individual report (final)
TRANSCRIPT
Process Design A 2014-2015:
Input Gathering Lines and
Storage TankGdansk Oil Terminal
Brendan [email protected]
Student ID: H00155203
AbstractIn this design project, Group 12 has been tasked with designing the new oil terminal in Gdansk, Poland. The refinery at Gdansk is supplied with oil from both the Gdansk port
and the Druzba Oil Pipeline from Russia. For this section, the design of the gathering pipeline will considered and the construction of the storage tank with safety considerations will be
explored in depth.
Artists Depiction of finished Oil Terminal (sourced from Gazoprojekt)
Table of ContentsIntroduction.................................................................................................................4
Process Overview....................................................................................................5
Overview of Process Employed...............................................................................5
Overall Mass Balance for the Process.....................................................................6
Overall Energy Balance...........................................................................................7
Tank Design............................................................................................................7
Type of Tank........................................................................................................8
Tank Dimensions.................................................................................................9
Maintaining Tank Conditions..............................................................................10
Temperature Control..........................................................................................11
Materials of Construction...................................................................................13
Further Safety Concerns....................................................................................13
Gathering Pipeline Design.....................................................................................15
Introduction........................................................................................................15
Pipeline Parameters...........................................................................................16
Suction Side Factors..........................................................................................17
Discharge Side Factors......................................................................................19
Pump Selection..................................................................................................21
Preventing Heat Loss.........................................................................................23
Heat Exchanger Design.........................................................................................25
Introduction........................................................................................................25
Type of Shell......................................................................................................25
Fluid Properties..................................................................................................26
Type of Head.....................................................................................................27
Fluid Allocation...................................................................................................27
Calculation- Tube Side.......................................................................................28
Calculation- Shell Side.......................................................................................31
Overall Heat Transfer Coefficient (Uo)................................................................32
Pressure Drop Tube Side...................................................................................33
Pressure Drop Shell Side...................................................................................33
Design Justifications..........................................................................................34
Report Conclusion.................................................................................................34
Equipment Specification Sheets............................................................................34
...............................................................................................................................35
Introduction
For the oil terminal a number of requirements have been set to achieve in this
project. The design as shown in the cover image, is to have 6 crude oil storage tanks
with each a capacity of 375,000m3. This means around 318,750 tonnes of oil can be
stored per tank (using the average Alvheim field blend density (Norway) which will be
the standard used during this project). This oil is to be either stored to be sent for
refining at the Gdansk refinery or to be further transported by tanker as raw crude oil.
For this project, the process from delivery of crude oil from the Naftoport to the
storage tanks; the vapour recovery and the returning of the oil to either the Naftoport
or sending the oil to the Gdansk refinery will be explored and detailed designs
provided. For the purpose of this technical section, the design of the tank will be
explored, including type of tank, tank parameters, maintaining storage conditions,
materials of construction, and safety concerns associated with the tank design
chosen. The fluid mechanics will be explored in the moving of oil to the storage tank
along the gathering lines associated with the process. This includes type of piping,
piping parameters, pump design, control valve choice and the factors that must be
overcome such as friction and safety concerns. Finally this report will look at a heat
exchanger design that is required to prepare oil for the required storage conditions.
This will involve the type of exchanger, specification of the exchanger and its
justification.
Process Overview
The drawing presented below is the area of each individual tank process associated
with this report:
Overview of Process Employed
In the above drawing, the lines L3-1; L4-1; L5-1 are included in the design report with
the design of Pump PU2-1; Tank T1-1; and the Shell and Tube Heat Exchanger
HX4-1 also included. It can be seen that the main line splits into two. With one line
as part of the above process and the other goes to an identical line. Therefore this
design is a standard used for all the 6 oil storage tanks in the facility. The main line
that splits has a flowrate of 5000m3/h and splits into half between each line to the
tanks. Giving a flowrate of 2500m3/h to each tank at peak times.
Overall Mass Balance for the Process
A spreadsheet showing the mass balance is shown below. This gives the mass
flowrate and gives the compositions expected for individual components in the oil.
This helps to predict the flash off expected and therefore the load the VRU (vapour
recovery system) can expect. Whilst the mass going in is shown, the expected mass
going out via the VPU is not. This will be detailed in another section in this overall
report.
Mass Balance
Volumetric Flowrate 2500 m^3/h
Overall (Kg/s) 595.00
Component Mass % Per Tank Input Feed (Kg/s)
Methane 6 35.7
Ethane 4 23.8
Propane 5 29.75
Butane 9 53.55
Heptane 11 65.45
Hexane 17 101.15
Heavy Oil 39 232.05
Salt Water 5 29.75
Nitrogen 1.1 6.545
CO2 1.4 8.33
H2S 1.5 8.925
Total 100 595.00
Overall Energy Balance
In this process the overall energy balance is found from the gain in energy from the
heat recovery process and the energy loss as a result of pumping fluid through the
gathering lines. This is outlined below in a spreadsheet:
This shows an overall positive gain of energy because of the energy recovery
system used.
Tank Design
For the design of the tank a number of factors had to be considered. These include:
- Type of Tank
- Tank Dimensions
- Maintaining Tank Conditions
- Materials of Construction
- Safety Considerations
In this order the tank design will be looked at in brief sections.
Energy Balance
Equiptment Energy Consumption/Gain (per unit, J/kg)) Total Energy from Process (J/kg)Pump -418.2 -836.4Heat Exchanger 53,400 3,204,000
Total: 3,203,164
where consumption makes for a negative figure
Number of Heat Exchangers 60Number of Pumps 2
Type of TankThere are two types of tanks used in industry to store liquids:
- Fixed Head Tank
- Floating Roof Tank
Each have their pros and cons and therefore the liquid behaviour and local seasonal
variables must be explored.
