final english executive summary
TRANSCRIPT
Summary of the Draft EIA Report M/s Saravana Alloy Steels Pvt. Ltd
EHS Consultants, Bangalore.
0
SUMMARY OF THE DRAFT ENVIRONMENTAL IMPACT ASSESSMENT
REPORT
Prepared for
PROPOSED STEEL MELTING PLANT (72,000 TPA) & ROLLING MILL PLANT (90,000 TPA)
(M/s. Saravana Alloys Steels Pvt.Ltd)
at Sy No. 1/3, 1/5, 2/1, 2/2, 2/3, 2/4A, 2/4B, 2/5, 2/6,3P, 6/1,6/2, 61, 62 & 96/1, Gangadharanapalya Village, Kasaba Hobli, Nelamangala Taluk,
Bangalore Rural Dist, Bangalore.
Prepared by ENVIRONMENTAL HEALTH & SAFETY CONSULTANTS, No.1008, Manjunatha Complex, 8th ‘B’ Main Road, 3rd Stage, 3rd Block, Basaveshwaranagar, Bangalore - 560 079
TeleFax: 080 2323 8733.
Summary of the Draft EIA Report M/s Saravana Alloy Steels Pvt. Ltd
EHS Consultants, Bangalore. 1
CHAPTER 1.0
PROJECT DESCRIPTION
1.1 Introduction
M/s Saravana Alloy Steels Pvt. Ltd Company through their Directors having high
experience in the Steel Industry promotes the proposed project. The proposed project
envisages Steel Melting Plant (72,000 TPA) & Rolling Mill Plant (90,000 TPA) and
located at Sy No. 1/3, 1/5, 2/1, 2/2, 2/3, 2/4A, 2/4B, 2/5, 2/6,3P, 6/1,6/2 61, 62 & 96/1,
Gangadharanapalya Village, Kasaba Hobli, Nelamangala Taluk, Bangalore Rural Dist,
Bangalore.
1.2 Raw Material Requirements and Products 1. Steel Melting Shop:
Raw Materials:
• Sponge Iron : 48000 TPA • M.S.Scrap : 32000 TPA • Ferro Alloys : 1000 TPA • Aluminium : 30 TPA
Products : M.S.Billets: 72,000 TPA
2. Rolling Mill Plant:
Raw Materials : M.S.Billets : 95,000 TPA
Products:
• T.M.T.Bars : 80,000 TPA
• Plain Rounds : 10,000 TPA
Summary of the Draft EIA Report M/s Saravana Alloy Steels Pvt. Ltd
EHS Consultants, Bangalore. 2
CHAPTER 2.0
DESCRIPTION OF THE ENVIRONMENT
The proposed project site is at present barren land. The plant location is in the out skirts
of Nelamangala Town in Bangalore Rural District. The proposed project envisages the
construction of Steel Melting and Rolling Mill Plant. Production and manufacturing
processes include Billets from Steel Melting Plant and Rolled TMT Bars from Rolling
Mill Plant. The project is proposed to be developed on a total plot area of 44.03 acres
(17.81 ha).
The promoters after conducting all India surveys, proposed to put up the unit near
Nelamangala Town. The location is very well connected with Road, Rail and air ways.
Moreover, the unit will add to the Economy of the state and provide employment to the
unemployed Technical, Commercial and hard working workers of Karnataka and
adjoining areas.
Table 2.1: Salient features of the proposed project and its Environmental Settings
within 10 Kms radius
Sl.No Items Particulars
1 Project Proposed Steel Melting Plant (72,000 TPA) & Rolling
Mill Plant (90,000 TPA).
2 Investment Rs.40.00 crores including working capital.
3 Project location Sy No. 1/3, 1/5, 2/1, 2/2, 2/3, 2/4A, 2/4B, 2/5, 2/6,3P,
6/1,6/2 61, 62 & 96/1, Gangadharanapalya Village,
Kasaba Hobli, Nelamangala Taluk, Bangalore Rural
Dist.
4 Total project area 44.03 acres (17.81 Ha)
5 Water demand About 10 KLD from Borewells and 15 KLD from
municipal authority.
