lakeside reclamation landfill beaverton,...

62
STAFF REPORT RECOMMENDED REMEDIAL ACTION For Lakeside Reclamation Landfill Beaverton, Oregon ESCI # 4413 Prepared By OREGON DEPARTMENT OF ENVIRONMENTAL QUALITY Northwest Region Office August 2011

Upload: lydieu

Post on 22-Jul-2018

234 views

Category:

Documents


0 download

TRANSCRIPT

STAFF REPORT

RECOMMENDED REMEDIAL ACTION

For

Lakeside Reclamation Landfill Beaverton, Oregon

ESCI # 4413

Prepared By

OREGON DEPARTMENT OF ENVIRONMENTAL QUALITY

Northwest Region Office

August 2011

i

TABLE OF CONTENTS

1. INTRODUCTION .............................................................................................................................................. 1

1.1 INTRODUCTION ........................................................................................................................................... 1 1.2 SCOPE AND ROLE OF THE RECOMMENDED REMEDIAL ACTION .................................................... 1 1.3 PEER REVIEW SUMMARY ......................................................................................................................... 2

2. SITE DESCRIPTION AND HISTORY ........................................................................................................... 3

2.1 SITE LOCATION AND LAND USE .............................................................................................................. 3 2.2 BENEFICIAL WATER USES ........................................................................................................................ 4 2.3 PHYSICAL SETTING .................................................................................................................................... 5 2.4 LANDFILL OPERATIONS ............................................................................................................................ 9

3. REMEDIAL INVESTIGATION .................................................................................................................... 12

3.1 CONCEPTUAL SITE MODEL .................................................................................................................... 12 3.2 COVER EVALUATION ............................................................................................................................... 12 3.3 GROUNDWATER ........................................................................................................................................ 15 3.4 CONTAMINANT FATE AND TRANSPORT ............................................................................................. 18 3.5 SURFACE WATER ...................................................................................................................................... 18 3.6 SOIL .............................................................................................................................................................. 20 3.7 TUALATIN RIVER SEDIMENT ................................................................................................................. 21 3.8 RISK ASSESSMENT ................................................................................................................................... 22 3.9 IDENTIFICATION OF HOT SPOTS ........................................................................................................... 26

4. DESCRIPTION OF REMEDIAL ACTION ALTERNATIVES ................................................................. 27

4.1 REMEDIAL ACTION OBJECTIVES .......................................................................................................... 27 4.2 GROUNDWATER PLUME AREA AND VOLUME ................................................................................... 27 4.3 APPLICABLE REQUIREMENTS ............................................................................................................... 28 4.4 LANDFILL COVER REMEDIAL ACTION ALTERNATIVES ................................................................. 28 4.5 GROUNDWATER REMEDIAL ACTION ALTERNATIVES .................................................................... 30 4.6 PERIODIC REVIEW, MONITORING AND CONTINGENCIES ............................................................... 33

5. EVALUATION OF REMEDIAL ACTION ALTERNATIVES .................................................................. 35

5.1 EVALUATION CRITERIA .......................................................................................................................... 35 5.2 PROTECTIVENESS ..................................................................................................................................... 35 5.3 BALANCING FACTORS ............................................................................................................................. 38

6. COMPARATIVE ANALYSIS OF ALTERNATIVES ................................................................................. 45

6.1 LANDFILL COVER ..................................................................................................................................... 45 6.2 GROUNDWATER REMEDIAL ACTION ALTERNATIVES .................................................................... 47 6.3 TREATMENT, REUSE AND DISPOSAL OF EXTRACTED WATER......................................................................... 49

7. RECOMMENDED REMEDIAL ACTION ALTERNATIVES ................................................................... 52

7.1 DESCRIPTION OF RECOMMENDED LANFILL COVER ALTERNATIVE ........................................... 52 7.2 DESCRIPTION OF THE RECOMMENDED GROUNDWATER ALTERNATIVE .................................. 52 7.3 ADAPTIVE MANAGEMENT .............................................................................................................................. 54 7.4 RESIDUAL RISK ASSESSMENT ............................................................................................................... 55

8. ADMINISTRATIVE RECORD INDEX ........................................................................................................ 56

Figures

ii

1. Site Location Map

2. Regional Geologic Map

3. Regional Geologic Cross Section

4. Site Geologic Cross Section

5. Shallow Groundwater Flow – Water Table Surface

6. Surface Water Features and the Locality of Facility

7. Site Features and Monitoring Locations

8. Groundwater Quality -Total Dissolved Solids

9. Groundwater Quality – Iron

10. Groundwater Quality – Manganese

11. Groundwater Quality – Chloride

12. Tree Distribution on Evapo-Transpiration Cover

13. Site Cross Section – Groundwater Contamination

14. Conceptual Site Model of Potential Human Exposure

15. Conceptual Site Model of Potential Ecological Exposure

16. Groundwater Hot Spot

Tables

1. Detections in Riverside Wells – Contaminants with Ecological Screening Values

2. Detections in Riverside Wells – Contaminants without Ecological Screening Values

3. Comparison of Upgradient and Downgradient Water Quality

4. Data Summary and Chemistry-Toxicity Screening of COIs in Groundwater

5. Cumulative Ecological Risk Screening

6. Remedial Action Levels

7. Comparison of Remedial Action Alternatives

8. Comparison of Groundwater Treatment/Disposal Alternatives

1

1. INTRODUCTION

1.1 INTRODUCTION

This report presents DEQ‟s recommended remedial action for the Lakeside Reclamation Landfill

site (Lakeside) at 14930 SW Vandermost Road in Beaverton, Oregon. DEQ developed the

recommended remedial action in accordance with Oregon Revised Statutes (ORS) 465.200 et. seq.

and Oregon Administrative Rules (OAR) Chapter 340, Division 122, Sections 0010 through 0115

and OAR chapter 340, Division 40, sections 0040 through 0050.

The recommended remedial action is based on the administrative record for this site. A copy of the

Administrative Record Index is attached as Appendix A. This report summarizes the more detailed

information contained in the Remedial Investigation, Baseline Risk Assessment, Ecological Risk

Assessment and Feasibility Study reports completed under Oregon Department of Environmental

Quality (DEQ) Voluntary Agreement No. LQVC-NWR-05-08 dated December 9, 2005.

1.2 SCOPE AND ROLE OF THE RECOMMENDED REMEDIAL ACTION

The recommended remedial action addresses Lakeside‟s cover, and groundwater contamination

beneath and downgradient of the landfill currently discharging to the Tualatin River. The

contaminants of concern include ammonia, barium, calcium, chloride, iron, magnesium, manganese

and zinc. DEQ identified these chemicals based on: 1) their risks to aquatic organisms of the

Tualatin River and the degradation of the river‟s aquatic environment, and 2) the frequency and

consistency with which they exceed their respective ecologically based screening levels and/or

ambient water quality criteria. The remedy also addresses sporadically detected contaminants of

ecological concern such as selenium and cyanide and conditions and contaminants associated with

general water quality degradation including high chemical oxygen demand, depleted oxygen levels,

and high total dissolved solids.

The recommended remedial action consists of the following elements:

1) Enhancements to the evapotranspiration (ET) cover to improve tree growth, density, and

long-term health and to reduce the volume of water leaching landfill waste and releasing

contaminants to the environment;

2) Hydraulic containment of the plume of groundwater contamination through installation and

pumping from approximately 12 groundwater extraction wells;

3) Treatment of wastewater using on-site and/or off-site land application and subsequent

2

evapo-transpiration and contaminant uptake by trees, or beneficial re-use of the wastewater

for moisture control for Lakeside‟s composting operations;

4) Performance monitoring to: A) demonstrate hydraulic containment of the groundwater

plume has been achieved and is maintained over time, B) assess contaminant concentrations

over time, C) ensure land application/ of wastewater is not adversely impacting the soil

column and groundwater, and D) demonstrate compliance with ET cover performance

criteria (currently set at an infiltration rate of less than 1.0 inches of water annually).

5) Contingency measures administered through an Adaptive Management process that will be

implemented if the hydraulic containment system does not meet remedial objectives, if land

application causes adverse impacts, or if the ET cover does not meet performance

objectives. Refer to Section 7.3 for discussion of the adaptive management process.

1.3 PEER REVIEW SUMMARY

Plans and reports produced during the investigation of the Lakeside site have been reviewed by the

Project Manager/Hydrogeologist Henning Larsen, a solid waste and Environmental Engineer, Tim

Spencer, and Toxicologist Paul Seidel. The team unanimously supports the recommended remedial

action. Refer to the technical team evaluation file for more detailed information. Additionally, Bill

Mason, DEQ Western Region senior hydrogeologist, reviewed the staff report and concluded it is

consistent from a programmatic and regulatory basis.

3

2. SITE DESCRIPTION AND HISTORY

Lakeside Reclamation Landfill is a 37-acre former construction debris landfill that closed in 2009.

The landfill is owned by Grabhorn Inc. When filling operations began in the early 1950s waste

was placed directly on native soils, thus it is an unlined landfill. In 1991, Lakeside began closing

sections of the landfill with an evapotranspiration cover consisting primarily of hybrid poplar

and pine trees. Currently, final grading of the landfill cover is nearing completion and a plan for

enhancing the cover‟s performance is under development. The only structure associated with the

landfill is a small building formerly used as a scale house by employees weighing loads of waste

entering the facility. The landfill is roughly rectangular in shape and its 1400-foot southern edge

borders the Tualatin River. The landfill is approximately 130 feet in height. The base of the landfill

ranges from an elevation 120 feet above mean sea level in the south to 170 feet in the north with a

crown elevation of approximately 250 feet above mean sea level.

2.1 SITE LOCATION AND LAND USE

The landfill is located at 14930 SW Vandermost Road in Beaverton, Oregon, Township 2S, Range

1W, Section 12, Washington County [See Figure 1]. The site latitude is 45.41 and the longitude is -

122.87.

Lakeside is located along the Tualatin River in rural Washington County, approximately 0.8 miles

west of the City of Beaverton Urban Growth Boundary and approximately 0.75 miles south of

Scholls Ferry Road. Land use within a 1 mile radius of Lakeside is a mixture of small nonfarm

residential parcels on “exception land”, urban development within the boundary, and land

designated by Washington County as “Resource Land,” zoned for Exclusive Farm Use (EFU) or

Forestry (FF). The properties occupied by the Lakeside facility and the areas proposed for land

application are designated by Washington County as “Exclusive Farm Use‟ Crops grown in the

vicinity of the landfill include Christmas trees, filberts, and grapes (vineyards). The nearest

residence is approximately 600 feet of the western facility boundary and a vineyard and associated

buildings are on the adjacent property to the east. Three wetlands listed in the National Wetlands

Inventory are located adjacent to the former landfill and three others are located within one half mile

of the facility. Within a mile of the landfill, several units of the Tualatin River Wildlife refuge are

located along the Tualatin River upstream and downstream of the landfill. Several wetlands listed

in the National Wetlands Inventory are also located within one mile.

4

2.2 BENEFICIAL WATER USES

2.2.1 Groundwater

Lakeside completed a beneficial use determination for groundwater and surface water prior to the

Feasibility Study (Beneficial Water Use and Land Use Determination – Lakeside Reclamation

Landfill). This determination evaluated beneficial uses for each water-bearing zone, considering

current use and the following factors listed in OAR 340-122-080(3)(f)(F):

Historical land and water uses

Anticipated future land and water uses

Concerns of community and nearby property owners

Regional and local development patterns

Regional and local population projections

Availability of alternate water sources

The reasonable likely future beneficial uses of groundwater in the vicinity of Lakeside include:

Discharge to and sustaining of aquatic environments in the Tualatin River by the shallow

water-bearing zone occurring within alluvial and lacustrine deposits at the site.

Deep water-bearing zones occurring within interflow zones of the Columbia River Basalt

group for domestic drinking/water, supplying livestock, and irrigation, although there are no

current uses within the Locality of Facility1(LOF).

2.2.2 Surface Water

Beneficial uses of the Tualatin River include aesthetics, recreation (i.e. swimming, fishing), and

wildlife and aquatic habitat. Beneficial uses of nearby wetlands include: groundwater recharge,

and wildlife and aquatic habitat.

1Defined in OAR 340-122-115(35) (35) "Locality of the facility" means any point where a human or an ecological

receptor contacts, or is reasonably likely to come into contact with, facility-related hazardous substances,

considering: (a) The chemical and physical characteristics of the hazardous substances; (b) Physical, meteorological,

hydrogeological, and ecological characteristics that govern the tendency for hazardous substances to migrate

through environmental media or to move and accumulate through food webs; (c) Any human activities and

biological processes that govern the tendency for hazardous substances to move into and through environmental

media or to move and accumulate through food webs; and (d) The time required for contaminant migration to occur

based on the factors described in subsections (35)(34)(a) through (c) of this rule.

5

2.3 PHYSICAL SETTING

Geographically, Lakeside Reclamation Landfill lies near the eastern edge of the Tualatin Basin

south of Cooper Mountain and west of Bull Mountain. The landfill‟s southern edge borders the

Tualatin River, a slowly flowing, low gradient tributary of the Willamette River. To the east the

facility site is bounded by a perennial creek (unnamed) that discharges to the Tualatin River. At the

site, the Tualatin flows east through a gap in the Chehalem Mountains. These mountains form

topographic highs located north and east of the Lakeside. The landfill sits on a terrace of recent

Tualatin River alluvial deposits, and extends from this lower river terrace roughly 2500 feet north.

The top of the landfill slopes gently to the north and blends into the land surface of the upper

terrace.

2.3.1 Climate

The climate in the valleys west of the Cascades is characterized by mild year-round

temperatures, abundant winter rains, and dry summers. The average annual temperature is

approximately 52-54F. Data provided by the Western Regional Climate Center indicates average

annual precipitation in the Beaverton area is approximately 39 inches, falling primarily in the form

of rain. The majority of the precipitation falls between October and March, with monthly totals

ranging from 4.0 to 7.0 inches. December is generally the wettest month. Precipitation totals for the

remainder of the year are generally less than 2 inches per month.

2.3.2 Geology

2.3.2.1 Regional

Lakeside Reclamation Landfill lies within the Tualatin Basin, an Eocene age pull-apart basin

formed by regional tectonic forces (i.e. where crustal plates are moving away from each other). The

basin is defined by the Coast Range Mountains to the west, the Tualatin Mountains to the north, and

the Chehalem Mountains to the south.

The deepest geologic formation relevant to the site is the Columbia River Basalt (CRB) group,

Miocene to Pliocene age theolitic flood basalts originating in western Idaho, southeastern

Washington and northeastern Oregon. Within the valley this formation is typically 500 to700 feet

thick with the upper 100-200 feet deeply weathered and decomposed. In the Tualatin Basin tectonic

forces deformed the basalt and deeper formations to create a synclinal structure (fold) that was

subsequently filled with alluvial and lacustrine deposits during the Pliocene and Pleistocene ages

(See Figures 2 and 3).

The most extensive of the valley fill sediments is the Willamette Silt, which forms the valley floor.

It ranges from 30 ft to several hundred feet thick within the Tualatin Basin. The Willamette Silt was

deposited in the Tualatin Basin after sands and gravels transported by the Bretz Floods dammed the

mouth of the Willamette River causing water to back up and flood the Tualatin Basin. Geologically,

the Willamette Silt in this area is described as unconsolidated, very fine micaceous silt and silty

sand. Entrenched within the Willamette Silt are Holocene age river channel and overbank deposits

6

associated with the present day Tualatin River.

2.3.2.2 Site

The southern portion of the landfill overlies an alluvial terrace formed by the Tualatin River. This

terrace, referred to in site documents as the lower terrace, consists of sand and silty-sand river

channel deposits and sandy silt, silt, and clayey silt overbank deposits extending from the surface to

a depth of about 60 feet below ground surface. At the facility site, this terrace extends

approximately 1100 feet north to a relatively steep escarpment that rises 60 feet to an upper terrace

composed of the Willamette Silt which forms the broader valley floor.

Adjacent to the Tualatin River, terrace deposits are underlain by the very fine sediments of the

Helvetia Formation. At Lakeside, the Helvetia Formation is primarily clay and silty clay deposits

that extend to depths of at least 100 feet below ground surface. The Helvetia Formation is likely

contemporaneous with the Troutdale formation observed in the Portland Basin. In the vicinity of the

site, the Helvetia Formation appears to pinch out to the north where the Willamette Silt lies directly

over the Columbia River Basalt [See Figure 4].

2.3.3 Hydrogeology

2.3.3.1 Shallow Sedimentary Deposits

On the facility site the uppermost aquifer is present in two different hydrogeologic units. Near

the Tualatin River, the sand and silt channel and overbank terrace deposits represent the

uppermost groundwater-bearing zone. Northward on the upper terrace, the water table occurs

within the Willamette Silt. Water table depths range from 25 to 38 ft below ground surface near

the landfill‟s north end and 7 to 22 feet below ground surface near the Tualatin River. Because of

their fine-grained structure and limited thickness these shallow sediments transmit small volumes

of groundwater, thereby restricting discharge to the river. The flow direction in shallow

groundwater generally mimics surface topography. Near the site shallow groundwater flows

south and southwest, discharging to the Tualatin River [See Figure 5]. Local precipitation is the

primary source of shallow groundwater recharge.

