executive summary english - mppcbmppcb.nic.in/pdf/exe_summ/exe_summ_trimulaspong_eng.pdf ·...
TRANSCRIPT
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 0
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 1
INTRODUCTION
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 2
1.1 INTRODUCTION
TRIMULA INDUSTRIES LIMITED is the flagship company of Trimula Group of Companies,
having registered office at C-27/95-E Jagatganj Varanasi & Works at Village & Post, Godwali,
Tehsil-Devassar, Distt-Singrauli- Madhya Pradesh is engaged in Coal trading, Manufacturing &
Coal handling business for more than two decades. The Directors in addition to the above
mentioned company are also promoters of a 100 TPD sponge iron plant being operated under
the name & style of M/s Trimula Sponge Iron Private Limited. Trimula Group which has already
diversified into steel sector is now embarking on the second phase of the expansion in this core
sector of Steel and is proposing to setup the following facilities in phases mentioned below:
In the first phase the company has already set up Sponge Iron Plant with production
capacity of 220,000 TPA and 38.5 MW Power Plant along with 84 TPH Fluidized Bed
Combustion shall be made operational.
In the second phase another Sponge Iron Plant with 110,000 TPA, of production shall be
made operational.
In the third and the final phase, the sponge iron and steel plant of 1,00,000 TPA Production
Capacity and 60 MW Power Plant along with 16 MW WHRB & 44 MW Fluidized Bed
Combustion. Additional 2x500 MT Rolling Mill with Auxiliary will be included. Further in
order to reduce dependence on outside source for coal, a Coal Washery to beneficiate F-
Grade coal from Northern Coal Fields would also be set up. The coal middling generated
during beneficiation would be used as a fuel in the Fluidized Bed Boiler to produce power.
The phase–I of the project has been commissioned, Phase – II will be immediately
implemented and PHASE-III respectively will be taken up after completion of Phase–II. Total
cost of the project is Rs. 410.0 Crores.
Trimula Industries Limited is a registered Company under the Indian Companies Act, 1956.
The Company was incorporated with the main objective of setting up Sponge Iron, Steel &
Expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant in India.
The company proposed to set up facilities in the State of Madhya Pradesh for production of
above mentioned Integrated Steel Complex in order to cater to the requirements of the region
& also to provide employment to the locals of the region.
TRIMULA INDUSTRIES LTD. proposes for the expansion of Sponge Iron plant (1X350) into
Integrated Steel Melting Plant. In the Phase-III TRIMULA INDUSTRIES LTD propose to
manufacture 1,10,000 TPA Sponge Iron & 60MW Power Generation. Sponge Iron will be
manufactured from Iron Ore (3,52,000 TPA) and coal (3,08,000 TPA) in 350 Kiln. The sponge
produced will be the raw material for SMS plant and waste gases so produced will be utilized to
generate power of 8 MW through WHRB. Sponge Iron (3,30,000 TPA), Scrap (1,04,039 TPA),
Ferro Alloys (1,380 TPA) will be used as raw material in Steel Melting Shop to produce MS
billets. Billets will be manufactured by melting in induction furnace and casting in continuous
casting machine. 16 MW power will be produced from Waste Heat Recovery Boiler (WHRB)
and balance 44 MW will be produced from Atmospheric Fluidized Bed Combustion (AFBC)
boiler. This AFBC boiler utilizes coal (2,85,805 TPA) and Char (5,500 TPA). The char is by
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 3
product of DRI. The details of Production facilities, utilities, raw material requirement, and
power consumption norms are described below:
FOLLOWINGS ARE THE PROPOSED PRODUCTION CAPACITIES:
Details Annual Production (TPA)
Sponge Iron 1,10,000 MS billets 3,28,500
TMT/Structure 3,00,000
FOLLOWING UNITS WILL BE INSTALLED:
Unit Capacity DRI with Auxiliary 1X350 TPD SMS with Auxiliary 6X15 MT
ROLLING MILL with Auxiliary 2X500 MT 60 MW Power Plant
WHRB 2 Nos. 16 MW AFBC 44 MW
RAW MATERIALS:
Sponge Iron will be manufactured from Iron Ore (3,52,000 TPA) and coal (3,08,000 TPA) in
350 Kiln. The sponge produced will be the raw material for SMS plant and waste gases so
produced will be utilized to generate power of 8 MW through WHRB. Sponge Iron (3,30,000
TPA), Scrap (1,04,039 TPA), Ferro Alloys (1,380 TPA) will be used as raw material in Steel
Melting Shop to produce MS billets. Billets will be manufactured by melting in induction furnace
and casting in continuous casting machine. 16 MW power will be produced from Waste Heat
Recovery Boiler (WHRB) and balance 44 MW will be produced from Atmospheric Fluidized
Bed Combustion (AFBC) boiler. This AFBC boiler utilizes coal (2,85,805 TPA) and Char (5,500
TPA).
1.2 SITE AND SURROUNDINGS
The plant site is located in Godwali, Singrauli district of Madhya Pradesh, having latitude and
longitude of plant center 22°12' 12" N and 22° 12' 28” N respectively. An approach road
already constructed during Stage-I of this Station. Nearest railway station is Singrauli located at
a distance of about 18 km. The site is approachable about 02 km. from Godwali. The nearest
airport is Varanasi located at a distance of approximately 220 km from the project site
The Environmental Impact Assessment (EIA) study is awarded to M/s In Situ Enviro Care,
Bhopal (M.P.) The baseline data monitoring was started from January 2011 to March 2011 by
Rewa Pollution Control Board. However, EIA report is prepared based on that report.