6 Power supply 15,000KVA from BESCOM
Summary of the Draft EIA Report M/s Saravana Alloy Steels Pvt. Ltd
EHS Consultants, Bangalore. 3
7 Nearest Highway NH 4 – 1.0 km
8 Nearest River Arkavathy River – 8.4 Kms
9 Nearest Railway line 4.50 Kms
10 Nearest Heritage sites None within 10 Kms
11 Nearest National park/ Wildlife sanctuaries/ Biosphere reserves
None
12 Nearest State Forest Bommanahalli State Forest – 3.0 Kms
13 Nearest Tank Hesarghatta Tank – 7.6 Kms
14 Latitude 13007’05’’ N
15 Longitude 77022’51’’ E
Summary of the Draft EIA Report M/s Saravana Alloy Steels Pvt. Ltd
EHS Consultants, Bangalore. 4
CHAPTER 3.0
ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES
Table 3.1: Construction Phase - "Site Clearing"
Environmental
Impacts
Mitigation Remarks
Soil erosion • Extent of vegetation removal shall
be minimized to prevent extent of
soil erosion.
• Vegetative cover shall be re-
projected /rehabilitated at the earliest
practicable time to minimize
duration & extent of soil erosion.
Implementation responsibility:
• Contractor
• Project Consultants
• M/s Saravana Alloy Steels
Pvt. Ltd.
Noise generation • Selection of equipment with less
noise generation to be used.
• The earth moving equipment shall
be periodically checked and
maintained for noise levels. Since
the site is more or less even use of
these earth-moving equipments may
not be necessary.
• The workers shall be provided with
adequate PPE such as earplugs to
reduce impact of high noise levels.
Implementation responsibility:
• Contractor
• Project Consultants
• M/s Saravana Alloy Steels
Pvt. Ltd.
Dust generation • The site cleared shall be periodically
watered to reduce emission of dust
particles.
• The workers shall be provided with
PPE such as nose masks and goggles
to reduce impact on health.
Implementation responsibility:
• Contractor
• Project Consultants
• M/s Saravana Alloy Steels
Pvt. Ltd.
Summary of the Draft EIA Report M/s Saravana Alloy Steels Pvt. Ltd
EHS Consultants, Bangalore. 5
Table 3.2: Construction Phase Impacts
"Transportation of Construction Materials”
Environmental
Impacts Mitigation Remarks
Noise
generation
• Periodic maintenance of
vehicles is required
Implementation responsibility:
• Contractor
• Project Consultants
• M/s Saravana Alloy
Steels Pvt. Ltd
Dust generation • Construction materials shall be
covered with tarpaulin sheets
to prevent the material from
being air borne.
• The vehicle speed shall be
regulated.
• The workers transporting
materials shall be provided
with PPE such as nose asks to
reduce impact of air borne dust
on their health
Implementation responsibility:
• Contractor
• Project Consultants
• M/s Saravana Alloy
Steels Pvt. Ltd
Vehicular
emissions
• Periodic emission check for
vehicles is required.
• Clean fuel shall be used for
vehicles.
Implementation responsibility:
• Contractor
• Project Consultants
• M/s Saravana Alloy
Steels Pvt. Ltd
Summary of the Draft EIA Report M/s Saravana Alloy Steels Pvt. Ltd
EHS Consultants, Bangalore. 6
Table 3.3: Construction Phase Impacts "Construction Activities”
Environmental
Impacts Mitigation Remarks
Noise
generation
• Personnel Protective Equipment
(PPE) such as ear plugs and
helmets shall be provided for
construction workers.
• The working hours shall be
imposed on construction
workers.
Implementation
responsibility:
• Contractor
• Project Consultants
• M/s Saravana Alloy
Steels Pvt. Ltd.
Dust generation • PPE in the form of nose masks
shall be provided for
construction workers.
• Use of water sprays to prevent
the dust Contractor from being
air borne.
Implementation
responsibility:
• Contractor
• Project Consultants
• M/s Saravana Alloy
Steels Pvt. Ltd
Air Emissions
from
construction
machinery
• Periodic check and regular
maintenance of construction
machinery for emissions
• Clean fuel shall be used in
equipments
Implementation
responsibility:
• Contractor
• Project Consultants
• M/s Saravana Alloy
Steels Pvt. Ltd.
Summary of the Draft EIA Report M/s Saravana Alloy Steels Pvt. Ltd
EHS Consultants, Bangalore.
