inl calcine disposition jim beck calcine disposition clean/close intec
TRANSCRIPT
INL Calcine Disposition
Jim BeckCalcine DispositionClean/Close INTEC
2
Idaho Completion ProjectBechtel BWXT Idaho
• Calcinated aqueous raffinate from the chemical dissolution and reprocessing of spent nuclear fuel (SNF)
• Classified as high-level waste by DOE Order 435.1
• Contains RCRA characteristic metals and listed constituents
• Currently stored in six concrete vaults (Bin Sets or CSSFs*) containing between three to twelve stainless steels bins each
• Destined for disposal at the geologic repository,Yucca Mountain
• Dispose “as is” at Yucca Mountain in 15-foot by 2-foot diameter SNF standards canisters
High-Level Waste Calcine
3
Idaho Completion ProjectBechtel BWXT Idaho
High-Level Waste Calcine (Continued)
RCRA hazardous, High Level Waste resulting from dissolution of multiple reactor fuel types for uranium recovery
Abrasive, granular oxides ranging from 0.2 to 0.6 mm, (~15% “fines”)
4
Idaho Completion ProjectBechtel BWXT IdahoRegulatory Background
• Calcine is RCRA regulated; characteristically hazardous and listed
• Yucca Mountain will not accept RCRA hazardous waste
• Settlement Agreement requires acceleration of treatment alternative evaluations
– Record of Decision for calcine treatment by 2009
– Application for RCRA by 2012
– Calcine ready for shipment by about 2035
– Missed milestone = suspension of DOE SNF shipments into Idaho
• Project Management Plan (PMP) accelerates schedule to complete shipping by 2035
• ICP Request for Proposal (RFP) further accelerates these dates
5
Idaho Completion ProjectBechtel BWXT IdahoRegulatory Background (Continued)
• Site Treatment Plan– Submit schedule of milestones for permitting, construction and
operation by September 30, 2005
• High-Level Waste & Facilities Disposition Final EIS– DOE Proposed Action includes:
• Making calcine suitable for disposal
• Safe storage of calcine
– Excluded alternatives• Storage in CSSF for an indefinite period
• Shipment to Hanford for treatment
– State of Idaho preferred alternative - direct vitrification
6
Idaho Completion ProjectBechtel BWXT Idaho
Direct Disposal of Calcine
2000 2035
2070
High Level Waste CalcineShipped from Idaho
Direct Disposal - PMP
Vitrification
Clean-up Activity Completion Date
Direct Disposal - RFP
ACCELERATED DISPOSITION
• PMP End State = 2035• ROD for calcine treatment path forward by
12/31/09 (SA)
• RCRA Part B permit application by 12/1/12 (SA)
• RFP End State = 2022
• RCRA Part B permit application by 9/30/09
• GFSI – ROD for calcine treatment by 9/30/09
• GFSI - Removal of calcine from RCRA regulationBENEFITS
• No interim storage/vitrification facility• Waste volume reduction > 50% compared to
direct vitrification• Cost Savings: >$6B (treatment), $3-4B (disposal)
compared to direct vitrification• Safer than vitrification
7
Idaho Completion ProjectBechtel BWXT Idaho
Permit Application
Project Timeline - RFP2005 2006 2007 20222008 20112009 201
02015
(calendar year)
Calcine Treatment ROD
Submit RCRA Part B permit application
RCRA permit approved
Incorporate prelim design in RCRA permit application
Conceptual Design
Preliminary Design
Final Design
Construction
Ops
Develop & Test Alt Treatment
Regulatory Activity
Critical Path
RFP Milestone
GFSI Milestone
Schedule EPA Pre-Petition Meeting (Fed Baseline)
Calcine removed from RCRA regulation
EPA Pre-Petition Meeting
Calcine removed from RCRA regulation
Optimistic Realistic
Settlement Agreement Milestone
RCRA Initiative – Alt Treatment
6 month lag to obtain EPA commitment
6 month lag to obtain EPA commitment
Send RCRA Petition to DOE/HQ (Fed Baseline)
EPA Pre-Petition Meeting (Fed Baseline)
DOE Decision: EPA approval expected?
Project Initiation
MNS
CD-0
CD-2,3ACD-3
CD-4
Critical Decision
2012
RCRA Petition – Direct Disposal
RCRA
Incorporate final design into permit application
CD-1
8
Idaho Completion ProjectBechtel BWXT IdahoTreatment Options
TREATMENT CATEGORIES
Vitrification• Direct• Chemical
Separations
Alternate Treatment• Multiple Possibilities
- Grout- stabilizers- Ceramics- Hot Isostatic Press- Etc.
