oer.unn.edu.ng · web viewtitle page. appraisal of construction management. practice in nigeria....
TRANSCRIPT
TITLE PAGE
APPRAISAL OF CONSTRUCTION MANAGEMENT
PRACTICE IN NIGERIA
BY
ATTAH, IMOH CHRISTOPHER
PG/M.ENG/12/61891
THESIS SUBMITTED TO THE DEPARTMENT OF CIVIL ENGINEERING,
UNIVERSITY OF NIGERIA, NSUKKA
IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE AWARD OF DEGREE OF MASTERS OF ENGINEERING (M.ENG)
THE DEPARTMENT OF CIVIL ENGINEERING
UNIVERSITY OF NIGERIA, NSUKKA
i
CERTIFICATION
We certify that this thesis on APPRAISAL OF CONSTRUCTION MANAGEMENT
PRACTICE IN NIGERIA is an original work done by ATTAH, IMOH CHRISTOPHER a
student with registration number PG/M.ENG/12/61891. We examine and found it acceptable for
the award of the degree of Masters of Engineering (M.ENG).
------------------------------------------------------- ------------------------------------
ENGR. PROF. O. O. UGWU DATE
PROJECT SUPERVISOR
------------------------------------------------------- ------------------------------------
ENGR. PROF. O. O. UGWU DATE
HEAD OF DEPARTMENT (HOD)
-------------------------------------------------------- ------------------------------------
DR. O. O. ONWUKA DATE
EXTERNAL EXAMINER
ii
DEDICATION
This work is dedicated to God Almighty for his enablement, for the achievement of excellence
and to all those who love the progress of mankind.
iii
ACKNOWLEDGEMENT
I thank the Lord God Almighty for the successful completion of this study. Indeed it is the Lords
doing and it is marvelous in our sight.
My profound gratitude goes to my supervisor Engr. Prof O. O. Ugwu for the effort invested in
mentoring me and guiding me through the research. I wish to thank my lecturers: Engr. Prof. J.
C. Agunwamba, Engr. Dr. M. E. Onyia, Engr. Dr. B. O. Mama and Engr. Dr. C. C. Nnaji the
postgraduate co-ordinator.
I deeply appreciate my mother Deac. Theresa Attah and my aunty Mrs Henreitta Offiong for
their encouragement and support. I am also very grateful to my siblings Comfort, Victoria and
Joy for all their moral encouragement.
I want to thank Mr. Charles Umoh and his family for all their support. In the same vein, I
appreciate the effort of Mr. Emmanuel Ekpemyong, Engr. & Engr. (Mrs.) Kufre Primus Okon
and Engr. Nkpa Ogarekpe, for the love, care, editing and helping correct my work.
My profound gratitude goes to my fiancée Deborah John and PINNICATT NIGERIA LTD
towards the successful completion of this project.
My roommates: Mr. Ben Nwachukwu, Mr. Johnmark Ocheje, Pst. Ernest Ochai, Engr. Edward,
Engr. Ibiang Ebri, you guys are wonderful.
iv
TABLE OF CONTENTS
Pages
Title Page……………………………………………………………………………………….....i
Certification……………………………………………………………………………………….ii
Dedication………………………………………………………………………………………...iii
Acknowledgement………………………………………………………………………………..iv
Table of Contents ………………………………………………………………………………....v
List of Tables …………………………………………………………………..……………….viii
List of Figures………………………………………………………………………………….....x
Abstract………………………………………………………………………………………………………………….xii
CHAPTER ONE
INTRODUCTION………………………………………………………………………………...1
1.0 Background……………………………………………………………………………………1
1.1 Statement of the problem……………………………………………………………………...3
1.2 Objectives of study……………………………………………..............................................3
1.3 Significance of the study………………………………………………………………………4
1.4 Scope of the study……………………………………………………………………………..4
1.5 Limitation of study…………………………………………………………………………….4
1.6 Hypothesis……………………………………………………………………………………..4
1.7 Thesis structure………………………………………………………………………………..5
CHAPTER TWO
LITERATURE REVIEW…………………………………………………………………………6
2.0 Review of related works………………………………………………………………………6
2.1 Construction management……………………...……………………………………………..7
2.2 Functions of management in construction…………………………………………………….8
v
2.3 Resources for Construction Industry………………………………………………………...11
2.4 The Roles of Construction Actors……………………………………………………………12
2.5 Factors that Influence Construction Management Practice…………………………………14
2.6 Quality Management during Design…………………………………………………………14
2.7 Quality Management during Construction…………………………………………………...14
2.8 Construction Management Techniques Used In Practice……………………………………15
2.9 Economic Policy…..…………………………………………………………………………18
2.10 Management Style………………………………………………………………………….19
2.11 Socio – Political considerations…………………………………………………………….19
2.12 Motivation of Staff………………………………………………………………………….20
CHAPTER THREE
RESEARCH METHODOLOGY………………………………………………………………...23
3.0 Methodology…………………………………………………………………………………23
3.1 Study Area…………………………………………………………………………………...23
3.2 Data Collection Instrument…………………………………………………………………..24
3.3 Administration of the Data Collection Instrument…………………………………………...24
3.4 Population and Sample………………………………………………………………………24
3.5 Data Collection………………………………………………………………………………26
3.6 Method of Analysis…………………………………………………………………………..27
CHAPTER FOUR
DATA PRESENTATION, ANALYSIS AND INTERPRETATION………………………...…30
4.0 Data Presentation…………………………………………………………………………….30
4.1 Analysis and Interpretation…………………………………………………………………..48
4.2 Test of Hypothesis (Computation of Kendall’s Coefficient of Concordance)………………56
vi
CHAPTER FIVE
CONCLUSION AND RECOMMENDATIONS………………………………………………..58
5.0 Conclusions………………………………………………………………………………......58
5.2 Recommendations……………………………………………………………...…………….59
REFERENCES...........................................................................................................................62
APPENDIX………………………………………………………………………………………66
vii
LIST OF TABLES
Pages
Table 3.1: Ordinal scale for data measurement...........................................................................26
Table 3.2: Distribution of questionnaires to the target groups…………………………………..27
Table 4.1: Relative Importance Index and Rank for Quality Management during Design……..30
Table 4.2: Relative Importance Index and Rank for Quality Management during Construction.31
Table 4.3: Relative Importance Index and Rank for Construction Management Techniques…..32
Table 4.4: Relative Importance Index and Rank for Economic Policy………………………....33
Table 4.5: Relative Importance Index and Rank for Management Style………………………..34
Table 4.6: Relative Importance Index and Rank for Socio – Political Consideration…………..35
Table 4.7: Relative Importance Index and Rank for Motivation of Staff…………………….....36
Table 4.8: Relative Importance Index and Rank for Obstacles in Construction Management.....37
Table 4.9: Relative Importance Index and Rank for benefits applying construction management
tools in practice…………………………………………………………………………………..38
Table 4.10: Usage of planning method………………………………………………………….39
Table 4.11: Frequency of meeting of project team……………………………………………...40
Table 4.12: Co-ordination frequency of current schedule with master schedule………………..40
Table 4.13: Frequency of co-ordination with sub-contractors and supplier schedule…………..41
Table 4.14: Usage of incentive system………………………………………………………….42
Table 4.15: Usage of software for planning and scheduling…………………………………….42
Table 4.16: Formal participation in the pre-project planning effort…………………………….43
Table 4.17: Presence of cost schedule associated with the estimated time schedule……………44
viii
Table 4.18: Applying the actual value and earned value concept in controlling cost…………...44
Table 4.19: Having a cost engineer responsible for cost control………………………………..45
Table 4.20: Applying software to plan, monitor and control cost………………………………45
Table 4.21: Implementation level of safety factors………………………………………...……46
Table 4.22: Meeting frequency for safety issues………………………………………………..47
Table 4.23: Frequency of pre-task planning for safety conducted by contractor foremen or other
site managers……………………………………………………………………………………..47
ix
LIST OF FIGURES
Pages
Figure 3.1: Map of Nigeria……………..……………………………………………………….24
Figure 3.2: Percentages of received questionnaires……………………………………...……...27
Figure 4.1: Response for Quality Management during design………………………………….30
Figure 4.2: Response for Quality Management during Construction…………………………...31
Figure 4.3: Response for Construction Management Tools…………………………………….32
Figure 4.4: Response for Economic Policy………………………………………………..……33
Figure 4.5: Response for Management Style……………………………………………………34
Figure 4.6: Response for Socio – Political Consideration………………………………………35
Figure 4.7: Response for Motivation of Workers……………………………………………….36
Figure 4.8: Response for Obstacles facing Construction Management…………………………37
Figure 4.9: Response for Applying Construction Management Tools………………………….38
Figure 4.10: Responses to Usage of Planning Method.................................................................39
Figure 4.11: Responses to Meeting of Project Team……………………………………………40
Figure 4.12: Response for Co-ordination of Current Schedule with Master Schedule................41
Figure 4.13: Responses for Sub-contractors & Supplier Schedule...............................................41
Figure 4.14: Responses for Usage of Incentive System...............................................................42
Figure 4.15: Responses for Usage of Software for Planning & Scheduling.................................43
Figure 4.16: Responses of Formal Participation in Pre-project Planning.....................................43
Figure 4.17: Responses for Presence of Cost schedule with Estimated Time Schedule..............44
x
Figure 4.18: Response of Applying Actual & Earned Value Concept in Controlling Cost.........45
Figure 4.19 Responses for Having a Cost Engineer Responsible for cost Control......................45
Figure 4.20 Responses for Applying Software to Plan, Monitor & Control Cost........................46
Figure 4.21 Responses for Implementation Level of Safety Factors............................................46
Figure 4.22 Responses of Meeting for Safety Issues....................................................................47
Figure 4.23 Responses of Pre-task Planning for Safety Conducted by Site Managers................48
xi
ABSTRACT
Construction industry has complexity in it nature because it contains large number of parties
such as clients, consultants and contractors. The factors that influence construction management
practice differ from country to country, due to prevailing conditions. The objective of this project
is to identify factors that influence construction management practice in Nigeria construction
industry and elicit perceptions/ranking of the severity using relative importance index of the
various factors. A comprehensive literature review was conducted to generate a set of factors
believed to influence construction management practice in Nigeria. A questionnaire survey was
conducted and fifty-seven (57) factors were identified, grouped into nine (9) categories,
evaluated and ranked from the construction actors perspectives. 108 questionnaires was produced
and distributed to the key construction actors as follows: 45 to contractors, 33 to consultants and
30 to clients. Out of these questionnaires distributed, 92 were received (85%) as follows:
40(88.9%) from contractors, 28(84.8%) from consultants and 24(80%) from clients as
respondents. They nine categories considered in this research work are as follows: quality
management during design, quality management during construction, construction management
techniques used in practice, economic policy, management style, socio-political consideration,
motivation of staff, obstacles facing construction management practice and benefits of applying
construction management tools in practice.
The enlarged features included those from both previous Nigerian studies and other related
international studies represented in the literature. The degree of agreement between parties
regarding the ranking of factors was determined according to Kendall's Coefficient of
Concordance and the survey findings indicate from three target groups (contractors, consultants
and clients) agree that the most important factors that influence management of construction
projects are as follows: conflicting design information, effective co-ordination of resources,
critical path method, materials availability, setting timeliness, civil strife of riots, sense of
belonging & identification with the project team, lack of construction management knowledge
and known work progress.
xii
CHAPTER ONE
INTRODUCTION
1.0 Background
The construction sector in Nigeria plays an important role in the development of our nation’s
economy. The construction industry is said to have contributed about half of the total stock of
fixed capital investment in the Nigeria economy (Olaloku, 1987). During the last decades, the
Nigerian construction sector has experienced some rapid changes and advancement in
construction practices as well as the management of the construction works.
Many definitions have been given to Construction Management by different authors due to the
fact that it has different meaning from different perspective and orientation in the engineering
profession.
The term construction is no longer limited only to the physical activities involving men,
materials and machinery but covers the entire gamut of activities from conception to realization
of a construction project (Gahlot, 2002). While management is a social process by which a co-
operative group (superiors) directs the action of others (subordinates) towards accomplishing a
common goal (Drucker, 1999).
Construction projects in Nigeria are worth Billions of Naira, it is of great importance that
construction management practice is given great attention, including the best practice methods of
construction and it challenges. Moreover, construction management makes adequate provision of
necessary leadership and motivates employees to complete their tasks within a particular time
frame.
Serious concerns has been expressed about construction projects which have not been delivered
in various parts of the country after huge financial mobilizations has been made. The practice of
construction management requires appropriate skills and techniques that go beyond technical
expertise only. It encompasses good and sound management skills to manage resources within
the budget, monitor the progress of work, prepare job schedule and unpredicted outcomes, while
at the same time dealing with people and organizational issues (Abbasi & Al-Mharmah, 2000).