7
Table 3.4: Environmental Impacts - Operational Phase
Impact characteristics Activity Environmental
Attributes Cause Nature Duration Reversibility Significance
Afforestation / Green belt development
Ecology Planting of trees Direct Negative
Long -Term
Reversible High positive impact
Air Quality (SPM, RSPM, SO2, NOx, CO, HC)
Vehicle operation and fuel combustion
Direct Negative
Long -Term
Reversible Low, asphalted roads and regular checks of exhaust emissions are performed.
Vehicular traffic for conveyance of people
Noise levels Noise generation from vehicles
Direct Negative
Short-term
Reversible Low, with periodical maintenance of vehicles
Employment generation
Direct and indirect employment
Direct Negative
Long -Term
Irreversible High, new opportunities of steady income for many families in the surrounding nearby areas
Socio- economic
Quality of life In-flow of funds in the region/nation
Direct Negative
Long -Term
Irreversible High, the project will generate employment
Solid waste disposal Land and soil Generation of solid wastes
Direct Negative
Short-term
Reversible Low, proper collection and scientific disposal
Sewage discharge Water quality Generation of Sewage Direct Negative
Short-term
Reversible Low, as Septic Tank and Soak Pit will be provided.
Air Quality Exhaust emissions Direct Negative
Short-term
Reversible Medium (DG set is only a standby). Low if emission checks are performed regularly
DG set, operation
Noise levels Noise generation Direct Negative
Short-term
Reversible Low as the noise protection measures (enclosures, PPE etc.)
Summary of the Draft EIA Report M/s Saravana Alloy Steels Pvt. Ltd
EHS Consultants, Bangalore.
8
Table 3.5: Monitoring Schedule for Environmental Parameters for mitigation of
anticipated Environmental Impacts
Sl. No. Particulars Monitoring
frequency Duration of monitoring
Important parameters for
monitoring I Air Quality 1 Ambient Air Quality
Monitoring within premises
Once in a month
Grab, 24 hrly sample
SPM, RSPM, SO2, NOx.
2 Stack/Chimney Monitoring
Once in a month
Grab Temperature, Velocity, SO2, SPM, NOx, HC, CO
II Water Quality
1 Ground Water at two locations (up-gradient & down-gradient) of solid waste dumping area.
Once in a month
Grab As per KSPCB requirements
III Soil Quality 1 Near Solid Waste dump Pre monsoon
and post monsoon
Grab Colour, Textural Class, pH, C, Infiltration rate, Moisture retention capacity, Organic matter, Na, K,P,Pb,Cu,Zn,Cd,Fe
IV Ecological preservation and up gradation
Seasonal Visual observations
Survival rate
V Noise Quality • Main
Gate/Boundary • Melting Plant • D.G Set Room • Rolling Mill Plant • Compressor • Loading and
Unloading • Others as noticed
Once in a Month
24Hrs Monitoring
Noise levels in dB(A)
Summary of the Draft EIA Report M/s Saravana Alloy Steels Pvt. Ltd
EHS Consultants, Bangalore. 9
CHAPTER - 4.0
ENVIRONMENTAL MONITORING PROGRAMME
4.1 Environmental Monitoring Plan:
Regular monitoring in a systematic and standardized manner helps in assessment of
current environment and provides information on operational performance of installed
pollution control facilities.
Following are the Environmental aspects will be strictly considered in conducting
routine Environmental Monitoring:
• Monitoring of Stack emissions for Temperature, Velocity, SPM, SO2, NOx and
CO. This will be carried out once in a month.
• Monitoring of Ambient Air Quality at plant boundary for fugitive emissions for
SPM, RSPM, SO2 and NOX. This will be carried out once in a month.
• Work Zone Air Quality Monitoring will be carried out in areas like Furnace
areas, Melting Plant, Rolling Mill Plant, Loading and Unloading of materials etc.,
This will be carried out once in a month.
• Monitoring of ground water quality of surrounding area of dump yard for pH,
conductivity, total solids, suspended solids and oil and grease. This will carried
out once before monsoon and after monsoon.
• Recirculation water after Cooling will be analyzed for pH, TSS, TDS, COD, Iron
and Oil and Grease.
