fukushima daini independent review and walkdown documents/action 01... · fukushima daini...
TRANSCRIPT
Authors:
John Richards, EPRI
Jim Johnson, JJJ & Assoc.
Ken Huffman, EPRI
Greg Hardy, SGH
Antonio Godoy, JJJ & Assoc.
Fukushima Daini Independent Review and Walkdown
IAEA Experts Meeting on Protection
Against ExtremeEarthquakes and
Tsunamis-------------
September 2012
2© 2012 Electric Power Research Institute, Inc. All rights reserved.
Scope of Independent Review and WalkdownFukushima Daini
Reactor BuildingsTurbine BuildingsHeat Exchanger Buildings
Area Description
Seismic Assessment of the earthquake event and effects upon the plants.
Tsunami Assessment of the tsunami effects upon the plants.
Safe Shutdown Technical considerations related to sustaining safe shutdown.
Reporting Reporting of walkdown and review of technical resul ts (EPRI report 1023422).
3© 2012 Electric Power Research Institute, Inc. All rights reserved.
Response of Fukushima Daini Units to the Earthquake
Event Main Item Main Operation Unit No. 1 Time
Status Prior to
Earthquake
Status of Plants Reactor
Rated Power Operation
-----
Offsite Power Supply3 of 4 Circuits
Available-----
Emergency Diesel Generator
Standby State-----
Emergency Core Cooling System
Standby State-----
Earthquake Occurrence Mar. 11 14:46
ReactorShutdown
Reactor Shutdown
Reactor Auto Scram Yes 14:48
Confirm Subcritical Yes 15:00
Power Supply External Power Supply
2 Circuits Available
-----
Emergency Diesel Generator
Standby State -----
Reactor Pressure, Reactor Cooling
Emergency Core Cooling System
Standby State -----
Close Main Steam Isolation Valve
(Auxiliary Boiler Trip)Yes 15:36
Suppression Chamber Cooling (Start-up of
Residual Heat Removal)Yes 15:30
• Seismic trip
• Normal shutdown
• JMA tsunami warning
• Tsunami counter-measures initiated
All units responded the same,Unit 1 response shown here.
4© 2012 Electric Power Research Institute, Inc. All rights reserved.
Tsunami Inundation Reenactment CalculationVideo Record of Tsunami
TEPCO calculation resultsreproducing inundation
observations. Direction of View
5© 2012 Electric Power Research Institute, Inc. All rights reserved.
Unit 1 Emergency Diesel Generator
ExteriorLouvered
IntakeOpening
InteriorAir
FilterFrames
DieselUndergoingMaintenance
6© 2012 Electric Power Research Institute, Inc. All rights reserved.
Heat Exchanger Buildings
Unit 3 North Building North Equipment Hatch
Unit 4 South Building South Equipment Hatch
Components in HeatExchanger Building
Power Cubicles in Heat Exchanger Building
7© 2012 Electric Power Research Institute, Inc. All rights reserved.
Post-Tsunami Station Capabilities
Availability of Several Key Functions After the Tsunami, Before Recovery Actions
FunctionsUnit
1Unit
2Unit
3Unit
4
Offsite Power Yes Yes Yes Yes
Emergency Diesel GeneratorsDivision ADivision BHigh Pressure Cooling System H
NoNoNo
NoNoNo
NoYesYes
NoNoYes
Power to Heat Exchanger Building Equipment
No No Partial No
Operable Equipment in Heat Exchanger Building
No No Partial No
Core Cooling (RHR) No No Yes No
Entry Into UnlightedHeat Exchanger Building
Roadway to Site Protected Area
General Conditions
8© 2012 Electric Power Research Institute, Inc. All rights reserved.
Recovery EffortsRHR Pump Motors
RHR Closed Cooling Pump / Motor
Flooded Motor in Heat Exchanger Building
• First Day• Located replacement motors• Evaluated flooded motors
• Second Day• Motors delivered by
helicopter / overland truck
• Third Day• Installed motors
9© 2012 Electric Power Research Institute, Inc. All rights reserved.
Recovery EffortsTemporary Power for Heat Exchanger Buildings
• First Day• Located replacement
motors• Evaluated flooded
motors• Located temporary cable• Obtained emergency
power vehicles
• Second Day• Motors delivered by
helicopter / overland truck
• Cable delivered by helicopter
• Third Day• Installed motors• Ran cables
10© 2012 Electric Power Research Institute, Inc. All rights reserved.