The application of construction management practice is an efficient approach which would aid in
xiii
improving management capabilities and enable the construction sector to efficiently deliver
projects and attain developmental objectives (Arnaboldi, 2004).
The need for professionalism in the practice of construction management assumes special
significance in order to ensure that the huge resources invested in the construction industry are
deployed efficiently for the benefits of Nigerians (Gahlot, 2002). The application of modern
construction management method in practice has a great effect in the construction sector. In
Nigeria, the practice of construction management has not been well defined; this resulted in
failure by contractors in performing their duties concerning the budget, specifications and
deadlines of project awarded. However, when practiced efficiently it would result in tangible
benefits in all aspects of planning, scheduling, monitoring the time, cost and specification of the
project.
In the practice of construction management, experience, quality of the materials used in the
project will be of great importance amongst others. According to the International Organization
for Standardization (ISO 8402, 1994), Quality can be defined as the totality of characteristics of
an entity that bear on its inability to satisfy stated or implied needs (Project Management
Institute, 2000). The special conditions affecting the project are reflected during the planning and
organizing stage of the construction to ensure that quality is fully built in even before the actual
construction takes off (Idike, 2004).
In construction management, the level of competency of a project manager may directly or
indirectly affect the project. The information flow process determines the nature, quality and
timeliness of project execution. A weak link in the process, such as lack of project management
competence could adversely affect timely execution / timely completion of projects (Dainty et
al., 2003). According to Cookie - Davies (2001), project management is a tool for project
success; it is people who deliver projects and not processes and systems. Effective project
management is a derivative of competency and authority levels.
The project will investigate how various factors influence construction management practice in
Nigeria both positively and negatively, construction management tools, their challenges and
proffer solutions to the challenges.
xiv
1.1 Statement of the Problem
The construction sector is the major contributor of GDP in Nigeria and in the practice of
construction management there are some tools to be used to achieve the best results in project
delivery. Also there are some challenges faced in the process which is of great detriment to the
nation’s economy. In management of construction projects, there are factors that have great
influence in management of construction projects such as quality management during design &
construction, management techniques, economic policy, management style, socio-political
consideration, motivation of staff and some practices concerning construction management
practices such as time management, time management, safety management etc. Therefore, this
research will appraise the factors affecting the management of construction projects in Nigeria in
order to assist clients, consultants and contractors to overcome management problem and to
improve performance of their construction projects.
1.2 Objectives of Study
The main objective of the study is to appraise construction management practices in Nigeria.
The objectives of the study are as follows:
i) To investigate the level of construction management practice in Nigeria.
ii) To study and evaluate the factors that influence’s construction management practice
in Nigeria.
iii) To identify the factors that affect construction management practice and to examine
their relative importance.
iv) To evaluate the factors affecting construction management practice using enlarged
indicators that could be related to various dimensions such as quality management
during design & construction, management techniques, economic policy,
management style, socio-political consideration, motivation of staff etc and hence the
overall project sustainability.
xv
1.3 Significance of Study
The Nigerian construction sector is facing some challenges in which a greater percentage of the
problems are management oriented. It is therefore important to plan and ensure due process in
the management of construction projects so to achieve the best practice and quality delivery of
the products.
Also, this research work will enable the entire construction actors (i.e clients, contractors and
consultants) to be able to appreciate the importance of best practice of construction management
in Nigeria right from the design stage to the commissioning stage.
1.4 Scope of Study
i) The scope of this research is limited to construction management activities in Nigeria.
ii) The research is targeted to know how construction management is practiced and the
management tools used in practice.
iii) The result will be analyzed using basic statistical method.
1.5 Limitation of study
A number of factors militated against this research work. These include: the attitude of
respondents who were reluctant to provide answers to the questions asked in the questionnaire,
the security challenges in some parts of the country and a study of this magnitude requires a
much longer time compared with the normal academic load.
1.6 Hypothesis:
In order to know whether there is disagreement or agreement between the target groups
(contractors, consultants and clients) on the ranking factors, a test of hypothesis was used.
Null Hypothesis: H0: There is a disagreement in ranking among the three groups.
Alternate Hypothesis: H1: There is no disagreement in the ranking among the three groups.
xvi
1.7 Thesis Structure:
The research consists of five main chapters as follows:
Chapter one: Introduction: This chapter shows the main objectives of work, statement of problem
etc.
Chapter two: Literature review: This chapter gives a historical review from previous studies
concerning construction management practice.
Chapter Three: Methodology: This chapter discusses the methodology used in this research in
order to achieve the required objectives.
Chapter Four: Data Analysis: This chapter discusses as well as analysis, description and
discussion of research results.
Chapter Five: Conclusions and Recommendations.
Appendix
xvii
CHAPTER TWO
LITERATURE REVIEW
2.0 Review of Related Work
In Nigeria, like most developing countries the construction industry plays a dominant role in the
economic activities of the country. According to Olowo – Okere (1988), the construction
industry accounts for about 60 percent of the Nation’s capital investment and 30 percent of the
Gross Domestic Product (GDP).
The construction industry has continuously occupied an important position in the Nigerian
economy. In a study by Olaloku (1987) it was observed that: the relative large investment
commitment to construction makes the industry an important source of demand generation and
that this multiplier effect constitutes another contribution it makes to the economy.
Studies have confirmed that the application of modern project management tools has a great
effect in the construction sector. Arnaboldi et al (2004) observed that applications of project
management strategy in Italy were as result of pressure on government to abandon bureaucratic
organization in favour of leaner structures.
Similarly, Abbasi & Al-Mharmah (2000) explored the management tools and techniques used by
the public sector in Jordan by surveying 50 individual public firms. The study found out that the
use of management tools and techniques among the public sector companies was very low.
In Nigeria, the implementation of modern project management tools, methods and techniques has
not been well established. This results in failure in public projects and the contractors not able to
deliver the project within the budget. Studies have recognized social and political systems,
cultural blocks and lack of financial support as barriers to successful project planning and
execution in Nigeria (Idoro & Patunola-Ajayi, 2009).
There has been a profound change in the construction sector and practice of management by
organizations over the past years. The customer focused marketplace and fierce competitive
service positioning have demanded attention to practice improvement and value addition in
delivery.
xviii
The application of project management practice in Nigeria has been identified as an efficient
approach which would help in upgrading management capabilities and enable the construction
sector to efficiently complete projects and attain developmental objectives (Arnaboldi et al,
2004).
In order to ensure that quality is paramount and customers are therefore satisfied, personnel must
be carefully placed and managed with effective management tools.
Government and organizations usually embark on different projects with the aim of creating new
service or improving the functional efficiency of the existing ones. All these projects require
appropriate skills and techniques that go beyond technical expertise only but combines good and
sound skills to manage resources and unpredicted outcomes whilst at the same time dealing with
people and organizational issues (Abbasi & Al-Mharmah, 2000).
Nitithamyong (2004) remarked that information technology is now routinely used in the
construction industry as a tool to reduce some of the problems generated by fragmentation. The
use of information technology improves collaboration and co-ordination between the
stakeholders participating in the construction project, leading to better communication and good
practices. Its benefits include speedy progress of work, quality work, better financial control,
communications, simpler and faster access to common data as well as decrease in documentation
errors.
2.1 Construction Management
According to Gahlot (2002) objectives include the following:
i) It ensures completing the work within estimated budget and specified time.
ii) Creating an organization that works as a team.
iii) Construction management motivates people to give of their best within their capacities.
iv) Evolving a reputation of high quality workmanship.
v) It provides safe and satisfactory working conditions for all personnel and workers.
xix
vi) Also, construction management ensures taking sound decisions at the lowest practical
management level through delegation of authority.
2.2 Functions of Management in Construction
Also according to Gahlot (2002) the following are functions of management in construction:
planning, organizing, staffing, directing, controlling and co-ordinating.
2.2.1 Planning:
Planning involves formulation of a number of alternative realistic work plans for achieving
specified objectives and finally selecting a plan which is best suited from the stand-point of
available resources and constraints imposed upon the project. It is also the process of
establishing objectives and courses of action prior to taking action (Dessler, 2004). Planning is
that aspect of management that gives guidance and direction. There are two planning
considerations: plan the task carefully and manage the plan to ensure that all tasks are completed
on time.
2.2.1.1 Planning steps:
According to Smit and Cronje (2002), planning involves a lot of steps before arriving at the test
alternative plan. These include the following:
i) Identify opportunity and threats.
ii) Formulate objectives.
iii) Make assumptions & draw up plans of action accordingly.
iv) Identify alternative plans of action.
v) Analyze and consider alternative plans of action.
vi) Choose a final plan.
vii)Draw up a budget.
vii) Implement the plan.
xx
2.2.2 Organizing:
Organizing is concerned with division of the total construction work into manageable sections
and systematically arranging various operations by delegating specific tasks to individuals. Also,
it is the process of creating a structure for the business that will enable it people to work
effectively towards it vision, mission and goals. The process involves determining how, where,
when, by who and with what resources these tasks must be carried out to achieve the objectives
of the organization. The following steps are vital in organizing: finding the necessary
information, identifying & analyzing activities, grouping related tasks together and dividing the
workload according to resources.
2.2.3 Staffing:
Organizing involves the division of construction work into sections while staffing is the
provision of people to fill the positions so created. Recruiting the right people, arranging staff
training courses and carrying out proper staff assessment are all part of the staffing and human
resource management functions.
2.2.4 Directing or Leadership:
It’s concerned with training the sub-ordinates to carryout assigned tasks, supervising their work
and guiding their efforts. The essence of directing lies in the ability to motivate people
individually and as groups to utilize their creative efforts in achieving specified objectives.
Zigarmi et al. (2005) defined leadership as the act of arousing, engaging and satisfying the
motives of followers in the environment of conflict competition or change that result in followers
taking a course of action towards a mutually shared vision. Leadership indicates the relationship
between one person, the leader and the other members of the working group. This relationship
must be such that the members of the working group will work together voluntarily to achieve
the objectives of the group.
2.2.4.1 Types of leadership power:
xxi
Power is not gained only through the possession of a rank or job title it should be earned by the
leader. Pedler (2004) define power as the ability to do or to act, or to get work done, to make
things happen. There are many different kinds of power that a manager can have. Pedler (2004)
describe the following sources of power:
i) Legitimate power: This refers to the authority granted to a particular position. This gives
the person the right to insist on the execution of certain duties by staff and also to dismiss
them if they fail to comply.
ii) Reward power: This is power to give or withhold rewards in terms of salary, bonuses,
recognition or interesting assignments to individuals / staff.
iii) Coercive power: The type of power that enforces compliance through fear, whether
psychological, emotional or physical.
iv) Referent power: This is personal power based on identification or charisma. Employees
obey a leader simply because they like, respect or identify with him / her.
v) Expert power: It’s a type of power derived by the reason of the expertise or speciality in
skills, knowledge or professional ability.
2.2.5 Controlling:
Controlling is necessary for ensuring effective and efficient working. It involves constant review
of the work plan to check on actual achievements and to discover and rectify deviations through
appropriate corrective measures.
The essential steps in management control are: measurement of actual performance in terms of
progress, quality & cost incurred, comparison of actual and planned performance.
2.2.6 Co-Ordinating:
Since authority converges to the top of the organizational pyramid, it is necessary to bring
together and co-ordinate the work of various sections. This requires an efficient system of
communication so that each section is aware of its role and the assistance to be expected from
others. Regular meetings of sectional heads with the top management are fundamental to proper
co-ordination so that plans, problems and remedies are discussed for determining the best
xxii
solution. The functions to co-ordinate are those of: the general management, finance, operations,
purchasing, human resources, administrative and public relations function.
2.3 RESOURCES FOR CONSTRUCTION INDUSTRY
The main resources for the construction industry Gahlot (2002) are as follows:
2.3.1 Materials:
Materials such as cement, aggregates, steel, blocks, timber, water supply, electrical fittings,
petrol, diesel, lubricants etc are required for construction works.
2.3.2 Manpower:
Manpower in the form of technical and managerial personnel and workforce in various trades is
essential to carry out project activities. Technical and managerial personnel are essential for
efficient use of human resources and to achieve project completion within the estimated time and
budget.
The technical personnel include engineers, architects, quantity surveyors, supervisors,
technicians etc. The workforce consists of skilled and unskilled workers.
2.3.3 Machinery and Power:
For any construction work, various plants and tools are required. Depending on the type and
nature of construction job, machinery required at site include batching plant, mixers, trucks,
excavators, dumpers, cranes, pumps, generators, workshop equipment etc. For efficient
construction activity these plants need to be properly maintained. Power is an essential resource
required for lighting, running the plants, equipments and for other facilities.