• Ambient Noise Level Monitoring near the Steel Melting Plant, Rolling Mill
Plant, D.G set areas, Plant boundary, main gate, loading and unloading of raw
materials, Near Machinery and equipment areas etc as noticed. This will be
carried out once in a month.
• Monitoring of solid wastes quantity and utilization potential (Slag, accretions,
flue dust etc.,)
Summary of the Draft EIA Report M/s Saravana Alloy Steels Pvt. Ltd
EHS Consultants, Bangalore. 10
CHAPTER – 5
ADDITIONAL STUDIES
Following are the additional studies taken up with respect to the proposed project:
• Land use pattern of the proposed project surrounding area determined through
using Satellite Imagery for a radius of 10Kms which was procured from
the Karnataka State Remote Sensing and Technology Utilization Centre,
Bangalore.
• Air Quality Modelling studies.
CHAPTER – 6
PROJECT BENEFITS
Following are the benefits from the proposed project:
• The Proposed project is being developed to meet the raw material requirement
for various related Industries and also for New Infrastructure and Construction
Projects in the surrounding areas/places.
• The proposed project would generate an optimum employment for the
local population, direct employment for about 80 people and indirect
employment of about 160 people together constituting 240 people.
• All the construction workers will be employed from the nearby local
villages around 5 kms.
Summary of the Draft EIA Report M/s Saravana Alloy Steels Pvt. Ltd
EHS Consultants, Bangalore. 11
CHAPTER – 7.0
ENVIRONMENTAL MANAGEMENT PLAN
7.1 Environmental Management during Construction Stage
i) During excavation and transportation on roads at the plant site, there is
a scope for local fugitive dust emissions. Frequent water sprinkling in
the vicinity of the construction activity should be done.
ii) There is a likelihood of fugitive dust from the construction activity and
material handling from the truck movement in the premises of the
proposed plant. The industry shall take up tree plantation program
around the plant site.
iii) It shall be ensured those construction vehicles are properly maintained.
The vehicle maintenance area shall be located in such a manner, so as
to prevent contamination water sources by accidental spillage of oil.
iv) Proper care shall be taken for storage of LSD etc. Site shall be
identified for the storage of such flammable liquids, away from the
main plant. The storage shall be as per institutional safety standards.
v) The construction workers shall be provided with sufficient and suitable
toilet facilities to allow proper standards of hygiene.
vi) Onsite workers using high noise equipment shall adopt noise
protection devices. Noise prone activities will be restricted to daytime
hours only.
vii) Hazardous material will be stored in proper areas.
viii) After completion of construction activities the rubbish shall be cleared
and disposed to nearby authorized sites.
ix) Safety devices/equipments will be provided for construction workers
depending upon the type of activity.
Summary of the Draft EIA Report M/s Saravana Alloy Steels Pvt. Ltd
EHS Consultants, Bangalore. 12
7.2 Environmental Management during Operation Stage
7.2.1 Air Environment:
The mitigation measures needs to be adopted during the operation stage to control the
negative impacts on air environment of the surrounding of the project area given below:
• Dense green belt is planted around the dust generation points at surface.
• Trees are planted on both sides of the roads used for transportation in order to
arrest dust.
• Afforestation around the unit to act as barrier
• Water sprinkling along the haul road
• Proper maintenance air pollution control equipment
• Regular maintenance of vehicles and machinery’s in order to control emissions
• Cabins for shovel and dumpers and dust masks to workmen.
• A good house keeping and proper maintenance will be practiced in the industry,
which helps in controlling pollution.
In addition to the above, the following recommendations are made:
• The air pollution control equipment like Bagfilters and other dedusting
equipments shall be operated continuously and provision shall be made for
backup power supply for these.
• Monitoring of stack emissions and emissions from the dedusting equipments shall
be carried out regularly to ascertain the performance of the air pollution control
equipments.
• Water spraying shall be adopted at loading and unloading points, storage yards
and near solid waste dumping yards which will reduce fugitive emissions due to
movement of truck.
• All the internal roads shall be asphalted to reduce the fugitive dust due to truck
movement.
• Green belt cover shall be provided. For this, the project has proposed to have
green belt cover to an extent of 28 % of the total site area.
