gravity fed system

31
Gravity Fed System Team Members: James Brinkerhoff, Christopher Kulbago, Patrick O’Connell, Lauren Pahls, Ted Rakiewicz, Sarah Salmon Group Number: P13631 1

Upload: gaurav

Post on 05-Jan-2016

25 views

Category:

Documents


1 download

DESCRIPTION

Gravity Fed System. Team Members: J ames Brinkerhoff, Christopher Kulbago, Patrick O’Connell, Lauren Pahls, Ted Rakiewicz, Sarah Salmon Group Number: P13631. Table of Contents. Team Roles Project Background Schedule MSD II High Level Customer Needs Budget and Costs Bill of Materials - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Gravity Fed System

Gravity Fed SystemTeam Members: James Brinkerhoff, Christopher Kulbago, Patrick O’Connell, Lauren Pahls, Ted Rakiewicz, Sarah Salmon Group Number: P13631

1

Page 2: Gravity Fed System

Table of Contents1. Team Roles2. Project Background3. Schedule MSD II4. High Level Customer Needs5. Budget and Costs6. Bill of Materials7. Engineering Specifications8. Concept Generation9. Feasibility Analysis10. Original System Architecture11. Original P&ID12. Original Cart Layout13. MSD I vs. MSD II Comparison14. Final P&ID15. Final Cart Layout16. Test Results Data17. Labview Layout18. Risk Assessment19. Successes and Failures20. Issues and Actions MSD I21. Issues and Actions MSD II22. Questions

2

Page 3: Gravity Fed System

Team Roles

• Chris Kulbago- Project Manager• James Brinkerhoff- Lead Engineer• Lauren Pahls- Fluids Specialist• Sarah Salmon- Group Facilitator• Patrick O’Connell- Lead Mechanical• Ted Rakiewicz- Lead Electrical

3

Page 4: Gravity Fed System

Project Background• TaskDemonstrate process control in a lab environment using a gravity fed loop with a control valve with an existing flow cart as reference.• Customer and SponsorRIT’s Chemical Engineering Department• Other SupportKodak’s Steve Possanza was our guide through this process. Kodak also donated old parts to make our cart fully functional.• Product StakeholdersStudents who will use the machine, the Department, Dr. Sanchez, Dr. Richter, and staff who will maintain the machine.• CollaborationTwo other groups are designing similar process control machines whose aesthetic appearances must match ours.

4

Page 5: Gravity Fed System

Schedule MSD II

5

Page 6: Gravity Fed System

Customer Needs• Did we meet them?

Customer need: Does project fulfill need?

Safety Yes

Ergonomics Yes

Mobility Yes

Teaching Manually Yes

Teaching Auto-Controls Yes

Ease of Assembly Yes

Low Cost Yes

Use of LabVIEW Yes

Drained Tank Dynamics Yes 6

Page 7: Gravity Fed System

High Level Customer Needs• Machine Design Needs:• A way for students to manually manipulate flow. • A way to manually measure flow. • Easily operated by 3 students.• A safely operating machine.• Interface of machine with LabVIEW.• A way to demonstrate main concepts of process control.• A way to demonstrate noise and time lag in sensors.

• Student Learning Needs:• A lab manual that guides students through lab in a way that

engenders learning. • Discussion questions within lab manual that test understanding

of process control. • Lab manual that focuses on PID control, noise, filtration, data

modeling, disturbances, and/or hysteresis.

7

Page 8: Gravity Fed System

Budget & Costs

0

200

400

600

800

1000

1200

1400

1600

1086.74

1206.28

1500

Budget Tracking

Actual SpentAnticipated SpendingOriginal Request

Mon

ey ($

)

8

Page 9: Gravity Fed System

Bill of Materials

9

Grouping of items:• Items were first divided into three main subsections:

1. Donated by Kodak2. Donated by RIT3. Bought ourselves

• Items purchased were further divided:1. Cart construction equipment2. Electrical equipment3. Miscellaneous Lowe’s items

• Dimensions, part numbers, price, location, and arrival were all listed to better inform team of item status.

• Budget was tracked by entering an estimated cost for items not yet purchased and confirming the cost when the items arrived.

• Our bill of materials is very large and can be viewed on our Edge site.