2.3.4 Funds:
Adequate fund should be available for smooth implementation of the project. Financial planning
is essential for smooth cash inflow and outflow to avoid delays in project activities. Fund form
an important resource. All other resources are dependent on the availability of funds. Financial
resources should therefore be planned and managed with special care.
xxiii
2.3.5 Space:
For any construction activity to proceed efficiently, it is essential to plan the available space at
site for: storing materials, providing yards for bar benders, carpenters, installation of equipments
and plants, repair workshops, casting yard, site office, labour camps etc.
2.4 THE ROLES OF CONSTRUCTION ACTORS
There are diverse interests in the construction industry. The principal interest or actors in the
construction industry are: Client, Consultant and Contractor.
2.4.1 The Client
Boyd and Chinyio (2006) quotes Aktin and Flanagan (1995) who stated that “a client is someone
who freely chooses to avail themselves of a service, that a client is the initiator of a project and
those that contract with other parties for the supply of construction goods or services”.
The client also represents other interests, which include the owner if different, the end-user and
other identified persons, group or organization that may influence and are affected by the
acquisition, use, operation and demolition of the proposed project. Examples include:
institutions, environmental pressure groups and neighborhood. The Client expresses a desire to
have an infrastructure constructed for him example bridge, building, road etc. Also, he is the
single most important member of the construction team. He is the initiator and financier of all the
projects. Omole (1986) noted that the major contribution the client can make to the successful
operations of the construction industry lies in his skill in specifying his needs prior to the
preparation of the design. It is also important for the client to set cost limits of the project at the
briefing .He should also ensure that adequate financial provisions are made prior to the
commencement of any project.
2.4.2 The Consultant
Slack and Giles (1981) maintained that experienced consulting engineers had become very
illustrious in engineering history by virtue of their role as co-ordinators of all specialist design
xxiv
elements making up the project. Good workmanship and right quality of materials are usually
checked by some testing procedures and it is the duty of the consultant to ensure compliance by
the contractor. He assesses or confirms the measurement of the job for purposes of raising
interim payment certificates. Any negligence in this measurement could lead to over payment to
the contractor. Cost considerations are among the most important and basic considerations that
Consultants must deal with. It is essential to see that projects are contained within the client’s
budget and cost forecasts.
2.4.3 The Contractor
Omole (1986) further reveals that the major task of Contractors is to assemble and allocate the
resources of labour, equipment and materials to the project in order to achieve completion at
maximum efficiency in terms of time, quality and cost.
Also, he is the person (company) that implements the construction process and concretizes the
dream of the client. As soon as a contract is signed, one of the critical assignments is the
appointment of the Site Agent by the contractor. The agent sets up the site office and prepares an
organogram, indicating the key persons whose activities are relevant to project implementation.
This equally defines the channels of communication and programme of work, which the
consultant engineer must be abreast with. Snowdon (1979) enumerated the salient qualities of
good site agent as follows:
i) Having well developed skills of leadership.
ii) Having a logical, orderly and systematic approach to his work.
iii) Ability to understand and evaluate several aspects of the problems which undoubtedly
will come his way.
iv) Having a good knowledge of the principles of management and organization as well as
flexibility to new ideas.
v) Having sufficient experience relating to broad-based technology so as to appreciate the
contributions of others and detect possible omissions or faults.
vi) Ability to communicate.
xxv
2.5 FACTORS THAT INFLUENCE CONSTRUCTION MANAGEMENT PRACTICE
Based on the literature, several factors have been identified that have great influence in
construction management practice. The influence can be positive or negative. These could be
grouped into the following: Quality management during design, Quality management during
construction, Management techniques, Economic policy, Management style, Socio – political
considerations, Motivation of staff. Also, obstacles facing construction management practice,
benefits of applying construction management tools and Management practices (time, cost and
safety management practices)
2.6 QUALITY MANAGEMENT DURING DESIGN
The design engineers play important roles in the construction industry because their services are
engaged from the conception to it completion stage. Also, the functions of the designers are
important because any decision made at the inception of the project will affect the entire project.
Defective designs adversely impact on the project and the participants are responsible for many
construction failures (Andi and Minato, 2003). Failure at the conceptual planning and design
stages may lead to successive problems in significant stages of the project. Design inefficiencies
could lead to redesign and poor quality of construction materials.
Oyedele and Tham (2006) provides a listing of client’s ranking of designers performance criteria
among which were those relating to quality of design co-ordination, smooth flow of work,
conflicting design information, timeliness of issuing revised drawings, missing information etc.
2.7 QUALITY MANAGEMENT DURING CONSTRUCTION
Quality management includes the process required to ensure that the project will satisfy the
needs for which it was undertaken (Project Management Institute, 2000).
Quality management during construction is the steps to be taken to ensure that products are in
accordance with quality standards and measure the competency of consultants and contractors.
xxvi
Supervision during construction project is critical to ensure that quality products are used during
the construction. On the part of the consultant, the assessment of the following will determine the
speed of the construction and ensure quality of the products: timely inspection procedure,
adequate quality management inspection resources, quality management information processing
requirements and clean working environment requirements. While on the part of the contractor,
the effectiveness of construction management will affect the speed of construction. The factors to
be considered here are: analysis of construction methods, analysis of resources movement to and
within the site, effective co-ordination of resources, analysis of work sequencing to achieve and
maintain workflow, monitoring and updating of plans to reflect work status.
Idike and Agunwamba (2011) noted that Quality management is aimed at achieving the
following:
i) Ensuring that only competent and well trained personnel are used in the project.
ii) Certifying that product of the project meets all necessary specifications, standards,
regulations and proffer corrective measures when there is need.
iii) Ensuring that the project is delivered within the budget constraints.
iv) Certifying that the processes used in the construction project are in accordance with
the specification.
v) Encouraging the use of high quality materials, tools and equipments in the
construction project.
vi) Boosting the reputation of the company, as when a high quality project is delivered, it
increases customer satisfaction and reputation of the company.
2.8 CONSTRUCTION MANAGEMENT TECHNIQUES
In the process of managing construction projects, different tools and techniques are used so as to
help construction parties complete the projects on time. Construction management techniques
indicate the direction of the project at each time and reveal progress. They are utilized in the
construction industry for the planning and control of materials, labour, and machinery/equipment
for project delivery & sustainability. Some of these tools & techniques are discussed below:
xxvii
2.8.1 Work Breakdown Structure (WBS):
It is the act of breaking down the projects into manageable individual components in a
hierarchical structure. Such a structure defines tasks that can be completed independently of
other tasks, facilitating resource allocation, assignment of responsibilities and measurement and
control of project. Wysocki (2009) also observed that it is a veritable tool for defining work
packages and developing and tracking the cost and schedule for the project. WBS provides a
common framework for the natural development of the overall planning and control of a project
and is the basis for dividing work into definable increments from which the Statement of Work
can be developed and technical, schedule cost, and labour hour reporting can be established.
2.8.2 Gantt Chart:
According to Patrick (2004), the chart shows a list of activities and a bar chart indicates the start
and the end dates of each activity. It has both horizontal and vertical divisions. The horizontal
scale is divided into days, weeks or months and the vertical scale shows project work elements
such as: tasks, activities and work packages. It is a useful tool for planning and scheduling
projects. It was developed by Henry Gantt in 1915 purposely for monitoring projects progression
and tracking. Henry Gantt who the Gnatt chart is named, worked for the department of defense
during the First World War. A good Gnatt Chart shows the activities and events with time matrix
that permit comparisons and relationships to be worked out and readily inspected. Gantt charts
have become a common technique for representing the phases and activities of project Work
Breakdown Structure (WBS) so they can be understood by a wide audience all over the world
(Wysocki, 2009). The Gnatt chart is very useful in construction projects because it’s constituent
activities can easily be broken down into manageable components but it does not show directly
show dependent relationships between given tasks.
2.8.3 Prince 2:
Prince 2 which connotes Project in Controlled Environment 2 is a process based method for
effective project management. It is a de facto standard used extensively by the UK government
and is widely recognized in the private and public sector both in the UK and internationally. Its
features include focus on business justification, division of project into manageable and
controllable stages, flexible in application at a level appropriate to the project management team.
xxviii
Prince 2 basically describes product based planning, change control technique and quality review
technique.
2.8.4 Critical Path Method (CPM):
It’s also a project network analysis technique used to determine which sequence of activities
(path) has the least amount of scheduling flexibility and therefore will most likely determine
when the project can be completed. According to Ndiomu (1994), for CPM to be useful, project
activities by their nature should be specific having points/times and definite terminal
points/times. The CPM involves systematic planning, scheduling and controlling of construction
projects. The activities must be such that they are identified in an orderly sequence, all
connecting and leading to the completion of the project. It underscores certain operations which
are considered necessary to complete the entire project which are conscientiously identified and
shown in a graph called network. The network indicates the order in which the operations can be
undertaken comprehensively or the activities that must follow each other. Experts recommend
that the effective use of critical path method has the capacity to reduce costs.
2.8.5 Programme Evaluation and Review Technique (PERT):
It’s an event-and-probability based network analysis system generally used in projects where
activities and their durations are difficult to define. PERT is often used in large programme
where the project involves numerous organizations at widely different locations. To address the
deterministic dimension, analysts employ the PERT which is stochastic. The PERT is very close
to the CPM but it differs in the procedure for determining activities duration.
2.8.6 Project Sensitivity Analysis
Project sensitivity analysis determines which variables have the most potential to affect project.
Variables include, task duration, success rate and costs, risks, lags between predecessors and
successors, project duration, total project cost and so on. It is also useful in decision-making
under uncertainty and risk.
xxix
2.8.7 Cost Benefit Analysis (CBA)
It’s one of the most widely accepted and applied methods for project appraisal for large scale
infrastructure in the public and private sector. CBA is a prescriptive method that provides
guidance on the criteria to take account in decision making, ensuring that the net aggregate
benefits to society outweigh net aggregate costs (Patel, 2008).
2.8.8 Graphical Evaluation and Review Technique (GERT):
It’s a network analysis technique used in construction management that allows probabilistic
treatment of both network logic and activity duration estimates. It is a useful management tool
for planning, co-ordinating, and controlling complex projects (Westland, 2003). The key
objective of GERT is to evaluate on the basis of the network logic and estimated duration of the
activity and derive inference about some activities that may not be performed. GERT can be used
with a complimentary network analysis evaluation techniques used in project management such
as CPM and PERT.
2.8.9 Line of Balance:
This is a planning tool that is best suited for repetitive works. It’s used for planning house
building, to a lesser extent for jetty work and in conjunction with networks for road construction
project. The basis of the technique is an identification of the required resources for each
stage or operation so that it does not interfere with the next and the process is continued until
operations are completed.
2.9 ECONOMIC POLICY:
Chan and Scott (2004) is of the opinion that unfavorable economic environment adversely
affects the success of a project. There are various government policies such as transportation,
education, health, planning and economic policy. Economic policy determines the amount of
money in circulation and thus the level of construction activity in a country at a given time. In
the construction sector, the economic policy that affects the construction activities are the
policies on interest rates and inflation. According to Sloaman (2008), the interest rate is an
important determinant of business activities. If the interest rate rises, it will be more expensive
for business to borrow and it will lead to a curtailing of investment. Furthermore high interest
xxx
rates render borrowing by the general public expensive. The consequence of this phenomenon is
that the purchasing power of clients in construction sector is reduced.
2.10 MANAGEMENT STYLE:
Management style deals with the personal attributes possessed by the manager in managing an
organization. Machines and systems are operated by human beings. Humans tend to require
coercion to work. This is evidenced by the low productivity of some labourers. Supervision is
required to push workers to meet scheduled targets. Managers operate within an organization and
manage the functions of an organization. Griffith and Watson (2004) identify three management
styles. These are exemplified by the following types of leaders:
i) Autocratic leaders: They give orders which the insist shall be obeyed; determine policies
for the group without consulting it; give no detailed information about future plans but
simply tell the group what immediate step it must take and give personal praise or
criticism to each member on their own initiative.
ii) Democratic leaders: They give orders only after consulting the group; see to it that
policies are worked out with the acceptance of the group, which is critical for effective
implementation; never ask people to do things without sketching out the long term plans
on which the are to work and make it clear that praise or blame is a matter for the group.
iii) Laissez-faire leaders: They do not lead but leave the group entirely to itself and do not
participate.
Griffith and Watson (2004) further divided autocratic and democratic leaders into the following:
i) Autocratic leader: Strict, benevolent and incompetent autocrat.
ii) Democratic leader: Genuine and pseudo-democrat.
