planning studies for connection of 500 mw photovoltaic
TRANSCRIPT
Helwan University
From the SelectedWorks of Omar H. Abdalla
November 11, 2018
Planning Studies for Connection of 500 MWPhotovoltaic Power Plant to Oman Grid at IbriHisham A. Al-RiyamiAdil Al-BusaidiAhmed Al-NadabiMusabah N. Al-SayabiOmar H. Abdalla
Available at: https://works.bepress.com/omar/53/
Planning Studies for Connection of 500 MW Photovoltaic Power
Plant to Oman Grid at Ibri
H. A. Al Riyami1, A. G. Al Busaidi
1, A. A. Al Nadabi
1, M. N. Al Sayabi
1, A. S. Al Omairi
1, & O. H. Abdalla
2
1Oman Electricity Transmission Company (Sultanate of Oman)
2Helwan University (Egypt)
Summary:
The paper presents techno-economic studies
for connecting a 500MW Photovoltaic (PV) power
plant to the Main Interconnected Transmission
System (MITS) at Ibri. The objective is to justify
the required capital expenditure on the basis of the
submission of a full, complete and robust study
report insuring the transmission system in Oman
is planned, developed and operated in an efficient
manner. Three connection options are proposed
and compared considering cost, compliance with
the Security Standard, technical performance,
deliverability, environmental conditions, flood risk
assessment and safety.
The MITS models of 2020 and 2021 have been
updated to include the simulation of the alternative
connections of the 500MW PV power plant. The
DIgSILENT PowerFactory professional software is
used to perform system analyses for different
cases. The solar PV technology and components
are discussed. The MITS description and is
presented. Steady-state analyses; including power
flow, 3-phase short-circuit, 1-phase short-circuit
and contingency are presented. Transient analyses;
including system responses to line fault and
generator outage are presented.
Keywords: Ibri Solar Power Plant, MITS,
Photovoltaic.
1. INTRODUCTION
There has been a considerable interest in
renewable energies over the world in recent decades.
Oman Electricity Transmission Company (OETC) has
received a connection application from Oman Power
and Water Procurement Company (OPWP) [1] for
connection of a 500 MW Photovoltaic (PV) power
plant to the Main Interconnected Transmission
System (MITS) at Ibri. The target date of the PV
power plant connection is 1st of December 2020 and
the scheduled commercial operation date is June
2021. In order to meet the Transmission Licence
Conditions 8, 23 and 26 [2] and mitigate any risk
associated with non-compliance of these obligations,
OETC has to prepare a Pre-Investment Appraisal
Document (PIAD) including technical and economic
studies to assess a number of available connection
options and recommend the most financially and
technically suitable solution [3, 4].
The following three proposed options have been
assessed and compared:
Option 1: 132 kV connection by LILO of Ibri-
Dank Line.
Option 2: 220 kV direct connection to Ibri IPP grid station.
Option 3: 400 kV direct connection to Ibri IPP grid station.
The preferred option providing a technically
viable, deliverable and financially preferable solution
is Option 2: the construction of a 220 kV double
circuit connection from Ibri Solar Power Plant to Ibri
Independent Power Plant (Ibri IPP). This solution
allows new generation at Ibri Solar Power Plant to
supply local loads in the Ibri area with a parallel
connection into the wider 400 kV network to New
Izki. Furthermore, the selected option aligns with the
OETC master plan (2014-2030) [5]. The preferred
option presented a lower lifetime cost (on an NPV
basis), lower losses, higher technical performance and
a more deliverable solution.
Figure 1: The MITS of Oman in 2018.
The paper is organized as follows: Section 2 describes the existing transmission system in Oman. Section 3 provides a brief description of the PV Power Plant concept. Section 4 presents Ibri generation site and surrounding transmission assets. Section 5 presents the technical and economic studies of connecting Ibri IPP to the MITS and provides a comparison of the options. Section 6 presents full technical and economic studies of the preferred connection option. Section 7 summarises the main conclusions of the paper.