Page 10: Gravity Fed System

Engineering Specifications• In order to complete the project, the group had to translate

customer needs into technical specifications.• How well the group did in staying within the 19 specifications is

summarized below:

18

1

Specifications

Specifications met

Specification assumed met

Specification not met 10

Page 11: Gravity Fed System

Specifications Met: Part 1

11

Page 12: Gravity Fed System

Specifications Met: Part 2

12

Page 13: Gravity Fed System

Specifications Met: Part 3

13

Page 14: Gravity Fed System

Specification Assumed Met

14

Page 15: Gravity Fed System

Contingency Plan for Assumed Specification

• Contact 4th year Chemical Engineering students to test cart.• Conduct time and operation trials on all contacted persons with cart

and lab manual.

15

Page 16: Gravity Fed System

Concept Generation

16

Page 17: Gravity Fed System

Feasibility Analysis• Line pressure confirmation• With one faucet received around 50 psi• With all faucets on decreased to about 45 psi

17

Page 18: Gravity Fed System

Original System Architecture

18

Page 19: Gravity Fed System

Original P&ID

19

Page 20: Gravity Fed System

Original Cart Layout

20

Page 21: Gravity Fed System

MSD I vs. MSD II ComparisonItem MSD I MSD II

Overall goal Concept Generation Building and Integration

Deliverables Theoretical; Organization and charts

As-built final documents

Time 10 weeks 16 weeks

Individual Contributions About equal More work from EE and ME

Grading Throughout; Several milestones

Only a Functional Review and a Final Review

21

Page 22: Gravity Fed System

Final P&ID

22

Page 23: Gravity Fed System

Final Cart Layout

23

Page 24: Gravity Fed System

Test Results Data

24

Page 25: Gravity Fed System

Labview Layout

25

Page 26: Gravity Fed System

Risk Assessment

26

Page 27: Gravity Fed System

Successes & Failures• Successes• Cart is aesthetically constructed, and highly functional.• LabVIEW provides accurate data collection and adequately allows

for student interaction for real-time process control of a dynamic system.

• Group overcame an equipment failure, and adapted to prevent project hindrance.

• Project is under budget.• All deliverables submitted on time.

• Failures• Digital-to-Analog Converter operation is deviated from design

intent (as of right now).• Cart water usage is not optimized. 27

Page 28: Gravity Fed System

Issues/Actions MSD I• Gravity fed to line feed• We initially were going to have a project that was “gravity fed to a

line feed,” where we had a permanent height for a gravity feed stream.

• Instead of this, we decided to use a second control loop and set of code in order to be able to be more versatile and mimic different heights with different water pressures from a water line.

• Coordinating cart purchase• We discussed a cart design that fits the needs of all three groups.• After negotiating, we came up with a final cart to be used by all

three groups.• Slow start to project• Edge was not readily available for students at the start of MSD I.• The lab learning portion was in progress

28

Page 29: Gravity Fed System

Issues/Actions MSD II• Misinterpreted Pressure Loss• Water pressure loss across flow tube was greater than calculated, and therefore

the water flow rate out in preliminary testing was too low.• We rearranged the cart layout to use potential energy to make our cart drain at

the required flow rate.

• Delicate Level Transmitter• The original mounting design for the level transmitter damaged it. After

mounting, it gave erroneous readings.• A new level transmitter was rush delivered and mounted with electrical tape.

Special handling instructions were noted in manual.

• Interface Issues• The equipment given to us by Kodak was very used and worn. At first, we did

not know how to properly control the 2 I/P circuits, preventing control valve operation.

• Through rigorous testing, this problem was solved and our I/P’s are now fully functional as anticipated.

29

Page 30: Gravity Fed System

Future Suggestions• Recycle Loop• Install a pump with a recycle stream and an additional tank or vessel in

order to reduce water usage.• Time Study• Have 4th year Chemical Engineering students perform the lab procedure

and measure time it takes for students to complete the lab.• Switch Microcontroller• Replace the msp430 Microcontroller with a more reliable National

Instruments Data Acquisition for increased accuracy, ease of assembly and use.

• Newer and More Robust Parts• The Level Transmitter we purchased was low in cost but carries a risk. A

differential pressure cell would minimize this risk.• Parts donated by Kodak are used and worn, and if these are replaced the

robustness of the cart can improve.

30

Page 31: Gravity Fed System

Questions?

31