12
ENGINEERING DEPARTMENT Presented by: Ian Chapman City Engineer 1 City of Penticton – Budget 2012

Upload: others

Post on 30-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Final-2012 Design only Operating Budget Presentation.pptx ... › sites › default › files › docs › city-hall › finan… · engineering design budget $286,800 (after transfers)

ENGINEERINGDEPARTMENT

Presented by:

Ian Chapman

City Engineer

1City of Penticton – Budget 2012

Page 2: Final-2012 Design only Operating Budget Presentation.pptx ... › sites › default › files › docs › city-hall › finan… · engineering design budget $286,800 (after transfers)

ENGINEERING OVERVIEW

DESIGN

WATER TREATMENT

PLANT

ADVANCED WASTE WATER

TREATMENT PLANT

MANAGER – CITY ENGINEER

City of Penticton – Budget 2012 2

Page 3: Final-2012 Design only Operating Budget Presentation.pptx ... › sites › default › files › docs › city-hall › finan… · engineering design budget $286,800 (after transfers)

ENGINEERING BUDGET OVERVIEW

DESIGN

WATER TREATMENT

PLANT

ADVANCED WASTE WATER

TREATMENT PLANT

� THREE AREAS; DESIGN, AWWTP and WTP

� OPERATING AND CAPITAL BUDGET FOR EACH

� DESIGN – OPERATING BUDGET

� AWWTP OPERATING BUDGET.

� WTP OPERATING BUDGET.

� AWWTP AND WTP CAPITAL BUDGET.

� DESIGN CAPITAL BUDGET.

3City of Penticton – Budget 2012

Page 4: Final-2012 Design only Operating Budget Presentation.pptx ... › sites › default › files › docs › city-hall › finan… · engineering design budget $286,800 (after transfers)

ENGINEERING DESIGN TEAM

City Engineer

Design Supervisor

Surveyor Technician I

Survey Rodperson –

(Seasonal)

Engineering Technician II –

Design

Engineering Technician II –

Design

Engineering Technician II –

Mapping

Engineering Technician II -

Inspection

Development Engineer (Vacant)

Engineering Technician -

Development

9 FTE2 exempt6 non-exempt1 seasonal

City of Penticton – Budget 2012 4

Page 5: Final-2012 Design only Operating Budget Presentation.pptx ... › sites › default › files › docs › city-hall › finan… · engineering design budget $286,800 (after transfers)

• Undertake Master Utility Planning And Budget Preparation.

• Design And Construction Management For Budgeted Capital Works.

• Provide Support To Development Services For Development Approvals.

• Address Public Queries Eg Traffic, Signage, Etc

• Process Permits For Water And Sewer Services, Earthworks, 3rd Party Works In Roads, Etc.

• Maintain Records Of Capital Works And Development Construction.

• Provide Survey And Mapping Services To All Departments.

• Address Unplanned Construction Projects Eg Correctional Centre, City Centre Building Frontage, Etc.

City of Penticton – Budget 2012 5

ENGINEERING DESIGNFUNCTION

Page 6: Final-2012 Design only Operating Budget Presentation.pptx ... › sites › default › files › docs › city-hall › finan… · engineering design budget $286,800 (after transfers)

General

Revenue ,

$286,800

Sewer Utility,

$1,470,959

Water Utility ,

$1,293,933

2012 Engineering Budget By Cost

Centre

General

Revenue ,

$224,450

Sewer Utility ,

$1,432,041

Water Utility,

$1,352,137

2011 Engineering Budget By Cost

Centre

City of Penticton – Budget 2012 6

ENGINEERING DESIGN OPERATING BUDGET OVERVIEW

Page 7: Final-2012 Design only Operating Budget Presentation.pptx ... › sites › default › files › docs › city-hall › finan… · engineering design budget $286,800 (after transfers)

ENGINEERING DESIGN BUDGET HIGHLIGHTS

• Engineering Technician – Development added (+$72,800)

• Incremental increases from last year (+$13,200)

• Holiday relief eliminated (-$2,500)

• Rod-person (seasonal) shown as working full year. (+$57,200)

• Secretary transferred to Purchasing (-$56,600)

• Overtime allowance increased(+$9,000)

• Secretary transferred in from Purchasing (+$59,150)

• Increased salary transfers to Capital for related effort (+$68,925)

• Salary transfers to other department for related effort (+$50,600)

• Cell phone expenses added, plotter expenses transferred in from IT, CAD allowance decreased, transfer to Capital increased (Net +$3,200)

• Vehicle transfer to Capital increased (+$3.575)

• Consulting costs associated with development transferred from Development Services (+$30,000)

• NET BUDGET INCREASE FROM 2011 TO 2012 IS $62,350

City of Penticton – Budget 2012 7

Page 8: Final-2012 Design only Operating Budget Presentation.pptx ... › sites › default › files › docs › city-hall › finan… · engineering design budget $286,800 (after transfers)

ENGINEERING DESIGN BUDGET$286,800 (AFTER TRANSFERS)

2012 2011 VARIANCE

SALARIES, WAGES AND OVERTIME $917,000 $823,900 $93,100

SECRETARY TRANSFER IN $59,150 - $59,150

SALARY TRANSFER TO CAPITAL ($512,925) ($444,000) ($68,925)

SALARY TRANSFER TO OTHER DEPT. ($241,800) ($191,200) ($50,600)