2. SYSTEM DESCRIPTION
The existing transmission system in northern
Oman has three HV operating voltages, i.e. 400 kV,
220 kV and 132 kV while in Dhofar 132 kV is
employed. The transmission system extends across the
whole of northern Oman and interconnects bulk
consumers and generators of electricity located in the
Governorates of Muscat, Batinah South, Batinah
North, Dhahirah, Buraimi, Dakhliyah, Sharquiya
South and Sharqiya North as shown in Figure 1.
The present OETC transmission system of the
MITS consists of [6]:
1214.5 circuit-km of 400 kV overhead
transmission lines
1607.36 circuit-km of 220 kV overhead
transmission lines
3538.73 circuit-km of 132 kV overhead
transmission lines
75.1 circuit-km of 220 kV underground cables
158.52 circuit-km of 132 kV underground cables
9750 MVA of 400/220 kV transformer capacity
15630 MVA of 220/132 kV transformer capacity
570 MVA of 220/33 kV transformer capacity
19479 MVA of 132/33 kV transformer capacity
150 MVA of 132/11 kV transformer capacity
Three 400/220/132/33 kV grid stations
Two 400/220 kV interconnection grid stations
Three 220 kV interconnection grid stations
Six 220/132/33 kV grid stations
Two 220/132 kV grid stations
Two 220/33 kV grid stations
Fifty Three 132/33 kV grid stations
One 132/11 kV grid station
In addition, the present OETC transmission
system at Dhofar consists of [6]:
503.99 circuit-km of 132 kV overhead
transmission lines
33.64 circuit-km of 132 kV cables
2062 MVA of 132/33 kV transformer capacity
Eight 132/33 kV grid stations
3. PHOTOVOLTAGE POWER PLANT
A photovoltaic system is a green power source, which converts sunlight directly to electricity. The main advantages of the PV system are that it requires
no fuel, produces no emissions, and involves no moving parts. Figure 2 shows the main components of a PV power plant. It consists of a large number of solar arrays, DC/DC converters, DC/AC inverters, filters, and step up transformers.
Figure 2: Main components of a PV power plant.
A solar PV module, which consists of a number of solar cells, produces only a small amount of current and voltage. In order to produce a large amount of electric power, the solar cell modules are connected into arrays. The output voltage from a PV array changes with solar radiation and ambient temperature. In order to connect the PV system to the transmission grid, the output DC voltage from PV system should be first regulated by a DC/DC converter and then converted to AC voltage source by a DC/AC inverter. A filter is used to eliminate harmonics. The power electronic components (DC/DC converter, DC/AC inverter, and filter) have the tasks to guarantee safe and efficient operation, to track the maximum power point tracking of the PV system, and to maintain power quality of the PV system output.
4. IBRI IPP GENERATION SITE AND
SURROUNDING MITS ASSETS
The Ibri Solar IPP site is proposed to be located approximately midway between the towns of Ibri and Dank (see Figure 3). Nearby there exists a 220 kV double-circuit OHTL which terminates at Ibri from Mahadha in the north (~150 km total length). In parallel to this, a 132 kV network extends from Ibri to Mahadha via Dank and Wadi Sa’a (see Figure 1). These 132 kV circuits also continue from Ibri to the east towards Izki. Also, there is 400 kV double-circuit line connected between Ibri IPP grid station and New Izki grid station (~264 km total length). There is a designed 400 kV overhead line but currently operated at 220 kV; it is under construction between Sohar-3 IPP via SFZ and Mahadh and is expected to be completed by end of July 2018. Mahadh is connected to the UAE grid and Ibri IPP via a double-circuit 220 kV overhead line. Therefore, the evacuation corridors of the generated power at Ibri area will be via the 400 kV system towards Izki and Misfah and via 220 kV system towards Mahadh and consumed locally at Ibri through the 220 kV and 132 kV systems in Ibri, Dreez, Dank and Heyal grid stations.
Figure 3: Ibri generation site
With reference to the Annual Five Year Capability Statement 2018 [6], it is expected that new 400 kV double circuit lines from Ibri to New Izki (under construction – June 2018 expected completion date), and 400/220 kV with 3x500 MVA transformers (already Energized). Additionally, the ongoing project of construction 400 kV double circuit lines from New Izki to Misfah is expected to be completed by the end of March 2019. New 400 kV lines to SFZ and Mahadh grid stations are construction.
