b Overview and Scrutiny Committee 29 January 2013 NORTHERN LINE EXTENSION – TECHNICAL UPDATE Stockwell, Oval and Princes Wards Report authorised by: Executive Director, Housing, Regeneration & Environment: Sue Foster Executive summary In March 2012 Cabinet gave approval in principle to the Northern Line Extension (NLE) proposals including the route alignment, the location of a new station on Wandsworth Road, the location of permanent shafts and the location of a temporary shaft required during the construction period subject to; (1) all the concerns raised by residents at this meeting being considered. (2) Cabinet responding to the clear appetite for further active engagement and consultation with residents. At the meeting the Executive Director of HRE undertook to report back to Cabinet on technical issues related to the NLE and specifically on those concerns raised over noise. In response to concerns raised the scheme design and the potential impacts on Lambeth residents a technical consultant, Ramboll, was engaged to undertake a technical assessment of the NLE design and to advise the Council on any matters arising. This report provides an update on how the NLE design work being undertaken by Transport for London (TfL) has progressed since April and the outcomes of the technical assessment undertaken by Ramboll. Summary of financial implications This is status report and there are no specific financial implications arising from the recommendations. This report does not commit the council to funding the NLE. Recommendations (1) To note the content of this report.

Upload: others

Post on 10-Mar-2020

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

b

Overview and Scrutiny Committee 29 January 2013

NORTHERN LINE EXTENSION – TECHNICAL UPDATE Stockwell, Oval and Princes Wards

Report authorised by: Executive Director, Housing, Regeneration & Environment: Sue Foster

Executive summary

In March 2012 Cabinet gave approval in principle to the Northern Line Extension (NLE) proposals including the route alignment, the location of a new station on Wandsworth Road, the location of permanent shafts and the location of a temporary shaft required during the construction period subject to; (1) all the concerns raised by residents at this meeting being

considered. (2) Cabinet responding to the clear appetite for further active

engagement and consultation with residents. At the meeting the Executive Director of HRE undertook to report back to Cabinet on technical issues related to the NLE and specifically on those concerns raised over noise. In response to concerns raised the scheme design and the potential impacts on Lambeth residents a technical consultant, Ramboll, was engaged to undertake a technical assessment of the NLE design and to advise the Council on any matters arising. This report provides an update on how the NLE design work being undertaken by Transport for London (TfL) has progressed since April and the outcomes of the technical assessment undertaken by Ramboll. Summary of financial implications

This is status report and there are no specific financial implications arising from the recommendations. This report does not commit the council to funding the NLE. Recommendations

(1) To note the content of this report.

Page 2: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

Consultation

Name of consultee

Department or Organisation Date sent Date response received

Comments appear in report para:

Internal

Sue Foster Executive Director HRE 16/01/13 17/01/13

Michael O’Hora Governance and Democracy 11/01/13 11/01/13 4.1

Hamant Bharadia Department Finance Officer 06/12/12 15/01/13 3.1 & 3.2

Sandra Roebuck Regeneration 08/01/13

Carolyn Dwyer Divisional Director Public Realm 02/01/13

Frank Higgins Corporate Finance 15/01/13 16/01/13

Elena Nicolau Governance and Democracy 17/01/13 17/01/13

Councillor Peck Leader of the Council 13/01/13 18/01/13

Councillor Robbins Cabinet Member for Housing & Regeneration

13/01/13

Councillor Walker Cabinet Member for Environment and Sustainability

13/01/13

Report history

Date report drafted: Report deadline: Date report sent: Report no.:

XX.XX.12 XX.XX.12 XX.XX.12 217/10-11

Report author and contact for queries:

William Howe, Senior Transport Planner

020 7926 0190 [email protected]

Background documents

• Northern Line Extension Report Cabinet (16.01.12 - report 245/11-12)

• Overview and Scrutiny Committee Minutes (09.02.12)

• Northern Line Extension to Battersea: Independent Technical Review - Ramboll Appendices

Appendix 1 – Kennington Park Shaft technical note Appendix 2 – Minutes from Resident and Stakeholder Technical Engagement meeting, September 16th 2012 Appendix 3 – Minutes from Resident and Stakeholder Technical Engagement meeting, December 4th 2012

Page 3: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

Northern Line Extension – Technical Update

1. Context

1.1 In March 2012 Cabinet gave in principle approval for the NLE project including the route alignment, location of a new station on Wandsworth Road and the location of permanent and temporary shafts. At that time stakeholders raised concerns that the Council had not provided the appropriate amount of scrutiny to the proposals and that there had been a lack of consultation and communication with residents both from TfL and the Council.

1.2 In response to this Ramboll who are a multi-disciplinary engineering consultancy with experience of major tunnelling projects were engaged to act as technical consultants in respect of the NLE and tasked with undertaking a full review of the scheme proposals and to advise the Council on the potential impacts of the scheme both during the construction and operation of the NLE.

