    IBM

    Process Definition Document

    Materials Management Physical Inventory Process

    Client: Hill Metals Establishment.

    Author: Sulman Ahmad Khan/ Aamir Masood Arbab

  • 7/31/2019 HME PDD MM 10 Physical Inv 041110 v01

    2/13

    Page 2 of13

    Table of Contents

    1. INTRODUCTION TO PHYSICAL INVENTORY ................................................................... 5

    2. PHYSICAL INVENTORY PROCESS ........................................................................................ 6

    3. OUTPUTS (FORMS) ................................................................................................................. 9

    4.

    STANDARD REPORTS ........................................................................................................... 10

    5. KEY PERFORMANCE INDICATORS ................................................................................... 11

    6. INTEGRATION CONSIDERATIONS .................................................................................... 12

    7. TESTING SCENARIOS ............................................................................................................ 13

  • 7/31/2019 HME PDD MM 10 Physical Inv 041110 v01

    3/13

    Page 3 of13

    Document History

    AUTHORS & PARTICIPANTS

    Role Name

    HME Project Process Owner Mr. Abdul Aziz Sajid

    HME Business Unit Process Owner Mr. Chaudhary Javaid Iqbal

    HME Business Unit Process Owner Mr. Samiullah Khan

    HME Business Unit Process Owner Mr. Mohammad Anees

    HME Business Unit Process Owner Mr. Shahid Saeed

    HME Business Unit Process Owner Mr. Mohammad Ashraf

    HME Business Unit Process Owner Mr. Imran Khalid

    HME Business Unit Process Owner Mr. Ahtesham Awan

    IBM Consultant Sulman Ahmad Khan/ Aamir Masood Arbab

    IBM Project Manager Adeel Hashmi

    Workshop Participant

    REVISION HISTORY

    Date Document Version Document RevisionDescription

    Author

    04-11-2010 1.0 Customer review Sulman/ Aamir

  • 7/31/2019 HME PDD MM 10 Physical Inv 041110 v01

    4/13

    Page 4 of13

    REVIEWED AND APPROVED BY

    Name Title Date Approved

    Mr. Abdul Aziz Sajid HME Project ProcessOwner

    Mr. Chaudhary Javaid Iqbal HME Business Unit ProcessOwner

    Mr. Samiullah Khan HME Business Unit ProcessOwner

    Mr. Mohammad Anees HME Business Unit ProcessOwner

    Mr. Shahid Saeed HME Business Unit ProcessOwner

    Mr. Mohammad Ashraf HME Business Unit ProcessOwner

    Mr. Imran Khalid HME Business Unit ProcessOwner

    Mr. Ahtesham Awan HME Business Unit ProcessOwner

    Sulman Ahmad Khan/ AamirMasood Arbab

    IBM Consultant

    Adeel Hashmi IBM Project Manager

  • 7/31/2019 HME PDD MM 10 Physical Inv 041110 v01

    5/13

  • 7/31/2019 HME PDD MM 10 Physical Inv 041110 v01

    6/13

    Page 6 of13

    2. Physical Inventory Process

    The physical inventory process comprises three phases:

    Creation of physical inventory documents

    Entry of count

    Posting of inventory difference

    In the first phase, you create the physical inventory (PI) documents. It is possible to generate

    inventory documents in large quantities using batch input. After selecting the stocks to be counted

    and creating the PI documents, you print out the documents in order to start the counting process.

    You enter the count results in the system in the second phase. The system calculates the inventory

    differences. If some of the results seem doubtful, you can arrange for a recount of the stock

    management units affected. In this case, further PI documents are generated.

    In the third phase, you post the inventory differences that have been identified. The quantities and

    values of the stock are updated. The stock accounts are updated in FI.