The groundwater hydraulic gradient is approximately 0.01 ft/ft in the lower terrace deposits and

estimated seepage velocities are 25 to 50 feet per year. The shallow groundwater and the

Tualatin River are hydraulically connected, although a thick layer of fine-grain material that

forms the River channel influences the rate and locations of groundwater discharge to the river.

Consequently, changes in river stage directly influence groundwater levels and shallow

groundwater flow, but the influence is muted by the presence of the fine-grained sediments. For

most of the year the river is a gaining stream (groundwater discharges to the river), however in

the winter months during periods of high river stage the direction of flow may reverse with water

flowing away from the river recharging adjacent alluvial deposits. The area within which these

flow reversals occur is limited to about 300 feet away from the river channel.

7

DEQ compared the U.S. Geological Survey‟s measured seepage rates in river channel deposits

with groundwater flow rates in the shallow aquifer estimated from Lakeside‟s monitoring well

tests. This analysis and hydrostratigraphy of the site suggest that pore water beneath the river‟s

landfill reach is dominated by groundwater that has passed beneath the landfill.

2.3.3.2 Columbia River Basalt

The site‟s most productive groundwater-bearing zones occur within Columbia River Basalt

complex. As noted in section 3.8.1, shallow groundwater within the valley fill sediments are not

hydraulically connected to the water-bearing zones within the Columbia River Basalt group,

preventing contamination from migrating into these aquifers under natural conditions.

The basalt‟s aquifer horizons generally are associated with intra-flow structures (e.g., vesicular

flow-top breccias and flow-foot breccias) of sheet flows. The interiors of thick basalt flows have

very limited permeability and act as aquitards. These structural features typically create a series

of stacked, confined aquifers within the CRB aquifer system. In these aquifers the dominant

groundwater flow usually follows horizontal to sub-horizontal pathways along individual,

laterally extensive, interflow zones. Vertical groundwater movement through undisturbed basalt

flow interiors is greatly restricted unless basalt flow interiors are disturbed or fractured (by folds

or faults), truncated (by flow pinchout and erosional windows), or cross-connected by wells.

Aquifers within the basalt units can be very productive. In the site vicinity individual

agricultural wells can produce from 50 to200 gallons per minute. In the Tualatin Valley‟s eastern

portion the Columbia River Basalt is recharged by precipitation falling on highland areas such as

the Tualatin and Chehalem Mountains. Near Lakeside, the groundwater flow direction in CRB

aquifers is unknown but the Willamette River is the assumed regional discharge area for these

aquifers.

2.3.4 Surface Water and Stormwater Features

The major surface water features near Lakeside are: 1) the Tualatin River which flows adjacent

to the landfill‟s southern boundary for approximately 1400 feet; 2) an unnamed creek that

roughly parallels the landfill boundary approximately 500 to1000 feet east of the former waste

disposal area; 3) a cluster of four manmade irrigation ponds located along the landfill‟s southeast

boundary; 4) two areas (PEM1A and PFOA, Figure 6) included in the U.S. Fish and Wildlife‟s

National Wetlands Inventory (NWI) and located within the cleanup site LOF (where

groundwater from beneath the landfill may flow into or under these areas; 5) three wetland areas

located within 1500 feet of the landfill but likely outside the site LO, and 6) A surface water seep

near the boat ramp on the Lakeside facility property, that is wet year round and at times forms

small down-stream pools before flowing into the Tualatin River. These features are presented in

Figure 6.

2.3.4.1 Tualatin River

The Tualatin River‟s main stem is roughly 80 miles long and flows generally from west to east.

The river originates in the forested Coast Range mountains and empties into the Willamette

8

River near West Linn, Oregon. The river‟s characteristics change dramatically from its

headwaters to its mouth. The headwater reach, from river mile 79.4 to 55.3, is narrow, has an

average slope of 74 feet per mile, and includes several waterfalls.

Once the river reaches the valley floor, its slope decreases and it begins to meander. This

meandering reach (river miles 55.3-33.3) has an average slope of 1.3 feet per mile, a width of

about 50 feet, and relatively complete riparian shading. Downstream of the meandering reach,

the river flows into a backwater reach (river miles 33.3- 3.4) with an estimated slope of only 0.08

feet per mile. The backwater characteristics are caused both by the low slope of the basin and the

presence of a low-head dam at river mile 3.4. In this reach, the river continues to meander and

widens to roughly 150 feet. These characteristics expose much of the river surface to direct

sunlight and solar insolation. From the low-head dam to the mouth (river miles 3.4-0.0), the

Tualatin is characterized by small pools and riffles, with an average slope of 13 feet per mile.

The Tualatin River‟s discharge rises and falls as a function of seasonal rainfall amounts. Most of

the annual precipitation falls between October and March, and seasonal stream flow is typically

highest from December through April and lowest from July through October. The low-flow

summer period is defined as May 1st through October 31st. Since January of 1975, Tualatin

River stream flow has been augmented during this low-flow period with water releases from

Henry Hagg Lake, a man-made reservoir on Scoggins Creek. River flow is managed in an

attempt to maintain 150 cubic feet per second (cfs) of flow at river mile 33.3. Mean annual

stream flow in the Tualatin averaged 1,362 cubic feet per second between 1940 and 1957.

In addition to Scoggins Creek, the Tualatin River has four other major tributaries, Gales Creek,

Dairy Creek, Rock Creek and Fanno Creek. The regional sanitary authority, Clean Water

Services, operates four wastewater treatment plants in the basin, but only the two largest plants

discharge into the Tualatin River during the May 1 to October 31 period. Currently, the Rock

Creek (river mile 38.1) and Durham (river mile 9.3) wastewater treatment plants discharge a

combined flow of approximately 80 cubic feet per second (52 million gallons per day) of treated

effluent into the river or approximately 40 percent of its typical low summer flow (approximately

200 CFS). These discharges strongly influence water quality and chemistry within the Tualatin

river during low flow periods.

Lakeside is located between river miles 20 and 21, within the backwater reach. In the backwater

reach the streambed is uneven and forms occasional deep pools (15-18 ft in depth). Heavy

sedimentation occurs there due to the river‟s low gradient and channel geometry. Thick deposits

of organic material collect in depositional zones during the low-flow season. The oxygen

demand of these organic-rich sediments contributes to low dissolved oxygen conditions in the

river.

The Tualatin River is water quality limited for several chemicals and parameters including

phosphorus, dissolved oxygen, and temperature for which total maximum daily loads (TMDLs)

have been established. It is also designated as water quality limited for iron, manganese, and

arsenic, although TMDLs have not been established for these contaminants. Leachate contaminated

groundwater from the landfill potentially exacerbates these conditions due to depleted oxygen

levels, high chemical oxygen demand (COD), elevated phosphorus, iron, manganese, and arsenic.

9

2.3.4.2 Unnamed Creek

As described earlier, an unnamed perennial creek flows just east of the landfill and discharges to

the Tualatin River. Lakeside diverts some creek flow to fill and maintain the on-site ponds at an

elevation of 128 feet above mean sea level. The creek receives no direct discharges from the

landfill or the ponds. Based on groundwater elevation and water quality data, is does not appear

to receive any contaminated seepage from the shallow aquifer.

2.3.4.3 Stormwater

The landfill has an immature and underperforming evapotranspiration cover that allows a

portion of the incident precipitation to infiltrate. As a consequence, the ET cover significantly

reduces stormwater runoff; however, periods of heavy precipitation can produce overland flow

on some of the steeper landfill slopes and along access roads. The landfill itself does not have a

site-wide stormwater collection or treatment system. In 2009 Lakeside installed a localized

stormwater collection system and a lined stormwater holding pond along the landfill‟s northwest

boundary. The stormwater system is designed to capture stormwater from paved site access roads

and building roofs. Lakeside does not discharge the impounded stormwater, but instead uses it

to irrigate Lakeside‟s orchards and tree farms in summer months. There is no direct discharge to

surface water, and therefore, DEQ does not require a permit.

2.4 LANDFILL OPERATIONS

The Grabhorn family started the landfill operation in the early 1950s (Note: solid waste facilities

in the State of Oregon were not required to be permitted by DEQ until 1972). In 1972, Grabhorn

Incorporated and submitted a permit application for Lakeside. Later that year DEQ issued an

operating permit to Lakeside. The 1972 permit application indicates the landfill had a footprint

of approximately 7 acres. The permit restricted the fill to materials like construction/demolition

debris and tree prunings, although, Lakeside did receive case-by-case authorizations from DEQ

to take limited amounts of non-putrescible and non-hazardous industrial wastes.

Filling initially began in the landfill‟s southern portion and progressed northward until the

facility‟s closure in 2009. Waste and debris were trucked in and deposited within the landfill

working face. Lakeside then spread and compacted the waste with heavy equipment including

waste compactors. The DEQ permit required Lakeside to cover the compacted waste with

interim soil cover at the end of each week to help contain and stabilize wastes until they placed

final cover.

In 1991, Lakeside proposed using a type of alternative evapo-transpiration final cover to close

completed portions of the landfill. DEQ analyzed the cover‟s potential performance and

compared the proposal to conventional final soil covers. DEQ approved Lakeside‟s use of the

evapo-transpiration cover. The cover, vegetated with grass, shrubs, and various tree species

including poplars and pines, now covers approximately 37 acres of the landfill. Lakeside‟s

landfill closure permit required completion of the final cover for the entire 37 acre waste disposal

10

area in 2010. Lakeside has since planted the closed landfill with a mixture of deciduous and

coniferous trees.

Lakeside currently operates under a DEQ closure permit issued March 27, 2008. As specified in the

permit, the landfill stopped accepting waste on July 1, 2009. At closure, the landfill had a total

footprint of 36 acres. The landfill‟s original planned size was about 43 acres but the closure permit

required Lakeside to close early. Since its 2009 closure, Lakeside has accepted clean soils to bring

the landfill up to grade and to create a final soil profile that will support the cover system.

Lakeside started composting and recycling operation concurrent with the start of landfilling

operations. DEQ did not have a separate permit for composting until the late 1990s. In the late

1990s, Lakeside obtained a permit and operated the adjacent composting facility under a separate

DEQ solid waste facility permit. The recycling and composting operation, located northeast of the

landfill, continues to receive source-separated wastes and process yard wastes and woody debris.

Lakeside composts yard wastes, and grinds clean woody debris to produce wood chips that are used

for bio-filter bags, agricultural bedding, and other marketable products. Lakeside also continues to

accept recycled concrete and asphalt, which they use for maintaining onsite roads and for other on-

site and off-site construction projects and for sale, including stormwater control facilities.

2.4.1 Groundwater Compliance Monitoring

For many years, Lakeside‟s solid waste permit has required routine groundwater monitoring at

designated compliance points to identify leachate releases from the landfill. Quarterly groundwater

monitoring began in 1987 with two shallow wells (MW-3 and MW-4) installed downgradient of

the landfill, between its southern edge and the Tualatin River. Over time, Lakeside added additional

wells to the compliance network and by 1997 the number had increased to seven riverfront

compliance wells (MW-3, MW-4, MW-6, MW-7, MW-8, MW-9, MW-10), and one background

well (UG-1) to characterize up-gradient water quality (See Figure 7). While UG-1 is screened

within the Willamette Silt and weathered basalt hydrogeologic formations downgradient

compliance wells are completed into recent alluvial sediments, Although the two hydrogeologic

units have different properties and origins for most chemical parameters of interest the upgradient

wells approximate background water quality (pre-landfill conditions) in the channel and overbank

deposits.

In the late 1990s downgradient groundwater quality began to deteriorate significantly.

This trend included rapidly increasing concentrations of contaminants and leachate indicators in

compliance wells [See Figures 8, 9, 10 and 11]. Concentration trends of most constituents in

most wells appear to have flattened in the last 6 to 10 years, and VOC concentration trends (not

shown on the figures due to very low concentrations) have been relatively unchanged over the

last 10 years.

After performing a routine review of Lakeside‟s annual environmental monitoring reports, DEQ

informed Grabhorn Inc. in an August 2004 letter that: “The data indicates that contaminant

levels and indicator parameters in several compliance wells are exhibiting upward trends and

11

that in recent years various permit specific limit concentration2 have been exceeded,

consistently.” The data also indicated that numerous groundwater contaminants exceeded

surface water screening level values and/or ambient water quality criteria; threshold contaminant

concentrations considered protective of aquatic organisms and aquatic habitat. The contaminants

included: ammonia, chloride, calcium, iron, magnesium, zinc and the hazardous substances

barium, manganese, and selenium3. In addition, sampling consistently detected various volatile

organic compounds also called VOCs and other hazardous substances including: benzene,

tetrahydrofuran, 1,1 dichloroethane, and tert-butyl alcohol. However, VOCs are not identified as

chemicals of concern at Lakeside due to either very low concentrations relative to aquatic

screening levels or infrequent detections.

DEQ‟s August 2004 letter noted that nitrate exceeded a numerical groundwater quality reference

level standard and maximum contaminant levels for drinking water in the landfill‟s designated

upgradient well and asked Lakeside to develop a work plan and schedule for: 1) investigating

nitrate contamination, 2) determining groundwater action limits, and 3) monitoring surface water

quality. In response to the detection of nitrate at concentrations above its primary water quality

standard in former background well MW-5, Lakeside conducted an investigation to determine

the source and extent of the nitrate in 2005. The investigation included a sampling program of

MW-5, surface water, and direct push borings advanced near up-gradient of well MW-5. An

October 28, 2005 report documented the findings. The investigation concluded that the source of

the nitrate detected in MW-5 was not related to the landfill and the source, although uncertain,

appeared to up-gradient forestry and/or agricultural-related activities occurring of the well.

Beginning in early 2006, nitrate concentrations in monitoring well MW-5 decreased rapidly and

dropped below the water quality standard in 2007.

2 Based on the goal of preserving all groundwater in the state for its highest potential beneficial use ( typically presumed to be drinking water),

PSCLs previously specified in Lakeside‟s permit were human health and aesthetic (i.e. taste and odor) based.

3 It was later concluded that early detections of selenium were spurious and a consequence of bromide interference. However in 2009, several

years after implementing laboratory procedures to eliminate the interference, selenium was again detected above its SLV.

12

3. REMEDIAL INVESTIGATION

The remedial investigation incorporated multiple environmental data sources including: 1) the

results of historical and on-going groundwater and surface water monitoring required under their

solid waste permit, 2) surface water, sediment, and benthic organism studies within the Tualatin

River, 3) evaluation of the existing ET cover, and 4) results of human health and ecological risk

assessments. The Remedial Investigation was based on a conceptual site model that generally

applies to solid waste landfills. The investigation excluded soil sampling based on the presence

of the landfill cover and ambient air monitoring based on the absence of buildings on the landfill.

Each of these elements are summarized below.

3.1 CONCEPTUAL SITE MODEL

At the Lakeside site, construction and demolition debris, tree prunings, various industrial solid

wastes, and clean soil were filled over the top of 37 acres of floodplain and valley floor adjacent

to the Tualatin River. Precipitation, falling directly on the waste exposed in the working face of

the landfill during its years of operation, and infiltrating through what appears to be a poorly

performing ET final cover system, forms a leachate enriched with salts, metals, and organic

compounds. The leachate drains through the waste then mixes with and contaminates shallow

groundwater underlying the landfill. Depth discrete sampling of groundwater at the riverfront

indicated specific conductivity and total dissolved solids (TDS) decreased substantially at depths

greater than approximately 35 feet to 40 feet below ground surface (85 to80 feet above mean sea

level), or approximately 25 to 30 feet into the water table. As contaminated groundwater

emerges from beneath the landfill footprint it flows approximately 50 to 100 feet south before

seeping out into the main channel of the Tualatin River through sediment pores. Based on

hydrogeologic and geochemical conditions, DEQ presumes that attenuation of landfill

contaminants prior to discharge to the Tualatin is minimal.

3.2 COVER EVALUATION

Lakeside‟s solid waste disposal permit required that all landfill waste be covered on both an

interim and permanent basis to prevent nuisance conditions, minimize leachate generation, and

protect groundwater quality. As an alternative to the conventional low permeability soil cap

typically used at construction and demolition landfills, Lakeside capped the landfill with an ET

cover beginning in 1990. Conventional capping technologies rely on layers of soil and grass or

synthetic, impermeable membrane materials to prevent precipitation from infiltrating into the

waste. In contrast, the ET cover functions as a “sponge” to retain rainfall within the cap and then

relies on evaporation and tree/plant transpiration to minimize the volume of water infiltrating the

waste.

13

In 1989, when Lakeside first proposed using an ET cover, such covers were considered an

experimental landfill-closure technology. Since then, ET covers have been demonstrated to be an

effective method of capping landfills in arid and semi-arid climates. Lakeside initially planted

hybrid poplar trees on the cover at a density of one tree per 3.4 square feet. The ET cover

designer, Dr. Louis Licht, projected the tree canopy would close within 4 to6 years and achieve

optimal evapotranspiration rates, and result in approximately 1 inch per year infiltration or less.

