first blu 500 mw

49
First boiler light up A K Das DGM(OS) NTPC Ltd

Upload: rajanme083

Post on 28-Apr-2015

126 views

Category:

Documents


8 download

TRANSCRIPT

Page 1: First Blu 500 Mw

First boiler light up

A K Das

DGM(OS)

NTPC Ltd

Page 2: First Blu 500 Mw

Points of discussion

• Parameters

• General preparation before boiler light up

• System readiness for first light up

• Protection and interlock

Page 3: First Blu 500 Mw

Parameters

Parameter Unit Predicted

Load MW 500

Total fuel MT 344

Superheater O/L pressure Kg/sqcm 176.7

Drum pr Kg/sqcm 191.3

First stage pressure Kg/sqcm 157.44

Reheater I/L pressure Kg/sqcm 43

Reheater O/L pressure Kg/sqcm 41

Super heater O/L steam flow T/hr 1498.5

Feed water flow T/hr 1488.5

Superheater spray flow T/hr 13

Reheater spray flow T/hr 0

Page 4: First Blu 500 Mw

Parameters

ECO I/L temp degC 253

ECO O/L temp degC 324

Superheater O/L temp degC 540

Reheater O/L temp degC 540

Flue gas temp at Pri APH I/L degC 338

Flue gas temp at Pri APH O/L degC 127

Flue gas temp at Sec APH I/L degC 338

Flue gas temp at Sec APH O/L degC 127

PA fan O/L pr mmWC 830

Primary air flow T/hr 652

Sec air flow T/hr 993

Total air flow T/hr 1847

O2% % 3.6

Page 5: First Blu 500 Mw

Preparation for 1st BLU

System readiness for the SIX main systems to be ensured

1. Air system2. Gas system3. Water system4. Fuel system5. Steam system6. FSSS

Page 6: First Blu 500 Mw

Preparation for 1st BLU

Trial run of all auxiliaries (Except Mills)Availability of instruments, interlocks and

protections neededRefractory and insulation work completedAvailability of DM waterCommunication at different locationsSufficient illumination Functioning of chemical lab

Page 7: First Blu 500 Mw

Preparation for 1st BLU

Ensure fire fighting systemEnsure sufficient stock of fuel oil,

lubricants & commissioning sparesWorking instructions and log sheets

Page 8: First Blu 500 Mw

Preparation for 1st BLU

Remove all loose construction materials around boiler

Cut off temporary supports , construction platforms not envisaged in the drgs

All valves marked with tag noAll lines identified by painting by colour

codeInspect water WW,SH,

RH,Eco,APH ,ducts

Page 9: First Blu 500 Mw

Preparation for 1st BLU

Retractable soot blowers must be in withdrawn conditions

Instrument tapping point valves must be open

Drum level signaling and instruments should be made operational

Page 10: First Blu 500 Mw

READINESS FOR FIRST BOILER LIGHT UP

Page 11: First Blu 500 Mw
Page 12: First Blu 500 Mw
Page 13: First Blu 500 Mw
Page 14: First Blu 500 Mw
Page 15: First Blu 500 Mw

BOILER PROTECTIONS

Page 16: First Blu 500 Mw

FSSS• Furnace Safeguard and Supervisory System:

- A fully digital control system which governs mandatory requirements related to safe startup and safe shutdown of the boiler

- Includes main boiler permissives and protections

- Includes heavy oil and light oil firing interlocks

- Includes permissives and protections (digital logic) related to mills and feeders

Page 17: First Blu 500 Mw
Page 18: First Blu 500 Mw

TO HAVE ALL THE MFT (03) DPUS HEALTHY. MFT CIRCUIT IS READY.

Page 19: First Blu 500 Mw

TO ENSURE NO BOILER TRIP IS PRESENT.

Page 20: First Blu 500 Mw

TO PREVENT FUEL TO BOILER.

Page 21: First Blu 500 Mw

TO HAVE PROPER AIR FLOW FOR REMOVAL THE UNBURNT FUEL LEFT IN THE FURNACE

Page 22: First Blu 500 Mw

NO FLAME IN FURNACE

Page 23: First Blu 500 Mw

BOILER PURGE

• A 9 minute mandatory cycle in which FD and ID fans are

run with 30 to 40% air flow, with NO Fuel input to the

furnace, to ensure the removal the unburnt fuel left over in

the furnace area after the last master fuel trip

Page 24: First Blu 500 Mw

BOILER FSSS PROTECTIONS

Three contacts each for Individual ID Fan are generated in corresponding VFD circuit when the electronic speed is sensed to be less than minimum (i.e. 90 rpm)

Page 25: First Blu 500 Mw

BOILER FSSS PROTECTIONS

Three contacts each for Individual

FD Fan are generated in

corresponding 11kV MCC Motor

Feeder Panel

Page 26: First Blu 500 Mw

BOILER FSSS PROTECTIONS

TO FACILITATE OPEARTOR

TO TRIP BOILER MANUALLY

IN IMPENDING SERIOS

CONDITION. BOTH

HARDWIRED & SOFT TRIP.