2.11 SOCIO-POLITICAL CONSIDERATIONS
xxxi
The social environment concerns needs for projects or individuals while the political
environment is concerned with government policy and the effect of political decisions on
projects. Chan and Scott (2004) confirm the fact that the political environment
affects the management of construction project. Fortune and White (2005) in their review of sets
of critical success factors in sixty-three publications listed political stability as one of the twenty-
seven socio-political critical success factors.
2.12 MOTIVATION OF STAFF:
Huczynski and Buchanan (2007) defines motivation as employees job satisfaction or the degree
to which employees are satisfied with their jobs, which leads to higher quality, better growth and
improved profitability.
Andawei (2002) reports on a study finding that motivational factors significantly influence the
performance of workers. The quality of human performance depends on largely upon motivation.
Several techniques can be used to positively influence workers behavior. Two of these
techniques are behavioral and economic approach. The behavioral approach, views motivation
from workers psychological requirement and the second views it from economic approach and
places emphasis on monetary rewards (Andawei, 2002)
There are many competing theories which attempt to explain the nature of motivation. These
theories help to explain the behavior of certain people at certain times. Any theory which aids in
understanding of how best to motivate people at work is useful. The existence of many theories
may be an indication that there are many motives which influence workers behavior in
construction. The most well-know theories which explain employee’s motivation are as follows:
Maslow’s hierarchy of needs theory, Theory X and theory Y, Herzberg’s theory, ERG theory,
McClenllan’s theory of need, Cognitive theory, Goal-setting theory, Reinforcement theory,
Equity theory and Expectancy theory.
2.12.1 Maslow’s hierarchy of needs theory:
According to Robbins (2001), Maslow hypothesised that within every human being there exists a
hierarchy of five needs. These needs are:
i) Physiological: Hunger; thirst; shelter; sexual and other bodily needs.
xxxii
ii) Safety: Security and protection from physical and emotional harm.
iii) Social: Affection, sense of belonging, acceptance and friendship.
iv) Esteem: Internal esteem factors such as self-respect, autonomy and achievement, and
external esteem factors such as status, recognition and attention.
v) Self-actualisation: The drive to become what one is capable of becoming.
As each of these needs becomes substantially satisfied, the employee’s concentration on his / her
job becomes high and positively influence’s success of the project.
2.12.2 Theory X and Theory Y:
Theory X and Theory Y is another important motivational theory managers should familiarise
themselves with. Douglas McGregor proposed two distinct views of human beings: one basically
negative (Theory X) and the other basically positive (Theory Y). There are four assumptions
made of employee’s attitude under the Theory X cited by Robbins (2001). They include the
following:
i) Employees inherently dislike work and whenever possible, will attempt to avoid it.
ii) Since employees dislike work, they must be coerced, controlled, or threatened with
punishment to achieve goals.
iii) Employees will avoid responsibilities and seek formal direction whenever possible.
iv) Most workers place security above all other factors associated with work and will display
little ambition.
2.12.3 Herzberg’s Theory:
Herzberg’s theory is one of the important theories applicable in the construction industry.
Frederick Herzberg proposed the two-factor theory, also called the Motivation Hygiene theory.
This theory relates to views on job satisfaction and dissatisfaction. Conditions surrounding the
job, such as quality of the job, supervision, pay, company policies, physical working conditions,
relations with others and job security were characterized by Herzberg as hygiene factors.
xxxiii
2.12.4 ERG Theory
ERG theory is a theory proposed by Clay Alderfer. Hellriegel (2001) stated that Alderfer
maintains there are three groups of core need namely existence, relatedness and growth (ERG).
The existence group is concerned with the provision of the basic materials and existence
requirements. These are similar to the psychological and safety needs posited by Maslow.
2.12.5 McClelland’s theory:
McClelland’s theory was developed by David McClelland and his associates. Huczynski and
Buchanan (2007) states that the theory focuses on three needs: achievement, power and
affiliation.
xxxiv
CHAPTER THREE
RESEARCH METHODOLOGY
3.0 Methodology:
This research work discusses the factors that influence construction management practice.
From existing literature in the construction industry in Nigeria and elsewhere, it was possible to
identify fifty – seven (57) major factors that influence’s construction management practice in
Nigeria. A questionnaire survey was used to elicit the attitude of clients, consultants and
contractors towards construction management practice, the factors were ranked in various
categories. On the basis of the factors by various categories, it is important to identify the most
important factors that influence’s construction management practice in Nigeria.
3.1 Study Area:
The results used in this study were obtained from six (6) states in Nigeria (Akwa Ibom, Enugu,
Lagos, Taraba, Jigawa, Kogi) covering the six geopolitical zones of Nigeria including the
Federal Capital Territory.
xxxv
Figure 3.1: Map of Nigeria
Source: GIS Unit, Department Of Geography, University of Nigeria Nsukka.
3.2 Data Collection Instrument:
xxxvi
Two sets of data were identified as being relevant to the effective conduct of this research
namely primary and secondary.
The primary data which refers to field data were obtained through the use of well structured
questionnaires.
Secondary data through the review of various relevant literatures, journals, textbooks dealing
with construction management practice were also used in the course of carrying out the research.
The questionnaire was validated before it administration. The questionnaire is in appendix A.
3.3 Administration of the Data Collection Instrument
The questionnaires were delivered by hand to the various target groups. These groups include:
contractors, consultants and clients.
3.4 Population and Sample
The total population of elements under study was 244. Out of this, 128 represented contractors,
63 consultants while 53 were clients. To obtain the sample sizes for each target groups, a formula
for determining the sample size put forward by Kish (1965) for 94% confidence level is given
by:
n = n1
1+ n1
N
(3.1)
Where N = total population size, n = sample size from finite population, n1 = sample size from
infinite population and is given as S2
V 2 .
n1 = S2
V 2
(3.2)
xxxvii
where S2 is the variance of the population elements and V 2 is a standard error of sampling
population (usually S = 0.5, V = 0.6)
Thus n1 = S2
V 2 = ( 0.50.06 )
2
= 69.44
(3.3)
For contractors, n = 69.44
1+ 69.44128
= 45 contractors
(3.4)
For consultants, n= 69.44
1+ 69.4463
= 33 consultants
(3.5)
For clients, n = 69.44
1+ 69.4453
= 30 clients
(3.6)
On the whole, 45 contractors, 33 consultants and 30 clients were randomly selected for the study.
3.5 Data Collection:
The instrument used for this research was questionnaire. In order to choose a suitable method for
analysis of this work, the level of measurement of data must be identified. In this study, ordinal
scales were employed. Based on Likert Scale, the following table indicates values assigned to
different options used in the questionnaires (Cheung et al, 2004; Iyer and Jha, 2005; Ugwu and
Haupt, 2007):
Table 3.1: Ordinal scale for data measurement
ITEM NO EXTENT MODERATE
EXTENT
MEDIUM
EXTENT
LARGE
EXTENT
VERY LARGE
EXTENT
SCALE 1 2 3 4 5
xxxviii
Questionnaires were distributed to randomly selected target groups based on their sample sizes.
This implies that questionnaires were distributed to 45 contractors, 33 consultants and 30 clients.
Out of these questionnaires distributed, 40 contractors (88.9%), 28 consultants (84.8%) and 24
clients (80%) returned their questionnaires.
Table 3.2: Distribution of Questionnaires to the target groups.
CATEGORY NO OF
QUESTIONNAIRES
DISTRIBUTED
NO. OF
QUESTIONNAIRES
RETURNED
PERCENTAGE OF
QUESTIONNAIRES
RETURNED
CONTRACTORS 45 40 88.9%
CONSULTANTS 33 28 84.8%
CLIENTS 30 24 80.0%
TOTAL 108 92 85.0%
CONTRACTORS 89%
CONSULTANTS85%
CLIENTS80%
Figure 3.2: Percentages of Received Questionnaires
xxxix
3.6 Method of Analysis:
3.6.1 Relative Importance Index (RII):
The procedure used in the analysis of this work was Relative Importance Index, which is a
measure of determining the relative importance of factors considered in this study. To do this,
scores for each factor were calculated by summing up the scores by the various respondents. The
Relative Importance Index, as given by Cheung et al (2004), Ugwu and Haupt (2007) and Iyer
and Jha (2005), is computed using equation (3.7)
Relative Importance Index (RII) = ∑j=1
5
a j m j (3.7)
a5 N
Where N is the total number of respondents in a given group, a j = constant expressing the weight
given to the jth response, j = 1, 2, 3, 4, 5.
For a response of ‘no extent’ a1 = 1
For a response of ‘moderate extent’ a2 = 2
For a response of ‘medium extent’ a3 = 3
For a response of ‘large extent’ a4 = 4
For a response of ‘very large extent’ a5 = 5
mj = frequency associated with response j, j = 1,2,3,4,5
The Relative Importance Index (RII) computed for all factors in each category were ranked in
their order of magnitude.
3.6.2 Kendall’s Coefficient of Concordance or Agreement (W):
Kendall’s Coefficient of Concordance is a measure of the degree or extent of agreement or
concordance amongst responses from groups in a certain population. The closer the value of W is
to 1, the stronger the degree of agreement among the target groups and the closer the value of W
is to 0, the weaker the level of agreement amongst the target groups. Kendall’s Coefficient of
Concordance (W) can be determined using equation (3.8) as given by Moore et al (2003) and
xl
Frimpong et al (2003). W = 12U−3 m2n(n+1)2
m2 n(n¿¿2−1)¿
(3.8) Where u = ∑i=1
n
(∑k=1
m
R k)2
;
(3.9)
Rk=Ranking for group K ,k=1,2,3 ………m
n = number of factors
m = number of groups
i = the factors, 1, 2, 3......n
W = Coefficient of Concordance.
∑k =1
m
Rk=∑ of ranks∈all t h e groups for eac h factor
In this research work, the Kendall’s Coefficient of Concordance (W) is used to determine the
agreement in response of the three target groups (contractors, consultants and clients) concerning
the factors that influence management of construction in Nigeria.
3.6.3 Test for the Null Hypothesis
In order to test the hypothesis of agreement or disagreement among these three groups on the
ranking of factors, chi-square (X2) test approximation of sampling distribution of W was used,
since n = 58 was too large for the table of critical value of W.
The X2 approximation of W is given as expressed in X2 = m (n – 1) W
(3.10)
for (n – 1) degrees of freedom
The decision rule is that if the computed value of X2 is greater than the tabulated value of X2, Ho
is rejected; otherwise accepted.
xli
CHAPTER FOUR
DATA PRESENTATION, ANALYSIS AND INTERPRETATION
4.0 Data Presentation:
The results of this part of study provide an indication of the relative importance index and rank
of factors influencing construction management practice in Nigeria.
Table 4.1: Relative Importance Index and Rank for Quality Management during Design.