Although in some areas of the cover trees have matured and the canopy is closed, over the

majority of the cover planted more than six year ago (anticipated period to reach canopy closure)

tree growth is stunted and tree mortality rates are high. The result, as the aerial photograph in

Figure 12 shows, is an ET cover with a patchy distribution of trees.

By several measures, the ET cover at Lakeside has not developed as expected; over significant

areas of the cover the original trees have suffered high mortality rates and many of the remaining

trees are stunted showing signs of rodent damage, disease and drought stress. This has resulted

in a cover that is patchy and sparse over significant sections of the landfill cover. The sparse and

patchy tree canopy and evidence of rodent damage, disease, and drought stress observed in the

living trees indicate the cover is not performing optimally to prevent leachate generation and the

associated groundwater contamination. Other potential problems include landfill gas, soil quality

and permeability/compaction and the reliance on deciduous trees that are dormant during the

rainy season and active during the dry season. In particular, poplars may not be well-suited to the

consistently dry summers and falls characteristic of this region. Lakeside subsequently

experimented with planting other tree species on the cover including willow and hybrid and

native Ponderosa pines to identify ones with characteristics more conducive to maintaining an

effective ET cover. Additional ongoing development and testing will correlate tree health to the

cover soil conditions.

At unlined landfills such as Lakeside the cover is the primary engineered feature preventing

groundwater contamination. The deteriorating groundwater quality at Lakeside suggests the

cover is inadequately controlling leachate generation. In 2005, DEQ requested Lakeside evaluate

the cover as part of the remedial investigation. In 2006, Lakeside installed six borings within

areas of the landfill that had received final cover to collect data on cover thickness, soil

permeability, and soil moisture content. The intent of this work was to evaluate the cover soil

characteristics with respect to maintaining an optimally functioning ET cover and to gather semi-

quantitative data that could be used to infer cover performance with respect to deep infiltration

rates. The six cover borings were later modified into 5 feet deep landfill gas monitoring wells. In

2007, Lakeside installed 4 landfill gas observation wells into the waste fill. The depth of the

observation wells range from 36 feet to 44 feet bgs and have 25-foot long screen completed in

waste fill. In 2008, Lakeside installed 6 soil gas probes adjacent to the landfill. The depth of

these soil gas probes range from 10 feet to 35 feet bgs. These investigations, and several others

conducted under the feasibility study, will provide information to assess and enhance the cover.

3.2.1 Cover Evaluation Results

The results of Lakeside‟s 2006 evaluation indicate the soil cover ranged from 1.5 feet to more

than 17 ft thick with an average thickness of more than 10 feet. For comparison, four feet of

cover soil was identified as minimum thickness necessary to store incident precipitation during

14

the trees dormant winter season. The average soil thickness appears adequate for the ET cover

design. In the areas where drilling identified thin cover, Lakeside has since added additional

material so that the cover thickness exceeds the minimum in all areas.

Permeability measurements collected by Lakeside at six locations indicate the 1 x 10-5

cm/sec

permeability requirement4 (applicable to conventional soil covers) was exceeded at three of the

locations with a maximum measurement of 1 x 10-3

cm/s. Since the ET cover does not meet the

low-permeability soil-cover specifications, it must rely on evapotranspiration as the primary

mechanism for minimizing leachate production. DEQ has been concerned that these more

permeable soils may not provide adequate moisture storage and retention to support tree growth

and may contribute to the drought stress observed in portions of the cover.

Soil moisture content was another parameter measured during the cover evaluation completed in

2006. The purpose of collecting this data was to construct soil moisture profiles and to determine

the “net” performance of the ET cover. Irrespective of the more indirect measures of the cover‟s

adequacy (i.e. permeability, thickness, etc.) are the combination of soil characteristics and ET

processes effectively preventing deep infiltration of percolating precipitation. The results of the

data collection found moisture levels at the base of the cover ranged from 70 to100 percent

saturation. These levels of saturation, measured in July of 2006, exceed the soil‟s field capacity

and indicate the cover was not effectively preventing moisture from infiltrating into the

underlying landfill waste. Additional testing and analysis being conducted under the feasibility

study will provide information to assess limitations of the cover and to develop measures to

enhance its performance.

In 2007, Lakeside began a study of landfill gas and oxygen concentrations within the cover. The

purpose was to gain a greater understanding of methane distribution and to characterize

conditions in the cover with respect to supporting tree growth. Six soil gas monitoring wells were

installed to a depth of 5 feet and monitored for methane and major gases. These six cover well

points constructed to measure in situ permeability as part of the cover investigation completed in

2006. The well points were subsequently modified and used to measure for the presence of

landfill gas. In five of the points average methane and carbon dioxide concentrations ranged

from 10-52 percent, and 13-38 percent, respectively. An important observation was that the

oxygen level in 5 of the 6 points was 0.0 percent for extended periods. This suggests that landfill

gas displacement of oxygen may be significantly retarding tree growth and contributing to high

tree mortality. Recent monitoring (2010) indicates that gas concentrations decrease and oxygen

concentrations increase in the upper several feet of the soil cover (See Section 3.6.1). Lakeside is

conducting additional testing to correlate tree health with the presence of landfill gas.

4 Permeability is a measure of the soil‟s ability to transmit fluids. The cited values equate to rates water will percolate downward through a

saturated soil.

15

3.2.2 Cover Evaluation Conclusions

The data collected confirmed the existing ET cover is not performing as designed and is likely

not sufficiently effective in preventing surface water infiltration through the cover and into the

waste. Lakeside and DEQ concluded additional study is necessary to more conclusively

determine the causes of tree mortality and identify remedies to improve cover performance. The

testing is ongoing.

3.3 GROUNDWATER

3.3.1 Plume Dimensions

At Lakeside all groundwater monitoring wells and piezometers are located along the landfill

perimeter. No groundwater monitoring wells are located within the landfill footprint. Absent

such wells, there is no effective means to identify specific source areas within the landfill that

may contribute to the groundwater contaminant plume. However, considering the existing

cover‟s ineffective performance, DEQ presumes that the entire landfill contributes

contamination.

Data indicates upgradient well UG-1 is uncontaminated (except for nitrate, the source of which is

likely upgradient agricultural activities), thus the contaminant plume is inferred to be less than

2400 feet long. At the Tualatin River, the plume‟s width (transverse to the direction of

groundwater flow) is approximately 1500 to 1600 feet, roughly 10 to20 percent greater than the

width of the landfill. Groundwater sampling from monitoring wells near the river and

reconnaissance borings indicate the vertical distribution of chemicals of interest. Depth-discrete

sampling at two locations downgradient of landfill in 2006 indicates specific conductivity and

total dissolved solids decrease substantially at depths greater than 35to 40 feet below the ground

surface, or about 20 to 30 feet into the water table. These measurements are indicators of the

depth of landfill related impacts. [See Figure 13].

The approximate “locality of the facility” is shown in Figure 6. Although the plume is located

mainly within the landfill boundaries, groundwater along the landfill‟s western margin appears to

flow in a southwesterly direction relative to the rest of the shallow groundwater system and the

contaminant plume. This flow pattern tends to push contaminated groundwater westward beneath

private agricultural land. An area mapped as wetlands5 by the U.S. Fish and Wildlife Service lies

downgradient of the groundwater plume‟s southwestern lobe. A flow analysis conducted by

Lakeside as part of the remedial investigation asserted groundwater flowing beneath the landfill

does not migrate to the wetland to the west. These findings have not been verified in the field

and are inconsistent with groundwater monitoring results that indicate the presence of landfill-

related contamination in piezometer P-2, the closest monitoring point located upgradient of the

wetland. Water quality data collected from P-2, suggests the wetland may be within the LOF of

the landfill. DEQ previously requested Lakeside to collect field data to determine the extent of

5 Figure x, adapted from the National Wetland Inventory, U.S. Fish and Wildlife Service. www.fws.gov/nwi/

16

the off-site plume and validate their model of shallow groundwater flow. DEQ expects Lakeside

to conduct additional monitoring and investigation under the remedial design and remedial action

to clarify hydrology in this part of the site.

3.3.2 Plume Chemistry

Total dissolved solids, alkalinity, hardness and chloride levels are significantly elevated in

groundwater relative to natural background (typically an order of magnitude higher). Redox

conditions are depressed and dissolved oxygen levels are depleted. The plume also exhibits

elevated concentrations of ammonia, metals, phosphorus, total organic carbon and trace to

moderate levels of Volatile Organic Compounds (Tables 1 and 2).

VOCs are absent in upgradient (background) groundwater. Consequently, DEQ assumes VOCs

in downgradient groundwater emanate from the landfill. Most VOCs including benzene,

tetrahydrofuran, and 1,1 DCA are consistently detected at trace concentrations and generally near

or below the most stringent human health and ecological risk-based cleanup levels. One

exception is, tert-butyl alcohol which ranges as high in concentration as 300 parts per billion

(ppb) and is more widely distributed throughout the compliance well network than other VOCs.

There have been sporadic detections of semi-volatile organic compounds such as bis-hexyl-

phthalate in compliance wells. Typically, however, the results are not repeatable and suggest the

source may be lab contamination. In addition, there usually are from 400 to 600 ppb of

undifferentiated organic compounds in groundwater samples. Their nature and source are

unknown, but a portion of these contaminants may relate to non-hazardous organic compounds

such as humic and fulvic acids. Because semi-volatile organic compounds are detected

infrequently at concentrations below risk-based levels, they are not considered to be chemicals of

concern at Lakeside.

Metals such as iron, magnesium, manganese and zinc occur naturally and detectable levels are

present in the background/upgradient well UG-1. However, as groundwater passes beneath the

landfill, mixes with landfill leachate, and reaches the downgradient compliance wells these

metals increase greatly in concentration, many by a factor of 10 or more (See Table 3).

Detections of selenium have varied over time, and sometimes exceed DEQ‟s screening level and

EPA‟s national recommended ambient water quality criterion of 5 ppb. However, the observed

levels are near the analytical method‟s quantification limits and there have been some spurious

detections of selenium previously reported at Lakeside that were later determined to have been

caused by chemical interference. Mercury has been detected in only one sample since 2005 at a

concentration just above the reporting limit and at a concentration less than the ecologic

screening level.

DEQ assumes the metals detected in groundwater at Lakeside‟s compliance wells have two

sources, the landfill waste itself and the native soils the waste was placed on. Under natural

conditions, metals are primarily bound up in minerals present in the soil that are only slightly

soluble in groundwater. However at Lakeside, landfill leachate has altered the groundwater

geochemistry by depleting oxygen and creating chemically reduced conditions. Under reducing

conditions otherwise immobile metals become more soluble and mobile and their concentration

17

increases in groundwater. The same mechanism has mobilized metals within the landfill waste

itself.

3.3.3 Other Contaminants and Physiochemical Conditions

Barium, calcium, and ammonia concentrations in compliance wells significantly

exceed background levels. The Tualatin is water quality limited for dissolved

oxygen from May through October, and TMDLs have been established for

ammonia as it relates to oxygen depletion.

Cyanide concentrations sporadically exceed the ambient water quality criteria for

free cyanide (the most toxic form of cyanide). Cyanide‟s toxicity varies greatly

depending on its chemical state. At Lakeside, the cyanide‟s chemical form is

unknown.

Phosphorus concentrations in compliance wells also exceed background levels.

Although slow seepage rates limit the Tualatin River‟s mass loading by

contaminated groundwater, phosphorous concentrations typically exceed DEQ‟s

TMDL (background concentration) for the Tualatin of 0.17 mg/L.

In 2007 Dissolved oxygen levels in UG-1 averaged 6.6 mg/l. ODEQ Table 21

Dissolved Oxygen & Intergravel Dissolved Oxygen Criteria (2/22/07) indicates 6.5

milligrams/liter dissolved oxygen provides optimal conditions for supporting cool

water aquatic habitat. DEQ has characterized as “cool water” aquatic habitat the

Tualatin reach that includes Lakeside. Lakeside‟s background water quality

indicates that natural DO levels will support the river‟s cool water habitat.

However, as groundwater passes beneath the landfill and mixes with leachate,

dissolved oxygen levels decline and become significantly depressed. The result is

anoxic groundwater with high chemical oxygen demand. DO levels in MW-3, MW-

8, and MW-10 in 2007 averaged 0.9 milligrams/liter, 1.1 milligrams/liter, and 1.2

milligrams/liter, respectively. As indicated in Table 3 the dissolved oxygen levels in

riverfront wells are below the threshold required to support cool water aquatic

habitat.

Lakeside‟s low dissolved oxygen in groundwater is associated with high chemical oxygen

demand levels. This chemical-affected groundwater represents an oxygen sink to the aquatic

environment. Since 2008, chemical oxygen demand averaged less than 5 milligrams/liter in up-

gradient well UG-1, as compared to 236 milligrams/liter, 230 milligrams/liter, and 392

milligrams/liter in down-gradient wells MW-3, MW-9 and MW-10, respectively. Note: historic

highs have been as great as 500 mg/l along river front wells. For comparison, chemical oxygen

demand in untreated domestic wastewaters range 250 to1000 mg/l (Metcalf and Eddy, 1991).

18

3.4 CONTAMINANT FATE AND TRANSPORT

Lakeside‟s downgradient monitoring wells are located 35 to 75 feet from the Tualatin River.

Considering this small separation distance and the hydrogeological and geochemical

environment along the plume‟s transport pathway, DEQ concluded that most contaminants

undergo minimal attenuation before entering the river‟s shallow sediment benthic environment.

3.4.1 Chemical Attenuation

As observed during the Lakeside remedial investigation and documented by the USGS and

others, the Tualatin‟s sediment environment is highly reducing. Under these oxygen deficient

conditions many of the contaminants mobilized by reducing conditions (i.e. arsenic, iron,

manganese, zinc) in and beneath the landfill are unlikely to precipitate out of groundwater along

its flow path to the river. VOCs such as tetrahydrofuran tend to be more persistent under

reducing conditions and are also expected to migrate the relatively short distance to the river.

Chloride, a stable, highly soluble anion is also expected to enter the benthic environment

relatively unchanged, because chloride transport is not chemically attenuated by any known

natural mechanisms.

3.4.2 Mixing and Dilution

Mixing and dilution of contaminated groundwater is not anticipated to be a significant

attenuation mechanism at Lakeside. USGS and Lakeside estimates of groundwater flux rates at

the downgradient boundary of the landfill, when compared to estimated seepage rates through

the channel bottom, suggest most of the water discharged to the Tualatin River along the landfill

reach consists of leachate contaminated groundwater. Furthermore, the strong upward hydraulic

gradient within river sediments observed by the USGS indicates there is minimal mixing of

groundwater with surface water before it reaches the benthic environment.

3.5 SURFACE WATER

3.5.1 Tualatin River

Between 2004 and 2006, Lakeside collected samples of river water to determine if contaminated

groundwater discharges were impacting the Tualatin‟s water quality. In the fall of 2004 and in

the spring and summer of 2006 Lakeside sampled the river at four locations [See Figure 7]

adjacent to the landfill. This effort provided data on site contaminant concentrations in the river

water-column for a range of river flow conditions.

The testing results indicated that downstream concentrations of calcium, magnesium, iron, and

manganese consistently exceeded upstream concentrations by 10 to45 percent. Concentrations of

barium and ammonia, were essentially uniform along the landfill reach while zinc levels

consistently declined over this section of the river. Ammonia and barium exceeded ambient

water quality criteria and/or DEQ screening level values during two of the monitoring events and

manganese exceeded these criteria during one monitoring event. All other compounds were well

below their respective aquatic screening levels.

19

Discussions with US Geological Survey staff (Stuart Rounds, August 22, 2008) confirmed that:

1) the Tualatin River‟s water quality near Lakeside varies unpredictably over short times frames,

and 2) The Rock Creek wastewater treatment plant discharges strongly influence the river‟s

overall water quality. Because of these conditions, it is difficult to determine how possible

discharges of contaminated groundwater might impact surface water quality. Moreover, the

treatment plant effluent is the likely the predominant source of the river‟s elevated ammonia

concentrations. After evaluating these conditions and observations, DEQ allowed Lakeside to

discontinue their surface water sampling program.

Available data indicates that most landfill contaminants have acceptable levels within the river‟s

surface water column. Ammonia and barium are exceptions, but DEQ does not attribute their

uniformly elevated concentrations along the landfill reach to landfill impacts. Manganese is the

only element with downstream concentrations that are significantly elevated relative to upstream

concentrations and which also exceed DEQ ecologically-based screening level values for

surface water. The following qualifiers should be considered when evaluating surface water

data collected at Lakeside:

All sampling points were potentially within the influence of the landfill and contaminated

groundwater discharges. Consequently, upstream/baseline conditions may be represented

inaccurately and associated conclusions lack certainty.

The Remedial Investigation did not evaluate the vertical or lateral distribution of

contaminant levels within the Tualatin River water column.

The data does not reflect pore-water chemistry and conditions within the benthic

environment.