Summary of the Draft EIA Report M/s Saravana Alloy Steels Pvt. Ltd
EHS Consultants, Bangalore. 13
7.2.2 Water Environment
Water requirement for proposed project will be met by Borewells of about 10 KLD and
15 KLD from Municipal authorities. The water will be used majorly for cooling
purposes. There is no any effluent water in this process. The quantity of canteen
wastewater generated of about 9.72 m3/day will be treated in the Septic Tank and
Soakpit.
Apart from above, following additional measures will minimize operational impacts:
• There is no any effluent water in this process
• Use of high pressure hoses for area cleaning
• Oily waste from the facility will be separately collected and will be disposed off
scientifically according to the KSPCB norms.
• No wastewater will be discharged to any ground water or to the surface water
body.
• Storm water drains shall be provided to avoid flooding in the proposed project site
area and provision will be made for runoff get diverted to recharge pits with pre
oil and grease trap there by increasing the groundwater table.
7.2.3 Noise Environment:
• Personnel working near noisy areas shall be provided with adequate personal
protective equipment such as earplugs and earmuffs, use of which will be strictly
enforced.
• Sophisticated and low noise generating equipments will be selected.
• Proper mounting of equipments and providing noise insulating enclosures or
paddling where practicable.
• The equipments will be maintained at all times to ensure permissible noise levels.
• Appropriate advanced silencers, acoustic barriers; vibration-reducing pads will be
provided for all noise generating equipments.
• The sources of continuous noise generating equipment such as compressors,
pumps, motors etc will be designed to have noise level not exceeding 85-
90dB(A).
Summary of the Draft EIA Report M/s Saravana Alloy Steels Pvt. Ltd
EHS Consultants, Bangalore. 14
• It would be ensured that there would not be any operator near the noise generating
equipments on continuous basis.
• Boundary walls and dense green belt will be erected to act as acoustic barriers.
• Adequate and appropriate type of green belt would be developed in and around
the proposed project site for noise mitigation in the area.
7.2.4 Solid Waste & Hazardous waste generation
The proposed Solid waste and Hazardous waste generation from the plant is given below:
I Slag from Induction Furnace - 45 TPD
II Canteen Waste - 40 Kgs/day
III Municipal Solid Waste - 60 Kgs/day
IV Hazardous waste - Used Oil from D.G sets – 250 Ltrs/Annum
- Scrubbed Sludge 1 TPA
• Slag from Induction Furnace will be disposed within the site itself.
• Canteen and MSW will be disposed to Nelamangala municipal authorities.
• Hazardous waste (Used Oil) generated from D.G Sets will be collected and stored
in barrels or drums and later handed over to Karnataka State Pollution Control
Board (KSPCB) authorized reprocessors.
• Scrubbed sludge generated from the industry will be collected and stored for later
disposal in scientific manner as per the norms of the Karnataka State Pollution
Control Board.
• Any other solid waste generated from the facility will be disposed off by using
proper disposal mechanism in a scientific manner.
7.2.5 Greenbelt Development
• An extent of about 34% of total site area in the plant premises is proposed for
greenbelt development.
Summary of the Draft EIA Report M/s Saravana Alloy Steels Pvt. Ltd
EHS Consultants, Bangalore. 15
7.2.6 Ecological Aspects
The following measures are proposed to have minimum impact on ecology of the
project area:
• Zero discharge of wastewater from the proposed project in the operation
stage.
• Continuing greening efforts in and around the project site.
• Conservation of existing vegetation and afforestation covering larger areas
near and around existing project area.
• The dump yard is treated by a gentle gradient and pitching will be done all
around the earthen heap will be formed into terraces and it will be
stabilized by planting grass sets and also by sowing grass seeds.
7.2.7 Aesthetics Aspects
• The entire dump yard area will be planted with local tree species of
aesthetic value, fodder value, fruit bearing, and birds attracting tree
species.
7.2.8 Socio Economic Aspects
• Local people of Nelamangala Taluk and nearby villages surrounding
the site will be employed to the maximum extent.
7.3 Post Project Environmental Monitoring
M/s Saravana Alloy Steels Pvt. Ltd. will implement various productivity management
programs in the plant to improve the work environment, effective house keeping and
environment quality. All the necessary steps shall be taken in the plant to meet standards
prescribed by the Karnataka State Pollution Control Board and Central Pollution Control
Board and Department of Ecology and Environment, Government of Karnataka.