CATEGORY: Quality Management
During Design
(RII) RANK
Factors:
Conflicting design information 0.8739 1
Timeliness of revised drawing issue 0.6826 3
Missing information 0.8 2
Dimensional inaccuracies 0.5696 4
xlii
CONFL
ICTI
NG DES
IGN IN
FORM
ATIO
N
TIM
ELIN
ESS
OF
REVIS
ED D
RAWIN
G ISSU
E
MIS
SING IN
FORM
ATIO
N
DIMEN
SIO
NAL INACCURACIE
S
00.10.20.30.40.50.60.70.80.9
10.8739
0.6826
0.8
0.5696
RE
LA
TIV
E I
MP
OR
TA
NC
E I
ND
EX
Fig. 4.1: Response for Quality Management during Design
Table 4.2: Relative Importance Index and Rank for Quality Management during Construction
CATEGORY: Quality Management During Construction
(RII) RANK
Factors:
Analysing resources movement to and on site 0.515217 7
Forecasted planning date such as activity duration and resource quantities required
0.782609 3
Monitoring and updating of plans to appropriately reflect work status
0.736957 4
Work sequencing to achieve and maintain workflow 0.636957 5
Effective co – ordination of resources 0.895652 1
Inspection of construction 0.621739 6
Development of appropriate structure to maintain workflow
0.815217 2
xliii
ANALYSIN
G RESOURCES
MOVEM
ENT T
O AND O
N SITE
FOREC
ASTED
PLANNIN
G DATE
SUCH A
S ACTIV
ITY D
URATION A
ND RESOURCE Q
UANTITIES
MONITO
RING A
ND UPDATIN
G OF P
LANS T
O APPROPRIA
TELY
REFLE
CT WORK ST
ATUS
WORK SE
QUENCIN
G TO A
CHIEVE A
ND MAIN
TAIN
WORKFL
OW
EFFE
CTIVE C
O-ORDIN
ATION O
F RES
OURCES
INSP
ECTIO
N OF C
ONSTRUCTIO
N
DEVEL
OPMEN
T OF A
PPROPRIATE
STRUCTU
RE TO M
AINTA
IN W
ORKFLOW
0
0.2
0.4
0.6
0.8
1
0.515217
0.7826090.7369570.636957
0.895652
0.621739
0.815217R
EL
AT
IVE
IM
PO
RT
AN
CE
IN
DE
X
Figure 4.2: Response for Quality Management During Construction
Table 4.3: Relative Importance Index and Rank for Construction Management Techniques
CATEGORY: Construction Management Techniques (RII) RANK
Factors:
Work Breakdown Structure 0.645652 3
Critical Path Method 0.726087 1
PRINCE 2 0.393478 8
Cost Benefit Analysis 0.541304 4
Programme Evaluation & Review Technique 0.367391 9
Project Sensitivity Analysis 0.469565 5
Bar Chart 0.673913 2
Graphical Evaluation & Review Technique 0.413043 7
Line of balance 0.445652 6
xliv
WORK BREA
KDOWN ST
RUCTURE
CRITICAL P
ATH M
ETHOD
PRINCE 2
COST BEN
EFIT
ANALYSIS
PROGRAMM
E EVALU
ATION &
REVIEW
TECHNIQ
UE
PROJECT S
ENSIT
IVITY A
NALYSIS
BAR CHART
GRAPHICAL EVALU
ATION &
REVIEW
TECHNIQ
UE
LINE O
F BALA
NCE00.10.20.30.40.50.60.70.8
0.6456520.726087
0.393478
0.541304
0.3673910.469565
0.673913
0.413043 0.445652
RE
LA
TIV
E I
MP
OR
TA
NC
E I
ND
EX
Figure 4.3: Response for Construction Management Tools
Table 4.4: Relative Importance Index and Rank for Economic Policy
CATEGORY: Economic Policy (RII) RANK
Factors:
Equipment availability 0.771739 2
Materials availability 0.882609 1
Indirect impact of interest rates 0.495652 5
Bankruptcy 0.547826 4
Supervision / management staff availability 0.656522 3
xlv
EQUIPMEN
T AVAILA
BILITY
MATERIALS
AVAILABILIT
Y
INDIRECT I
MPACT OF I
NTERES
T RATE
S
BANKRUPTCY
SUPER
VISION / M
ANAGEMEN
T STA
FF AVAILA
BILITY0
0.2
0.4
0.6
0.8
1
0.7717390.882609
0.495652 0.5478260.656522
RE
LA
TIV
E I
MP
OR
TA
NC
E I
ND
EX
Figure 4.4: Response for Economic Policy
Table 4.5: Relative Importance Index and Rank for Management Style
CATEGORY: Management Style (RII) RANK
Factors:
Providing specific direction 0.71087 4
Setting specific goals people are to achieve 0.86087 2
Setting timelines 0.893478 1
Seeking peoples opinion 0.454348 8
Involving team members 0.641304 5
Provide support and encouragement 0.576087 6
Organizing work situation for people 0.497826 7
Conducting regular updates on progress 0.758696 3
xlvi
PROVIDIN
G SPEC
IFIC D
IRECTIO
N
SETT
ING SP
ECIFI
C GOALS
PEOPLE
ARE T
O ACHIEV
E
SETT
ING TI
MEL
INES
S
SEEK
ING PEO
PLE'S
OPINIO
N
INVOLV
ING TE
AM M
EMBER
S
PROVIDE S
UPPORT AND EN
COURAGEMEN
T
ORGANIZING W
ORK SITU
ATION FO
R PEOPLE
CONDUCTING REG
ULAR U
PDATES O
N PROGRESS
00.10.20.30.40.50.60.70.80.9
1
0.71087
0.86087 0.893478
0.454348
0.6413040.576087
0.497826
0.758696
RE
LA
TIV
E I
MP
OR
TA
NC
E I
ND
EX
Figure 4.5: Response for Management Style
Table 4.6: Relative Importance Index and Rank for Socio – Political Consideration
CATEGORY: Socio-Political Consideration (RII) RANK
Factors
Civil strife or riots. 0.852174 1
Influence of protest action-groups 0.704348 2
Disruption due to environmental concerns 0.636957 3
xlvii
CIVIL ST
RIFE O
R RIOTS
INFL
UENCE O
F PROTE
ST A
CTION-G
ROUPS
DISRUPTIO
N DUE T
O ENVIROM
ENTA
L CONCER
NS0
0.10.20.30.40.50.60.70.80.9 0.852174
0.7043480.636957
RE
LA
TIV
E I
MP
OR
TA
NC
E I
ND
EX
Figure 4.6: Response for Socio-Political Consideration
Table 4.7: Relative Importance Index and Rank for Motivation of Workers
CATEGORY: Motivation of Workers (RII) RANK
Factors:
Pay and allowances. 0.545652 6
Job security. 0.771739 2
A sense of belonging and identification with the project team. 0.9 1
Recognition of contribution 0.695652 4
Opportunity for extending skills and experience through learning as a means of job satisfaction and higher productivity.
0.75 3
Equitable reward relative to others input to the project 0.528261 7
xlviii
Exercise of power. 0.46087 8
Opportunity to career advancement for future benefit 0.6 5
PAY & A
LLOW
ANCE
JOB SE
CURITY
SENSE
OF B
ELONGIN
G & ID
ENTIF
ICATIO
N WITH
THE P
ROJECT T
EAM
RECOGNITI
ON OF C
ONTRIB
UTION
OPPORTUNITY
FOR EX
TENDIN
G SKILL
S & EX
PERIEN
CE THROUGH LE
ARNING A
S A M
EANS O
F JOB SA
TISF
ACTION &
HIG
HER P
RODUCTIVITY
EQUITA
BLE R
EWARD R
ELATIV
E TO O
THER
S INPUT T
O THE P
ROJECT
EXER
CISE O
F POW
ER
OPPORTUNITY
TO C
AREER A
DVANCEMEN
T FOR FU
TURE B
ENEF
IT
0
0.2
0.4
0.6
0.8
1
0.545652
0.7717390.9
0.6956520.75
0.5282610.46087
0.6
RE
AL
AT
IVE
IM
PO
RT
AN
CE
IN
DE
X
Figure 4.7: Response for Motivation of Workers
Table 4.8: Relative Importance Index and Ranks for Obstacles facing Construction Management Practice.
CATEGORY: Obstacles facing Construction Management Practice
(RII) RANK
Factors:
Lack of professional training 0.726087 3
Lack of construction management knowledge 0.91087 1
Bribery and corruption 0.815217 2
Lack of leadership commitment 0.508696 6
Incessant change of authority 0.573913 5
Rigid organization structure 0.684783 4
xlix
LACK O
F PROFE
SSIO
NAL TRAINING
LACK O
F CONST
RUCTION M
ANAGEMEN
T KNOW
LEDGE
BRIBERY &
CORRUPTION
LACK O
F LEA
DERSH
IP COMMITMEN
T
INCESSA
NT CHANGE O
F AUTH
ORITY
RIGID ORGANIZA
TION ST
RUCTURE0
0.2
0.4
0.6
0.8
1
0.726087
0.910870.815217
0.5086960.573913
0.684783
RE
LA
TIV
E I
MP
OR
TA
NC
E I
ND
EX
Figure 4.8: Response for Obstacles facing Construction Management Practice
Table 4.9: Relative Importance Index and Rank for benefits of applying construction management tools in practice.
CATEGORY: Benefits of Applying Construction Management Tools in Practice
(RII) RANK
Factors:
Better communication 0.786957 3
Good management of resources 0.791304 2
Known work progress 0.88913 1
Defined goals and objectives 0.523913 6
Better quality 0.580435 5
Better work organization 0.519565 7
l
Better time utilization 0.693478 4
BETTE
R COM
MUNIC
ATION
GOOD MANAGEM
ENT O
F RES
OURCES
KNOWN W
ORK PROGRES
S
DEFIN
ED G
OALS &
OBJE
CTIVES
BETTE
R QUALIT
Y
BETTE
R WORK O
RGANIZATIO
N
BETTE
R TIM
E UTIL
IZATIO
N0
0.10.20.30.40.50.60.70.80.9
1
0.786957 0.7913040.88913
0.5239130.580435
0.519565
0.693478
RE
LA
TIV
E I
MP
OR
TA
NC
E I
ND
EX
Figure 4.9: Response for Benefits of Applying Construction Management Tools
PRACTICES CONCERNING CONSTRUCTION MANAGEMENT:
The target groups in this study are contractors, consultants and clients. 108 questionnaires were
distributed as follows: to 45 contractors, 33 consultants and 30 clients. 92 questionnaires were
received from the target groups as follows: from 40 contractors (88.9%), from 28 consultants
(84.8%) and from 24 clients (80%) as respondents. This part presents some construction
management practices.
1. The time management practice:
a) What kind of method do you use to represent the project plan and schedule?
Table 4.10: Usage of planning method:
ITEM PERCENT % (FREQUENCY)CONTRACTOR CONSULTANT CLIENT
Bar Chart Method 67.5(27) 28.57 (8) 54.17 (13)
li
Critical Path Method 25 (10) 67.86 (19) 41.67 (10)S-Curve Method 5 (2) 3.57 (1) -Others 2.5 (1) - 4.17 (1)Total 100 (40) 100 (28) 100(24)
BAR CHART CPM S-CURVE OTHERS0
5
10
15
20
25
30
CONTRACTORCONSULTANTCLIENT
Figure 4.10 Responses to Usage of Planning Method
b) How often does your project team formally meet for discussion of monitoring, updating and
controlling the progress?
Table 4.11: Frequency of meeting of project team:
ITEM PERCENT % (FREQUENCY)CONTRACTOR CONSULTANT CLIENT
Daily 2.5 (1) 14.28 (4) 4.17 (1)Weekly 77.5 (31) 71.43 (20) 54.17 (13)Monthly 20 (8) 14.28 (4) 41.67 (10)
No -Total 100 (40) 100 (28) 100 (24)
lii
DAILY WEEKLY MONTHLY NO0
5
10
15
20
25
30
35
CONTRACTORCONSULTANTCLIENT
Figure 4.11 Frequency of responses to meeting of Project Team
c) How often do you co-ordinate your schedule with master schedule of the project?
Table 4.12: Co-ordination frequency of current schedule with master schedule:
ITEM PERCENT % (FREQUENCY)CONTRACTOR CONSULTANT CLIENT
Daily 2.5 (1) 14.28 (4) 20.83 (5)Weekly 22.5 (9) 71.43 (20) 62.5 (15)Monthly 75 (30) 14.28 (4) 16.67 (4)
No - - -Total 100 (40) 100 (28) 100 (24)
DAILY WEEKLY MONTHLY NO0
5
10
15
20
25
30
CONTRACTORCONSULTANTCLIENT
Fig 4.12 Frequency of response for co-ordination of current schedule with master Schedule of
the Project
d) How often do you require the sub-contractors or supplier to submit their detailed activities
schedule for you in advance to adjust your actual schedule?
liii
Table 4.13: Frequency of co-ordination with sub-contractors and supplier schedule:
ITEM PERCENT % (FREQUENCY)CONTRACTOR CONSULTANT CLIENT
Daily 17.5 (7) 10.71 (3) 4.17 (1)Weekly 47.5 (19) 10.71 (3) 37.5 (9)Monthly 35 (14) 75 (21) 37.5 (9)
No - 3.57 (1) 20.83 (5)Total 100 (40) 100 (28) 100 (24)
DAILY WEEKLY MONTHLY NO0
5
10
15
20
25
CONTRACTORCONSULTANTCLIENT
Figure 4.13 Frequency of responses for sub-contractors and supplier schedule
e) How do you supply the incentive system to stimulate the success of the project?
Table 4.14: Frequency for usage of incentive system:
ITEM PERCENT % (FREQUENCY)CONTRACTOR CONSULTANT CLIENT
Salary increase 52.5 (21) 64.29 (18) 62.5 (15)Bonus in position 12.5 (5) 14.28 (4) 4.17 (1)
Training 35 (14) 14.28 (4) 12.5 (3)Others - 7.14 (2) 20.83 (5)Total 100 (40) 100 (28) 100 (24)
liv
SALARY INCREASE BONUS IN POSITION TRAINING OTHERS0
5
10
15
20
25
CONTRACTORCONSULTANTCLIENT
Figure 4.14 Frequency of responses for usage of incentive system
f) Which software do you apply for planning and scheduling the progress of the project?