The primary environmental concern related to groundwater contamination from Lakeside is its

potential adverse impact on aquatic organisms, particularly those inhabiting the Tualatin River‟s

channel sediments (benthic environment) and nearby wetlands. Another concern is that

contaminated groundwater emanating from Lakeside is exacerbating the Tualatin River‟s well

documented water quality problems.

3.5.2 Unnamed Creek

In November 2005, Lakeside sampled water from the unnamed creek east of the landfill and

analyzed the samples for ammonia, nitrate, phosphorus, TDS, and several other water quality

parameters. Ammonia was not found in any sample (although nitrogen as nitrate is detected), and

other parameters reflected relatively good water quality conditions. The one exception, nitrate,

was significantly elevated relative to typical surface water concentrations. The highest

concentrations were upstream of the landfill and the concentration trend as the creek approaches

the Tualatin River indicates elevated levels are not related to the landfill.

20

3.5.3 Landfill Seep

In August 2006, Lakeside sampled a seep located near staff gauge SG-1. The results indicate that

landfill contaminants ammonia, barium, iron, and manganese significantly exceeded background

concentrations (based on recent data from UG-1 and past data from MW-5) and their respective

DEQ screening level values.

The sample‟s general chemistry including elevated total dissolved solids, low redox potential,

and depleted oxygen indicate the seep is leachate impacted.

The seep represents a direct, albeit small, discharge of leachate contaminated groundwater to the

Tualatin River.

The ground near the seep was clear of trees and underbrush, and the exposed seep easy to see.

Areas further upstream of the seep are heavily vegetated, potentially obscuring other active

seeps.

3.6 SOIL

The long-term landfill operations involved placing clean cover soils over non-hazardous solid

waste. Therefore, no contaminated soil is anticipated at or near the surface. Furthermore, DEQ

and Lakeside have not observed chronic or perennial landfill-related seeps that would

contaminate surface soils.

3.6.1 Landfill Gas and Methane

The DEQ closure permit requires Lakeside to conduct landfill gas monitoring in soil gas probes

to evaluate the distribution of methane concentrations and pressures in and around the landfill.

The main focus of Lakeside‟s landfill gas monitoring program is to monitor for methane soil-gas

concentrations around the landfill perimeter and near onsite structures.

The gas monitoring network includes six compliance probes located as follows: three probes

(SGP-1, SGP-2 and SGP-3) along the landfill‟s western boundary; one probe (SGP-4) in the

large equipment storage building next to Lakeside‟s shop; one probe (SGP-5) near the landfill

scale house; and one probe (SGP-6) north of the landfill near piezometer P-7. In addition, four

landfill gas observation wells are located within the landfill footprint. These observation wells

provide information about the methane generation rates and gas pressures within the landfill

itself.

Initially, Lakeside monitored the six compliance probes on a monthly frequency to assess gas

generation and migration trends under worst-case winter weather conditions. After establishing

this database and assessing trends, Lakeside reduced the monitoring frequency to a quarterly

schedule. Lakeside‟s compliance monitoring has detected methane in two compliance probes,

SGP-2 and SGP-5. Typical methane concentrations in SGP-2 vary from about 35 percent to

about 47 percent by volume. Although these concentrations greatly exceed the methane

compliance limit of 5 percent by volume (which is a condition of potential concern if there could

be gas migration to structures), static pressures in this probe have been minimal, suggesting low

21

potential for lateral migration in subsurface soils. In addition, SGP-2 is located next to un-

developed property in Lakeside‟s ownership that serves as a buffer to neighboring, developed,

properties.

Methane concentrations in SGP-5 vary from 0 percent to about 16 percent by volume. Although

these methane concentrations also exceed the 5 percentcriterion, and could pose a potential risk

to the existing scale house structure, Lakeside indicates they keep the scale house open to

maintain adequate ventilation.

Methane concentrations in the landfill observation wells (GP-1, GP-2, GP-3, and GP-4) have

been consistent across the landfill and indicative of typical landfill-source conditions (52 percent

to 57 percent methane by volume). Static pressures have been low at these wells suggesting that

overall landfill gas generation rates also are relatively low. The landfill‟s high internal methane

concentrations, though, may adversely impact tree growth and survival on the ET cover.

Attempts to enhance the ET cover‟s tree growth and performance must consider and potentially

mitigate landfill gas related impacts.

3.7 TUALATIN RIVER SEDIMENT

3.7.1 Sediment Chemistry

In February 2009, Lakeside sampled sediment from three separate river reaches approximately

1400 feet in length. Lakeside collected forty-four grab samples at about 100 feet intervals in 10-

19 feet of water between the north river bank and the center of the channel. These samples were

analyzed for site contaminants ammonia-nitrogen, barium, calcium, chloride, magnesium,

manganese, and zinc. Review of the data indicates that concentrations of some constituents

(ammonia, barium, chloride and manganese ) where higher in sediments from the landfill and/or

downstream reaches than in sediments from the upstream (reference) reach, but except for one

case, the differences were not statistically significant, and it is not clear whether any differences

are caused by the landfill. Chloride (an anion) in particular may not be readily attenuated in

localized areas.

When Lakeside submitted its Tualatin River Sediment Sampling report to DEQ, sediment

ecological screening values to protect aquatic organisms existed for iron, manganese and zinc.

The iron concentration exceeded its sediment SLV in the upstream and downstream reaches.

Manganese exceeded its screening level value in the downstream reach only.

Overall, within the landfill and downstream reaches there appeared to be some increase in

landfill related contaminants in sediments relative to samples collected within the upstream

reference/baseline reach. In particular, DEQ considers the detection of chloride along the landfill

reach as evidence that contaminated groundwater is reaching the benthic environment

(biologically active zone) relatively un-attenuated. Chloride was observed at concentrations up to

210 milligrams per kilogram in sediment sampled along the landfill reach of the river. DEQ

calculated a chloride concentration in sediment pore water assuming the chloride was dissolved

in water consistent with chloride‟s chemical properties and the sediment‟s origin and

characteristics. DEQ calculated chloride concentrations in pore water were consistent with

22

levels measured in groundwater compliance monitoring wells located near the river, which

exceed ambient water quality criteria of 230 milligram/liter.

3.7.2 Benthic Macroinvertebrate Survey

In the summer of 2007, Lakeside conducted a benthic macroinvertebrate bioassessment study as

an alternative to a porewater study to determine if macroinvertebrate (i.e. aquatic insects, worms,

freshwater shellfish) communities located adjacent to and downstream of Lakeside differed from

upstream communities. The sampling included two approaches: fixed-area, sediment grab

samples; and fixed-time samples. The fixed-area sediment grab samples were collected at

random locations along a fixed transect established in each of the five reaches studied. The fixed-

time samples used a fixed level of effort (30 minutes) to sample common microhabitats present

within the study area.

The resulting data showed almost identical macroinvertebrate populations in each of the reaches

studied. The results of this investigation do not indicate that activities associated with the

Lakeside Landfill are affecting invertebrate assemblages in aquatic habitats located adjacent to,

or directly downstream of the Landfill, as compared to upstream conditions. The survey,

however, also concluded that the river‟s macroinvertebrate populations consisted mostly of

“pollution tolerant” to “highly pollution tolerant” species that reflect a highly degraded habitat.

DEQ concluded the widespread degradation rendered the benthic invertebrate study inconclusive

and not useful for determining if the landfill has impaired the shallow groundwater‟s recognized

beneficial use (sustaining aquatic habitats). Subsequently, DEQ informed Lakeside that

groundwater/pore water chemistry should be the sole basis for such a determination.

3.7.3 Ambient Air

The low level of VOC concentrations detected in groundwater monitoring wells at Lakeside are

well below conservative DEQ screening levels developed to protect outdoor air quality.

Consequently, DEQ has not required Lakeside to conduct ambient air sampling.

3.8 RISK ASSESSMENT

Lakeside‟s risk assessment results for human health and potential ecological receptors are

summarized below. More detail is available in Level I Scoping Ecological Risk Assessment,

Lakeside Reclamation Landfill, URS, 2007; Screening-Level Human Health Risk Assessment &

Level II Screening Ecological Risk Assessment, URS/Parametrix, 2009 ]. The residual risk

assessment for the recommended remedial action alternative is summarized in Section 6.2 of this

document.

3.8.1 Human Health Risk Screening

The human health risk screening was based on the conceptual site model and land and water use

identified in the vicinity of the landfill (see Sections 3.1 and 2.4). Groundwater, surface water

and sediment were the media where human exposure could occur. Since the Tualatin River has a

beneficial use for fish consumption, this pathway was also considered a potentially complete

exposure pathway.

23

The risk assessment used the following three criteria to identify chemicals of concern at

Lakeside: 1) frequency of detection, 2) exceedence of background concentrations and, 3)

exceedence of a risk-based concentration. Based on these criteria, arsenic, benzene and zinc were

identified as chemicals of concern. First, the contaminant concentrations for each environmental

medium were compared with conservative risk-based screening level values to determine which

media and contaminants posed potential risk to human health.

If concentrations of chemicals detected in a particular medium did not exceed the screening

levels, that medium was eliminated as a medium of potential concern and was not evaluated

further. Chemicals and pathways that exceeded the screening levels were carried through for

detailed evaluation in the baseline risk assessment. The risk assessment evaluated contaminant

concentrations in groundwater based on data collected between April 2004 and July 2007.

A brief summary of the results for each environmental medium is provided below:

Sediment – No sediment samples exceeded human health screening levels.

Solid Wastes – The landfill‟s typical operating procedure (consistent with permit

conditions), involved placing clean cover soils over non-hazardous solid waste.

Therefore, DEQ does not expect contaminated soil to be present at or near the surface.

Furthermore, no chronic or perennial groundwater seeps that could contaminate surface

soils have been observed on the landfill.

Methane monitoring in the form of soil gas sampling has been conducted by Lakeside to

evaluate the distribution of methane concentrations and pressures in and around the

landfill. The monitoring results indicate that no onsite structures, offsite properties, or

offsite structures are currently at risk from methane migration. Considering the high

methane concentrations within the landfill, however, and the unpredictability of landfill

gas migration, the DEQ closure permit requires Lakeside to continue methane

monitoring indefinitely and re-evaluate the program periodically to assure that

conditions remain safe.

Surface Water – No Contaminants of Interest (COIs) were detected in surface-water

samples at levels that exceeded applicable screening levels.

Bioaccumulation and Fish Ingestion - The risk assessment completed by URS

dismissed the potential fish-ingestion pathway based on assumed significant dilution

and attenuation occurring in the water column.

Groundwater - Lakeside‟s human health screening indicated the arsenic groundwater

concentrations exceeded the screening level for trench worker direct contact exposure

due to an error in concentration units. However, the actual DEQ screening level is 5.8

milligrams/liter or a factor of 1000 higher than the level used in the risk screening.

Arsenic concentrations in groundwater have never been above the screening level.

Consequently, this pathway does not lead to unacceptable risk for worker exposure.

24

Site groundwater exceeds EPA tap water regional screening levels for the following

contaminants: arsenic, benzene, iron, manganese, and zinc. Tert-butyl alcohol is

another groundwater contaminant of concern. Although EPA and DEQ have not derived

regulatory or risk-based screening levels for tert-butyl alcohol, the California Health

Hazard Assessment established a notification level of 12 micrograms/liter for this

contaminant. Lakeside‟s groundwater concentrations of tert-butyl alcohol consistently

exceed California‟s notification level.

Hydrogeologic conditions and historic patterns of groundwater use indicate

groundwater contaminants emanating from the landfill will not affect domestic or

agricultural supply wells located in the vicinity of the site. As indicated by a

comparison of static water levels in wells completed into the Columbia River Basalt

and shallow groundwater monitoring wells completed at the site, shallow groundwater

within the valley fill sediments are not hydraulically connected to the water-bearing

zones within the Columbia River Basalt group preventing contamination from migrating

into these aquifers. Hydraulic gradients within shallow groundwater occurring beneath

and downgradient of landfill further prevent deep migration of contamination and

isolate shallow groundwater from the productive aquifers of Columbia River Basalt

group. Consequently, DEQ has concluded groundwater within the Columbia River

Basalt group is outside (or more appropriately, below) the site locality of facility.

To summarize, Lakeside‟s risk assessment carried forward and evaluated specific chemicals and

media that exhibited complete risk pathways. Accordingly, Lakeside screened out arsenic,

benzene and zinc from the groundwater pathway. The remaining media and chemicals did not

exceed acceptable human-health risk levels and were dropped from any further assessment. A

conceptual site model for human health exposure to site contaminants is presented in Figure 14.

Based on the above analysis and site conditions, DEQ concludes that the site does not pose

unacceptable human health-risks to site-related contaminants.

3.8.2 Ecological Risk Assessment

The ecological risk assessment was completed in accordance with Oregon Department of

Environmental Quality, Guidance for Ecological Risk Assessment, April 1997. Lakeside

conducted a level I ERA in 2007 (URS/Parametrix, 2007) that indicated further assessment was

necessary. In response, Lakeside submitted a draft Level II ERA in December 2007 and a revised

Level II ERA in July 2009. The ERA screened Chemicals of interest for their potential impacts

to ecological receptors by comparing site concentrations measured at downgradient compliance

points to generic screening criteria. This process identified chemicals of potential ecological

concern. The screening method used maximum detected concentrations of contaminants in

relevant media to assess potentially unacceptable risks to stationary biota (i.e. freshwater clam)

and compared the 90 percent upper confidence limit of the mean contaminant concentrations to

screening criteria for mobile aquatic receptors. The ratio of the exposure point concentration to

the aquatic standard or screening level value depicts the degree of impairment or adverse

ecological impacts. This ratio is defined as a hazard quotient. A hazard quotient exceeding one

indicates a potential significant risk to ecological receptors from exposure to that compound. The

sum of the hazard quotients provides a measure of overall toxicity posed to the ecological

25

receptor. Some contaminants have hardness-dependent toxicity. The concentrations of such

contaminants were adjusted consistent with EPA guidance (EPA, 2006c (ERA), Appendix B)6.

The risk assessment also considered general water quality parameters associated with landfill

leachate-impacted groundwater to determine potential effects on the Tualatin River‟s ecological

receptors. This list of parameters, referred to as physiochemical parameters, includes: total

dissolved solids, dissolved oxygen, phosphorus, chloride, pH, temperature and specific

conductance.

3.8.2.1 Chemicals of Concern.

The chemicals of ecological concern at Lakeside are: ammonia, barium, calcium, chloride, iron,

magnesium, manganese and zinc [See Table 4]. Additional chemicals without established SLVs

will also be monitored.

3.8.2.2 Physiochemical Conditions of Concern

Because this reach of the Tualatin River is classified as “cool water habitat” and total maximum

daily loads (TMDLs) are established for the Tualatin, the risk assessment also evaluated the

impact of dissolved oxygen and phosphorus levels in groundwater.

3.8.2.3 Pathway Analysis

The exposure pathway for ecological receptors results from contaminated groundwater

discharging to surface water [See Figure 15]. Groundwater concentrations are assumed to be

undiluted as they enter the river‟s benthic environment (e.g. porewater concentrations are equal

to groundwater concentrations measured at riverfront compliance wells).

Although certain contaminants exceeded their respective aquatic screening level values, the

distribution of chemical concentrations in sediments does not allow a definitive identification of

the source. Furthermore, the magnitude of the impacts does not indicate a need for remedial

action. Based on these factors, DEQ is not requiring additional sediment sampling at this time.

3.8.2.4 Cumulative Risk.

Cumulative ecological risks are summarized in the Table 5. Contaminants in groundwater with a

hazard quotient significantly exceeding one, which is the threshold for potential toxicity, include

ammonia-nitrogen, barium, calcium, chloride, iron, manganese, and zinc. The cumulative sum

of the hazard quotients is 395, indicating sediment dwelling organisms are likely to be harmed if

exposed to groundwater discharging through the river‟s sediment bed.

6 Typically, the hardness referred to in these calculations is that of the receiving water not the discharging water as was done by URS. However,

the conceptual site model indicates groundwater is unmixed with surface water as it enters the benthic environment, therefore, modifying hardness dependent concentrations based on the discharging water chemistry is appropriate.

26

3.9 IDENTIFICATION OF HOT SPOTS

The criteria used to evaluate remedial alternatives for groundwater and surface water depend on

whether a “hot spot” is present or not, as determined by a loss of “current or reasonably likely

future” beneficial use of the water resource.

OAR 3401-122-115(9) defines beneficial uses of water as:

Any current or reasonably likely future beneficial use of groundwater or surface water by humans or

ecological receptors.

OAR 340-122-115(32) defines hot spot of contamination as:

(a) For groundwater or surface water, hazardous substances having a significant adverse effect on beneficial uses of

water or waters to which the hazardous substances would be reasonably likely to migrate and for which treatment is

reasonably likely to restore or protect such beneficial uses within a reasonable time, as determined in the feasibility study; and

(b) For media other than groundwater or surface water, (e.g., contaminated soil, debris, sediments, and sludges;

drummed wastes; "pools" of dense, non-aqueous phase liquids submerged beneath groundwater or in fractured bedrock;

and non-aqueous phase liquids floating on groundwater), if hazardous substances present a risk to human health or the environment exceeding the acceptable risk level, the extent to which the hazardous substances:

(A) Are present in concentrations exceeding risk-based concentrations corresponding to:

(i) 100 times the acceptable risk level for human exposure to each individual carcinogen;

(ii) 10 times the acceptable risk level for human exposure to each individual noncarcinogen; or

(iii) 10 times the acceptable risk level for exposure of individual ecological receptors or populations of ecological

receptors to each individual hazardous substance.

