[ieee 2012 china international conference on electricity distribution (ciced) - shanghai, china...
TRANSCRIPT
C I C I C I C I CCCC E D E D E D E D 5th International Conference on Electricity Distribution Shanghai, 5-6 Sept 2012
Paper FP0147
Paper No. FP0147 1/4
OPTIMAL CAPACITOR PLACEMENT FOR DISTRIBUTION
FEEDER MAXIMUM SAVINGS
Meng Zhang
National Grid - USA
ABSTRACT
This paper illustrates the process used for capacitor
placement on an existing radial distribution feeder with an
objective of reducing the downstream power loss while
minimizing total cost. The Loss Sensitivity Factors are
used to determine the candidate buses for capacitor
placement and an experimental methodology is used to
find the exact optimal capacitors locations and capacitors
sizes. The method is tested on an existing 13.2kV feeder.
Simulation is done using CYME and results are presented.
Keywords: Optimal Capacitor Placement, Maximum Loss
Savings
INTRODUCTION
The increase in power demand exposes loading capacity
challenges to the existing power systems. To meet the load
demand, systems are sometimes required to upgrade the
existing cables and transformers to have more capacity or
to expand by increasing the number of feeders. However,
this may not be easily achieved by many utilities due to
various constraints. Radial distribution systems typically
spread over large areas and suffer a significant portion of
total power losses. Therefore, minimizing system loss can
also provide more capacity for the substation and feeders
and relieve loading issues. In addition, the heat dissipated
due to power loss increases the temperature of the
associated electric components and can result in insulation
failure. By minimizing the power losses, the system may
acquire longer life span and have greater reliability [3].
The loss minimization in distribution systems is very
essential to improve the overall efficiency and profit of
power delivery. The utility companies in practice usually
reduce these losses by placing capacitor banks on
distribution primary feeders. Advantages with capacitor
bank placement include improving feeder voltage profile,
improving power factor, reducing power losses and
increasing feeder capacity. It is therefore of utility
companies’ great interest and benefit to optimize capacitor
placement to reduce power loss and maximize net profit.
A considerable amount of research work was done on the
subject of optimal capacitor placement. M. Damodar Reddy
[1] used fuzzy logic to include heuristics and engineering
judgments into the capacitor allocation optimization
process to compensate for any lack of certainty in the data,
and proposed using Real Coded Genetic Algorithm
(RCGA) to find the optimal capacitor sizes. R. Srinivasa
Rao [2] took into account that the commercially available
capacitors were discrete and proposed using Loss
Sensitivity Factors to find candidate locations and using
Plant Growth Simulation Algorithm (PGSA) to estimate the
required level of capacitive compensation. In
Mahmoodianfard’s paper [3], the cost of capacitor
placement, the cost of power losses and the bus voltage
profiles were considered in the optimization problem.
In those studies however, distance between each capacitor
and that between station and each capacitor were usually
not considered. In this project, capacitor placement
optimization problem is to minimize power losses, taking
into account the minimum distance constraint, along with
other constraints including bus voltage limits, “kW loss
saved/kVar installed” criteria and available discrete
capacitor sizes. “Loss Sensitivity Factors” are used to
decide the sequence in which buses are to be considered for
placement. Only 600kVar and 900kVar capacitors are used
in the project as is the case of the utility company’s
practice. Three different options are discussed and an
optimal solution is proposed based on minimizing the total
of energy loss cost and capacitor placement cost. The
project is performed on a real feeder (Watt St 23052
13.2kV) and simulation is performed on CYME.
OBJECTIVE
The objective of the project is to reduce the energy losses
on the feeder while minimizing the total cost, and at the
same time the bus voltage should be maintained within
minimum and maximum limits, the cumulative “kW loss
saving/ kVar installed” ratio with each new capacitor
installed should satisfy the minimal value that is decided by
the utility company and the distance of each capacitor from
the station and that between each capacitor should also
satisfy certain design criteria. Thus the optimal capacitor
placement problem can be expressed as:
min f=min (COST)
s.t maxmin VVV ≤≤
.