Table 4.15: Frequency for usage of software for planning and scheduling:
ITEM PERCENT % (FREQUENCY)CONTRACTOR CONSULTANT CLIENT
Primavera 17.5 (7) 10.71 (3) 8.33 (2)Microsoft Project 52.5 (21) 53.57 (15) 66.67 (16)
Excel Sheet 30 (12) 35.71 (10) 25 (6)No - - -
Total 100 (40) 100 (28) 100 (24)
PRIMAVERA MICROSOFT PROJECT EXCEL SHEET NO0
5
10
15
20
25
CONTRACTORCONSULTANTCLIENT
Figure 4.15 Frequency of responses for usage of software for planning and scheduling
g) Do your company formally participate in the pre-project planning?
Table 4.16: Frequency of formal participation in the pre-project planning:
ITEM PERCENT % (FREQUENCY)CONTRACTOR CONSULTANT CLIENT
Yes, as pre-project 15 (6) 10.71 (3) 75 (18)
lv
plannerYes, as the consultant - 78.57 (22) -
No 85 (34) 10.71 (3) 25 (6)Total 100 (40) 100 (28) 100 (24)
YES, AS PRE-PROJECT PLANNER
YES, AS CONSULTANT NO0
5
10
15
20
25
30
35
CONTRACTORCONSULTANTCLIENT
Figure 4.16 Frequency of responses for formal participation in pre-project planning
2. The cost management practice:
a) Do you have the cost schedule associated with the estimated time schedule?
Table 4.17: Presence of cost schedule associated with the estimated time schedule:
ITEM PERCENT % (FREQUENCY)CONTRACTOR CONSULTANT CLIENT
Yes 47.5 (19) 85.71 (24) 70.83 (17)No 17.5 (7) 3.57 (1) 4.17 (1)
Sometimes 35 (14) 10.71 (3) 25 (6)Total 100 (40) 100 (28) 100 (24)
lvi
YES NO SOMETIMES0
5
10
15
20
25
CONTRACTORCONSULTANTCLIENT
Figure 4.17 Responses for Presence of Cost Schedule with Estimated Time Schedule
b) Do you apply the actual value and earned value concept in controlling cost for the project?
Table 4.18: Applying the actual value and earned value concept in controlling cost:
ITEM PERCENT % (FREQUENCY)CONTRACTOR CONSULTANT CLIENT
Yes 55 (22) 64.28 (18) 66.67 (16)No 17.5 (7) 14.28 (4) 12.5 (3)
Sometimes 27.5 (11) 21.43 (6) 20.83 (5)Total 100 (40) 100 (28) 100 (24)
YES NO SOMETIMES0
5
10
15
20
25
CONTRACTORCONSULTANTCLIENT
Figure 4.18: Response of applying actual value and earned value concept in controlling cost
c) Do you have a cost engineer who is only responsible for dealing with cost control?
Table 4.19: Having a cost engineer responsible for cost control:
ITEM PERCENT % (FREQUENCY)CONTRACTOR CONSULTANT CLIENT
Yes 35 (14) 25 (7) 12.5 (3)No 50 (20) 64.28 (18) 66.67 (16)
Sometimes 15 (6) 10.71 (3) 20.83 (5)Total 100 (40) 100 (28) 100 (24)
lvii
YES NO SOMETIMES0
2
4
6
8
10
12
14
16
18
20
CONTRACTORCONSULTANTCLIENT
Figure 4.19 Responses for having a cost engineer responsible for cost control
d) Do you apply any software to plan, monitor and control cost for the success of the project?
Table 4.20: Applying software to plan, monitor and control cost:
ITEM PERCENT % (FREQUENCY)CONTRACTOR CONSULTANT CLIENT
Yes 62.5 (25) 75 (21) 66.67 (16)No 20 (8) 14.28 (4) 12.5 (3)
Sometimes 17.5 (7) 10.71 (3) 20.83 (5)Total 100 (40) 100 (28) 100 (24)
YES NO SOMETIMES0
5
10
15
20
25
CONTRACTORCONSULTANTCLIENT
Figure 4.20 Responses for applying software to plan, monitor and control cost
3. The safety management practice:
a) To what extent has an overall project safety been implemented?
Table 4.21: Implementation level of safety:
ITEM PERCENT % (FREQUENCY)CONTRACTOR CONSULTANT CLIENT
Not at all - 3.57 (1) 8.33 (2)
lviii
Moderately 55 (22) 60.71 (17) 70.83 (17)Extensively 45 (18) 35.71 (10) 20.83 (5)
Total 100 (40) 100 (28) 100 (24)
NOT AT ALL MODERATELY EXTENSIVELY0
5
10
15
20
25
CONTRACTORCONSULTANTCLIENT
Figure 4.21 Frequency of responses for Implementation Level of Safety
b) How often do you organize the meeting for safety issue?
Table 4.22: Meeting frequency for safety issues:
ITEM PERCENT % (FREQUENCY)CONTRACTOR CONSULTANT CLIENT
None 15 (6) 7.14 (2) 12.5 (3)Monthly 12.5 (5) 67.86 (19) 66.67 (16)Weekly 12.5 (5) 14.28 (4) 12.5 (3)Daily 60 (24) 10.71 (3) 8.33 (2)Total 100 (40) 100 (28) 100 (24)
NONE MONTHLY WEEKLY DAILY0
5
10
15
20
25
CONTRACTORCONSULTANTCLIENT
Figure 4.22 Responses of meeting frequency for safety issues
lix
c) To what extent is pre-task planning for safety conducted by contractor foremen or other site
managers?
Table 4.23: Frequency of pre-task planning for safety conducted by contractor foremen or other
site managers:
ITEM PERCENT (FREQUENCY)CONTRACTOR CONSULTANT CLIENT
Not at all 12.5 (5) 14.28 (4) 8.33 (2)Moderately 67.5 (27) 67.86 (19) 70.83 (17)Extensively 20 (8) 17.86 (5) 20.83 (5)
Total 100 (40) 100 (28) 100 (24)
NOT AT ALL MODERATELY EXTENSIVELY0
5
10
15
20
25
30
CONTRACTORCONSULTANTCLIENT
Figure 4.23 Frequency of Responses of Pre-Task Planning for Safety conducted by Site Managers
4.1 Analysis and Interpretation
4.1.1 Quality Management during Design factors
Table 4.1 presents the respondents perceptions of relative importance index (RII) and ranking
regarding the factors that influence quality management during design in construction
management practice.
The factor that is ranked 1st in the category of quality management during design is Conflicting
Design Information. The probable reason for this is the process it will take to correct a mistake.
It may require checking the design from the beginning, which may take longer time thereby
affecting the success of the project.
lx
Missing information was ranked 2nd. This factor may lead to delays as a result of carelessness or
incompetence in design. Missing design information will inhibit the smooth flow of operations
on site, thereby causing some setbacks to the scheduled project completion date.
Dimensional inaccuracies is ranked 4th in this category. However, it does not imply that its
influence is negligible because the duration it takes to clarify inaccuracies may influence success
of the project.
4.1.2 Quality Management during Construction factors
Table 4.2 presents the respondents perceptions of relative importance index (RII) and ranking
regarding the factors that influence quality management during construction.
Effective co-ordination of resources was ranked 1st in this category. The lack of effective control
of resources such as plants, materials and human resources may lead to disorder on construction
sites. A clash of activities which may in turn lead to a shortage of materials and labour on site
may in turn result to low productivity.
Development of an appropriate organization structure to maintain workflow was 2nd in this
category.
Construction activities are carried out by issuing instructions, providing guidance and support for
a particular task. Instructions are given by superiors to subordinates. The labourers and
supervisors must be aware of whom they must take instructions from and to whom to report to. A
situation where these are not well defined may lead to poor performance on the project.
Analyzing resources movement to and on site is ranked 7th in this category. The various times
resources are required on site should be estimated so as to avoid idleness which engenders waste.
This could be in the form of time losses which is indirectly wasting of funds and may lead to
abandonment of the project.
4.1.3 Construction Management Techniques
Table 4.3 presents the respondents perceptions of relative importance index (RII) and ranking
regarding the influence of construction management technique factors in construction
management practice.
lxi
Critical Path Method was ranked 1st. The likely reason for this degree of influence is the fact that
it enables the identification of critical activities which when executed sequentially leads to the
success of the project.
The Bar Chart is ranked 2nd after the CPM. It’s a simple tool to use, understand and interpret by
most construction workers but do not really have an advantage over CPM.
4.1.4 Economic Policy factors
Table 4.4 presents the respondents perceptions of relative importance index (RII) and ranking
regarding the influence of economic policy factors in construction management practice.
Availability of materials is ranked 1st in this category. The reason is that when other resources for
construction are available and there is lack of materials, then no work can be executed.
Availability of equipments is ranked 2nd. This may be as a result of the fact that equipments are
required for some critical tasks on site. There is hardly any task that does not require the use of
equipment. There are different kinds of equipment, namely powered and mechanical. Powered
equipment makes delivery of work faster while mechanical equipment takes a longer time.
4.1.5 Management Style factors
Table 4.5 presents the respondents perceptions of relative importance index (RII) and ranking
regarding the influence of management style factors in construction management practice.
Setting timeliness is ranked 1st in this category. In order to achieve meaningful progress
construction managers need to define the number of tasks to be performed within a specific time.
The lack of specification of timelines for the performance of activities may have an adverse
effect on the success of projects. There are measures such as setting time lines which need to be
applied for meaningful output to be achieved.
Specifying the goals people are to accomplish is ranked 2nd in this category. Construction project
consist of activities and these activities need to be specified to workers and supervisors through
information given by the management team for monthly, weekly and daily task execution
completion of the project. This is partly the reason for the need to provide a work schedule and
cash flow for a particular project.
lxii
Seeking people’s opinion is ranked 8th in this category. It’s a managerial tool used for success in
projects which is not often utilized. Workers are very skilful in contributing ideas for
improvement of work execution. Most of the workers are not opportuned to speak to their
supervisors.
4.1.6 Socio – Political Consideration factors
Table 4.6 presents the respondents perceptions of relative importance index (RII) and ranking
regarding the influence of socio-political consideration factors in construction management
practice.
Civil strife and riots is ranked 1st in this category. The basic initiator of civil strife and riots is
agitation for higher wages. Agitation for higher wages by workers is applicable to all industries.
Strike in the construction sector may affect construction workers in that they may not have
access to and from sites, especially when an organization does not have it own transport vehicle.
Disruption due to environmental concern such as fire and flood is ranked 3rd. Construction sites
could be considered safe from fire occurrences.
4.1.7 Motivation of Staff factors
Table 4.7 presents the respondents perceptions of relative importance index (RII) and ranking
regarding the factors that influence motivation of staff in construction management practice.
A sense of belonging and identification with the project team is ranked 1 st in this category. The
word belonging means to be part of the project issues while identification with the project team
comes from recognizing every efforts and contributions. A worker that is made to understand
he / she belongs to a team will not look elsewhere to find a sense of belonging rather he / she
does all in his / her own ability to ensure the objectives of the team are achieved. This is
applicable to identification with the project team.
The next factor in this category is job security and it was ranked 2nd. When workers have an
understanding that they have a bright future with an organization, it motivates them to high
productivity at all times. The factors motivating such a reaction are satisfaction with wages, the
ability to sustain family, train children and opportunity for postgraduate studies.
lxiii
The factor with the lowest influence is exercise of power and its rank 7 th in this category. Every
human being wants to be treated with respect and to be recognized. Commanding attitude at
work may have moderate influence on achieving high productivity.
4.1.8 Obstacles facing Construction Management
Table 4.8 presents the respondents perceptions of relative importance index (RII) and ranking
regarding the influence of obstacles facing construction management practice.
Lack of construction management knowledge is ranked 1st. This shows that most of the
construction managers are not well trained in the art of construction management. Therefore to
apply construction management tools in project life cycle becomes a serious problem to these
untrained managers.
4.1.9 Benefits of applying Construction Management Tools in Practice.
Table 4.9 presents the respondents perceptions of relative importance index (RII) and ranking
regarding the influence of benefits of applying construction management tools factors.
Known work progress is ranked 1st in this category. The respondents believe that if construction
management tools are well applied, it will lead to high productivity and success of the project,
thereby affording the opportunity of tracking the project progress. This in line with the study of
Abbasi and Al-Mharmah (2000) that discovered that among other benefits, known work progress
is a highly perceived benefit of applying construction management tool.
Good management of resources was ranked 2nd. The respondents believed that if construction
management tools are well applied it will enhance better communication.
4.1.10 Usage of Planning Method:
Table 4.10 shows that bar chart method is the most widely used planning and scheduling method
for owners and contractors because bar chart method can facilitate time performance control for
each scheduled activity through project implementation. However, critical path method (CPM) is
lxiv
the most important one for consultants because CPM can be used to determine critical activities
of project. This will assist consultants to evaluate overall time performance and to identify the
effectiveness of critical path on completion date of project.