2. Proposals and reasons

2.1 The case for the NLE

The need for the NLE is development led, with significant additional transport capacity being required to accommodate the additional trips that will be generated by all developments in the Vauxhall Nine Elms Battersea (VNEB) Opportunity Area (OA) . The NLE has been identified by TfL as the only viable option that will provide enough public transport capacity in the long term to accommodate the scale of development proposed for the VNEB OA. The Planning Framework concludes that in order to enable and support this development a package of strategic transport measures, supported by a series of more local transport improvements will be required to support growth and development of the OA. These include:

• An optimum package of bus service enhancements including the introduction or extension of bus routes;

• An extension to the Northern -Line, from Kennington to Battersea Power Station, with an intermediate stop in the Nine Elms area;

• Improvements to the National Rail, Underground stations and interchange facilities at Vauxhall and Battersea Park stations;

• A step change in the walking and cycle environment both within and to/from the OA and ensuring improved legibility and connections;

• An approach to development which reduces the need to travel by car/reduces the number of private vehicle trips within the OA;

• Improving conditions for taxis, coaches, freight and river services within and to/from the OA; and

Page 4: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

• Private investment to enable these improvements to be secured and delivered in line with the future development of the area.

The Council has always stated that a wider transport strategy, with a significant emphasis on bus improvements, is required and that this would link the new developments to existing residents and businesses in Lambeth. Such improvements formed a key part of the Council’s initial support for the NLE.

2.2 NLE Reference Design Review

Ramboll have undertaken a full assessment of the NLE Reference Design produced by Halcrow, who are TfL’s consultants for the NLE, in order to confirm that all relevant work has been undertaken and that design methodologies are in line with industry best practice.

The detailed outcomes of this are contained within Ramboll’s report which is included as a background paper to this report but the headline issues are set out below.

2.3 Working with residents and other stakeholders.

In response to Cabinet recommendations and concerns from residents about the impact of the NLE officers in conjunction with Ramboll have worked with residents and stakeholders to ensure that their views and concerns are appropriately considered and addressed. There has also been regular dialogue with TfL officers and their consultants to ensure that any impacts on Lambeth are minimised with appropriate mitigation measures put in place.

A public meeting chaired by Valerie Shawcross AM was held on Tuesday 16th September 2012 which was attended by 80 members of the public who were given the opportunity to give their opinions and to raise any concerns. All issues were compiled and circulated in the form of a meeting note, contained in Appendix B, with an undertaking from the Council given to investigate all issues and to report back at a later date once answers were known. A follow-up meeting was held on Tuesday 4th December 2012 where an update on these issues was given and a further opportunity for stakeholders to discuss outstanding issues was provided. Both meetings were attended by Councillor Lib Peck.Ramboll’s findings were published in a report on 24 December which was circulated to residents and stakeholders that had taken part and is available on our website. Ramboll were commissioned so that the Council can ensure that it makes the best possible representations and the impact of the Northern Line Extension is mitigated as much as possible for Lambeth residents.

On 30th December 2012 TfL completed their second round of consultation on the updated proposals with 40,000 leaflets distributed to affected properties along the proposed route and holding a series of public exhibitions held offering stakeholders the chance to raise any concerns and put their views forward.

2.4 Noise and Vibration

Page 5: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

Significant concerns were expressed by a number of stakeholders that the potential noise and vibration impacts of the NLE had not been fully assessed by either TfL or the Council and that significant further work should be undertaken on this issue before any decision on the TWAO was made. These concerns related to both the impacts during the construction period as well as once the NLE is operational.

Ramboll were instructed to focus significant attention on this area and have undertaken a thorough assessment of this element of the scheme. The detailed outcomes of this are contained within Ramboll’s report contained in appendix 2 but the headline findings are;

• The work completed to date is in accordance with current best practice and working methods and has been progressed to an appropriate stage;

• There is still significant work outstanding that should be completed as part of the Environmental Statement for the TWAO application;

• There are a range of mitigation measures available to the scheme designers to reduce nose levels but until further assessment of groundbourne noise is undertaken as part of the further detailed assessment currently being undertaken it is not possible to identify which would be required/most appropriate;

• TfL’s adopted design standard of 35dB LAmax,F is an improvement over previous standards and in Ramboll’s experience this is acceptable to most people but a lower level of 30dB is preferable.

2.5 Design Progression and Alterations

Since in principle approval was given in March 2012 the scheme design has evolved with the most significant change being that TfL have now confirmed that the proposed permanent shaft in the vicinity of Claylands Green / Cottingham Road is longer no required and has therefore been removed from the proposals. This represents a significant victory for the local residents and notably The Claylands Green Action Group who have been campaigning against this element of the scheme since the proposals were first set out.

However, it should be noted that this change has required that the diameter of the tunnel along this section of the route to be increased to allow for a trackside walkway to be introduced and also that some of the plant proposed for this shaft will now be located in the proposed Kennington Park Lodge shaft instead. Officers have requested that TfL thoroughly investigate the knock-on impacts of these changes to ensure that problems are not merely transferred from one area to another; particular concern on this has been raised by the Kennington Park Neighbourhood Action Group (KPNAG) who are concerned that the removal of the Claylands Green shaft will mean larger, noisier fans being required in the Kennington Park shaft. KPNAG object to the use of the Kennington Park Lodge

Page 6: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

as a vent site in principle and have proposed an alternative site in the existing Kennington Park service yard which they consider would have less of an impact on residents living in close proximity to the lodge site. These proposals have been submitted to TfL for consideration but it is officers’ understanding that TfL do not support them primarily due to the increased distance of the shaft form Kennington Station and logistical problems over access during construction. A separate note on this issue is provided in appendix 1.