Raw Crude Oil in any case will experience flash off of low carbon number
hydrocarbons which form a vapour above the liquid surface. This means the vapour
pressure of these hydrocarbons is much higher and (and associated gases also
entrained in the oil) will begin to form and typically grow the vapour film unless high
pressures/low temperatures are used. Using either of these options would increase
safety concerns and wouldn’t be applicable for oil storage (crude oil is usually stored
at atmospheric pressure). The best way to prevent this using floating roof tanks as
the weight of the roof will stop any vapour forming and sit on top of the liquid. This is
an advantage over the fixed roof tank as pressure relief valves and inert gas supply
would be necessary to prevent pressure build-up which adds more complications to
the design. (Engineering, 2014, pp. 4-5)
Another concern in the design is the seasonal weather conditions of Gdansk.
Gdansk (which is located in the north of Poland on the Baltic coast) is subject to a
temperate climate which means warm summers and very cold winters. This creates
further concern particularly in winter. Winters are subject to seasonal snowfalls which
can result in large build-up of snow depth. This would risk becoming a hazard with
the floating roof tank as the weight could cause the roof to sink below the stored
crude oil allowing for a spill if this snow is not removed. This would require a lot of
man hours to remove and it is very hard to predict when this work would be needed.
Whilst a floating roof is better for dealing with flash off it makes more sense in this
location for fixed roof tanks to be employed. For this reason the fixed roof tank is the
preferred option for the design in this report as it is much easier to control and
predict the behaviour of stored liquid and its vapour output than seasonal weather
forecasting. (Engineering, 2014, p. 5)
Tank Dimensions The aim during the building of tanks is to a) ensure they are safe to use (looking at
the local area and what events happen) and b) to build the most economical tank.
The best way to do this is using mathematical optimisation taking the known
requirement of the volume being 375,000m3. Optimisation can be used to find the
smallest surface area to fulfil the set volume. This has numerous advantages such
as reduced construction cost (less material required); reduces the environmental
effect (less surface area for the wind loading factor); and also reduces the area for
force from the liquid-vapour pressure in the tank to affect. The optimisation method
uses differentiation to find the minimum turning point (at which the least surface
exists at). The following method was employed:
First the equations for both surface area and volume are obtained:
Volume (Cylinder )=π r2h
Surface Area (Cylinder )=2 πrh+2π r2
The volume is equal to 375,000m3 so:
π r2h=375,000
So it can be assumed:
h=375,000π r2
This can be substituted into the Surface Area equation to remove the height variable
making for a one variable equation. Hence this can be solved to find the radius:
Surface Area=2πr (375,000π r2 )+2π r2
Simplification finds:
Surface Area=(750,000r )+2π r2
Beginning the differentiation leads to the following:
S A '=4πr−( 1,500,000r2 )Making SA’ equal to zero:
4 πr=( 1,500,000r2 )Multiplying throughout by r2:
4 π r3=1,500,000
Making the radius (at the minimum turning point):
r=49.24m
Substituting this back into the volume formula to get height:
h= 375,000π (49.24 )2
Getting a height of 49.23m
Surface Area is therefore:
Surface Area=2π (49.24 ) (49.23 )+2 π (49.24 )2
Giving a surface area of 30,465.05m2
Maintaining Tank ConditionsIt has been proposed that the following conditions are maintained. The tank is to be
kept at atmospheric pressure and 10°C. Atmospheric pressure means there is no
pressurised vessel explosion potential, which in turn improves safety. The extra
pressure would require an increased vessel wall thickness which would incur
increased building cost. Keeping the tank at 10°C reduces the vapour pressure of
the crude blend, which in turn reduces the amount of flash off of light hydrocarbons
and keeps the oil in mix to be sent to its final destination as a raw material.
To maintain pressure and temperature:
- Making use of a pressure relief valve (which sends vapour to a flare or a
Vapour Recovery System (VPU))
- Inert gas supply (here nitrogen will be used)
- Using a temperature control system
Temperature ControlThere are a few designs that could be employed for this requirement which include:
- External Heat Exchange System
- Internal Tank Coils
- Jacketed Vessel
An external heat exchange system would require both piping/pumps and a heat
exchanger such as a shell and tube. There are many options on using this design
which as a result could make it rather complicated. The required pumping power and
pipes would have an extra cost making this non-economical in both the short and
long term. The small temperature difference would make the exchanger inefficient
and with a high flowrate this would make it even more difficult to design (the tank can
contain large amounts of fluid so the required volumetric flowrate to maintain this
temperature would be very high). The other two design options will be considered.
(Richardson, 1999, p. 505)
Internal Coils are another option. For heating, it would be required that the coils be
situated at the bottom (much like a kettle) and for cooling at the top (which is all to do
with heat rising and cold sinking so convection will occur). As both heating and
cooling abilities will be needed, this would increase the area of coils required, with
the overall cost to install and maintain these coils from factors such as corrosion;
increasing the overall cost. However the heat transfer is very good with coils (as
there is direct contact between liquid and heat transfer surface) so it would not be
much trouble to ensure conditions are maintained. There are many options available
for choosing the fluids inside the coil (whether they are heating or cooling) and coils
are widely used in industry so sourcing need not be too much hassle. (Perry, 2008,
p. Section 11 p21)
The other option is the Jacketed Vessel design. Jacketed vessels are simply vessels
where within the walls of the vessel are heating/cooling mediums which can reduce
the effect of local temperatures on tank fluid and change temperature in the tank.
This makes the jacketed vessel option very desirable in dealing with the safety
concerns brought about by Gdansk’s local seasons. However jacketed vessels are
not very effective with vessels on the scale that is considered in this design as heat
transfer area would be very limited (to the surface area of the inside of the tank).
(Perry, 2008, p. Section 11 p22)
For this design internal coils have been chosen to perform the maintaining of
temperature in the tank. Below is further design info:
- For large tanks, the hairpin design is typically used as it is easily erected in
the field where it is more economical to construct a storage tank of the scale
considered in this project.
- For heating this is built at the bottom of the tank and for cooling the top due to
heat rising and cold sinking.
