“it’s only an estimate!” a panel discussion: roundtable · “it’s only an estimate!” a...

44
Montreal Section of AACE International Presents…. “It’s Only an Estimate!” A Panel Discussion: Roundtable

Upload: dinhtruc

Post on 29-Apr-2018

227 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Montreal Section of AACE International Presents….

“It’s Only an Estimate!” A Panel Discussion: Roundtable

Page 2: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Agenda “It’s Only an Estimate!”

• Safety Topic • Panel Introduction • Overview on Capital Cost Estimating • Panel Questions & Discussion • Question period

Page 3: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Safety Topic

• Walking on Montreal Streets in Winter…..

Page 4: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

The PANEL Introduction

• The Owner: Guillaume Lafortune – Hydro Quebec

• The Consultant: John Alarcon – Hatch • The Contractor: Patrick Habib – LCO

Page 5: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

It’s Only an Estimate! The concept……

Of Course, That’s Only an ESTIMATE…..

The ACTUAL cost will be much

more!

Page 6: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Art Imitates Life….. Why estimators are cautious

Page 7: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Industry Results

J. Hollmann Presentation 2011

Page 8: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

• COST ESTIMATING – A predictive process used to quantify, cost, & price

resources required by scope of an asset investment option, activity, or project.

– As a predictive process, estimating must address risks & uncertainties.

– Outputs of estimating are used primarily as inputs for budgeting, cost or value analysis, decision making in business, asset & project planning, or for project cost & schedule control processes.

It’s Only an Estimate! Definitions

Page 9: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Estimate Defined

Estimate (aace): A compilation of all the costs of the elements of a project or effort included within an agreed upon scope. PMBoK: A quantitative assessment of the likely amount or outcome. Usually applied to project costs, resources, effort and durations and is usually preceded by a modifier (i.e. preliminary, conceptual, feasibility, OoM, definitive). It should also include some indication of accuracy e.g. +/-percent).

Page 10: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Basic Estimating Process

Planning Preparation Development Summation Document Review

Final Estimate

Mandate Owner req’ts

Estimate Level WBS

Est. Resources Est. Methods

Schedule

Scope of Work Site Survey

Labour rates Productivity

Prev. Est.

Equip. Lists & Eng. Docs MTOs

Quotes/$ Databases Direct Labour Schedule Data

Indirect Costs/Owner Risk Review

Methodology Data Sources

Inclusions Exclusions

Quantities Cost summaries Historical data

Benchmark data Risk Evaluation

Variance Analysis

Owner Requirements

WBS Commodity

Coding

Estimate

Plan

Quantified & priced Line items

Direct & Indirect Allowances

Contingency & Esc.

Summary by WBS Discipline

Quantities , hours & cost

Variance report

Basis of Estimate

Supporting worksheets

Labour rates & Crews

productivity

Activities typically shown for Class 3 estimate

Page 11: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities
Page 12: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities
Page 13: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities
Page 14: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Reference: AACE International Recommended Practice No. 18R-97 COST ESTIMATE CLASSIFICATION SYSTEM

It’s Only an Estimate! Estimate Classes

Page 15: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Capacity factors (6/10 rule), analogous, expert judgment, cost indices (top down)

Factors applied to plant (Hand factor) or equipment (Lang factor)

Parametric estimating (related to a physical attribute/s)

Model based with CAE 5D (BIM)

Detail line items with MTOs and pricing from estimating databases & market pricing (bottom-up estimating)

School of Project Controls Estimating Methods

Reference: Estimating in 3D: the Next Dimension, Barmania & McMullan, AACE International Annual Meeting, 2004

Page 16: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Estimate Elements Direct Contractor View

COST ESTIMATE

Direct Costs

Indirect Costs

Labor Material Equipment Subcontract

Taxes General Conditions Risk / Reward Overhead

Profit Contingency

Page 17: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

It’s Only an Estimate! Estimate Summary

Page 18: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Class & Stage-Gate

Doing the Right Project

Doing the Project Right

Project Shaping

18

Class 5 Class 4 Class 3 Class 4,5

Sanction Appropriation

4 Definitive 5 Tender

Check

Page 19: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Estimate types and “Stage-Gate” At what stage are you most involved?