S-Curve method is never used by clients and it is rarely used by consultants and contractors. This
is because S Curve method can compare only between actual time and estimated time at any
stage through project implementation. It is difficult to control time performance for each
scheduled activity and it is difficult to obtain critical path affecting overall time performance of
project.
Koo et al (2007) stated that construction planners face many scheduling challenges during the
course of a project. Planners today rely on CPM-based scheduling tools to evaluate different
sequencing alternatives for their feasibility and whether they will meet project deadlines.
4.1.11 Meeting of Project Team:
Table 4.11 shows that contractors, consultants and clients often meet weekly for discussion.
Weekly meeting assist them in monitoring, updating and controlling the progress through project
implementation. In addition, they can solve problems, evaluate current performance, and
improve future works. Daily meeting are required in the case of sensitive and very important
works. Monthly meeting is not effective for monitoring or updating processes. Navon (2005)
stated that a controlling and updating is an important element to identify factors affecting
construction project performance.
4.1.12 Co-ordination frequency of Current Schedule with Master Schedule:
Table 4.12 shows that most of the clients and consultants co-ordinate current schedule with
master schedule of the project weekly. This weekly co-ordination assists them to evaluate
performance of project comparing with base schedule. However, most of the contractors co-
ordinate current schedule with master schedule of the project monthly. In fact, contractors should
do that weekly in order to have continuous monitoring, controlling and updating of time
lxv
performance of project. Generally, monitoring and updating the progress depends up on project
duration, type of works and degree of project complexity.
4.1.13 Co-ordination with Sub-Contractors and Supplier Schedule:
Table 4.13 shows that most of the clients co-ordinate with sub-contractors and supplier schedule
monthly or weekly. However, this depends up on the need for co-ordination and controlling
processes. Also, most consultants co-ordinate with sub-contractors and supplier schedule
monthly.
Most contractors co-ordinate with sub-contractors and suppliers schedule on weekly basis.
This co-ordination depends mainly on project nature, type of work, duration of supplying and
implementation. Thomas (2006) remarked that the selection of suitable suppliers for the
provision of various construction materials is one of the most important aspects in ensuring
successful performance of construction projects.
4.1.14 Supply of Incentives:
Table 4.14 shows that most of the contractors, consultants and clients use increase salary system
in order to ensure the success of construction. This system motivates employees and enables
them to improve productivity and performance. The system is more important for employees
than bonus in position or training. Training is required according to nature of project and its
duration. In addition, training is important for improvement and development overall
performance of organization.
It is remarked that better training and motivation system can help to ensure success of the
project.
4.1.15 Usage of Software for Planning and Scheduling:
Table 4.15 shows that Microsoft project is the most widely used program by contractors,
consultants and clients for planning and scheduling. This program enables them to schedule,
lxvi
monitor, update and control many criteria of project such as time, cost and resources. It is
observed that Primavera program is an advanced and a complex program compared with
Microsoft project. However, Excel program has a limitation in usage for planning and
scheduling.
4.1.16 Participation in the Pre-Project Planning Effort:
Table 4.16 shows that most clients participate in the pre-project planning effort as the pre-project
planner. Most consultants participate in the pre-project planning effort as the consultant.
However, most contractors do not participate in the pre-project planning effort. Planning of
construction projects is one of the main duties and responsibilities of consultants. Owners mainly
need planning for budget and time estimation of projects. Some contractors participate in the
planning for complex and large projects. This depends on the nature and type of implemented
works.
4.1.17 Presence of Cost Schedule Associated with the Estimated Time Schedule:
Table 4.17 shows that contractors, consultants and clients often use cost schedule associated with
the estimated time schedule. This assists the construction actors to evaluate performance of cost
and time together at any stage through project implementation. It will also assist the construction
actors to know if the project is ahead or behind of schedule and if it is over or under estimated
4.1.18 Applying the Actual Value and Earned Value Concept in Controlling Cost:
Table 4.18 shows that most of owners, consultants and contractors apply the actual value and
earned value concept in management of project. Earned value concept provides a system for
evaluating the performance of the project through integrating cost, schedule and work. This will
assist for evaluation cost and time performance of projects. For example, at any stage of project,
if earned value is more than actual value, the cost performance will be good.
Vandevoorde (2006) stated that earned value project management is a well-known management
system that integrates cost, schedule and technical performance. The earned value method
provides early indications of project performance to highlight the need for eventual corrective
action.
lxvii
4.1.19 Cost Engineer responsible for Cost Control:
Table 4.19 shows that most of the contractors, consultants and clients do not have a cost engineer
who is only responsible for dealing with cost control.
4.1.20 Applying Software to Plan, Monitor and Control Cost:
Table 4.20 shows that most contractors, consultants and clients use software program in order to
facilitate planning, monitoring and controlling cost. The programs used in construction industry
in order to control and monitor cost are: Excel and Ms project. Most of the construction actors
are familiar with these programs because they are easy to use and have different facilities and
functions to control the cost. Goh (2005) remarked that information technology management
leads to performance improvement in the construction industries.
4.1.21 Implementation of Safety factors:
Table 4.21 shows that in most cases overall project safety factors have been moderately
implemented in construction sector. This is because of absence of safety control or its application
through project implementation stage. In Nigeria, most contractors do not care about health and
safety during construction of projects. In addition, consultants do not have sufficient control or
continuous supervision for safety compliance. All these often lead to occurrence of accidents and
problems in construction projects. Cheung et al (2004) remarked that safety factor affects
strongly on performance of projects. Ugwu and Haupt (2007) stated that safety factors are
significant for consultants and contractors because it affects strongly the safety and sustainability
performance of construction projects.
4.1.22 Meeting for Safety Issue:
Table 4.22 shows that most of the clients and consultants organize the meeting for safety issue
monthly. However, most of contractors organize safety meeting daily. This is because
contractors are more interested with operational factors which require frequent and continuous
meeting for safety issues
4.1.23 Level of Pre-Task Planning for Safety conducted:
lxviii
Table 4.23 shows that in most cases, pre-task planning for safety was moderately conducted by
contractor foremen or other site managers. This is because of absence of safety planning and
control through project implementation stage. In the Nigerian construction industry, there are
many contractors who do not care with planning health and safety issues during construction of
projects. This will lead to occurrence of accidents and problems in construction projects.
4.2 TEST OF HYPOTHESIS
Computation of Kendall’s Coefficient of Concordance (w):
Using equation (3.2), Kendall’s Coefficient of Concordance (W) is calculated as;
U = ∑i=1
n
(∑K=1
m
RK)2
=561597
m= 3 and n = 58
Therefore, W = 12 x 561597−3 (3 )2 (58 ) (59 )2
(3 )2 (58 ) [ (58 )2−1 ]
=6,739,164−5,451,246
1,755,486
¿6,739,164−5,451,246
1,755,486
Kendall’s Coefficient of Concordance (W) = 0.7337
The chi-square approximation of W is given in equation (3.3), which gives:
X2(n-1) = m (n – 1) W
= 3 x 57 x 0.7337 = 125.485
Therefore X2 computed = 125.485
X2 tabulated = X2(n-1) = X2
57 = 79.08
DECISION: Since X2 computed (125.485) is greater than X2 tabulated (79.08), Ho is rejected.
lxix
CONCLUSION: Therefore, there is a significant agreement among the three target groups
(contractors, consultants and clients) in respect of their responses.
CHAPTER FIVE
CONCLUSION AND RECOMMENDATION
5.0 Conclusion
The test of hypothesis revealed that there was a degree of agreement among the three target
groups with respect to their ranking of factors, Kendall’s coefficient of concordance and chi-
square was used to determine the degree of agreement. From the result of this research, the
clients were concerned with financial related issues while the contractors were more concerned
with contractual related issues and consultants considered project management issues more
important. This result is inconformity with a research done by Mezher (1998).
Construction industry is considered as an important sector in the world as it develops and
achieves the goals of society. The management of construction projects is influenced by clients,
lxx
contractors, consultants, stakeholders, national economies and others. The main aim of this thesis
is to identify the factors that influence the management of construction projects in Nigeria.
i) Also, the lack of motivation of workers is of great importance in management of
construction project in Nigeria. The result of the analysis shows that the important factors
relative to motivation of workers are a sense of belonging and identification with project
team, job security, opportunity to extend skills and experience, recognition of
contribution, opportunity to career advancement. There are two factors that can be
classified as poor indicators of motivating workers, which are exercise of power and
paying of allowance.
ii) Critical path method, Bar chart, Work breakdown structure, Cost benefit analysis are
some of the applied tools and techniques by the respondents because of their simple and
understanding nature, however lack of in-depth knowledge of this tools and techniques
still form a crucial obstacle facing construction management practice. Among the
construction management techniques and tools used in practice, CPM is the most critical
and it has the advantage of revealing critical activities of a project from start to end. This
affords good control of project activities and enhances prompt delivery of infrastructure.
iii) Thus, from the analysis two of the three factors associated with socio-political conditions
which are civil strife or riots and influence of protest action groups are of great
importance more than environmental concerns. This may be as a result of incessant
strikes by construction workers.
iv) In terms of economic policy, material and equipment availability are very important. If
there are no materials despite the availability of other resources it will result in no
progress on the project. Also, the availability of equipment assists in getting job done
quickly while lack of equipment leads to non delivery of infrastructure on time.
v) In terms of benefits, it has been observed that applying construction management tools
efficiently will help in knowing work progress, good management of resources, better
communication etc.
5.1 Recommendations:
lxxi
Based on the findings of this research work, it becomes imperative, therefore to make the
following recommendations:
i) Clients should evaluate the quality performance of contractors before awarding a
contract.
ii) All managerial levels should be participated with sensitive and important decision-
making.
iii) Continuous co-ordination and relationship between project participants are required
through project life cycle in order to solve problems and ensure success of the project.
Employees in construction industries should be more interested with belonging to work to
productivity and success of project.
iv) Consultants should be more interested with design cost by using multi criteria analysis
and choosing the most economic criteria in order to improve their performance.
v) In addition, consultants are recommended to facilitate and quicken orders delivered to
contractors to obtain better time performance and to minimize disputes and claims.
vi) Contractors should not increase the number of projects that cannot be executed
successfully. In addition, contractors should consider political and environmental risk in
their cost estimation in order to ensure success of a project.
vii) Also, contractors classified as incompetent should be identified for training. They
should be trained through workshops on the various construction methods and contract
administration. This will ensure the maintenance of a high standard of construction
projects.
viii) A proper motivation and safety systems should be established for improvement of
productivity and success of construction projects.
ix) Contractors are recommended to minimize waste rate through project implementation in
order to improve cost performance. They should be more interested with conformance to
project specification to overcome disputes.
lxxii
x) Contractors are recommended to be more interested with sequencing of work according
to schedule.
xi) Contractors should come up with a clear plan and strategy before starting a project. Early
project planning and scheduling of labour, equipment and cash, will help to ensure
success and sustainable infrastructure.
xii) In addition, contractors should have a cost engineer in their projects to control cost
successfully.
xiii) There should be proper coordination and communication among various parties
working on the project in order to improve management and a better control of the
project.
xiv) The construction industry should provide quality management guidelines and
should be enforced by the consultants on projects. Stakeholders should be committed to
quality management and adequate motivation should be given to workers.
xv) Much focus should be placed on the factors influencing construction management
practice in order to enhance better construction performance and generate confidence
within the construction industry.
xvi) It is recommended to develop human resources in the construction industry
through proper and continuous training programs about management of construction
projects. These programs can update their knowledge and can assist them to be more
familiar with construction management techniques and processes. In addition, it is
preferred to develop and improve the managerial skills of engineers in order to improve
success of construction projects. All of that can be implemented by offering effective and
efficient training courses in scheduling, time, cost, quality, safety, productivity,
information systems and management of human resources. These courses will lead to
success delivery of construction projects such as availability of resources as planned
through project duration, availability of personals with high experience and qualification,
proper quality of equipments and raw materials used in project.
lxxiii
xvii) Adequate construction management training should be given to employee in
charge of projects; this would increase the knowledge of employees about different
construction management tools and techniques available for appropriate choice. Also
construction management professionals should be employed for proper and adequate
application of construction management tools and techniques.
xviii) Clients should set aside funding that is required for the completion of the project
long before the contract is placed.
xix) Also, for sustainability of construction projects, the quality of materials used in
construction projects must not be compromised.
xx) To ensure competence of the professionals in construction industry, the Nigeria society of
Engineers (NSE), the Council for Relation of Engineering in Nigeria (COREN), the
Nigeria institute of building (NIOB), the Nigerian institute of Architects (NIA) and the
government should jointly work together.