Another significant change in the design since March 2012 has been the removal of the proposed cross-over to the immediate east of the new Nine Elms station which as been determined by TfL as being surplus to requirements. The removal of this will reduce disruption during construction and by removing the need for multiple sets of points to enable trains to cross between the tracks will reduce noise and vibration levels.

2.6 Impact on existing Northern Line and Kennington Station

Concerns have been raised related to the potential impacts of the NLE on the existing Northern Line, which already experiences significant congestion and overcrowding at peak times, with some stakeholders unclear as to what level of assessment has been undertaken to ensure that the additional numbers of passengers entering the network at Battersea Power Station (BPS) or the intermediate station at Nine Elms can be accommodated. The question of whether the constrained internal layout of Kennington Station will be suitable to cater for the potential numbers of passengers wanting to interchange between the Charing Cross and Bank branches of the Northern Line has also been raised.

To assess these concerns TfL have already undertaken the first stage of modelling the expected usage patterns of the NLE and its connections to the existing network and whilst it is too early to draw any firm conclusions from this TfL are at this stage satisfied that the integration of the NLE in to the wider network would not have any significant impact. Council officers have requested that further assessment of the potential impacts on Kennington Station are undertaken prior to submission of the TWAO to ensure that there would not be no adverse impact on its safe operation.

2.7 Implications

The extension is part of a major package of works which will complete the obligations of the Vauxhall, Nine Elms & Battersea Opportunity Area Planning Framework. This is a developer led project which will allow the development of the Battersea Power Station site, as well as developments in the Vauxhall and Nine Elms areas. The station at Nine Elms is critical to provide benefit to Lambeth, and would assist in the regeneration of a part of Lambeth in need, as well as potentially easing pressure on the transport network in the Vauxhall area. The station would also allow greater benefit to accrue from the redevelopment sites of Banham’s and Sainsbury’s in the Nine Elms area.

Page 7: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

The extension from the Kennington Loop to Battersea would preclude any alternative extension of the Northern Line to areas such as Brixton and/or Streatham, although TfL have stated their opposition to any extension to Streatham on the basis of cost, no plausible external funding being available, and the ensuing overcrowding on the current Northern Line.

3. Finance Comments

3.1 This is a status report and there are no specific financial implications arising from the recommendations.

3.2 This report does not commit the council to funding the NLE.

4. Comments from Director of Governance and Democracy

4.1 There are no legal matters arising from the contents of this report.

5. Results of consultation

5.1 In response to Cabinet recommendations officers in conjunction with Ramboll have sought to engage with stakeholders to ensure that their views and concerns are appropriately considered and addressed. There has also been regular dialogue with TfL officers and their consultants to ensure that any impacts on Lambeth are minimised with appropriate mitigation measures put in place.

5.2 A public meeting chaired by Valerie Shawcross AM was held on Tuesday 16th September 2012 which was attended by 80 members of the public who were given the opportunity to give their opinions and to raise any concerns. All issues were compiled and circulated in the form of a meeting note, contained in appendix 2, with an undertaking from the Council given to investigate all issues and to report back at a later date once answers were known. A follow-up meeting is planned for Tuesday 4th December 2012 where an update on these issues will be given and to provide an opportunity for stakeholders to discuss outstanding issues, the note from this meeting is contained in appendix 3.

5.3 A second round of consultation by TfL on the updated proposals closed on the 30th December 2012 with 40,000 leaflets distributed to affected properties along the proposed route and with a series of public exhibitions held that offered stakeholders the chance to raise any concerns and put their views forward.

6. Organisational implications

6.1 Risk management: Potential risks include the developers not being able to bridge the funding gap and asking for contributions. This is especially relevant if work has already started when funding runs out, which could leave construction having started including the loss of public open space, and the loss of development across the Opportunity Area.

6.2 Equalities impact assessment:

Page 8: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

Both new stations on the extension will be fully accessible stations, and the station at Nine Elms will massively improve Public Transport accessibility to a relatively deprived area.

6.3 Community safety implications:

None.

6.4 Environmental implications: The extension would be expected to improve air quality through the reduction in car journeys. There would be temporary negative effects during construction relating to increased lorry journeys and noise effects from the tunnel boring, but these are expected to be minimal and only for a short duration. There will be a temporary loss of public open space during construction, but public open space is expected to be replaced and enhanced after the construction period.

6.5 Staffing and accommodation implications: None

6.6 Any other implications: None

7. Timetable for implementation

7.1 TfL is aiming for a Transport and Works Act Order submission in April 2013. The extension has a target opening of 2018

__________________________

Page 9: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

Appendix 1 Kennington Park Shaft - Technical Note 1. Context

1.1 In March 2012 the Council gave in principle approval of the proposed Northern

Line Extension (NLE); this included the route alignment, new station site and the location of permanent and temporary shafts.

1.2 The above plan shows the northern end of Kennington Park with the black circle indicating the general location of the above ground structure of the proposed shaft. Currently this site is occupied by the park keeper’s lodge building and some temporary structures which house a community bee keeping project. Whilst Cabinet approval was granted for the use of this site for a shaft it is contingent on TfL submitting a high quality design to mitigate its visual and environmental impact.