Is the stage-gate process

effective?

Where are there areas for improvement? (e.g. communications, interfaces)

It’s Only an Estimate! Panel Discussion

Page 20: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Flaws • Each of the stages do not meet required

deliverables, leading to recycling: – FEL G1 = Robust business case – FEL G2 = Scope complete (base case selected) – FEL G3 = Project ready to execute

• Stage-gate approval conditional • FEL drives cost and schedule predictability* • FEL & Context: 3 key areas of context*

– Challenges of physical location – Availability & quality of construction labour – Permitting

* industrial megaprojects by E.W. Merrow, chapter 10

Page 21: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

From Social Media……

Reference: When Good Projects Go Bad – SOR - April 2011

Page 22: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

One of the reasons given for project overrun is “poor estimating”.

How do you respond?

What is the most variable part of the estimate and has greatest impact?

What can the industry do to improve?

It’s Only an Estimate! Panel Discussion

Page 23: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Flyvbjerg’s Top Reasons for Mega project Overrun

Page 24: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Most variable costs

• Typical areas of highest growth: – Bulk Quantities – Construction Labour hours – Indirect related labour costs – Construction indirect costs – Field Overheads – Consultant services – Owner costs

EQUIP 23%

BULKS 24%

DIR. LAB. 21%

HO 13%

INDIR. 19%

RATIOS

Page 25: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Contingency & Escalation

How do you define each?

How do you assess cont’y? Deterministic, probabilistic or parametric?

Who owns the project contingency?

It’s Only an Estimate! Panel Discussion

Page 26: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Project Contingency

• Contingency – An amount added to an estimate to allow for

items, conditions, or events for which the state, occurrence, and/or effect is uncertain and that experience shows will likely result, in aggregate, in additional costs.

– Typically estimated using statistical analysis or

judgment based on past asset or project experience.

Page 27: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Risk Methods

Page 28: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Risk Methods

Page 29: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Escalation

Page 30: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Estimating Accuracy:

What does it mean?

How do you establish and validate it?

How do we improve it?

It’s Only an Estimate! Panel Discussion

Page 31: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities
Page 32: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Estimate accuracy

Page 33: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

International Projects:

How is labour productivity evaluated in the estimate?

What are the things to watch for remote locations?

It’s Only an Estimate! Panel Discussion

Page 34: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Sample Labour Productivity evaluation sheet

Page 35: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

“Selling” the estimate: why so important?

What is your estimate review process/processes?

How do you convince mgmt, client and stakeholders?

School of Project Controls Panel Discussion

Page 36: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Typical Reviews

Progressive internal reviews

Estimating/Controls team review Project Review Consult. Mgmt

Review Owner Review

Page 37: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Collecting Benchmarking & Historical Data:

Is it really worthwhile?

What is your approach?

It’s Only an Estimate! Panel Discussion

Page 38: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Budget and Cost Control Workflow

Capital Estimate Scope of

Work Budget

Trending & Forecasting

Commitments Change Orders

Progress

Databases

Design Data/ Quantities

Project Statistics

and Metrics

Final Cost

Market Data

Page 39: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Estimating & Project Controls:

Should front end estimating be part of project controls?

How has technology affected the estimating process? ( Systems/Methods)

What is role of estimating during execution?

It’s Only an Estimate! Panel Discussion

Page 40: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Lessons learned and estimating:

In summary, is there a lesson learned that means the most to you that you would like to share?

It’s Only an Estimate! Panel Discussion

Page 41: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities

Question Period

Page 42: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities
Page 43: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities
Page 44: “It’s Only an Estimate!” A Panel Discussion: Roundtable · “It’s Only an Estimate!” A Panel Discussion: Roundtable . ... Estimate Defined Estimate (aace): ... Activities