construction of 500 mw steam boiler
DESCRIPTION
It is the Construction of 500 MW Subcritical Boiler. as well as the Steam cycle flow and water cycle flow of a BoilerTRANSCRIPT
Construction of 500 mw boiler
by Vaibhav G. Paydelwar ( Project Engineer) Sunil Hi-Tech Engineers Limited
Boiler means any closed vessel exceeding 22.75 Ltr. in capacity used for steam generation under pressure. The first boiler was developed in 1725 and its working pressure was 10 kg/ cm2.
Boiler can be regarded as a number of interconnected heat exchangers arranged in such manner that heat available by burning of fuel is transferred to convert water into steam in most efficient manner.
WHAT DO YOU MEAN BY BOILER ?
FUNCTION OF BOILER
To produce the steam at the desired
rate at desired pressure and temperature
with use of resources such as oil, coal &
water for generating the power.
Types of BoilersNatural circulation Boiler :- Drum to down comer - to main ring header – to ww tubes and back -to drum. Due to difference in density of water and steam this types of circulation takes place.
Forced circulation (Assisted circulation) Boiler :- As per operating pressure of the boiler approaches to the critical pressure, additional pumps are required to install in down comers, because at this pressure there is no appreciable density difference between water and steam to have natural circulation of water.
NEED FOR ASSISTED CIRCULATION
80 100 120 140 160 180 200 220 2400
0.1
0.2
0.3
0.4
0.5
0.6
0.7
Pressure (Kg/cm2)
Density of Water
Density of Steam
Critical Point
According to working pressure
Sub critical pressure boiler : when working pressure of boiler is between 130 to 180 kg/ cm2
critical boiler : when working pressure of boiler is 225.56 kg/ cm2
Super critical boiler : when working pressure of boiler is 240.10 kg/ cm2
Why to go for higher capacity ?
1’-2’ = Work done in turbine from P1 – P2
2’-3 = Heat Rejection in condenser
3-4 = Water pumped to boiler
4-1 = Heat addition in eco and boiler.
SPECIAL FEATURES OF 500MW BOILER
Controlled circulation of feed water in water walls with the help of 3 Nos. of boiler circulating water pumps installed on down comers. Rifled bore water wall tubes as against smooth bore tubes in 210 MW boiler.
Provision of Orifices for equal distribution of water in water wall tubes from bottom ring header.
All down comers are connected to front header of the bottom ring header.
DESIGN FACTORFor the construction of boiler parts subjected to pressure and their integral attachment, the designer takes into account several factors Relative Cost Mechanical Properties Manufacturing Method Scaling Resistance Maintenance
Various parts of BoilerBOILER IS DIVIDED INTO TWO PASS:- FIRST PASS SECOND PASS
First pass of the boiler consists of:-
Furnace water wall.
Divisional super heater pendent assembly.
Final Super heater pendent assembly.
Reheater front pendent assembly. (CRH)
Reheater rear pendent assembly. (HRH)
Rear Arch Panel.
Water Wall screen tubes.
Second pass of the boiler consists of:-
Steam cooled wall.
Economizer lower bank coils.
Economizer middle bank coils.
Economizer upper bank coils.
LTSH lower bank coils
LTSH upper bank coils
Eco. Hanger tubes.
LTSH terminal tubes.
ECONOMISER Requirement why ? Advantages• As the economiser recover the heat in the flue gas that leaves the boiler
and transfer to working fluid there will be saving in fuel consumption.• As the feed water is preheated in the economiser and enter the boiler
tube at an elevated temperature( near to saturation temp.) the heat transfer area required for the evaporation surface required will be reduce considerably. As the size of boiler also will be reduced.
Types of Economiser Steaming Non steaming• Plain tube economiser• Fin-tube economiser
Plain tubes Direction of Gas Flow
Direction of Gas Flow
Inline Arrangement Staggered Arrangement
Fin-tube Eonomiser
Tube size and spacing The tubes can be made any length and diameter with 38mm to 52mm
OD. The side spacing and back spacing can be arranged for good cleaning, absorption of heat and less draught loss. Spacing about 90mm to 140mm.