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 4
1.3 LAND REQUIREMENT
The project of Expansion of 1X350 TPD Sponge Iron Plant into Integrated Steel Plant at
Godwali, Singrauli District, Madhya Pradesh of the project will be accommodated in 61.61
hectares that is already available for Stage-I and Stage-II. However 1.07 ha out of 61.61 Ha is
kept reserved for ash pond. There is no forest land present in the proposed ash disposal area.
Particulars Area (ha) Existing Plant (Sponge Iron) 10.03 38.5 MW Proposed Captive Power Plant 12.30 60 MW Proposed Captive Power Plant
20.9
Steel Melting Shop Rolling Mill 1X350 TPD Kiln
Plant Area 15.5
Storage (raw material) 1.18 Storage (Solid waste) 1.21
Storage (Water) 0.91 Storage (Fuel) 0.20
Road 0.50 Ash Pond 1.0
Other (Truck parking, Office & other misc) 0.40 Green Belt 18.11 Total 61.61
1.4 WATER AVAILABILITY AND REQUIREMENT
The makeup water for the plant is proposed to be drawn from hot water channel of Stage I & II.
However, water availability of 1835 m3/hr has been obtained from Bijul River.
Normal make up water requirement for the proposed expansion project would be about 1835
m3/hr with ash water re-circulation system in operation. However, whenever ash water system
needs to be operated in once thru mode, water drawal shall be of 75 cu meters per day.
1.5 FUEL AVAILABILITY & REQUIREMENT
Coal requirement for Thermal Power Plant is estimated at 2,85,809 TPA, considering average
GCV of 3300 - 3700 kcal/kg and 90 % PLF, Ministry of Coal, Government of India vide letter
dated 09.03.2010 recommended to Coal India Limited for issue of letter of assurance for coal
commitment for Expansion of STPP, Singrauli. Coal is proposed to be met from Gorbi mines of
Northern Coal Fields through Road network. The coal quality considered in EIA is as follows:
Ash 35 % GCV (kcal/kq) 3300 – 3700 Sulphur(Max) 0.4 % - 0.5 %
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 5
1.6 TRANSMISSION SYSTEM
The power generated will be evacuated through a transmission system to be evolved and
implemented by Power Grid Corporation of India Limited
1.7 PROJECT DESCRIPTION
TRIMULA INDUSTRIES Ltd proposes Expansion of Sponge Iron Plant (1X350 TPD) into
Integrated Steel Plant Project, which is intended for faster implementation of power and other
infrastructure projects in the country. At present, land of about 61.61 ha is in the possession of
TRIMULA INDUSTRIES LTD. The estimated cost of the 2nd phase of project is 410 Crores.
TABLE-1
SALIENT FEATURES OF PROPOSED EXPANSION OF POWER PLANT
S. NO. PARTICULARS DETAILS 1 Project Name Expansion of Sponge Iron Plant (1X350 TPD) into
integrated Steel plant at Village Godwali & Bastali Biran, Tehsil Devasar & Chitarangi, District Singrauli, Madhya Pradesh by M/s Trimula Industries Limited.
2. Location Village Tehsil District State
Godwali Devasar & Chitarangi Singrauli Madhya Pradesh
3 Nearest railway station/airport alongwith distance in kms.
Railway Station: Singrauli – 12 km
Airport : Varanasi – 220km
4 Nearest town, city, district
Headquarters alongwith
distance in kms.
Nearest Town/City: Singrauli – 12 km
District Headquarter: Singrauli – 12 km
5 Village panchayat, Zilla
Parishad, Municipal
Corporation, Local body
(complete postal addresses with
telephone nos. to be given).
Village Panchayat :
The Sarpanch, Godwali Village; Po- Godwali, Tehsil-Devsar, Thana – Barganwa, District – Singrauli, Madhya Pradesh – 486 892 Tele No. 09893674704
Zilla Parishad/Panchayat:
The CEO/Chairman, Zilla Panchayat, Singrauli, Madhya Pradesh – 486886 Tele No. (07805) 234650
6 Total area of the plant and land use
61.61 acres
7 Power Evacuation Existing system will be utilized 8 Fuel Coal and Char A Source of Fuel Northern Coal Fields B Fuel Transportation By road C Fuel Requirement (Coal) for
60 MW Coal- 2,85,809 TPA Char- 5,500 TPA
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 6
D Average calorific value GCV around 1800 to 2600 Kcal/kq E Ash content 35% G Sulphur content 0.8% (Max) 9 Ash Generation Fly ash
Bottom ash SMS slag 55804 TPA, 13950 TPA, 405 TPA
10 Water Requirement 1835 m3/hr B Source of water Bijul river
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 7
DESCRIPTION OF THE
ENVIRONMENT
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 8
2.0 DESCRIPTION OF THE ENVIRONMENT The topography of the land in the plant site is plain with hillocks and no water streams
present in the site area. The environmental setting of the proposed plant site is given in
Table-2. The study area map of 15 km radius is also given in Figure-2.1
TABLE-2
ENVIRONMENTAL SETTING OF THE SITE
S. NO. PARTICULARS DETAILS 1 Name & Location Trimula Industries Limited A Village Godwali B Tehsil Devssar C District Singrauli D State Madhya Pradesh 2 Elevation above MSL 380 m 3 Seismicity Zone - II as per IS 1893 (Part - I), 2002 4 Present land use Industrial Use 5 Climate Condition (IMD - Sidhi) Annual Max. Temperature – 42°C
Annual Min. Temperature - 7.5°C Average Annual Rainfall - 1234.6 mm Predominant annual wind direction: West)
6 Study period: (January to March 2011
7 Nearest Highway NH -75E (01 km, N) 8 Nearest Railway Station Singrauli (18 km, W) 9 Nearest Airport Varanasi (220 km)
10 Nearest Village Godwali & Bastali Biran 11 Nearest Town Singrauli (18 Km.) 12 Protected areas as per Wildlife
Protection Act, 1972 (Elephant Corridors, Tiger Reserves, Sanctuaries, National parks, Conservation reserves, Community reserves)
No protected areas as per Wildlife Protection Act, 1972 within the 15 km radius of study area.
