenchmarkToolsorProjectCost Estimating Tool

    ProjectCost Estimating Tool

    Risk Analysis

    Foreach availablepreliminaryplanning

    study

    Validate/Update AssociatedEstimate

    Foreach incorporatedpreliminaryplanning

    studyProjectCost Estimating Tool

    AEFeeEstimate

    Independent Government CostEstimate

    54projectestimating requirements P120

    section3.2

    tasking matritraditional CMc

    DB bridging/concepts

    DB pure/perform. based

    3

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    65/92

    programdevelopmentstudy(pds)

    taskingmatrix concepts perform. based

    new r&a/mod new r&a/mod new r&a/mod new r&a/mod

    activity task

    $25M+

    $1025M

    $210M

    $25M+

    $1025M

    $210M

    Under2M

    $25M+

    $1025M

    $210M

    $25M+

    $1025M

    $210M

    Under2M

    $25M+

    $1025M

    $210M

    $25M+

    $1025M

    $210M

    Under2M

    $25M+

    $1025M

    $210M

    $25M+

    $1025M

    $210M

    Under2M

    Feasibility StudyCritique

    Foreach development

    submission

    Foreach availablepreliminaryplanning

    study

    Foreach incorporatedpreliminaryplanning

    study

    Validate Feasibility StudyEstimate

    ProjectCost Estimating Tool

    GCCRGforBudget Analysis

    Market surveys(one submission only)

    Validate / Update AssociatedEstimate

    Validate / Update AssociatedEstimate

    design buildRFP

    Estimating SupportIndependent Government

    Cost Estimate

    concept design

    PreliminarySubmission

    VE workshop

    Final Submission

    Cost EstimatesperTable1foreach submission

    Uniformat or MasterformatCost Estimate

    Market Survey

    Review of AEEstimate

    Cost EstimatesperPQ250/251

    Cost EstimatesperTable1

    Uniformat or Masterformat CostEstimate

    IndependentEstimate

    SpaceType cost analysis

    Budget Analysis

    delivery methodsanddeliverables

    section3.255

    tasking matrixtraditional CMc

    DB bridging/concepts

    DB pure/perform. based

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    66/92

    Final Submission(continued)

    Life CycleCost Analysis(Per P100/Design Program)

    Risk Analysis

    OCAReview &Estimate

    design development

    PreValueEngineeringDDSubmission

    Cost EstimatesperTable1

    Review of AEEstimate

    Life CycleCost Analysis (PerP-100/Design Program)

    VE Workshop/Study Cost EstimatesperPQ250/251

    FinalDDSubmission

    Cost EstimatesperTable1

    Market Survey

    Cost Growth Report

    OCAReview &Estimate

    IndependentEstimateandreconciliationwith AEEstimate

    construction documents

    75% CDs

    Cost EstimatesperTable1

    Review of AEEstimate

    Market Survey

    CMcGuaranteedMaximumPrice

    90% CDs

    Cost EstimatesperTable1

    Market Survey

    IndependentEstimateandreconciliationwith AE

    Estimate

    Review of AEEstimate

    Cost Growth Report

    tasking matrixnew r&a/mod new r&a/mod new r&a/mod new r&a/mod

    activity task

    $25M+

    $1025M

    $210M

    $25M+

    $1025M

    $210M

    Under2M

    $25M+

    $1025M

    $210M

    $25M+

    $1025M

    $210M

    Under2M

    $25M+

    $1025M

    $210M

    $25M+

    $1025M

    $210M

    Under2M

    $25M+

    $1025M

    $210M

    $25M+

    $1025M

    $210M

    Under2M

    56projectestimating requirements P120

    section3.2

    3tasking matrix

    traditional CMcDB bridging/

    conceptsDB pure/

    perform. based

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    67/92

    OCAReview&Estimate

    Uniformat or MasterformatCost Estimates

    100% CDs

    Cost EstimatesperTable1

    Market Survey

    IndependentEstimateandreconciliationwith AE

    Estimate

    Review of AEEstimate

    CostGrowthReport

    construction procurement

    Construction AwardBid Analysis

    Database Informationpreparation

    Cost andPriceAnalysis

    construction

    Construction Mods &ClaimsAnalysis

    Masterformat Cost Estimates

    ValueEng. ChangeProperty (VECP)