(B) Are reasonably likely to migrate to such an extent that the conditions specified in subsection (a) or paragraphs (b)(A) or (b)(C) would be created; or

(C) Are not reliably containable, as determined in the feasibility study.

The shallow groundwater system located beneath the southern half of the landfill and extending

to midline of the Tualatin River channel is a potential hot spot. At this location, groundwater

contaminant concentrations exceed levels considered protective of aquatic organisms and

adversely impact the beneficial use of groundwater (sustaining aquatic habitat). A hot spot of

contamination is defined in OAR 340-120-115(32). The approximate location of the groundwater

hot spot is described in Figure 16. Figure 16 approximates the hotspot area based on an

interpolation and extrapolation of available groundwater quality data. The hotspot boundaries

will be further refined based on additional groundwater data collected during the remedial design

phase of the project.

27

4. DESCRIPTION OF REMEDIAL ACTION ALTERNATIVES

This section describes the remedial action objectives, protective levels and regulatory requirements

or considerations used in developing the remedial action alternatives to address the unacceptable

risk posed by shallow groundwater contamination discharging to the Tualatin River. The evaluation

of the alternatives follows in Sections 5 and 6.

4.1 REMEDIAL ACTION OBJECTIVES

DEQ developed acceptable risk levels, as defined in OAR 340-122-115(1) through (6), and

remedial action objectives based on the identified beneficial uses, exposure pathways and the

risk assessment.

4.1.1 Risk Based Concentrations

DEQ established risk-based concentrations and screening level values (See Table 6) in

micrograms per liter (parts per billion) for groundwater and surface water to protect the

identified beneficial uses and potential receptors. These are considered preliminary remedial

action levels that may be modified based on one or more of the following: 1) water hardness

(according to Table 20 guidance), 2) temperature and pH (according to guidance presented in

EPA-822-R-99-014), and/or 3) site-specific background water quality data.

4.1.2 Remedial Action Objectives

DEQ developed site-specific remedial action objectives (RAOs) for landfill cover performance

and groundwater cleanup. OAR 340-122-040 requires the RAOs to protect human health,

ecological receptors, and beneficial uses. The RAOs for the site are as follows:

RAO #1 - Prevent further degradation of groundwater quality beneath the landfill

RAO #2 - Protect the Tualatin River‟s surface water beneficial uses by preventing current

or future discharge of contaminated groundwater that would result in violations of

ambient water quality criteria, total maximum daily load, or applicable risk-based criteria.

RAO#3 - Treat the groundwater hot spot of contamination to the extent feasible, as

specified in OAR 340-122-090(4).

4.2 GROUNDWATER PLUME AREA AND VOLUME

The area of potential groundwater contamination subject to remedial action is approximately 60

acres, with an estimated volume of 1.7 million cubic feet.

28

4.3 APPLICABLE REQUIREMENTS

The following regulations were identified by DEQ in the evaluation of the FS and development

of the proposed remedial action for the facility:

4.3.1 Oregon Solid Waste Management (ORS 459 and OAR 340-93 and 340-95).

This statute and implementing rules govern the management of solid wastes, including the

permitting of disposal sites, and are applicable to the off-site management of contaminated soils

that are not hazardous wastes.

4.3.2 Oregon Water Pollution Control Act (ORS 468B).

This act and the implementing administrative regulations (OAR 340-45) govern discharge of

pollutants to surface waters. The act incorporates the federal Clean Water Act programs

including the National Pollution Discharge Elimination System (NPDES) permitting program.

These regulations would be applicable to any alternative involving discharge of treated

groundwater to the Tualatin River. Pursuant to OAR 340-045-0062, the DEQ may issue an order

in lieu of to an NPDES permit, or exempt the NPDES permit requirement under ORS

465.315(3).

4.3.3 Oregon Water Quality Standards (ORS 468B and OAR 340-41).

The state-wide water quality management plan under OAR Chapter 340, Division 41, specifies

beneficial uses, policies, standards and treatment criteria for Oregon. These standards protect

aquatic life and public health, and are applicable to the site as recharge to the Tualatin River is

one of the beneficial uses of groundwater. Beneficial uses specified in these rules were used in

the identification of remedial action objectives and groundwater cleanup levels for the facility.

4.3.4 Oregon Groundwater Quality Protection Act (ORS 468B).

This act and the implementing administrative regulations (OAR 340-40) constitute Oregon's

groundwater protection program. The program incorporates federal Safe Drinking Water Act

requirements and maximum contaminant level (MCL) standards. The groundwater protection

program policy states that the rules are not to be used as cleanup standards, but they may be used

to evaluate non-degradation of existing groundwater resources subject to the requirements of

Lakeside‟s closure permit. The groundwater protection act would apply to land application of

extracted groundwater.

4.4 LANDFILL COVER REMEDIAL ACTION ALTERNATIVES

Candidate technologies to address RAO #1, infiltration control to restore groundwater quality

beneath the landfill, include 1) no action, 2) replacement of the existing cover with an

impermeable membrane, and 3) enhancement of the existing ET cover. All remedy components

will be subject to performance monitoring and complemented by the Adaptive Management

Program (See Section 7.2).

29

4.4.1 Alternative 1: No Action

The landfill‟s existing ET cover consists of patchy stands of poplars, willows and conifers. The

trees range in age (years since planted) from 1 to 21 years old. Much of the landfill cover was

recently closed and planted with young poplar and pine trees in 2010. The older distressed stands

of trees and the newly planted areas leave much of the landfill footprint devoid of tree cover.

Under this no-action alternative the existing ET cover would not be modified or enhanced.

No action would be taken to augment or enhance the existing ET cover or improve cover

performance. This alternative does nothing to reduce current or future rates of infiltration,

leachate generation, or mitigate existing groundwater contamination beneath the landfill.

The total projected cost of this remedy alternative is $2 million, which represents the cost for

maintaining the ET cover as required under the landfill closure permit.

4.4.2 Alternative 2: Impermeable Cap

Modern municipal solid waste landfills commonly are capped with an impermeable

geomembrane barrier layer to prevent or minimize infiltration of precipitation into the underlying

waste, thus limiting the production of leachate. A typical MSW landfill cap is multi-layered

consisting of a gas-venting layer, a low permeability barrier layer (i.e. compacted soil,

geosynthetic clay liner and/or a geomembrane), a drainage layer, and a vegetated top-soil layer.

Construction of an impermeable cap would require complete removal of the existing vegetative

cover and regrading of the cover surface. The existing mixture of trees, shrubs and grasses would

likely be replaced with a mono crop of shallow rooting grasses. Construction of an impermeable

cap would eliminate pathways for landfill gases to vent to the atmosphere. To mitigate gas

buildup and gas migration away from the landfill, an active gas collection system would likely

be incorporated into the cap design and maintained for an indeterminate period. Furthermore,

water storage capacity in the cover, and removal through evapotranspiration would be greatly

reduced compared to the existing ET cover. Installation of an impermeable cap would likely

require construction and operation of a stormwater collection and disposal system.

The estimated total cost of the remedy is $8 million.

4.4.3 Alternative 3: Enhancement of the Existing ET Cover

Properly designed and maintained ET covers can prevent or minimize drainage of precipitation

through the cover and into the waste. An ET cover consists of a layer of soil and mixed

community of grasses, shrubs and trees. Some of the incident precipitation is intercepted by the

vegetation and directly evaporates off of leaves and branches to the atmosphere. The component

of precipitation that does infiltrate the surface is held by the cover soil like a sponge and is

subsequently taken up by the trees through transpiration. Deciduous trees, like the poplars

planted at Lakeside dry out the soil cover in the summer, creating storage capacity in the soil for

water falling as precipitation during the trees dormant winter period. Alternatively, conifers can

be used to provide year round interception and transpiration. The shrubs and trees of an ET cover

30

also provide habitat for wildlife and enhance the aesthetic appearance of the landfill.

Enhancement of the existing ET cover would consist of three phases: 1) additional testing and

surveying to determine tree distribution and health, determine the distribution of landfill gases

and the relationship to tree growth/health, testing of cover thickness and moisture regimes, and

evaluation of alternative tree species; 2) enhancement of the cover to optimize conditions for

native tree species, health, and growth based on the results of phase 1; and 3) conduct cover

performance monitoring, implement adaptive management and verify RAO achievement.

The estimated total cost of the remedy is $2.3 million.

4.5 GROUNDWATER REMEDIAL ACTION ALTERNATIVES

The FS screened response actions and remedial technologies to address RAO #2, protection of

the Tualatin River. The list of general response actions included groundwater containment,

extraction, and treatment, and in-situ treatment. The FS evaluated several remedial technologies

for each general response action and developed remedial action options from viable response

actions and technologies that can meet the RAOs.

Remedial action alternatives 2a, 2b, 3, and 5 include extraction of contaminated groundwater at

rates initially estimated at approximately 20,000-25,000 gallons per day. The Feasibility Study

discusses several options for treating and reusing this water7. DEQ reviewed the technology

alternatives and preliminarily selected a treatment/reuse option based on the same balancing

factors used in the remedy selection process. For clarity, DEQ included its evaluation of the

feasibility balancing factors for groundwater treatment and/or disposal option in Section 5.3

Disposal or reuse of treated groundwater would be considered on-site for purposes of ORS

465.315(3). ORS 465.315 provides that for onsite portions of an approved remedial action no

state or local permit, license or other authorization will be required for, and no procedural

requirements will apply, although substantive requirements are not affected. There does not

appear to be substantive state or local legal barriers to the land application of ground water on

the parcels identified in the FS Addendum. Substantive NPDES requirements have not been

determined for discharge of treated groundwater to the Tualatin River. Lakeside would be

required to coordinate with local government bodies as to substantive requirements and pay fees

of such bodies as stated in ORS 465.315(3). A remedial action/remedial design work plan will

provide the design basis and details.

This total cost for each groundwater remedial alternative in total net present value cost (2011

dollars) assumes a 2.5 percent annual discount rate8. The total net-present value of the alternative

includes capital costs for construction, operation, maintenance, monitoring, reporting, system

decommissioning and closure, and contingent actions. Cost estimates are generally within plus

or minus 30 percent of the likely costs and are refined after the final remedy design is completed.

7 Although the May 2010 feasibility study does not explicitly break out groundwater treatment and/or reuse options

separately from other components of the groundwater remedy, for clarity DEQ has done so. 8 Note: All remedy cost estimates in this report are expressed as net present values costs that assume a 2.5% annual

discount rate.

31

A description of the groundwater treatment and disposal/reuse alternatives are provided below.

4.5.1 Alternative 1: No Action

Under Alternative 1, contaminated groundwater exceeding criteria for protection of the surface

water beneficial uses (maintenance of aquatic habitat) would be allowed to discharge to the river

unabated.

The total projected cost of this remedy alternative is $1.2 million, which represents the cost for

compliance monitoring required under the landfill closure permit.

4.5.2 Alternative 2a: Groundwater Extraction (Wells), Pretreatment, and Land Application

Under Alternative 2a, a network of approximately 129 extraction wells will be placed within an

area of the groundwater hot spot located between the toe of the landfill and the river to control

groundwater seepage into the river. Pumping down water levels in the extraction wells will

hydraulically reverse the flow direction of contaminated groundwater, preventing groundwater

contaminated above remedial action cleanup levels (RACLs) from discharging to the Tualatin

River. It is estimated that a total groundwater extraction rate of 15 gallons per minute

(approximately 22,000 gallons/day) is required to achieve hydraulic control over the portion of

the groundwater plume exceeding RACL, with each well pumping approximately 1.25 gpm.

Hydraulic control and containment of groundwater can be achieved within hours to days after

pumping begins.

Data collected on groundwater elevations and river stage indicate the typical direction of

groundwater flow (southerly towards the river) reverses seasonally due to high stage conditions

in the Tualatin. This information indicates the network of groundwater extraction wells can be

operated/shut down seasonally and still effectively prevent the plume of contamination from

discharging to the river. The seasonal pumping strategy will be refined during the remedial

design phase and its implementation adjusted based on performance monitoring data.

Initially, extracted groundwater will be routed to a cascade aerator for the primary purpose of

oxidizing iron and manganese into less soluble forms that can be removed through precipitation

and filtration. The aerated water would then be conveyed to two approximately 1000 ft2 lined

emergent wetlands populated by natrophilic (salt loving) plant communities. The wetlands are

designed to retain the extracted water for 10-20 minutes to allow adequate time for particulates

(i.e. oxidized iron and manganese) to settle out, and to trap or absorb other contaminants of

9 The Feasibility Study (URS, May 2010) indicated 10 groundwater extraction wells would be used to

contain/capture plume of groundwater contamination. The July feasibility study addendum revised the number of

wells to 12.

32

ecological concern. It is anticipated a portion of the CPEC load including ammonium/nitrogen,

metals and phosphorus will be taken up by, and sequestered within, the tissue of the natrophilic

plants.

After the pretreatment steps, the extracted water would be pumped to the northern end of the site

and land applied to approximately 8 acres of natrophilic grasses at agronomic rates using spray

irrigation methods. The natrophilic grasses were chosen for the land application area to target

and take-up CPECs such as barium, chloride, and calcium. The grass stand will be irrigated at a

rate of about 1.9 inches per month during the months of May through September depending on

actual weather and operating conditions. Soil moisture sensors, lysimeters, groundwater

monitoring wells, and soil quality will be monitored to assure water is applied at agronomic rates

and is not having a deleterious effect on the agricultural productivity of land and the beneficial

uses of the underlying groundwater.

Prior to constructing a full scale pretreatment system and planting the land application area, pilot

testing will be conducted to evaluate the effectiveness of various treatment trains and to identify

the appropriate configuration and sizing of treatment system components.

There may be periods when land application is not feasible and it is necessary to provide

temporary storage of the extracted water until crop irrigation can be resumed. The FS addendum

indicates a lined pond with 60,000 to 80,000 cubic feet of storage capacity (approximately one

month‟s flow based on an extraction rate of 15 gpm) is a component of the remedy.

The estimated total cost including capital, monitoring and operation and maintenance costs of the

remedy is estimated at $4.96 million.

4.5.3 Alternative 2b: Groundwater Extraction (Wells), Pretreatment , and Discharge to Tualatin River

Under alternative 2b pretreatment of the extracted groundwater is identical to that described in

alternative 2a, however, rather than applying the treated water to agricultural land it is directly

discharged via a conveyance pipe to the Tualatin River. This alternative presumes pretreatment

of the extracted groundwater reduces CPECs and TMDL related contaminants below remedial

action cleanup levels established at Lakeside and that these levels are met at the end of the

discharge pipe.

The total projected cost of this remedy alternative including capital, recurring and future costs is

$4.4 million.

4.5.4 Alternative 3: Groundwater Extraction Trench or Horizontal Extraction Wells, Pretreatment and Land Application or Direct Discharge

Alternative 3 is identical to alternative 2a, however, a 1300 feet trench would be installed for

pumping groundwater as an alternative to the 12 vertical wells. Pumping would hydraulically

control the plume of groundwater contamination preventing its discharge to the Tualatin River.

Extracted groundwater is treated above ground and land applied or directly discharged

(depending on the effectiveness of pretreatment) as described in alternatives 2a and 2b.

33

Rreversal of hydraulic gradients and groundwater capture and containment would occur within

hours to days after starting the pumps. The estimated total cost of the remedy presuming a 20

year operational period is $4.7-$5.2 million.

4.5.5 Alternative 4: Impermeable Barrier

Under Alternative 4, a subsurface barrier, such as sheet pile or slurry wall would be installed to

prevent groundwater discharge into the Tualatin. A 1300 feet barrier would be “keyed” into

underlying low permeability strata such as the Helevtia Formation at Lakeside. The barrier‟s

effect would be immediate after construction. The estimated total remedy cost over operating

period, including monitoring, decommissioning, closure and contingencies is $3.2 million.

4.5.6 Alternative 5: Impermeable Barrier with Groundwater Extraction, Pretreatment, and Land Application or Direct Discharge

Under Alternative 5, an impermeable barrier would be installed as described in alternative 4 but

would include a groundwater extraction system to prevent groundwater from flowing around the

barrier and into the river. Extracted water would be pretreated and land applied or directly

discharged to the Tualatin River as described in alternatives 2a and 2b. Containment and control

would prevent contaminated groundwater discharges to the river within hours to days after

starting the pumps. The estimated total cost of the remedy is $ 5.7 -6.3 million for the anticipated

operating period of 20 years.

4.5.7 Alternative 6: Permeable Reactive Barrier

Under Alternative 6, permeable barriers would be installed that allows groundwater passage

through the wall while removing and/or treating contaminants. The barrier would be to depths of

35 to 40 feet along the 1300 foot landfill width that would be filled with materials such as

chelators, sorbents, reactive agents, or microorganisms. Reducing contaminant loading to the

Tualatin would take an estimated 9 to12 months based on groundwater velocities. The total

remedy cost is $3.0 million for the estimated operating period.