13 Reserved / Protected forests Mohanban RF Jiawan RF Parari PF Teldah PF Muher RF Muher RF Chokra PF Mehrauli PF Gorvi PF Vihara PF Orgari PF Pokhara PF Parihasi PF Majhigawan North PF Pachwar PF Lohra PF Gidher PF Uska PF
7.8 Km/SW 12.3 Km/NNW 2.5 Km/SE 1.4 Km/SW 9 Km/E 4.1 Km/S 6.6 Km/S 9.4 Km/SE 4.7 Km/E 13.5 Km/SSW 4.5 Km/NW 7.8 Km/NNW 9.4 Km/NW 10.3 Km/NNW 11.3 Km/NNW 13.3 Km/NW 12.3 Km/WNW 2.13 Km/NNW
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 9
Nawanagar PF 13.1 Km/NNW
14 Hills/valleys Silyari (578 m) Chela Pahar (565 m) Chhuiya (617 m) Bandarighori (605 m) Kharawan (505 m) Uska (586 m) Chokra PF (517 m) Vihara PF (511 m) Teldah PF (439 m) Burma Pahar (567 m) Tarkedei (528 m)
7.6 Km/N 8.2 Km/NNE 9.4 Km/N 11.9 Km/NNW 14.4 Km/NE 2.6 Km/NNE 7.6 Km/SSE 13.9 Km/SSW 3.3 Km/SSW 12.3 Km/SW 15 Km/NE
15 Streams/ Rivers Kanchan Nadi Chalki Nadi Kanjas Nadi Silhor Nala Bijul Nala Kamjhawan Nala Bukuru Nala Juri Nala Khakan Nala Badhaniya Nala Kanchanmuda Nala
6.2 Km/W-SE 3.5 Km/NW-S 5.7 Km/NW-S 5.7 Km/NW-SE 0.6 Km/W-E 1.4 Km/W-E 2.9 Km/W-E 6.5 Km/ESE-W 7.5 Km/W-E 8.6 Km/N-S 10.6 Km/S-N
16 Topography Plain with hillocks 17 Defense Installation No defense installations within 15 km radius
from the project site. 18 Inter State Boundary NA
19 Historical places Varanasi (220 km)
Fig 2.1- Geographical Location map of the Project Site:
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 10
2.1 BASELINE ENVIRONMENTAL SCENARIO
The baseline environmental status for various environmental attributes within the study area
has been established through field monitoring supported by data from secondary sources.
The environmental disciplines studied include land use, demography and socio-economics,
geology, soils, hydrology, water use, water quality, meteorology; air quality, terrestrial and
aquatic ecology and noise.
2.1.1 Land Use
As per the Revenue Records of 2001 the area within the radius of 10 km from the proposed
project site exhibited mixture of various land utilization activities. The land use pattern of the
project area is given below:
Sr. No. Particulars of Land use
0-3 km 3-7 km 7-10 km 0-10 km Area %
1 Forest Land 75 692 65 832 3.3 2 Land under Cultivation
a) Irrigated Land 0 0 20 20 0.1 b) Un irrigated Land 130 249 551 930 3.5
3 Cultivable Waste Land 2 1 14 17 0.1 4 Area not available for
cultivation 8544 9727 5487 23758 93.0
Total Area 8751 10669 6137 25557 100
2.1.2 Demography and Socio Economics
In the study area total population in 2001 was 245714 with a density of about 380 per square
kilometer. The annual growth rate was about 4%. The analysis of the literacy levels in the
study area reveals an average literacy rate of 60.2% as per 2001 census data. The
distribution of workers by occupation indicates that the non-workers are the predominant
population. The study area is predominantly rural in character. As per 2001 census records
the main workers are 24.4% of the total population. The marginal workers and non-workers
constitute to 3.5 % and 72.1 % of the total population respectively.
2.1.3 Soils
Soil samples were collected from 5 locations. Out of five samples, one sample was collected
from the ash pond area. The analysis of samples indicates that soils in the plant area are
silty clay, whereas in the ash pond area it is moderate clay. The soils in general are neutral
to alkaline and fertile.
Baseline Soil Status
It has been observed that the pH of the soil in the study area ranged from 7.2 to 8.3. The
min. pH value of 7.2 was observed at S2, and where as the max. value of 8.3 was observed
at S3. the pH was observed to be slightly to moderately alkaline.
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 11
The electrical conductivity was observed to be in the range of 224 µmhos/cm to 394
µmhos/cm, with the minimum observed at S5 and the max. observed in S2.
The nitrogen values range between 32.9 to 79.4 kg/ha. The nitrogen content in the study
area falls in very less to less category.
The phosphorus values range between 30.1 to 115.8 kg/ha, indicating that the phosphorus
content in the study area falls in medium to more than sufficient category.
The potassium values range between 75.6 to 169.4 kg/ha. The potassium content in the
study area falls in very less to more than sufficient category.
The chlorides were found to be in the range of 122.7 to 143.5 mg/kg of soil.
2.1.4 Hydrology
Ground water is the part of precipitation that seeps (infiltrates) deep into the ground. It flows
downward by gravity until it reaches a hard layer of rock i.e. impermeable to water. Just
above this impermeable rock layer is saturation zone, where all water that has socked deep
underground is stored. Most of the rocks contain numerous open spaces, called interstices,
in which water may be stored and can move. The pore spaces (tiny spaces or fractures
between pieces of rock or soil) in this zone are completely filled with water.