- For the size of vessel, it is best to agitate the fluid to improve heat transfer
(note: on the downside, this will encourage more flash off)
- When heating with steam on the coil side, transfer coefficients range between
200 and 400 W/m2 K (Towler, 2009, p. 820)
- When cooling with water, transfer coefficients are between 60-300W/m2 K
(Towler, 2009, p. 819)
- A drawing of the design is shown below:
(Perry, 2008, p. Section 11 p21)
Materials of ConstructionThe choice of building material is important as it must withstand a) pressure of tank
contents and b) local environment variables. For the tank type chosen (fixed roof
tank) there is a chance pressure could build, such as the event of a pressure relief
valve failing. Because the tanks are on the scale they are, it can take hours to empty
the tanks contents so it is important this material can withstand any increased
pressure from within. Otherwise the pressure will be atmospheric so should not
present too many problems but consideration is needed in case of the above event.
Gdansk being close to the coast is subject to storms and high winds. This creates a
factor known as wind loading. From earlier the surface area of the tank is minimised
seriously limiting this effect but this factor is still worth being respectful of. Asides
from this not much else affects Gdansk that would present construction issues.
(Anon., n.d.)
For this design, steel-reinforced concrete will be considered due to its availability,
cost effectiveness and strength. Specifically deformed steel bars will be used. These
are by far the most commonly used and will be post-tensioned. Post-tensioning
means that the concrete will be tensioned on site and this is simply because the tank
is such a large size that it would not be economical to do so in the factory and then
transport such large and numerous pieces to the site. Whilst this requires some
special hardware at the end of each steel tendon to anchor them to the concrete, this
is not a big enough issue to consider using pre-tensioned concrete instead. (Perry,
2008, pp. 10-140) (Suchorski, 2000 (Reapproved 2006))
Further Safety ConcernsFurther safety concerns are standard when it comes to designing storage vessels to
contain hydrocarbons:
- Risk of Spills
- Risk of Fire
- Risk of Explosion
- Risk of Corrosion
Risk of spills are a danger to both the installation, the environment and company
reputation. Spills can cost billions in damages as seen with the recent spill in the Gulf
of Mexico by British Petroleum. Whilst the spill by BP is a slightly different scenario it
does demonstrate the affect oil can have if not under close control. In the event of an
oil tank spill the liquid needs to be contained to minimise its affects to the
surrounding area. A good method to do this is designing a bund area or a pool in
which the spilled oil may collect in. It is a simple idea but very effective on the basis it
is designed well and proper response instructions are followed. The Australian
government environmental department suggests the bund area should be able to
contain 133% of the total volume of the vessel requiring bunding (SA, n.d., p. 4). As
vapour is likely in the event of a spill, quick action is required to reduce
environmental impact of escaping gases. This is because methane in a well-known
greenhouse gas which is twenty-times worse than its counterpart carbon dioxide
(US, n.d.). A potential solution could be for the spilled oil to be collected in drains
surrounding to tank and stored underground, this in turn will reduce escaping gases.
The risk of fire is a big problem with crude oil. When burned a thick black smoke
cloud forms which in large quantities can cause health concerns in the local area.
Due to the size of the installation at Gdansk this becomes very important. A similar
accident was seen in London at the Buncefield oil terminal which produces aviation
fuel for neighbouring Gatwick airport (UK, n.d.). The fire caused a cloud of soot
particles to form over London which could be seen from space. Therefore it essential
that freighting capabilities are available to the installation. One of the most important
parts of any hydrocarbon combusting is the requirement of oxygen which if cut off,
stops the reactions occurring. In this case a foam injection system can be employed
to help fight crude oil fires. The foam helps cut oxygen off from the oil and being
flame retardant forms an unreactive layer on top of the oil killing and preventing any
flames. (Engineering, 2014, p. 5)
Risk of explosion is another issue requiring consideration. As a fixed roof tank is the
design of choice it comes with an added concern, hydrocarbon vapour formation.
Light hydrocarbons are very susceptible to sudden explosions in the right conditions.
These conditions include being in the vapour phase, in which more surface area in
available for reactions to occur. This results in unstoppable chain reactions. Not only
are these explosions catastrophic to any installation (as fire fighting systems such as
foam injection can be destroyed) but the following fires can add to problems. Whilst
explosions are dangerous, they are easily prevented. Purging the tanks with inert
gases to mix in with hydrocarbons prevents oxygen creating an explosive
atmosphere. Also ignition sources can be eliminated. As hydrocarbons are well-
known insulators, electrical potential can grow inside a tank which with time can
create a spark. By earthing a tank, this potential can be removed. Strict rules are
also needed to prevent workers bringing any potential ignition sources near the tank
area during cleaning for example. (Engineering, 2014, pp. 3-5)
Corrosion is the final risk that should be considered. Since internal heating coils are
being considered for this design it is important to look at what effect the fluid may
have. Since raw crude oil is being stored, this brings the issue of brine and its
corrosive properties. Water is known to corrode metals but this is generally a very
slow process. However alkali metallic salt solutions speed this process up by a large
factor. It has been proposed that water drains are used at the bottom of the vessels.
Water is much denser than oil so sinks and forms at the bottom of tanks when
stationary. This water or brine requires removal to prevent corrosion to the coils
situated at the bottom of the tank. Using drains with level control systems (which can
detect how high water level is due to differing electrical conductivities) can eliminate
this and also create a more desirable crude which has reduced water content
therefore requiring less treating further downstream. (Engineering, 2014, pp. 3-5)
Gathering Pipeline Design
IntroductionThe naftoport in Gdansk can have up to 4 tankers docked at any one time. From this
it is estimated that a maximum flowrate of 15,000 m3/h can be a possibility in supply
for the storage installation. This is split into three transmission line (each carrying
5,000 m3/h) and each transmission line feeds two tanks (as there are 6 crude
storage tanks) so a flowrate of 2,500 m3/h will be considered in this design.