    Cost Estimates

    LifeCyclecost analysis review(asrequired)

    construction closeout

    CloseoutDatabase Information

    including ChangeOrders

    taskingmatrixnew r&a/mod new r&a/mod new r&a/mod new r&a/mod

    activity task

    $25M+

    $1025M

    $210M

    $25M+

    $1025M

    $210M

    Under2M

    $25M+

    $1025M

    $210M

    $25M+

    $1025M

    $210M

    Under2M

    $25M+

    $1025M

    $210M

    $25M+

    $1025M

    $210M

    Under2M

    $25M+

    $1025M

    $210M

    $25M+

    $1025M

    $210M

    Under2M

    delivery methodsanddeliverables

    section3.257

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    68/92

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    69/92

    a

    appendices

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    70/92

    estimatingformats

    1 uniformatlevel15costelements

    a

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    71/92

    Level 1 Level 2 Level 3 Level 4 Level 5

    A1

    Substructure

    A11

    Foundations

    A111Standard

    Foundations

    WallFoundations ColumnFoundations&PileCaps PerimeterDrainage&Insulation

    A112Special

    Foundations

    PileFoundations GradeBeams Caissons Underpinning Dewatering RaftFoundations

    PressureInjectedFootings OtherSpecialFoundations

    A12

    BasementConstruc

    tion

    A121Basement

    Excavation

    ExcavationforBasements StructureBackfill&Compact Shoring

    A122Basement

    Walls

    BasementWallConstruction MoistureProtection BasementWallInsulation InteriorSkin

    A123 SlabonGrade

    StandardSlabonGrade StructuralSlabonGrade

    InclinedSlabonGrade TrenchesPits&Bases UnderSlabDrainage&Insulation

    A2

    Superstructure

    A21

    Superstructure

    A211

    FloorandColumn

    Construction

    SuspendedBasementFloorConstruction UpperFloorsConstruction BalconyFloorConstruction Ramps FloorRacewaySystems OtherFloorConstruction

    Roof

    Construction

    FlatRoofConstruction PitchedRoofConstruction

    Canopies OtherRoofConstruction

    A2

    Superstructure

    A21

    Superstructure

    A212Stair

    Construction

    RegularStairs CurvedStairs SpiralStairs ExteriorFireEscapes StairHandrailsandBalustrade

    A214Special

    SuperstructureConstruction

    61appendices

    appendixa

    a Level 1 Level 2 Level 3 Level 4 Level 5B1

    Exter

    B111

    ExteriorWallConstruction

    ExteriorWallConstruction Parapets ExteriorLouvers&Screens Sun Control Devices (Exterior)

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    72/92

    E

    B11

    ior

    Walls

    1 Construction SunControlDevices(Exterior) BalconyWalls&Handrails

    ExteriorSoffitsxterior

    B112

    SpecialWallElements

    Enclos

    Exter

    B121

    Windows Windows CurtainWalls Storefronts

    B1

    ure

    B12

    iorGlazing&

    Doors B12

    2Doors

    GlazedDoors&Entrances SolidExteriorDoors RevolvingDoors OverheadDoors OtherDoors&Frames

    B123 SpecialGlazing

    Ext.Enclos

    B13

    Roofing

    B131

    RoofCoverings&Insulation

    RoofFinishesTrafficCoatings&PavingMembranes

    RoofInsulation&Fill Flashings&Trim RoofEavesandSoffits GuttersandDownspouts

    ure B13

    2Skylightsand

    RoofOpenings

    GlazedRoofOpenings RoofHatches GravityRoofVentilators

    Partitio

    C11

    Partitions

    FixedPartitions DemountablePartitions RetractablePartitions SiteBuiltToiletPartitions SiteBuiltCompartments&Cubicles InteriorBalustrades&Screens InteriorWindows&Storefronts

    C1

    InteriorConst

    ruction

    C11

    ns,Doors&Specialties

    1

    InteriorDoors

    InteriorDoors InteriorDoorFrames InteriorDoorHardware InteriorWallOpeningElements InteriorDoorSidelights&Transoms InteriorHatches&AccessDoors DoorPainting&Decoration

    C113

    Specialties/Fittings

    FabricatedToiletPartitions FabricatedCompartments&Cubicles StorageShelvingandLockers OrnamentalMetalsandHandrails IdentifyingDevices ClosetSpecialties

    C12

    Access/

    Platform

    Floors

    C121

    AccessFloors

    C122

    PlatformFloors

    62projectestimatingrequirementsP120

    appendixa

    Inter

    In

    C131

    WallFinishes WallFinishestoInsideofExteriorWall WallFinishestoInteriorWalls ColumnFinishes