01.0
1
, ≥∆
∑=
i
j
C
j
lossT
Q
P
C I C I C I C I CCCC E D E D E D E D 5th International Conference on Electricity Distribution Shanghai, 5-6 Sept 2012
Paper FP0147
Paper No. FP0147 2/4
,1000. ftCSta i ≥− ftCC ji 1500≥− ,
i=1, 2…n, j=1, 2… i, ij ≠
Where COST is the objective function and can be written
as:
)(1
,
C
ii
n
i
cfLossTp QKKPKCOST ++/= ∑=
Where
pK : Equivalent annual cost per unit of power loss in
$/kW
cfK : Fixed cost for capacitor installation in $
iK : Capacitor purchase rate in $/kVar
C
iQ : Size of the thi capacitor in kVar
ALGORITHM
Consider the simplified one-line diagram of a feeder in
Figure 1. From the one-line, it can be derived that the real
power loss and reactive power loss between bus i and bus
i+1 are:
1,2
22
)1,(
1,2
22
)1,(
)(
)(
++
++
⋅+
=
⋅+
=
ii
i
ii
iilineloss
ii
i
ii
iilineloss
XV
QPQ
RV
QPP
Then the real and reactive power flowing out of bus i+1 are
)1,(11 +++ −−= iilinelossLiii PPPP
)1,(11 +++ −−= iilinelossLiii QQQQ
Where iP and iQ are the real and reactive power flowing
out of bus i, and LiP and LiQ are the real and reactive loads
at bus i. 1, +iiR and 1, +iiX are the resistance and reactance
of the line section between buses i and i+1.
The Loss Sensitivity Factors ( efflineloss QP ∂∂ / ) were
introduced by R. Srinivasa Rao [2] to determine the
sequence in which the candidate buses are to be considered
for capacitors placement.
Consider a distribution line as given below:
Real power loss in the line is given by [ ] [ ]kRIk ∗2 which
can be expressed as
[ ][ ]kR
qV
qQqPqP
effeff
lineloss 2
22 )][][(][
+=
Similarly the reactive power loss can be expressed as
[ ] [ ]kXqV
qQqPqQ
effeff
lineloss 2
22
][
)][][( +=
Where
][qPeff = Total effective real power supplied beyond bus
“q”.
][qQeff = Total effective reactive power supplied beyond
bus “q”.
Then, Loss Sensitivity Factors can be expressed as
[ ]
[ ]2
2
][
][2
][
][2
qV
kXqQ
Q
Q
qV
kRqQ
Q
P
eff
eff
lineloss
eff
eff
lineloss
∗∗=
∂
∂
∗∗=
∂
∂
The Loss Sensitivity Factors
eff
lineloss
Q
P
∂
∂are calculated from
base case load flow. They are used to identify the most
suitable buses for capacitors placements and to decide in
which sequence they are to be considered. The larger the
Loss Sensitivity Factor of a bus, the more suitable the bus is
for capacitor placement.
Buses that are within 1000ft from the substation are
excluded from Loss Sensitivity Factors calculation, since
those buses are too close to the substation for capacitors
placements. The remaining buses form the modified vector
b_lsf. Loss Sensitivity Factors are calculated of those buses
in vector b_lsf and elements are rearranged in descending
order based on the calculated Loss Sensitivity Factor.
C I C I C I C I CCCC E D E D E D E D 5th International Conference on Electricity Distribution Shanghai, 5-6 Sept 2012
Paper FP0147
Paper No. FP0147 3/4
A capacitor is first placed at the first bus in the vector as
that is the most suitable bus based on Loss Sensitivity
Factors. Load flow is then performed and downstream
power loss at the station is calculated. Then move the
capacitor to the second bus in the vector. Repeat these steps
for the first ten buses in vector b_lsf. Bus b_lsf[k] which
results in the minimum downstream power loss at the
station is decided as the location for the first capacitor bank.
Then revise the candidate buses and remove those that are
within 1500ft from b_lsf[k]. Then repeat these steps until
no more capacitor banks are needed. The restrictions can
be all candidate buses are within 1500ft away from the
buses with capacitors, some bus voltages are above
1.05p.u, or cumulative 01.0,
<installed
savedloss
Q
Pfor any
additional capacitor banks.
The complete optimal capacitor placement process in this
project can be simplified into following steps:
Step 1 Perform load flow analysis on base case using
CYME.
Step 2 Filter the buses based on the constraints and save the
buses for Loss Sensitivity Factors calculation in vector
b_lsf.
Step 3 Rearrange the buses in b_lsf in descending order
based on the calculated Loss Sensitivity Factors.
Step 4 Place the first capacitor at the candidate buses in
b_lsf one at a time and calculate the corresponding
downstream power loss at the station.