1.3 Given its location adjacent to a listed park it is imperative that the appearance of

the shaft structure is of a high quality reflecting its surroundings and to this end TfL have been in discussion with the Council’s Design & Conservation team. The design is still being developed and TfL have confirmed that they will shortly be holding a meeting with local stakeholders to get their views.

Page 10: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

1.4 In addition to the visual impact of the shaft TfL will have to demonstrate as part of the Transport and Works Act Order (TWAO) submission that all potential environmental impacts from the shaft such as noise and air quality have been appropriately mitigated. The Council’s technical consultants Ramboll will make an assessment of these proposals and advise on their acceptability.

2. Kennington Park Neighbourhood Action Group (KPNAG) 2.1 Both the Council and TfL have had representations made to them specifically in

relation to the Kennington Park shaft from KPNAG who are opposed to the shaft location as they consider that it will have a negative impact on their members both visually and environmentally. KPNAG have developed proposals for an alternative shaft location within the service yard of Kennington Park and these have been submitted to TfL for consideration.

2.2 TfL has responded that they do not consider that this alternative site is

acceptable due to both its distance from Kennington Station and concerns over vehicular access. This view has been conveyed to KPNAG but they do not accept this and have requested that TfL re-examine all available options with a view to removing the shaft from the lodge site. Ramboll have also assessed the KPNAG alternative shaft site and have reported that other than the issues raised by TfL they consider that there are no in principle reasons to exclude the service yard site from further consideration.

2.3 As can be seen on the above plan the boundary between Lambeth and

Southwark runs immediately around the north-eastern boundary of Kennington Park meaning that the properties in closest proximity to the proposed shaft are within Southwark. The full membership of KPNAG is not known to officers but it is understood that the majority of their membership are Southwark residents from Kennington Park Place and St Agnes Place.

2.4 At a recent public meeting on 4th December where the NLE was debated

members of KPNAG requested Valerie Shawcross AM to assist them in discussions with Southwark Council with whom they felt frustration over their perceived lack of action on the NLE proposals so far. Valerie Shawcross AM agreed to facilitate a meeting between KPNAG and relevant Southwark representatives including councillors.

3. Friends of Kennington Park 3.1 The Friends of Kennington Park have been consulted by TfL and the council over

the use of the park keeper’s lodge site and have confirmed their full support of these proposals. KPNAG have liaised with them directly over their proposals for the alternative site within the park’s service yard but the Friends have stated to both KPNAG and the council that they do not support this option and have urged the council to continue in supporting the park keeper’s lodge site.

4. Summary 4.1 Officers are continuing to work with TfL to negotiate a solution that will mitigate

design and environmental concerns, and which will also improve this neglected

Page 11: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

corner of the park. TfL are keen to agree outline designs for the shaft and a list of conditions relating to planning issues with the council in advance of making the TWAO submission. Officers will ensure that all relevant issues are covered.

Page 12: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

Appendix 2 – Covering Letter & Minutes from 16th September 2012 public meeting

28th September 2012

Dear resident,

Thank you for attending the recent meeting on the Northern Line Extension chaired by Val Shawcross

Assembly Member for Lambeth and Southwark. We know that residents have concerns about the effect

of the Northern Line Extension. We have listened to those concerns and that is why we have

commissioned engineering consultants Ramboll to carry out a review of Transport for London’s design

work on the Northern Line Extension. As explained at the meeting, this work will be carried out during

the autumn and we will feedback to you throughout this process. It was very helpful to hear all your

concerns and views. Please find enclosed our notes from this meeting, these are intended to capture the

issues raised and we will now be working through these.

Noise, vibration, shaft locations and construction methodology were clearly the main concerns. Transport

for London are planning to hold drop in events in November to help inform residents about the temporary

shaft proposed at Radcot Street and Harmsworth Street. We will ensure that dates are circulated to you as

soon as we have them.

One of the issues of immediate concern is the option to locate a shaft at Claylands Green, we understand

that Transport for London are due to make announcement in the coming weeks and we have written to

them to make clear that using this location is unacceptable.

We have commissioned Ramboll so we can ensure that we make the best possible representations and that

the impact of the Northern Line Extension is mitigated as much as possible for Lambeth residents. With

the majority of the extension lying in Lambeth, we want to minimise disruption for our communities. If

you have any queries relating to this work then please contact my colleague William Howe, Senior

Transport Planner, Lambeth Council on 020 7926 0190 or email [email protected] .

Best wishes,

Cllr Lib Peck

Cabinet Member for Regeneration and Strategic Housing

[email protected]

Page 13: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

Northern line Extension

Resident and Stakeholder Technical Engagement Meeting

Chaired by Val Shawcross CBE London Assembly Member for Lambeth and Southwark

Monday 10 September 2012

18:00 – 21:00 Ashmole Tenants’ Hall, Meadow Road, SW8 1AA

Attendees

Val Shawcross AM (Chair) – London Assembly Member for Lambeth & Southwark

Cllr Lib Peck – Cabinet Member for Regeneration and Strategic Housing

Lambeth Council officers – Abu Barkatoolah - Head of Transportation

Rob Heslop – Transport Planning Manager

William Howe – Senior Transport Planner

Ramboll – Matthew Garner - Associate

Ray Browne - Associate

Max Elliott – Senior Engineer

Residents and community groups

Purpose of the meeting

Transport for London has continued to develop the Northern Line Extension scheme design. Lambeth Council

know that residents have concerns about the affect of the Northern Line Extension. We have listened to those

concerns and that is why we have commissioned engineering consultants Ramboll to carry out a review of

Transport for London’s design work. This is to ensure that Lambeth secures the best possible outcome with

minimum disruption on its residents and businesses. The aim of this meeting was to offer a forum for all

stakeholders who may be affected by the NLE to raise their concerns and queries on the design and

construction work so that this can form part of Ramboll’s work.