Furthermore to this the crude oil must be taken to a height of 32.2m so extra head
will be required of the pump. At this stage it’s clear to see a large centrifugal pump
will be required. A balance of both flowrate and head needs to be found so to make
this more economical the line will be further split in two giving two input gathering
lines per tank. This means flowrate in each line will be a maximum of 1250m3/h
reducing the velocity and allowing for a more economical pump to be employed.
As part of the design the following factors will be looked at:
- Pipeline Parameters
- Suction Side Factors (Friction and NPSH)
- Discharge Side Factors (Friction and Head)
- Pump Selection
- Preventing Heat Loss
Pipeline ParametersA rule of thumb used by engineers estimates the optimum inside diameter of
pipeline. On top of this gathering lines for oil range from 8-12” in diameter. The
equation used for finding the optimum inside diameter is shown:
di=0.33(MFρ )
0.5
Where;
- MF is the mass flowrate in kg/s
- ρ is the density of the fluid in kg/m3
(Towler, 2009, p. 260)
From this equation the optimum inside diameter was found to be about 195mm.
From this the standard pipe DN300 schedule 20 was chosen (Blue Scope Pipeline
Supplies, 2008). The chosen diameter is larger than the optimum however this was
to keep fluid velocity low enough not to cause significant pressure drops (as the
crude is rather viscous so incurs more friction). This has a wall thickness of 6.4mm.
However it should be considered that crude oil is particularly corrosive so for this
application the inside of the tube will be lined with rubber (with the same thickness as
the tube wall). The outside diameter is 323.9mm. The inside diameter is found by
taking away the wall thickness multiplied by four when the rubber lining is included.
This is demonstrated below:
di=323.9−4 (6.4 )
This gives an inside diameter of 298.3mm. From this pipe calculations can be made.
Furthermore to this schedule 20 piping for this pipe gives a pressure rating of 49.95
barg which is more than sufficient as transmission lines are expected to pump fluid at
a maintained ten bar giving a safety factor of just under 5.
It is important to calculate factors such as volumetric flowrate for later calculations on
the suction and discharge sides of the pump. So using the below formula we get:
Q=MFρ
Where:
- Q is volumetric flowrate
Volumetric flowrate for the whole line will be a maximum of 0.35m3/s.
Suction Side FactorsIn terms of the suction side of the pump it must be ensured that pressure drop is not
greater than the pressure supplied by the previous pump or vessel. If so it risks fluid
not making it to the suction point of the pump and the NPSH (Net Positive Suction
Head) being very low or negative. In this design, it is known that pressure in the
transmission line was held at 10 bar. However the last pump had to provide pressure
to overcome heat exchangers in the start of the gathering line and pump along a
relatively long pipeline to reach the gathering lines. The following factors are
considered:
- Pressure Drop on first heat exchanger is equal to 0.3 bar
- The length of pipeline from the end of the gathering line start to the pump is
57m
Pressure at the start of the gathering line is 4.625 bar. Once the gathering line
begins, 57m of pipeline must be crossed with a 90 degree junction and gate valve to
also overcome until the suction side of the pump is reached. Following this a
pressure drop of 1.07 bar was calculated allowing for a NPSH of 39.1m at maximum
flowrate. This is sufficient for the pump and eliminates the risk of cavitation.
To calculate pipeline friction losses first fluid velocity; Reynolds number; and relative
roughness must be calculated. They can be found with the following equations:
u=QA
Where:
- u is the velocity
- A is the cross sectional area of the pipe (A=π4
(di))
ℜ= ρudiμ
(Towler, 2009, p. 240)
Where:
- ρ is the density of the fluid (850kg/m3)
- Re is the Reynolds number (which is a dimensionless unit)
- μ is the viscosity of the fluid
RR= edi
(Towler, 2009, p. 240)
Where:
- RR is relative roughness
- e is absolute roughness of pipe material (rubber- 0.00015m)
So velocity is 5m/s; Reynolds number is 143645; and relative roughness is 0.0005.
Also pipe fittings and equipment drops must be accounted for. Along the suction side
there is a heat exchanger (with drop 0.3 bar); a 90° bend; a sudden constriction (as
the pipe reduces in diameter from the transmission line diameter); and a gate valve.
For the fittings, the equivalent length method will be used. For this data was used
from Coulson and Richardson’s Volume 6 for the values for pipe fittings (Towler,
2009, p. 243) . The table on the following page shows the fittings equivalent length:
So 55.5 multiplied by the inside diameter will give the equivalent length. This added
to the length of 57m of pipeline that already exists gives a total length of 73.56m.
This can now be applied into the pipe pressure loss equation.
Now the pipe pressure loss can be found:
∆ Pf=8∅ ( Ldi )( ρ u2
2 ) (Towler, 2009, p. 239)
Where:
- ∅ is the Stanton-Pannell friction factor found from the chart with Reynolds number and relative roughness (0.0024)The total pressure drop on this side plus the heat exchanger pressure drop was
found to be 1.07 bar. Now NPSH (Net Positive Head Suction) should be found for
pump specification, found by:
NPSH=( Pρg )+H−( Pfρg )−(Pvρg )
(Towler, 2009, p. 251)
Where:
- P is the pressure at the start of the gathering line
- g is the gravitational acceleration constant (9.81m2/s)
- H is the height of the fluid above the pump centreline (in this case zero)
- Pv is the vapour pressure of the liquid (found to be 29.6kPa)
This gives a NPSH value of 39.1m. This gives plenty of pressure at the suction
nozzle of the pump to prevent cavitation.
Discharge Side FactorsEverything on this side of the pump is working against the energy provided by the
pump. Performing an energy balance finds that without a pump present the fluid
would lack energy by 418 joules for every kilogram of fluid. From this energy balance
it is found that the pump must have a power rating of roughly 165kW (once taking
into account efficiency). To summarise the discharge pipe is a length of 40.2m with a
globe valve; three 900 bends; a set of parallel heat exchangers and pressure drop
from the tank inlet nozzle. This pipe also must climb vertically by 33.2m to reach the
tank inlet. The following page shows the pump data sheet produced for the design:
Like the suction side the pressure drop along the discharge is calculated in the
same way. First the pipe fittings must be accounted for. The table on the following
page shows this:
This gives a total length (equivalent + actual pipeline length) of 250.2m long.