It is composed of three banks of 130 parallel tube elements arranged in horizontal rows in such a manner that each row is in line with the row above and below.
Drum & Drum Internals Requirement Separation of saturated steam from the steam-water mixture produced by the
evaporating tubes Mixing feed water from economiser and water separated from steam – water
mixture, and re-circulate through the evaporating tubes. Carrying out blow down for reduction of boiler water salt concentration. Treatment of Boiler water by chemicals
construction of drum
1 11111
BOILER DRUM: Construction: Fusion weldedMaterial specification: SA299Design pressure: 204.9 kg/cm2
Maximum operating press: 193 kg/cm2
Thickness for straight portion: 195/165 mmOverall length of drum : 22070 mmOutside dia. Of Drum : 2138 mmInternal dia. Of Drum :1778 mmElevation of drum centre above ground level: 71.583 meterNo. of distribution headers : 6No. of cyclonic separator :92No. of secondary dryers : 92No. of final dryers : 124Maximum permissible DT between any two parts of Drum : 50 0C
Connection to Boiler Drum Main connection• Feed lines • Down comers • Up risers• Super heater supply tubes
Auxiliary connection• Blow down line• Chemical dosing line• Instrumentation tapping• Air vents• Safety valves• Nitrogen filling line• High and low level trips
Drum InternalsFeed headerAnti vortex spiderSteam separatorSteam dryers or scrubbersC.B.D. line E.B.D. line chemical dosing line
Water Walled Furnace Requirement Advantages In furnace not only combustion but also heat transfer is taking place
simultaneously. The maintenance work involved in repairing the firebricks (which is
otherwise necessary) is completely eliminated. Due to heat transfer in the furnace, temperature of the flue gas leaving
the furnace is reduced to the acceptable level of the superheating surfaces.
Higher heat loading in the furnace is possible, as heat is being simultaneously removed by heat transfer, and hence economy in surfacing.
Providing a Gas tight seal to the combustion chamber to prevent air infiltration.
Water Wall Furnace Constuction
Expansion and Sealing
330 mm
36mm
29mm
53mm
174mm
58mm
Buckstay and Furnace Guides
Superheaters Requirement?
By increasing the temperature of the steam, the useful energy that can be recovered economically increases thus the efficiency of the cycle also as can be seen in Fig.3.40.
Superheating of steam eliminates the condensation of steam during transporting of steam in pipelines and inside the early stages of turbines which is harmful to the turbine blades and pipe lines.
Limits the work done by turbine stages to avoid excessive erosion of blades
Types of superheater radiant superheater convective superheater
Relationship in SH DesignThe steam temperature desiredThe super heater surface area requiredThe rate of steam flow through the tubes (mass
flow)The material best suited for the super heater
tubesThe gas temperature zones where the surfaces
are to be locatedThe arrangement of surfaces to meet the
characteristics of the fuel to be used with specific reference to the spacing of tubes