Recovery EffortsTemporary Cable Installation
Temporary Cables from RadWaste Building to HX Build ings
Temporary Cable Connection to Motor
Temporary Cables Inside Heat Exchanger Building
11© 2012 Electric Power Research Institute, Inc. All rights reserved.
Seismic ObservationsEarthquake Motion EvaluationRecorded Motions Compared to Back-Check (Ss)
Base Mat PGA (Peak Ground Acceleration) Comparisons
East/West (g) North/South (g) Up/Down (g)
Recorded Ss Recorded Ss Recorded Ss
Unit 1 0.234 0.442 0.259 0.442 0.311 0.522
Unit 2 0.200 0.437 0.248 0.436 0.236 0.514
Unit 3 0.220 0.438 0.282 0.436 0.212 0.514
Unit 4 0.209 0.423 0.214 0.423 0.293 0.514
12© 2012 Electric Power Research Institute, Inc. All rights reserved.
Seismic ObservationsWalkdown Conclusions
• Four person seismic team inspected a cross-section of 27 types of SSCs
• Safety-related SSCs did not appear to have evidence of seismic damage
• Safety-related buildings, foundations and equipment generally in excellent condition, virtually no signs of significant damage
Hair Line CrackIn Concrete
13© 2012 Electric Power Research Institute, Inc. All rights reserved.
Seismic ObservationsWalkdown Conclusions
• Non-safety related SSCs performed well, very few instances of seismic damage
• Cause of non-safety related gantry crane displacement was not determined
• Inspection results corresponded to the lowest seismic damage intensity level using either the EPRI or IAEA post-earthquake guidelines
Non-Safety Water Tank“Elephant foot” Buckling
Gantry Crane with One Wheel Displaced from Rail
Displaced WheelOne of a Few Damaged
Tank Anchorages
14© 2012 Electric Power Research Institute, Inc. All rights reserved.
• Complete the evaluation of all (in-structure in addition to base mat) motion records from the earthquake
• Validate truncated motion records by comparison to non-truncated records
• Assign either No Action Required or Action Level 1* to the event using the IAEA post-earthquake guide action levels
• Provide additional focus on any components that had not completed the “back check” process prior to the earthquake and consider Action Level 5* for these* Actions associated with Action Level 1 include focused inspections
and tests (to verify function, operability) and if successful restart the plant
* Action Level 5 actions are the same as Action Level 1 plus re-evaluation of the seismic hazard, if deemed necessary
Seismic ObservationsRecommendations
15© 2012 Electric Power Research Institute, Inc. All rights reserved.
Tsunami ObservationsDirect and Indirect Flooding
Unit #3 Turbine Building B2 Floor
Pipe Penetration in Unit #1 Reactor Building
Unit #1 Heat Exchanger Building
Ventilation Louver on the Ground Floor of Unit #1 Reactor Building
Direct Flooding Indirect Flooding
16© 2012 Electric Power Research Institute, Inc. All rights reserved.
Tsunami ObservationsTsunami Recommendations
• Protection of buildings from major water entry points– Significant flooding would not
be expected
– Extent of in-leakage would be manageable
• Component repair / refurbishment / replacement recommendations– >20 component types
– Test methods and acceptance criteria
– Actions for reuse
– Need for on-going periodic testing
17© 2012 Electric Power Research Institute, Inc. All rights reserved.
Safe Shut Down ObservationsAdequate Cooling, Additional Protection
• Current cooling capabilities were adequate to meet decay heat load needs– Temperature margins sufficient to
address contingencies like replacement of RHRC / RHRS motors
• Recommended additional protection of critical, non-redundant RHR capabilities– Unintentional damage or
disruption of power sources
– Blockage of damaged seawater intakes
– Aggressive equipment condition monitoring
18© 2012 Electric Power Research Institute, Inc. All rights reserved.
EPRI Review and Walkdown Participants
Shiego Hattori
Ken Huffman
Sam Bass
Antonio Godoy
Jim Johnson
Greg Hardy
John Richards
Gary Toman
Jim Heishman
Steve Hess
Drew Mantey
19© 2012 Electric Power Research Institute, Inc. All rights reserved.
Key TEPCO Review and Walkdown Participants
Kazuyuki NagasawaGroup Manager Atsushi Taniguchi
Team Leader
Yukiko OgawaTeam Leader
Naohiro MasudaSuperintendent
Shinichi KawamuraUnit Superintendent