Figure 4 shows the forecasted peak demand
growth against the net maximum generation export in
the area (substations along the corridor from Mahadha
in the north to Nizwa in the south).
5. TECHNICAL AND ECONOMIC
EVALUATION OF OPTIONS
Three options have been considered to mitigate the risks associated with non-compliance of License Conditions 8, 23 and 26 [2]. These options are summarised as follows:
Option 1: 132 kV connection by LILO of Ibri-
Dank Line.
Option 2: 220 kV direct connection to Ibri IPP
grid station.
Option 3: 400 kV direct connection to Ibri IPP
grid station.
Each of these options is assessed on the basis of the following performance considerations:
i. Deliverability
All the associated circumstances on every option have been assessed on term of circuit routes, grid station location …etc.
DC/AC Inverter
DC/DC Convert
er
Grid
0 200 400 600 800 1000 1200 1400 1600 1800 2000 2200 2400
2018
2019
2020
2021
2022
762.8
819.5
832.7
881.4
934
1261
1803
1802
1801
2299
MW
Ye
ar
Peak Demand VS Net Generation
Net Generation
Peak Demand
Figure 4: Peak demand and net generation forecast in study area.
ii. TSS Compliance The Transmission Security Standard has been
prepared in accordance with Condition 26 of OETC's Transmission and Dispatch Licence [2]. OETC implements the TSS for the planning and operation of its licensed transmission system.
iii. Capital cost Cost of every asset and civil works cost on every options have been be calculated thoroughly.
iv. Net Present Value (NPV) The net present value is calculated for every option for 40 years.
v. Environmental considerations As OETC is an ISO 14001 (EMS) “Environmental Management System” certified company, it is committed toward environment so all the environmental impacts of every project are considered.
vi. Flood risk assessment OETC maintains a check list that considers the location of all assets associated to every option to the nearest flood or valleys.
vii. Safety As OETC is an ISO 18001 (OHSAS) “Occupational Health and Safety Assessment Series” certified company, it is committed toward safety so all the safety impacts of every project are considered.
viii. Comparison of options Table I provides a comparative summary of the
options based on the key aspects assessed including financial, technical performance, deliverability, environmental considerations including Flood Risk
Assessment (FRA) and safety aspects. Colour coding is provided for visual reference such that green indicates no issues, yellow indicates feasibility but with some additional considerations, red indicates a non-feasible aspect which prevents the option from being considered further and black notes items in non-feasible options that have not been fully assessed due to a prior limitation.
As summarised in Table I, Option 1 is deemed not feasible as a result of significant overloads seen under (N-1) assessments across a range of outage conditions and therefore non-compliant with the OETC TSS and subsequent Licence Condition 26. This option is therefore not considered further, leaving Option 2 and Option 3 as the remaining feasible options. While both options 2 and 3 are having almost similar technical performance, then the main factor for comparison is the capital cost for the present and future solar expansion. A summary of Option 2 and Option 3 and the relative merits of each are subsequently provided below:
Option 2
This option presents the least cost lifetime cost solution with regard to capital cost by minimising any new 400 kV infrastructure and utilising the 220 kV voltage level. It is proposed that the 220 kV overhead lines be constructed for a length of 3 km. It also complies with the TSS requirements. In addition, option 2 has lower power losses in comparison with option 3. Furthermore, option 2 incurs lower capital cost by about two million for the present connection of Ibri Solar-PV power plant and also lower capital cost by about one million for future solar expansion if required.