Depth to water level
Based on the well inventoried and measurement of water level at the time of field
investigation, reported groundwater level in summer season (pre monsoon) and actual
ground water level measurement in winter (post monsoon) the following conclusion were
drawn.
Post monsoon depth to water level
Based on field data and well inventoried, depth to water level map of post monsoon period of
the investigated area has been prepared. The water level in the post monsoon seasons
varies in the range of 3.00 m to 12.0 m bgl. In general average water level ranges between 8
to 10 m bgl. Variation in general ground water level is due to only due to the ground surface
slope.
Pre monsoon depth to water level
The ground water level monitoring of dug wells and bore wells during pre-monsoon season
could not the carried out as the field investigation was taken during the month of December
2010. The actual ground water level measurement may be carried out during pre-monsoon
2011.The field information was collected by the enquiry with the local people and former and
it is inferred that ground water level during pre-monsoon ranges from 15 to 20 m bgl.
Seasonal fluctuation
It is a fact that in and around area the fluctuation in groundwater level is mainly due to
withdrawal, recharge and movement of groundwater. A seasonal ground water level
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 12
fluctuation has been observed on the basis of field data and inventoried wells. The average
ground water level fluctuation in the investigated area is 10 m bgl.
2.1.5 Water Quality
Surface (8 Locations) and ground (8 Locations) water quality within the study area was
established through monthly monitoring of physico-chemical and bacteriological
characteristics at eight surface water locations were collected from the Bijul River upstream
and downstream and other surface water sources and eight ground water sources are taken
from tube wells and dug wells. The analysis indicates that the surface water quality and
ground water at all sampling locations is fairly good.
Surface water quality
The analysis result indicates the pH values in the range of 6.9 to 8.0, min. value was
observed at SW2 and max. Value was observed at SW3 which are well within the specified
standard of 6.5 to 8.5.
The TDS was observed in the range of 84 mg/l to 223 mg/l, the min. TDS value was
observed at SW2 and max. value was observed at SW4
DO was observed to be in the range of 2.9 to 6 mg/l respectively.
The fluorides and sulphates were found to be in the range of 0.5 to 0.9 mg/l and 1.0
to 3.9 mg/l respectively. It is observed that fluorides and sulphates are well within the
permissible limits. It is evident from the above values that all the parameters are found to
comply with the requirements of IS: 2296 specification of surface water.
The water quality result indicate that the Badhaniya nallah is moderately polluted
since the concentrations of BOD, COD, Fluorides and mercury are exceeding the
permissible standards.
Ground Water Quality
Most of the villages in the project area have hand pumps and wells, as most of the resident
of these villages make use of this water for drinking and other domestic uses.
The analysis result indicate that the pH ranges in between 7.1 (GW1) to 7.9 (GW3),
which is well within the specified standard of 6.5 to 8.5
Total hardness was observed to be ranging from 168 to 334 mg/l. The min. hardness
(168mg/l) was recorded at GW4 and max. Hardness (334 mg/l) was recorded at GW2.
Chloride was found to be in the range of 27.8 mg/l (GW4) to 99.5 mg/l (GW1).
Sulphates were found to be in the range of 2.7 mg/l (GW3) to 15.9 mg/l (GW2).
The Total Dissolved Solids (TDS) concentrations were found to be ranging in
between 395 mg/l (GW4) to 531 mg/l (GW2)
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 13
2.1.6 Meteorology
The climate of the area is hot, humid and tropical. Maximum and minimum temperatures
recorded are 420C and 7.50 C, respectively. Winds are gentle with moderate strengths. The
data collected during the study indicate that the site meteorology is similar to that of climatic
data.
2.1.7 Ambient Air Quality
Pre Monsoon Season (2011)
The min. and Max. Concentration for SPM were recorded as 253.7 g/m3 and 310.4 µg/m3
respectively. The max & min concentration was recorded at Chanduli (AAQ3) Telgawan
(AAQ 2) respectively.
The min. and Max. Concentration for PM10 were recorded as 74.3 µg/m3 and 96.8 µg/m3.
The min. and max. Concentrations were recorded at Chikadand (AAQ4) and Paraswar
(AAQ1) respectively. The max. Concentrations found to be exceeding the standard limit of
100 µg/m3. The min. & max. SO2 concentrations were recorded as 19.8 µg/m3 Telgawan
(AAQ2) and 56.1 µg/m3 Paraswar (AAQ1). All the concentrations found to be less than
standard limit of 80 µg/m3.
The min. & max. NOx concentrations were recorded as 28.3 µg/m3 at Telgawan (AAQ2) and
62.2 µg/m3 at Paraswar (AAQ1) respectively. All the concentrations are found to be less than
standard limit of 80 µg/m3.
The concentration of mercury found to be in the range of 0.1 to 1.1 µg/m3.
The concentration of ozone in the study area is observed to be in the range of 2.4 and 8.9
µg/m3.
Winter Season (Dec. 2010 – Feb 2011)
The min. and Max. concentration for SPM were recorded as 272.8 mg/m3 and 318.5 mg/m3
respectively. The max. and min. concentrations were recorded at Paraswar (AAQ1) and
Chilkadand (AAQ4) respectively.
The min. and Max. concentration for PM10 were recorded as 84.3 µg/m3 and 98.3 µg/m3. The
min. and max. concentrations were recorded at Chikadand (AAQ4) and Paraswar (AAQ1)
respectively. The max. concentrations found to be exceeding the standard limit of 100 µg/m3.