Issues were addressed by location:

1. Radcot Street/Ravensdon Street temporary Shafts

2. Kennington Park / Kennington Green / Claylands Road shafts

3. Nine Elms Station

4. General queries – apply across the Northern Line Extension area

Issues raised, discussion points and actions from the meeting are listed under each of these headings.

1. Radcot Street / Ravensdon Street Temporary Shaft

Issues raised by residents/community

• Location of shaft

• Parking

• Traffic

Page 14: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

• Properties adjacent to shaft and the affect on them.

• Noise and vibration currently, during construction and in the long term once the Northern Line Extension

is complete.

• Truck movements during construction

• Trucks movements and safety for cyclists

• Trains into and out of Kennington , will there be more overcrowding, congestion what is the capacity on

the Northern Line

• Air quality

• Need to make sure that residents are kept informed/communicated with.

Discussion

• Location of shaft may not be fixed until the planning process – Ramboll advised that this will need a

review of further information such as location of electricity cables, gas and water pipes and other buried

services.

• Concern that the timeframe has not been clearly communicated to residents

• Construction Management – need to ensure that this is written into the planning conditions.

• Radcot Street will be closed during construction, this will mean loss of parking, will additional spaces be

provided?

• Closing streets for construction will have an impact on traffic flow , the streets are narrow .

• Boundary with London Borough of Southwark is close so there will be cross border issues to consider.

These should not be ignored.

• Parking for contractors, need to have agreement for construction staff (can they park elsewhere? Former

bottling plant at Distillery (owned but Tesco?) could be used for parking?)

• Dust / pollution will be controlled but needs to be a condition in the construction management plan

Actions

• Ramboll will advise on what needs to go into Construction Management Plan

• Need real-time hotline to contact contractors

• Hours of working to be controlled. Where 24 hour working is essential for certain elements this should be

agreed with the Council and then clearly communicated to residents in advance.

2: Kennington Park / Kennington Green / Claylands Road shafts

Issues raised by residents/community

• Noise / shafts

• Capacity and demand

• Kennington Park - impact during construction - noise

• Consultation needed with ‘Friends of Kennington Park’

• Technology to reduce noise above minimum standards

• Process, are there alternatives to green spaces

• Disruption of Park shaft

• Budget for landscaping

• Bees at Kennington Park

• Closure of streets / traffic flow / resident communication

• Monitoring – costs resources

• Timescales

• Air quality from shafts

• Is the route of the new tunnel decided or are there still potential for changes?

Kennington Park – issues, discussion and actions

• Friends of Kennington Park are happy with the use of the Lodge

• Construction will use dog walking area, where will alternative facilities be provided?

Page 15: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

• Query about noise and air quality of shaft

• TfL and Lambeth Council should consult Friends of Kennington Park on the Construction Management

Plan

• Will there be a temporary arrangement for beekeeping provided during the construction period?

• Can Lambeth Council confirm that current users will not be impacted during construction and what will

happen to them in the longer term?

Kennington Green - issues, discussion and actions

• Can the Beefeater Distillery site be used for the permanent shaft location rather than Kennington Green.

• Can TfL retain trees and preserve the green, residents want trees protected.

Claylands Green - issues, discussion and actions

• Claylands Green Action Group made representations on potential shaft locations, constraints on

emergency access and construction methodology

• TfL say site of shafts to be decided in September; this is now likely to be October.

• There is no reason to have shafts at all. On Crossrail local authorities argued successfully that shafts

should be removed.

• Our politicians should make case to Transport for London, Cllr Lib Peck and Val Shawcross AM have

sent a letter to TfL about Claylands Green.

• Could Oval Station be used to evacuate? It is located close to the new tunnels.

• Why are the options for Oval Green / Offley Works not included on the plans?

• Fire brigade say the maximum number of fire engines at shaft would be 2. How can this be guaranteed and

what happens if ambulances are needed?

• Construction impact on trees in Claylands – the impact needs to be investigated by LBL tree officer.

• There should be no loss of parking

• Air pollution

• Can Ramboll look at alternatives (e.g. oval Green) and look at tweaking the route to avoid more houses?

• Plant and fans will technology be up to date?

• Cottingham Road – sheltered housing requires ambulance access 24/7 – need TfL to talk to Metropolitan

Housing Trust

• If Claylands shaft goes ahead spoil from shafts comes out locally but should not be taken across the green

– this is a disruption to residents

• The Construction Management Plan should look at construction impacts on a street by street basis

3: Nine Elms Station

Issues and Discussion

§ Have the location and entrance been finalised yet? The site is adjacent to Pascal Street and there will be

one entrance on the Wandsworth Road side of the viaduct. Details are currently being worked up.

Actions

§ Lambeth to help facilitate a meeting between Crimsworth/Thorparch TRA and Transport for London.

