oak street project summary - phoenix, arizona · 2018-03-15 · st87600121 ahur oak st: 3 rd st –...
TRANSCRIPT
ST87600121
AHUR Oak St: 3rd St – Grand Canal Bike Improvement Project
Project Summary
This project will include the following improvements by segment:
3rd St to 7th St: The Alternative 1 was chosen for this section. It will include a sign
removal, additional signs installed to include way-finding, bike lane signs and no parking
signs. Removal of existing striping, the addition of yellow, white and green thermoplastic
and traffic delineators. Lighting improvements will include a conductor, electrical
conduit, pull box, light poles, mast arms, LED heads, and removal and salvage of existing
poles. This section also includes drought tolerant landscape improvements on the south
side and micro-surfacing. This section has been changed from a cycle track to bike lanes
on both sides of the street with 8 feet of parking on the north side unless chicanes can be
installed in this section to alternate street side parking. Install crosswalks and stop bars at
all intersecting cross-streets. Include a turn lane bicycle box at the 3rd Street intersection.
Keep west approaching bike lane on south side, modify hawk crossing and northbound
stop bar to accommodate a new crosswalk on the south side of the intersection to
accommodate eastbound bicycle travel, install green paint on south side adjacent to
intersection on west and east approaches in conflict zones.
7th St Intersection: The Alternative 1 for the intersection was chosen. It will include an
addition of 4 ped push buttons requested on each of the corners of the 7th Street
intersection. There will be a sign removal, sign installations at HAWK for better bike
safety, stamped asphalt across 7th street, removal of existing striping, pavement marking
added and green thermoplastic. Existing HAWK will remain but be modified for bicycle
use with push buttons that the rider does not need to dismount for.
7th St to 10th St: The Alternative 1 was chosen for this section. Improvements include
bike lanes, green paint in conflict zones on south side of street east of 7th Street
intersection, add crosswalk. Remove existing 5 foot sidewalk on the south side and
replace with an 8 foot sidewalk, include ADA ramps if needed. There will also be a sign
removal, sign installation, removal of existing striping, white, yellow and green
thermoplastic as well as pavement markings being added and traffic delineators. Lighting
improvements will include conductors, electrical conduit, pull boxes, light poles, mast
arms, LED, landscape improvements on the south side will be replaced in kind and
micro-surfacing. The proposed section consists of two 10ft traffic lanes, two 6ft bike
lanes and 7ft parking lanes on the north and south side. Sidewalk ramp bump-outs will
be considered for installation between Richland Street and 9th Street per the conceptual
exhibit below.
10th St to Dayton St: The Alternative 2B was chosen for this section. Improvements will
include bike lanes, a typical street widening, paving, sidewalk, ADA ramps, sign removal
and sign installation. Other improvements include white and yellow thermoplastic,
pavement markings, and lighting improvements of conductor, electrical conduit, pull
boxes, light poles, mast arms, LED’s, removal and salvage of existing poles, low impact
drainage and landscape improvements. The proposed section consists of two 10ft traffic
lanes, two 6ft bike lanes and parking lanes on the south side.
Dayton St to 12th St: The Alternative 1 was chosen for this section. Improvements will
include bike lanes, sign removal, sign installations, new splitter island at the 12th street
traffic circle intersection, stamped asphalt crosswalks at all four legs of the intersection,
removal of existing striping, white and yellow thermoplastic, and pavement markings.
Lighting improvements include a conductor, electrical conduit, pull boxes, light poles,
mast arms, LED’s, remove and salvage existing poles as well as micro-surfacing,
crosswalks and stop bars at all cross-street intersections. Remove parking on the south
side in this section. The proposed section consists of two 10ft traffic lanes, two 6ft bike
lanes and 8ft parking lanes on the north side. Chicanes will be explored to split off-street
parking between the north and south side of the street.
12th St – 14th St: The Alternative 1 was chosen for this section. Improvements will
include bike lanes, sign removal, sign installation, removal of existing striping, white and
yellow thermoplastic, and pavement markings. Lighting improvements include
conductors, electrical conduit, pull boxes, light poles, mast arms, LED’s, remove and
salvage existing poles and micro-surfacing as well. This section removes the parking on
the south side and installs crosswalks and stop bars at all cross-street intersections. The
proposed section consists of two 10ft traffic lanes, two 6ft bike lanes and 8ft parking
lanes on the north side. Chicanes will be explored to split off-street parking between the
north and south side of the street.
14th St Intersection: The Alternative 1 was chosen from this section. Improvements
apply four-way stop signs and traffic calming speed table at the intersection, ADA ramps,
sign removal, sign installations, stamped asphalt, pavement markings, asphalt concrete
and concrete pavement milling and drainage items impacted by the speed table.