The min. & max. SO2 concentrations were recorded as 23.4 µg/m3 Telgawan (AAQ2) and
58.1 µg/m3 Paraswar (AAQ1). All the concentrations found to be less than standard limit of
80 µg/m3. The min. & max. NOx concentrations were recorded as 29.6 µg/m3 at Telgawan
(AAQ2) and 65.1 µg/m3 Chikadand (AAQ4) respectively. All the concentrations are found to
be less than standard limit of 80 µg/m3.
The concentration of mercury found to be in the range of 0.1 to 1.6 µg/m3.
The concentration of ozone in the study area is observed to be in the range of 2.7 and 11.2
µg/m3. The concentrations have been observed to be on the higher side due to the prevailing
industrialization in the region. The high concentrations of SPM, RPM and other gaseous
emissions can be attributed to the opencast coal mining activities and industrial activities in
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 14
the Singrauli region.
TABLE – 2.1
AMBIENT AIR QUALITY OF THE STUDY AREA
Parameters Concentration (µg/m3)
Pre Monsoon Winter SPM 253.7-310.4 272.8-318.5 PM10 74.3-96.8 84.3-98.3 SO2 19.8-56.1 23.4-58.1 NOx 28.3-62.2 29.6-65.1 O3 2.4-8.9 2.7-11.2 Hg 0.1-1.1 0.1-1.6
Source : SGS India pvt. ltd
2.1.8 Ecology
The study area is devoid of forest vegetation and grass cover. Only scattered trees along
with bunds and road side are recorded during survey. Shrubs and herbs have found in the
barren land and along the Rihand reservoir. As the dense vegetation is not there, the
environment is not moderate for higher animals. Though aquatic ecosystem has some plant
life along the bank of Rihand reservoir there is no important aquatic life except some fishes
reported.
No rare and endangered species of fauna and flora have been reported in the study area.
There is no National park and wild life sanctuary within 15 km radius area.
2.1.9 Noise
The night time noise levels ranged in between 35.2 dB (A) to 44.5 dB (A). The maximum
value (44.5 dB (A)) was recorded at parari and the minimum value (35.2 dB (A)) was
recorded at Kasar.
NOISE LEVELS dB (A) IN THE STUDY AREA
Sr. No. Location L10 L50 L90 Leg Lday Lnight Ldn 1 Godwali 45.2 40.9 38.1 41.5 42.6 37.9 45.0 2 Kasar 40.3 38.5 36.7 38.4 42.5 35.2 43.7 3 Ghorvi 50.3 46.1 39.8 44.2 45.9 42.6 49.6 4 Parari 50.3 47.6 42.1 48.4 51.0 44.5 53.8 5 Ramghar 52.1 48.6 44.2 49.3 50.2 43.6 51.9
Source : SGS India pvt. ltd
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 15
ENVIRONMENTAL IMPACT
AND MITIGATION
MEASURES
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 16
3.1 LAND USE
The land selected for proposed expansion of power plant project is within the premises of
DRI, which is categorized as industrial area. There will not be change in land use.
Therefore the impact on the land use is not envisaged.
Out of 61.61 Ha, 1.07 Ha is spared and kept reserved for Ash Pond
3.2 WATER USE
The Project will abstract its entire water requirement from discharge outlet of Stage-I & II.
Therefore, no impact on water use is envisaged.
3.3 DEMOGRAPHY AND SOCIO ECONOMICS
In this section, the prevailing socio-economic aspects of people in the study area around the
proposed plant boundary, which would form the basis for making planning efforts for the
socio-economic development of people in the study area, have been described.
In the study area total population in 2001 was 245714 with a density of about 380 per square
kilometer. The annual growth rate was about 4%. The analysis of the literacy levels in the
study area reveals an average literacy rate of 60.2% as per 2001 census data. The
distribution of workers by occupation indicates that the non-workers are the predominant
population. The study area is predominantly rural in character. As per 2001 census records
the main workers are 24.4% of the total population. The marginal workers and non-workers
constitute to 3.5 % and 72.1 % of the total population respectively. There will be a positive
impact on the local economy.
3.4 AIR QUALITY
The impact on air quality assessed based on combined emissions of the proposed
expansion of coal based thermal power plant. Suspended Particulate Matter (SPM). Sulphur
dioxides (SO2) and Nitrogen (NOx) will be the important pollutants emitting from the power
plants. To minimize emissions from the stack, concerned authority will take necessary steps.
TABLE -3.1
RESULTANT MAXIMUM GROUND LEVEL CONCENTRATION AFTER
IMPLEMENTATION OF PROJECT
Pollutant Concentration (µg/m3) Baseline Incremental Resultant
Pre Monsoon SPM 310.4 0.7 311.1 SO2 56.1 11.5 67.6 NOx 62.2 5.6 67.8 Winter SPM 318.5 0.9 319.4 SO2 58.1 14.8 72.9 NOx 65.1 7.2 72.3
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 17
1. High efficiency ESPs to limit SPM emission to below 50 mg/Nm3.
2. Tall stack of 75 m height for wider dispersal of pollutants, resulting in lower ground
level concentrations.
3. Space provision for retrofitting Flue Gas Desulphurization (FGD) system, if required
in future.
4. Installation of dust suppression and extraction system at coal handing area to
control fugitive dust.
5. Water spraying at all dust generation areas viz. The coal and ash handling areas.
3.5 SOILS
The impacts on soil during construction phase shall be mainly due to loss of topsoil in the
construction areas and contamination of the soils of surrounding area due to construction
materials such as cement, sand, oils, etc. However, it shall be temporary and shall be
confined to the areas of construction only. Conservation measures would minimize such
local impacts.
3.6 WATER QUALITY
Ash water recirculation system for the ash disposal shall reduce the quantity of effluent.