§ Impact on Crimsworth road Brooklands Passage needs to be looked at. These currently quiet streets

would be a natural pedestrian route to the station.

§ Need to look into Capacity of NLE, will trains be full by time they get to Nine Elms station?

§ Lambeth Council have stated that their support for the NLE is conditional on the delivery of an

intermediate station at Nine Elms.

4. General queries

Impact on value of properties.

Page 16: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

Settlement

• What is the process for claiming? What is the process for monitoring any settlement or

damage

• When would TfL carry out detailed surveys of properties to check existing settlement levels?

Ramboll comment - There is a well set out process for predicting settlement, looking into build /

foundations etc and Lambeth need to ensure that this will be communicated to residents by TfL. LBL

need to request a timetable for these surveys from TfL.

Long term noise and vibration impacts:

• Additional trains on Kennington Loop, existing trains already lead to noise and vibration

meaning that any increase in the number of trains could exacerbate this. Need maximum

noise mitigation around the Kennington Loop – where the NLE will meet the existing track

and be at its most shallow – and the need for the existing track on the Loop to be upgraded to

reduce noise disruption

• Can improvements be made to the existing track at Kennington loop as part of the NLE

works?

• What would the impact be on the track north of Kennington due to the additional trains?

• Residents would like to have a meeting with TfL to discuss noise.

• Fans in ventilation shafts are likely to be used more often during summer months when

residents will typically have windows open and be in gardens – need to look closely at noise

reduction and pollution

• Noise and vibration asset design guidance states 40decibels – residents would like LBL to

commit to a maximum noise level of 25 decibels as per the proposed Dublin Metro system

(Ramboll commented that this was only under theatres and not residential properties)

Ramboll comment - Ramboll will consider if all possible mitigation measures have been

investigated and TfL would have to justify what they are proposing and would need to investigate

noise mitigation measures in the following order:

i. rolling stock

ii. wheels / track interface

iii. track (continuously welded)

iv. track bed

v. tunnel lining

vi. horizontal alignment

Ramboll also confirmed that the tunnel diameter has been increased so that a floating track bed

could be accommodated although the use of this has not yet been confirmed.

Accessibility of information

• Will further information be available to the public? If so when?

• Residents need a noise map showing likely noise levels along the route.

• Route 2 goes under most properties so this enforces the requirement that they provide best

mitigation possible.

• Feedback – write to residents with actions and timescales

- Written updates (leaflets / letters)

- Website

• Need to make technical feedback available to residents and action groups for use in public

enquiry

Construction impacts

• Residents stated that LBL need to press for more than maximum standards that TfL is legally

obliged to work to.

Page 17: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

• Can TFL plan periods of high and low construction activity and let residents know when these

periods are?

Ramboll comment - Control of Pollution Act (Construction) covers construction pollution so LB

Lambeth can control this using separate legislation. LBL can influence construction process using

the CMP and TfL would need agreement on noise levels from LB Lambeth

Capacity of existing Northern Line

• LBL need to check TfL predictions because residents have concerns that this will be adversely affected by the NLE in the following ways:

• Capacity of line – how will the additional trains be accommodated when the existing

service is every 2 minutes? TfL predictions regarding the ability to accommodate

additional trains should be checked carefully.

• Capacity of Kennington station – how will the extra people/interchange with the City

branch be accommodated? It is wrong to expect that all additional trips will be on the

CX branch and experience of using the station supports this.

• A comment was made that the Treasury Holdings/TfL review of the impact of the NLE

should be discredited. This relates to the predicted usage of the NLE and the capacity of

the existing NL to accommodate these trips. TH/TfL studies into capacity on NL and

Bank Branch should be carefully checked.

• What is the underlying assumption for TfL passenger numbers? High cost luxury

apartments so have they taken demographics into account in modelling – people will

work in the City / Docklands

Page 18: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

Appendix 3 – Minutes from 4th December 2012 public meeting

Northern Line Extension

Resident and Stakeholder Technical Update Meeting

Chaired by Val Shawcross CBE London Assembly Member for Lambeth and Southwark

Tuesday 4 December 2012

18:00 – 21:00 South Lambeth Library, 180 South Lambeth Road

Attendees

Val Shawcross AM (Chair) – London Assembly Member for Lambeth & Southwark

Cllr Lib Peck – Leader of Lambeth Council

Lambeth Council officers – Abu Barkatoolah - Head of Transportation

Rob Heslop – Transport Planning Manager

William Howe – Senior Transport Planner

Ramboll – Matthew Garner - Associate

Ray Browne - Associate

Max Elliott – Senior Engineer

Pete Syddall – Principal Transport Planner

Residents and community groups

Purpose of the meeting

Lambeth Council held a public meeting on the 10th September 2012 that offered stakeholders the

opportunity to raise concerns and ask any questions they had in relation to the Northern Line Extension

(NLE). At that meeting the council undertook to take all away all of the points raised and to provide

feedback on them when able to. This meeting was proposed to provide this feedback as well as to update

on overall scheme progress.

The following issues were addressed:

1. Introduction & General Update

2. Noise & Vibration

3. Construction Methodology

4. Shaft Design and Locations

5. Impact on the Northern Line including Kennington Station

Issues raised, discussion points and actions from the meeting are listed under each of these headings.