Table I: Comparison of options
Option 1
Option 2
Option 3
Capital Cost
[R.O.] 8,284,726.23 10,197,550.61
NPV -29,463,075 -33,448,649
Future Solar Expansion
Cost 1,354,497 2,202,375
Tech
nic
al
Perfo
rm
an
ce
Intact TSS Violation (Loading Issue) No issues No issues
N-1 TSS Violation (Loading&
Supply lost Issues) No issues No issues
N-M-1
No issues No issues
Short Circuit
No issues No issues
Losses (2022 Peak) High losses (51MW) Lower losses (32.13MW) Medium losses (33.03MW)
Deliverability
LILO of the 132kV OHL will
required long Shutdown and
proper coordination to secure
power supply to Dank and
Yanqul areas
- Crossing rail way
route
- Securing new OHL
route
- Crossing rail way route
- Securing new OHL
route
Environmental No issues No issues No issues
FRA Low risk Low risk Low risk
Safety Has medium risk dealing with
existing OHL diversion
Has medium risk by working in
live system at Ibri IPP GS
Has medium risk by working in
live system at Ibri IPP GS
Option 3
This option results in a greater capital cost due to
the establishment of a 400 kV substation at Ibri Solar-
PV PS with associated 400 kV OHL and additional
two 400 kV bays at Ibri IPP substation. Moreover, the
future solar expansion will entails higher capital cost
compared to option 2. Furthermore, it has higher loss
compared to be option 2.
Based on the comparison of the options presented
above, it is clear that option 2 represents the
technically preferred long term solution whilst
providing the lowest lifetime cost with minimised
deliverability risks. Subsequently, option 2 is
recommended for the connection of the proposed Ibri
Solar-PV IPP generator.
ix. Dynamic studies
Subsequently, dynamic studies of the preferred option (option 2) relating to a close and remote three phased fault of one of the 220 kV lines from Ibri Solar-PV PS to Ibri IPP have been conducted. Also, a Solar-PV PS trip at Ibri have been conducted and the results are presented. The studies have been completed for peak and off peak demand conditions. It is concluded that there are no issues to report with regard to the dynamic assessment with all generators in MITS remaining stable under the conditions assessed.
6. PREFERRED CONNECTION OPTION
A. Configuration Figure 5 shows the location of Ibri Solar power
plant with option 2 connection. Figure 6 shows a
simplified connection of Option 2. This preferred
option mitigates the licence condition risks whilst
providing a technically viable, deliverable and
financially preferable solution through the
construction of a 220 kV double circuit connection for
a length of 3 km from Ibri Solar-PV IPP to Ibri IPP
station. The solution allows new generation at Ibri
Solar-PV power plant to supply local loads in the
Ibri/Nizwa area with a parallel connection into the
wider 400 kV network to Misfah, Izki and Mudharib.
Figure 5: Location of Ibri 500 MW power plant
Figure 6: Simplified configuration of Option 2.
B. Works and Equipment
The outline specification of the works associated
with the preferred option is as follows:
Establish 220 kV switchgear (GIS) in Ibri Solar-PV
PS Substation
2 x 220 kV GIS: unit incomers
4 x 220 kV GIS: two bus section and two bus
coupler
2 x 220 kV GIS: outgaining feeders
Associated civil, auxiliary and infrastructure
works to support the above equipment
2 x 220 kV GIS as feeder incomers at Ibri IPP
substation with associated protection and civil
modification.
3 km 220 kV twin Araucaria overhead line double
circuit from Ibri Solar-PV IPP to Ibri IPP grid
station.
500 m, 220 kV, 2500 mm2 XLPE cable
between the gantries to the 220 kV GIS at Ibri
IPP station.
This option 2 is capable to cater for the future
solar expansion in Ibri area with additional investment
but with lower cost in comparison with option 3. It is
recommended that the works are carried out in time
for meeting the proposed schedule commercial
operation date of June 2021 to ensure compliance
with OETC licence conditions. Maximum export of
500 MW for the Ibri Solar-PV IPP generator is
expected in June 2021.
C. Cost
The chosen option aligns well with the OETC
principles of developing the Oman electricity
transmission system in a cost effective manner whilst
providing a secure and reliable service to customers in
compliance with statutory requirements (i.e. the Oman
Grid Code, Transmission Licence, etc.). The preferred
option provides lower lifetime cost (on NPV basis),
lower losses, higher technical performance and a more
deliverable solution. The estimated capital cost for
connection of the Ibri IPP to the MITS is R.O.