14th St – 15th St: The Alternative 2A was chosen for this section. Improvements will
include bike lanes, asphalt concrete pavement milling, sign removal, sign installation,
stamped asphalt pattern in the middle of Oak street, and pavement markings for shared
use lanes. Lighting improvements will include a conductor, electrical conduit, pull boxes,
illuminated bollards, removal and salvage of existing poles and low maintenance
landscape improvements on both sides of the road. Proposed 14ft of pavement for this
section. Low impact drainage improvements such as bio-swales. Parking will be
restricted on both sides of the road.
15th St – 16th St: The Alternative 2A was chosen for this section. Improvements will
include bike lanes, asphalt concrete pavement milling, ADA ramps, curb, gutter, sign
removal, sign installation, stamped asphalt pattern in the middle of Oak street, and
pavement markings for shared use lanes. Lighting improvements will include a
conductor, electrical conduit, pull boxes, removal and salvage of existing poles and low
maintenance landscape improvements on both sides of the road. Low impact drainage
improvements such as bio-swales. Parking will be restricted on both sides of the road.
Proposed two 12ft shared-use lanes of pavement for this section. Add push button for
cyclists crossing 16th Street so the rider does not need to dismount before crossing.
16th – 18th St: The Alternative 1 was chosen for this section. Improvements will include
bike lanes, sign removal, sign installation, removal of existing striping, white and yellow,
green thermoplastic, and pavement markings. Lighting improvements will include a
conductor, electrical conduit, pull boxes, removal and salvage of existing poles and
micro-surfacing. Speeding is an issue in this segment, chicanes should be a strong
consideration to preserve parking in front of multi-family units and to slow speeds. If
chicanes are not used parking should be restricted to the south side of the road only. The
proposed section consists of two 10ft traffic lanes, two 6ft bike lanes and 8ft parking
lanes on the north side.
18th – 20th St: The Alternative 1 was chosen for this section. No cycle track, bike lanes
will be on both sides of the street. Improvements will include sign removal, sign
installation, removal of existing striping, white, yellow and green thermoplastic, and
pavement markings along with flexible traffic delineators. Lighting improvements will
include a conductor, electrical conduit, pull boxes, removal and salvage of existing poles
and micro-surfacing. Speeding is an issue in this segment, chicanes should be a strong
consideration to preserve parking in front of multi-family units and to slow speeds. Add
crosswalks and stop bars at cross-street intersections. The proposed section consists of
two 10ft traffic lanes, two 6ft bike lanes and 8ft parking lanes on the north side.
Oak St and 20th St Intersection: The Alternative 1 was chosen for this section. The
improvements apply two-way stop signs and traffic calming speed table. Other
improvements include ADA ramps, sign removal, sign installations, stamped asphalt
crosswalks, pavement markings, asphalt concrete, asphalt concrete pavement milling,
bike lanes and drainage items impacted by speed table.
20th Pl: Oak St to Thomas Rd: The Alternative 2 was chosen for this section.
Improvements will include a proposed 20th Place section between Oak Street and
Sheridan Street is a 10ft two-way cycle track, a 2ft buffer and a 12ft one-way traffic lane,
ADA ramps, sign removal, sign installation, white, yellow and green thermoplastic, and
pavement markings along with flexible traffic delineators. Lighting improvements will
include a conductor, electrical conduit, pull boxes, removal and salvage of existing poles
and micro-surfacing. Parking will be restricted on both sides.
20th St & Thomas Rd Intersection: The Alternative 1 was chosen for this section. The
N/E and S/E corners will have an RFB, expand the triangle to reduce lanes to one, for the
N/E corner convert to a multi-use path with striping. There will be a reduction of one
free-flow right turn lane, install RFB, may need to coordinate with ADOT. Other
improvements include sign removal, sign installation, white, and yellow thermoplastic,
pavement markings and micro-surfacing. Restripe the existing free right turn on the
southeast corner of the intersection to provide one free right turn lane rather than two.
Thomas Rd to Grand Canal: The Alternative 1 was chosen for this section. Potential
coordination with ADOT may be needed. The section will have two-way multi-use
paths, 10ft cycle track, 3ft buffer and two 16ft traffic lanes, bollards between Greenfield
Rd and the Grand Canal. Coordination will be required with ADOT and the lane width
north of Greenfield Road will be reduced. Other improvements will include sidewalk
removal, ADA ramps, sign removal, stamped asphalt crosswalks, removal of existing
striping, sign installation, white, yellow and green thermoplastic, and pavement markings
along with flexible traffic delineators. Lighting improvements will include a conductor,
electrical conduit, pull boxes, and micro-surfacing.