Lessons from 5 years of
Operations and Maintenance
of Solar PV in South AfricaLiam May
Operations Manager, SOLA Future Energy, South
Africa
• Introduction to SOLA Group
• Track Record of rooftop solar PV
• Black River Park – No. 1 grid tied with the City
• O&M – 5 years
• Presentation Outline – “Critical Experience” and
“Lessons Learned”
INTRODUCTION
• Ensure financial savings: correlated with tariff ranges
– Maximise energy production
– Maximise demand savings
• Capital investments – ROI
• Environmental – reduce coal usage/CO2
• Client green initiatives – corporate drive/customer
behaviour
PURPOSE OF O&M?
• O&M Contract:
– Stipulates service intervals/inspections
– Response times
• Performance Guarantees – Performance Ratio or Yield (annual kWh)
– Peace of mind to client
– “insurance policy”
• Liability of both parties
– Plant-wide damages (hail storm, severe weather events)
– Within/without warranty• Inverters – not all faults covered (5yrs, 10yrs, extended warranties)
• Panels – covered within bounds
LEGAL GOVERNANCE OF
O&M
• No continuous monitoring, no O&M
• Essential – real-time behaviour + status of the plant
• One single monitoring platform
• Identify faults, diagnose faults, decide on remedy
• Understand scale of fault – severity – determines the
urgency of response and scheduling
FUNDAMENTALS:
MONITORING
• Remote access to remote sites
• Reset comms boards and equipment
• Reset inverters if possible and safe
• Strong comms link + function = good operation
– Critical item – migrogrid operations
– Intermittent comms – missing data - reporting
– Internal network comms – inverters/generators/controller
FUNDAMENTALS:
COMMUNICATIONS
• Site hand-over: completion certificate
• O&M contract signature, or O&M included in EPC?
• Test week report
• Inverters – monitoring + strong comms
• Inverters – performance relative to each other
• Strings – string tests
• Ground Faults
MAINTENANCE
GROUND FAULTS
• Common problem
• Hard to locate – transient – moisture
• Can damage certain inverters – not covered under warranty!
• String tester – methods
• Home runs
• Connectors between panels
• Causes: – improper installation
– DC cables too short
– Expansion/contraction
– Sun damage – UV stable DC cables
REPORTING
• Financials – Budget/Proposal vs Actual
• Client savings
• Expectations
• Display performance of plant
• Reporting = vital
CLEANING 1
• Research on the topic
• Quantification difficult – environmental variance
• Experience:
– Up to 10-15% daily improvement with clean (or more)
CLEANING 2
• Environmental factors – type of dust/grime/open
fields/veld?
• Birds – breeding colony locations (Robben Island)
CLEANING 3
• Climate regime – Summer (JHB) or Winter (CPT) rainfall.
• Clean at the start of the dry season – monitor
• Daily various analysis – comparison to simulation
• Plant running correctly but underperforming?
• Safety of cleaning crew – rope access experience
• Number of cleans a year? Site dependent.
• Water restrictions?
CONCLUSION
• O&M for 20 – 25 years
• Protects the asset, ensures returns – “Run the
powerplant”
• Importance of:
– Accurate monitoring
– Accurate communications links
– Accurate data
– Accurate reporting
– Competent and effective maintenance