8,284,726.23. The requested funding will be
distributed over five years as follows:
2018 – R.O. 1,656,945.25
2019 – R.O. 2,899,654.18
2020 – R.O. 2,899,654.18
2021 – R.O. 828,472.62
D. Deliverability
This option would require the delivery of a new
220 kV specification double circuit line for a length of
approximately 3 km. Initial site surveys have been
conducted and indicated that there is scope to acquire
a suitable right of way to allow this development.
Also, the rail route is passing in between the Ibri
Solar-PV and Ibri IPP sites which shall be considered
during the OHTL design. However, at this time the
survey has indicated that the use of overhead line
throughout the route length should be feasible.
E. Technical Performance
A digital model of the MITS has been developed
[9] using the DIgSILENT professional software [10].
The model has been updated to accommodate new
assets to be added in studied years (2021). The
following simulation studies have been performed to
assess the technical performance of the MITS with
Option 2 of Ibri Solar IPP connection.
Intact Conditions
Tables II show power flow results at peak
demand condition after adding the Ibri IPP in 2021.
Although Ibri IPP and Ibri Solar-PV IPP physically
are in one site and Ibri Solar is connected through 3
km of 2 x 220 kV OHTL to Ibri IPP 220 kV BB, but
electrically they have a common connection point.
Therefore, it looks like one generation site with
approximately 2039 MW (500 MW Solar plus 1539
MW Ibri IPP). Since the connection of the Solar-PV
IPP under this option is via the 220 kV, the flow from
400 kV Ibri IPP GS to Ibri load group decreases and
the majority of the Ibri IPP power is now exported by
the 400 kV lines in the direction of New Izki and
Misfah areas around 1072 MW compared to 654.7
MW prior the connection of the Solar-PV IPP. Thus,
there is no concern for the out of frim loading of the
3x500 MVA, 400/220 kV transformers at Ibri IPP.
However, the risk of the out of firm loading is
cascaded to the 220/132 kV, 2x500 MVA
transformers at Ibir grid station where the loading
reached 56.18%. However, it should be highlighted
that the loading of these transformers is not mainly
driven by the connection of Ibri Solar-PV IPP rather
than the load growth in Ibri area where their loading
before the connection of the Solar-PV IPP was
47.91%. However, tripping any of these transformer
has not resulted in overloading of the second
transformer and therefore comply with TSS
requirement.
The other lines and transformers at Ibri network
are well within the standard limits. The loading of the
2 x 220 kV line between Ibri IPP to Ibri grid stations
is 41.74% which is very well within the firm capacity.
With respect to the voltage profile for Ibri network
area at different voltage levels 400 kV, 220 kV and
132 kV, it shows acceptable voltage profile and no
voltage violation has been detected for the system
peak condition.
(N-1) Contingency Conditions
A loss of one of the 400 kV lines to New Izki
results in small impact on the remaining network with
flows seen to be in line with intact conditions (with
exception to the second 400 kV line which is now
loaded to 41.62%). Similarly, a loss of one of the 220
kV lines to Mahadha also results in small impact on
the remaining network.
Subsequently, a loss of one of the 220 kV circuits
from the Ibri IPP substation to the Ibri 220/132 kV
substation results in other circuit loading to 77.48%.
Furthermore a loss of one of the 220/132 kV
transformers results in loading of the remaining
transformer to 96.66% which complies with TSS
criteria. Therefore, a third transformer may be will
required in the future considering the load growth of
the area which is subject to another assessment.
Moreover, losing one of the 3 x 400/220 kV
transformers at Ibri IPP station has no major impact as
the Solar-PV IPP connection is at 220kV system and
no violation has been observed. Additionally, a loss of
any of the 132 kV circuits in the Ibri to Jebreen
corridor results in loading of the remaining circuit (up
to 46.67%).
Finally, from voltage profile perspective, the
most credible scenario that has the highest voltage
changes is the loss of one of the 220/132 kV
transformers at Ibri grid station. However, the drop of
voltages were within the acceptable limits, where the
lowest voltages were (0.96-0.97 pu) noted at Dreez,
Hayel and Jebreen stations of as shown in Table II.