Applying this to the pressure drop formula used in the suction side section and
adding on the pressure drop over the heat exchangers (60kPa), the total comes to
Fitting Equivalent Length90 degree bend 23d x3Globe Valve 450dTank Inlet 50dTotal 569d
3.22 bar. Now the head required of the pump must be found to define the duty. This
is found by using the equation:
Head Required=( Pfρg )−( Pρg )+Z
(Towler, 2009, p. 245)
Where:
- Z is the height that the fluid must overcome
This gives a head requirement of 40.38m.
Also the energy balance should be found at this point as this can be used later to
find the power rating of the pump. The equation is shown below:
W=g ∆ z+ ∆Pρ
−∆ Pfρ
Where:
- ∆z is the change in height (m)
- g is the gravitational constant (m2/s)
- ∆P is the difference in system pressures (N/m2)
- ∆Pf is the pressure loss due to friction (N/m2)
(Towler, 2009, p. 245)
This came out at a value of -418J/kg. The negative suggests that a pump is required.
Pump SelectionThe previous page shows the pump data sheet with the type of pump. This section
aims to justify the choice of pump. The pump chosen is a centrifugal magnetic drive
sealless pump. One of its main applications is in the petrochemical industry so its
design makes it ideal for the fluid being handled. It is capable of handling high
viscosity liquids and can provide the very high flowrate required in this design. More
importantly, it can provide the head needed to lift the crude oil into the tank inlet. The
suction specific speed shows a value greater than 9000 which according to Perry’s
Chemical Engineering Handbook makes this particular pump sitting at the average
for pump design. The sealless design is excellent in preventing spills and leaks
which is important in the transporting of any hydrocarbon. Also the magnetic drive
prevents any heat gain by the liquid as it travels through the pump casing reducing
the requirement of the following heat exchangers. This also in turn increases the
efficiency of the pump as less energy is lost as heat. Being centrifugal makes
maintenance of this pump relatively easy and the manufacturer has designed this
pump to require less maintenance over the course of time. Allowing for more
continuous operation. Its limitations are of course the inability to dry start so fluid is
required to be in the casing prior to start up. There is enough NPSH to allow for this
but in the event of pressure loss upstream this pump must be switched off or risk
breaking down. Finally extra power must be allowed for as if extra head is required
(say if the liquid temperature is lower, making the liquid more viscous) then it should
be available to ensure the process is continuous (M-Pumps, n.d.). More info on this
pump can be found at:
http://www.mpumps.it/?plg_cat_view=c&id=3&g=2
The performance curves of this model of pump defines what size the pump must be.
The following page shows the performance curves:
22
(M-Pumps, n.d.)
23
The performance curve shows the ideal pump is in the 300-500 type. This pump can handle the
flowrate and head plus a little extra if any complications present themselves. Now that the type of
pump is chosen, the power rating can be found. Taking large centrifugal pumps to have an
efficiency between 75-93% (Evans, n.d.)The lowest of this range shall be selected as the viscosity
of the oil is likely to lower the efficiency anyway. The equation to find the power rating is shown:
PR=W (MF) /efficiency
(Towler, 2009, p. 245)
Where:
- PR is power rating
The power rating was found to be 165kW.
Preventing Heat LossHeat Loss is considered here as winter temperatures in Gdansk can be particularly low. The
temperature of the fluid is important as the lower the fluid is, the more viscous it becomes and
therefore the more resistant to flow it becomes. With oil this is of concern. The piping is already
lined with a thick layer of rubber. Rubber is a well-known insulator so will reduce the heat transfer
to the steel pipe wall. Steel of course is a good conductor so would pass heat easily. A calculation
has been made to show heat loss at average winter night time temperatures and calm conditions
(i.e. low or no wind where only natural convection occurs). Heat Loss can be found from the below
equation:
Q=UAo (Tco−Ta )
Where:
- Q is the energy of heat transferred in Watts
- U is the heat transfer coefficient
- Ao is the outside area of the pipe
- Tco is the temperature of the crude oil (30°C/303K)
- Ta is the temperature of the surrounding air
(Chopey, n.d.)
0
Average night time temperatures in Gdansk are -2.7°C (Ta= 270.3K). The outside area is found
with a simple calculation:
Ao=2πrL
Where:
- r is the radius of the pipe
- L is the length
In the calculation the aim was to find heat loss per meter of pipeline so L in this case was taken as
1. For these calculations the imperial system was used so there was unit conversion at the
beginning and end.
Now U is to be found:
U= 1
r 3r 1hi
+r 3 ln (r 2
r 1)
k 1+r 3 ln ¿¿¿
Where:
- r3 is the outside radius
- r2 is the radius to the steel wall
- r1 is the radius to the rubber wall (inside radius)
- hi is the inside heat transfer coefficient
- ho is the outside heat transfer coefficient
- k1/k2 are thermal conductivities with respect to their materials
K1 (natural rubber) was found to be 0.13W/m K (Toolbox, n.d.) and K2 (steel) 51W/m K
(Richerson, 2006)
(Chopey, n.d.)
1
A pipe drawing is shown below:
hi was found to be 150W/m k and ho was calculated finding both the heat transfer coefficients due
to convection and radiation. Overall this came to ho being 54BTUhf t 2
.
This gave a U value of 4.944BTU
hf t 2℉
After calculating Q and converting it to standard units it gave an answer of 71.36W per m of
pipeline. Since the pipeline prior to the heat exchanger is 60m this loss can become significant.
For this reason the pipeline will require insulation to reduce heat loss to the surroundings. It should
also be noted that this is assuming calm conditions which with a costal location it is unlikely the
loss of heat will be as low as calculated. Types of insulation for outdoor purposes include foam
rubbers, asbestos (not really used however), and polymers.