Step 5 Identify the optimal bus which results in the
minimum downstream power loss.
Step 6 Revise vector b_lsf and remove buses within 1500ft
from the optimal bus found in step 4.
Step 7 Repeat steps 4 to 6 until no more capacitors are
needed.
Step 8 Record the total real power loss on the feeder after
all the capacitors are placed.
SIMULATION & RESULTS
The project works on Watt St 23052 13.2kV feeder in
Schenectady, Central New York State. Total of 1260 line
sections are modeled in CYME including primary and
secondary, overhead and underground. The primary side of
the feeder is 13.2 kV with some step-down 4.16kV areas.
And the feeder runs mostly overhead.
In the project, only overhead primary three phase sections
over 1000ft away from the substation are considered for
capacitors placement. Applying these constraints, a vector
containing 233 buses is formed from the base case for Loss
Sensitivity Factors calculation.
The complete simulation is done using CYME.
CAP200_13.2 and CAP300_13.2 are chosen from CYME
capacitor library for the 600kVar and 900kVar capacitors
since those are the sizes National Grid uses on 13.2kV
feeders. Load Flow function is used to provide buses
voltages, real power loss on each section and the total real
power loss at the station.
Three options are studied: Option 1, only use 600kVar
capacitors; Option 2, only use 900kVar capacitors; Option
3, use both 600kVar and 900kVar capacitors. A
comparison among the three options regarding total real
loss saving and costs is shown in the table below.
The assumptions used in the cost calculation are:
1. Energy rate K=$0.06/kWhr
2. Installation of each capacitor is $11,000/location
3. Purchase rate of capacitor is $3.0/kVar
4. The calculation is for a year, 365 days period.
Table 1. Net Annual Saving for the Three Options
It is observed from the table that Option 2 has the
maximum net annual saving, which is minimum annual cost
including capacitor placement and energy lost cost.
Therefore, option 2 to install 3 900kVar capacitor banks is
the optimal solution for this feeder. The image below shows
the feeder in GIS (Geographic Image System) with the
black dots indicating the locations of the three capacitors in
the optimal option.
C I C I C I C I CCCC E D E D E D E D 5th International Conference on Electricity Distribution Shanghai, 5-6 Sept 2012
Paper FP0147
Paper No. FP0147 4/4
CONCLUSIONS
In this project, exhaust experiment method along with Loss
Sensitivity Factors to find the optimal capacitors placement
on a real feeder is presented. Loss Sensitivity Factors are
calculated to decide candidate buses and thus reduce the
exhaust experiment sizes. Exhaust experiment is used to
identify optimal location and size for each capacitor.
Three options for capacitors placements are proposed.
Based on the net annual dollar saving, Option 2 installing
three 900kVar capacitors is recommended.
It should be pointed that system is assumed to be balanced
in this project, while in reality unbalanced system requires
different algorithm and further study is needed. It should
also be noticed that the final recommendation relies heavily
on all the cost assumptions made, including cost for
capacitor placement and cost for energy loss. When those
costs in practice are different from the assumptions made,
the recommendation could be different.
REFERENCES
[1] Damodar Reddy, M; Veera Reddy, V.C, 2008,
"Optimal capacitor placement using fuzzy and real
coded generic algorithm for maximum savings",
Journal of Theoretical and Applied Information
Technology, 2005-2008, 219-226
[2] Srinivasa Rao, R; Narasimham, S.V.L, 2008, “Optimal
capacitor placement in a radial distribution system
using plant growth simulation algorithm”, World
Academy of Science, Engineering and Technology 45,
715-722
[3] Forough Mahmoodianfard, Hossein Askarian Abyaneh,
HamidReza Salehi, 2010, “Optimal capacitor
placement for loss reduction”, Modern Electric Power
Systems, Wroclaw, Poland
[4] Shikha Gupta, Gursewak Singh Brar, 2011, “An
efficient approach for capacitor sizing and location on
a radial distribution system using artificial intelligence
technique”, Journal of Engineering Research and
Studies, Vol. II, Issue II
BIOGRAPHY
Meng Zhang received a B.S in Electrical Engineering
from University of New Orleans in 2009 and an M.S in
Electrical Engineering with a concentration in Power
System from Northeastern University in 2011. She is a
distribution and sub-transmission planning engineer at
National Grid USA since 2010.