The wastewater generated in water treatment units will be utilized in ash handing units.
The cooling tower blowdown will be utilized in ash handling and coal handling units. The
power cycle discharge will be collected in CMB and discharged into hot water channel.
The ash pond leachates are generally alkaline and, therefore, heavy metals are not likely
to leach from the ash and, therefore contamination of ground water is unlikely.
3.7 NOISE
Day time Noise Levels (Lday)
The maximum value (51.0 dB (A)) was recorded at Parari, and the minimum value (42.5 dB
(A)) was recorded at Kasar.
Night time Noise Levels (Lnight)
The maximum value (44.5 dB (A)) was recorded at parari and the minimum value (35.2 dB
(A)) was recorded at Kasar.
The main noise generating sources from the power plant will be pumps, compressors
along with cooling towers, turbo generators and boilers. The noise levels at the source for
these units will be in the range of 80-90 dB (A). The noise dispersion from the plant units
has been computed based on the mathematical model.
The ambient noise levels at most of the places in the region are within the CPCB
standards.
The nearest village is situated 0.1 km north from the plant boundary. The impact of the
noise pollution due to the proposed expansion will be insignificant on the community.
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 18
3.8 TERRESTRIAL ECOLOGY
This formation corresponds to the optimum encountered in the area. In accordance with the
department of forests, the forests can be conveniently classified into Sai forests and mixed
forests. In fact, it is now difficult to make a distinction between what has a natural origin and
what is a result of a thousand years of human activity. Consequently, mixed forests and Sal
forests have been brought together.
The encountered plant species in this forest blocks are listed below. Three layers can be
distinguished in the forest. Scrub Woodland vegetal formation is composed of trees rising,
more or less, from a bushy stratum, here, there is strong anthropogenic pressure and
practically all of the trees regularly supply firewood.
3.9 AQUATIC ECOLOGY
Larger organism tends to get entrapped and impinged in the intake system. However, this
will be minimized by providing suitable structures at the intake location. Smaller organisms
as phytoplankton, zooplankton is entrainable and subject to entrainment in the treatment
system. The entrapped organisms would be subjected to a combination of physcio-
chemical and mechanical stresses, leading to their destruction.
There would not be any tangible change in the water quality of the receiving water due to
the wastewater discharges from the plant operation. As such, it may be concluded that no
adverse effects on the existing aquatic biota are envisaged due to the discharges from the
project during operation.
3.10 POTENTIALITY OF ASH UTILIZATION
The main areas of ash utilization are manufacturing of fly ash based products (Portland
Pozolana cement, brick, light weight aggregates, asbestos cement products, cement
concrete etc.) and use in landfills etc. TRIMULA INDUSTRIES LTD. will take all possible
actions to utilize the ash in above mentioned areas. Provisions such as facilities for 100%
extraction of dry fly ash, segregation of coarse and fine ash and fly ash storage and
loading facilities; providing infrastructural facilities to the entrepreneurs, etc will encourage
utilization of ash based products in the area.
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 19
ENVIRONMENTAL
MONITORING PLAN
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 20
The post operational environmental monitoring programme has been formulated.
4.1 ENVIRONMENTAL MONITORING PROGRAMME
Post project environmental monitoring is important in terms of evaluating the performance of
pollution control equipments installed in the project. The sampling and analysis of the
environmental attributes will be as per the guidelines of CPCB/MPPCB. Following attributes
will be covered in the post project environmental monitoring in and around the project site:
Ambient air quality monitoring on bi-weekly, 24 hours basis in the plant area and in
the surrounding villages with respect to SPM, PM, SO2, NOx and CO;
Source emissions will be mentored on monthly basis. Automatic continuous online
monitoring system shall be installed in the stacks;
Water quality monitoring at intake point, surface water bodies and ground water in
the surrounding villages. Further, the wells around the ash pond area will be
identified and monitored on the monthly basis;
Treated wastewater before routing to clarifier will be analyzed on fortnightly basis.
The pH, temperature, electric conductivity, TDS and flow will be monitored regularly;
The noise level will be recorded in and around plant. The noise levels at boundary of
the plant will be recorded on monthly basis;
The soil quality around ash pond area will be monitored on six monthly basis for the
fertility of the soil;
All the results will be compiled and thoroughly analyzed to assess the performance
of the power plant;
The results will be reported on regular basis to the Madhya Pradesh State Pollution
Control Board and regional office of MoEF; and
Ecological monitoring.
4.2 ENVIRONMENT MANAGEMENT PLAN
During operation phase, the impacts on the various environmental attributes should be
mitigated using appropriate pollution control equipment. The Environment Management Plan
prepared for the proposed project aims at minimizing the pollution at source.
AIR POLLUTION MANAGEMENT
Fugitive and stack emissions from the power plant will contribute to increase in
concentrations of SPM, SO2 and NOx pollutants. The mitigative measures proposed in the
plant are:
Installation of ESP’s of 99.9% efficiency to limit the SPM concentrations below 50
mg/Nm3;
Provision of 75 m high stack for wider dispersion of gaseous emissions;
Providing low NOx burners to reduce the NOx emissions;
Dust extraction system will be provided at transfer point of conveyor system;
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 21
Conveyor belt will be closed with rubber lining installed to prevent dust generation;
Provision of water sprinkling system at material handling and storage yard;
The ash will be transported by closed bulkers;
Asphalting of the roads within the plant area;
WATER POLLUTION MANAGEMENT
Wastewater will be generated from various streams of the power plant. Additionally,
domestic wastewater from canteen and employees wash area will also be generated.