    Fl T i

    Level 1 Level 2 Level 3 Level 4 Level 5 a

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    73/92

    C1

    riorConstruction

    C13

    teriorFinishes

    C132

    FloorFinishes

    FloorToppings TrafficMembranes

    HardenersandSealers Flooring Carpeting Bases,Curbs&Trim

    C133

    CeilingFinishes CeilingFinishesAppliedtoStructure SuspendedCeilings OtherCeilings

    D1

    ConveyanceSystems

    D11

    ConveyanceSystems

    D111

    Elevators&Lifts

    PassengerElevators FreightElevators Lifts Escalators&MovingWalks

    Escalators MovingWalks

    D112

    Escalators,Moving

    Walks

    &Other

    OtherConveyingSystems

    Dumbwaiters PneumaticTubeSystems Hoists&Cranes Conveyors Chutes Turntables BaggageHandling&LoadingSystems TransportationSystem

    D2

    Mechanical

    D21

    Plumbing

    D211

    Plumbing

    Fixtures

    WaterClosets Lavatories Sinks Bathtubs WashFountains

    Showers DrinkingFountainsandCoolers Bidets&OtherPlumbingFixtures

    D212

    Distributionand

    DrainageSystems

    DomesticWater Distribution

    ColdWaterService HotWaterService DomesticWaterSupplyEquipment

    SanitaryWaste

    WastePiping VentPiping FloorDrains SanitaryWasteEquipment PipeInsulation

    RainWaterDrainage

    Pipe&Fittings RoofDrains RainwaterDrainageEquipment Insulation

    D213

    Other

    PlumbingSystems

    GasDistribution AcidWasteSystem Interceptors PoolPipingandEquipment DecorativeFountainPipingDevices OtherPipingSystem

    63appendices

    appendixa

    a Level 1 Level 2 Level 3 Level 4 Level 5 OilSupplySystem

    GasSupplySystem

    CoalSupplySystem

    C l S l S t

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    74/92

    EnergySupply CoalSupplySystem

    SteamSupplySystem HotWaterSupplySystem

    SolarEnergySystem

    WindEnergySystem

    D22 CentralPlant Boilers&Furnaces

    1 Equipment HeatGeneratingSystems

    BoilerRoomPiping&Specialties

    AuxiliaryEquipment

    Insulation

    M

    CoolingGeneratingSystems ChilledWaterSystem

    DirectExpansionSystem

    D2

    echanicala

    D22

    HVAC

    DistributionSystems

    AirDistributionSystems ExhaustVentilationSystems SteamDistributionSystem HotWaterDistribution ChilledWaterDistribution

    D222

    DistributionSystems

    ChangeoverDistributionSystem

    GlycolHeatingDistributionSystem

    Terminal&PackageUnits TerminalSelfContainedUnits PackageUnits

    SystemsTesting&Balancing

    PipingSystemTesting&Balancing AirSystemTesting&Balancing HVACCommissioning OtherSystemsTesting&Balancing

    SpecialCoolingSystems&Devices SpecialHumidityControl Dust&FumeCollectors

    SpecialHVACSystems&Equipment AirCurtains

    AirPurifiers PaintSprayBoothVentilation GeneralConstructionItems(HVAC)

    D22

    3

    Controls&

    Interfacew/Bldg.Automation

    HeatingGeneratingSystem Exhaust&VentilatingSystems TerminalDevices EnergyMonitoring&Control BuildingAutomationSystems OtherControlsandInstrumentation

    64projectestimatingrequirementsP120

    appendixa

    D31

    1

    SprinklerandStandpipe Systems

    FireProtectionSprinklerSystems SprinklerWaterSupply SprinklerPumpingEquipment DrySprinklerSystem

    Water Supply

    Level 1 Level 2 Level 3 Level 4 Level 5 a

  • 7/21/2019 P120-Project Estimating Requirements GSA 2007

    75/92

    D3

    FireProtection

    D3

    1

    F

    ireProtection/Alarm

    1 StandpipeSystems

    StandpipeandHoseSystems WaterSupply StandpipeEquipment

    FireHoseEquipment

    D31

    2

    FireAlarmSystems&Interfacew/Bldg.

    Automation

    D313

    SpecialtiesandotherSystems

    FireProtectionSpecialties FireExtinguishers FireExtinguisherCabinets

    OtherFireProtectionSystems

    CarbonDioxideSystem FoamGeneratingEquipment CleanExtinguishingAgentSystem DryChemicalSystems Hood&DuctFireProtection

    D4

    Electrical

    D41

    ElectricalService,

    Distribution&

    EmergencyPower

    D411

    HighTensionService&Dist.

    D412

    LowTensionService&Dist.

    D413

    EmergencyPowerSystems

    D414

    RenewableElectricGene