4.5.8 Alternative 7: Phytoremediation by Deep-Rooted Coniferous or Deciduous Trees

Under Alternative 7, trees would be used to remove, degrade, contain, and/or sequester

contaminants in soils, sediments and groundwater. Special cultivation practices train roots to

extend through a relatively thick vadose zone to the interface of saturated and unsaturated soils.

To achieve a fully functional phytoremediation barrier with maximum mitigation potential would

take at least 4-6 years after planting the trees. The estimated total remedy cost is $3.0 million for

the anticipated operating period of 20 years.

4.6 PERIODIC REVIEW, MONITORING AND CONTINGENCIES

Predicting the long-term effectiveness of any of the remedial action alternatives is difficult,

because of the site‟s many uncertainties including:

34

Heterogeneity in the subsurface environment.

Potential changes in future land use and zoning.

Changes in community concerns regarding remedial actions.

Long-term performance of remediation systems.

Periodic monitoring and review of the remedy‟s performance and a contingency plan would be

implemented if the remedy does not achieve the remedial action objectives. The objective of

these steps will be to maintain the selected remedy‟s overall protectiveness. The contingency

plan will consider the remedial action objectives identified in this report‟s Section 4.1.2 and

establish a series of decision criteria and corresponding response actions for potential problems.

The remedial design/remedial action work plan and adaptive management plan will describe

details of the remedy implementation. Section 7.3 discusses the framework of this plan. The

remedial design/remedial action work plan and adaptive management plan process is similar to

DEQ‟s contingency plan process outlined here.

The contingency plan will include the following components: 1) establish performance criteria

based on achieving the remedial action objectives within specific time-frames; 2) if monitoring

data exceed trigger values in select monitoring wells, Lakeside initiates an expanded monitoring

program; 3) if the supplemental monitoring data fails the remedial action objectives, evaluate

additional remedial actions needed to ensure adequate protection of human health and the

environment.

35

5. EVALUATION OF REMEDIAL ACTION ALTERNATIVES

5.1 EVALUATION CRITERIA

DEQ regulations (OAR 340-122-0090) define the criteria used to evaluate the remedial action

alternatives described in Section 6. Included is a two-step approach to evaluate and select a

remedial action.

Step One, evaluate the remedial action‟s protectiveness; if it is not protective, the alternative is

unacceptable and the step two evaluation is unnecessary. Step two, evaluate the “protective”

remedial alternatives and compare them against five balancing factors. The five balancing factors

are: 1) effectiveness in achieving protection, 2) long-term reliability, 3) implementability, 4)

implementation risk, and 5) reasonableness of cost.

For hot spots, the evaluation proceeds as follows: 1) Determine how well each alternative treats

the identified hot spot; 2) Select and implement the alternative that compares most favorably

against these balancing factors, and complies with the hot spot criteria; and. 3) Then conduct a

residual risk assessment for the selected alternative to document that it is protective of human

health and the environment.

5.2 PROTECTIVENESS

DEQ evaluates a particular remedial action‟s protectiveness by comparing actual or estimated

future COC concentrations to the acceptable risk levels described in section 4.1 of this document.

DEQ anticipates that the maximum concentration of a contaminant of concern will exceed the

acceptable risk level for the following pathways or beneficial uses:

Groundwater discharge to surface water and maintenance of aquatic habitat

DEQ will require hydraulic analysis of shallow groundwater and/or water quality monitoring to

evaluate this pathway and to establish if a given remedial alternative is protective.

OAR 340-122-090 states that protectiveness may be achieved by any of the following methods:

Treatment

Excavation and off-site disposal

Engineering controls

Institutional controls

Any other method of protection

A combination of the above

36

With the exception of hot spots, there is no preference for any one of the above methods for

achieving protectiveness. Where a hot spot has been identified, OAR 340-122-0090(4)

establishes a preference for treatment, to the extent that it is feasible, and includes a higher

threshold for evaluating the reasonableness of costs for treatment.

5.2.1 Landfill Cover Alternatives

5.2.1.1 Alternative 1 – No Action

Under alternative 1 there would be no enhancements of the existing landfill cover and thus no

improvement in cover performance is anticipated. Generation of leachate within the landfill and

releases of leachate to the environment would continue. This alternative would require long term

reliance on a hydraulic containment system to protect the Tualatin River and does not attempt to

further control or eliminate sources of groundwater contamination. DEQ does not consider it

protective in the long term or acceptable.

5.2.1.2 Alternative 2 – Replacement of Existing Cover with an Impermeable Cap

Impermeable caps are a demonstrated effective technology for preventing surface water and

precipitation from infiltrating landfill waste and generating leachate. This alternative is capable

of achieving RAO#1, is considered protective, and is retained for further consideration of its

feasibility.

5.2.1.3 Alternative 3 – Enhancement of the Existing ET Cover

In theory, a properly constructed and maintained ET cover will provide sufficient moisture

storage and evapotranspiration potential to reduce deep infiltration of precipitation rates to the

point it prevents or sufficiently minimizes groundwater contamination. Under this scenario,

enhancement of the existing cover provides adequate environmental protection. This alternative

is retained for further consideration.

5.2.2 Groundwater Alternatives10

5.2.2.1 Alternative 1 - No Action

Alternative 1, as the heading suggests, involves taking no action to minimize potential human or

environmental exposure. No action translates into no additional contaminant concentration

reductions, no additional contaminant plume controls, and no additional engineering or

institutional controls. In this scenario, the potential would still exist for future human or

ecological exposures to groundwater/surface water contaminant levels that exceed the acceptable

risk criteria. Considering these circumstances DEQ concluded Alternative 1 is not adequately

protective and did not evaluate this alternative any further.

10

Evaluation of Groundwater Alternatives in this section focuses exclusively on containing the groundwater plume

of contamination and does discuss treatment or reuse of the extracted water.

37

5.2.2.2 Alternative 2a and 2b – Groundwater Extraction Using Vertical Wells

Alternative 2 would contain and control landfill-impacted groundwater, and significantly reduce

contaminated groundwater discharges to the Tualatin River. Groundwater pumping is a common

and potentially effective method for mitigating groundwater contamination. DEQ considers this

alternative protective and considered it for further analysis.

5.2.2.3 Alternative 3 – Groundwater Extraction Trench or Horizontal Extraction Wells

Alternative 3 would use an extraction trench or horizontal wells to capture and contain

contaminated groundwater and significantly reduce its discharge to the Tualatin River. This

approach is a variation on alternative 2. DEQ considers it protective and considered it for further

analysis.

5.2.2.4 Alternative 4 – Impermeable Barrier without Groundwater Pumping

Alternative 4 would use an impermeable barrier to block groundwater flow towards the river.

Lacking any pumping influences, groundwater would simply move under, over, or around the

barrier and continue discharging to the river. This alternative would not reduce contaminant

loading to the river. Consequently DEQ does not consider it protective and did not evaluate this

alternative further.

5.2.2.5 Alternative 5 – Impermeable Barrier with Groundwater Pumping

Alternative 5 would couple an impermeable barrier with groundwater extraction wells. This

combination of elements could produce a protective remedy. However, contamination located

downgradient of the wall would be difficult to extract. DEQ considers this alternative protective

and considered it for further analysis.

5.2.2.6 Alternative 6 – Permeable Reactive Barrier

Alternative 6 would use a permeable reactive barrier to remove and/or treat groundwater

contaminants of concern. This method allows groundwater to pass unimpeded and discharge to

the Tualatin River. The remedy‟s protectiveness is highly uncertain, however, considering the

groundwater contaminants involved and their geochemical properties. Chloride is one

contaminant that is generally not mitigated by reactive barriers. Unless Lakeside conducts further

testing to verify its effectiveness, DEQ presumes this technology is not protective and did not

retain it for further analysis.

5.2.2.7 Alternative 7 – Phytoremediation

Alternative 7 relies on hybrid poplar and pine trees to hydraulically control, capture and treat the

contaminant plume. There are many uncertainties regarding this technology‟s effectiveness.

DEQ‟s main concerns with the technology in general areas its limited ability to capture

contaminated groundwater at depth and its inability to effectively treat chloride contamination.

Furthermore, it would take a minimum of 4 to6 years after planting for : 1) the trees to mature

and remedy performance was optimized, and 2) before remedy effectiveness could be fully

38

evaluated However, based on a DEQ site visit to Lakeside in September 2009, the most obvious

and significant obstacle to implementing this remedy is a lack of available space to plant a

phytoremediation barrier downgradient of the landfill. Based on these concerns and questions

DEQ concluded phytoremediation technology was infeasible for groundwater control/treatment

and thus did not retain this technology for further consideration.

5.3 BALANCING FACTORS

DEQ evaluated the three “protective” remedial action alternatives against the following

balancing factors defined in OAR 340-122-0090(3):

Effectiveness in Achieving Protection. DEQ‟s evaluation of this factor considered the

following components:

Magnitude of the residual risk from untreated waste or treatment residuals, without

considering risk reduction achieved through on-site management of exposure

pathways (e.g., engineering and institutional controls). The characteristics of the

residuals are considered to the degree that they remain hazardous, based on their

volume, toxicity, mobility, propensity to bio-accumulate, and propensity to degrade.

Adequacy of any engineering and institutional controls necessary to manage residual

risks.

The extent to which the remedial action restores or protects existing or reasonably

likely future beneficial uses of water.

Adequacy of treatment technologies in meeting treatment objectives.

The time until remedial action objectives are achieved.

Long-term Reliability. DEQ‟s evaluation of this factor considered the following

components:

The reliability of treatment technologies in meeting treatment objectives.

The reliability of engineering and institutional controls needed to manage residual

risks, considering the hazardous substances involved and their characteristics, the

long-term effectiveness and enforceability of the controls and their ability to

prevent migration and manage risk.

The nature and degree of uncertainties associated with any necessary long-term

management (e.g., operations, maintenance, monitoring).

39

Implementability. DEQ„s evaluation of this factor considered the following

components:

Practical, technical, legal difficulties and unknowns associated with constructing and

implementing the technologies, engineering controls, and/or institutional controls,

including the potential for scheduling delays.

The ability to monitor the effectiveness of the remedy.

Consistency with regulatory requirements, and requirements for coordinating with

other public agencies and obtaining necessary approvals and permits.

Availability of necessary services, materials, equipment, and specialists, including

the availability of adequate wastewater treatment and disposal services.

Implementation Risk. This factor considers the remedy‟s effectiveness, reliability,

implementability, construction timeline and potential risks to receptors including: the

neighboring community, workers involved in remedy construction, and the

environment;

Reasonableness of Cost. This factor assesses the reasonableness of each remedial

alternative‟s costs, including capital, operation and maintenance, and periodic review

costs, as well as the net present value of all costs. For identified hot spots, treatment

costs are compared to the benefits to human health and the environment to determine if

the cost is proportionate.

In general, DEQ prefers the least expensive remedial action unless a more expensive

corrective action‟s additional cost yields proportionately greater benefits in terms of one

or more of the other balancing factors. For sites with hot spots in groundwater, DEQ

evaluates the remedial action‟s costs and its environmental benefits to determine the

degree to which the two factors are proportionate. DEQ uses a higher threshold for

evaluating the reasonableness of costs for treatment of hot spots than for remediating

non-hot spots. DEQ also considers cost sensitivities and uncertainties.

Table 7 describes in detail how each alternative compares to the balancing factors including all

sub-criteria. The sections below summarize the major conclusions derived from this comparison

and provide additional discussion about site complexities and tradeoffs between alternatives.

5.3.1 Cover Alternatives

5.3.1.1 Impermeable Cap

With proper maintenance and contingency measures, an impermeable cap would likely provide

long-term reliability with respect to preventing excessive infiltration into the underlying landfill

waste. However, an impermeable cap would require greater maintenance to respond to issues of

soil settlement that can stress and tear synthetic membranes, sloughing of the cover soil that can

40

expose the geomembrane to sun and photolytic breakdown. Impermeable caps trap landfill gases

that otherwise would vent through a conventional soil cap or ET cover. To address the buildup of

landfill gases and their potential off-site transport, an active gas collection system would have to

be installed in conjunction with the impermeable cap. Landfill gas collection systems require

long-term monitoring and maintenance. Failure of the landfill gas extraction system could result

in migration of landfill gases from the facility and onto adjacent properties, potentially resulting

in explosion hazards.

Impermeable caps have been successfully constructed at numerous landfills and it is a

technology that can be implemented at Lakeside. Other than removal of the existing vegetation

and regrading of the site, no site-specific conditions preclude construction of an impermeable

cap.

The estimated 30 year net present value cost of construction and maintenance of an impermeable

cap is approximately $8.0 million.

5.3.1.2 Enhanced ET Cover

Once established and meeting performance criteria, an enhanced ET cover would likely provide

long term reliability in protecting groundwater quality. Maintenance requirements for an

established ET cover is anticipated to be low. A mature mixed forest would help maintain slope

stability and provide long term self-sustaining habitat consistent with the surrounding Tualatin

River National Wildlife Refuge. Recent soil gas data collected by Lakeside suggests that this

remedy likely would not require a landfill gas collection system and that low concentrations of

landfill gases at the surface would vent passively through the cover. This eliminates a significant

maintenance responsibility and greatly reduces the potential for off-site landfill gas migration.

The enhanced ET cap has greater aesthetic appeal and provides higher quality wildlife habitat

than the impermeable cap. An ET cover of mixed tree species, as is planned, for the cover is also

consistent with the goals of the Tualatin River National Wildlife Refuge, which adjoins the

Lakeside site. The remedy coupled with the adaptive management process will capture the

benefits of an ET cover, while addressing the uncertainties and improving on the performance of

the existing cover.

The estimated 30 year net present value of implementing an enhanced ET cover is $2.3 million.

5.3.2 Groundwater Alternatives

5.3.2.1 Alternative 2 - Groundwater Extraction Wells

DEQ considers conventional groundwater extraction systems highly effective. Although, wells

are subject to clogging, wells that foul with precipitates or clog with sediment usually can be

reconditioned, redeveloped or if necessary, replaced to maintain their effectiveness. As a

consequence, DEQ assumes they will be reliable in the long term. Groundwater extraction wells

are a widely used technology that can be easily implemented at the site. There are no known

41

implementation risks associated with extraction well systems. This remedy‟s cost is $4.511

million and DEQ considers it reasonable.

5.3.2.2 Alternative 3 – Groundwater Extraction Using a Trench or Horizontal Wells

DEQ considers the cut-off trench or horizontal well system‟s effectiveness and long-term

reliability similar to that of a vertical–well groundwater extraction system. Implementing this

type of system is less certain, though, because of its complex construction requirements.

Potential technical challenges relate to the trench depths and the horizontal well system‟s

installation and maintenance over an area spanning 1300 feet of riverbank terrain. This

alternative does not appear to have any significant technical advantages over vertical wells and it

would cost $5.2 million.

5.3.2.3 Alternative 5 – Impermeable Barrier with Groundwater Extraction

This alternative is similar to other groundwater extraction and containment technologies

evaluated in the feasibility study but includes an impermeable-barrier component. DEQ

concludes that Alternative 5 (combined impermeable barrier and extraction system) would not be

more effective or protective than a groundwater extraction system alone. Installing the barrier

adds $1.1-1.8 million to the remedy‟s cost with no discernable benefit compared to other

groundwater extraction alternatives.

5.3.3 Extracted Groundwater Treatment and Disposal or Reuse

5.3.3.1.1 Option a. Chemically-Physically Treat Extracted Groundwater and Discharge to

Tualatin River

Technologies for chemical-physical treatment of groundwater contaminants at Lakeside are

effective and capable of attaining discharge limits established under an NPDES permit, further

modified by TMDL allocations. Components of the treatment system would include

oxidation/precipitation reactors, filtration media, and an advanced form of treatment such as

reverse osmosis and/or ion exchange to treat highly soluble contaminants such as barium,

chloride, and calcium. These wastewater treatment technologies have been demonstrated to be

reliable in the long-term, however, they have high operation and maintenance costs.

Regarding implementability, materials, design and construction services are available to install a

wastewater treatment plant. Furthermore, its effectiveness is easily monitored. Obtaining

authorization to discharge treated water to the Tualatin River under an NPDES permit or with a

permit exemption is uncertain. Groundwater contamination primarily poses an ecological risk,

human health exposures are not considered significant, and the on-site storage, treatment and

conveyance of contaminated groundwater are assumed to have very low implementation risks.

11

This cost estimate is based on a network of 10 extraction wells as described in the feasibility study. The

feasibility study addendum revised the proposed system to have 12 extraction wells. The addition of two extraction

wells will nominally increase the estimated cost of this remedy alternative.

42

Implementation risks associated with the discharge of treated water to the Tualatin River are also

considered very low.

Although the capital, operation, and maintenance costs associated with construction of the

treatment plant and associated outfall were not presented in the FS report, DEQ assumes they are

high relative to other wastewater treatment/disposal options. Costs are highly sensitive to rates

and volumes of extracted groundwater and chloride treatment requirements.