Material for SHASME CODE NOMINAL
COMPOSITION
TEMP.LIMIT 0C
SA 213 CARBON STEEL 450
SA 213 T1 C-1/2 Mo. 470
SA 213 T11 11/4 Cr. –1/2 Mo. 550
SA 213 T22 21/4 Cr.-1 Mo. 580
SA 213 T9 9 Cr.-1 Mo. 635
SA 213 TP 304 H 18 Cr.-8 Ni. 705
SA 213 TP 347 H 18 Cr.-10 Ni. 705
SA 213 TP 316 H 16 Cr.-12 Ni.-2 Mo. 705
Description Tube Size Material
Radiant Roof Tubes i. Ø 63.5 X 6.3 ii. Ø 57 X 5.6
SA 213, T11SA 213, T11
Steam Cooled Side wall tubes
i. Ø 63.5 X 6.3ii. Ø 51 X 5iii. Ø 76.1 X 10
SA 210, Gr CSA 210, Gr CSA 210, Gr C
Steam Cooled front wall tubes
i. Ø 51 X 5ii. Ø 63.5 X 6.3iii. Ø 44.5 X 7.1
SA 210, Gr CSA 210, Gr CSA 210, Gr C
Front Wall Hanger Tubes Ø 51 X 5.0 SA 210, Gr C
Rear Roof Tubes i. Ø 51 X 5ii. Ø 44.5 X 7.1
SA 210, Gr CSA 210, Gr C
Eco and LTSH Support tubes
Ø 47.63 X 8.6 SA 210, Gr C
Description Tube Size Material
Steam Cooled Side Wall tubes Ø 51 X 5 SA 210, Gr C
Bifurcate Tubes (Bottom Header) Ø 51 X 5 SA 210, Gr C
LTSH Horizontal Tubes i. Ø 51 X 5ii. Ø 51 X 5.6
SA 210, Gr C SA 210, Gr C
Pendent Coil Tubes i. Ø 51 X 5ii. Ø 51 X 5.6
SA 213, T11SA 213, T11
Divisional Panel inlet loose tubes i. Ø 51 X 6ii. Ø 44.5 X 4.5
SA 210, Gr C SA 210, Gr C
Divisional Panel Outlet loose tubes i. Ø 51 X 6 SA 213, T11
Steam Cooled Spacer i. Ø 63.5 X 8ii. Ø 51 X 5.6iii. Ø 63.5 X 6.5iv. Ø63.5 X 7.1v. Ø 63.5 X 7.1vi. Ø 51 X 5.0vii. Ø 51 X 5.0
SA 213, T11SA 213, TP347HSA 213, TP347H SA 213, T11 SA 210, Gr C SA 213, T11 SA 210, Gr C
Reheater
Requirement?
Description Tube Size Material
Reheater Wall tubes Ø 60.3 X 4 SA 313, T11
Cross over tubes Ø 54 X 3.6 SA 213, T11
Sr
.
N
o.
Type
Heating Surface
Area in m2
1 Radiant roof, steam cooled wall LTSH
Horizontal and pendent.
9620
2 Super Heater Divisional Panel 1361
3 Final Super heater Platen 1458
4 Reheater radiant wall front and side,
front platen, rear platen.
5075
Total Heating Surface 17514 M2
Sr.
No.
Parameters Rating
1 Super heater system flow 1681 TPH2 Reheater System Flow 1430.64 TPH3 Pressure at super heater outlet 179 Kg/cm2
4 Temperature at super heater outlet 540 oC5 Pressure at reheater inlet 44.88 Kg/cm2 (g)6 Temperature at reheater inlet 342.7 oC7 Pressure at reheater outlet 42.68 Kg/cm2 (g)8 Temperature of reheater outlet 540 oC 9 Feed Water temperature 255 oC10 Ambient air temperature 28 oC11 Combustion air temperature secondary 335 oC12 Fuel Quantity 330 TPH13 Air Quantity (Total Combustion air) 2030 TPH14 Temperature of Gas at boiler exit 142 oC15 Total Heat output of the system 1076 Kcal/Hr
A B
PLSH RH FSH
LTSH
ECO
APH
ESP
MAX-134 ºC
1135-1020 ºC
1020-793 ºC
758-726 ºC 720 ºC
461 ºC
355 ºC
147 ºC 137 ºC
DRUM
1300-1400
BOILER AIR & FLUE GAS TEMPERATURES
1100-1250
SA-318 ºC PA-313 ºC
143 ºC
A B
PLSH RH FSH
LTSH
ECO
APH
ESP
DRUM
BOILER WATER & STEAM TEMPERATURE
243-286 ºC
286-349 ºC
349-426 ºC426-520 ºC
520-540 ºC
344-540
1300-1400
BOTTOM RNG HDR WW PANELS & 1ST PASS W.W.
1ST PASS W.W O/L HDRS ROOF I/L HEADER
2ND PASS UPPER C-HDR 2nd PASS LOWER C-HDRS
LTSH I/L HEADER LTSH & O/L HEADER
D.P.I/L HEADER D.P.O/L HEADER
FINAL S.H. R.H.HEADER
2ND PASS ROOF O/L HDR(REAR ECONOMISER
M.S
H.R.HC.R.H
FROM F.R.S
500MW BOILER
BCW Pump
Thank You