2
Heat Exchanger Design
IntroductionFor the design proposed, it is required that the feed be cooled down to ten degrees centigrade for
storage. However for transportation it is better for the oil to be heated for more laminar flow and
reduced resistance. So a heat exchanger has been designed to bring crude oil temperature from
30°C down to storage temperature (10°C). For designing the exchanger, a number of factors had
to be considered before getting into calculations:
- The type of shell
- The heat load and fluid properties
- The type of head to use
- Fluid Allocation (to which side fluids are on)
Type of ShellIn this design, the most economical design was chosen, this being the TEMA E-type shell 1:1
pass. This means both shell and tube side have one pass. This design is the most widely used
with heat exchangers in industry. Its downside is the pressure drop is typically larger than some
comparable designs. (Towler, 2009, p. 826)
Fluid PropertiesIn order to carry out the design calculations, the properties of both fluids should be collected at
both the inlet and outlet temperatures of the fluid respectively. This includes;
- Specific Heat Capacity (J. Burger, 1985)
- Viscosity (Jiskoot, n.d., p. For viscosity)
- Thermal Conductivity (S. K. Elam, 1989)
- Density (Jiskoot, n.d., p. For density)
- Fouling factors (Towler, 2009, p. 822)
The table on the following page shows the properties collected:
3
Proposed valuesT1 (°C) 30 t1 (°C) 5T2 (°C) 10 t2 (°C) 12.22927631Mass FR (kg/s) 5 6.5
Fluid PropertiesAlveheim Crude Oil (Shell Side- T1/T2) Inlet Mean Outlet Cooling Water (Tube Side- t1/t2) Inlet Mean OutletCp (kJ/kg k) 1.9200 4.1009 4.0860 4.0710(J/kg k) 1920.0000 4085.9500K (W/m k) 0.1250 0.5795 0.5978 0.6160p (kg/m^3) 839.3400 846.4850 853.6300 1000.0000 997.9000 995.8000v (m^2/s) 0.0000 0.0000 0.0000 0.0000 0.0000 0.0000µ (Ns/m^2) 0.00614 0.00978 0.01343 0.00146 0.00556 0.00965Ro/Ri (m^2 k/W) 0.0005 0.0010
Heat Load Calculating t2Q= MCp(T1-T2) Rearranging the heat load equation
Q (kW) 192 t2 12.2292763W 192000
This also shows the heat load and exit temperature of the cooling water stream (t2). It should be
noted that it was difficult to obtain a lot of the properties of the Alvheim Crude Oil because of the
number of components present. However the change in density and viscosity were possible to
estimate. Using “IP Part VII Density, Sediment and Water; Section 2 Continuous Density
Measurement September 1997; Formulae from Annex F "Correlation Equations"; API-ASTM-IP
(ISO 91-1) Petroleum Measurement; Tables\database\tech\notes\spreadsheet\Density Correction”
helped to find the density compensation for temperature for the crude oil. Also using the ASTM
D341 standard to estimate the kinematic viscosity at varying temperatures, helped find the values
of viscosity. These values are fortunately widely available for water. (Laboratory, n.d.)
Type of HeadThere are two head types typically used. This is the fixed head and floating head types. For this
design the log mean temperature difference was found to be relatively low, therefore there is not
much risk of thermal stress on the tubes. It is more economical to use the fixed head in this case
as it is much cheaper than the floating head design. (Towler, 2009, p. 826)
Fluid Allocation
4
Which side the fluid is allocated to can improve the overall economics of the design. The tube side
fluid is typically:
- The lowest flowrate
- The most corrosive liquid
- The most fouling liquid
Tube side typically is the most difficult at keeping pressure drops low. However tubes are much
more easily cleaned and replaced making the above ideals. Shell side fluid typically has the
following characteristics:
- Highest viscosity
- Highest flowrate
It is better to have the viscous liquid in the shell side as it tends to work better with lower flowrates
and the viscosity also improves the heat transfer of the shell side. As the diameter of the shell is
always greater than tube diameter it is easier to achieve a high flowrate without too much pressure
drop. From the fluid properties it is easy to see the cooling water is much more fouling so passing
this through the tubes is the best option. Also the water should be pumped at a flowrate close to
but not exceeding 4m/s to reduce the fouling. (Towler, 2009, p. 843)
Following this discussion the design can now be calculated and specified following any required
optimisation. For the calculation values of the overall heat transfer coefficient are typically between
60-300W/m2 K however as discovered after numerous trials the coefficient was found to be only
28.5W/m2 K. This may be due to the high fouling of the water and the low flowrates used.
Furthermore the log mean temperature for the optimised design was found to be 10.07°C using
the equation shown:
∆Tm=(T 1−t 2 )−(T 2−t 1)
ln (T 1−t 2)(T 2−t 1)
(Towler, 2009, pp. 838-839)
Where:
- T1 is the entry temperature of Hot Side (Crude Oil)
- T2 is the exit temp. of hot side
- t1 is the entry temp. of the cold side (Cooling Water)
- t2 is the exit temp. of the cold side
Applying these values the following formula can be used to find the trial area required:
5
Q=UA ∆Tm
Rearranged to:
A= QU ∆Tm
Giving an area of 1069m2. (Towler, 2009, p. 817)
Calculation- Tube SideFor tube side calculations, the parameters of the tube had to be found. From optimising the
design, it was found that a 10m length (exchangers are more efficient when longer), DN50 tube (2”
outside diameter), which gave a tube area of 1.57m2 (per tube, denoted as At). From this the
number of tubes can be found using:
Nt= AAt
Here Nt was found to be 426 tubes.
Now the cross sectional area if the tube inside is found so that fluid velocity and the factors
affecting heat transfer can be found (these factors include Reynolds number and finally Nusselts
number).