The measures proposed to minimize the impacts are:
Closed cycle cooling tower;
Recycle and reuse cooling tower blow down in service area, ash and coal handling
system
Oil separation;
Reuse of treated domestic waste water in horticulture; and
Rainwater harvesting
NOISE POLLUTION MANAGEMENT
In the process, various equipments like pumps, cooling tower, compressors etc generate
noise. The proposed means to mitigate higher noise levels are:
Equipment will conform to noise levels prescribed by regulatory authorities;
Provision of acoustic enclosures to noise generating equipments like pumps;
Provision of earplugs to the workers working in high noise level area.
SOLID WASTE MANAGEMENT
The main solid waste from the proposed power plant will be ash (fly ash and bottom ash).
The average coal consumption rate for the power project will be 2, 85, 809 TPA, which will
result in ash generation of about 69754 TPA. Out of this, the bottom ash will be about i.e.
13950 TPA and the fly ash will be about 55804 TPA. It is proposed to utilize 100% of the fly
ash generated.
Several major cement factories in North India have expressed their willingness to take the
entire production of fly ash for their in-house consumption. During emergency the ash will be
disposed off safely in ash pond area to avoid environmental hazards. All efforts, however,
will be made to utilize fly ash for various purposes.
Unused fly ash and bottom ash will be disposed off in the ash dyke in an area of about 1.07
Ha. To control fugitive dust emission from the ash pond area water sprinkling would be done.
After the ash pond is abandoned, its area will be reclaimed through tree plantation.
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 22
4.3 RISK ASSESSMENT DISASTER MANAGEMENT PLAN
The risk analysis for fuel storages such as LDO & HSD have been carried out. The
possibility of any risks due to fire will be confined to the plant premises only. There will not
be any community risks. Suitable disaster management plan has been prepared.
4.4 PROJECT BENEFITS
The proposed project by TRIMULA INDUSTRIES LTD. would enable to meet part of the
growing power demand due to rapid industrialization and also due to large scale use of
electricity for irrigation, domestic and commercial purposes. Further, the proposed power
plant will result in improvement of infrastructure as well upliftment of social structure in the
area. It is anticipated that the proposed power plant will provide benefits for the locals in two
phases i.e. during construction phase as well as during operational stage.
The major benefit due to the proposed project will be in the sphere of generating temporary
employment for substantial number of personnel. The construction phase of power plant is
expected to span over 06 months. Approximately 180 persons would be required for the
construction work, most of whom would be unskilled workers, although the power plant
construction needs a large number of skilled personnel as well. These construction workers
shall be taken from the study area to the extent possible. Hence, the proposed project will
benefit locals to some extent.
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 23
ENVIRONMENTAL
MANAGEMENT PLAN
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 24
5.1 INTRODUCTION Environment Management Plan is required for ensuring sustainable development of the proposed project site. The management plan presented in this chapter needs to be implemented by the proposed Project of M/s. Trimula Industries Limited at Village
Godwali, Tehsil Devsar, District Singrauli (M.P.). The Environment Management plan aims at controlling pollution at source with available and affordable technology followed by treatment measures. Waste minimization and waste recycling measures are emphasized. In addition to the industry specific control measures the proposed industry will adopt following guidelines.
Application of Low and Non Waste Technology in the production process; and
Adoption of Reuse and recycling technologies to reduce generation of wastes and to optimize the production cost of the industry.
The recycling and reuse of industrial waste not only reduces the waste generation but also
can be an economic gain to the industry.
The environment impact assessment is based on the industrial site coming up without any
control measures. The major affected environmental aspect is air quality. Other environment
aspects are marginally affected. The mitigation measures suggested in this chapter are to
reduce the impacts on the aforementioned adversely affected areas. The management
action plan aims at controlling pollution at the source level to the possible extent with the
available and affordable technology followed by treatment measures before they are
discharged. The management will be committed to eco-friendly production.
5.2 Management During Construction Phase
During construction phase, there is a scope for local dust emissions Suitable
measures will be taken to protect workers against dust arising from leveling, drilling
crushing, excavation and transportation. Frequent water will be sprinkled in the
vicinity of the construction activity. Provision will be made for water sprinklers as an
initial project construction investment.
Industry will go for tree plantation program at the outset of the project itself along the
boundaries of the proposed plant site and along internal roads to mitigate dust from
construction activities.
The construction site will be provided with sufficient and suitable sanitation facilities
for workers to maintain proper standards of hygiene.
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 25
For controlling noise, ear muffs will be provided to the workers those are working
using high noise construction equipment like bulldozers, concrete mixers. To reduce
noise exposures, shifting duty may also be adopted.
5.3 Management during the Post Construction Phase
Air Pollution Management
The major air pollutant expected to be generated, as results of various industrial operations
are Suspended Particulate Matter (SPM) and SO2, The stack heights have to be calculated
by using the formula recommended by CPCB. For D.G. set, CPCB’s formula based on KVA
of D.G. sets is to be used to arrive at the height of stack.
Water Management
The required water will be supplied by nearby water bodies. Due to the various activities in
the proposed project, the Domestic effluent will be generated. Industrial effluent would be
totally from cooling discharges resulting from water used on rotary kiln and cooler for cooling
purposes moreover, there will not be any discharge of the cooling effluent in environment (on
land or in surface or ground water). The entire quantity of cooling effluent would be re-
circulated in the cooling circuit / system so as to observe zero discharge. The Domestic
wastewater would be treated in well-designed septic tanks followed by soak pits. The
overflow water from soak pit will be used for gardening purpose.