Page 19: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

1. Introduction & General Update

A general update on the NLE together with an overview of the ongoing assessment work being

undertaken by Ramboll was given. Residents requested that LBL increases the amount and frequency of

information shared with residents; it was suggested that regular updates would be an appropriate means of

communicating progress.

The issue of costs was raised with Ramboll advising that their work up to this point had not included any

assessment of the overall scheme costs although they had looked at the relative costs of individual

elements. Valerie Shawcross AM confirmed that the TWAO process would involve a thorough

examination of all issues related to scheme costs.

2. Noise & Vibration

Ray Browne provided an update on the work undertaken by Ramboll in respect of noise and vibration.

- TfL are designing the scheme to not exceed 35dB which is a lower level than used for Crossrail

and have committed to using best endeavours to achieve this;

- Ramboll consider that a design standard of 30dB would eliminate any impact on residents and

will advise LBL to formally request this;

- TfL’s consultants URS have undertaken significant noise assessment work along the route which

Ramboll consider to be in accordance with ‘best practice’;

- Ramboll have amended the proposed route to achieve the lowest possible impacts in terms of

noise and vibration and this will be submitted to TfL for comment;

- TfL have a range of mitigation measures available to them and need to consider long term

maintenance issues as well as short term performance and cost;

- LBL would have the ability to control noise impacts during the construction phase through

Section 61 legislation.

Questions and points raised by residents/community

Q. Is the 35dB target in addition to any background noise levels? A. Only if this is within 10bB of

existing.

Q. What does ‘best endeavours’ mean? A. TfL will use 35dB as a starting point and will employ

mitigation measures to achieve this.

Q. Has the cumulative impact of where the two tunnels are very close to each other with the potential for

two trains passing under a property simultaneously been considered? A. Yes TfL should take this in to

account in their assessment.

Q. Has the issue of vibrations been fully assessed? What is the risk of damage to properties from

vibration? A. Vibration is very closely linked to noise and TfL have targets to meet in respect of this.

They are using experts to assess vibration and this will form part of the TWAO. Any damage to buildings

is extremely unlikely.

Q. A resident who currently lives above the Kennington Loop confirmed that the existing track does not

cause them any disturbance but asked what noise monitoring would be carried out in that area? A. TfL

have taken noise and vibration readings above the Loop.

Q. Will sound travel through the proposed shafts? A. TfL has to control noise from fans and tunnels and

will take background readings to ensure that noise emitted is 10dB below existing background noise.

Page 20: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

Q. Hann Tucker (acoustic consultants) produced a report on noise levels for the Victoria Station upgrade

programme which recommended that max noise levels should be 30dB during that day and 25dB at night.

Why are the same standards not being applied to the NLE? A. Ramboll will review this report.

Q. A World Health Organisation Report on the proposed Dublin Metro project proposed that noise levels

should not exceed 25dB. Why are the same standards not being applied to the NLE? A. Noise levels of

30dB have been shown to have no observable impact and this is the level recommended by Ramboll.

Q. What are the relative impacts of Ramboll’s amended route compared to TfL’s preferred route? A.

Once this option has been assessed by TfL these details will be published.

Q. How achievable is a design standard of 30dB? Is this a technical or economic issue? A. It’s difficult to

predict but Ramboll consider that it is achievable. Its both as cost is always a consideration in any project.

Q. Since the Claylands Green shaft has been removed is it necessary for the tunnels to be so close to each

other as spreading them out could reduce any cumulative impacts? A. Tunnels need to be close together

for safety reasons as linking cross passages allow for easy evacuation.

Q. Where the new track meets the existing Kennington Loop there will need to points. What level of

noise will this cause? A. The interface between the old and new tracks is called the ‘step plate’ and at this

point the tunnel will be constructed in such a way with an insulating lining that it is possible that noise

levels will decrease below the existing.

Q. Does the Control of Pollution Act cover construction traffic? A. Yes, both the environmental impact

from and the permitted hours of operation can be controlled.

Q. Will LBL be recommending to TfL that noise levels do not exceed the existing? A. LBL are

committed to ensuring that the NLE does not cause any significant negative impact on its residents and

will take on board all recommendations from Ramboll to ensure that the most resilient mitigation

measures are employed by TfL to achieve this.

Q. In respect of Kennington Station previous repairs to address noise complaints have taken a long time

in coming forward. What improvements are proposed to Kennington Station as part of the NLE? A. TfL

has confirmed that no improvements will be undertaken to Kennington Station as part of the NLE.

Q. Can TfL’s consultation period be extended to allow for residents to incorporate findings from

Ramboll’s report? A. This request should be put directly to TfL.

3. Construction Methodology

Matthew Garner provided an update on the work undertaken by Ramboll in respect of construction

methodology;

- Much of the detail on construction practices and working hours will not be known until after the

TWAO;

- TfL and their contractors will have to demonstrate that their works are necessary and LBL can

question this through the TWAO;

- The Code of Construction Practice will govern the way the scheme is implemented and this can

be amended throughout the project to respond to any problems arising;

Questions and points raised by residents/community

Page 21: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

Q. Will spoil from the tunnels be taken out via the river? A. Spoil from the main tunnel will be

transported by barge from Battersea but spoil from the shafts will need to be removed by road.