From the above assessment it is clear that Option
2, with connection arrangement does meet OETC TSS
requirements under (N-1) condition. This option is
therefore deemed feasible on the grounds of OETC
TSS compliance.
(N-M-1) Contingency Conditions
(N-M-1) conditions relate to a forced outage
occurring during the periods of low demand, when
another asset is already out for maintenance. The
network configuration for the (N-M-1) study reflects
the maintenance period (usually in winter) when the
OETC TSS requirements such that all 33 kV (and
below) connected loads are reduced to 67% of peak
demand unless realistic data is available, whilst direct
connected customers to transmission customers
remain at peak demand values. As the assessment
focus of this PIAD is the connection of Ibri Solar-PV
PS, it assumed to operate at its maximum output 500
MW to reflect the most challenging operation case.
Therefore, the connection arrangement that being
assessed must be capable to cater for full power
evacuation under the (N-M-1) condition whilst Ibri
IPP is dispatched in practical manner similarly to
other generation in the transmission network.
Therefore, the total generation at Ibri in this case is
892 MW (500 MW Solar plus 392 MW Ibri IPP).
The above arrangement provides a suitable
network configuration to allow the (N-M-1) studies to
be conducted, representing a reduced load scenario in
line with OETC TSS requirements (and practical
network loadings in the maintenance period) in
addition to a practical generation dispatch whilst
maintaining a maximum output of Ibri Solar-PV IPP.
Sur gas turbines, as the reference (swing bus)
machines, are seen to be at 54% output under this
arrangement, indicating a practical balance of
generation and demand. Further (N-M-1) contingency
analysis indicated no voltage constraints based on this
connection arrangement as the load during the
maintenance period is low.
Short Circuit Levels
Three-phase and single-phase to ground intact
system short circuit system levels (all generators on to
provide worst case assessment) have been calculated
(according to the IEC 60909) and are measured
against equipment ratings for relevant substation
locations in the vicinity of the new Ibri Solar IPP.
Table II: Branch power flow and voltage profile (2021)
Peak System Case Loading %
Condition N
Condition
N-1
Conditions
Lines / Scenarios Intact
System
220 kV OHL
Ibri Solar-
Ibri IPP
400 kV OHL
Ibri IPP-
New Izki
220 kV
OHL Ibri
IPP-Ibri GS
220 kV OHL
Ibri IPP-
Mahadha
132 kV
OHL Ibri
GS-Jebren
2x500 MVA
(220/132kV)
Tx @ Ibri GS
220kV OHL Ibri
Solar-Ibri IPP 35.99 71.19 36.3 35.64 35.74 35.52 35.63
400kV OHL Ibri
IPP-New Izki 29.07 29.07 47.94 29.69 30.99 29.86 30.29
220kV OHL Ibri
IPP-Ibri GS 41.74 41.74 47.65 77.48 44.24 38.48 35.91
220kV OHL Ibri
IPP-Mahadha 24.14 24.14 34.84 25.71 33.84 24.91 27.2
132kV OHL Ibri
GS-Jebren 32.7 32.68 41.47 28.95 34.13 46.67 25.62
3x500MVA
(400/220kV) Tx
Ibri IPP
28.55 28.62 42.35 27.43 25.39 26.4 26.09
2x500MVA
(220/132kV) Tx @
Ibri GS
56.18 56.18 64.13 52.14 59.54 51.79 96.66
Peak System Case Voltage Profile (pu)
220kV Ibri Solar
BB 1.04 1.04 1.02 1.04 1.04 1.05 1.04
400kV Ibri IPP BB 1.04 1.04 1.03 1.04 1.04 1.04 1.04
400kV New Izki
BB 1.02 1.02 1.0 1.02 1.01 1.01 1.01
220kV Ibri IPP BB 1.04 1.04 1.02 1.04 1.04 1.05 1.04
220kV Ibri GS BB 1.02 1.02 1.0 1.0 1.01 1.02 1.02
220kV Mahadha
GS BB 1.04 1.04 1.02 1.03 1.03 1.04 1.03
132kV Ibri GS BB 1.01 1.01 1.0 1.0 1.01 1.02 0.98
132kV Jebreen GS
BB 0.98 0.98 0.96 0.97 0.97 0.97 0.96
132kV Al Hayl GS
BB 1.0 1.0 0.97 0.98 1.0 1.0 0.97
132kV Dreez GS
BB 1.0 1.0 0.98 0.98 1.0 1.01 0.97
Table III shows a sample of the calculated short
circuit currents of 2022 system condition. These and
fault currents at other busbars are within the
corresponding thermal busbar fault levels.