Effluent treatment Plant
The effluent generated consists of cooling tower blow down, boiler blow down, service water,
D.M. Plant regeneration water and sanitary waste. Initially the acidic and alkaline effluent
streams coming from cation and anion units of DM plant will be neutralized in a
neutralization tank. Water will then be passed through an oil separator to remove the oil
content in the effluent. All these effluent streams will be mixed in holding tank along with
cooling tower blow down. The treated effluent will be recycled and sent to the DRI plant &
rolling mill as make-up water for cooling and the remaining treated effluent will be used for
ash conditioning, dust suppression and for greenbelt development. The sanitary wastewater
will be treated in septic tank followed by soak pit.
Noise Level Management
Mitigation measures for noise levels are of following types:
Prevention at source
Control of transmission path
Protective measures in the work environment
Administrative control
In case of the exposure within the industry the noise levels at some sources may exceed 90
dB (A), in such cases, the exposure time of workers to noise will be regulated so as to be
within specified period. No exposure beyond 115 dB (A) for any amount of time is envisaged.
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 26
Land management
Adequate measures are proposed for taking care of other solid wastes. Dustbins will be
done in vehicles with closed container. So no solid waste will be allowed to litter around and
degrade the land. Proposed plantation around the industrial unit will arrest the aerial spread
of particulate contaminants, if any.
Measures for Socio-Economic Development
Better Employment Opportunities
The shift in the occupational structure from less productive agricultural to non-agricultural
base will improve the economic condition of the people. The proposed industry generate
indirect employment to the local populace.
Provision of Health Care Facilities
The proposed industry will consider provision of health care facilities for the workers of
industry. Regular health checkups and doctor visits will be arranged. Necessary first aid as
well as emergency situation handling facilities will be provided.
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 27
CORPORATE SOCIAL
RESPONSIBILITY
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 28
Trimula Industries Ltd. Will generate more direct and indirect employment opportunity for nearby
village. Presently we have 83% employment from near villages. The company will maintain same
status for all its future expansion.
Company determined to provide clean and green environment. The power plant is the solution
for the same. The power plant will consume char, the byproduct generated from DRI operation. It
also consumes coal fines generated in coal crusher.
The company acquired separate 30% of its land for green belt. Already 30000 trees have been
planted in this region. To add further more we made a policy to plant 10000 trees every year with
proper consultation with Forest department. This enables the better and greener environment.
The area GODWALI is drastically declared draught area. To meet water Requirement Company
made five water pond as reservoir. This reservoir is not only meeting the plant water requirement
but also maintain underground water level of nearby area. Due to this all hand pump and well are
not getting dry in peak summer. The company already planned to increase number of such
reservoir in near future. Already sixth pond is under construction.
The company already made provision to monitor air quality, water quality and noise level from
Pollution Control Board. The same will continue for all its future expansion. This will help to
protect the environment better. If any immediate preventive and corrective action required the
company follow the same proper consultation will pollution control Board experts. This will not
only provide better working condition inside plant but also to nearby area.
The company reserved 2% of its profit for CSR development. The fund will be utilized to
upbringing condition of nearby villages. The fund will be planned to invest in:
For development of quality education in the area. This includes providing assistance in
education need like distributing books and scholarship for nearby villages.
For better hygiene and sanitation facility in villages.
For assistance to bring quality crop production facility in the area. The same will be done
by proper consultation of renowned expert agriculturist. If any extra training and guidance
required the same will be incorporated.
The part of fund will be reserved for developing forestation in nearby area.
Apart from CSR activity in this project company planned to open one higher secondary school in
plant premises for its staff where equal scopes for villagers are also kept. The school will run as
per norm of Madhya Pradesh Higher Secondary Education Board, Bhopal.
The project already had a provision of opening Hospital in plant premises. The hospital opened
will have one MBBS doctor and Ambulance facility to provide primary health checkup and first aid
facilities. The hospital will be commonly utilized for staff and villagers. There is also provision to
provide basic health and family planning guidelines villages. All necessary training camp will be
organized time to time.
The project has already provision for upbringing status of nearby operating Technical Institutes
like ITI and Polytechnique. The necessary seminars will be arranged. There is also provision to
Executive Summary of Draft Environment Impact Assessment Report of Trimula Industries Limited for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran,
Tehsil Devassar & Chitrangi, District Singrauli (M.P.)
Page No.: 29
provide in plant and vocational training. The necessary certificates issued to all qualified students
so that they can be well absorbed in society. The necessary placement can be made according
to qualification and requirement of plant.
The expansion of project demands more manpower for its operation. This already generates the
secondary expansion of demand like canteen, transportation and basic needs. This will generate
opportunity for indirect employment like consumption of vegetable, basic commodity, dhabas as
transportation will increase. This will boost the size of existing market. Villagers have opportunity
to sell their commodities to plant area only. Also there is opportunity to open new shop and
dhabas in nearby area. This will also boost the consumption for opening new fast food corner
and boost the demand for existing one.
The plant will provide all socio economic growth opportunity for its staff and villagers. This will
boost the demand of skilled and unskilled worker. The villagers have opportunity to work in plant
area when there is slack period in harvesting. With joint involvement of company and villagers no
stone can be made unturned.
With joint efforts of company and villagers leads to arrange Community Development Program
(CDP) in society where people have equal opportunity to discuss their common problems and
find solution for the same. This will leads to boost morale of villagers. This also has opportunity to
tap the necessary talents and generate scope for utilizing these talents. Under CDP necessary
gathering for pujas and bhajans will be arranged which will uplift the status of society. In CDP
various lectures and guideline will be discussed to solve problems of villagers.
The expansion of project will also leads opportunity for Entrepreneur Development Program
(EDP). Under this opportunity will be generated for opening of new workshop, fly ash brick
making plant, market for two/ four wheelers and tractors, lubricants, cement, poultry farms,
steels, hardware shop. This opportunity will be available for villagers only.