REFERENCES
Abbasi, Y. G. & Al-Mharmah (2000) ‘Project management practice by the public sector in a developing country’ International Journal of Project Management, 18(3), pp 105-109.
Andi and Minato, T. (2003) Representing Casual Mechanism of Defective Designs: A system Approach Considering Human Errors. Journal of Construction Management and Economics, pp 21, 297 – 305.
Andawei, M. M. (2002) Motivation: An alternative to Improve workers Performance in Today’s Construction Industry. The Quantity Surveyor, 40(3), 2-6.
Arnaboldi M., Azzone G. & Savoldelli A. (2004) ‘Managing public sector project: the case of the Italian Treasury Ministry’ International Journal of Project Management, 22(3), pp 213-223.
Boyd, D. and Chinyio, E. (2006) Understanding the Construction Client. 1st Ed. London: Blackwell Publishing.
Chan, A. P. C. and Scott, D. (2004) Factors Affecting the Success of a Construction Project. Journal of Construction Engineering and Management, ASCE 130(1), 153 – 155
lxxiv
Cheung Sai On, Suen Henry C. H. and Cheung Kevin K. W. (2004) PPMS: A web-based Construction Project Performance Monitoring System, Automation in Construction, Vol. 13, pp 361 – 376
Cooke – Davies, T. (2001) The Real Success Factors on Projects. International Journal of Project Management. 20(3), 185 – 190.
Dainty, A. R. J., Cheng, M. and Moore, D. R. (2003) Redefining Performance Measures for Construction Project Managers: An Empirical Evaluation. Journal of Construction Management and Economics. 21,pp 209 – 218.
Dessler. G. (2004), Management Principles for Tomorrow Leaders, 3rd Ed. New Jersey; Pearson
Drucker, P. F. (1999), The Practice of Management. Harper and Row Publishing. New York.
Fortune, J. and White, D. (2005) Farming of Project Critical Success Factors by a System Model. International Journal of Project Management, 24(1), 53 – 65.
Frimpong Yaw, Jacob Oluwoye and Lynn Crawford, (2003), Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study, International Journal of Project Management Vol. 21, pp. 321-326.
Gahlot, P. S.(2002) Construction Planning and Management. New Age International Ltd, Ansari
Road, Daryaganj, New Delhi
Goh Bee Hua, (2005), IT barometer 2003: survey of the Singapora construction industry and a comparison of results, ITcon Vol. 10, pp.1.13.
Griffith, A. and Watson, P. (2004), Construction Management Principles and Practice, 1st Ed. New York: Palgrave Macmillan.
Hellrigel, D., Sloum, J.W. and Woodman, R.W. (2001) Organisational Behaviour. 9th Ed. Ohio: South West College Publishing.
Huczynski, A and Buchanan, D. (2007), Organizational Behaviour. 6th Ed. London: Prentice Hall
Idike, C. E. (2004), Quality Management in Construction. M.Eng. Project Report. UNN. 102 pp
Idike, C. E. & Agunwamba, J. C. (2011) “Quality Management in Construction” in O. O. Ugwu & Agunwamba, J. C. (eds) “Civil Engineering Practice and Enterprenuership” De-Adroit Innovation, 13 Annang Street, Ogui New Layout; p. 91.
lxxv
Idoro, G. I. & Patunola – Ajayi J. B. (2009) ‘Evaluating the strategies for marketing project management system in the Nigerian construction industry’, Nordic Journal of surveying and Real Estate Research. 6(2), pp. 25-36
Iyer K.C. and Jha K.N., (2005), Factors affecting cost performance: evidence from Indian construction projects, International Journal of Project Management, Vol. 23, pp. 283.295
Koo Bonsang, Fischer Martin and Kunz John, (2007), A formal identification and resequencing process for developing sequencing alternatives in CPM schedules, Automation in Construction, Vol. 17, pp.75-89
Mezher, T. M. and Tawil, W. (1998), Causes of delays in construction industry in Lebanon. Engineering Construction and Architectural Management Journal, pp. 5, 251, 60.
Moore, D., McCabe, G., Duckworth and W., Sclove, S., (2003), The Practice of Business Statistics, Freeman. NewYork
Navon Ronie, (2005), Automated project performance control of construction projects, Automation in Construction, Vol. 14, pp. 467. 476
Ndiomu, A. M. (1994) Introduction to Project Planning and Evaluation, Port Harcourt: Pam Unique Publishers.
Nitithamyong Pollaphat and Skibniewski Miroslaw J., (2004), Web-based construction management project systems: how to make them successful automation in construction. Vol. 13, pp 491 – 506.
Olaoloku, F. A. (1987) ‘The Quantity Surveyor, the second tier Foreign Exchange market and the Construction industry in Nigeria; Options and Challenges’, Construction in Nigeria. Journal of the Federation of Building and Civil Engineering Contractors in Nigeria. 4(1) 4-8
Olowo – Okere (1988), Problems of Construction management in Nigeria, Paper presented to the workshop on National Construction Policy, ASCON, Badagry – Lagos, Nigeria.
Omole, A. O. (1986) Causes of High cost of Building and Civil Engineering Construction in Nigeria. The Nigerian Quantity Surveyor. (6) 1-2
Oyedele, L. O. and Tham, K. W. (2006) Clients Assessment of Architects Performance in Building Delivering Process: Evidence from Nigeria. Building and Environment.
Patel, B. M. (2008) ‘Project Management: Strategic Financial Planning, Evaluation and Control’; New Delhi, Vikas Publishing House PVT Ltd.
Patrick, C. (2004) Construction Project Planning and Scheduling. New Jersy: Pearson, Prentice Hall.
lxxvi
Pedler, M., Burgoyne, J. and Boydell, T (2004) A Manager’s Guide to leadership. Berkshire: McGraw-Hill.
Project Management Institute (2000). A Guide to Project Management body of Knowledge. 2nd
Ed. Project Management Institute Pennsylvania. USA.
Robbins, S.P. (2001) Organisational Behaviour. 9th Ed. New Jersey: Prentice Hall.
Slack, R. & Giles, S. (1981):”Management Contracting”, in Civil Engineering Proceedings, Institution of Civil Engineers.
Sloaman, S. P. (2008) Economic and the Business Environment. 2nd Ed. London: Prentice Hall.
Smit, P. J. and Cronje, G. J. (2002), Management Principles a contemporary Edition for Africa. 3rd Ed. Cape Town
Snowdon, M. (1979)”Project Management”, in Civil Engineering Proceedings, Institution of Civil Engineers.
Thomas Ng S., Li Wentao, (2006), A parallel bargaining protocol for automated sourcing of construction suppliers, Automation in Construction Vol. 15, pp. 365 . 373
Ugwu O. O. and Haupt T. C., (2007) Key Performance Indicators And Assessment Methods for Infrastructure Sustainability- A South African Construction Industry Perspective, Building & Environment, Vol. 42, pp. 665 – 680.
Vandevoorde Stephan and Vanhoucke Mario, (2006), A comparison of different project duration forecasting methods using earned value metrics, International Journal of Project Management Vol. 24, PP.289-302
Westland, A. (2003) ‘Project Management Lifecycle’, London, Kogan Rage Limited.
Wysocki, R. K. (2009) Effective Project Management: Traditional, Agile, Extreme, 5 th Ed, Indianapolis, IN: Wiley Publishing.
Zigarmi, D., Blanchard, K. , O’Connor, M. and Edeburn, C. (2005) The leader Learning Enough About Yourself To Lead Others Within. Ne w Jersey: Pearson, Prentice Hall.
lxxvii
APPENDIX A
QUESTIONNAIRE
DEMOGRAPHIC DATA
A. ORGANIZATIONAL.
1) In what organization do you work?
Private sector Public sector
2) Location of project:…………………………………………………………………………
3) Organization name:…………………...…………………………………………………….
4) Please indicate the actual number of years your organization has been involved in construction works…………………………….……………………………………………………
B. PERSONAL
5) Please indicate your gender.
Male Female
6) Please indicate your age:
Under 25 years 41 – 50 years
25 – 30 years Over 50 years
31 – 40 years
7) Please indicate your highest degree in education:
lxxviii
NATIONAL DIPLOMA HONOURS DEGREEHIGHER NATIONAL DIPLOMA MASTERS DEGREEPOSTGRADUATE DIPLOMA DOCTORAL DEGREEB. Eng / Bsc OTHER (PLS SPECIFY)B.Tech OTHER (PLS SPECIFY)8) Kindly indicate from below the category of construction profession you belong to:
CLIENT CONTRACTOR CONSULTANT9) Please indicate your status in the organization:
Managing Director Senior StaffDirector SupervisorManager TraineeOther (Pls specify)10) Please indicate your actual years of experience in the construction sector.
……………………………………………………………………………………………………
MAIN QUESTIONNAIRE
11) Below are the numbers of factors influencing construction management practice. From your experience, please express your opinion on the importance of the following factors as it influences construction management in Nigeria. (Please tick the appropriate box).
CATEGORY / FACTORS NO EXTENT
MODERATE EXTENT
MEDIUM EXTENT
LARGE EXTENT
VERY LARGE
EXTENT
QUALITY MANAGEMENT DURING DESIGN
Conflicting design information
Timeliness of revised drawing issue
Missing information
Dimensional inaccuracies
QUALITY MANAGEMENT DURING CONSTRUCTION
Analysis of construction methods
Forecasted planning date such as activity duration and resource quantities required
Monitoring and updating of plans to appropriately reflect work status
Work sequencing to achieve and maintain workflow
lxxix
Effective co – ordination of resources
Inspection of construction
Development of an appropriate organization structure to maintain workflow
CONSTRUCTION MANAGEMENT TECHNIQUES USED IN PRACTICE
Work Breakdown Structure
Gnatt chart
PRINCE 2
Critical Path Method
Programme Evaluation & Review Technique
Project Sensitivity Analysis
Cost Benefit Analysis
Graphical Evaluation & Review Technique
Line of balance
ECONOMIC POLICY
Equipment availability
Materials availability
Indirect impact of interest rates
Bankruptcy
Supervision / management staff availability
MANAGEMENT STYLE
Providing specific direction
Setting specific goals people are to achieve
Setting time lines
Seeking peoples opinion
Involving team members
Provide support and encouragement
Organizing work situation for people
lxxx
Conducting regular updates on progress
SOCIO-POLITICAL CONSIDERATIONS
Civil strife or riots.
Influence of protest action-groups
Disruption due to environmental concerns
MOTIVATION OF STAFF
Pay and allowances.
Job security.
A sense of belonging and identification with the project team.
Recognition of contribution
Opportunity for extending skills and experience through learning as a means of job satisfaction and higher productivity.Equitable reward relative to others input to the project
Exercise of power.
Opportunity to career advancement for future benefit
OBSTACLES FACING CONSTRUCTION MANAGEMENT PRACTICE
Lack of professional training
Lack of construction management knowledge
Bribery and corruption
Lack of leadership commitment
Incessant change of authority
Rigid organization structure
BENEFITS OF APPLYING CONSTRUCTION MANAGEMENT TOOLS
Better communication
Good management of resources
Known work progress
Defined goals and objectives
Better quality
lxxxi
Better work organization
Better time utilization
The Practices concerned with Construction Management:1. The time management practice: Please add () as appropriate: a. What kind of method do you use to represent the project planning and scheduling? Bar chart method Critical path method S-Curve method Othersb. How often does your project team formally meet for discussion of monitoring? Updating and controlling the progress? Daily Weekly Monthly Noc. How often do you coordinate your schedule with master schedule of the project? Daily Weekly Monthly Nod. How often do you require the sub-contractors or supplier to submit their detail activities schedule for you in advance to adjust your actual schedule? Daily Weekly Monthly Noe. How do you supply the incentive system to stimulate the construction time? Salary increase Bonus in position Training Othersf. Which software do you apply for planning and scheduling the progress the Project? Primavera Microsoft project Excel sheet Nog. Do your company formally participate in the pre-project planning effort? Yes, as the pre – project planner Yes, as the consultant No
2. The cost management practice: Please add () as appropriate: a. Do you have the cost schedule associated with the estimated time schedule? Yes No Sometimesb. Do you apply the actual value and earned value concept in controlling cost for the project? Yes No Sometimesc. Do you have a cost engineer who is only responsible for dealing with cost control? Yes No Sometimesd. Do you apply any software to plan, monitor, and control cost? Yes No SometimesIf yes, what is the name of software program? ..........
3. The safety management practice: Please add () as appropriate: a. To what extent has an overall project safety factors been implemented? Not at all Moderately Extensivelyb. How often do you organize the meeting for safety issue? None Monthly Weekly Daily c. To what extent is pre-task planning for safety conducted by contractor foremen or other site managers? Not at all Moderately Extensively
lxxxii