Table III: Short circuit levels
Bus Bars Rating
(kA)
Short Circuit
3-Ph
(kA)
1-Ph
(kA)
400kV Ibri IPP BB 63 18.1 20.88
220kV Ibri IPP BB 50 19.4 20.43
220kV Ibri GS BB 50 13.12 13.04
132kV Ibri GS BB 31.5 15.84 18.87
Losses
Real power losses at 2019 peak demand have been
calculated for this option to be included in the lifetime
cost assessment and as a comparison to other feasible
options. The real power losses have been calculated
for the network in the vicinity of the Ibri IPP which is
directly impacted by the additional generation.
Broadly this relates to the 400 kV network from Ibri
to Izki, the 220 kV network to Mahadha from Ibri, the
132 kV network from Ibri to Al-Hayl and Nizwa in
addition to relevant transformers at these locations.
After the connection of the Solar-PV power plant,
the transmission losses have increased from 14.36
MW to 32.13 MW. The major losses increase is
observed in the 400 kV line, the 220 kV line to
Mahadha and 132 kV to Jebreen. This is because, the
majority of generated power (around 1072 MW) of
Ibri IPP is transmitted to Izki and Misfah areas via the
400 kV and 338 MW flow to the direction of
Mahadha GS via the 220 kV line. In addition, the
power flow towards Jebreen and Nizwa GSs has
increased causing more power losses in the long 132
kV lines. The losses are dominated by the 220 km 400
kV overhead line from Ibri IPP to Izki grid station
with losses of 18.8 MW.
F. Financial Assessment
The capital cost assessment of this option in full,
including five year spend phasing, and can be
summarised as a total cost of R.O. 8,284,726.23. The
NPV assessment of the option which accounts for
lifetime costs associated with losses and estimated
operations and maintenance costs over a 40 year
period. The resulting NPV is R.O. -29,463,075.
G. Environmental Considerations Initial site surveys have been conducted which
suggest there is scope to obtain a suitable corridor for
the new circuit. Furthermore, it is assumed at this
time that overhead line can be utilised for the entire
route length. Therefore, there are limited unknown
environmental concerns at this time.
H. Flood Risk Assessment
A flood risk assessment for the Ibri Solar IPP
power station has been conducted with full details.
The assessment has illustrated that there is no
significant flood risk associated with this
development.
I. Safety
There is no significant safety considerations
associated with Option 2. The new line will be
constructed in a new line corridor, offline and away
from other live infrastructure.
J. Dynamic Studies
The compliance with TSS requirements has been
assessed by steady state and dynamic studies for both
peak and off peak demand with full evacuation of Ibri
Solar IPP. The dynamic studies cover the rotor angle
stability, voltage response and frequency response at
both peak and off peak demands. Samples of the
dynamic studies are presented here. Figure 7 shows
the frequency response to a three phase short-circuit
cleared in 120 ms (at the 220 kV line between Ibri
Solar-PV and Ibir IPP GS), at peak demand. Figure 8
shows the frequency response to tripping the 500MW
Solar PV power plant.
7. CONCLUSION
This paper describes the assessment for each
option from different aspects, technically, financially
and risk of deliverability of the Ibri Solar IPP
connection project. The assessment of each option has
been carried out on the basis of the following
performance considerations: deliverability,
Transmission Security Standard (TSS) compliance
technical performance, capital cost, net present value,
environmental considerations, safety and flood risk
assessment. Power losses have also been considered
in the NPV calculation. In addition, the paper
describes the optimal generation connection design
that is respected the TSS criteria. The compliance
with TSS requirements has been proved by steady
state and dynamic studies for both peak and off peak
demand with full evacuation of Ibri Solar IPP power
plant.