A=π4di
Where:
- di is the inside diameter (here is 45.8mm)
This gives an area of 0.00165m2. From this the velocity can be found but first the volumetric
flowrate needs to be derived. This is simply the mass flowrate (6.5kg/s) divided by the density
(average density is 846.5kg/m3). This gives a volumetric flowrate of 0.0065m3/s. Velocity is found
with the equation:
V=VFA
Where:
6
- VF is volumetric flowrate
- A is the cross sectional area (found in the previous calculation)
- V is the velocity of the fluid
Here the velocity of the water was found to be 3.95m/s which is close to but not exceeding 4m/s
as required.
Reynolds Number is found now by the equation:
ℜ=Vρdiμ
(Sieder, 1936)
Where μ is the viscosity and ρ is the density.
Re was found to be 32451 which gives turbulent flow.
Prandtl’s number is found from:
Pr=μCpK
(Towler, 2009, p. 846)
Where:
- Cp is the specific heat capacity
- K is the thermal conductivity
Here the solution was 38.
Before calculating Nusselt’s number the viscosity correction factor is calculated. This involves first
finding the mean temperature of the tube wall. The solution to this is the average of the two mean
bulk fluid values found by taking the average of the inlet and outlet temperatures of each fluid
respectively. The mean temperature of the wall was found to be 15°C. The viscosity correction
factor is given by:
VC= μμw
(Towler, 2009, p. 846)
Where μw is the viscosity at the mean tube wall temperature for water.
7
Nusselt’s number is found from the solution of:
Nu=0.0023 (ℜ )0.8 (Pr❑)0.33( μμw )
0.14
(Dittus, 1930)
Here the solution was Nu = 391.5
Now the tube side heat transfer coefficient can be found:
hi= K (Nu )di
Here, hi was 4954W/m2 K
Calculation- Shell SideFirst thing to find is the tube pitch (Pt) and the bundle diameter (Db):
Pt=1.25do
Db=do( Nt0.249 )
0.453
(Kern, 1950)
Here, Pt= 62.5mm and Db= 1.8m
The pitch was chosen with 1.25do spacing as this is the recommended amount for triangular pitch
design. The bundle diameter equation is given by Sinnott as a general correlation he found. To
find the shell diameter the chart given by Coulson and Richardson’s volume 6 gives typical values
for bundle clearances for fixed head exchangers. In this case the value of 26mm was taken.
Ds=Db+0.026
Whilst 1.8m bundle diameter wasn’t on the chart, an assumption was made to 26mm being the
clearance (Towler, 2009, p. 831). This gives a shell diameter of 1.83m. Now the estimated area for
cross flow can be found:
as=DsB ¿)
(Towler, 2009, p. 855)
8
This gives a value of 0.134m2. Where:
- B is the baffle spacing (which is in this case is equal to Ds/5)
Now equivalent diameter must be found:
(Kern, 1950)
This gives a value of 0.036m. Also the volumetric flowrate is equal to 0.006m3/s. The mean
velocity is therefore:
u=VFas
Which gives a value of 0.045m/s
The modified Reynolds number must be found. It is modified as the velocity which is normally
used is only an average (as velocity varies throughout the shell cross-sectional area). Now the
value G replaces u where G is the product of volumetric flowrate and density and viscosity it
multiplied by the cross sectional area. This is shown below
ℜ=Gdeasµ
(Kern, 1950)
This gives a value of 210. It should be noted that this is laminar flow so the Nusselt’s number is
adjusted for the shell side to account for this. Prandtl’s number is as before giving a value of 150
for oil. Nusselt’s number is found by the equation below (under laminar conditions):
Nu=1.86 (RePr )0.33( deL )0.33
( μμw )
0.14
(Towler, 2009, p. 847)
9
Where:
- L is the tube length (10m)
This gave Nu=8.83
The outside heat transfer coefficient is found the same way as the inside except it is denoted ho.
The value obtained was 29.66W/m2 K where μw was 0.01017Ns/m2
The calculated overall heat transfer coefficient can now be found.
Overall Heat Transfer Coefficient (Uo)Found by the following equation:
1Uo
= 1hi ( dodi )+ Xw
Kw ( doDw )+ 1ho +Ri( dodi )+Ro
(Towler, 2009, p. 817)
Where:
- Xw is the tube wall thickness (3.38mm)
- Kw is the thermal conductivity of steel (51W/m K) (Richerson, 2006)
- dw is the tube wall mean diameter (0.0479m)
Ri/Ro are the fouling factors shown in the fluid properties table. This gave a Uo value of
28.87W/m2K.
It can be seen that the error between trial Uo and calculated Uo is very small and the trial is smaller
than the calculated making this an acceptable value. Now pressure drops must be found for both
sides of the exchanger.
Pressure Drop Tube SideFound by finding the solution to:
∆ Pf=Np(8Ф [ Ldi ][ μμw ]
0.14
+4) [ ρ u22 ] (Moody, 1944)
10
Where:
- Np is the number of tube passes (1)
- Ф is the friction factor found from the Stanton-Pannell friction chart
Ф is found by finding the relative roughness (which is the absolute roughness divided by the inside
diameter of the tube) against the Re number. Relative roughness is 0.001 (as absolute roughness
of steel is 0.000045m). This gives a Ф of 0.0025. The pressure drop is therefore 0.55 bar
(550kPa).
Pressure Drop Shell SideThis is more important as this determines the drop that has to be compensated for in the pump
design. It is found by using:
∆ Pf=8Ф (Nb+1 )[Dsde ] [ pu22 ] [ μμw ]
0.14
(Kern, 1950)
Where:
- Nb is the number of baffles (found by L/B) which is 27
As the flow is laminar this time the friction factor is independent of relative roughness. Therefore Ф
is 0.08. The pressure drop calculated is 0.0077 bar (77kPa).
Design JustificationsIt was found during the design of this exchanger that it was very difficult to have high flowrates
with acceptable pressure drops and number of tubes. Despite using the largest tubing size
available it simply wasn’t acceptable to flowrates any higher than stated in the specification sheet.