Page 27: First Blu 500 Mw

BOILER FSSS PROTECTIONS

All elevations voted no flame (no

delay) AFTER any feeder is proven

in service for 2 seconds. An

elevation is said to vote for no flame

if the feeder is not proven, OR if 3/4

oil guns are not in service AND 2/4

fireball flame is not sensed

Page 28: First Blu 500 Mw

BOILER FSSS PROTECTIONS

All oil and coal inputs to the boiler are sensed as closed or OFF (no delay) i.e.- All LONV closed OR LOTV closed +All HONV closed OR HOTV closed + All Feeders OFF (after any LONV/HONV opens partially)

Page 29: First Blu 500 Mw

BOILER FSSS PROTECTIONS

All oil and coal inputs to the boiler are sensed as closed or OFF (no delay) i.e.- All LONV closed OR LOTV closed +All HONV closed OR HOTV closed + All Feeders OFF (after any LONV/HONV opens partially)

Page 30: First Blu 500 Mw

BOILER FSSS PROTECTIONS

Boiler ON AND All BCW OFF

(OR)

2/3 running BCWPs sense DP less than 10 psi=0.67 ksc (5 sec delay)

Page 31: First Blu 500 Mw

BOILER FSSS PROTECTIONS

Boiler ON AND Drum Pressure > 8 ksc AND Flow through reheater tubes is interrupted (10 sec delay). To maintain flow through reheater, both MS to CRH and HRH to condenser paths should be not fully closed. Either HP Turbine path or HPBP path should be not fully closed AND LP Turbine path or LPBP should be not fully closed

Page 32: First Blu 500 Mw

BOILER FSSS PROTECTIONS

Furnace Pressure Very high > +150 mmwc

2 out of 3 logic from 3 pressure switches

Page 33: First Blu 500 Mw

BOILER FSSS PROTECTIONS

Furnace Pressure Very low < -175 mmwc

2 out of 3 logic from 3 pressure switches

Page 34: First Blu 500 Mw

BOILER FSSS PROTECTIONS

Drum Level Very High 250 mm for 10 sec

2 out of 3 logic. 1 from electronic water level indicators (eg. Hydrastep) and 02 from transmitters limit value (average of left and right)

Page 35: First Blu 500 Mw

BOILER FSSS PROTECTIONS

Drum Level Very High -375 mm for 05 sec

2 out of 3 logic from 2 electronic water level indicators (eg. Hydrastep) and transmitter limit value (average of left and right)

Page 36: First Blu 500 Mw

BOILER FSSS PROTECTIONS

Loss of 220V DC in MFT circuit for more than 2 sec.

Loss of 220V DC generates software protection

Page 37: First Blu 500 Mw

BOILER FSSS PROTECTIONS

Loss of 24V DC in 2 out of 3 MFT panels.

Loss of 24V DC generates hardwired protection.

Page 38: First Blu 500 Mw

BOILER FSSS PROTECTIONS

Total air flow (secondary near windbox + primary to individual mills) is less than 30% of full load rated flow I.e. 540 TPH (no delay)

Page 39: First Blu 500 Mw

BOILER FSSS PROTECTIONS

All BFPs OFF with 10 sec delay.

03 contacts generated in Station C&I logic and then hardwired to MFT panels. TDBFP trip is sensed as Trip Oil pressure V Low OR ESV Closed.

Page 40: First Blu 500 Mw

BOILER FSSS PROTECTIONS

Both Secondary Air Heaters OFF with 5 sec delay

3 contacts generated in Station C&I logic and then hardwired to MFT panels. Air Heater OFF is sensed as Electric Motor OFF AND Air Motor OFF i.e. Solenoid valve exit pressure low.

Page 41: First Blu 500 Mw

BOILER FSSS PROTECTIONS

Loss of both communication networks in 2 out of 3 MFT processorsOR Processor failure in 2 out of 3 processorsOR Processor outputs frozen in 2 out of 3 processors

Page 42: First Blu 500 Mw

OIL FIRING LDO

Page 43: First Blu 500 Mw

OIL BURNER ELEVATION AB ONLY

Page 44: First Blu 500 Mw

FUEL OIL SYSTEM MIMIC

Page 45: First Blu 500 Mw

HEAVY OIL FIRING MIMIC

Page 46: First Blu 500 Mw

Coal firing MIMIC

Page 47: First Blu 500 Mw

MFT trip logic diagram

Page 48: First Blu 500 Mw

REHEATER PROTECTION LOGIC

Page 49: First Blu 500 Mw

FSSS COMMISSIONING PROCEDURE…