mitsui babcock

Upload: karthick-velayutham

Post on 09-Apr-2018

268 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/7/2019 Mitsui Babcock

    1/19

    Mitsui Babcock Biomass Co-firingExperience from the UK

  • 8/7/2019 Mitsui Babcock

    2/19

    Who is Mitsui Babcock?

    Leading, multi-specialist energy services company

    UK based, global operations, 4,500 employees worldwide

    A leader in utility coal fired power generation technology,

    regular participant in EU and DTI R D and D programmes

    Annual turnover approximately 600m, profitable and

    sustainable

    Established in 1891 as Babcock & Wilcox Ltd formation

    of Mitsui Babcock Energy Limited in 1995

    Products and services across all fuel types and throughout

    the complete plant life cycle

  • 8/7/2019 Mitsui Babcock

    3/19

    The Renewables DirectiveA Challenge for the British Power Industry

    The Renewables Directive has been key in driving biomass co-firing in the UK

    UK like some other EU states allow co-firing to contribute tomeeting targets

    Significant Renewable Energy Supply possible where fuel supplyand availability can be successfully integrated with effective co-firing methods

    UK co-firing rules allow,- extended co-firing on non-energy crop biomass- But forces a transition to energy crop from 2009

    Historical risks,- Poor or expensive fuel supply infrastructure,

    - Lack of flexible and robust handling/ combustion technology,- Insufficient legislative and market incentives for co-firing

    Successful large scale co-firing demands an integrated approach toovercome these risks

  • 8/7/2019 Mitsui Babcock

    4/19

    Overcoming Logisticaland Technical Challenges

    In-country Supply- Availability and sustainability

    - Extraction, processing and transport costs

    - Consistency of quality (moisture and heat value)

    - Drying and handling issues

    Imported Supply- Significant an sustainable volumes

    - Guaranteed quality (low moisture, consistent heat value)

    - Transport CO2/cost offset by less drying/handling risks

    - Can be cost competitive

    Co-firing v Dedicated plant- +50% more RES-E/tonne biomass

    - Lower capital cost and project risk

  • 8/7/2019 Mitsui Babcock

    5/19

    An Integrated Approach

    Co-firing Methods

    Technical Risks and

    Best Practice

    UK Co-firing Experience

  • 8/7/2019 Mitsui Babcock

    6/19

    Co-firing Methods

    Utility Co-firing of biomass isthe most efficient conversionroute to RES

    Co-firing can be achieved by,

    - Co-milling

    - Dedicated co-firing

    Direct Injection

    Dedicated burners

    Co-firing burners

  • 8/7/2019 Mitsui Babcock

    7/19

    Technical Risks and

    Best Practice

  • 8/7/2019 Mitsui Babcock

    8/19

    Co-milling

    Majority of stations co-firing by pre-blending thebiomass with the coal, before the mill

    Co-firing ratios typically 5% on a heat input basis.

    Minimal effect on boiler performance and environment.

    Most of the technical problems associated with thereception, storage and handling

    The constraints on the co-firing ratio have been:

    - Fuel availability,

    - Handling/blending system capacity

    - Limitations of the coal milling equipment.

  • 8/7/2019 Mitsui Babcock

    9/19

    Co-milling

    A range of biomass being co-milled in,- Ball and tube mills

    - Vertical spindle ball and

    - Ring, and roller mills.

    Mill performance depends on brittle fracture ofcoal into particles

    Biomass can accumulate in the mill - longer toclear the mill during shutdown.

    Mill differential pressure and powertake can increase on vertical spindle mills.

    Mill product top-size increases as largerbiomass particles exit the classifier.

    Biomass moisture affects mill heat balance

    Can be limiting factor (e.g. inadequate drying). Safety issues when co-milling biomass - mill

    operating procedures optimisation

  • 8/7/2019 Mitsui Babcock

    10/19

    Trend Toward Dedicated Co-firing

    The general approach at a number of British stations has been asfollows:

    Establish co-firing by pre-blending and co-milling on the preferredfuel at minimum capital cost, and with short project lead times.

    Obtain the Environmental License Variation for commercial co-firing activities.

    Modify the Variation to permit greater flexibility in the fuel supplyand the co-firing ratio.

    Integrate the biomass co-firing into the normal station operations.

    Upgrade the biomass reception, storage, handling and blendingfacilities, to increase throughput and reduce mechanical handlingconstraints, dust generation, etc.