5.5.1.1.2 Option b. Chemical-Physical-Phyto Treatment and Discharge to Tualatin River

Technologies for chemical-physical-phyto treatment of groundwater contaminants at Lakeside

are available and may be capable of attaining discharge limits established under an NPDES

permit, further modified by TMDL allocations. Treatment effectiveness must be further

evaluated through pilot testing. Under this alternative, extracted groundwater would initially be

aerated primarily to oxidize metal CPECs to less soluble forms. The aerated water would then

be routed through an emergent wetland to filter particulate (including oxidized metals), remove

phosphate, and other CPECs. The ability to reduce all CPEC to levels below the remedial action

cleanup levels is uncertain. Once adequate treatment is established, these wastewater treatment

technologies have been demonstrated to be reliable in the long-term.

Regarding implementability, materials, design and construction services are available to install a

wastewater treatment plant. Furthermore, its effectiveness is easily monitored. Groundwater

contamination primarily poses an ecological risk, human health exposures are not considered

significant, and the on-site storage, treatment and conveyance of contaminated groundwater are

assumed to have very low implementation risks. Implementation risks associated with the

discharge of treated water to the Tualatin River are also considered very low.

Costs have a low to moderate sensitivity to rates and volumes of extracted groundwater.

5.3.3.1.3 Option c. Chemically-Physically Treat Extracted Groundwater and Apply to

Agriculatural/Forest Land

Land application is an effective, proven technology for wastewater treatment or reuse. The

contaminants and their concentration in groundwater at Lakeside are generally effectively taken

up by agricultural crops and trees and/or are immobilized in underlying soil. There is uncertainty

regarding the amount of area required to reuse the volume of water produced by the hydraulic

containment system. Current estimates indicate 8 acres of land will be sufficient to

accommodate the daily groundwater extraction rate. However, Lakeside appears to have enough

crop and/or forestland to accommodate a large range of flow rates. DEQ considers this option

implementable from a technical standpoint.

Land use requirements have been identified as a possible implementation issue for this option.

The proposed application area is in close proximity to the contamination and necessary for

remediation, meeting the regulatory definition of “on site” under OAR 340-122-115(37) and is

therefore subject to ORS 465.315(3). ORS 465.315 provides that for on-site portions of an

approved remedial action no state or local permit, license or other authorization will be required

43

for, and no procedural requirements will apply, although substantive requirements are not

affected. The land identified for land application is zoned EFU by Washington County. The

proposed land application of water appears to be compatible with substantive requirements of

land use zoning in the area and therefore does not appear to present a substantial

implementability barrier. Application of water for purposes of irrigation is a farm use allowed

without restriction in an EFU zone. Further, land application of reclaimed water or industrial

process is also a permitted use, in conjunction with DEQ approval of the land application

pursuant to its water quality authorities and a determination in conjunction with that approval,

that the application rates and site management practices for the land application ensure continued

agricultural, horticultural or silvicultural production and do not reduce the productivity of the

tract. Land application contemplated by this option would be pursuant to a DEQ approval under

its water quality authorities, either in the form of a permit or a permit exemption under ORS

465.315(3) that includes applicable substantive water quality requirements, including any

required determinations. Lakeside would be required to coordinate with local government bodies

as to substantive requirements and pay fees of such bodies as stated in ORS 465.315(3).

Implementation risks are primarily associated with contamination of underlying groundwater as

a result of over-application or over-irrigation. At Lakeside, land application would be monitored

using a network of groundwater monitoring wells and/or lysimeters to assure underlying

groundwater was not impacted. Implementation risks would be further mitigated by locating the

land application area upgradient of the Lakeside hydraulic containment system, and by

maintaining buffers between the application area and private properties not associated with

Lakeside or Grabhorn Inc.

The costs of this option have not been directly presented in the Feasibility Study Report,

however, they are assumed to be low relative to other options and also have a low sensitivity to

rates and volumes of groundwater extraction.

5.3.3.1.4 Option d. Haul Extracted Groundwater to a Collector Sanitary Sewer

Hauling contaminated groundwater and discharging it to the nearest sanitary sewer collector is

considered an effective and implementable option for disposing of extracted groundwater.

Municipal waste water treatment plants are proven effective and reliable in treating the

groundwater contaminants observed at Lakeside. The primary implementation risk is associated

with increases truck traffic on Vandermost and Scholls Ferry Roads and increased energy usage

and greenhouse gas emissions. Although Lakeside did not present costs for this option, trucking

expenses and disposal fees are considered high relative to other options. Total costs for this

option are highly sensitive to the rates and volumes of extracted groundwater.

5.3.3.1.5 Option e. Pipe Extracted Groundwater Directly to a Collector Sanitary Sewer

Piping extracted groundwater directly to a sanitary sewer collection point is considered a highly

effective, reliable and implementable technology. Implementation risks associated with the

remedy include leakage from piping and contamination of shallow groundwater. Moreover, there

is significant likelihood of implementation delay due to uncertainties of land use permitting and

construction. Although costs for this option were not presented in the FS, they are assumed high

44

compared to other wastewater treatment/disposal options. Because the POTW would charge a

discharge fee, the operation cost is sensitive to groundwater extraction rates and volumes.

45

6. COMPARATIVE ANALYSIS OF ALTERNATIVES

In this section, DEQ uses the remedy selection criteria identified in Section 5.3 to compare the

landfill cover and groundwater remedial action alternatives for addressing the under-performing

cover and achieving the remedial action objectives.

6.1 LANDFILL COVER

6.1.1 Protectiveness

Both an enhanced ET cover and an impermeable cap are considered capable of achieving

sufficiently low average annual infiltration rates to prevent excessive leachate generation and

restore groundwater quality to levels there are protective of its beneficial uses.

6.1.2 Effectiveness

Both alternatives are considered potentially effective in achieving RAO #1, although a properly

installed and maintained impermeable cap would outperform an enhanced ET cover in reducing

infiltration rates. Furthermore, the impermeable cap is able to prevent precipitation from

infiltrating into the waste during years of exceptionally high rainfall that would likely overwhelm

the storage and removal capacity of the ET cover. A correctly installed and maintained

impermeable cap has greater effectiveness in controlling and limiting infiltration than an ET

cover.

6.1.3 Long-Term Reliability

A properly constructed and maintained impermeable cap is a reliable method for

reducing/preventing precipitation from infiltrating landfill waste. However, impermeable caps

are more susceptible to physical damage such as puncturing, tearing, and failure caused by soil

settlement and slope failure, and their longevity is uncertain to some degree Furthermore,

impermeable caps prevent the passive venting of landfill gases. To prevent the buildup of gases

beneath the cover and reduce their lateral transport, an active landfill gas collection system is

typically operated in conjunction with an impermeable cap. Landfill gas collection systems

require maintenance and monitoring and failure of the system could result in off-site gas

migration and associated safety risks.

A healthy community of grasses, shrubs and trees present on an ET cover can provide an

effective landfill cover in perpetuity. In addition, the network of tree, shrub and herbaceous roots

present within an ET cover stabilize slopes reducing the potential for failure. ET covers also are

relatively insensitive to settlement of the cover surface compared to an impermeable cap. An ET

cover allows landfill gases to vent passively preventing the buildup of gas pressure that can force

46

lateral transport of methane off of the facility property. Therefore it is unlikely a gas collection

system would be required. The absence of an active landfill gas collection system greatly

reduces long-term maintenance and monitoring requirements and potential safety concerns

relative to the impermeable cap.

Potential concerns affecting the long-term reliability of the ET cover include but are not limited

to: disease and/or rodent damage affecting the health of tree stands, wildfire, and a maturing soil

structure that can become increasingly permeable over time. A mature, properly functioning ET

cover is less vulnerable to catastrophic failure and is structurally more resilient than a

impermeable cover. Furthermore, it does not require the installation and maintenance of a

landfill gas collection system. As a consequence, an ET cover is anticipated to have greater

long-term reliability than an impermeable geosynthetic cover.

6.1.4 Implementability

No conditions have been identified that would prevent implementation of either remedy at the

site. Both remedies are considered equally implementable.

6.1.5 Implementation Risk

A synthetic impermeable landfill cover at Lakeside will trap landfill gases, likely requiring

installation of a gas collection system to prevent their off-site migration. An active gas collection

system would have to be operated, monitored, and maintained to prevent the off-site migration of

methane at unsafe levels and pressures. An unanticipated shut down of the gas collection

system, or simply impaired system performance, could result in offsite migration of methane

towards inhabited structures.

No implementation risks are known to be associated with enhancement of the ET cover.

Considering potential implementation risks associated with the impermeable cap, the ET cover is

the preferred alternative.

6.1.6 Reasonableness of Cost

The cost of constructing and maintaining the enhanced ET cover is $2.3 million as compared to

$8.0 million for the impermeable cap. The ET Cover has a substantial cost advantage over the

impermeable cap.

6.1.6 Comparative Analysis Summary

Although the impermeable cap will likely out perform an enhanced ET cover both are considered

protective and capable of achieving design objectives. Both remedies are considered

implementable at the site. Implementation risk for installing an impermeable cap is higher,

although not easily quantified. The enhanced ET cover is substantially less expensive to

implement than an impermeable cap ($2.3 million compared to $8.0 million). Furthermore, the

enhanced ET cap has greater aesthetic appeal and provides higher quality wildlife habitat than

the impermeable cap. Based on consideration of these factors, DEQ recommends implementation

of the enhanced ET cap as the remedy to achieve RAO #1.

47

6.2 GROUNDWATER REMEDIAL ACTION ALTERNATIVES

In this section, DEQ uses the remedy selection criteria identified in Section 5.3 to compare the

three remedial action alternatives.

6.2.1 Protectiveness

The four remedial action alternatives 2a, 2b, 3 and 5 each extract groundwater to establish

hydraulic control and prevent its discharge to the Tualatin River. DEQ recognizes there are

numerous well designs and network configurations that will achieve RAO #2 and thus have

equivalent protectiveness. Furthermore, an extraction well network can easily be augmented or

modified to decrease, enlarge or alter the shape of the groundwater containment area. Inclusion

of a barrier in the design provides only nominal enhancement of the protectiveness of the

groundwater extraction remedies.

Land application treatment is considered the most protective as contaminant load in the

wastewater would not be discharged to the river. Chemical treatment would likely not reduce

concentrations of certain chemicals such as chloride and it therefore considered less protective.

6.2.2 Effectiveness

As indicated previously, the four remedial action alternatives for groundwater extraction each

have equivalent effectiveness. The horizontal wells are more difficult to adjust the distribution of

extraction rates compared to vertical wells and thus have less flexibility to adjust to a non-

uniform groundwater flow field or non-uniform distribution of contamination. Inclusion of a

barrier in the groundwater capture and containment system nominally improves the effectiveness

of capture. While all proposed remedies are roughly equivalent in effectiveness, alternative 5

using vertical extraction wells with a wall is marginally better.

Chemical treatment has limitations for certain chemicals. Land application treatment has been

effective elsewhere for treatment of more-concentrated landfill leachate.

6.2.3 Long Term Reliability

Alternatives 2a, 2b, 3, and 5 have equivalent long-term reliability. Long-term operation has

some uncertainties and maintenance of horizontal wells is more difficult than in vertical wells.

Horizontal extraction well technology is less broadly used than vertical extraction wells and

general industry experience using them in remedial applications is much more limited. A

network of vertical wells would utilize individual pumps for each well. In contrast, a system

using horizontal wells would use fewer larger pumps to achieve the same level of capture. As a

consequence, during equipment breakdowns and routine maintenance, the horizontal extraction

wells are more vulnerable to a complete loss of hydraulic containment than a network of vertical

wells. Furthermore, the use of variable speed pumps in vertical wells allows for increases in

extraction rates to temporarily compensate for the loss of an adjacent extraction well. Based on

these factors, DEQ considers Alternatives 2a, 2b and 5 to be highly reliable and Alternative 3

only moderately reliable.

48

Land application treatment has been demonstrated as reliable in similar applications and is

considered to be the most reliable treatment option. Chemical treatment has limitations for

certain chemicals.

6.2.4 Implementability

Alternative 3, which uses horizontal extraction wells, on balance is the most easily implemented

of the four remedies. Horizontal wells use directional drilling techniques that are capable of

installing multiple long linear wells from a single location. The directional drilling technique

allows horizontal wells to be installed in areas with limited or no access and without constructing

drilling pads. Fewer contractors install horizontal wells and the technique requires specialized

drilling equipment, but this is not thought to strongly impact the implementability of the remedy.

Alternatives 2a and 2b use conventional well drilling techniques to construct a network of

vertical extraction wells that collectively form a hydraulic barrier. Vertical wells are used in the

most common extraction systems and the materials, equipment, and contractors for installing

them are readily available. However, unlike the horizontal wells, the drilling rig must have

access to each location a vertical well is drilled. At Lakeside an existing road runs along the toe

of the landfill that roughly coincides or parallels the proposed extraction well alignment, thus

access issues are greatly reduced.

Alternative 5 requires deep trenching using specialized equipment, and is a much more difficult

construction technique than drilling vertical extraction wells or directional drilling for the

horizontal wells. The preferred alignment of the barrier present significant implementation

challenges. Between the access road and the river is most desired location based on the site

topography and proximity to the river. The installation of a barrier in this area would likely

require extensive removal of mature riparian area vegetation.

DEQ concluded installation of horizontal wells is the most implementable groundwater remedy,

closely followed by a system using vertical wells. Installation of a barrier with an extraction

system, alternative 5, is the least implementable remedy due to the effort required to install the

barrier.

Land application of wastewater would be relatively straightforward to implement as Grabhorn

currently grows Christmas trees on adjacent parcels of land.

6.2.5 Implementation Risk

DEQ‟s evaluation of implementation risks associated with the various hydraulic

control/groundwater extraction systems focused on potential environmental impacts resulting

from their installation. DEQ is unaware of any significant implementation risks associated with

remedial alternative 3. Remedial alternatives 2a and 2b require considerable greater disturbance

of the riparian area within which the wells would be located. Each well requires its own leveled,

cleared drilling pad, thus mature riparian vegetation would disturbed or lost as result of the well

drilling activities.

49

Installation of a barrier carries the greatest ecological implementation risk. This alternative

would likely result in the greatest disturbance (largest footprint) in the riparian area vegetation.

Furthermore, once RAO#1 has been met and an groundwater extraction system is no longer

required, the barrier would have to be removed to restore the natural groundwater discharges to

the reach of the Tualatin River. No removal or partial removal of the barrier wall could

permanently impact aquatic habitat within the Tualatin.

Trucking would pose the most implementation risk due to daily truck traffic to the wastewater

treatment plant. The primary implementation risk for land application is over-application

resulting in localized impacts to underlying shallow groundwater.

6.2.6 Reasonableness of Cost

Alternative 2 is the least costly alternative of the three carried forward in the analysis. At 4.4-4.9

million, it is $300,000 less than alternative 3 and $1.8 million less than alternative 5. Land

application treatment provides the best cost-benefit option as water is beneficially used.

6.2.7 Comparative Analysis Summary

Each of the remedial action alternatives is equivalent with respect to protectiveness and

effectiveness of achieving protection. Alternatives 2 and 5 have equivalent long-term reliability.

Alternative 2 is the most easily implemented remedy. The materials, equipment, and contractors

for installing vertical wells are readily available. Alternative 5 would require deep trenching

which is considerably more difficult to implement than installation of vertical extraction wells.

There are no significant implementation risks associated with these remedial alternatives.

Alternative 2 is the least costly alternative at $1.8 million less than Alternative 5. Based on the

comparative analysis, Alternative 2 best meets the balancing criteria for remedy selection. In

addition, land application treatment using trees is the best feasible and protective treatment

option for the extracted groundwater.

6.3 Treatment, Reuse and Disposal of Extracted Water

In this section, DEQ uses the remedy selection criteria identified in Section 5.3 to compare the

four alternatives for treating and reusing/disposing of extracted water.

6.3.1 Protectiveness

Options c, d and e

Land application treatment, option c, is considered more protective than options including direct

discharge (options a and b) since the contaminant load in the wastewater would not be

discharged directly to the river. Soils provide additional contaminant treatment and uptake

beyond pretreatment steps alone and moderates variation in the level of pre-treatment

effectiveness. Chemical-physical treatment alone would likely not achieve RACL for certain

chemicals such as chloride and it therefore is considered less protective.

50

Options d and e convey untreated extracted water to a publicly owned treatment works. Issues

concerning discharge of partially treated water, or land application impacting shallow

groundwater are eliminated and thus they provide the highest level of protectiveness.

6.3.2 Effectiveness

Trucking untreated water or conveying it through a pipeline and disposing of it at a public

treatment works is not considered effective as it is not a sustainable solution.

Option a, chemical-physical treatment of the extracted water, has limited effectiveness for certain

CPECs such as chloride and is unlikely to meet surface water discharge limits necessary for a

direct discharge to the Tualatin River..