  • 7/31/2019 HME PDD MM 10 Physical Inv 041110 v01

    7/13

    Page 7 of13

    2.1.1. Process Flow To-Be

    Physical Inventory Process

    Authorized PersonStore

    Process End

    Process Start

    Manual sign-off by

    HOD

    2.1.2.5

    2.1.2.6

    Create Physical

    Inventory (PI)

    Document

    Take print output

    of PI for approval

    Conduct physical

    count of materials

    listed in PI

    document

    Check

    variances if too

    large

    YesEnter Count

    Results

    Post Inventory

    DifferencesNo

    Material &

    Accounting

    Document

    generated by SAP

    2.1.2.1

    2.1.2.2

    2.1.2.4

    2.1.2.72.1.2.3

    No Difference

  • 7/31/2019 HME PDD MM 10 Physical Inv 041110 v01

    8/13

    Page 8 of13

    2.1.2. Functional Description of Process Steps

    If differences are Zero in Book inventory and physical inventory then zero indicator is check to closed

    the physical inventory cycle

    ActivityNo Business Activity SAP Process

    SAPTransaction Input / Remarks

    2.1.2.1Physical Inventorydocument

    The Store Officercreates the PhysicalInventory Document inthe system

    MI01Materials are blockedfor movements.

    2.1.2.2 PrintoutThe Physical Inventorydoc printout is takenout for approval.

    MI21

    2.1.2.3 Approval Outside SAPThe HOD approval isobtained.

    2.1.2.4Conduct Physical

    Inventory

    Outside SAP

    The store keeper visitsthe store and conducts

    the physical inventorycount.

    2.1.2.5 Enter count resultsThe store officer entersthe count results in thesystem.

    MI04Release material formovementautomatically.

    2.1.2.6 Variance check

    If the variance to toolarge, another physicalinventory document iscreated with referenceto first PI document.

    MI01Complete data isadopted from the first PIdocument

    2.1.2.7 Post Difference

    The authorized personpost the inventorydifferences in thesystem

    MI07/ MI20

    Differences can beposted individually orfrom the differences list.

    Material and accountingdocuments aregenerated by thesystem.

  • 7/31/2019 HME PDD MM 10 Physical Inv 041110 v01

    9/13

    Page 9 of13

    3. Outputs (forms)

    Physical Inventory Document

  • 7/31/2019 HME PDD MM 10 Physical Inv 041110 v01

    10/13

    Page 10 of13

    4. Standard Reports

    Stock Overview MMBE

    Materials Document MB51

    Reason for Movement MBGR

    Physical Inventory Overview MIDO

    Physical Inventory List MI24

    Changes to Physical Inventory Document MI12

    Count/ Difference MI08

    Difference List MI20

  • 7/31/2019 HME PDD MM 10 Physical Inv 041110 v01

    11/13

    Page 11 of13

    5. Key Performance Indicators

    Physical Inventory for material with higher value can be undertaken more frequently than

    others, thereby providing a constant check to minimize the value/quantity differences.

    SAP can be configured to automatically enable the concerned dept. to undertake the physical

    inventory exercise (with list of materials already prepared) which requires physical inventory, via

    batch processing.

    Activating the Blocking function in SAP ensures that no goods movement of the material takes

    place until physical inventory process is completed, thereby minimizing any chances of

    discrepancy between the time physical inventory results recorded in SAP and any movements of

    goods that took place while the inventory count was going on.

    List of difference enables both quantity and value differences to be available for decision-making

    purposes, that is, those requiring a re-count and those where reasonable difference is

    acceptable.

  • 7/31/2019 HME PDD MM 10 Physical Inv 041110 v01

    12/13

    Page 12 of13

    6. Integration Considerations

    The entire goods movements processes, that is, receipts, issuances, transfer postings provides

    an instant source of information to form the basis of physical inventory in SAP and to cross-

    check the information from SAP to that of physical inventory.

  • 7/31/2019 HME PDD MM 10 Physical Inv 041110 v01

    13/13

    Page 13 of13

    7. Testing Scenarios

    Following are the scenarios which were listed by the user for the above mentioned processes:

    Store check physical stock on quarterly basis and match the quantity of the book quantity and