The preferred Option 2 has shown to mitigate the
licence condition risks whilst providing a technically
viable, deliverable and financially preferable solution.
It consists of construction of a 220 kV double circuit
10.008.006.004.002.000.00 [s]
50.0004
50.0003
50.0002
50.0001
50.0000
49.9999
[Hz]
132kV Al Kamil BB: Electrical Frequency
132kV Manah BB: Electrical Frequency
220kV Airport Height BB: Electrical Frequency
220kV Barka PS BB: Electrical Frequency
220kV Barka-3 PS BB: Electrical Frequency
220kV Ibri IPP BB: Electrical Frequency
220kV Sohar-1 PS BB: Electrical Frequency
220kV Sohar-2 PS BB: Electrical Frequency
400kV Ibri IPP BB: Electrical Frequency
400kV Misfah BB: Electrical Frequency
400kV New Izki BB: Electrical Frequency
400kV Sohar-3 IPP BB: Electrical Frequency
400kV Sur PS BB: Electrical Frequency
132kV Rusail Industrial BB: Electrical Frequency
connection from Ibri Solar IPP to Ibri IPP grid
stations. The NPV assessment of this option which
accounts for lifetime costs associated with losses and
estimated operations and maintenance costs over a 40
year period. The resulting NPV of this option has
been calculated to be R.O. -29,463,075.
8. REFERENCES
[1] OPWP: “Seven Year Statement (2016-2022)”,
www.omanpwp.com
[2] OETC: “Transmission and Dispatch Licence”,
2016, www.omangrid.com
[3] OETC: “PIAD for Connection of Ibri IPP
Generator Project”, Ref: 51/2018, 2012.
[4] OETC-AMP-P-SOP-M-007 Preparing PIADs,
2017.
[5] H. Al-Riyami, O. H. Abdalla, A. Al-Busaidi, A.
Al-Nadabi, M. Al-Siyabi, M. Al-Abri, Z. Al-
Rawahi, J. Dubois, V. Lambillon, Sh. Mirza, and
A. Bastens: “Development of Transmission
System Master Plan of Oman (2014-2030)”,
Paper No. A036, GCC Cigre 2014, Al-
Manamah, Bahrain, November 2014.
[6] OETC: “Five Year Annual Transmission
Capability Statement (2017-2021),
www.omangrid.com
[7] OETC: “The Grid Code”, Version 2, April 2010,
www.omangrid.com.
[8] OETC: Transmission Security Standard, July
2016, www.omangrid.com
[9] O. H. Abdalla, H. Al-Hadi, and H. Al-Riyami:
“Development of a Digital Model for Oman
Electrical Transmission Main Grid”, Proc. of the
2009 International Conference on Advanced
Computations and Tools in Engineering
Applications, pp. 451-456, Notre Dame
University, Lebanon, 15-18 July, 2009,
www.ieeexplore.ieee.org
[10] DIgSILENT 2016 Technical Reference.
Figure 7: Frequency response, at peak demand, to a three phase short of 120 ms, at .
10.008.006.004.002.000.00 [s]
50.01
49.97
49.93
49.89
49.85
49.81
[Hz]
132kV Al Kamil BB: Electrical Frequency
132kV Manah BB: Electrical Frequency
220kV Airport Height BB: Electrical Frequency
220kV Barka PS BB: Electrical Frequency
220kV Barka-3 PS BB: Electrical Frequency
220kV Ibri IPP BB: Electrical Frequency
220kV Sohar-1 PS BB: Electrical Frequency
220kV Sohar-2 PS BB: Electrical Frequency
400kV Ibri IPP BB: Electrical Frequency
400kV Misfah BB: Electrical Frequency
400kV New Izki BB: Electrical Frequency
400kV Sohar-3 IPP BB: Electrical Frequency
400kV Sur PS BB: Electrical Frequency
132kV Rusail Industrial BB: Electrical Frequency
Figure 8: Frequency response, at peak demand, to tripping the 500 MW Solar-PV power plant.