STATIONARY/SUPPLIES $10,650 $8,000 $2,650

STATIONARY TRANSFER TO CAPITAL ($5,450) ($6,000) $550

VEHICLES $27,500 $27,500 -

VEHICLE TRANSFER TO CAPITAL ($17,325) ($13,750) ($3,575)

CONSULTING $50,000 $20,000 $30,000

TOTALS $286,800 $224,450 $62,350

SALARIES &

WAGES,

$976,150

STATIONARY,

$10,650

VEHICLES,

$27,500

CONSULTING

$50,000

Design Budget Elements OPERATING -

GENERAL

REVENUE,

$286,800

TRANSFER

TO CAPITAL,

$535,700

TRANSFER

TO OTHER

DEPT.,

$241,800

Budget Allocation

City of Penticton – Budget 2012 8

Page 9: Final-2012 Design only Operating Budget Presentation.pptx ... › sites › default › files › docs › city-hall › finan… · engineering design budget $286,800 (after transfers)

ESTIMATED

EFFORT FOR

CAPITAL

PROJECTS,

$513,000, 75%

ALLOWANCE

FOR RE-

PRIORIZATION

$171,000, 25%

Capital Transfer

$535,700

Estimated effort to support proposed projects totalling $4,535,000 is $684,000.Only approximately 75% of work will proceed due to re-prioritisation.

Hence $$684,000 x 75% = $513,000 Plus stationary and vehicle - total $535,700

ADMINISTRATION

15%DEVELOPMENT

SERVICES

SUPPORT

10%

PUBLIC QUERIES

10%

PERMIT

PROCESSING

5%

MAPPING and

RECORDS

10%

MASTER

PLANNING

BUDGETING

10%

CONSULTING

17%

UNPLANNED

PROJECTS

23%

Work Allocation: $286,800

UTILITY FUND

45%

GRANT

ASSISTED

4%

CARRY

FORWARD

7%

GENERAL

REVENUE

44%

Estimated Capital Budget

$4,535,000

SOLID WASTE,

$18,500ROADS, $33,500

SEWER, $33,500

WATER, $38,500PARKS, $23,500

ELECTRICAL,

$75,800

DEV.

SERVICES,

$10,000

FLEET, $8,500

Design Budget Transfers

$241,800

City of Penticton – Budget 2012 9

ENGINEERING DESIGN OPERATING BUDGET TRANSFERS

Page 10: Final-2012 Design only Operating Budget Presentation.pptx ... › sites › default › files › docs › city-hall › finan… · engineering design budget $286,800 (after transfers)

City of Penticton – Budget 2012 10

ENGINEERING - DESIGN OPERATING BUDGET

DETAILED REVIEW

Page 11: Final-2012 Design only Operating Budget Presentation.pptx ... › sites › default › files › docs › city-hall › finan… · engineering design budget $286,800 (after transfers)

City of Penticton – Budget 2012 11

Department: DESIGN & ENGINEERING PAGE: 25.1

2012 2011

Account Proj Task Description Budget Budget

----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

570306-0000-1200000860 SALARIES- Design,CADD,Survey

0860-10 Director of Operations (1/3), City Eng 917,000 823,900

Design Sup, Eng Tech II (2), Eng Tech (3)

Survery (2),

Secretarial Support 59,150

Engineering Capital Projects

0860-10 Capita l Proje cts (512,925) (444,000)

Opera ting Depa rtments

0860-10 Roads (25,000) (20,000)

Solid Waste (10,000) (10,000)

Sewer (25,000) (15,000)

Water (30,000) (15,000)

Parks (15,000) (15,000)

Development Services (10,000)

Electrical 0520-50 Dir. Of Operations (25,000) (15,000)

Director of Opera tions to Ope ra ting Depts

Roads (8,500) (15,200)

Solid Waste (8,500) (5,100)

Sewer (8,500) (15,200)

Water (8,500) (15,200)

Parks (8,500)

Fleet (8,500)

Electrical 0520-50 Dir. Of Operations (50,800) (50,500)

221,425 188,700

Page 12: Final-2012 Design only Operating Budget Presentation.pptx ... › sites › default › files › docs › city-hall › finan… · engineering design budget $286,800 (after transfers)

City of Penticton – Budget 2012 12

570306-0000-1200000870 STATIONERY & SUPPLIES

0870-10 Photocopier (Plans) Lease - 0

0870-10 Survey Supplies & Equipment 2,000 1,000

0870-10 Print Machine Supplies & Mtce 2,000 0

0870-10 CAD System Software Maintenance 2,000 1,000

0870-10 Drafting Supplies/CAD System 1,000 5,000

0870-10 Misc Annual Items 1,000 1,000

Cell Phones 2,650

0870-10 Allocation to Capital Projects = 62% (5,450) (6,000)

5,200 2,000

570306-0000-1200000880 VEHICLE EXPENSE

0880-10 Vehicle # 9 Surveyors Van 5,500 5,500

0880-10 Vehicle # 83 Site Inspectors Truck 5,500 5,500

0880-10 Vehicle #107 Design Supervisor 5,500 5,500

0880-10 Vehicle Allowance - Engineer 5,500 5,500

0880-10 Vehicle Allowance - Director 5,500 5,500

0880-10 Allocation to Capital Projects - 62% (17,325) (13,750)

10,175 13,750

570306-0000-1200000890 CONSULTING

0890-10 Consulting Costs - Studies 50,000 20,000

0890-20 Outside Testing Costs - Development

0890-30 General Services - -

50,000 20,000

286,800 224,450