Direct Disposal• Calcine in a can
9
Idaho Completion ProjectBechtel BWXT IdahoTreatment Options (Continued)
Vitrification
• Baseline previous to PMP
• RCRA LDR required best demonstrated available technology– Direct vitrification
- 12,000 high-level waste canisters
- $7B EM life cycle cost
- Chemical separations with vitrification
- 650 high-level waste canisters
- $10B EM life cycle cost
• RCRA delisting required – minimum 3 years (based on Hanford delisting of 200 area waste)
10
Idaho Completion ProjectBechtel BWXT IdahoTreatment Options (Continued)
Alternate Treatment
• PMP back-up
• Performance requirements unknown
• Technology development – multiple possibilities; costs not well defined
• Unknown waste volume
• Still requires removal from RCRA regulation
11
Idaho Completion ProjectBechtel BWXT Idaho
Treatment Options (Continued)
Direct Disposal
• PMP direction
• Safe to ship and dispose without further treatment
• $1.3 B EM life cycle cost
• ~ 4,400 high-level waste canisters
• EPA Rulemaking based on demonstration of no-migration of RCRA hazardous contaminants
12
Idaho Completion ProjectBechtel BWXT Idaho
Key Issues
• Highest project risk - dual RCRA-NRC regulation
• Highest technical risk - retrieval and characterization
• Integrating with YMP licensing and shipping schedules
• Stakeholder concerns
13
Idaho Completion ProjectBechtel BWXT IdahoRetrieval
• Uncertainties– Physical characteristics
• Angle of repose, flow properties, and propensity for “rat-holing”
• Caking, fusing, abnormal clumping
• Surface friction (adherence to bin walls and supports)
– Bin set access• Number of access points
• Additional access points
• Access size
• 2007 demonstration
• AEA Technologies testing- Mooresville, North Carolina
14
Idaho Completion ProjectBechtel BWXT Idaho
AEAT Testing
15
Idaho Completion ProjectBechtel BWXT IdahoCharacterization
• Inventory development/maintenance– D-cell calcine sampling and analysis
• CSSF II (1978 sampling event)
• Analysis completed during February 2004
– Historical Processing Model (HPM)• Project’s central repository for calcine inventory data
• Feed data from calcination campaigns
• Other modeling input– ORIGEN
– HSC (thermodynamic)
16
Idaho Completion ProjectBechtel BWXT IdahoCharacterization (Continued)
• Waste Acceptance– Total System Performance Assessment (TSPA) modeling
• FEIS Version– Initial TSPA screening and sensitivity analysis of chemical and
radionuclide constituents completed in 2003
– Deterministic modeling of radionuclide constituents completed –concentrations well below levels of concern at point of compliance
– Stochastic modeling of RCRA metals completed – chemical concentrations well below levels of concern at point of compliance
17
Idaho Completion ProjectBechtel BWXT IdahoCanister Development
• Cost Comparison Completed– Comparison of three canister designs
• 2’ x 10’, 2’ x 15’, and 5.5’ x 17.5’ “Super Canister”
Cost Element Concept A ($K) Concept B ($K) Concept C ($K)Canister Purchase, Filling, and Sealing at the INTEC $166,320.0 $151,959.0 $127,546.4Shipping Cask Preparation and Consignment Costs $61,997.0 $41,415.0 $25,872.0Canister Handling and Final Disposition at the MGR $3,566,400.0 $3,566,400.0 $2,817,500.0Cask Purchase $105,776.0 $52,888.0 $52,888.0
GRAND TOTAL ($K) $3,900,493.0 $3,812,662.0 $3,023,806.4SAVINGS RELATIVE TO
CONCEPT A ($K) $0.0 $87,831.0 $876,686.6
– Cost savings associated with “Super Canister”• Canisters/casks required
• Surface facility handling at Yucca Mountain
• Less (1/2 mile) tunnel space required
18
Idaho Completion ProjectBechtel BWXT Idaho
Summary
• Highest project risk - dual RCRA-NRC regulation– Regulatory strategy/approach determined via DOE-HQ and U.S. EPA
interface and input
– Alternative treatment options to vitrification should direct disposal be determined “no go”
• Highest technical risk - retrieval and characterization– Retrieval studies and testing in progress
– Calcine inventory characterization evolving• Further modeling (HSC, etc.)
• 2007 demonstration
– Development of Alternate Treatment Process
• Risk compounded with accelerated schedule
• Regulatory strategy and technical approach may change with new ICP contractor