The effectiveness and protectiveness of chemical-physical-phyto treatment of extracted

groundwater, as described in Option b, is somewhat uncertain and will need to be further

evaluated through pilot testing. It is assumed to be more effective than Option a, but may not

adequate to achieve discharge limits listed in an NPDES permit.

Option c, pretreatment with land application treatment has been effective elsewhere for treatment

of more-concentrated landfill leachate. While the pretreatment step is identical to Option b, the

additional step of land applying the pretreated water to natrophilic plants would be a polishing

step to provide more complete treatment of the extracted water. This method in theory provides

very effective wastewater treatment, greater than option a and option b, and less than options d

and e.

6.3.3 Long Term Reliability

Once the groundwater pretreatment system is installed, tuned, and optimized, options a and b are

considered reliable alternatives. Changes in extracted water chemistry over time may require

adjustment of the treatment steps, but system operation is considered flexible enough to adapt to

changing conditions.

Option Land application Land application treatment has been demonstrated as reliable in similar

applications and is considered to be the most reliable treatment option. Loading rates to soils

with salts and other contaminants carry some uncertainty regarding useful life of an application

area, however, this should be clarified during the pilot testing phase. If the loading capacity of

the soil is exceeded before completion of the project this can be remedied by designating and

irrigating a backup application site.

Conveyance of untreated water to a public owned treatment works, Options d and e, are

equivalently the most reliable wastewater treatment options discussed in the feasibility study.

51

6.3.4 Implementation Risk

Trucking would pose the most implementation risk due to daily truck traffic to the wastewater

treatment plant and high emissions of hazardous air pollutants and greenhouse gases. The

primary implementation risk for land application is over-application resulting in localized

impacts to underlying shallow groundwater.

6.3.5 Reasonableness of Cost

Alternative 2 is the least costly alternative of the three carried forward in the analysis. At 4.9

million, it is $300,000 less than alternative 3 and $1.8 million less than alternative 5. Land

application treatment provides the best cost-benefit option as water is beneficially used.

6.3.6 Comparative Analysis Summary

Each of the remedial action alternatives are equivalent with respect to protectiveness and

effectiveness of achieving protection. Alternatives 2 and 5 have equivalent long-term reliability.

52

7. RECOMMENDED REMEDIAL ACTION ALTERNATIVES

Based on the evaluation of alternatives presented in Sections 6, DEQ has selected Landfill Cover

Alternative 3 - Enhanced ET Cover, and Groundwater Alternative 2 – Groundwater Extraction

with Wells and Land Application as the proposed remedial action at the Lakeside Reclamation

Landfill site. These alternatives would meet the the remedial action objectives and therefore

considered protective, best meet the balancing factors for remedy selection and treat hot spots of

contamination. A detailed description of the proposed actions is provided in following sections.

7.1 DESCRIPTION OF RECOMMENDED LANFILL COVER ALTERNATIVE

Alternative 3 would include extensive testing and surveys to evaluate soil conditions and identify

causes of stunted tree growth and high mortality rates. The results of this work would be used to

design additional testing and evaluation to enhancements to the cover to optimize its

performance. This may include but is not limited to: planting of more suitable tree species,

adding additional soil to provide sufficient moisture storage, reducing landfill gas levels in the

cover to enable deep rooting of trees, irrigating trees at critical times until they are self-sufficient.

To evaluate success in enhancing the cover, tree types, ages, health, growth rates and degree of

canopy closure will be tracked over time. To evaluate the effectiveness of the ET cover

instruments such as lysimeters and other tools will be used to monitor infiltration rates directly to

assure it achieves the performance criteria of less than 1.0 inch of deep infiltration annually, or

other infiltration rate demonstrated to be protective of groundwater quality.

7.2 DESCRIPTION OF THE RECOMMENDED GROUNDWATER ALTERNATIVE

7.2.1 Groundwater Extraction

The proposed groundwater remedy would involve installing vertical extraction wells between the

southern boundary of the waste disposal area and the Tualatin River. The extraction wells would

extract contaminated groundwater to capture and contain the portion of the groundwater plume

exceeding risk based concentrations for protection of Tualatin River. At this time it is presumed

the area of hydraulic containment is approximately 1500 feet long, extending to a depth of 40

feet below ground surface.

Preliminary groundwater modeling indicates 12 vertical wells would be necessary to effect

complete capture of the plume of groundwater contamination. The wells will be spaced

approximately120 to150 ft apart. The number of wells and their spacing may be adjusted after

taking into consideration the results of a recent aquifer test and refinement of the site

groundwater model. The extraction wells may be pulsed pumped and/or shut down on a seasonal

basis to reduce the volume of water extracted annually. The timing, pumping rates, and length of

pumping periods will be determined based on assuring contaminant plume capture, considering a

53

variety of factors including groundwater seepage rates and the period and magnitude of gradient

reversals (relative to the Tualatin River).

Treatment of extracted groundwater will be accomplished by initially aerating the water to

oxidze dissolved metals then routing it through an emergent wetland for additional CPEC

removal and uptake. Pretreated water will be conveyed to a 60,000 to80,000 cubic feet storage

pond that is sized to provide approximately one-month storage at a groundwater extraction rate

of 15 gallon per min. Water will be withdrawn as needed to irrigate trees/crops at agronomic

rates using a spray irrigation system. Lakeside has estimated that approximately eight acres of

crop land growing natrophilic grasses will be required to accommodate the volumes of extracted

groundwater. In the July 2011 addendum to the feasibility study, Lakeside estimated that

approximately eight acres of crop land planted with natrophilic grasses are necessary to

accommodate the volumes of extracted water. The RDRA/AMP will provide a more detailed

assessment of the required acreage.

7.2.2 Protective Levels and Background Concentrations

Protective levels for shallow groundwater are specified in Table 6. Site contaminants of concern

are naturally occurring inorganic substances that may have natural background concentrations at

levels that exceed protective levels. In those cases, natural background levels are defined as

protective. Lakeside may request DEQ concurrence on natural background as protective levels

for those constituents based on a statistically valid evaluation of background shallow

groundwater quality. Subject to DEQ approval, these background concentrations would replace

the protective levels specified for the facility.

7.2.3 Development of a Final Design

Based on the number of sampling points, the location and dimensions of the groundwater plume

requiring remedial action can only be approximated. As part of remedial design, the targeted

groundwater capture zone must be defined. An investigation will be performed to more

accurately delineate the vertical and horizontal extent of contamination exceeding remedial

action limits. This investigation will likely involve depth discrete sampling of groundwater, and

will also provide the bases for locating additional compliance wells.

7.2.4 Performance Monitoring

Evaluation of remedy effectiveness will be based on: 1) groundwater elevation and river stage

data for a hydraulic analysis of groundwater containment, and 2) water quality monitoring at

wells located between the extraction wells and the Tualatin River. The primary line of evidence

for demonstrating the remedy is successful is the reduction of groundwater contaminant levels to

below remedial action limits in the performance monitoring well network. A secondary, and

likely the initial, line of evidence for remedy success is groundwater elevation and river stage

data that demonstrate hydraulic containment of the contaminant plume is achieved and

maintained. DEQ anticipates additional groundwater wells will be installed to fully and

effectively monitor remedy performance and evaluate compliance with remedial action levels.

54

7.3 Adaptive Management

The proposed remedy may be modified through time through a process of adaptive management.

Adaptive management is a structured approach very similar to the DEQ contingency

development process triggered when certain remedy elements prove deficient in achieving

remedial objectives. The structured AMP process focuses on dealing with uncertainty in the

decision making for resource management. It is well-suited to ecological systems and problems

with uncertainty or complexity. In the context of the groundwater remedy implementation at

Lakeside, the generalized elements of adaptive management are as follows:

1. Assess problem and develop conceptual model of the system (e.g., ET cover must minimize

infiltration as characterized by a water-balance model).

2. Establish mitigation goals (e.g., Feasibility Study Remedial Action Objectiveness).

3. Identify and implement management actions or remedial actions (e.g., FS alternatives, such

as cover planting scheme and groundwater treatment methods).

4. Identify performance criteria (can be stated in terms of a hypothesis in the adaptive

management process). Clearly state hypotheses to assess performance criteria.

5. Design and implement a monitoring plan to collect data to test hypotheses.

6. Compare monitoring results to performance criteria by testing hypotheses with monitoring

data.

7. Continue management actions, or revise management actions, or adjust performance criteria

based on monitoring results and analysis. For example:

7a. If goals met, then remedial action or mitigation is complete (“no further action

determination by the DEQ).

7b. If goals not met, but criteria and actions are supported, continue management action

and AM process (i.e., continue remedial action).

7c. If goals not met, and data do not support hypothesis, criteria, or actions, revise

management actions (i.e., take contingent actions) and/or change the performance

criteria through the adaptive management process.

Elements of adaptive management are well-suited to projects such as the Lakeside Landfill

closure and mitigation project, where uncertainties favor a flexible and iterative approach over a

prescriptive plan. A landfill ET cover system is a complex combination of physical, chemical,

and biological conditions, such as native and imported soils, a variety of native and non-native

vegetation, variable landfill gas concentrations, and varying soil bulk densities. In such

environments, the uncertainties make it complex to predict the outcome of closure management

actions, especially where little baseline information is available, such as for ET covers in western

Oregon. Adaptive management is the process by which ecological conditions are monitored and

enhanced to trend conditions toward the stated goals and performance benchmarks, or “success

criteria”.

55

Although the process is structured, the adaptive management method promotes flexible decision

making that reflects improved understanding of the site conditions and outcomes of management

actions. Monitoring of outcomes advances scientific understanding and helps adjust actions and

criteria as part of an iterative learning process. It is not a “trial and error” process, rather it

emphasizes learning by doing. Adaptive management is not an end in itself but a means to make

more effective decisions with enhanced benefits.

Flexibility is an important component of adaptive management, so the potential responses cover

a broad range of possibilities. In adaptive management, the desired range of remedial outcomes

or habitat characteristics is met by applying site-specific environmental information in an

iterative framework of measurement and response. Within this framework, success or failure are

not evaluated by any one single goal. Instead, if one or more goals are not being met,

management strategies (or other adjustments) are adapted to reflect the monitoring data.

Responses to monitoring data may include continued operation and maintenance of specified

management actions (e.g., continue specified operation and monitoring of groundwater pumping

and treatment systems), additional monitoring, literature research, experiments, consultations

with discipline experts, re-evaluation, changes to current management strategies, and/or

reassessment of goals and success criteria.

Remedy implementation and adaptive management at Lakeside will be described further in a

Remedial Design/Remedial Action and Adaptive Management Plan. It is recommended that

implementation of the RDRA/AMP (subject to agency review and approval) be incorporated into

the Record of Decision.

7.4 RESIDUAL RISK ASSESSMENT

OAR 340-122-084(4)(c) requires a residual risk evaluation of the recommended alternative that

demonstrates that the standards specified in OAR 340-122-0040 will be met, namely:

Assure protection of present and future public health, safety, and welfare, and the

environment

Achieve acceptable risk levels

For designated hot spots of contamination, evaluate whether treatment is reasonably

likely to restore or protect a beneficial use within a reasonable time

Prevent or minimize future releases and migration of hazardous substances in the

environment

No formal residual risk assessment was presented in the Feasibility Study. Based on the

assumption of complete capture of groundwater exceeding applicable ecologically risk-based

criteria, no residual risks are anticipated.

56

8. ADMINISTRATIVE RECORD INDEX

The Administrative Record consists of the documents on which the recommended remedial

action for the site is based. The primary documents used in evaluating remedial action

alternatives for the Lakeside Reclamation Landfill site are listed below. Additional background

and supporting information can be found in the Lakeside Reclamation Landfill project file

located at DEQ Northwest Region Office, 2020 SW 4th

Avenue, Suite 400, Portland, Oregon.

SITE-SPECIFIC DOCUMENTS

Voluntary Agreement for Remedial Investigation/Feasibility Study between Grabhorn Inc. and

ODEQ (DEQ NO. LQVC-NWR-05-08), December 9, 2005

Parametrix. Reconnaissance Boring and Monitoring Well Installation. December 2006

URS. Level I Scoping Ecological Risk Assessment, Lakeside Reclamation Landfill. March 2007

URS. Work Plan for Remedial Investigation – Lakeside Landfill, May 2007

URS. Beneficial Water Use and Land Use Determination – Lakeside Reclamation Landfill,

September 2007

URS. Benthic Macroinvertebrate Bioassessment Study – Lakeside Reclamation Landfill.

November 2007

URS. Supplemental Remedial Investigation Work Plan – Lakeside Reclamation Landfill.

October 2008

Parametrix. 2008 Annual Environmental Monitoring Report – Lakeside Reclamation Landfill.

February 2009

Parametrix. 2009 Annual Environmental Monitoring Report – Lakeside Reclamation Landfill.

February 2010

Parametrix. 2010 Annual Environmental Monitoring Report – Lakeside Reclamation Landfill.

February 2011

URS. Tualatin River Sediment Sampling - Lakeside Reclamation Landfill, URS June 2009

URS. Response to DEQ June 6, 2008 Comments on the Level II Screening Ecological Risk

Assessment – Lakeside Reclamation Landfill Remedial Investigation. June 2009

57

URS. Technical Memorandum. Revised FS Work Plan for the Lakeside Landfill: Outline of Plan

for Groundwater Modeling. July 2009

URS. Technical Memorandum. Revised FS Work Plan for the Lakeside Landfill: Outline of Plan

for Analysis of Closure Cover. July 2009

URS. Screening-Level Human Health Risk Assessment & Level II Screening Ecological Risk

Assessment, URS, July 2009

URS. Work Plan for Feasibility Study – Lakeside Reclamation Landfill. August 2009

URS. Remedial Investigation Report – Lakeside Landfill. September 2009

URS. Feasibility Study – Lakeside Reclamation Landfill. May 2010

URS. Addendum to Feasibility Study, Land Application Treatment of Extracted Groundwater –

Lakeside Reclamation Landfill. July 2011

STATE OF OREGON

Oregon‟s Environmental Cleanup Laws, Oregon Revised Statutes 465.200-.900, as amended by

the Oregon Legislature in 1995.

Oregon‟s Hazardous Substance Remedial Action Rules, Oregon Administrative Rules, Chapter

340, Division 122, adopted by the Environmental Quality Commission in 1997.

Oregon‟s Hazardous Waste Rules, Chapter 340, Divisions 100 - 120.

Oregon‟s Water Quality Criteria, Chapter 340, Division 41, [RIVER] Basin.

Oregon‟s Groundwater Protection Act, Oregon Revised Statutes, Chapter 468B.

United States Geological Survey

USGS, Sources and Transport of Phosphorus and Nitrogen During Low-Flow Conditions in the

Tualatin River, Oregon, 1991-93. Water-Supply Paper 2465-C

Other

Metcalf And Eddy, Wastewater Engineering, Treatment, Disposal and Reuse, Third Edition.

McGraw-Hill, 1991.

GUIDANCE AND TECHNICAL INFORMATION

DEQ. Cleanup Program Quality Assurance Policy. September 1990, updated April 2001.

DEQ. Consideration of Land Use in Environmental Remedial Actions. July 1998.

58

DEQ. Guidance for Conducting Beneficial Water Use Determinations at Environmental Cleanup

Sites. July 1998.

DEQ. Guidance for Conduct of Deterministic Human Health Risk Assessment. May 1998

(updated 5/00).

DEQ. Guidance for Conducting Feasibility Studies. July 1998.

DEQ. Guidance for Ecological Risk Assessment: Levels I, II, III, IV. April 1998 (updated

12/01).

DEQ. Guidance for Identification of Hot Spots. April 1998.

DEQ. Guidance for Use of Institutional Controls. April 1998.

USEPA. Guidance for Conducting Remedial Investigation and Feasibility Studies Under

CERCLA. Office of Emergency and Remedial Response. OSWER Directive 9355.3-01. October

1988.

USEPA. Transport and Rate of Contaminants in the Subsurface. Robert S. Kerr Environmental

Research Laboratory. EPA/625/489/019. 1989.

USEPA. Exposure Factors Handbook. Office of Health and Environmental Assessment.

EPA/600/8-89/043. May 1989.

USEPA. Risk Assessment Guidance for Superfund, Volume 1, Human Health Evaluation

Manual, Part A, Interim Final. Office of Solid Waste and Emergency Response. EPA/540/1-

89/002. December 1989

USEPA. Human Health Evaluation Manual, Supplemental Guidance: Standard Default Exposure

Factors. OSWER Directive No. 9285.6-03, March 1991.

USEPA. Effectiveness of groundwater pumping as a restoration technology. U.S. Environmental

Protection Agency ORNL/TM-11866. May1991.

USEPA. Supplemental guidance for Superfund Risk Assessments in Region 10. U.S.

Environmental Protection Agency. August 1991.

USEPA. Integrated Risk Information System. Office of Research and Development. Cincinnati,

Ohio. 1992.

USEPA. Pump-And Treat Ground-Water Remediation, A Guide For Decision Makers And

Practitioners. U.S. Environmental Protection Agency. EPA/625/R-95/005. July 1996.

Verschueren, Karel. Handbook of Environmental Data on Organic Chemicals. Van Nostrand

Reinhold, New York. 1983.

59