Q. How many lorry movements will be needed? A. This will be set out in the transport assessment

accompanying the TWAO and TfL have guidance on managing construction traffic that they will need to

adhere to.

Q. How will TfL deal with any structural damage caused to properties especially old buildings with

shallow foundations etc? A. Any concerns related to a specific property should be relayed to TfL directly.

Following approval of the TWAO TfL should commission condition surveys on all properties where

significant movement is anticipated. This is part of the detailed design following the TWAO.

Q. What extent of compensation grouting might be required? A. it is anticipated that compensation

grouting will be required in the vicinity of the step-plate. TfL should be writing to all properties above the

tunnel to advise owners of the process for predicting and assessing settlement. TfL have committed to

paying a standard £50 fee for the compulsory purchase of sub-soil required for the tunnels.

Q. A previous drawing circulated by TfL showed the existing tunnel in the wrong place so can any

drawings be relied upon as accurate? A. Since the meeting TfL have confirmed that there was an error

with an indicative diagram used in some correspondence but that all engineering drawings and plans are

accurate.

Q. What level of detail is there over settlement elsewhere along the Northern line? A. TfL have

undertaken initial assessments the outcomes of which Ramboll consider to be acceptable although this

was based on the previously proposed smaller tunnel and therefore the results will have to be considered

in light of the new larger tunnel. Ramboll will be discussing the need for further ground investigation

with TfL as guidance suggests that ground conditions should be surveyed every 200m and more closely

near to proposed stations and shafts. As part of the TWAO an area of sub-soil would be secured for

construction of the tunnels as well as an envelope of permissible deviation around the tunnels allowing

for slight adjustment in the route alignment. It is critical that TfL get this right at TWAO stage as the area

of sub soil is fixed.

4. Shaft Design and Locations

Questions and points raised by residents/community

Q. What is Ramboll’s response to TfL’s position on the Kennington Park shaft? A. The use of Oval

Green has previously been suggested but TfL have confirmed that this is too far from the step plate and

that there should not be more than 2 trains between Kennington station and the shaft for safety reasons.

The use of signals within the tunnels to control train movements has also been ruled out. Ramboll will

relook at this issue and ask TfL to clarify any points of contention.

Q. What is the latest on the Kennington Green shaft and what assurances are there that the green will be

restored following works? A. The shaft headhouse is proposed to be within the Beefeater distillery site

and TfL are currently working on the proposals for reinstating the green including meeting with residents

to develop an acceptable design.

Q. Is there potential for the proposed temporary shafts to be removed from the proposals if an alternative

construction methodology is used? A. TfL is investigating this and will advise further once all options

have been considered.

Page 22: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the

Q. What are the knock-on impacts of removing the Claylands Green shaft on the remaining shafts or

stations? A. TfL has been asked to confirm this but it is anticipated that more fans would be required

within the remaining shafts.

Q. Will the proposed sub-stations generate any noise or vibration? Will the sub-stations be visible above

ground? A. TfL will have to assess any impacts from them but any noise would have to be 10dB below

background. All sub-stations will be below ground and thus not visible.

5. Impact on the Northern Line including Kennington Station

Questions and points raised by residents/community

Q. There is a discrepancy in the figures released by TfL for the number of extra passengers using

Kennington station. When will accurate figures be available? A. TfL is still at an early stage of modelling

these numbers but will need to justify all figures at the TWAO. LBL will require a robust assessment of

this issue and will be asking Ramboll to check these numbers.

Q. Why was an extension of the Victoria line or an extension of the Northern line via Vauxhall not

considered? A. This was considered but TfL ruled out an early stage due to current issues of

overcrowding on the Victoria line and at Vauxhall station respectively. TfL have an existing programme

of tube line improvements that will increase capacity by 25 – 30%.

Q. Would this increase of 25 – 30% create spare capacity or simply accommodate existing demand? A.

TfL will be asked to confirm this.

Q. TfL’s current figures indicate that during the AM peak hour 3900 extra passengers would use the

Charing Cross branch and 1200 extra passengers would use the Bank branch. Are these estimates accurate

given existing usage patterns and fluctuations that occur even within the AM peak? A. TfL is being

challenged on this and has provided reasons for their assumptions. Ramboll will scrutinise this and will

make their recommendations public.

6. General points raised

Valerie Shawcross AM opened the floor to general questions and comments related to the NLE to close

out the meeting. The main topics raised were;

- Concerns over the cost of the NLE and the relative benefit to Lambeth;

- Lack of involvement from Southwark Council;

- Quality and scope of consultation being undertaken by TfL;

- Lack of consideration for transport solutions other than the NLE.

Abu Barkatoolah requested that all comments or requests related to the NLE are submitted to

[email protected] so that the council can maintain an audit trail on all correspondence.

Valerie Shawcross AM closed the meeting by thanking all attendees for their input and reinforced the

importance of all individuals making full representation of their concerns to TfL.

TfL are running their consultation on the Northern Line Extension until 30 December, please visit their

website https://consultations.tfl.gov.uk/tube/nle or email [email protected] or write to;

Page 23: NORTHERN LINE EXTENSION – TECHNICAL UPDATE NLE Update.pdf · Northern Line Extension – Technical Update 1. Context 1.1 In March 2012 Cabinet gave in principle approval for the