The number of tubes for this design came to 680. Higher flowrates seen tubes in the thousands
and tens of thousands which simply wouldn’t be economical. For this reason it has been decided
that to cool all the fluid down around 60 heat exchangers in parallel would be needed. It is
suggested that perhaps lowering this number and using the coil system in the tank to cool the fluid
may be a better option however the parallel heat exchangers will be considered. On the up side,
the pressure drop achieved shell side for the oil is very good at only 0.01 bar so even a large
number of parallel exchangers would not cause to large a problem. Also the heat recovered by the
water could be used elsewhere on plant to use as hot water or steam at reduced production cost.
11
Report Conclusion
To conclude, this report has covered the relevant topics involved with the process described. A
storage tank has been designed, taking the most economical method via an optimisation
procedure which minimised cost and improved safety. Maintenance of conditions was looked at
including relief valves and immersion coils and the justification for their choice. The type of tank
used and its justification, also its setbacks and how they are handled. Further safety concerns
such as dealing with and preventing disasters like oil spills and fires was explored. The pipeline
design was explored looking at pipe parameters like size, piping losses and lengths. What type of
pump was looked at, giving the specification required of the chosen pump and the justification
given to why it was chosen. A heat exchanger design was detailed showing the most economical
approach and specifying and backing up the choice of exchanger chosen.
Equipment Specification Sheets
(On following pages…)
Works Cited
12
Anon., n.d. climatemps. [Online]
Available at: http://www.gdansk.climatemps.com/
[Accessed 29 March 2015].
Bell, K., 1963. Final Report of the Co-operative Research Program on Shell and Tube Heat
Exchangers.
Blue Scope Pipeline Supplies, 2008. Technical Data Chart. [Online]
Available at:
http://www.bluescopepipelinesupplies.com.au/sites/default/files/Revised_Flip_Chart_BSPS_May_
2008.pdf
[Accessed 14 March 2015].
Chopey, N. P., n.d. Heat Transfer- Heat Loss on uninsulated surfaces. In: Handbook of Chemical
Engineering Calculations (2nd Edition). s.l.:s.n., pp. 7-12 - 7-14.
Dittus, F. a. B. L., 1930. Heat Transfer in automobile radiators of the tubular type. In: University of
California at Berkeley: Publications in Engineering 2, p. 443.
Engineering, D. o. E. I. a. C., 2014. In: Processing Fluids in Process Industries. s.l.:Forth Valley
College, pp. 3-7.
Evans, J., n.d. Pump ED 101. [Online]
Available at: http://www.pumped101.com/efficiency.pdf
[Accessed 21 Feburary 2015].
J. Burger, P. S. M. C., 1985. Thermal Methods of OIl Recovery. [Online]
Available at: https://books.google.co.uk/books?id=9nWgt-
F7TNMC&pg=PA48&lpg=PA48&dq=specific+heat+capacity+of+crude+oil&source=bl&ots=hPcuuB
N4f9&sig=GUJndukm2pKzGIk_kH88h4tSTpw&hl=en&sa=X&ei=_sQbVZmcDcy17gb-
uYHwAw&ved=0CD4Q6AEwCQ#v=onepage&q=specific%20heat%20capacity%2
[Accessed 01 April 2015].
Jiskoot, n.d. Calculate Density. [Online]
Available at: http://www.jiskoot.com/Calculations/Density_VCF/index.html
[Accessed 20 March 2015].
Kern, D., 1950. Process Heat Transfer. s.l.:McGraw-Hill.
Laboratory, M. H. T., n.d. Fluid Properties Calculator. [Online]
Available at: http://www.mhtl.uwaterloo.ca/old/onlinetools/airprop/airprop.html
13
[Accessed 01 April 2015].
Moody, L., 1944. Friction factors for pipe flow, p. 671.
M-Pumps, n.d. CN MAG-M. [Online]
Available at: http://www.mpumps.it/?plg_cat_view=c&id=3&g=2
[Accessed 31 March 2015].
Palen, J. a. T. J., 1969. Solution of shell side flow pressure drop and heat transfer by stream
analysis method, p. 53.
Perry, D. W. G. a. R. H., 2008. Perry's Chemical Engineering Handbook. 8 ed. s.l.:McGraw Hill
Companies.
Richardson, J. M. C. a. J. F., 1999. Chemical Engineering. 6 ed. s.l.:Elsevier.
Richerson, D. W., 2006. Modern Ceramic Engineering- Properties, Processing and Use in Design,
s.l.: CRC Press.
S. K. Elam, I. T. K. S. R. A. A., 1989. Thermal Conductivities of Crude Oils. In: Experimental
Thermal and Fluid Science (Volume 2). s.l.:s.n., pp. 1-6.
SA, E., n.d. EPA South Australia. [Online]
Available at: http://www.epa.sa.gov.au/xstd_files/Waste/Guideline/guide_bunding.pdf
[Accessed 08 Feburary 2015].
Sieder, E. a. T. G., 1936. Heat Transfer and pressure drop of liquids in tubes. In: s.l.:s.n., p. 1429.
Stanton, T. a. P. J., 1914. Similarity of motion in relation to the surface friction of fluids, p. 199.
Suchorski, C. K. N. a. D. M., 2000 (Reapproved 2006). Reinforcement for Concrete- Materials and
Applications, s.l.: American Concrete Institute.
Toolbox, E., n.d. Thermal Conductivities of some common materials and gases. [Online]
Available at: http://www.engineeringtoolbox.com/thermal-conductivity-d_429.html
[Accessed 01 April 2015].
Towler, R. S. a. G., 2009. Chemical Engineering Design. 5 ed. s.l.:Elsevier.
Tubular Heat Exchangers Manufacturers Association, 1988. Standards of the Tubular Heat
Exchanger Manufacturers Association. 7 ed. New York: s.n.
UK, H., n.d. Buncefield Incident. [Online]
Available at: http://www.hse.gov.uk/comah/buncefield/buncefield-report.pdf
14
[Accessed 18 March 2015].
US, E., n.d. EPA US. [Online]
Available at: http://epa.gov/climatechange/ghgemissions/gases/ch4.html
[Accessed 16 Feburary 2015].
15
0
0