    Some now implementing direct firing of the biomass to permithigher co-firing ratios.

  • 8/7/2019 Mitsui Babcock

    11/19

    Dedicated Co-firing options

    The biomass can be pre-milled either off-site or on-site

    All direct co-firing systems involve pneumatic conveyingof the biomass from the fuel reception/handling facilityto the boiler house.

    There are three basic direct co-firing options:- Direct injection into the furnace with no combustion air,

    - New dedicated biomass burners, and

    - Co-firing with coal through the existing burners by injection ofthe biomass into the pulverised coal pipework or burner

  • 8/7/2019 Mitsui Babcock

    12/19

    Direct injection

    Direct injection through the furnace wall with onlyconveying air and no flame stabilisation.

    Demonstrated, on a trial basis, in a downshot-fired

    boiler in Britain, Simple and cheap to install,

    Limited application for wall or corner-fired boilers.

    Only conducted with dry biomass to date

    Handling and combustion risks with wetter biomass

  • 8/7/2019 Mitsui Babcock

    13/19

    Dedicated Burners

    Modified pulverised coal burners or cycloneburners

    New burner locations required in rear orside walls.

    Secondary air supply requires significantductwork modifications.

    New burner locations -Impact on thepulverised coal combustion and the furnaceperformance need assessment

    New burner maintainability and controlcould result in generation risk

    Dedicated biomass burners have not been

    extensively demonstrated commercially onUtility plant.

    Complex and relatively expensive to install.

  • 8/7/2019 Mitsui Babcock

    14/19

    Co-firing Burners

    Demonstrated in Britain and continental Europe.

    Injection locations at the mill outlet or local to theburners.

    Simple and cheap to install, but implications on the milloperation and control.

    The risks of interference with the operation of the coal

    firing system needs assessment.

    If the biomass is to be injected at the burner, there aresignificant burner modifications required.

  • 8/7/2019 Mitsui Babcock

    15/19

    Modified MB Mark III LNB forCoal-Straw Co-firing at Studstrup

  • 8/7/2019 Mitsui Babcock

    16/19

    UK Co-firing Experience

    All of the coal-fired power plants in Britain are co-firing biomass.

    The total number of ROCs (MWh) from biomass co-firing to datealmost 3 million.

    The range of biomass materials co-fired includes:

    - Wood in a variety of forms, principally sawdust or pellets,

    - Imported dry residues from the olive oil and palm oil industries, and- Liquid biomass materials, principally talloil.

    Volumes of biomass required are significant e.g.

    - 5% Co-firing on a 2GWe plant = 200-300 ktonnes/year(@ 40% load factor)

    Low Cost Imported biomass in high volumes has produced themajority of E-RES in the UK

  • 8/7/2019 Mitsui Babcock

    17/19

    Renewable Electricity (ROCs)from Co-firing to Sept 05

    3,799EdF1,980West Burton

    2,868,501Total ROCs/MWh

    11,777RWE npower1,085Tilbury

    128,089Int. Power1,000Rugeley

    20,409E.on UK2,010Ratcliffe

    209,420Scottish Power2,400Longannet

    168,515E.on UK2,034Kingsnorth

    127,681E.on UK970Ironbridge

    442,910SSE1,995Fiddlers Ferry

    977,172SSE2,035Ferrybridge

    10,092British Energy1,960Eggborough

    426,218Drax Power4,000Drax

    46,351RWE npower2,100Didcot

    75,630EdF2,000Cottam

    9,302Scottish Power1,200Cockenzie89,744RWE npower1,455Aberthaw

    Cumulative ROCsGeneratorCapacity (MWe)Station

  • 8/7/2019 Mitsui Babcock

    18/19

    Conclusions

    Large Scale co-firing is one of the most efficient and low costmethods in meeting EU RES targets.

    Co-milling is being practised by all Coal plant operators

    Direct co-firing projects are being developed in British coal-firedpower plants as a means of increasing the co-firing RES.

    Injection of the biomass into the existing burner currently appearsto be the optimal direct firing solution.

    Project risk increases with,

    - Co-firing Ratio

    - Fuel quality and diversity

    Integration of co-firing technology selection with low cost fuel

    supply in high volumes is key to profitability.

  • 8/7/2019 Mitsui Babcock

    19/19

    [email protected]

    www.mitsuibabcock.com

    +44 (0) 141 886 4141